Aggregate Planning (PPC)

download Aggregate Planning (PPC)

of 52

Transcript of Aggregate Planning (PPC)

  • 8/7/2019 Aggregate Planning (PPC)

    1/52

  • 8/7/2019 Aggregate Planning (PPC)

    2/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-2

    Learning ObjectivesLearning ObjectivesWhen you complete this chapter, you should be

    able to :

    Identify or Define:

    Aggregate planning

    Tactical scheduling

    Graphic technique for aggregate planning

    Mathematical techniques for aggregate planning

    Describe or Explain:

    How to do aggregate planning

    How service firms develop aggregate plans

  • 8/7/2019 Aggregate Planning (PPC)

    3/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-3

    AGREGAT ?

    KAPASITAS PRODUKSI.

    PERENCANAAN AGREGAT?

    Prosespenetapan tingkat output/kapasitasproduksi secara

    keseluruhangunamemenuhi tingkat permintaanyang diperolehdari peramalandanpesanandengan tujuanmeminimalkan totalbiayaproduksi.

  • 8/7/2019 Aggregate Planning (PPC)

    4/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-4

    FUNGSI PERENCANAAN AGREGATFUNGSI PERENCANAAN AGREGAT

    Menjamin rencanapenjualandanrencanaproduksikonsisten terhadaprencanastrategi perusahaan

    Alat ukur performansi prosesperencanaan

    produksi

    Menjaminkemampuanproduksi konsisten

    terhadaprencanaproduksi

  • 8/7/2019 Aggregate Planning (PPC)

    5/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-5

    Memonitor hasil produksi actual terhadaprencanaproduksi danmembuat penyesuaian

    Mengatur persediaanproduk jadi untukmencapai

    target danmembuat penyesuaian

    Mengarahkanpenyusunandanpelaksanaanjadwal

    indukproduksi

    FUNGSI PERENCANAANFUNGSI PERENCANAANAGREGATAGREGAT

  • 8/7/2019 Aggregate Planning (PPC)

    6/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-6

    TUJUAN PERENCANAAN AGREGATTUJUAN PERENCANAAN AGREGAT

    Mengembangkan perencanaan produksi yang feasiblepada tingkat menyeluruh yang akan mencapaikeseimbanagan antara permintaan dan suplai denganmemperhatikan biaya minimal dari rencana produksi

    yang dibuat, walaupun biaya bukan satu-satunya bahanpertimbangan.

    Sebagai masukan perencana sumber daya sehinggaperencanaan sumber daya dikembangkan untuk

    mendukung perencanaan produksi. Meredam (stabilisasi) produksi dan tenaga kerja

    terhadap fluktuasi permintaan

  • 8/7/2019 Aggregate Planning (PPC)

    7/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-7

    INPUT AGREGAT PLANNINGINPUT AGREGAT PLANNING

    Sumber dayayang tersedia sepanjangperioderencanaproduksi harus diketahui

    Data permintaanyang berasal dari peramalandan

    pesananharus tersediaMemasukkankebijakanperusahaanyang

    berkenaandenganperencanaanagregat,

    misalnyaperubahan tingkat tenegakerja, danpenentuankebutuhansumber daya

  • 8/7/2019 Aggregate Planning (PPC)

    8/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-8

    Aggregate Planning RequiresAggregate Planning Requires

    Logical overall unit for measuring sales andoutputs

    Forecast of demand for intermediate planning

    period in these aggregate units

    Method for determining costs

    Model that combines forecasts and costs so that

    planning decisions can be made

  • 8/7/2019 Aggregate Planning (PPC)

    9/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-9

    Setting goals & objectives

    Example: Meet demand within the limits

    of available resources at the least cost

    Determining steps to achieve goals

    Example: Hire more workers

    Setting start & completion dates

    Example: Begin hiring in Jan.; finish, Mar.

