Activity for Improving Port Management & Operation of ...
Transcript of Activity for Improving Port Management & Operation of ...
CONTENTS
I. Introduction
II. Current Situation of Sihanoukville Autonomous Port
III. Future Development Plan of Sihanoukville Autonomous Port
Sihanoukville Port New Container Terminal Development Project, JICA
Loan No. CP-P21 (2020-2024)
Sihanoukville Port Cruise Terminal Improvement Project, ADB Loan
(2020-2021)
IV. Vessel Operation
V. Cargo Offloading - Loading Operation
VI. Activities for Improvement
VII. Concept Plan for Sihanoukville Port Development
VIII. Conclusion
2
I. Introduction
• The challenges facing shipping and world class ports today are not
only the rapid increase of quantity but also the quality of ports’ related
services. The continuous progress of globalization of shipping and
trade business is resulting in the increasing pressures on ports cost
and improved operational efficiency.
• PAS is committed to providing its customers and port users with effective
and efficient, safe, secured and affordable port services.
• By land, PAS is connected to Phnom Penh by National Road
No. 4 (230Km) and NR No. 3 (244Km).
• By rail, PAS is connected to Phnom Penh by the southern line
(264Km) along National Road No. 3.
• By air, PAS is connected by Sihanoukville International
Airport (17km).
Local Transport Connectivity
3
• PAS has direct access to the major ports in the ASEAN
and Asia Pacific, while connecting to the EU and the US
via ports in Hong Kong and Singapore.
Geographical Location and Networks
Background of Sihanoukville Port Development Projects
Phase I
290m Old Jetty
1956-1960
Phase II
350m New Quay Berth
1967-1970
Phase III & IV
400m Container
Terminal-2002-2007
Phase V
Sihanoukville Port SEZ
2009-2012
Phase VI
330m Multi-Purpose Terminal
2015-2018
Sihanoukville
Port SEZ
5
Present Infrastructures and Facilities of PAS
Breakwater
Sihanoukville Port
SEZ
Railway Container Yard: 07 ha
PAS Admin-Building
Yard C: 9.2ha
Yard B: 2.3ha
Yard A: 1.7ha
Navigational Service:
PAS provides navigational services for all vessels call in-out of the port.
This service may also be provided to vessels for private ports.
Cargo Handling Service: PAS provides services such as stevedoring, lift-on lift-off and transportation
for container and general cargo operations and International Passenger
Services 24 hours per day and 7 days per week. Storage and Warehouse Services
Special Economic Zone Services
Logistic Base for Oil Exploration Services
PAS’s Main Services
8
Shipping Lines Regular Schedules (Container Ships)
There are 10 Shipping Lines Entered Into Contract with PAS with 15 Calls/Week
Shipping Line Regular Schedules and Calling Port Rotations
Shipping Lines Calling Schedules Frequency Calling Port Rotations
MAERSK/MCC
1.Wed 06:00 -Wed 20:00
2.Fri 22:00 - Sun 08:00
1 call/week
1 call/week
1.TPP-SHV-LZP-DAN-QNN-CGP-TPP-SIN-QIN-HPH-HCM- SIN- TPP-SIN-
QIN-HPH-HCM-SIN-TPP
2. HCM-SHV-TPP-SIN-QNN-DAN-HKG-KAO-TAI-YAT-HKG-HCM
RCL
1.Thu 15:00 - Fri 02-00
2. Sat 00:01- Sun 00:00
1 call/week
1 call/week
1. HKG-SHV-SGZ-HKG-HPH-HKG-KEL-TAI-HKG
2. SIN -SHV-SGZ-SIN
RCL/COSCO Fri 00:00 - Fri 10:00 1 call/week SHK-SHV-BKK-LZP-NBO-SGH-SHK
SITC
1.Sun 08:00 – Sun 00:00
