ADA Transition Plan Presentation-FINAL

19
ADA Transition Project 2016

Transcript of ADA Transition Plan Presentation-FINAL

Page 1: ADA Transition Plan Presentation-FINAL

ADA Transition Project2016

Page 2: ADA Transition Plan Presentation-FINAL

Purpose• Collect inventory of non-compliant ADA ramps and sidewalks• Bring non-compliant ramps to be compliant ADA ramps• Conduct ADA Transition Plan

Page 3: ADA Transition Plan Presentation-FINAL

Materials

• Smart Tool• Measuring Tape• iPad

Page 4: ADA Transition Plan Presentation-FINAL

Materials: Smart Tool

• Slope in Percentage %• Calibrating

– Instructions: • SmartTool Calibration• Video: Calibration Demo

Page 5: ADA Transition Plan Presentation-FINAL

Process

• ODOT Form– Extra information we do

not need– Only use a few standards

ODOT ADA InspectionForm

Page 6: ADA Transition Plan Presentation-FINAL

Process (Continue)What component of the ramp was measured

• Running Slope (1,2,3)• Cross Slope (1,2,3)• Landing Width (X,Y)• Clear Width• Counter Slope• Differential Slope • Wing (Left, Right)

Page 7: ADA Transition Plan Presentation-FINAL

Process (Continue)

• iPad– Modified ODOT form– GIS location tracking

Page 8: ADA Transition Plan Presentation-FINAL

Process (Continue)

• Google Maps– To locate and verify

ramps before making trip

– Street view– Aerial view

Page 9: ADA Transition Plan Presentation-FINAL

Process (Continue)• GIS Field Data Map

– Blue icon= Ramps not completed

– Red icon= Ramps completed

– Blue circle icon =Comment

Page 10: ADA Transition Plan Presentation-FINAL

Process (Continue)

• GIS Field Data Map– Plot existing ramps– Simplify trips– Inventory of all the

ramps in the county– Know how many ramps

are completed

Page 11: ADA Transition Plan Presentation-FINAL

Process (Continue)

Page 12: ADA Transition Plan Presentation-FINAL

iPad Demonstration

Page 13: ADA Transition Plan Presentation-FINAL

GIS Maps

Page 14: ADA Transition Plan Presentation-FINAL

GIS Maps (Continue)

Page 15: ADA Transition Plan Presentation-FINAL

Development Plan

• Requirements for Plan1. List of barriers (GIS Map)2. Outline of methods to remove barriers3. Schedule for removal4. Name of official responsible for plan

Page 16: ADA Transition Plan Presentation-FINAL

Development Plan

• Comparing cities plan– City of Portland– City of Eugene (Best)

• Time line• Complete new GIS map (End of August)• Complete written Transition Plan (October 31, 2016)

Page 17: ADA Transition Plan Presentation-FINAL

Benefits

• Obtain the county’s ramp inventory• Develop ADA Transition Plan• Begin constructing new ramps

Page 18: ADA Transition Plan Presentation-FINAL

How to improve

• Google and GIS Field Data Map- sync

• Prevent Application Crash

• 2 workers

Page 19: ADA Transition Plan Presentation-FINAL