Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10

download Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10

of 3

Transcript of Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10

  • 8/8/2019 Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10

    1/3

    Agenda for Package Review Meeting

    Water treatment Plant - M/s Triveni

    Agenda points Status as on date ResolutionStart Date

    A Engineering (Civil)

    1 Civil GA for Effluent Pit

    2

    3

    4

    5

    6 Reactor Clarifier (DM) Deleated

    7 Reinforcement detail for Effluent Pit

    8

    9 Reinforcement detail of DM WST

    0 Filter house

    1 by 24-11-10

    2

    3 Civil GA of Chemical building 5-Dec-10 Not yet sumbitted.

    4 5-Dec-10 Not yet sumbitted.

    5 5-Dec-10 Not yet sumbitted.

    6 5-Dec-10

    7 5-Dec-10 Not yet sumbitted.

    ate of Meeting : 17-12-10me : 2.30 pm Onwards

    articipants :lace : GMR Energy, Site office, Warora

    SlNo

    Planned Date / IssueDate Resolution on

    19.11.10CompletionDate

    Plan as perL2 Scheduleconstruction

    activities

    Effluent GA commentsare resubmitted byTriveni. Triveni agreedto issue the compliancereport by 22-11-10.Civil drawings ofcascade aerator andETP by 31-12-10

    Submitted on 13-12-2010. Pending withTCE for approval.

    Rein orcement etai o UF PRODUCT

    WATER STORAGE TANKFOUNDATION M/s Triveni agreed tosubmit completedrawing by 24-11-10and approval expectedby 1-12-10

    Submitted and

    approved.

    Reinforcement detail of DG WATERSTORAGE TANK FOUNDATION

    Submitted andapproved.

    GA of RO PRODUCT WATER STORAGE TANK FOUNDATION

    Submitted andapproved in BCategory.

    Reinforcement detail of ReactorClarifier (PT)

    It will be submitted by25-11-10 and to beapproved by 30-11-10

    Submitted on13/11/2010

    Submitted on15/12/2010

    Reinforcement detail of CascadeAerator & stilling chamber

    To be Submitted by17/12/2010

    u m e on - -and to be approved by30-11-10

    Submitted andapproved.

    Compliance submitted.Critical item. Priority tobe given on this and tobe issued by 15-12-10(calculation andfoundation drwng)

    GA of Partial flume and distrubutionchamber for PT clarifier.

    Submitted on 30-11-2010. Pending withTCE for Approval.

    DBR for Chlorination system, CWtreatment , AC & Ventilation, cranesfor all WTP building

    complete designengineering 31-12-102)Weekly review

    meeting to be heldfrom next weekonwards. This is a mustto complete thepackage with outschedule

    Civil GA of PT clarified waterstorage tankDesign calculation of Chemicalbuilding

    Reinforcement detail of PT clarifiedwater storage tank ( Comes in sideGravity sand filter House)Deleted(Part of Filter house )

    Reinforcement detail of ERS Clarifiedwater storage tank

  • 8/8/2019 Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10

    2/3

    Agenda for Package Review Meeting

    Water treatment Plant - M/s Triveni

    Agenda points Status as on date ResolutionStart Date

    ate of Meeting : 17-12-10me : 2.30 pm Onwards

    articipants :lace : GMR Energy, Site office, Warora

    SlNo

    Planned Date / IssueDate Resolution on

    19.11.10CompletionDate

    B Engineering (Mechanical)

    1 GA of Centrifuge / building Not yet sumbitted.

    2 GA of ERS clarifier feed pumps Open

    3 GA of Reservoir Water pumps. Provided

    4 Revised GA of ERS clarifiers Pending

    5

    6 Electrical

    7 15-Dec-10 Not yet sumbitted.

    8 10-Dec-10 Not yet sumbitted.

    9 Piping Layout for PT Plant 5-Dec-10 Not yet sumbitted.

    0 Piping Layout for DM Plant 5-Dec-10 Not yet sumbitted.

    1 5-Dec-10 Not yet sumbitted.

    2 Equipment GA of MCF - RO First Pass 5-Dec-10 Not yet sumbitted.

    3 Equipment GA of MCF - CIP 5-Dec-10 Not yet sumbitted.

    4 5-Dec-10 Not yet sumbitted.

