Acoustic Induced Vibration

download Acoustic Induced Vibration

of 15

Transcript of Acoustic Induced Vibration

  • 8/9/2019 Acoustic Induced Vibration

    1/33

    17 May 2009

    GN 44-005

     Assessment of Acoustically InducedVibration

    Guidance Note

    Document No. GN 44-005

    Date May 2009

    BP GROUPENGINEERING TECHNICAL PRACTICES

  • 8/9/2019 Acoustic Induced Vibration

    2/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 2 of 33

    Foreword

    This is the first issue of Guidance Note GN 44-005.

    Copyright © 2008 BP International Ltd. All rights reserved.

    This document and any data or information generated from its use are classified, as a

    minimum, BP Internal. Distribution is intended for BP authorized recipients only. The

    information contained in this document is subject to the terms and conditions of theagreement or contract under which this document was supplied to the recipient's

    organization. None of the information contained in this document shall be disclosed

    outside the recipient's own organization, unless the terms of such agreement or contractexpressly allow, or unless disclosure is required by law.

    In the event of a conflict between this document and a relevant law or regulation, therelevant law or regulation shall be followed. If the document creates a higher obligation, it

    shall be followed as long as this also achieves full compliance with the law or regulation. 

  • 8/9/2019 Acoustic Induced Vibration

    3/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 3 of 33

    Table of Contents

    Page

    Foreword............................................................................................................................................2  

    Introduction ........................................................................................................................................5 

    1.  Scope........................................................................................................................................6  

    .......................................................................................................................................6  

    1.2.  BP experience ...............................................................................................................6 

    2.  References ...............................................................................................................................6 

    3.  Symbols and abbreviations.......................................................................................................7 

    4.   AIF Proceedure.........................................................................................................................7 

    5.   Acoustically Induced Vibration Data Sheet...............................................................................9 

    5.1.  Calculation formula......................................................................................................10 

    5.2.  Design action: Continuously Operated System ...........................................................12 

    5.3.  Design action: Non- continuously Operated System...................................................12 

    5.4.  Piping integrity improvement .......................................................................................13 

    5.5.  Specialist assistance ...................................................................................................13 

     Annex A: Example 1 ........................................................................................................................15 

    Section 1: 8” line downstream of valve...................................................................................16 

     Annex B - Example 2 .......................................................................................................................17 

    Section 1: 8” line downstream of valve...................................................................................18 

    Section 2: 16” line downstream of valve.................................................................................19 

    Section 3: 24” line downstream of valve.................................................................................20 

     Annex C: Example 3 ........................................................................................................................21 

    Section 1: 12” line downstream of valve.................................................................................22 

     Annex D: Example 4 ........................................................................................................................23 

    Location A: valve #1 tail pipe to header..................................................................................24 

    Location B: valve #2 tail pipe to header..................................................................................25 

     Annex E: Mach Number Calculations ..............................................................................................26 

     Annex F: Addition of sound power levels.........................................................................................28 

     Annex G: Input Required For Detailed Analysis ..............................................................................29 

     Annex H: Design Limits for Acoustically Induced Vibration .............................................................30 

    Bibliography .....................................................................................................................................33 

  • 8/9/2019 Acoustic Induced Vibration

    4/33

  • 8/9/2019 Acoustic Induced Vibration

    5/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 5 of 33

    Introduction

    Experience in the gas production, petrochemical and other industries has demonstrated that acoustic

    energy in high capacity gas pressure reducing systems can cause severe piping vibrations. In extreme

    cases, these have led to piping fatigue failures after a few hours of operation. Typical systems where

    such problems may occur include large compressor recycle systems, Emergency Depressurisation

    systems (EDP) or blowdown valves and high capacity safety valve pressure let-down systems. The

    trend in recent years towards higher capacity systems has increased the likelihood of experiencing

    such failures.

    The most vulnerable systems have the following characteristics:

    a.  High mass flow rate

     b.  High pressure drop

    c.  Weldolet connection into large diameter, thin walled pipe.

  • 8/9/2019 Acoustic Induced Vibration

    6/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 6 of 33

    1. Scope

    This document is intended to provide the design engineer with methods for assessing potential failures

    from acoustic induced fatigue (AIF) at an early stage of design. This note should also be used to assess

    existing systems. The style of this document, with its use of decision diagrams, is intended to limit

    ambiguities of interpretation which are often inevitable in guidelines of this sort. However, wherethese exist and require clarification full consultation with the BP Representative should be made. Only

    valves in vapour or mixed flow service need be considered. Valves in liquid service do not need to be

    considered.