2.Mon 14:00 - Tue 02:00
1 call/week
1 call/week
1. HCM-SHV-BKK-LZP-HCM-NSA-SGH-OSA-KOB-BUS-SGH-HKG-HCM
2. HCM-SHV-BKK-LZP-HPH-FCH-SHK-XMN-INC-TAO-SGH-NGO-YOK- HKG-HCM
SSL/EML Fri 00:01 - Sun 19:00 1 call/week SIN - SHV-SIN
NAMYUEN YONG Mon 08:00 - Mon13:00 ~3 call/month BKK -SHV-BKK
WANHAI Sun 01:00 - Mon 14:00
Tue 14:00 – Tue 24:00
1 call/week
1 call/week
HKG - SHV – BKK – LZP-SHK-HKG
BKK- SHV – SHK – HKG-LZP- BKK
EVERGREEN Mon 20:00 - Tue 08:00 1 call/week HCM -SHV – SHK - HKG – HCM
QAS Wed 16:00 – Wed 24:00 1call/week Dongguan-SHV-HCM-QIN-Yangpu-NSA-Dongguan
Total ~ 15 calls/week
Remarks
BKK Bangkok, Thailand HKG Hong Kong MTT Than Hlyin, Myanma SIN Singapore
BUS Bussan, South Korea HPH Hai Phong, Vietnam NGO Nagoya, Japan SGZ Songkhla, Thailand
BTG Batangas, Philippines HSK Xingang, China NSA Nansha, China SHK Shekou, China
CGP Chittagong, Bangladesh HCM Ho Chi Minh, VN NBO Ningbo, China SWA Shantou, China
CGY Cagayan De Oro, PH HAK Haikou, China OSA Osaka, Japan TPP Tanjung Pelepas, Malaysia
DAN Danang, VN INC Incheon, South. KR PEN Penang, Malaysia TAI Taichung, Taiwan
DZV Dalzavod, Russia KOB Kobe, Japan PKG Port Klang, Malaysia TAO Quingdao, China
DGH Donghae, South.KR KAN Gwangyuang, S. KR PLM Palemban, Idonesia TJN Jianjing, China
FIP Fish Port, Russia KAO Kaohsiung, Taiwan QIN Qinzhou, China XMN Xiamen, China
FCH Fangcheng, China KEL Keelung, Taiwan QNN Quin Nhon, Vietnam YAT Yantian, China
GSC General Santos City, PH LZP Laem Chabang, Thai SHV Sihanoukville Port, Cambodia YGN Yangon, Myanma
HKT Hakata, Japan MNL Manila, Philippine SGH Shanghai, China YOK Yokohama, Japan
- Vessel Traffic Management System (VTMS) 1 set
- X-Ray Scanner 1 set
- Radiation Detective Scanner 1 Set
- Patrol Boat 100HP 1 Unit
- Oil Fence with 440 m long 1 set
- Oil Skimmer 1 Unit
- Oil Barge 100m³ 1 Unit
- CCTV Cameras to be equipped with Alarms 25 Sets
- ID Pass’s Card Entering System 5 Sets
- Security Station 2 Places
Radiation Detective Scanner 10
Port Security & Safety Facilities
Gamma-ray Scanner
Mobile Scanner
X-ray Scanner
12
Statistics of Cargo Throughput-Tons (2014-6M/2019)
8.11%7.4%
10%
14%
22.08%
2013 2014 2015 2016 2017 2018 2019-6M
Throughput 3 012 218 3 423 919 3 760 297 4 040 155 4 364 638 5 328 348 3 191 593
Import 2 213 112 2 508 807 2 744 920 2 981 860 3 186 892 3 916 958 2 563 724
Exported 799106 915 112 1 015 377 1 058 295 1 177 746 1 411 390 627 869
3 012 218
3 423 919
3 760 297
4 040 155
4 364 638
5 328 348
3 191 593
-
1 000 000
2 000 000
3 000 000
4 000 000
5 000 000
6 000 000
Ton
s
21.7%
Statistics of Container Throughput-TEUs (2014-6M/2019)
2.14%17.34%
16.57%
15%17.70%
2013 2014 2015 2016 2017 2018 2019-6M
Throughput 286 450 333 904 391 819 400 187 459 839 541 228 291 572
Import 148 076 173 039 195 854 198 509 233 623 276 753 155 185
Export 138 374 160 865 195 965 201 678 226 216 264 475 136 387
286 450
333 904
391 819 400 187
459 839
541 228
291 572
-
100 000
200 000
300 000
400 000
500 000
600 000
TEUs
12.50%
During the last five years (2014-2018), the volume of container throughput at PAS had drastically
increased with the average of 13.57%. Whereas, the total volume of container throughput in 6 Months
2019 is 291,572 TEUs increased 12.50% comparing with the same period of 2018..
