Ac 10 -Module 6- Standard Costing-Variances-Ans Key

29
PSBA-Manila ACCOUNTING 10 Second Semester SY 2013-2014 Prof. C. Gonzaga TOPIC: STANDARD COSTING SYSTEM/VARIANCE ANALYSIS _______________________________________________________________________ ______________ Terminologies Bill of materials a document that contains information about the product materials components and their specifications (including quality and quantities needed) Budget variance the difference between total actual overhead and budgeted overhead based on standard hours allowed for the production achieved during the period; computed as part of two-variance overhead analysis; also referred to as the controllable variance Controllable variance the budget variance of the two-variance approach to analyzing overhead variances Expected standard a standard set at a level that reflects what is actually expected to occur in the future period; it anticipates future waste and inefficiencies and allows for them; is of limited value for control and performance evaluation purposes Fixed overhead spending variance the difference between the total actual fixed overhead and budgeted fixed overhead; it is computed as part of the four-variance overhead analysis Flexible budget a presentation of multiple budgets that costs according to their behavior at different levels of activity Ideal standard a standard that provides for no inefficiencies of any type; impossible to attain on a continuous basis Labor efficiency variance the number of hours actually worked minus the standard hours allowed for the production achieved multiplied by the standard rate to establish a value for efficiency (favorable) or inefficiency (unfavorable) of the workforce Labor mix variance (actual mix × actual hours × standard rate) minus (standard mix × actual hours × standard rate); it presents the financial effect associated with changing the proportionate amount of higher or lower paid workers in production Labor rate variance the actual rate (or actual weighted average rate) paid to labor for the period minus the standard rate multiplied by all hours actually worked during the period; it is actual labor cost minus (actual hours × standard rate) Labor yield variance (standard mix × actual hours × standard rate) minus (standard mix × standard hours × standard rate); it shows the monetary impact of using more or fewer total hours than the standard allowed Material price variance total actual cost of material purchased minus (actual quantity of material × standard price); it is the amount of money spent below (favorable) or in excess (unfavorable) of the standard price for the quantity of materials purchased; it can be calculated based on the actual quantity of material purchased or the actual quantity used 1

description

Standard Costing

Transcript of Ac 10 -Module 6- Standard Costing-Variances-Ans Key

PSBA-ManilaACCOUNTING 10

Second Semester SY 2013-2014Prof. C. Gonzaga

TOPIC: STANDARD COSTING SYSTEM/VARIANCE ANALYSIS_____________________________________________________________________________________

Terminologies

Bill of materials a document that contains information about the product materials components and their specifications (including quality and quantities needed)

Budget variance the difference between total actual overhead and budgeted overhead based on standard hours allowed for the production achieved during the period; computed as part of two-variance overhead analysis; also referred to as the controllable variance

Controllable variance the budget variance of the two-variance approach to analyzing overhead variances

Expected standard a standard set at a level that reflects what is actually expected to occur in the future period; it anticipates future waste and inefficiencies and allows for them; is of limited value for control and performance evaluation purposes

Fixed overhead spending variance the difference between the total actual fixed overhead and budgeted fixed overhead; it is computed as part of the four-variance overhead analysis

Flexible budget a presentation of multiple budgets that costs according to their behavior at different levels of activity

Ideal standard a standard that provides for no inefficiencies of any type; impossible to attain on a continuous basis

Labor efficiency variance the number of hours actually worked minus the standard hours allowed for the production achieved multiplied by the standard rate to establish a value for efficiency (favorable) or inefficiency (unfavorable) of the workforce

Labor mix variance (actual mix × actual hours × standard rate) minus (standard mix × actual hours × standard rate); it presents the financial effect associated with changing the proportionate amount of higher or lower paid workers in production

Labor rate variance the actual rate (or actual weighted average rate) paid to labor for the period minus the standard rate multiplied by all hours actually worked during the period; it is actual labor cost minus (actual hours × standard rate)

Labor yield variance (standard mix × actual hours × standard rate) minus (standard mix × standard hours × standard rate); it shows the monetary impact of using more or fewer total hours than the standard allowed

Material price variance total actual cost of material purchased minus (actual quantity of material × standard price); it is the amount of money spent below (favorable) or in excess (unfavorable) of the standard price for the quantity of materials purchased; it can be calculated based on the actual quantity of material purchased or the actual quantity used

Material quantity variance (actual quantity × standard price) minus (standard quantity allowed × standard price); the standard cost saved (favorable) or expended (unfavorable) due to the difference between the actual quantity of material used and the standard quantity of material allowed for the goods produced during the period