    Engineering design criteria and methodology has been developed and is most appropriate for single

     phase vapour fluids. The effects of AIF in multi phase fluids is not as well developed. It is

    conservative to use the total mass flow rate on the assumption that the liquid will flash off. It is

    important to note that industry experience shows that it is connections to the main pipe, rather than

    circumferential or longitudinal butt welds, which are most vulnerable. Therefore any design

    modifications need to consider either thickening up the main pipe; applying attention to the detail of

    the connection or a combination of both of these design solutions. The connection may be a branch

     pipe, pipe support or small bore vent, drain or instrument connection. It is an acceptable designalternative to locally thicken up a pipe header in vulnerable areas and then use a reduced wall

    thickness where there are no branch connections or other structural discontinuities.

    Further, it is important to note that other vibration mechanisms in piping systems need to be

    systematically considered. Other mechanisms include

    a.  Flow induced turbulence

     b.  Pulsation past a dead leg

    c.  Momentum change due to fast opening valve

    d.  Surge due to liquid carry overThese mechanisms are beyond the scope of this document. ETP’s GP 44-80 and GP 44-70 outline

    issues associated with design of pressure relief systems and should be used in conjunction with this

    GN

    1.2. .BP experience

    BP have had multiple cases where failures have been caused by AIF, these include:

    a.  Alaska[4]

     b.  Krechba, Algeria

    c.  Schiehallion. North Sea

    d.  ALNG, Trinidad

    This GN has been developed considering latest industry practices and application of the

     principals of AIF should reduce the likelihood of these types of failures.

    2. References

    BP

    GP 42-10 Piping systems (ASME B31.3)

    GP 44-70 Overpressure Protection Systems

    GP 44-80 Relief Disposal Systems

  • 8/9/2019 Acoustic Induced Vibration

    7/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 7 of 33

    Industry Standards

    Energy Institute Guidelines for the Avoidance of Vibration Induced Fatigue in Process

    Pipework, 2nd Edition, January 2008

    3. Symbols and abbreviations

    For the purpose of this GN the following symbols and abbreviations apply:

    AIF Acoustically induced fatigue. Sometimes referred to as acoustically induced vibration

    (AIV). Fatigue and vibration due to high frequency acoustic excitation. Typically, the

    dominant frequency is between 500 Hz and 2 kHz.

    dB decibel

    Lw, PWL Sound Power level

    LOF Likelihood of failure

    4. AIF Proceedure

    It is intended that this guidance note supplements the use of the EI Guidelines and BP ETP’s GP 44-70

    and 44-80. This guidance note should be used on new projects in the design phase and for the

    assessment of existing facilities.

    It would be anticipated that new projects would normally implement the piping integrity

    improvements described in section 5 as required. However, this may not be practical for existing

    facilities That were either built to different standards or are being re-rated for higher capacities. In this

    case it may be possible to ensure integrity by completing a thorough acoustic structural finite element

    analysis and carry out local modifications to ensure acceptable integrity. This approach is described insection T10.7 of the EI guidelines. This detailed analysis is beyond the scope of this guidance

    document, however the input needed to complete this type of analysis is included in Annex G. This

    design approach should be supplemented by an inspection program on downstream piping. Inspection

    should be focused on looking for surface breaking defects that would act as fatigue initiation points.

    Any defects should be removed.

    It would normally be expected that the first stage of this analysis work (which is predominantly data

    gathering and a single simple calculation) would be completed by a BP engineer or qualified

    engineering contractor. Whilst the second stage which involves consideration of multiple relief valves

    operating simultaneously and a full assessment to the EI guidelines would normally be completed by a

    specialist consultant or engineering contractor who is familiar with the application method. However,

    there is sufficient detail in this document for a competent engineer to complete this stage of theassessment using this guidance note and the EI guidelines.

  • 8/9/2019 Acoustic Induced Vibration

    8/33

  • 8/9/2019 Acoustic Induced Vibration

    9/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    5. Acoustically Induced Vibration Data Sheet

    Calculations would normally be completed using a spreadsheet type format. Typical layout is shown in Table 1. Part

    used in the calculation. The formula and consistent set of units shown in section 5.1 should normally be used.

    Inputs Result Commen

    Valve Tag Mass flow UpstreamPressure

    DownstreamPressure

    Gas molecularweight

    Upstreamtemperature

    PWL Continuoservice

    kg/hr Bar(A) Bar(A) deg C dB (>5 hours

    V-001 20,000 30 1 25 40 154 N

    V-002 140,000 30 1 25 50 171 N

    V-003 100,000 40 1 18 53 170 N

    V-004 160,000 40 1 18 53 174 N

    V-005 150,000 60 1 22 53 172 N

    V-006 70,000 40 1 22 53 166 Y

    V-007 60,000 40 1 19 53 165 N

    V-008 30,000 40 1 19 53 159 N

    V-009 40,000 40 1 19 53 161 N

    Table 1: Typical layout for acoustic fatigue calculation

  • 8/9/2019 Acoustic Induced Vibration

    10/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 10 of 33

    5.1. Calculation formula

    There are a number of formulas used to assess AIF. The sound power level immediately

    downstream of the valve may be calculated using Equation 1. This equation is only valid for the

     pressure, temperature and mass flow measurement units shown in this section.

