Access to Electricity Distribution Networks - A Users Guide 1998

download Access to Electricity Distribution Networks - A Users Guide 1998

of 13

Transcript of Access to Electricity Distribution Networks - A Users Guide 1998

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    1/13

    Access to

    Electricity Distribution Networks

    A Users Guide

    version 1 August 1998

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    2/13

    TABLE OF CONTENTS

    1 SUMMARY .............................................................................................................................. 1

    2 INTRODUCTION .................................................................................................................... 1

    3 MARKET ARRANGEMENTS IN WESTERN AUSTRALIA ............................................... 1

    4 GENERAL TERMS AND CONDITIONS............................................................................... 2

    5 DESCRIPTION OF NETWORK ASSETS.............................................................................. 2

    6 TECHNICAL CODE................................................................................................................ 3

    7 DISTRIBUTION NETWORK PRICING............................................ .................................... 3

    8 NETWORK CHARGES........................................................................................................... 3

    8.1 DESCRIPTION OF CHARGES ................................................................................................... 3

    8.2 ENERGY BALANCING............................................................................................................ 4

    8.3 ANCILLARY SERVICES .......................................................................................................... 5

    9 CAPITAL CONTRIBUTIONS ................................................................................................ 5

    10 ACCESS ENQUIRIES.......................................................................................................... 6

    11 APPLICATION PROCEDURE ........................................................................................... 6

    12 FURTHER INFORMATION........................................................... .................................... 6

    13 BIBLIOGRAPHY................................................................................................................. 7

    FIGURE 1 WESTERN POWERS NETWORKS....................................................................... 8

    FIGURE 2 - DISTRIBUTION NETWORK - ASSET DESCRIPTION ......................................... 9

    FIGURE 3 - DISTRIBUTION NETWORK PRICING ZONES................................................... 10

    FIGURE 4 - ACCESS APPLICATION PROCEDURE FLOW CHART..................................... 11

    Picture on front cover: Western Powers Aaron Thiel performing live 33kV insulator change,

    Eastern Goldfields

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    3/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    1

    1 Summary

    The Western Power Corporation (WPC) distribution

    networks became available for open access on 1 July

    1997 in order to facilitate competition in the energyindustry. This provides opportunities for independent

    generators to contract with electricity users by

    utilising WPC distribution and transmission networks,

    and various ancillary services provided by WPC or

    third parties.

    Access to the South-West and Regional distribution

    networks is managed by the Network Services

    Division of WPC (Perth) and access to the North-West

    distribution networks is managed by the Pilbara Power

    Division (Port Hedland).

    The market arrangement is for bilateral contract

    trading between generators and loads. This is in

    contrast to the proposal for the National Electricity

    Market (NEM) in Eastern Australia where all

    electricity will be traded through a pool. In the WA

    arrangement, independent generators seeking access

    must do so in conjunction with contracted associated

    loads.

    The access regime has been developed through

    extensive consultation with the Office of Energy and

    industry representatives. The terms and conditions of

    network access are defined by the ElectricityDistribution Regulations 1997 (Regulations), the

    Distribution Access Technical Code and Planning

    Criteria (Technical Code) and the Electricity

    Distribution Access Pricing and Charges paper

    (Pricing and Charges Paper).

    Both the technical requirements for access and the

    distribution network pricing follow where practical

    the proposals for the National Electricity Market.

    The purpose of this user guide is to outline the

    distribution network open access regime that has beenset in place, and provide details on how to make a

    distribution network access application.

    2 Introduction

    WPC has two separate interconnected distribution

    networks: the South West Interconnected Network and

    the North West Interconnected Network (refer to

    figure 1). A brief outline of each is given below.

    The South West Interconnected Network extends

    from Kalbarri to Albany and across to the Eastern

    Goldfields. It contains 92 zone substations, and

    over 59,000km of high voltage (HV) lines owned

    by WPC.

    The North West Interconnected Network extends

    from Dampier/Karratha to Roebourne/Cape

    Lambert and across to Port Hedland. It contains 7

    zone substations and over 500km of HV linesowned by WPC.