Material mix variance (actual mix × actual quantity × standard price) minus (standard mix × actual quantity × standard price); it computes the monetary effect of substituting a nonstandard mix of material

Material yield variance (standard mix × actual quantity × standard price) minus (standard mix × standard quantity × standard price); it computes the difference between the actual total quantity of

1

input and the standard total quantity allowed based on output and uses standard mix and standard prices to determine variance

Mix any possible combination of material or labor inputs

Noncontrollable variance the fixed overhead volume variance; it is computed as part of the two-variance approach to overhead analysis

Normal capacity the long-run (5–10 years) average production or service volume of a firm; it takes into consideration cyclical and seasonal fluctuations

Operations flow document a document listing all operations necessary to produce one unit of product (or perform a specific service) and the corresponding time allowed for each operation

Overhead efficiency variance the difference between total budgeted overhead at actual hours and total budgeted overhead at standard hours allowed for the production achieved; it is computed as part of the three-variance analysis; it is the same as variable overhead efficiency variance

Overhead spending variance the difference between total actual overhead and total budgeted overhead at actual hours; it is computed as part of the three-variance analysis; it is equal to the sum of the variable and fixed overhead spending variances

Practical capacity the physical production or service volume that a firm could achieve during normal working hours with consideration given to ongoing, expected operating interruptions

Practical standard a standard that can be reached or slightly exceeded with reasonable effort by workers; it allows for normal, unavoidable time problems or delays and for worker breaks; it is often believed to be most effective in inducing the best performance from workers, since such a standard represents an attainable challenge

Standard cost a budgeted or estimated cost to manufacture a single unit of product or perform a single service

Standard cost card a document that summarizes the direct material, direct labor, and overhead standard quantities and prices needed to complete one unit of product

Standard quantity allowed the quantity of input (in hours or some other cost driver measurement) required at standard for the output actually achieved for the period

Theoretical capacity the estimated maximum production or service volume that a firm could achieve during a period

Total overhead variance the difference between total actual overhead and total applied overhead; it is the amount of underapplied or overapplied overhead

Total variance the difference between total actual cost incurred and total standard cost for the output produced during the period

Variable overhead efficiency variance the difference between budgeted variable overhead based on actual input activity and variable overhead applied to production

Variable overhead spending variance the difference between total actual variable overhead and the budgeted amount of variable overhead based on actual input activity

Variance analysis the process of categorizing the nature (favorable or unfavorable) of the differences between standard and actual costs and determining the reasons for those differences

Volume variance a fixed overhead variance that represents the difference between budgeted fixed overhead and fixed overhead applied to production of the period; is also referred to as the noncontrollable variance

Yield the quantity of output that results from a specified input

Lecture Outline

Development of a Standard Cost System

1. A standard is a benchmark or norm used for planning and control purposes; it is a model or budget against which actual results are compared and evaluated.

2

2. A standard cost system is a product costing system that determines product cost by using standards or norms for quantities and/or prices of component elements; it allows actual costs to be compared against norms for cost control purposes.

A standard cost is a budgeted or estimated cost to manufacture a single unit of product or perform a single service.

Variance Computations

1. A variance is any difference between an actual cost and a standard or budgeted cost.

a. Such a difference is favorable if actual cost is less than standard cost.

b. A variance is unfavorable if actual cost is greater than standard cost.

2. A total variance is the difference between total actual cost incurred and total standard cost for the output produced during the period.

a. A total variance can be computed for each production cost element.

b. Total variances indicate differences between actual and expected production costs, but they do not provide useful information for determining why such differences occurred.

3. Total variances for materials and labor are subdivided into price and usage variances in order to help managers in their control objectives.

a. A price variance reflects the difference between what was actually paid for inputs and what should have been paid for inputs during the period.

b. A usage variance shows the difference between the quantity of actual inputs and the quantity of standard inputs allowed for the actual output of the period. Usage variances focus on the efficiency of results—the relationship of inputs to outputs.

4. The standard quantity allowed is the quantity of input (in hours or some other cost driver measurement) required at standard for the output actually achieved for the period.

Material and Labor Variance Computations

1. The total material usage variance can be subdivided into the material price variance and the material quantity variance.

AP × AQP SP × AQP

Material Material Purchase Price Variance Quantity Variance

Total Material Variance

a. The material price variance (MPV) is the total actual cost of materials purchased minus (actual quantity of materials × standard price); it is the amount of money spent below (favorable) or in excess (unfavorable) of the standard price for the quantity of materials purchased; it can be calculated based on the actual quantity of materials purchased or the actual quantity used.

b. The material purchase price variance is the materials price variance when calculated based on the quantity of materials purchased during the period rather than the quantity of materials used, and is used in what is referred to as the point of purchase material variance model.

c. The material price usage variance is the material price variance when calculated based on the quantity of materials used during the period.