14
Vessel Calling at PAS-Units (2014-6M/2019)
2013 2014 2015 2016 2017 2018 6M-2019
Calling Vessels 988 1103 1292 1322 1305 1451 840
-Container 506 504 650 667 531 581 307
-Tanker 283 292 329 337 461 582 350
-General 178 282 277 283 283 251 151
-Passenger 21 25 36 35 30 37 32
988
1103
12921322 1305
1451
840
0
200
400
600
800
1000
1200
1400
1600
Un
it
11.19%
-1.282.32%
17.13%
11.64%
17.65%
15
Current Situation of Cruise-ship Calling at PAS (2014-6M/2019)
M/V WESTERNDAM M/V EUROPA2
M/V AIDA BELLA
M/V COSTA FORTUNA
2013 2014 2015 2016 2017 2018 2019-6M
Calling Vessels 21 25 36 35 30 37 32
Number of Passeger 12549 15295 31101 50314 25538 40598 29845
21
25
3635
30
37
32
0
10000
20000
30000
40000
50000
60000
0
5
10
15
20
25
30
35
40U
nit 31,101
15,295
40,598
25,538
50,314
12,549
29,845
16
Composition of Import & Export Items at PAS (2018)
Containerize
Cargo, 2 052 001
General
Cargo;
93 263 Machinery
; 80 630
Steel; 41 436
Steam coal;
66 978
Fuel,
1 582 649
52.38%
Import Items (Tons) in 2018
Machinary; 204
Sugar;
74 018
General Cargo;
246
Rice; 420 233
Containerize Cargo,
1 336 922
Export Items (Tons) in 2018
72.99%
40.40%
22.94%
The following stepwise for Future Development Plan in accordance with Container CargoDemand, conducted by JICA Study Team (as of Feb. 2017).
500
1,000
1,500
2,000
2,500
Cargo Demand Forecast (Low Case)
Cargo Demand Forecast (Middle Case)
Cargo Demand Forecast (High Case)
Thousand
TEUs
Existing Facilities
Introduction of New Cargo Handling Equipment
New Container Terminal (Phase I)
New Container Terminal (Phase II)Multipurpose Terminal
New Container
Terminal (Phase III)
Port Development Scenario in Line with Cargo Demand
15.%
10%
5%
19
Loan Amount: JP¥23,502,000,000.-(USD 203 Million)
Sihanoukville Port New Container Terminal Development Project, CP-P21 (2020-2024)
Scope of Works: Consulting Services: (Under D/D)Nippon Koei & Oriental Consultants Global JV
Package-1: Infrastructures (Civil Works) Package-2: Superstructures (Equipment)
20
Package-1: Infrastructures (2020-2024):
Construction of New Container Terminal with 350m length; 500m width and Depth of Berth Box: -14.5m considering the following vessel draft is targeted:One over-Panamax size container vessel Two under-Panamax size container vessel
Access Channel and Turning BasinWater depth of access channel and turning basin is expected to be -13.5m in order to ensure water depth that target vessel can navigate.
New Container Terminal with -13.5m draft toaccommodate the over-Panama size container
ships with capacity of 60,000DWT (5,000TEUs) to
meet the 93% of Asia Pacific route ships into PAS
causing the Ocean Freight Cost to be comparable
with neighboring ports.
Sihanoukville Port New Container Terminal Development Project, CP-P21 (2020-2024)
21
Project Schedule:
For Civil Works: it is estimated to construct in middle 2021 and will be completed in middle 2024 (36 Months).
For Procurement of Handling Equipment:It is estimated to construct in 2022 and will be installed in 2024 (28 Months).
Sihanoukville Port New Container Terminal Development Project, CP-P21 (2020-2024)
Package-2: Superstructures (2020-2024):
1-QC Cranes (Post Panamax-14Rows): 03 Units2-RTG Cranes (6 Row, 1 over 5, Hybrid type): 09 Units3-Reach Stacker (10Ton) : 02 Units4-Tractor & Trailer (Container40’) : 16 Units5-CCTV System : 01 Set6-Back-up Generator (2000KVA) : 03 Units7-Terminal Operation System : 01 Set.
23
Sihanoukville Port Cruise Terminal Improvement Project, Studied by ADB (2020-2021)
Project Layout Phase 1:
Refurbishment of the existing
Jetty and improvement of the
water front at port plaza and
promenade areas. within the
port premise.