    In addition there are 29 separate (non-interconnected)

    regional networks generally based on regional towns,

    located from Esperance to Kununurra.

    The programme of implementation of access to

    WPCs distribution and transmission networks, as

    determined by the Western Australian State

    Government, is as follows:

    Access to the transmission networks has beenavailable to all users regardless of load size since 1

    January 1997.

    Access to the distribution networks has been

    available to users with an average load of 10MW

    or above since 1 July 1997, and to users with an

    average load of 5MW or above from 1 July 1998.

    Load levels for distribution network access will be

    progressively reduced. The State Governments

    current timetable for further deregulation is:

    1 January 1999 for Regional networks. The

    threshold for access is annual consumption of

    300,000 kilowatt hours.

    1 January 2000 - Average load of 1MW or

    above;

    3 Market Arrangements in

    Western Australia

    Network access in Western Australia is via acontractual arrangement with Users of the network

    and WPC via an access agreement. A User of the

    network is the party to the access agreement with

    WPC and can be either a generator or a load

    connected to the network, or a third party trader, and

    includes the Retail Division of WPC.

    Where generators and loads are located on different

    distribution networks joined by the transmission

    network; there is a requirement to contract for

    transmission as well as distribution access services.

    Generators and associated loads will be required to

    balance energy injected to and taken from the

    network.

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    4/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    2

    In addition, generators will be required to supply

    additional energy to the system to cover network

    losses. Alternatively a generator will benefit from any

    reduction in network losses should their generation

    create a net reduction in system losses. Unless

    otherwise arranged, there should be zero net

    interchange of energy with Western Power.

    Users may contract to purchase standby power from

    Western Power or other generator Users.

    The methodology for energy balancing, excess

    network usage charges and loss factor determination

    is included in the Electricity Distribution Access

    Regulations 1997. There are worked examples in the

    Pricing and Charges paper to assist in understanding

    the process.

    Users must comply with the technical requirements setout in the Technical Code to ensure that the reliability

    and integrity of the networks are maintained.

    4 General Terms and Conditions

    The terms, conditions, and regulations that form the

    open access regime for the distribution networks in

    Western Australia are set out in the following

    documents:

    Electricity Corporation Act 1994;

    Electricity Distribution Regulations 1997 (the

    Regulations);

    Electricity Distribution Access - Pricing and

    Charges (published each financial year);

    Distribution Technical Code and Planning Criteria

    (Technical Code); and

    Electricity Referee and Dispute Resolution

    Regulations 1997.

    The Electricity Corporation Act 1994 requires WPC to

    provide access to its transmission and distribution

    networks, the manner and timing being prescribed by

    Ministerial order. Section 100 of the Act provides for

    the Governor to make any regulations necessary to

    give effect to the open access regime, in accordance

    with the principles and requirements set out in the

    Act.

    The Electricity Distribution Regulations 1997 provide

    the framework for access to WPCs distribution

    networks. They set out, among other things:

    the application and access procedure;

    confidentiality requirements;

    demand and energy balancing requirements;

    technical regulation provisions (contained in

    the Technical Code); and

    terms and conditions of an access agreement.

    The Pricing and Charges Paper sets out the prices to

    be charged for access. These charges are covered in

    more detail in sections 7 and 8 of this user guide.

    The Technical Code sets out the technical

    requirements applying to the distribution networks

    and users facilities, and the network planning criteria

    to be used when planning reinforcements or

    enhancements to the distribution networks. Furtherdetail is provided in Section 6 of this user guide.

    The Electricity Referee and Dispute Resolution

    Regulations 1997 establish the office of the Electricity

    Referee for resolving disputes regarding transmission

    and distribution access.

    5 Description of Network Assets

    Zone substations provide the interface between the

    transmission and distribution networks.

    The distribution network enables the transportation of

    electricity from the zone substations to customers.

