Airport IT&T 2013 Shane Zbrodoff
-
Upload
russell-publishing -
Category
Business
-
view
771 -
download
1
description
Transcript of Airport IT&T 2013 Shane Zbrodoff
IT Criticality in New Airport Design and Operations –
The Swing Gate System Case Study
Shane Zbrodoff IT Program Manager, Calgary International
Facilities Project Calgary International Airport
Information Technology Services in an Airport are not new…..
So what is so evolutionary?
Airport Information Technology is now critical to
Airport Building Design & Construction
International Facilities Project Swing Gate Case Study Calgary, Alberta Canada
Key Airport Stats
- “Medium” size classification - 12 Months Ending August 2013 14M Passengers - 142,398 square metres - 4 Concourses A, B, C, D - ~49 Gates
Why the IFP is needed…
And….
Reserved for existing and new terminal picture
Key IFP Building Stats - Designed: 2008 - Five Levels 183,500 square metres - Five – 737’s wing tip to wing tip in front hall - 22 Aircraft Gates - 300 Room Hotel - Central Hold Area - Commissioned: April 2015 - Full Service: October 2015 - 1.5B CAD
Building Design Principles and Challenges Must:
- Increase capacity - Meet environmental objectives - Keep the footprint small - Maintain operational flexibility - Provide excellent customer experience - Maximize operational capacity - Consider costs and revenue - Satisfy stakeholders!
Multiple Operational Stakeholders
Operational Information Operational Sectors - Domestic - International - Transborder (to United States)
- Pre-Clearance Facility with U.S. Customs on Site
Cash and Carry Duty Free
Rule: Passengers within sectors cannot blend or co-mingle!
This innovative design resulted in shared hallways, gateways, pathways, areas and doors!
Planners: Our job is done! Architect: Not an architectural problem – passenger flows complete! Operations: We want minimal costs and little manpower for this!
Implementation of Swing Gate Design
What do planners, architects and operators do when they have problems?
Give the problems to I.T!
IT inherited five major challenges: 1. Leading edge technology versus building design 2. Determine corridor change logic
3. Sector intelligence and data 4. Balance between automation and manual
5. Obtain Stakeholder Sign Off
First Challenge: Leading Edge Technology meets Building Design
Building design needs applied technology (Security and Controls)
CCTV and Access Control System
Coverage Problem?
Analytics
Architects love open glass – Analytic Cameras do not!!
Challenge two: Corridor change logic - Process and technology model - Stakeholders (airlines, agencies)
- Effective but easy to use
(DRAFT)
Touch Screens
• Wall Mounted • Strategically located
• Simple Feedback
• “Okay”, “Configuring” • “Corridor in use”
• Screen coordinates / echoes other
screens servicing same gate!
• Sector “state” fed to central console
Model Creation
Challenge three: Sector Intelligence and Data
- Problem: Sector knowledge and timing - REAL TIME Fix: Tie into AODB / Gate Planning and Active Management Tool
Key Technology
Related risk: Terminal Renumbering and Available Data
Challenge four: Degree of Automation / “IRROP”
Balance of Automation and Manual Processes
Technology breaks - Cameras fail - Door Motors Fail
Operations run late! Don’t want doors to swing in middle of boarding or deplaning!
Solution: Airline process finalizing flight
Solution: Contingency / Continuity Plans developed
Challenge five: External Stakeholder sign off Working committee Development of custom elements - Custom Console Presentations
Lab & Demo
Leading edge technology versus building design Determine corridor change logic Sector intelligence and data Balance between automation and manual Obtain Stakeholder Sign Off
Summary Report Card:
Thank you! Contact: Shane Zbrodoff International Facilities Project, IT Program Manager Calgary Airport Email: [email protected] Email2: [email protected]