3

d. The material quantity variance (MQV) is the standard cost saved (favorable) or expended (unfavorable) due to the difference between the actual quantity of materials used and the standard quantity of materials allowed for the goods produced during the period; (actual quantity × standard price) minus (standard quantity allowed × standard price).

2. The total labor variance can be subdivided into the labor rate variance and the labor efficiency variance.

AP × AQ SP × AQ SP × SQ

Labor LaborRate Variance Efficiency Variance

Total Labor Variance

a. The labor rate variance (LRV) is the actual rate (or actual weighted average rate) paid to labor for the period minus the standard rate multiplied by all hours actually worked during the period; actual labor cost minus (actual hours × standard rate).

b. The labor efficiency variance (LEV) is the number of hours actually worked minus the standard hours allowed for the production achieved multiplied by the standard rate to establish a value for efficiency (favorable) or inefficiency (unfavorable) of the workforce.

Overhead Variances

1. Capacity refers to any measure of activity.

a. Theoretical capacity is the estimated maximum potential activity for a specified time.

b. Practical capacity is the activity level that could be achieved during normal working hours given unused capacity and ongoing, regular operating interruptions, such as holidays, downtime, and start-up time.

c. Normal capacity is a firm’s long-run average activity (over 5 to 10 years) which gives effect to historical and estimated future production levels and to cyclical and seasonal fluctuations.

d. Expected capacity is a short-run concept representing the anticipated level of the firm for the upcoming annual period.

2. The use of separate variable and fixed overhead rates and accounts allows the calculation of separate variances for each type of overhead, providing managers with maximum detail and optimal flexibility for control and performance evaluation purposes. The use of separate rates permits a four-variance approach to be taken in analyzing overhead.

3. The total variable overhead variance is the difference between actual variable overhead costs incurred for the period and standard variable overhead cost applied to the period’s actual production or service output.

Actual VOH Budgeted VOH Applied VOHAP × AQ SP × AQ SP × SQ

(Price Subvariance) (Usage Subvariance)VOH VOH

Spending Variance Efficiency Variance

Total Variable Overhead Variance(Underapplied or Overapplied Variable Overhead)

4

a. The variable overhead spending variance is the difference between total actual variable overhead and the budgeted amount of variable overhead based on actual hours; it is computed as part of the four-variance analysis.

b. The variable overhead efficiency variance is the difference between budgeted variable overhead based on actual hours and variable overhead applied based on standard hours allowed for the production achieved; it is computed as part of the four-variance analysis.

4. The total fixed overhead variance is the difference between actual fixed overhead costs incurred and standard fixed overhead cost applied to the period’s actual production.

Budgeted FOH Applied FOH Actual FOH (budgeted) SP × SQ

FOHSpending Variance Volume Variance

Total Fixed Overhead Variance(Underapplied or Overapplied Fixed Overhead)

a. The fixed overhead spending variance is the difference between the total actual fixed overhead and budgeted fixed overhead.

b. The fixed overhead volume variance is the difference between budgeted and applied fixed overhead and is equal to the overhead volume variance. The volume variance is also called the noncontrollable variance.

c. To calculate fixed overhead variances, a company must have a flexible budget. A flexible budget is a planning document that presents expected overhead costs at different levels of activity.

d. In a flexible budget, all costs are treated as either variable or fixed; thus, mixed costs must be separated into their variable and fixed elements.

5. A four-variance approach is unworkable if the accounting system does not distinguish between variable and fixed costs.

6. The total overhead variance is the difference between total actual overhead and total applied overhead, and is the only variance computed under the one-variance approach.

Total Applied Overhead(Combined OH Rate × Standard

Input Allowed for ActualTotal Actual Overhead Production)

(Variable OH + Fixed OH) (SP × SQ)

Total Overhead Variance

7. A middle column representing budgeted overhead based on standard quantity is inserted between total actual overhead and total applied overhead under the two-variance approach.

Budgeted OHBased onStandardQuantity

Total Actual OH for Overhead(Variable OH Output Total Applied OH+ Fixed OH) Achieved SP × SQ

5

Budget Variance Volume Variance(Controllable (Noncontrollable

Variance) Variance)

Total Overhead Variance

a. The budget variance is the difference between total actual overhead and budgeted overhead based on standard hours allowed for the production achieved; it is computed as part of the two-variance analysis; it is also referred to as the controllable variance.

b. The volume variance can be computed under the four-variance, three-variance, or two-variance analysis.