    The principal elements include high voltage overhead

    and underground feeders, control devices such as

    automatic reclosers and other distribution switchgear,

    transformers, and low voltage overhead and

    underground feeders.

    For the purpose of distribution open access, the

    distribution network assets comprise connection assets

    and shared network assets. These are described asfollows:

    Connection Assets: those assets at the point of

    physical interconnection with the distribution

    network that are dedicated to a single user.

    Connection assets for generators are referred to as

    entry assets and for loads they are called exit

    assets.

    Shared Network Assets: all other distribution

    assets in the networks not dedicated to any

    particular customer, but shared to some extent by

    network users. All distribution network assets in

    existence prior to June 1997 are deemed as shared

    assets.

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    5/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    3

    Figure 1 shows the location of WPCs network assets.

    Figure 2 shows in simplified form the principal

    elements of the distribution networks and the

    categorisation of the assets as described above.

    6 Technical Code

    Regulations 28 and 29 of the Electricity Distribution

    Regulations 1997 require WPC to publish a Technical

    Code and Network Planning Criteria. The two are

    published together in the Distribution Technical Code

    and Planning Criteria document. It sets out, among

    other things:

    distribution network performance criteria,

    including network planning criteria;

    technical requirements of users facilities;

    inspection, testing, commissioning, disconnection

    and reconnection requirements;

    power system security requirements;

    metering requirements; and

    schedules of technical information required to

    support an application for access to the network.

    The Regulations require WPC and all users to use all

    reasonable endeavours to comply with the Technical

    Code.

    The requirements of the Technical Code are similar to

    those set out in the National Electricity Code.

    7 Distribution Network Pricing

    The principles used to develop network access pricing

    are similar to those used for the National Electricity

    Market.

    Prices are derived from an annual revenue

    requirement for the network business. This consists

    primarily of asset related charges, reflecting the

    capital intensive nature of the distribution business.

    The distribution network assets are independently

    valued and the financial rate of return is regulated.

    The annual revenue requirement also has an operating

    cost component. This reflects good operating practicebased on industry benchmarking and is scaled from

    year to year using an efficiency factor to reflect

    expected improvements in operating efficiency.

    The revenue requirement is allocated to the network

    components, which are grouped into geographic zones

    to reflect technical and cost structure similarities. A

    cost reflective network price is then calculated foreach zone. These zones are depicted in Figure 3.

    Network pricing is logically based on a Users relative

    utilisation of its part of the shared network. Therefore

    an individual users network price will be based on

    their proposed contract maximum demand and their

    distance from a zone substation.

    Network prices are not included in this publication

    since they are adjusted annually.

    8 Network Charges

    As described in Section 3, a user connected to the

    network will normally have both a distribution and

    transmission access agreement and will pay for access

    to both networks.

    The charges for the provision of distribution access

    services, which a user must pay WPC in respect of

    each of its connections, are summarised below.

    8.1 Description of Charges

    Distribution network access charges consist of the

    following.

    Use of network;

    Common services;

    Metering services;

    Stand-by network access (if applicable);

    Connection services (if applicable); and

    Excess network usage charge.

    These charges are calculated on an annual basis butbilled monthly.

    For regional networks, where no transmission network

    exists, there may be additional charges depending on

    the particular circumstances. These services and their

    related charges, would be negotiated individually and

    could include:

    Energy balancing;

    Excess stand-by generation capacity charge; and

    Ancillary service charges.

    Each of the above charges is described in detail as

    follows:

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    6/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    4

    The use of network charge relates to the

    financing, depreciation and operations and

    maintenance of the distribution network fixed

    assets.

    The common service charge relates to the

    administration of the distribution business and the

    financing and depreciation of non-network fixed

    assets (such as buildings, plant and equipment).

    The metering service chargerelates to the cost of

    provision of metering for both the generator and

    load user.

    The stand-by network access charge is

    applicable if a user requires network access that hewill not normally use. For example, this can occur

    where a user with on-site generation requires

    stand-by from the network when his own generator

    is unavailable.