    Table 2: Valve nomenc lature

    SFF m

    T W 

    P

    PPPWL   ++

    ⎥⎥⎦

    ⎢⎢⎣

    ⎡⎟ ⎠

     ⎞⎜⎝ 

    ⎛ ⎟⎟ ⎠

     ⎞⎜⎜⎝ 

    ⎛    −= 1.126log10

    2.1

    12

    6.3

    1

    2110  

    Equation 1

    Credit may be taken for attenuation of acoustically induced vibration due to pipe length

    downstream of the valve. For the purpose of these design calculations, assume attenuation of

    3dB/50 diameters downstream of the pressure let-down device. The sound power level at a

    distance x from the valve may be calculated using Equation 2.

     Normally there is no need to extend the analysis beyond the feature that acts as an acoustic

     block such as a flare knock out drum. In many cases, the piping isometrics will not be

    available at the time this study is required. It is conservative to ignore attenuation due to piping.

     D

     xPWL xPWL

    06.0)(   −=   Equation 2

    The Mach number of gas downstream of the valve may be calculated using Equation 3. The

    derivation of this formula is given in Annex C. This equation is only valid for the units shown

    in this section.

    γ  mT 

     DPW  M  2

    2

    2

    2 116=   Equation 3

     p1 

    T1 

     p2 

    T2 

    PWL

    Direction of flow

    x

    PWL(x)

  • 8/9/2019 Acoustic Induced Vibration

    11/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 11 of 33

    Where:

    P1  = upstream pressure Bar(A)

    P2  = downstream pressure Bar(A)

    T1, = upstream temperature K

    T2  = downstream temperature (0oC=273 K K

    PWL = sound power level dB

    SFF = A correction factor to account for sonic flow . If sonicconditions exist (M2>1) then SFF=6; otherwiseSFF=0

    dB

    M2  = Downstream Mach number

    W = flow rate of gas and liquid kg/s

    D = nominal pipe diameter m

     x   = distance downstream of valve m

    γ  = ratio of specific heats Cp/Cv, see Appendix E

    m = molecular weight

    DL = Design limit sound power level dB

    5.1.1. Downstream Pipe Diameter

    The diameter used in setting the LOF limit may not be that at the pipe outlet. Careful

    consideration must be given to all pipework downstream of the valve. Pipework with a larger

    diameter is more vulnerable to AIF See example 2 calculation in Annex B.

    5.1.2. Downst ream pressure

    It is normal to use 1 Bar(A) as the downstream pressure for an atmospheric relief line. The back

     pressure will build up during relief, but the maximum damage is likely to be during the initialevent when the flow rates are greatest and the back pressure is lowest.

    5.1.3. Low Noise Valves

    Where ‘low noise’ type valves with small passages are required, strainers should be installed

    upstream of the valve to avoid debris accumulation in the valve itself. The strainers may be

    omitted if there are sufficient, similar devices to ensure a debris-free system fitted elsewhere

    upstream of the valve.

    5.1.4. Sonic flow correction factor

    Sonic flow conditions in the downstream pipework should normally be avoided. To avoid sonic

    flow a larger pipe is normally used downstream of the pressure device.The selection of Mach number as the sole criteria that should be used in determining the flare or

    relief header piping sizing where the process conditions are transient, can be problematic. It is

    too conservative to use the Mach number when the downstream pressure is atmospheric. If this

    is a critical factor then expert advice should be taken.

    5.1.5. Design limits for Acoustically induced vibration

    Using the EI guidelines, an LOF score may be calculated. Depending on the LOF score, the

    design actions shown in the following sections should be followed. Examples of calculations are

    given in Annex A and Annex B. It is important that the design of the piping is balanced between

    the pipe wall thickness and attention to the connection type.

    For example, a weldolet connection into schedule 10S piping is particularly vulnerable.

  • 8/9/2019 Acoustic Induced Vibration

    12/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 12 of 33

    5.2. Design action: Continuous ly Operated System

    For the purposes of AIF, any valves that are used for greater than 5 hours during the life of the

     plant are normally considered to be operating continuously. The high frequency nature of AIF

    (typically 500 Hz to 2KHz) means that a very high number of cycles can be rapidly

    accumulated.

    Experience shows that piping systems associated with blow-down valves that are used during

     plant commissioning or start-up are particularly vulnerable.

