Adopting COBIT 5 in a Government Entity

download Adopting COBIT 5 in a Government Entity

of 7

Transcript of Adopting COBIT 5 in a Government Entity

  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    1/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 1/7

    Spanish

    Adopting COBIT 5 in a Government Entity

    By Sean Atkinson, CISA, CISM, CGEIT, CRISC, COBIT 5Foundation, CCSA, CEH, CFE, CISSP, CRMA, CSM, GCIH, N+,PMP, SCTS, Sec+, and Roger F. Aucoin, COBIT 5 Foundation,PMP

    COBIT Focus | 19 January 2015

    Imagine being on the ground floor of a

    new government agency in the United

    States, first conceived in 1994 and

    implemented in 2012, with the initial

    responsibility of developing an

    information system that would

    eventually process well over US $1 billion in payments monthly,

    produce enterprisewide reporting, be implemented as Software as a

    Service (SaaS) to more than 85,000 users in 72 external agencies and

    by more than 100,000 vendors. Further, imagine that your responsibility

    included ensuring that the fledgling enterprise accomplished this mission

    while following its documented processes and procedures.

    Where to begin? How would one know whether existing processes were

    sufficient?

    In the original request for proposal (RFP) for the software (2008), COBIT

    was selected to be implemented as a holistic framework to manage and

    govern the software. Until 2012, the enterprise used COBIT 4.1 on alimited basis only due to the lack of development and maturity in the

    enterprises overall processes.

    In September 2012, the decision was made by executive management

    to expand the application of COBIT in a more holistic manner and to

    adopt COBIT 5 and all 37 processes (which have come to be known

    internally as enterprise processes) across the enterprise (which does

    not include the vendors or external agencies noted previously). The

    focus of COBIT would now be utilized as the governance and

    management framework that provides an integrated process in which toreview, manage and control the enterprise.

    The planning process, Phase 1, began with the use of COBIT 5

    Implementationand COBIT 5: Enabling Processesfor direction on how to

    proceed. After digesting the contents of these 2 documents, a business

    case was drafted using the 7-phase approach recommended in the

    COBIT 5 Implementation, and submitted to the executive sponsor for

    approval. Adopting a holistic framework for any entity is a daunting task,

    as is the decision leading up to the commitment of the necessary

    resources. Upon approval of the business case, the original

    implementation team moved forward with the adoption of COBIT 5. The

    COBIT 5 implementation team was formed with staff from 2 separate

    areas of the enterprise: 2 staff members from security operations (1

    certified COBIT Foundation trainer) and 3 staff members from the

    Subscribe toNewsletter

    View Archives

    Submit an Article

    Read More CaseStudies

    Join theConversation

    More About COBIT 5

    Back to Focus Home

    http://www.isaca.org/COBIT/Pages/COBIT-5-Implementation-product-page.aspxhttp://www.isaca.org/cobit/pages/default.aspxhttp://www.isaca.org/cobit/pages/default.aspxhttp://www.isaca.org/restricted/Pages/Conversation.aspxhttp://www.isaca.org/restricted/Pages/Conversation.aspxhttp://www.isaca.org/Knowledge-Center/cobit/Pages/COBIT-Case-Studies.aspxhttp://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity-Spanish.aspxhttp://www.isaca.org/Knowledge-Center/cobit/cobit-focus/Pages/COBIT-Case-Studies-Submission-Guidelines.aspxhttp://isaca.informz.net/isaca/profile.asp?fid=1002http://www.isaca.org/restricted/Pages/Conversation.aspxhttp://www.isaca.org/Knowledge-Center/cobit/cobit-focus/Pages/COBIT-Case-Studies-Submission-Guidelines.aspxhttp://www.isaca.org/COBIT/Pages/COBIT-5-Enabling-Processes-product-page.aspxhttp://www.isaca.org/COBIT/focus/Pages/archive.aspxhttp://www.isaca.org/COBIT/Focushttp://www.isaca.org/cobit/pages/default.aspxhttp://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity-Spanish.aspxhttp://www.isaca.org/Knowledge-Center/cobit/Pages/COBIT-Case-Studies.aspxhttp://isaca.informz.net/isaca/profile.asp?fid=1002http://www.isaca.org/COBIT/Pages/COBIT-5-Implementation-product-page.aspx
  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    2/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 2/7

    process quality/compliance team. Bringing together staff from the 2

    different areas of the organization provided 2 different perspectives that

    fostered a deeper understanding of the value and challenge of the full

    adoption.