    The connection service charge is based on the

    connection assets provided. Provision of the

    connection asset is a contestable service that

    means there is no obligation on the user to utilise

    Western Power to provide the asset. However

    Western Power would normally make an offer for

    the connection service that would include a capital

    contribution and an annual charge.

    Excess network usage chargerefers to a network

    charge incurred when the customer exceeds his

    contracted maximum demand.

    Energy balancing chargesare discussed in detail

    in section 8.2.

    The excess stand-by generation capacity charge

    is discussed in detail in section 8.2.

    Ancillary service charges are discussed in detail

    in section 8.3.

    8.2 Energy Balancing

    Customers utilising network access are required to

    have half-hourly demand metering in place. Energy

    balancing is required for each half-hour period so that

    all energy provided to the network by generators is

    reconciled with all energy taken from the network by

    load users and all energy losses on the network.

    Monthly charges are based upon monthly meterreadings and the related balancing and reconciliation

    process. These include:

    Energy balancing charges;

    Excess network usage charge; and

    Excess stand-by generation capacity charge.

    In regional networks, charges that relate to alternative

    generation will frequently not apply because there willgenerally be only one source of generation in place.

    Losses

    Network energy losses cannot be measured. However

    they are calculated utilising transmission and

    distribution loss factors which are determined in

    accordance with the Regulations. They are to be re-

    calculated annually and based on past system

    operating conditions.

    Loss factors are used to determine the half hourly

    energy to be sent out from generators to meet the halfhourly energy usages at the associated load points plus

    system losses.

    Balancing

    Energy balancing is included as part of the

    transmission access agreement for users of the south-

    west and north-west interconnected networks. For

    users the non-interconnected regional networks,

    energy balancing requirements will be included in

    their distribution access agreement.

    The energy balancing charge consists of the

    balancing service charge,the out of balance charge,

    and the half hourly out of balance charge. The

    balancing service charge depends on the number of

    connections involved in the access arrangement. The

    out of balance and half hourly out of balance charges

    depend on energy usage.

    The principles of energy and demand balancing are

    given in Part 4 of the Electricity Distribution Access

    regulations 1997. A practical example is provided in

    the Pricing and Charges Paper.

    As stated earlier, the energy market arrangement

    currently operating in the Western Australian

    distribution open access regime is not based on a

    generator pool system, but on bilateral contracts

    between generators and loads.

    Therefore, network users must use reasonable

    endeavours to ensure that the energy imported at their

    load (exit) points is balanced, after considering losses,

    with the energy exported at their generation (entry)

    points. It is likely that some form of load following

    equipment would need to be installed to achieve this.

    Energy imbalances that occur within a permitted

    tolerance of 3% of the Contract Maximum Demand,

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    7/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    5

    (ie small load following errors), may be settled on an

    energy basis. Where imbalances exceed this

    tolerance, settlement will be on a financial basis at

    published half-hourly seasonal energy rates for the

    interconnected networks and at contracted rates for

    the non-interconnected networks.

    To assure reliability of supply during periods of

    generator maintenance or unplanned outages, users

    are encouraged to contract for the provision of stand-

    by power. This stand-by power, or stand-by

    generation reservation, may be contracted from WPC

    or from any independent generator user.

    Where a users import power demand exceeds its

    generators export power supply by more than its

    stand-by generation reservation it will incur an

    excess stand-by generation capacity charge for

    each kW in excess. This charge can only be appliedonce in every seven days and is applied to the

    maximum demand imbalance occurring during that

    period (called the excess demand period).

    Unlike energy imbalances, there is no permitted

    tolerance for demand imbalances. This provides users

    with a significant incentive to contract for the

    provision of stand-by power.

    8.3 Ancillary Services

    WPC in its role of system operator is responsible formaintaining the quality of supply, and ensuring the

    safe, secure and reliable operation of the power

    system.

    To this end WPC has defined a number of related

    ancillary services:

    Voltage Control;

    Spinning Reserve;

    Post Trip Management; and

    Control System Services.

