Agenda for Package Review Meeting
Water treatment Plant - M/s Triveni
Agenda points Status as on date ResolutionStart Date
A Engineering (Civil)
1 Civil GA for Effluent Pit
2
3
4
5
6 Reactor Clarifier (DM) Deleated
7 Reinforcement detail for Effluent Pit
8
9 Reinforcement detail of DM WST
0 Filter house
1 by 24-11-10
2
3 Civil GA of Chemical building 5-Dec-10 Not yet sumbitted.
4 5-Dec-10 Not yet sumbitted.
5 5-Dec-10 Not yet sumbitted.
6 5-Dec-10
7 5-Dec-10 Not yet sumbitted.
ate of Meeting : 17-12-10me : 2.30 pm Onwards
articipants :lace : GMR Energy, Site office, Warora
SlNo
Planned Date / IssueDate Resolution on
19.11.10CompletionDate
Plan as perL2 Scheduleconstruction
activities
Effluent GA commentsare resubmitted byTriveni. Triveni agreedto issue the compliancereport by 22-11-10.Civil drawings ofcascade aerator andETP by 31-12-10
Submitted on 13-12-2010. Pending withTCE for approval.
Rein orcement etai o UF PRODUCT
WATER STORAGE TANKFOUNDATION M/s Triveni agreed tosubmit completedrawing by 24-11-10and approval expectedby 1-12-10
Submitted and
approved.
Reinforcement detail of DG WATERSTORAGE TANK FOUNDATION
Submitted andapproved.
GA of RO PRODUCT WATER STORAGE TANK FOUNDATION
Submitted andapproved in BCategory.
Reinforcement detail of ReactorClarifier (PT)
It will be submitted by25-11-10 and to beapproved by 30-11-10
Submitted on13/11/2010
Submitted on15/12/2010
Reinforcement detail of CascadeAerator & stilling chamber
To be Submitted by17/12/2010
u m e on - -and to be approved by30-11-10
Submitted andapproved.
Compliance submitted.Critical item. Priority tobe given on this and tobe issued by 15-12-10(calculation andfoundation drwng)
GA of Partial flume and distrubutionchamber for PT clarifier.
Submitted on 30-11-2010. Pending withTCE for Approval.
DBR for Chlorination system, CWtreatment , AC & Ventilation, cranesfor all WTP building
complete designengineering 31-12-102)Weekly review
meeting to be heldfrom next weekonwards. This is a mustto complete thepackage with outschedule
Civil GA of PT clarified waterstorage tankDesign calculation of Chemicalbuilding
Reinforcement detail of PT clarifiedwater storage tank ( Comes in sideGravity sand filter House)Deleted(Part of Filter house )
Reinforcement detail of ERS Clarifiedwater storage tank
-
8/8/2019 Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10
2/3
Agenda for Package Review Meeting
Water treatment Plant - M/s Triveni
Agenda points Status as on date ResolutionStart Date
ate of Meeting : 17-12-10me : 2.30 pm Onwards
articipants :lace : GMR Energy, Site office, Warora
SlNo
Planned Date / IssueDate Resolution on
19.11.10CompletionDate
B Engineering (Mechanical)
1 GA of Centrifuge / building Not yet sumbitted.
2 GA of ERS clarifier feed pumps Open
3 GA of Reservoir Water pumps. Provided
4 Revised GA of ERS clarifiers Pending
5
6 Electrical
7 15-Dec-10 Not yet sumbitted.
8 10-Dec-10 Not yet sumbitted.
9 Piping Layout for PT Plant 5-Dec-10 Not yet sumbitted.
0 Piping Layout for DM Plant 5-Dec-10 Not yet sumbitted.
1 5-Dec-10 Not yet sumbitted.
2 Equipment GA of MCF - RO First Pass 5-Dec-10 Not yet sumbitted.
3 Equipment GA of MCF - CIP 5-Dec-10 Not yet sumbitted.
4 5-Dec-10 Not yet sumbitted.