    Phase 2, the Where are we now? step, entailed staff identifying all

    existing processes and procedures as well as any that were needed that

    did not yet exist. These processes were mapped to the 210 COBIT 5

    practices. This gap analysis indicated that the enterprise had nodocumented processes that could be related to 11 of the COBIT

    processes and incomplete processes that could be related to the

    remaining 26 COBIT processes. This discovery prompted the team to

    revise the original business case to include the recommendation to

    management that the organization needed to examine the regulatory and

    process requirements for all 37 COBIT processes on a detailed level

    and decide which were indeed needed for this specific business. This

    moved the project into phase 3 from COBIT 5 Implementation, the

    Where do we want to be? phase.

    The executive sponsor was not surprised by this development due to

    the evolution of the enterprise, its overall structure and the enterprises

    fast-paced progression, the latter of which had not allowed for a

    comprehensive review and understanding of the governance and

    regulatory processes needed for the business.

    In phase 3, the team needed the assistance of subject matter experts

    (SMEs) to get a better picture of the situation along with their support to

    close the gaps. To begin, the team members and executive sponsor

    earned their COBIT 5 Foundation certificates. Executive management

    was engaged through a modified training session in COBIT 5

    Foundation, which included discussion of the results of the initial gap

    analysis, a live demonstration of the process the COBIT 5 team

    performed to identify the gaps (called the Process Author Approach),

    and the proposed plan for moving forward (figure 1). This generated the

    needed buy-in for the next stages of the plan, which included presenting

    the 2-hour executive management training session to the direct reports

    of the executive managers (team leads), along with a half-hour overview

    session for all staff members (All Staff meeting in figure 1).

    Figure 1Overall Approach to COBIT 5 Implementation

    View Large Graphic

    Source: Atkinson and Aucoin reprinted with permission.

    http://www.isaca.org/COBIT/focus/PublishingImages/CF-19-January-2015-1-lg.jpghttp://www.isaca.org/COBIT/focus/PublishingImages/CF-19-January-2015-1-lg.jpg
  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    3/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 3/7

    Because the enterprise set out to formally align itself with the 37 COBIT

    5 processes, 37 organizational documents were created and referred to

    as enterprise process documents. Each document contains the original

    COBIT 5 process overview and description the practices and the

    activities Responsible, Accountable, Consulted and Informed (RACI)

    matrices, modified to fit the organizations management structure and

    the inputs, outputs and related guidance tables.1

    Figure 1displays a graphical representation of the implementation up to

    the point where all the enterprise process documents are created and

    the gaps are identified. The starting point to this stage of engagement

    was the Process Author Approach. This approach involved identifying

    which team lead owned each enterprise process. After this was

    determined, the lead staff person became the process author for that

    enterprise process document. For example, APO07 Manage human

    resourceswas clearly in the domain of the human resources (HR) unit

    of the enterprise, so the organizations HR lead became the process

    author. However, in the case of BAI06 Manage changes, which crosseda series of domains within the organization, multiple team leads became

    process authors, each responsible for their individual part of the

    process. The process authors then identified the SMEs to be involved

    and the development discussions began.

    To facilitate the multiple owners of a process, the implementation team

    served as the intermediary to coordinate the overall goal and successful

    completion of items within the process.

    This then led to the heart of the approach: the enterprise-process-facilitated sessions. At these meetings, the COBIT 5 team engaged the

    process author and received input from SMEs. This approach provided

    several benefits: Initially, it set the stage for teams to get to know their

    processes and develop a sense of ownership of them. It also allowed for

    input from the implementation team who provided relevant materials,

    direction on compliance and best practice recommendations.

    Within the overall update process (figure 2), the process authors were

    sent the enterprise process document they were responsible to develop

    to determine the need for assistance. The implementation team then

    met with each process author separately (along with any support SMEs

    identified by the process author) to develop the enterprise process

    document by determining the following:

    Is the enterprise process one the organization needs?Is the COBIT 5 definition of the process accurate for the enterprise? Ifnot, it was modified.Is the COBIT 5 definition of each practice accurate? If not, it wasmodified.

