AGOS Quarter 3 2014 Summary - AuScope Limited | AuScope€¦ · ·...
Transcript of AGOS Quarter 3 2014 Summary - AuScope Limited | AuScope€¦ · ·...
AGOS Milestone Report No 13 May 2014
AuScope Limited Australian Geophysical Observing System
AGOS Progress Quarter 3 2014
At the conclusion of Quarter 3 2014 (31 March 2014), most planned milestones had been reached in line with the AGOS Agreement. Good progress is being made to erode previously reported delays. Only one of the planned remote CORS GNSS sites now remains to be completed with construction underway. Subsurface access projects continue behind schedule and progress is being closely monitored. The new Ocean Bottom Seismometer (OBS) equipment is being tested under a revised and more costly testing plan, which has begun but remains behind schedule. Otherwise, all equipment and physical infrastructure originally planned for the AGOS investment has been acquired and deployments by end-‐user research groups are underway.
The Earth Sounding Network
All construction and procurement components of the project are now complete.
During this quarter a major new broad-‐band experiment representing collaboration between GSWA, UWA and Macquarie University has been started in the Capricorn Orogen of Western Australia using 36 Earth-‐data recorders.
AGOS electric and magnetic MT field instruments are currently deployed in a major geophysical monitoring experiment in Queensland for a coal seam gas program.
The first trials of the OBS units were undertaken off the NW Shelf with support from Woodside Petroleum. Tests in shallow water identified a problem with the release springs and in the absence of spares from the manufacturer, only 8 units were tested in deep water rather than the 12 planned. Seven instruments were recovered; the eighth appeared to release but did not reach the surface in a 27 hour search period. Under the terms of the contract, the manufacturer, Guralp, will replace the lost unit. Despite this incident, good data was recorded on the OBS out to 33 km range from the Woodside One of the AGOS OBS Fleet of 20 instruments seismic survey vessel.
The Geohistory Laboratory
Establishment of the Geohistory Laboratory is essentially complete. No further infrastructure expenditure has been undertaken on the Melbourne University node or the Curtin node of the laboratory. Inter-‐node calibration experiments between the Melbourne and Curtin have continued.
AGOS Milestone Report No 13 May 2014
AuScope Limited Australian Geophysical Observing System
The Subsurface Observatory
The Subsurface Observatory petrophysics laboratory has moved into a new space during this quarter in order to facilitate some required building renovations at the University of Melbourne. This has resulted in the facility getting a newer, larger and better suited space for it operations. During the move to the new space the petrophysics lab was offline for a period of about 2 weeks but it is operating again now.
Access projects are now well underway with three major drilling and logging programs currently in progress. New Petrophysics Lab at University of Melbourne
A request to utilise unspent project funds to acquire supplementary subsurface equipment including tilt meters, seismometers and flux monitors has been submitted to the Commonwealth following Board approval last March.
The Inversion Laboratory
The major event for the quarter was the launch of the iLab software portal. The iLab project is intended to make advanced inference and data analysis software available to the geophysical community. The website provides a portal for researchers to share their software. There are currently seven codes available through the portal (http://www.iearth.org.au/codes/) with a further 12 software packages lined up to be included prior to the completion of the project. This includes both inversion codes and some Red dots show the locations of registered iLab specific applications of inversion. users. At UQ node work continued on the main objective to develop a software facility for inversion of geophysical data sets focused on large scale seamless integration of different physics and joint inversion. During the last quarter
• inversion tool kit has been installed on NCI facility and benchmarked showing scalability up to 8000 cores.
• improvements were made on software testing and delivery. • a 2D Transverse Electric MT forward model was implemented in escript and tested against
benchmark solutions. • implementation of 2D MT code for the Transverse Magnetic MT mode was started. • work progressed on 2D waveform inversion.
AGOS Milestone Report No 13 May 2014
AuScope Limited Australian Geophysical Observing System
The Geospatial Observatory
The GNSS instrument pool remains operational. GA, ANU, UNSW, UTAS and the Australian Antarctic Division currently have AGOS supported research projects underway with equipment being using across Australia, Indonesia and Antarctica.
The AGOS GNSS CORS build (4 sites) is almost complete. The WA, Tasmania and Queensland CORS stations are fully operational. Civil construction for remaining site in SA is now complete and instrumentation will be installed in May 2014 -‐ completing the AGOS CORS build program.