    Piping integrity improvement

    Minimum schedule

    LOF

    rqd?CS SS    M

      a  x .

       d   /  s

       M  a  c   h   N  o .   M   2

       S  p  e  c   i  a   l   i  s   t

      a  s  s   i  s   t  a  n  c  e

       L  o  w

       N  o   i  s  e

       V  a   l  v  e  s   (   Y   /   N   )

    ≤ 0.5 No ≤ 0.5 No No

    0.5 < LOF ≤ 1.0 Yes STD 40S ≤ 0.5 No Yes

    > 1.0 Yes

    Table 3: Design actions: Continuously operated systems

    Table 3 should be interpreted such that either:

    a.  the pipe thickness may be increased such that the LOF is less than or equal to 0.5. In whichcase a low noise valve or piping integrity improvements detailed in paragraph 5.4 are not

    required. Experience has shown that it would not be normal to increase the wall thickness

    of the pipe above 19mm (3/4”) to meet the requirements of AIF. Documented failures to

    date have been in pipe work with wall thickness less than 19mm.

    or

     b.  an LOF of between 0.5 and 1.0 is acceptable provided that a low noise valve is used and the pipe minimum schedule is used and the piping integrity improvements detailed in

     paragraph 5.4 are included in the design.

    If the LOF is greater than 1, then refer to paragraph 5.5.

    5.3. Design action: Non- continuously Operated System

    Relief valves are normally considered to operate non -continuously.

    Piping integrity Improvement

    Minimum schedule

    LOF

    rqd?CS SS    M

      a  x .

       d   /  s

       M  a  c   h   N  o .   M   2

       S  p  e  c   i  a   l   i  s   t

      a  s  s   i  s   t  a  n  c  e

    ≤ 0.5 No ≤ 0.75 No

    0.5 < LOF ≤ 1.0 Yes STD 40S ≤ 0.75 No

    > 1.0 Yes

    Table 4: Design actions: Non-continuously operated systems

  • 8/9/2019 Acoustic Induced Vibration

    13/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 13 of 33

    Table 4 should be interpreted such that either:

    a.  the pipe thickness may be increased such that the LOF is less than or equal to 0.5. In whichcase piping integrity improvements detailed in paragraph 5.4 are not required. It would not

     be normal to increase the wall thickness of the pipe above 19mm (3/4”) to meet the

    requirements of AIF.

    or

     b.  an LOF of between 0.5 and 1.0 is acceptable provided that the pipe minimum schedule isused and the piping integrity improvements detailed in paragraph 5.4 are included in the

    design.

    If the LOF is greater than 1, then refer to paragraph 5.5.

    5.4. Piping integrity improvement

    a.  Use welding tees or sweepolets at all branch connections 80mm diameter and larger.Weldolets, partial reinforcing pads and reinforced branch connections shall not be used.

     b.  Small diameter branch connections ≤ 50mm diameter should be made using 6,000 lb Nipolets.

    c.  Use full wraparound reinforcement at welded-on support shoes or restraint points.Consider bolted-on shoes or clamps to eliminate all welding to pipe at supports or anchors.

    d.  In the piping length requiring Integrity Improvement branches shall be avoided wherever possible. Pressure gauge, pressure tapping, vent and drain branches and similar free-end

     branches shall be braced back to the header (run pipe).

    e.  Eliminate small vents and drains where possible. Where not, when testing is completeremove flanged valve(s) from hydrotest vents and drains and blank off flanged connection

    with a blind flange.f.  All small diameter valves and instrument components (50mm diameter and smaller)

    attached to the main line and packing nuts for in-line control valves and block valves,

    should employ locking nuts, e.g. elastic stop nuts, or double locking nuts to prevent

    loosening due to vibration.

    5.5. Specialist assis tance

    If the LOF is greater than 1, then specialist assistance should be sought. An additional check

    may be made using Figure 3 in Annex H. If the PWL exceed the design limit by about 15dB or

    more, then more significant system changes will probably be required. Consideration should be

    given to splitting the flow into parallel paths not terminating at the same point or taking the

     pressure letdown across stages in series such as by orifice plates downstream of the controlvalve (where possible). The design approach to be used in these “extreme” cases will depend on

    the particular system involved and the amount of attenuation needed. These should be discussed

    as separate issues and resolved on an “item by item” basis.

    It is possible to perform an acoustic structural finite element calculation to determine the actual

    design fatigue life of the piping configuration. This is an analysis that should only be completed

     by specialists who are competent and experienced in this technique. The data that is typically

    required to carry out this analysis is given in Annex G.

    A possible design modification is to use circumferential stiffening rings, however, this should

    only be considered for existing facilities and should not be used on new designs.

    Should it be determined that “specialist assistance” is required, then an external specialist

    consultant should be brought in to assist in the analysis and develop recommendations. It is

  • 8/9/2019 Acoustic Induced Vibration

    14/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 14 of 33

    strongly recommended that a BP mechanical specialist provide oversight to the external

    specialist work.

  • 8/9/2019 Acoustic Induced Vibration

    15/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 15 of 33

     Annex A: Example 1

    The relief valve has a 30 Bar(A) upstream pressure and discharges into a header that is initially at

    atmospheric conditions. The mass flow rate is 20,000 kg/hour. The relief temperature is 40oC, the gas

    molecular weight is 25 and the ratio of specific heats is 1.21.

