O’Riordan Street looking north towards King Street Airport North precinct road upgrade May 2016 The NSW Government is planning to upgrade roads north of Sydney’s Kingsford Smith Airport to improve traffic flow and connections to the airport and Port Botany. Sydney Airport and Port Botany are two of Australia’s most important international gateways. The roads around the airport and Port Botany are becoming increasingly congested and need to be upgraded. Roads and Maritime Services is planning to upgrade roads north of Sydney Airport to improve traffic flow and connections to the airport and Port Botany. This includes widening O’Riordan Street to three lanes in each direction between Bourke Road and Robey Street. Roads and Maritime has prepared a Review of Environmental Factors to examine the potential impacts of the Airport North Precinct proposal and outline measures to reduce and manage these impacts. The Review of Environmental Factors and concept design for the proposal are on display for community and stakeholder feedback from Monday 23 May to Monday 13 June. During the display period, printed copies of the Review of Environmental Factors will be available to view in two locations and we will hold two community information sessions. The times and locations are listed in this project update. Key features and benefits The key features of the Airport North precinct proposal include: Converting the southern sections of Robey Street and O’Riordan Street into one‑way roads Widening O’Riordan Street to provide six through lanes between Bourke Road and Robey Street Reconfiguring the existing traffic lights on O’Riordan Street between Qantas Drive and Bourke Road Upgrading the footpath on the eastern side of O’Riordan Street. The proposal would help increase traffic capacity and reduce congestion along O’Riordan Street and improve access to Sydney Airport domestic terminals. Sydney Airport precinct upgrades The Airport North precinct proposal is part of a suite of upgrades to improve traffic flow around Sydney Airport. Airport West: Widening Marsh Street, Arncliffe to three lanes in each direction between Giovanni Brunetti Bridge and the M5 interchange. Work started earlier this year and is expected to be completed by late 2017 Airport East: Widening Joyce Drive and General Holmes Drive between O’Riordan Street and Mill Pond Drive and replacing the General Holmes Drive rail level crossing with a road underpass that links General Holmes Drive, Botany Road and Wentworth Avenue. Work started in late 2015 and will be completed by mid‑2018. More information about these projects is available at rms.nsw.gov.au/sydneyairport.

Transcript of Airport North precinct road upgrade · The proposal would help increase traffic capacity and reduce...

Page 1: Airport North precinct road upgrade · The proposal would help increase traffic capacity and reduce congestion along O’Riordan Street and improve access to Sydney Airport domestic

O’Riordan Street looking north towards King Street

Airport North precinct road upgradeMay 2016

The NSW Government is planning to upgrade roads north of Sydney’s Kingsford Smith Airport to improve traffic flow and connections to the airport and Port Botany.

Sydney Airport and Port Botany are two of Australia’s most important international gateways. The roads around the airport and Port Botany are becoming increasingly congested and need to be upgraded.

Roads and Maritime Services is planning to upgrade roads north of Sydney Airport to improve traffic flow and connections to the airport and Port Botany. This includes widening O’Riordan Street to three lanes in each direction between Bourke Road and Robey Street.

Roads and Maritime has prepared a Review of Environmental Factors to examine the potential impacts of the Airport North Precinct proposal and outline measures to reduce and manage these impacts. The Review of Environmental Factors and concept design for the proposal are on display for community and stakeholder feedback from Monday 23 May to Monday 13 June.

During the display period, printed copies of the Review of Environmental Factors will be available to view in two locations and we will hold two community information sessions. The times and locations are listed in this project update.

Key features and benefitsThe key features of the Airport North precinct proposal include:

• Converting the southern sections of Robey Street and O’Riordan Street into one‑way roads

• Widening O’Riordan Street to provide six through lanes between Bourke Road and Robey Street

• Reconfiguring the existing traffic lights on O’Riordan Street between Qantas Drive and Bourke Road

• Upgrading the footpath on the eastern side of O’Riordan Street.

The proposal would help increase traffic capacity and reduce congestion along O’Riordan Street and improve access to Sydney Airport domestic terminals.

Sydney Airport precinct upgradesThe Airport North precinct proposal is part of a suite of upgrades to improve traffic flow around Sydney Airport.