C Engineering (Electrical & Instrumentation)
1 5-Nov-10
2 8-Nov-10 Not yet sumbitted.
3 10-Nov-10
4 10-Nov-10
5 10-Nov-10 Not yet sumbitted.
6 - Not yet sumbitted.
D Procurement Activities - Floating enquiries and order placement
1 PT Plant - Clarifier 11-Oct-10 29-Oct-10
2 PT Plant - Thickener 20-Oct-10 9-Nov-10
3 PT Plant - Clarifier-ETP Plant 20-Oct-10 9-Nov-10
4 PT Plant - Dosing Tanks 1-Nov-10 12-Nov-10
5 PT Plant - Dosing Pumps 1-Nov-10 19-Nov-10
6 PT Plant - Centrifuge 15-Nov-10 10-Dec-10
7 PT Plant - Motors 15-Nov-10 10-Dec-10
Revised GA of filter tank cumpumphouse
Pending with TCE
Rev-01 dated20/11/2010 TL No. 64
Design Basis Report For ChlorinationSystemLayout Diagram for ChlorinationSystem
Skid drawing for RO First Pass &Second Pass
Equipment GA of MCF - RO SecondPass
oc no. . - - - ,Incomer sizing calculations ,Submission date 5-11-10
omp ance y25/11/2010 (TL-68dated 25 11 2010
oc no. . - - - ,Sizing Calculations , Submission date8-11-10oc no. . - - - ,Lighting calculations , Submissiondate 10-11-10
omp ance y30/11/2010 (TL-70dated 29 11 2010
Doc no. TCE.5773A-612-EL-0141,
Data Sheet & GA Drawing for LocalPush Button Stations , Submissiondate 10-11-10
Compliance by
25/11/2010 (TL-68dated 25/11/2010
Doc no.TCE.5773A-612-IC-0120,GADrawing for Junction Box , Submissiondate 10-11-10
oc no. . - - - ,Instrument Data Sheet , Submissiondate 15-01-10
Status on the same to
be update by M/sTriveni - OrderPlacementexpected by Dec 10
-
8/8/2019 Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10
3/3
Agenda for Package Review Meeting
Water treatment Plant - M/s Triveni
Agenda points Status as on date ResolutionStart Date
ate of Meeting : 17-12-10me : 2.30 pm Onwards
articipants :lace : GMR Energy, Site office, Warora
Slo
Planned Date / IssueDate
Resolution on19.11.10Completion
Date
E MANUFACTURING, INSPECTION & DESPATCH
1 2-Nov-10 11-Feb-10 Not Yet started
2 11-Nov-10 23-Feb-11 Not Yet started
3 11-Nov-10 23-Feb-11 Not Yet started
4 16-Nov-10 7-Feb-11 Not Yet started
F Construction ( As per L2 Schedule Activities Major Milestone - upto Jan 2011)
1 Mobilization and site enabling facility
2 20-Sep-10
3 20-Sep-10
4 Start of Civil Work for PT clarifier tank 20-Sep-10
5 20-Sep-10
6 15-Dec-10
7
8 Look ahead schedule till Jan 2011
9 Catchup plan for major milestones
G C&C
H Other
1 Monthly Progress Report Submitted
2 updated L2 Schedule
Participants
M/S GMR M/S Triveni
Clarifier - PT Plant - Materialprocurement and manufacturing
Thickener - PT Plant - Materialprocurement and manufacturing
Clarifier - ETP Plant - Materialprocurement and manufacturing
Dosing Tank - Material procurementand manufacturing
Excavation forClarifier tank Started ,Recovery Plan notsubmitted
Start o Civi Wor or Casca eaeratorStart of Civil Work for Stillingchamber, parshall flume &distribution channel
Start of Civil work for RCC Channelbetween calrifier & RGF inlet chambe
Start of Civil work for Rapid GravitySand filterVendor Approval for ClarifierConstruction
submitted the MPR ,however it needs to besubmitted within 4th ofeverry month.
Submitted in pdfformat, requested forSoft copy in MicrosoftProject format