    Users of transmission networks will pay for ancillary

    services through their transmission access agreement.

    In the case of regional networks that have no

    transmission network and only a single source of

    generation, ancillary services will generally not be

    required. Any requirement for ancillary services by

    the prospective user can be discussed with WPC

    during negotiations for access.

    A full description of ancillary services is contained in

    the Transmission Network Access User Guide.

    9 Capital Contributions

    Up front capital charges may be required as part of the

    process to obtain network access. This capital

    contribution could include:

    Connection service capital charge;

    Shared network augmentation capital charge.

    The connection service capital charge is normally

    the full capital cost for provision of the asset.

    Provision of the connection asset is a contestable

    activity and the prospective user is at liberty to seek

    competitive prices for provision of this service.

    The shared network augmentation capital charge

    relates to augmentation work required to be carried

    out on the shared network to provide the level of

    capacity required for the prospective new user.

    A new user who requires WPC to augment the

    network will be required to make a capital

    contribution if the necessary capital investment is not

    commercially viable for WPC.

    The investment is commercially viable for WPC if:

    WPC can recover within a reasonable time the

    costs, the capital investment and a reasonable rate

    of return without increasing the charges payable by

    the existing users; and

    WPC has sufficient allocated capital funds to

    undertake the augmentation.

    The reasonable time, which is limited to 15 years, is

    determined based on:

    the expected commercial life of the augmentation;

    the potential future use of the augmentation by

    existing and potential users; and

    the financial viability of the applicant and the

    applicants business.

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    8/13

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    9/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    7

    13 Bibliography

    1. Electricity Corporation Act 1994.

    2.Electricity Distribution Access regulations 1997(as amended).

    3. Electricity Referee and Dispute ResolutionRegulations 1997.

    4. Western Power Corporation, ElectricityDistribution Access - Pricing and Charges - July

    1998.

    5. Western Power Corporation, Distribution

    Technical Code and Planning Criteria .

    Documents 1, 2 and 3 are available from:

    State Law Publisher

    10 William Street

    PERTH WA 6000

    Telephone: (08) 9321 7688

    Facsimile: (08) 9321 7536

    Documents 4 and 5 are available from the WPC

    contacts listed in Section 11 above.

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    10/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    8

    FIGURE 1 WESTERN POWERS NETWORKS

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    11/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    9

    FIGURE 2 - DISTRIBUTION NETWORK - ASSET DESCRIPTION

    GenLoad

    TransmissionNetwork

    Zone

    Substation

    Zone

    Substation

    Zone

    Substation

    LoadLoad

    Distribution Network

    Gen

    Load

    Gen

    Load

    Gen

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    12/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    10

    FIGURE 3 - DISTRIBUTION NETWORK PRICING ZONES

  • 8/13/2019 Access to Electricity Distribution Networks - A Users Guide 1998

    13/13

    Access To Western Powers Distribution Networks - A Users Guide

    Version 1 - August 1998

    11

    FIGURE 4 - ACCESS APPLICATION PROCEDURE FLOW CHART

    R E S P O N S I B I L I T Y

    APPLICANT WESTERN POWER

    1. Formulate proposal.

    2. Submit access application

    with optional request for

    preliminary assessment.

    3. Prepare written response to

    access application. Response

    to be provided within 20

    business days (unless further

    information requested by

    Western Power).Response to include:

    Time for preliminary

    assessment

    Time to make access offer

    Estimated costs.

    4. If a preliminary assessment is

    required, prepare report within

    time specified in response;

    otherwise prepare access offer

    within period specified in

    response (unless further

    information requested by

    Western Power).

    5. Prepare access offer within

    time specified (unless furtherinformation requested by

    Western Power).6. Accept access offer

    within 20 business days

    or such longer period as

    is agreed.7. Finalise access agreement.

    NOTE: The process shown in this flow chart is in simplified form, is for illustrative

    purposes only and otherwise has no force or effect. The process and times for

    performing activities are subject to conditions and variations set out in Part 2 ofthe Regulations.