    Assigning responsibility

    PlanningPlanning

  • 8/7/2019 Aggregate Planning (PPC)

    10/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-10

    Planning Tasks and ResponsibilitiesPlanning Tasks and Responsibilities

  • 8/7/2019 Aggregate Planning (PPC)

    11/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-11

    Planning HorizonsPlanning Horizons

    Today 3 Months 1 year 5 years

    Planning Horizon

    Short-range plans

    Job assignmentsOrdering

    Job scheduling

    Dispatching

    Intermediate-range plans

    Sales planning

    Production planning and

    budgeting

    Setting employment, inventory,subcontracting levels

    Analyzing operating plans

    Long-range plans

    R&D

    New product plans

    Capital expenses

    Facility location, expansion

    Responsible:

    Operationsmanagers,

    supervisors,

    foremen

    Responsible:

    Operations

    managers

    Responsible:

    Top executives

  • 8/7/2019 Aggregate Planning (PPC)

    12/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-12

    Relationships of the Aggregate PlanRelationships of the Aggregate Plan

    Aggregate

    Plan forProduction

    Demand

    Forecasts,

    orders

    Master

    Production

    Schedule, and MRP systems

    Detailed Work

    Schedules

    External

    Capacity

    Subcontractors

    Inventory On

    Hand

    Raw Materials

    Available

    Work Force

    Marketplace

    and Demand

    Research and

    TechnologyProduct

    Decisions

    Process

    Planning & Capacity

    Decisions

  • 8/7/2019 Aggregate Planning (PPC)

    13/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-13

    Master scheduling

    Material requirements planning

    Order schedulingWeekly workforce andcustomer scheduling

    Daily workforce and customer scheduling

    Process planning

    Strategic capacity planning

    Sales and operations (aggregate) planning

    Long

    range

    Intermediate

    range

    Short

    range

    Manufacturing

    Services

    Exhibit 14.1Exhibit 14.1

    Sales plan Aggregate operations plan

    Forecasting

    & demandmanagement

  • 8/7/2019 Aggregate Planning (PPC)

    14/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-14

    A mathematically based aggregate planning model requiresconsiderable: time

    problem definitionmodel developmentmodel verification

    model application expertise

    people who understand the problem people who understand both the modeling process, and the

    specific model

    moneymoney to pay for all of the above often requires funding for several people for several months!

    WhatWhat s Needed for Aggregates Needed for AggregatePlanningPlanning

  • 8/7/2019 Aggregate Planning (PPC)

    15/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-15

    Provides the quantity and timing of production forintermediate future

    Usually 3 to 18 months into future

    Combines (aggregates) production Often expressed in common units

    Example: Hours, dollars, equivalents

    (e.g., FTE students)

    Involves capacity and demand variables

    Aggregate PlanningAggregate Planning

  • 8/7/2019 Aggregate Planning (PPC)

    16/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-16

    Meet demand

    Use capacity efficiently

    Meet inventory policy

    Minimize cost

    Labor

    Inventory

    Plant & equipment

    Subcontract

    Aggregate Planning GoalsAggregate Planning Goals

  • 8/7/2019 Aggregate Planning (PPC)

    17/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-17

    Aggregate Planning StrategiesAggregate Planning StrategiesPure StrategiesPure Strategies

    Capacity Options change capacity:

    changing inventory levels

    varying work force size by hiring or layoffs

    varying production capacity through overtime or idle

    time

    subcontracting

    using part-time workers

  • 8/7/2019 Aggregate Planning (PPC)

    18/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-18

    Aggregate Planning StrategiesAggregate Planning StrategiesPure StrategiesPure Strategies

    Demand Options change demand:

    influencing demand

    backordering during high demand periods

    counterseasonal product mixing

  • 8/7/2019 Aggregate Planning (PPC)

    19/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    The Aggregate Operations PlanThe Aggregate Operations Plan Main purpose: Specify the optimalcombination of

    production rate (units completed per unit oftime)

    workforce level (number of workers)

    inventory on hand (inventory carried fromprevious period)

    Product group or broad category(Aggregation)

    This planning is done over an intermediate-range planning period of 3 to 18 months

  • 8/7/2019 Aggregate Planning (PPC)

    20/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Balancing Aggregate DemandBalancing Aggregate Demandand Aggregate Production Capacityand Aggregate Production Capacity

    0

    2000

    4000

    6000

    8000

    10000

    Jan Feb Mar Apr May Jun

    45005500

    7000

    10000

    8000

    6000

    0

    2000

    4000

    6000

    8000

    10000

    Jan Feb Mar Apr May Jun

    4500 4000

    90008000

    4000

    6000

    Suppose the figure to

    the right representsforecast demand inunits

    Suppose the figure tothe right representsforecast demand inunits

    Now suppose thislower figure represents

    the aggregate capacityof the company to meetdemand

    Now suppose thislower figure represents

    the aggregate capacityof the company to meetdemand

    What we want to do is

    balance out theproduction rate,workforce levels, andinventory to makethese figures match up

    What we want to do is

    balance out theproduction rate,workforce levels, andinventory to makethese figures match up

  • 8/7/2019 Aggregate Planning (PPC)

