ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job...

19
Accelerator Installation Team D.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm ACCELERATOR INSTALLATION SAFETY SUPPORT – Strategy and lessons learned 2 nd BrightnESS Best Practice Workshop – June 13 and 14

Transcript of ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job...

Page 1: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

ACCELERATOR INSTALLATION

SAFETY SUPPORT – Strategy and lessons learned

2nd BrightnESS Best Practice Workshop – June 13 and 14

Page 2: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

In-Kind/Supplier

What are the Personal Protective Equipment required to be on site?

What documentation do I need to fill-in before starting installation activities?

Which kind of training do I need to follow before going on the site?

Who should I contact in case of an incident?

Who is responsible for the safety aspects during installation activities?

Etc…

Main objective of this presentation: provide you with a better understanding of the pre-requisites and instructions before and during installation activities

Recurrent Questions

Page 3: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Picture taken in May 2017

Page 4: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Cryogenic buildings – Helium Compressor Building, Coldbox Building, Cryogenic Transfer Line

Gallery

Accelerator Cryoplant Hall

Pictures taken on 8th June 2017Helium Compressor Building

Cryogenic Transfer Line Gallery Coldbox Building

Page 5: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Klystron Gallery and Test Stand 2

Pictures taken on 8th June 2017

Test Stand 2

Test Stand 2Klystron Gallery

Page 6: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Accelerator Tunnel

Pictures taken in May 2017

Accelerator Tunnel Front-End Building

Stubs

Page 7: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Accelerator Tunnel

1. Marking2. Drilling3. Installation of cooling piping, cable

trays and Grounding bus bar4. Installation of Racks (FEB level 090)5. Installation of Phase Reference Line6. Installation of Ion Source7. Installation of cables, RF waveguides in

Stubs8. Installation of Cooling skids (FEB level

100)

9. Commissioning of the Ion Source10. Installation of RF distribution wall and

Cryogenics Distribution System11. Installation of Warm LINAC12. Installation of Cryomodules and LWU’s

30 consecutive months of installation

Several institutes and companies present on site

Concurrent commissioning and installation

Skanska Construction Site Rules

≈30-50 people at the same time estimated

Main challenges

Page 8: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Vacuum Cryogenics

Project Support &Administration

Director General

RFLINACBeam Physics, Operation and Beam Diagnost

icsSafety

Specialized Technical Services

Machine

ESH Q HR IT GS PS I NI DMSCA T

ES&H and Q Science

Dir

ec

tora

tes

Div

isio

ns

Gro

up

sS

ec

tio

ns

Communications and external relations

L SP&L ICS EIS SA NSS

CF

Engineering Resources

A cc . I n s ta l la t ionM a n a g er

S a fety s u p p o rt

Q A / Q C s u p p ort A rea s u p erv i s ors

Accelerator Installation Team

T ea m a s s i s ta n t

ACCP TMCP TICP CDS

Sy

stem

s

A lso

I n s ta l la t io n S u p p o rt C o o rd in a t io n

E S & H a n d Q E S S S ka n s ka H & S

Page 9: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

AD Safety Group

Involvement in the accelerator installation activities, in collaboration with ES&H and Skanska

Today

Support in the preparation of safety templates (e.g. WSCP, JHA, AHA)

ESS

Participation to the pre-work visit(System Leader, contractor representative, Area

Supervisor, Safety Team)

Coordination of safety training(e.g. BAS-U/P, safety harness, first-aid)

Review of safety documentation (e.g. JHA, AHA, WSCP)

ESSContractor

Soon

Preparation of online training courses

…………………………………

Participation to regular safety inspections on site

Support in the definition of control measures

Safety procedur

esAccelerator Division

ES&H Division

Interface between AD, ES&H and Skanska

ESS-Skanska

Work permit issuing

Page 10: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Work and Safety Coordination Plan (WSCP)

Working hours

GENERAL INFORMATION

Duration of the activity

Contractor information

Regulatory framework

PREPATORY MEASURES

Pre-work visit Organizational measures

Provision of services by ESS

Provision of safety measures by ESS

Description of the installation work

HAZARD IDENTIFICATION & CONTROL MEASURES

Area Hazard Analysis (AHA)

Job Hazard Analysis (JHA)

Control documents

INFORMATION AND TRAINING

ESS-0085649

Safety trainings First aiders Site map

Accident/incident reporting

Status: released on May 3rd, 2017

Page 11: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Review and Approval of the safety documentation

Area supervisor

Accelerator Division

Group leader

System leader

Safety

representative

OK OK OK

ES&H Division

Safety

representative

OK

OK

Skanska

Safety

representative

OK

Page 12: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Good progress in the preparation of documentation

ESS-0093892 ESS-0093460

Page 13: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Accident/incident reporting templates

(temporary)

(temporary)ESS-0093892

Page 14: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Area Hazard Analyses (G01, G02 & G04)

ESS-0105581

ESS-0105616

ESS-0104828

Cryo buildings

Accelerator Tunnel

Klystron Gallery

Page 15: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Safety Training Matrix

Training

Purpose

HS site

Induction

Site

orientation

training at

gate

Safe lifting

(slinging/rig

ging)

Hot work

training

Fall

protection

and rescue

training

(with

harness)

High voltage

Electrical

awareness,

ESA 14

MEWP

(Scissor lift,

Skylift, Boom

lift)

First Aid

course

(1 per

working

team)

Forklift

truck

training

Crane

operator

training for

specific

crane

Access to site X Work on site (general) X X

Access to site with

vehicle/transportX

Performing hot work X XPerforming lifting and

coupling workX X

Accessing energized areas,

high voltageX X

Working on MEWP X X XOperating forklift X X

Operating mobile crane,

overhead crane, etc.X X X

VALIDITY of courses

(duration)- -

-

(Swedish

certificate)

5 years

(Nordic

certificate)

-

(Swedish

certificate)

3 years

(Swedish

certificate)

5 years

(ISO

18878 certific

ate)

3 years

Swedish

BYN or TYA

validation

Swedish

BYN or TYA

validation

Trainings provided by ESS-Skanska on site

Training provided by external companies

Page 16: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Safety trainings organized by AD in 2016/2017

BAS-U/BAS-P Hot WorkSveriges

Byggindustrier

RäddningstjänstenSyd

Safety Harness

Procurator

Use of overhead crane + forklift

Truckverket

First aidRäddningstjänsten

Syd

And many more to come…

Page 17: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Personal Protective Equipment (PPE)

Albert Einstein

MANDATORY

EN 397

EN 166

EN 388

EN ISO 20345

EN 471 Class 2

Page 18: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

Classroom courseRisk specific not defined yet

Safety Induction (1 hour)

Safetyat

ESS site

Self-learningRegulations

Installation Path

Preparation of thesafety documentation

Pre-work visit

ESS

Contractor

Companies and IK-partners

Pre-registration for the ID06

Albert Einstein

Awareness session(30 min)

Waste handling

Submission of the safety documentation

ESSContractor

Day-14

Approval of the safety documentation

System leader

OK

Area supervisor

OK

Safety team

OK

Group leader

OK

Online courseInstallation specific not defined yet

ESS

Contractor

Arrival on site

D-Day

Morning briefings

To be continued…

Personal ProtectiveEquipment

Page 19: ACCELERATOR INSTALLATION SAFETY SUPPORT … Contractor information Regulatory ... Analysis (AHA) Job Hazard Analysis (JHA) Control ... Forklift truck training Crane operator

Accelerator Installation TeamD.Phan, N.Gazis, D.de Wit, M.Green, I.Sjöholm

[email protected]