Connectathon Eric Poiseau, INRIA IHE Europe Technical Manager.
Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore...
-
Upload
priscilla-fowler -
Category
Documents
-
view
213 -
download
1
Transcript of Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore...
![Page 1: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/1.jpg)
AfdasfdasfdAdfasdfasfdasd
Connectathon Timeline
Connectathon Manager TrainingSteve Moore
Mallinckrodt Institute of Radiology
![Page 2: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/2.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
The Aztec Calendar was based on a Mesoamerican that counted both a 260 day religious calendar and a 365 day solar calendar. Researcher Garulich found, by studying how far behind the Aztec calendar was from the seasons, since they don't take leap years into account, that the calendar began in 682 A.D.
![Page 3: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/3.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
Participants and You
• Have a lot of work to do• Need an organized schedule to get through
the entire cycle
![Page 4: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/4.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
Letter Designations
• T: Start of the Connectathon• R: Opening of registration
![Page 5: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/5.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 9 months: Document Support Plan• Before you apply to IHE to hold a
Connectathon:– Which domains to test– Which tools you will need– How you will support the testing– How you will support the tools you select
![Page 6: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/6.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 9 months: Petition T/T, Board• This is a sponsor responsibility, but you will
help– List of domains and profiles– Plan for recruitment– Plan for staffing
![Page 7: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/7.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 6 months:Call for Participation• This is a sponsor responsibility, but you will
help– List of domains and profiles– Plan for recruitment– Plan for staffing
![Page 8: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/8.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
Profile Data Entry, Tool Development• If you are a Technical Project Manager• You should be entering data in Gazelle to
identify your new profiles, actors, transactions, options
• Developing new test tools
![Page 9: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/9.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
R – 2 weeks: Reg System Ready• All domains, profiles for testing entered in
Gazelle or in manual tool• Participants able to generate a contract• All logistics for submitting contract published• Rules/regulations/guidelines published
![Page 10: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/10.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
Registration Opens
• Provide registration support– How do I do this in the system?– I think I want to participate. I have an electronic
shovel. What profile can I test?
![Page 11: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/11.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T-12 Weeks: Registration Closes• IHE policy is that registration needs to close 3
months in advance of the Connectathon
![Page 12: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/12.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
R + 1 Week: Registration Closes• Review profile subscription– Drop profiles with low subscription– Warn participants about marginal subscription
• Enable pre-Connectathon tests
![Page 13: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/13.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 12 weeks
• Recruit monitors– Experience in industry– Non-partisan (no vendors!!)
• Schedule any specialty monitors– Mammography– NMI
• Logistics: Should be sponsor responsibility – Lodging, travel, expenses
![Page 14: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/14.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 12 weeks: Digital Certificates• ATNA tests require digital certificates• Participants will want to have these in
advance for Internet testing
![Page 15: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/15.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 12 weeks: OIDS and Codes • Some actors require OIDS to function– XDS.b Document Source
• Many profiles need coded values– You will publish all coded values either by
referencing an existing publication or by stipulating them
– Feel free to reuse ours; don’t be afraid to invent– Do not leave it up to the participants
![Page 16: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/16.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 10 weeks: Publish Network Design• Private addresses, public addresses• Connections to the evil Internet• Fixed IP addresses for test systems• DHCP if you want for laptops, etc• Default gateway• Netmask• DNS
![Page 17: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/17.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 8 weeks: Understand all Tests• By this time, you need to understand all
Connectathon tests and implications for support (people, tools)– You can delegate profiles to partners (but not
committee members or vendors)– You will need to assign monitors (slide coming
up)
![Page 18: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/18.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 8 weeks: Assemble Data Sets • Some tests use pre-defined data sets• Some tests use data sets from previous
Connectathons– Because it is difficult to get the creators to attend
each event
![Page 19: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/19.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 8 weeks: Assign Monitors to Profiles• They need time to read the profiles and test
cases• You need to make sure you have covered the
profiles and have time to recover
![Page 20: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/20.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 8 weeks: IP Addresses
• Assign and publish fixed IP addresses• Know that you will have participants asking
at the event:– What is my IP address?– What is Ralph’s IP address?– Can I have one more IP address?– Can I have 10 IP addresses for my VM?
![Page 21: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/21.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 6 weeks: Monitor Training• Webex/phone call to discuss process, tooling– All monitors
• Separate webexes to cover specific domains– You might have 3 monitors who only do ITI while
2 different monitors cover Radiology– We are building a library of training material
![Page 22: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/22.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 6 weeks: Table Assignments
• Important for large Connectathons• Participant equipment might need a table
number to facilitate delivery• Curb the desire to annex space from others• Assign seats based on functions– Make it easy to find important actors of like
capabilities– Put the Radiology Order Fillers together
![Page 23: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/23.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 6 weeks: Adjust Test Requirements• Examine the 3 peer rule in the context of
your registration
![Page 24: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/24.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 6 weeks: Accept Participants• Participants have pre-Connectathon
requirements• You need to assess their compliance– Pre-Connectathon tests– Configuration data entry
![Page 25: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/25.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 6 weeks: Staff Registration
• If you are using Gazelle– Extract staff registration– Provide guidance on per day charges– Forward to sponsors for catering
• If not Gazelle– My advice is to make this a sponsor item
![Page 26: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/26.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 4 weeks: Stable Connectathon Tests • All Connectathon tests should be published
and stable• Participants need a chance to review in
advance– No surprises
![Page 27: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/27.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 4 weeks: Publish Test data• Some tests require a fixed set of
demographics for simplification• Some tests require test files / objects• Publish in advance to enable setup
![Page 28: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/28.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 4 weeks: Participant Training• Webex, Live Training– Review the Connectathon process– How to use the tools for the event
• We are building a library of recorded sessions• You do want a live session to assist your
participants– They will have questions
![Page 29: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/29.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 3 weeks: Hardware / Tools• Your onsite hardware– Anything needed for tooling– Configured, ready for shipping
• Some tools depends on profiles tested, others are of general use– Gazelle– DNS Server– Audit Record Repository– …..
![Page 30: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/30.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
T – 2 weeks
• Workflow test assignments– Some tests are run in large groups to test a full
profile or several profiles (XDS.b, ATNA, PIX)– These are best published in advance
• Mon/Tue/Wed partner assignments– Minimize context switching– In the US• XDS.b: Doc Repository, Doc Registry• SWF: Order Filler, Modality
![Page 31: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/31.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
Continuous
• Drops– Accept, you cannot force someone to test
something they cannot implement• Requests for adds– In the US, these are denied– They lead to bad behavior– I recommend you deny them, but this is a
regional decision
![Page 32: Afdasfdasfd Adfasdfasfd asd Connectathon Timeline Connectathon Manager Training Steve Moore Mallinckrodt Institute of Radiology.](https://reader038.fdocuments.in/reader038/viewer/2022110404/56649e8a5503460f94b90244/html5/thumbnails/32.jpg)
AfdasfdasfdAdfasdfasfdasd
AfdasfdasfdAdfasdfasfdasd
Post Connectathon (30 days)
• Finish grading– Announce preliminary results
• One week challenge period– Process requests
• Work with sponsors, T/T to publish results• Collect suggestions for improvement• Update Connectathon tests• Thank you’s to participants and monitors