    21/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Required Inputs to the Production Planning SystemRequired Inputs to the Production Planning System

    Planning

    for

    production

    Externa

    l

    capacity

    Competitors

    behavior

    Raw

    material

    availability

    Market

    demand

    Economic

    conditions

    Current

    physical

    capacit

    y

    Current

    workforce

    Inventory

    levels

    Activities

    required

    for

    productio

    n

    Externalto firm

    Internalto firm

  • 8/7/2019 Aggregate Planning (PPC)

    22/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-22

    Aggregate Scheduling OptionsAggregate Scheduling Options --Advantages and DisadvantagesAdvantages and Disadvantages

    Option Advantage Disadvantage Some

    Comments

    Changinginventory levels

    Changes inhuman resourcesare gradual, not

    abruptproductionchanges

    Inventoryholding costs;Shortages may

    result in lostsales

    Applies mainlyto production,not service,

    operations

    Varying

    workforce sizeby hiring orlayoffs

    Avoids use of

    other alternatives

    Hiring, layoff,

    and trainingcosts

    Used where size

    of labor pool islarge

  • 8/7/2019 Aggregate Planning (PPC)

    23/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-23

    Option Advantage Disadvantage Some

    CommentsVaryingproduction ratesthrough overtimeor idle time

    Matches seasonalfluctuationswithouthiring/training

    costs

    Overtimepremiums, tiredworkers, may notmeet demand

    Allowsflexibility withinthe aggregateplan

    Subcontracting Permitsflexibility andsmoothing of thefirm's output

    Loss of qualitycontrol; reducedprofits; loss offuture business

    Applies mainlyin productionsettings

    Advantages/DisadvantagesAdvantages/Disadvantages --ContinuedContinued

  • 8/7/2019 Aggregate Planning (PPC)

    24/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-24

    Advantages/DisadvantagesAdvantages/Disadvantages --ContinuedContinued

    Option Advantage Disadvantage Some

    CommentsUsing part-timeworkers

    Less costly andmore flexiblethan full-timeworkers

    Highturnover/trainingcosts; qualitysuffers;

    schedulingdifficult

    Good forunskilled jobs inareas with largetemporary labor

    pools

    Influencingdemand

    Tries to useexcess capacity.Discounts draw

    new customers.

    Uncertainty indemand. Hard tomatch demand to

    supply exactly.

    Createsmarketing ideas.Overbooking

    used in somebusinesses.

  • 8/7/2019 Aggregate Planning (PPC)

    25/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-25

    Advantage/DisadvantageAdvantage/Disadvantage --ContinuedContinued

    Option Advantage Disadvantage Some

    CommentsBack orderingduring high-demand periods

    May avoidovertime. Keepscapacity constant

    Customer mustbe willing towait, butgoodwill is lost.

    Many companiesbackorder.

    Counterseasonalproducts andservice mixing

    Fully utilizesresources; allowsstable workforce.

    May requireskills orequipmentoutside a firm'sareas of

    expertise.

    Risky findingproducts orservices withopposite demandpatterns.

  • 8/7/2019 Aggregate Planning (PPC)

    26/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-26

    STRATEGI DAN TEKNIKSTRATEGI DAN TEKNIK

    PERENCANAAN PRODUKSIPERENCANAAN PRODUKSI

    STRATEGI MURNISTRATEGI CAMPURAN

  • 8/7/2019 Aggregate Planning (PPC)

    27/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-27

    STRATEGI MURNIStrategi murni adalahstrategi denganmelakukanperubahanpadasalahsatu factor yang tersebut diatas,

    yang meliputi :1.Mengendalikan jumlahinventori

    2.Mengendalikan jumlah tenagakerja

    3.Subkontrak4.Mempengaruhi permintaan

  • 8/7/2019 Aggregate Planning (PPC)

    28/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-28

    STRATEGI CAMPURANStrategi ini merupakanpenggunaanduaatau lebih

    strategi murni untukmenghasilkanperencanaan

    produksi yang feasible.