Project Cost:
USD 4 >12 Million.
Project Schedule:
2020 to 2021 (12 Months)
Sihanoukville Port Cruise Terminal Improvement Project, Studied by ADB (2019-2021)
Project Layout Phase 2:
Refurbishment of the existing
Jetty and improvement of the
water front at port plaza and
promenade areas within the
port premises;
Additional Construction of
New Jetty.
Project Cost:
USD 20 Million.
Project Schedule:
2039 to 2041 (24 Months)
25
Sihanoukville Port Cruise Terminal Improvement Project, Studied by ADB (2019-2021)
• Concession period: 25-50 years (PPP)
• Construction period (Phase 1): 12 months (2020-2021)
• Construction period (Phase 2): 24 months (2039-2041)
• Operations period: 49 years from COD for Phase 1
Project Timeline:
26
IV. Vessels Operation
• Major role and function to be improved and adapted by business partners
and relevant authorities are the followings:
Marine Services
Shipping Lines
Cargo Owners
Stakeholders
Container Terminal
Relevant Authorities
Economic growth, job creation, access to the port premises, human resourcedevelopment, minimised externalities, sustainability.
Pre-arrival and departure communication, port clearance (online), proposed EDIutilization, sustainability.
Port AuthorityCargo and vessel volumes, maximum targeted levels of capacity utilisation, highproductivity levels, quick turnaround of vessels, smooth logistics flows, marketgrowth.
Cargo volumes, compliance with schedules, high productivity, flexibility,reduced operating costs.
Targeted volumes, asset utilization, berth productivity levels, demand coverage, competency, safety, sustainability.
Compliance with dwell times and lead times, storage, cargo handlingproductivity, no cargo damage, reduced costs.
Container volumes, compliance with schedules, high productivity, flexibility,reduced operating costs.
27
PLANNING
- Prepare/plan marine movement
e.g docking, sailing or shifting
- Actual marine productivity
- Resource utilization
- Performance activities on
daily, weekly & monthly basis
- Report on capacity utilization
- Accurate cargo information
- Prepare-start/completion times
- Prepare yard/vessel planning
- Prepare maintenance works
- Terminal productivity
- Capacity utilization
- Performance activities on
daily, weekly & monthly basis
- Report on capacity utilization
- Actual truck movement
- Actual road efficiency
- Performance activities on
daily, weekly & monthly basis
- Report on capacity utilization
- Actual train movement
- Actual rail efficiency
- Performance activities on
daily, weekly & monthly basis
- Report on capacity utilization
- Prepare trucking plan to/from
the port’s work sites/premises
- Prepare maintenance work
- Prepare train plan to/from the
port’s premises
MONITORING REPORTING
V. Cargo offloading-Loading Operation
28
MARINE OPERATIONS• Resource availability • Marine service levels
- Report about docking, sailing, or
shifting on daily, weekly
& monthly basis
INFRASTRUCTURES
•Infrastructure: Cont. Yard, Warehouses, Container Terminal, Cruise Terminal •Superstructure: QCs, RTGs,
Trucks & Trailers
- Report about the requirements
and PAS’s actual capacity on
daily, weekly & monthly basis
•Berth productivity•Quay crane productivity•Yard productivity•Gate & Labor productivities
- Report about performance activities on daily, weekly, and
monthly basis
• Settle work load and cope with the requirements and clearance timeframes
- Report about performance activities on daily, weekly, and
monthly basis
CONTAINER TERMINAL
PORT SERVICES/OTHER GOV. AGENCIES
KEY PERFORMANCE MEASURES AND REPORTING
- Report about performance activities on daily, weekly, and
monthly basis
• Delivery: KAMSAB Delivery Order, Billing, Yard Operation, Gate out.
• Receiving: Trucking company, Billing, Gate in, Yard Operation
GATE OPERATION
VI. Activities for Improvement
PASInvesting in Cambodia’s Future
Conceptual Long Term PlanConcrete Business Plan to Accommodate the Growth Potential
Short & Medium Term Plan: (2017-2030)
New Container Terminal (draft -14.5m):
- Phase 1 : 350m
- Phase 2 : 350m
- Phase 3 : 350m
Long Term Plan:
Stage I: Development of remaining inner area of the existing breakwater.
Stage II: Expansion to outer area of the existing breakwater.