    Figure 2Enterprise Process DevelopmentActivity Flow

  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    4/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 4/7

    View Large Graphic

    The implementation team encouraged process authors to make

    modifications to the COBIT wording to better represent how the process

    related to the organization, but without changing the original intent. As

    an overall implementation step, the original versions of the processes,

    practices and activities were preserved for ease of future reference,

    should any question arise. The enterprise processes were notated where

    any wording was modified.

    The next step was a review of the COBIT 5 activitiesall 1,112

    activities. The reviews were complicated by the fact that the IT

    infrastructure of this enterprise has functions that are performed by

    service providers therefore, not all activities were seen as necessary

    for the enterprise. Each activity was examined using the same approach(process authors and SMEs) to augment the delivered COBIT 5

    literature regarding each activity: Wording was modified as necessary to

    make the process document relevant to the enterprise, and each activity

    was categorized to simplify and sort the answers:

    Is the activity done, but not documented?Is the activity done, but documentation needs to be updated?Is the activity done, documented and not in need of updating?Is the activity not done, but needed?Is the activity not done and not needed at this time?Is the activity done by 1 or more of the enterprises service providers?

    Finally, the RACI matrix was examined for any needed changes to

    reflect titles and responsibilities specific to the enterprise.

    Enterprise process documents were then sent to the full team, which

    http://www.isaca.org/COBIT/focus/PublishingImages/CF-19-January-2015-2-lg.jpghttp://www.isaca.org/COBIT/focus/PublishingImages/CF-19-January-2015-2-lg.jpg
  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    5/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 5/7

    included executive management and all of the process authors/team

    leads, for final review to determine if any further changes were needed

    before releasing the documents for further development. Given that each

    document averaged 10 to 12 pages and the reviews were spread over 6

    review meetings, the task was manageable. Approvals to move the

    document forward were formed though a consensus of executive

    management, the members of which based their decision on

    achievability and sustainability through the review and subsequent

    improvement processes. The organization defines approval to meansimply that the larger team agreed with the gap analysis and any

    updates made during the review meetings, and that executive

    management authorized the work that is needed to close the gaps in

    order to begin. It was gratifying to note that these review and approval

    meetings were lively at times and not simply rubber-stamping approvals

    of the documents. This speaks to the value seen by the participants in

    the overall process.

    After they were approved for further development, the documents were

    stored in the organizations central document repository. The activitiesrequiring modifications were prioritized by the process authors with input

    from management, and the work was scheduled to be done. Each

    enterprise process schedule was determined by the process author(s)

    and was managed though the central repository.

    All of this activity provided the scope of work for phase 4, What needs

    to be done? For perspective, the initial results included that:

    9 enterprise processes were identified as complete (not in need of anyfurther modification)

    28 enterprise processes had gaps (at least 1 activity needed furtherdevelopment)At the activity level:

    139 activities were done, but not documented208 activities were done, but documentation needs to beupdated476 activities were done, documented and not in need ofupdating189 activities were not done, but were needed47 activities were not done and were not needed at this time53 activities were done by 1 or more of the enterprises serviceproviders

    The enterprise then moved into the 5th

    , or How do we get there?,phase. This is where team members are currently engaged and this

    phase is expected to last 18 months. The activities belonging to 1 or

    more service provider will be reviewed with the service provider and

    included in the service level agreement (SLA), as appropriate, and

    metrics will be used to enable the tracking of progress and celebrate

    success as it occurs.

    After a document is deemed complete and all needed processes and

    procedures are in place and working, the process improvement cycle for

    each enterprise process document begins and is set at 1 year. This

    moves the organization into phase 6 (Did we get there?) in a piecemeal

    fashion until all 37 documents are complete. Completion is planned for

    the end of 2015.

  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    6/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 6/7

    Process assessments and audits will then enable phase 7, the How do

    we keep the momentum going? phase, to engage the enterprise in

    continuous improvement. The new EDMO1 Ensure Governance

    Framework Setting and Maintenance Audit/Assurance Program document

    (which includes a focus on the assessment of the process enabler)

    and/or the COBIT Assessment Programme (COBIT Assessor Guide: Using

    COBIT 5 and COBIT Process Assessment Model (PAM)): Using COBIT 5,

    which focuses on COBIT 5 process capability), can be used to

    effectively assess the enterprise processes and the organizational GEITarrangements as a whole. These will assist in identifying processes and

    procedures (practices and activities) or other aspects of GEIT that need

    attention to enhance their performance.