  • 8/7/2019 Aggregate Planning (PPC)

    29/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-29

    METODE PERENCANAAN PRODUKSIMETODE PERENCANAAN PRODUKSI

    LEVEL METHODLEVEL METHOD WITH OVERTIME

    CHASE STRATEGY

    LINIER PROGRAMMING

    COMPROMISE STRATEGY

  • 8/7/2019 Aggregate Planning (PPC)

    30/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-30

    The ExtremesThe Extremes

    Level

    Strategy

    Chase

    Strategy

    Production

    equals

    demand

    Production rate

    is constant

  • 8/7/2019 Aggregate Planning (PPC)

    31/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-31

    Mixed strategy

    Combines 2 or more aggregate scheduling options

    Level scheduling strategy

    Produce same amount every day

    Keep work force level constant

    Vary non-work force capacity or demand options

    Often results in lowest production costs

    Aggregate Planning StrategiesAggregate Planning Strategies

  • 8/7/2019 Aggregate Planning (PPC)

    32/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Key Strategies for Meeting DemandKey Strategies for Meeting Demand

    Chase

    Level

    Some combination of the two

  • 8/7/2019 Aggregate Planning (PPC)

    33/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-33

    LEVEL METHODMetode ini menghitung jumlah tenagakerjayang

    dibutuhkanberdasarkanpermintaandan inventori yang

    ada. Dengan inventori tetapsetiapperiodenya. Tenagakerja yang adaharusdapat memenuhi kebutuhan

    permintaan total selamasatu tahun. Dan diasumsikan

    tidak adaovertime.

  • 8/7/2019 Aggregate Planning (PPC)

    34/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-34

    LEVEL METHOD WITH OVERTIME

    Perhitunganyang dilakukansamaseperti level work

    force, hanyadiasumsikanadanyaovertime.

    CHASE STRATEGYPadastrategi ini adanyakebutuhan tenagakerjayang

    bervariansi setiapperiodeberdasarkanpermintaan

    yang harusdipenuhi. Dan adanyainventori yangbesarnyasamatiapperiodenya.

  • 8/7/2019 Aggregate Planning (PPC)

    35/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-35

    LINIER PROGRAMMINGLinier programming digunakanbilaproduksi yang

    berjalan terdiri dari duamacamprodukatau lebih.

    Karena tidakmungkin diselesaikandenganmetodesebelumnya. Prosedur perhitunganyang dilakukan

    melalui metodesimplekyang biasanyaterdapat dalam

    perhitunganmengenai penelitianoperasional.

  • 8/7/2019 Aggregate Planning (PPC)

    36/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-36

    TAHAPAN AGREGAT PLANNINGTAHAPAN AGREGAT PLANNING

    COLLECTING DATA : SALESFORECAST,ORDERS, ADANYA

    BACKORDERS,INVENTORY AWAL

    MEMBUAT TABEL INFORMASIMENENTUKAN KAPABILITAS PRODUKSI

    MELAKUKAN PARTNERSHIP MEETING YANG

    DIHADIRI OLEH SELURUH MANAJER.

  • 8/7/2019 Aggregate Planning (PPC)

    37/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-37

    FORMULAFORMULA

    RENCANA PRODUKSI = (PERMINTAAN TOTAL-

    INVENTORI AWAL)+INVENTORI AKHIR

    RENCANA PRODUKSI HARIAN=

    RENCANA PRODUKSI BULANAN / JML HARIKERJA

    SIKLUS WAKTU=

    JAM KERJA YG TERSEDIA PERHARI / PRODUKSIHARIAN

  • 8/7/2019 Aggregate Planning (PPC)

    38/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-38

    LEVEL METHODLEVEL METHOD

    MEMPUNYAI DISTRIBUSI MERATAMEMPERTAHANKAN TINGKAT KESTABILAN

    PRODUKSI SEMENTARA MENGGUNAKAN

    INVENTORI YANG BERVARIASI UNTUKMENGAKUMULASI OUTPUT

    RENCANA PRODUKSI = PERMINTAAN TOTAL

    TAHUNAN / BANYAKNYA PERIODE INVENTORY= (INVENTORI AWAL + PRODUKSI)

    PERMINTAAN TOTAL

  • 8/7/2019 Aggregate Planning (PPC)

    39/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-39

    CHASE STRATEGYCHASE STRATEGY

    MEMPERTAHANKAN TINGKAT KESTABILANINVENTORY

    PRODUKSI BERVARIASI MENGIKUTI

    PERMINTAAN TOTALRENCANA PRODUKSI = PERMINTAAN TOTAL

  • 8/7/2019 Aggregate Planning (PPC)

    40/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-40

    COMPROMISE STRATEGYCOMPROMISE STRATEGY

    KOMPROMI ANTARA KEDUA METODEPERENCANAAN PRODUKSI

    DITETAPKAN TERLEBIH DAHULU HORISONWAKTU PERENCANAAN PRODUKSI

    PRODUKSI DILAKUKAN KETIKA INVENTORY ONHAND HABIS.