    Where:

    P1  = upstream pressure 30 Bar(A)

    P2  = downstream pressure 1 Bar(A)

    T2  = downstream temperature 313 K

    SFF = A correction factor to account for sonic flow . If sonic conditions existthen SFF=6; otherwise SFF=0

    0 dB

    M2  = Downstream Mach number

    W = flow rate of gas and liquid 5.56 kg/s

    D = nominal pipe diameter 0.2 m

    Di  = Inside pipe diameter (std wall) 0.211 m

    γ  = ratio of specific heats Cp/Cv  1.21

    m = molecular weight 25

    8” DIA

    24” DIA

    60m16” DIA

    10m

  • 8/9/2019 Acoustic Induced Vibration

    16/33

  • 8/9/2019 Acoustic Induced Vibration

    17/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 17 of 33

     Annex B - Example 2

    The relief valve example used in Annex A has its capacity increased to 140,000 kg/hour.

    Where:

    P1  = upstream pressure 30 Bar(A)

    P2  = downstream pressure 1 Bar(A)T2  = downstream temperature 313 K

    SFF = A correction factor to account for sonic flow . If sonic conditions existthen SFF=6; otherwise SFF=0

    0 dB

    M2  = Downstream Mach number

    W = flow rate of gas and liquid 38.89 kg/s

    D = nominal pipe diameter 0.2 m

    Di  = Inside pipe diameter (std wal) 0.211 m

    γ  = ratio of specific heats Cp/Cv  1.21

    m = molecular weight 25

    8” DIA

    24” DIA

    60m

    16” DIA

    10m

  • 8/9/2019 Acoustic Induced Vibration

    18/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 18 of 33

    Section 1: 8” line downstream of valve

    Step 1 Calculate Mach number. The developed back pressure in the system is 8 Bar(A).

    41.0

    21.125

    313

    211.0108

    89.38116

    116

    25

    2

    2

    2

    2

    =×××

    =

    =

     M 

    m

     DP

    W  M 

    i  γ  

     

    Step 2 Calculate sound power level.

    dB

    SFF m

    T W 

    P

    PPPWL

    171

    01.12625

    31389.38

    30

    130log10

    1.126log10

    2.1

    2

    6.3

    10

    2.1

    12

    6.3

    1

    110

    =

    ++⎥⎥⎦

    ⎢⎢⎣

    ⎡⎟ ⎠

     ⎞⎜⎝ 

    ⎛ ⎟ ⎠

     ⎞⎜⎝ 

    ⎛    −=

    ++⎥⎥⎦

    ⎢⎢⎣

    ⎡⎟ ⎠

     ⎞⎜⎝ 

    ⎛ ⎟⎟ ⎠

     ⎞⎜⎜⎝ 

    ⎛    −=

     

    Step 3 171>155 additional analysis in accordance with EI guidelines is required

    Step 4 There is a welded support immediately downstream of the relief valve. Neglect attenuation andtake the pipe as 8” standard wall

    Use flowchart T2-6

    D=219 ; d=219

    S=65.1 ; B=160.2 ; N=8.3x107 

    FLM1=1.75 ; FLM2=1 ; FLM3=1

    N=1.4x108 

    Step 5 Calculate the LOF

    ( )

    ( )

    7.0

    1.34.2

    1.31044.1ln1303.0

    1.3ln1303.0

    8

    =

    +−=

    +××−=

    +×−=

     LOF 

     N  LOF 

     

    Step 6 As the LOF is greater than 0.5, corrective action is required

    Increasing the wall thickness to 11 mm reduces the LOF to 0.5. An alternative to increasing thewall thickness would be to increase the wall thickness to 40S (for a stainless line) or STD wall

    (for a carbon steel line) and use a wrap around reinforcement or bolted pipe shoe.

  • 8/9/2019 Acoustic Induced Vibration

    19/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 19 of 33

    Section 2: 16” line downst ream of valve

    The 8” pipe now joins a 16” header using a fabricated tee. The 8” to 16” branch must be

    assessed.

    Step 1

    dB

     D

     xPWL xPWL

    168

    3171

    219.0

    1006.0171

    06.0)(

    =

    −=

    ×−=

    −=

     

    Step 2 168>155 additional analysis in accordance with EI guidelines is required

    Step 3 Use flowchart T2-6

    D=406 ; d=219

    S=49.3 ; B=161.5 ; N=4.5x107 

    FLM1=1.34 ; FLM2=1 ;FLM3=1

    N=5.9x107 

    Step 5 Calculate the LOF

    ( )

    ( )

    8.0

    1.33.2

    1.3109.5ln1303.0

    1.3ln1303.0

    7

    =

    +−=

    +××−=

    +×−=

     LOF 

     N  LOF 

     

    Step 6 As the LOF is greater than 0.5, corrective action is required

    Increasing the wall thickness to 16 mm reduces the LOF to 0.5. An alternative would be to

    increase the wall thickness locally to 40S (for a stainless line) or STD wall (for a carbon steel

    line) and use a sweepolet or forged tee.