    Get Started With COBIT 5

    At this point, one might be asking, What is in it for my organization? or

    Where do I begin? Any organization can begin as this one did by

    following the same steps:

    1. Do not be overwhelmed by the wealth of knowledge encapsulated inCOBIT 5 and its scope, as it can seem daunting.

    2. Begin with COBIT 5 Implementation. Use this to understand theimplementation process that underpins COBIT 5 and recognize that itwill take time to fully adopt. Seek to break up the work into bite-sizedpieces so that your organization is not overwhelmed with the work.

    3. Then engage with COBIT 5: Enabling Processes. Consciouslyexamine all the processes, practices and activities to answer the samequestions asked here and put a plan in place to resolve any identifiedgaps.

    Or one might be tempted to say, We have everything we need already.

    If that is the case, COBIT 5 provides the opportunity to self-assess

    where the organization is and potentially illuminate areas that might

    need some work to ensure the organization can reasonably accomplish

    its mission.

    Evolving With COBIT 5

    Understanding COBIT 5 and its implementation life cycle is well

    underway for the enterprise in this case example. As it moves forward,

    collaboration between units and process owners will be required as the

    defined processes will cross organizational lines and bridge the gaps

    between service support, operational management and overallgovernance of the organization. These intended consequences of an

    integrated, operational environment will allow the enterprise to measure

    the return on investment (ROI) and evaluate the contribution of COBIT 5

    toward the overall goal of a holistic and managed enterprise, encourage

    collaboration, and create a systematic process of excellence among all

    teams. Progression through the implementation life cycle to a point of

    measuring capability is the next step in the evolution as an

    implementation team.

    Sean Atkinson, CISA, CISM, CGEIT, CRISC, COBIT 5Foundation, CCSA, CEH, CFE, CISSP, CRMA, CSM, GCIH, N+,PMP, SCTS, Sec+

    Is an internal control officer, risk manager and information security

    officer with more than 10 years of experience working in both security

    http://www.isaca.org/COBIT/Pages/Assessor-Guide.aspxhttp://www.isaca.org/Knowledge-Center/cobit/Pages/COBIT-Assessment-Programme.aspxhttp://www.isaca.org/Knowledge-Center/Research/Documents/Audit-Programs/EDM01-Ensure-Governance-Framework-Setting-and-Maintenance-Audit-Assurance-Program_icq_Eng_0214.dochttp://www.isaca.org/COBIT/Pages/COBIT-5-PAM.aspx
  • 7/23/2019 Adopting COBIT 5 in a Government Entity

    7/7

    23/1/2015 Adopting COBIT 5 in a Government Entity

    http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?cid=edmi_1105872&PF=1 7/7

    > DISCUSS Share:

    and auditing roles. He also teaches an introduction to computer science

    course for a local college.

    Roger F. Aucoin, COBIT 5 Foundation, PMP

    Has more than 34 years of experience in information technology, 16 of

    those years as a project manager and most recently managing the

    adoption of COBIT 5. He also teaches an online project management

    course for a local college.

    Endnotes

    1The titles for these sections came from the 10 COBIT 5 Governance

    and Management Practices Activities Microsoft Excel document available

    in the COBIT 5 Tool Kit and COBIT 5: Enabling Processes.

    http://twitter.com/home?status=Currently%20readinghttp://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?&title=https://plusone.google.com/_/+1/confirm?hl=en&url=http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?http://www.facebook.com/share.php?u=http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?http://www.linkedin.com/shareArticle?mini=true&url=http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?&title=http://www.isaca.org/Groups/Professional-English/cobit-5-use-it-effectively/Pages/ViewDiscussion.aspx?PostID=355mailto:?subject=%20&body=http://www.isaca.org/COBIT/focus/Pages/Adopting-COBIT-5-in-a-Government-Entity.aspx?http://www.isaca.org/COBIT/Pages/COBIT-5-Implementation-product-page.aspxhttp://www.isaca.org/COBIT/Pages/COBIT-5-Enabling-Processes-product-page.aspx