    RENCANA PRODUKSI = PERMINTAAN TOTAL

    TAHUNAN / BANYAKNYA HORISON WAKTUPERENCANAAN

  • 8/7/2019 Aggregate Planning (PPC)

    41/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Aggregate Planning Examples: Unit Demand and Cost DataAggregate Planning Examples: Unit Demand and Cost Data

    Materials $5/unit

    Holding costs $1/unit per mo.

    Marginal cost of stockout $1.25/unit per mo.Hiring and training cost $200/worker

    Layoff costs $250/worker

    Labor hours required .15 hrs/unit

    Straight time labor cost $8/hourBeginning inventory 250 units

    Productive hours/worker/day 7.25

    Paid straight hrs/day 8

    Workforce 200 people

    Suppose we have the following unitdemand and cost information:

    Suppose we have the following unitdemand and cost information:

    Demand/mo Jan Feb Mar Apr May Jun

    4500 5500 7000 10000 8000 6000

  • 8/7/2019 Aggregate Planning (PPC)

    42/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-42

    Jan Feb Mar Apr May Jun

    Days/mo 22 19 21 21 22 20

    Hrs/worker/mo 159.5

    Units/worker 23.98

    $/worker $1,408

    Productive hours/worker/day 7.25

    Paid straight hrs/day 8

    Demand/mo Jan Feb Mar Apr May Jun4500 5500 7000 10000 8000 6000

    Given the demand and cost information below, whatare the aggregate hours/worker/month, units/worker, anddollars/worker?

    Given the demand and cost information below, whatare the aggregate hours/worker/month, units/worker, anddollars/worker?

    7.25x2

    2

    7.25x0.15=1.09 &

    1.09x22=23.9822x8hrsx$8=$14

    08

    CutCut--andand--Try Example: DeterminingTry Example: Determining

    Straight Labor Costs and OutputStraight Labor Costs and Output

  • 8/7/2019 Aggregate Planning (PPC)

    43/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Chase StrategyChase Strategy(Hiring & Firing to meet demand)(Hiring & Firing to meet demand)

    Jan

    Days/mo 22

    Hrs/worker/mo 159.5

    Units/worker 23.98

    $/worker $1,408

    Jan

    Demand 4,500

    Beg. inv. 250

    Net req. 4,250

    Req. workers 177.23

    Hired

    Fired 22

    Workforce 200

    Ending inventory 0

    Lets assume our current workforce is 7 workers.Lets assume our current workforce is 7 workers.

    First, calculate net requirements forproduction, or 4500-250=4250 units

    Then, calculate number of workersneeded to produce the netrequirements, or 4250/23.98=177.23or 178 workers

    Finally, determine the number ofworkers to hire/fire. In this case weonly need 178 workers, we have200, so 22 can be fired.

  • 8/7/2019 Aggregate Planning (PPC)

    44/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Jan Feb Mar Apr May Jun

    Days/mo 22 19 21 21 22 20

    Hrs/worker/mo 159.5

    Units/worker 24

    $/worker $1,408

    Jan Feb Mar Apr May Jun

    Demand 4,500 5,500 7,000 10,000 8,000 6,000

    Beg. inv. 250

    Net req. 4,250

    Req. workers 177.23

    Hired

    Fired 22

    Workforce 200 200 200 200 200 200

    Ending inventory 0 0 0 0 0 0

    Below are the complete calculations for the remainingmonths in the six month planning horizon

    Below are the complete calculations for the remainingmonths in the six month planning horizon

  • 8/7/2019 Aggregate Planning (PPC)

    45/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Jan Feb Mar Apr May Jun

    Demand 4,500 5,500 7,000 10,000 8,000 6,000

    Beg. inv. 250

    Net req. 4,250 5,500 7,000 10,000 8,000 6,000

    Req. workers 3.997 5.989 6.897 9.852 7.524 6.207

    Hired 2 1 3

    Fired 3 2 1

    Workforce 4 6 7 10 8 7

    Ending inventory 0 0 0 0 0 0

    Jan Feb Mar Apr May Jun Costs

    Material $21,250.00 $27,500.00 $35,000.00 $50,000.00 $40,000.00 $30,000.00 203,750.00

    Labor 5,627.59 7,282.76 9,268.97 13,241.38 10,593.10 7,944.83 53,958.62Hiring cost 400.00 200.00 600.00 1,200.00