  • 8/9/2019 Acoustic Induced Vibration

    20/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 20 of 33

    Section 3: 24” line downst ream of valve

    The 16” pipe now joins a 24” header using a fabricated tee. The 16” to 24” branch must be

    assessed.

    Step 1

    dB

     D

     xPWL xPWL

    159

    9168

    406.0

    6006.0168

    06.0)(

    =

    −=

    ×−=

    −=

     

    Step 2 159>155 additional analysis in accordance with EI guidelines is required

    Step 3 Use flowchart T2-6D=610 ; d=406

    S=27.9 ; B=156.3 ; N=6.5x108 

    FLM1=1.44 ; FLM2=1 ;FLM3=1

    N=9.3x108 

    Step 5 Calculate the LOF

    ( )

    ( )

    4.01.33.2

    1.3103.9ln1303.0

    1.3ln1303.0

    8

    = +−=

    +××−=

    +×−=

     LOF 

     N  LOF 

     

    Step 6 The LOF is less than 0.5, no further corrective action is required

  • 8/9/2019 Acoustic Induced Vibration

    21/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 21 of 33

     Annex C: Example 3

    The relief valve has a 80 Bar(A) upstream pressure and discharges into a header that is initially at

    atmospheric conditions. The mass flow rate is 340,000 kg/hour. The relief temperature is 80oC, the gas

    molecular weight is 18 and the ratio of specific heats is 1.25.

    Where:P1  = upstream pressure 80 Bar(A)

    P2  = downstream pressure 1 Bar(A)

    T2  = downstream temperature 353 K

    SFF = A correction factor to account for sonic flow . If sonic conditions existthen SFF=6; otherwise SFF=0

    0 dB

    M2  = Downstream Mach number

    W = flow rate of gas and liquid 94.4 kg/s

    D = nominal pipe diameter 0.323 m

    Di  = Inside pipe diameter (std wal) 0.313 m

    γ  = ratio of specific heats Cp/Cv  1.25

    m = molecular weight 18

    12” DIA

    24” DIA

  • 8/9/2019 Acoustic Induced Vibration

    22/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 22 of 33

    Section 1: 12” line downst ream of valve

    Step 1 Calculate Mach number. The developed back pressure is 8 Bar(A)

    55.0

    25.118

    353

    313.0108

    4.94116

    116

    25

    2

    2

    2

    2

    =×××

    =

    =

     M 

    m

     DP

    W  M 

    i  γ  

     

    Step 2 Calculate sound power level.

    dB

    SFF m

    T W 

    P

    PPPWL

    181

    01.12618

    3534.94

    80

    180log10

    1.126log10

    2.1

    2

    6.3

    10

    2.1

    12

    6.3

    1

    110

    =

    ++⎥⎥⎦

    ⎢⎢⎣

    ⎡⎟ ⎠

     ⎞⎜⎝ 

    ⎛ ⎟ ⎠

     ⎞⎜⎝ 

    ⎛    −=

    ++⎥⎥⎦

    ⎢⎢⎣

    ⎡⎟ ⎠

     ⎞⎜⎝ 

    ⎛ ⎟⎟ ⎠

     ⎞⎜⎜⎝ 

    ⎛    −=

     

    Step 3 181>155 additional analysis in accordance with EI guidelines is required. Consider the 12”

    to 24” connection. This is a fabricated tee. Both lines are schedule 10S stainless steel.

    Step 4 Use flowchart T2-6

    D=604 ; d=323

    S=-3.2 ; B=181.4 ; N=3.6x104 

    FLM1=1.34 ; FLM2=1 ;FLM3=0.35

    N=1.6x104 

    Step 5 Calculate the LOF

    ( )

    ( )

    8.1

    1.33.1

    1.3106.1ln1303.0

    1.3ln1303.0

    4

    =

    +−=

    +××−=

    +×−=

     LOF 

     N  LOF 

     

    Step 6 As the LOF is greater than 0.5, corrective action is required

    Increasing the wall thickness to 19 mm reduces the LOF to 1.4. This is not acceptable. Checking

    the sound power level (181 dB) against pipe size (24”) shows that these values fall into the

    range where a substantial redesign is required. It would be recommended that specialist

    assistance is sought or the flare design is substantially revised.

  • 8/9/2019 Acoustic Induced Vibration

    23/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 23 of 33

     Annex D: Example 4

    Two relief valve are designed to operate simultaneously into a common header.

    Valve #1 has a sound power level of 172 dB and valve #2 has a sound power level of 165 dB. The

    flow is not sonic.