The radar reflector array at Gunning near Canberra (shown in picture) has been imaged by four space agencies. The reflectors are being tested with the ultimate aim of improving radar sensor calibrations. Specific work with the Italian Space Agency is continuing after issues with radar data from the COSMO Sky MED satellite were identified using the AGOS Gunning reflectors.
The Gunning experiment will now conclude and the radar reflectors will be deployed to the Surat Basin, Queensland. Work in the Surat Basin will support the measurement of subsidence in Coal Seam Gas extractions areas. Tenders to build this infrastructure in Queensland have been finalised with civil work to commence in the coming quarter.
Tenders to build a survey ground mark infrastructure in the Surat and Galilee Basins have been finalised with civil work to commence in the coming quarter. Land access issues are progressively being resolved after successful negotiations with aboriginal and rural land owners in the areas of interest.
The Geophysical Education Observatory
This quarter the Australian Seismometers in Schools Network is in the final stages of installation of the network and is focusing on the development of support and educational materials. 40 Instruments are now installed in schools and installation is complete in WA, SA, VIC, NSW and Queensland. One instrument still remains unassigned for the Alice Springs or Tennant Creek area and a primary school is being considered for this instrument. Work continues on trying to improve ways of maintaining data flow and connectivity. A major highlight was the installation of Melrose High student Charlotte Anderson explains the final NSW instrument at The King’s AuSIS to Australia’s Chief Scientist Professor Ian Chubb School, Parramatta. It was installed in time at the ACE Science Centre Launch. for the launch of their new Science Centre.
AGOS Milestone Report No 13 May 2014
AuScope Limited Australian Geophysical Observing System
The GPS in Schools program is progressing in Tasmania, ACT, NSW, Victoria and Queensland. All Jurisdictions have commenced working with schools to identify requirements and are undertaking planning. The first GPS in Schools station has been installed in the ACT. A strong partnership has been developed with the University of Tasmania (UTAS) who has provided draft educational material that is targeted to high school students explaining the program. Work with the Department of Education, Tasmania, is continuing to refine this material. Project Milestones The status of project milestones is shown in the table below. Note that milestones shown incomplete in earlier Quarters are included below to show that progress has been made.
No. Milestone Projected completion Date
Status
Milestones to 31 December 2013 (reported not complete in earlier Reports)
43
Geospatial Observatory: 4 new permanent GNSS CORS stations installed
30 June 2013 3 sites complete and Civil construction for remaining site in SA is now complete with instrumentation to be installed in May 2014 -‐ completing the CORS build program scheduled for completion by end June 2014.
59 Geospatial Observatory: GNSS and radar reflector arrays designed and installed (first 50%)
30 September 2013 Complete
60
Subsurface Observatory: Third stage sites selected (Third Stage Sites refers to Borehole Seismology sites and associated Borehole Logging Data Access Infrastructure)
30 September 2013 75% complete. Final borehole seismometry access project planned for completion by September 2014.
63
Inversion Laboratory: Integration of inversion capability into Escript prototype released
31 December 2013 60% complete. Delayed to December 2014 because the AGOS inversion tools based on Escript are to be integrated into the Escript distribution as a package and are distributed with Escript releases rather than prototypes.
64 Geophysical Education Observatory: Remaining seismometer pool purchased
31 December 2013 Complete 40 school sites installed
65 Subsurface Observatory: Second stage completed
(second stage refers to Borehole
31 December 2013 This milestone is 65% complete. Delays relate largely to delays experienced by the 3rd party
AGOS Milestone Report No 13 May 2014
AuScope Limited Australian Geophysical Observing System
Logging Toolkit & Borehole Logging Data Access Infrastructure)
research groups in specifying and finalising subsurface research activities that require access funding. The matter has been flagged with DoE for further discussion and resolution. Planned completion revised to October 2014
Milestones to 31 March 2014
67
Geospatial Observatory: Remote sensing web portal developed
31 March 2014 Complete Approval sought for new data, additional to the original plan, to be purchased and included
68
Subsurface Observatory: Third stage logging pool procured
31 March 2014 All planned procurements complete. Approval sought for supplementary equipment, additional to original plan, to be purchased.
69 Milestone Report 13 31 March 2014 Complete for internal
distribution