    Firing cost 750.00 500.00 250.00 1,500.00

    $260,408.62

    Below are the complete calculations for the remaining months in

    the six month planning horizon with the other costs included

  • 8/7/2019 Aggregate Planning (PPC)

    46/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Level Workforce Strategy (Surplus and Shortage Allowed)Level Workforce Strategy (Surplus and Shortage Allowed)

    Jan

    Demand 4,500

    Beg. inv. 250

    Net req. 4,250

    Workers 6

    Production 6,380

    Ending inventory 2,130Surplus 2,130

    Shortage

    Lets take the same problem

    as before but this time usethe Level Workforce strategy

    Lets take the same problemas before but this time usethe Level Workforce strategy

    This time we will seek to usea workforce level of 6workers

    This time we will seek to usea workforce level of 6

    workers

  • 8/7/2019 Aggregate Planning (PPC)

    47/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Jan Feb Mar Apr May Jun

    Demand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250 2,130 2,140 1,230 -2,680 -1,300

    Net req. 4,250 3,370 4,860 8,770 10,680 7,300

    Workers 6 6 6 6 6 6

    Production 6,380 5,510 6,090 6,090 6,380 5,800Ending inventory 2,130 2,140 1,230 -2,680 -1,300 -1,500

    Surplus 2,130 2,140 1,230

    Shortage 2,680 1,300 1,500

    Note, if we recalculate this sheet with 7 workerswe would have a surplusNote, if we recalculate this sheet with 7 workerswe would have a surplus

    Below are the complete calculations for theremaining months in the six month planning horizonBelow are the complete calculations for theremaining months in the six month planning horizon

    B l th l t l l ti f th

  • 8/7/2019 Aggregate Planning (PPC)

    48/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO

    Jan Feb Mar Apr May Jun

    4,500 5,500 7,000 10,000 8,000 6,000250 2,130 10 -910 -3,910 -1,620

    4,250 3,370 4,860 8,770 10,680 7,300

    6 6 6 6 6 6

    6,380 5,510 6,090 6,090 6,380 5,800

    2,130 2,140 1,230 -2,680 -1,300 -1,500

    2,130 2,140 1,2302,680 1,300 1,500

    Jan Feb Mar Apr May Jun

    $8,448 $7,296 $8,064 $8,064 $8,448 $7,680 $48,000.00

    31,900 27,550 30,450 30,450 31,900 29,000 181,250.002,130 2,140 1,230 5,500.00

    3,350 1,625 1,875 6,850.00

    $241,600.00

    Below are the complete calculations for the

    remaining months in the six month planninghorizon with the other costs included

    Below are the complete calculations for the

    remaining months in the six month planninghorizon with the other costs included

    Note, totalcosts underthis strategyare less than

    Chase at$260.408.62

    Note, totalcosts underthis strategyare less thanChase at$260.408.62

    Labor

    MaterialStorageStockout

  • 8/7/2019 Aggregate Planning (PPC)

    49/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-49

    The Graphical Approach toThe Graphical Approach toAggregate PlanningAggregate Planning

    Forecast the demand for each period

    Determine the capacity for regular time, overtime,and subcontracting, for each period

    Determine the labor costs, hiring and firing costs,

    and inventory holding costs Consider company policies which may apply to the

    workers or to stock levels

    Develop alternative plans, and examine their total

    costs

  • 8/7/2019 Aggregate Planning (PPC)

    50/52

    C m lati e Demand Graph forCumulative Demand Graph for

  • 8/7/2019 Aggregate Planning (PPC)

    51/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-51

    Cumulative Demand Graph forCumulative Demand Graph for

    Plan 1Plan 1

    Jan Feb Mar Apr May Jun

    Cumulative forecast

    requirements

    Cumulative level

    production using

    average monthly

    forecast

    requirements

    Reduction ofinventory

    Excess inventoryC

    umulativeD

    emand(Units)

    7,000

    6,000

    5,000

    4,000

    3,000

    2,000

    1,000

  • 8/7/2019 Aggregate Planning (PPC)

    52/52

    JURUSAN TEKNIK INDUSTRI

    UNISSULA SEMARANG

    ANDRE SUGIYONO04-52

    Controlling the Cost of Labor inControlling the Cost of Labor inService FirmsService Firms

    Seek:

    Close control of labor hours to ensure quick responseto customer demand

    On-call labor resource that can be added or deleted to

    meet unexpected demand Flexibility of individual worker skills to permit

    reallocation of available labor

    Flexibility of individual worker in rate of output or hours

    of work to meet demand