• Airport West: Widening Marsh Street, Arncliffe to three lanes in each direction between Giovanni Brunetti Bridge and the M5 interchange. Work started earlier this year and is expected to be completed by late 2017

• Airport East: Widening Joyce Drive and General Holmes Drive between O’Riordan Street and Mill Pond Drive and replacing the General Holmes Drive rail level crossing with a road underpass that links General Holmes Drive, Botany Road and Wentworth Avenue. Work started in late 2015 and will be completed by mid‑2018.

More information about these projects is available at rms.nsw.gov.au/sydneyairport.

Page 2: Airport North precinct road upgrade · The proposal would help increase traffic capacity and reduce congestion along O’Riordan Street and improve access to Sydney Airport domestic

Airport North precinct

O’Riordan StreetRobey Street

Rob

ey S

tree

t

Kin

g S

tree

t

Hig

h S

tree

tEw

an S

tree

t

Bourke R

oad

Qantas Drive

Joyc

e D

rive

Mascot

To City

To B

rig

hto

n L

e Sa

nd

s

To Southern Sydney

SydneyAirport

New right turn bay from O’Riordan Street into King Street

Widening O’Riordan Street to three lanes in each direction between Bourke Road and Robey Street

Upgrading the footpath along the eastern side of O’Riordan Street

One-way between Joyce Drive and Robey Street

One-way between Qantas Drive and O’Riordan Street

Dual left turn into Bourke Road

Modify property access to Stamford Hotel

Ausimage aerial photography under licence to Roads and Maritime Services by Jacobs Pty Ltd

Metres 10050

KEYAirport North proposal area

Footpath

Bus lane

Page 3: Airport North precinct road upgrade · The proposal would help increase traffic capacity and reduce congestion along O’Riordan Street and improve access to Sydney Airport domestic

May 2016RMS 16.201

Privacy Privacy Roads and Maritime Services (“RMS”) is subject to the Privacy and Personal Information Protection Act 1998 (“PPIP Act”) which requires that we comply with the Information Privacy Principles set out in the PPIP Act. All information in correspondence is collected for the sole purpose of assisting in the assessment of this proposal. The information received, including names and addresses of respondents, may be published in subsequent documents unless a clear indication is given in the correspondence that all or part of that information is not to be published. Otherwise RMS will only disclose your personal information, without your consent, if authorised by the law. Your personal information will be held by RMS at 27 Argyle Street, Parramatta NSW 2150. You have the right to access and correct the information if you believe that it is incorrect.

Community information sessionsWe will host two community information sessions where you can view the Review of Environmental Factors and speak to members of the project team. Feel free to drop in at any time:

• Saturday 28 May, 10am to midday Eastlakes Community Hall 2 Florence Avenue, Eastlakes

• Thursday 2 June, 5pm to 7pm Eastlakes Community Hall 2 Florence Avenue, Eastlakes

Display locationsThe Review of Environmental Factors is available to view in person at:

• City of Botany Bay Council Administration Centre 141 Coward Street, Mascot

• Mascot Library 2 Hatfield Street, Mascot

You can also view or download it online at rms.nsw.gov.au/airportnorth.

Have your sayRoads and Maritime is seeking community and stakeholder feedback on the Airport North precinct proposal concept design and Review of Environmental Factors from Monday 23 May to Monday 13 June. Written comments should be sent to:

Email: [email protected]

Mail: Airport North precinct Roads and Maritime Services PO Box 973, Parramatta CBD NSW 2124

Contact Us

For more information or to provide feedback, please contact the project team:

1300 852 557

[email protected]

Airport North precinct Roads and Maritime Services PO Box 973, Parramatta CBD, NSW 2124

rms.nsw.gov.au/airportnorth

This document contains important information about road projects in your area. If you require the services of an interpreter, please contact the Translating and Interpreting Service on 131 450 and

ask them to call the project team on 1300 852 557. The interpreter will then assist you with translation.

What happens next?Roads and Maritime will prepare a submissions report outlining the feedback received and our responses. We will consider all comments in finalising the proposal and continue to keep the community informed as the project progresses.

Consultation on strategic design

Investigations to develop concept design and review of environmental factors

Consultation report

Consultation on concept design and Review of Environmental Factors

Submissions report

Finalise detailed design

Award construction tender

Start construction

Open to traffic

WE ARE HERE