    C Engineering (Electrical & Instrumentation)

    1 5-Nov-10

    2 8-Nov-10 Not yet sumbitted.

    3 10-Nov-10

    4 10-Nov-10

    5 10-Nov-10 Not yet sumbitted.

    6 - Not yet sumbitted.

    D Procurement Activities - Floating enquiries and order placement

    1 PT Plant - Clarifier 11-Oct-10 29-Oct-10

    2 PT Plant - Thickener 20-Oct-10 9-Nov-10

    3 PT Plant - Clarifier-ETP Plant 20-Oct-10 9-Nov-10

    4 PT Plant - Dosing Tanks 1-Nov-10 12-Nov-10

    5 PT Plant - Dosing Pumps 1-Nov-10 19-Nov-10

    6 PT Plant - Centrifuge 15-Nov-10 10-Dec-10

    7 PT Plant - Motors 15-Nov-10 10-Dec-10

    Revised GA of filter tank cumpumphouse

    Pending with TCE

    Rev-01 dated20/11/2010 TL No. 64

    Design Basis Report For ChlorinationSystemLayout Diagram for ChlorinationSystem

    Skid drawing for RO First Pass &Second Pass

    Equipment GA of MCF - RO SecondPass

    oc no. . - - - ,Incomer sizing calculations ,Submission date 5-11-10

    omp ance y25/11/2010 (TL-68dated 25 11 2010

    oc no. . - - - ,Sizing Calculations , Submission date8-11-10oc no. . - - - ,Lighting calculations , Submissiondate 10-11-10

    omp ance y30/11/2010 (TL-70dated 29 11 2010

    Doc no. TCE.5773A-612-EL-0141,

    Data Sheet & GA Drawing for LocalPush Button Stations , Submissiondate 10-11-10

    Compliance by

    25/11/2010 (TL-68dated 25/11/2010

    Doc no.TCE.5773A-612-IC-0120,GADrawing for Junction Box , Submissiondate 10-11-10

    oc no. . - - - ,Instrument Data Sheet , Submissiondate 15-01-10

    Status on the same to

    be update by M/sTriveni - OrderPlacementexpected by Dec 10

  • 8/8/2019 Agenda for Monthly Review Meeting WTP - Triveni - 17-12-10

    3/3

    Agenda for Package Review Meeting

    Water treatment Plant - M/s Triveni

    Agenda points Status as on date ResolutionStart Date

    ate of Meeting : 17-12-10me : 2.30 pm Onwards

    articipants :lace : GMR Energy, Site office, Warora

    Slo

    Planned Date / IssueDate

    Resolution on19.11.10Completion

    Date

    E MANUFACTURING, INSPECTION & DESPATCH

    1 2-Nov-10 11-Feb-10 Not Yet started

    2 11-Nov-10 23-Feb-11 Not Yet started

    3 11-Nov-10 23-Feb-11 Not Yet started

    4 16-Nov-10 7-Feb-11 Not Yet started

    F Construction ( As per L2 Schedule Activities Major Milestone - upto Jan 2011)

    1 Mobilization and site enabling facility

    2 20-Sep-10

    3 20-Sep-10

    4 Start of Civil Work for PT clarifier tank 20-Sep-10

    5 20-Sep-10

    6 15-Dec-10

    7

    8 Look ahead schedule till Jan 2011

    9 Catchup plan for major milestones

    G C&C

    H Other

    1 Monthly Progress Report Submitted

    2 updated L2 Schedule

    Participants

    M/S GMR M/S Triveni

    Clarifier - PT Plant - Materialprocurement and manufacturing

    Thickener - PT Plant - Materialprocurement and manufacturing

    Clarifier - ETP Plant - Materialprocurement and manufacturing

    Dosing Tank - Material procurementand manufacturing

    Excavation forClarifier tank Started ,Recovery Plan notsubmitted

    Start o Civi Wor or Casca eaeratorStart of Civil Work for Stillingchamber, parshall flume &distribution channel

    Start of Civil work for RCC Channelbetween calrifier & RGF inlet chambe

    Start of Civil work for Rapid GravitySand filterVendor Approval for ClarifierConstruction

    submitted the MPR ,however it needs to besubmitted within 4th ofeverry month.

    Submitted in pdfformat, requested forSoft copy in MicrosoftProject format