    5m 24” DIA

    10 m 8” DIA10 m 8” DIA

    valve #1 valve #2

    A B

  • 8/9/2019 Acoustic Induced Vibration

    24/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 24 of 33

    Location A: valve #1 tail pipe to header

    The 8” tail pipe from valve #1 joins the 24” header using a fabricated tee. The 8” to 24” branch

    must be assessed by first finding the total sound power level at the junction.

    Step 1 Contribution from valve #1

    dB

     D xPWL xPWL

    169

    3172

    219.0

    1006.0172

    06.0)(

    =

    −=

    ×−=

    −=

     

    Contribution from valve #2

    dB

     D

     xPWL xPWL

    162

    5.03165

    610.0

    506.0

    219.0

    1006.0165

    06.0)(

    =

    −−=

    ×−

    ×−=

    −=

     

    Calculate the total sound power level at A using Table 5

    dB170dB162dB169)(

    = += APWL  

    Step 2 170>155 additional analysis in accordance with EI guidelines is required

  • 8/9/2019 Acoustic Induced Vibration

    25/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 25 of 33

    Location B: valve #2 tail pipe to header

    The 8” tail pipe from valve #2 joins the 24” header using a fabricated tee. The 8” to 24” branch

    must be assessed by first finding the total sound power level at the junction.

    Step 1 Contribution from valve #1

    dB

     D

     xPWL xPWL

    168

    5.03172

    610.0

    506.0

    219.0

    1006.0172

    06.0)(

    =

    −−=

    ×−

    ×−=

    −=

     

    Contribution from valve #2

    dB

     D xPWL xPWL

    162

    3165

    219.0

    1006.0165

    06.0)(

    =

    −=

    ×−=

    −=

     

    Calculate the total sound power level at A using Table 5

    dB169

    dB162dB168)(

    =

    += APWL 

    Step 2 169>155 additional analysis in accordance with EI guidelines is required

    Locations A and B may now be assessed using the same method as shown in previous

    examples. This calculation is conservative as no account of attenuation at the header connection

    or energy loss split between upstream and downstream. However, it is normally adequate for

    initial screening purposes.

    It is normally good practice to start with the valve with the highest sound power level.

  • 8/9/2019 Acoustic Induced Vibration

    26/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 26 of 33

     Annex E: Mach Number Calculations

    The mach number would normally be calculated at as part of the system process design. If this

    calculation is not readily available, then the Mach number downstream of the valve may be calculated

    as follows;

    2

    2

    2

    2

    :where

     ZRT 

    m p

    wv

    m

     RT c

    c

    v M 

    =

    =

    =

    =

     ρ 

     ρ π 

    γ   

    Where:

    M = Mach number (dimensionless)

    v = Gas velocity in pipe (m/s)

    c = Speed of sound of gas in pipe (m/s)

    γ    = Ratio of specific heats

    R = Universal gas constant

    T2  = Downstream temperature (K)

    m = Molecular weight of gas

    w = Mass flow rate (kg/s)

    r = Pipe inside radius (m)

    D = Pipe inside diameter (m)

     ρ    = Gas density (kg/m3)

    p2  = Downstream pressure (Pa)

    Z = compressibility

    If equation is rearranged to give the Mach number then:

    γ  π 

    γ  π 

    m

     D p

    w R Z 

     RT 

    m

    m p

     ZRT 

    w M 

    2

    2

    2

    2

    22

    2

    2

    2××⎟

    ⎟ ⎠

     ⎞⎜⎜⎝ 

    ⎛ =

    ××=

     

    Using the normal values for R (8315) and Z (1).

    γ  

    γ  π 

    m

     D p

    w M 

    m

     D p

    w M 

    2

    2

    2

    2

    2

    2

    2

    116

    831512

    ×=

    ××⎟⎟ ⎠

     ⎞⎜⎜⎝ 

    ⎛    ××=

     

  • 8/9/2019 Acoustic Induced Vibration

    27/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 27 of 33

    Figure 2: Graph to estimate the ratio o f specific heats for hydrocarbon gases

  • 8/9/2019 Acoustic Induced Vibration

    28/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 28 of 33

     Annex F: Addit ion of sound power levels

    Equation 1 shows that the sound power level is measured in dB (decibel). The Bel is a unit which

    gives the number of tenfold changes between two quantities, whilst the deci indicates that that the Bel

    is divided into units of ten. Sound power level is defined as shown in Equation 4

    dB power reference

     power sound log10 10   ⎥

    ⎤⎢⎣

    ⎡=PWL   Equation 4

    Where reference power is 10-12

    watts.

    Using this equation, it can be seen that 3dB represents a doubling of energy.

    PWL= 155 dB watts000,30110 power sound  1210 =×=   −PWL

     

    PWL= 170 dB watts000,1000110 power sound  1210 =×=   −PWL

     

    PWL= 173 dB watts000,2000110 power sound  1210 =×=   −PWL

     

    It can be seen that care must be taken when adding two decibel values. This can be done by using

    Table 5.

    Difference between thetwo levels

     Add to higher level

    dB dB

    0 3

    1 2.5

    2 2

    3 2

    4 1.5

    5 1

    6 1

    7 1

    8 0.5

    9 0,5

    10 0

    Table 5: Addition of sound levels

  • 8/9/2019 Acoustic Induced Vibration

    29/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 29 of 33

     Annex G: Input Required For Detailed Analysis

    The input required to complete an acoustic structural finite element analysis includes the following:

    Relief system design philosophy and details including

    a.  P&ID showing scope of system

     b.  Isometrics showing all connections and details of supports and any pad reinforcementdetails

    c.  Valve data sheets

    d.  Simultaneous relief scenarios

    e.  Relief system design simulation output (flarenet or equivalent)

    For non-relief systems, similar information will be required to complete the acoustic structural finite

    element review.

    The analysis results in a design time to failure. For non-continuously operated valves this design life

    will normally be assessed against a required life of five hours.

  • 8/9/2019 Acoustic Induced Vibration

    30/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 30 of 33

     Annex H: Design Limits for Acoustically Induced Vibration

    Prior to the introduction of the EI guidelines, assessment of AIF was often based on figures such as

    shown in Figure 3 and Figure 4. Such charts has been included in this section to act as a second design

    check against the EI LOF method. The figure clearly demonstrates that AIF is a function of pipe

    diameter. Whilst such figures are useful they do not highlight the particular vulnerability of weldolet branch connections and other structural discontinuities.

    Figure 3: Design limits for acoustically induced vibration

  • 8/9/2019 Acoustic Induced Vibration

    31/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 31 of 33

    The data from Carrucci and Mueller [1]

    were plotted using the diameter to thickness ratio by

    Eisenger [5]. This is shown in Figure 4.

    Figure 4: Design limits for acoustically induced vibration

  • 8/9/2019 Acoustic Induced Vibration

    32/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Page 32 of 33

    The assessment of the various action levels is given in Table 6 and Table 7 for continuously and non

    continuously operated valves respectively. Relief valves are normally considered to operate non -

    continuously. If the PWL exceed the design limit by about 15dB or more, then more significant system

    changes are normally required.

    Piping integrity improvement

     Action Δ=PWL-DL (dB)

    rqd?Length to apply

    downstream

    Min. pipethk (mm)

       M  a  x .

       d   /  s

       M  a  c   h   N  o .   M   2

       R  e   d  e  s   i  g  n

       L  o  w

       N  o   i  s  e

       V  a   l  v  e  s   (   Y   /   N   )

    No Action ≤ 0 No ≤ 0.5 No No

     A ≤ 3 Yes 50 D 13 ≤ 0.5 No No

    B 3 < Δ ≤ 5 Yes 50D. Δ/3 13 ≤ 0.5 No Yes

    C

    D5 < Δ ≤ 15 Yes 50D. Δ/3 16 ≤ 0.5 No Yes

    E > 15 Yes

    Table 6: Design actions: Continuously operated systems

    Piping integrity Improvement

     ActionΔ=PWL-DL

    (dB)

    rqd?Length to apply

    downstream

    Min. pipe

    thk (mm)    M  a  x .

       d   /  s

       M

      a  c   h   N  o .   M   2

       R

      e   d  e  s   i  g  n

    No Action ≤ 0 No ≤ 0.75 No

     A ≤ 3 Yes 50D. Δ/3 13 ≤ 0.75 No

    B 3 < Δ ≤ 5 Yes 50D. Δ/3 13 ≤ 0.75 No

    C 5 < Δ ≤ 10 Yes 50D. Δ/3 13 ≤ 0.75 No

    D 10 < Δ ≤ 15 Yes 50D. Δ/3 16 ≤ 0.75 No

    E > 15 Yes

    Table 7: Design actions: Non-continuously operated systems

  • 8/9/2019 Acoustic Induced Vibration

    33/33

      GN 44-005 Assessment of Acoustically Induced Vibration

    Bibliography

    [1] Acoustically Induced Piping Vibration In High Capacity Pressure Reducing Systems. V.A. Carucciand R.J. Meuller. ASHE winter annual meeting 14-19

    th November 1982.

    [2] Acoustic Fatigue in Pipes. Concawe Report No. 85/52, 1985

    [3] Acoustically induced structural fatigue of piping. F.L.Eisenger and J.T.Francis. Transactions of ASMEVol121, November 1999.

    [4] Prudhoe Bay Central Gas Facility Start-up planning, commissioning and early operation. C.B.’Nan.MD.D.Kyrias, Gas Processors Annual Convention Proceedings, 1988

    [5] Designing piping systems against acoustically-induced structural fatigue. F.L.Eisenger, ASME PVP-

    Vol 328