8. A column representing budgeted overhead based on actual hours is inserted immediately to the right of total actual overhead under the three-variance approach.

BudgetedOverheadBased onStandard

Budgeted QuantityTotal Actual Overhead Allowed for Total AppliedOverhead Based on Output Overhead

(VOH + FOH) Actual Hours Achieved (SP × SQ)

Overhead Overhead OverheadSpending Efficiency VolumeVariance Variance Variance

Total Overhead Variance

a. The overhead spending variance is the difference between total actual overhead and total budgeted overhead at actual input activity; thus, a flexible budget is required. It is computed as part of the three-variance analysis; it is equal to the sum of the variable and fixed overhead spending variances.

b. The overhead efficiency variance is the difference between total budgeted overhead at actual input activity and total budgeted overhead at standard input allowed (output activity); it is computed as part of the three-variance analysis; it is the same as variable overhead efficiency variance.

Mix and Yield Variances

1. A mix is any possible combination of materials or labor inputs.

2. A yield is the quantity of output that results from a specified input.

3. Material price, mix, and yield variances can be calculated.

a. The material mix variance measures the monetary effect of substituting a nonstandard mix of materials; (actual mix × actual quantity × standard price) minus (standard mix × actual quantity × standard price).

b. The material yield variance is the difference between the actual total quantity of input and the standard total quantity allowed based on output and uses standard mix and standard prices to determine variance; (standard mix × actual quantity × standard price) minus (standard mix × standard quantity × standard price).

4. Labor rate, mix, and yield variances can be calculated.

6

a. The labor mix variance presents the financial effect associated with changing the proportionate amount of higher or lower paid workers in production; (actual mix × actual hours × standard rate) minus (standard mix × actual hours × standard rate).

b. The labor yield variance shows the monetary impact of using more or fewer total hours than the standard allowed; (standard mix × actual hours × standard rate) minus (standard mix × standard hours × standard rate).

CLASS REVIEW PROBLEMS

Problem 1ABC Company has the following information available for the current year:

Standard:Material 3.5 feet per unit @ P2.60 per footLabor 5 direct labor hours @ P8.50 per unit

Actual:Material 95,625 feet used (100,000 feet purchased @ P2.50 per foot)Labor 122,400 direct labor hours incurred per unit @ P8.35 per hour

25,500 units were produced REQUIRED: (1) Compute the material purchase price and quantity variances.

ANSWER: Material price variance:100,000 × $2.50 = $250,000100,000 × $2.60 = 260,000

$ 10,000 F

Material quantity variance:95,625 × $2.60 = $248,62589,250 × $2.60 = 232,050

$ 16,575 U

(2) Compute the labor rate and efficiency variances.

ANSWER: Labor rate variance:122,400 × $8.35 = $1,022,040122,400 × $8.50 = 1,040,400

$ 18,360 F

Labor efficiency variance:122,400 × $8.50 = $1,040,400127,500 × $8.50 = 1,083,750

$ 43,350 F

Problem 2OP Co. applies overhead based on direct labor hours and has the following available for November:

Standard:Direct labor hours per unit 5Variable overhead per DLH P.75Fixed overhead per DLH (based on 8,900 DLHs) P1.90

Actual:Units produced 1,800Direct labor hours 8,900Variable overhead P6,400Fixed overhead P17,500

7

REQUIRED: (1) Compute all the appropriate variances using the two-variance approach.

ANSWER:Actual ($6,400 + $17,500) $23,900

Budget Variance: $240 UBFOH (8,900 × $1.90) $16,910VOH (1,800 × 5 × $.75) 6,750 $23,660

Volume Variance: $190 FApplied OH:(1,800 × 5 × $2.65) $23,850

(2) Compute all the appropriate variances using the three-variance approach.

ANSWER: Actual $23,900

Spending Variance: $315 UFlexible Budget Based on Actual Input BFOH $16,910VOH (8,900 × $.75) 6,675 $23,585

Efficiency Variance: $75 FFlexible Budget Based on Standard DLHsBFOH $16,910VOH (1,800 × 5 × $.75) 6,750 $23,660

Volume Variance: $190 FApplied OH:(1,800 × 5 × $2.65) $23,850

(3) Compute all the appropriate variances using the four-variance approach.

ANSWER: Actual VOH $6,400

Variable Spending Variance: $275 FFlex. Bud. Based on ActualInput Hours (8,900 × $.75) $6,675

Variable Efficiency Variance: $75 FApplied VOH (1,800 × 5 × $.75) $6,750

Actual FOH $17,500FOH Spending Variance: $590 U

BUDGETED FOH $16,910FOH Volume Variance: $190 F

Applied FOH (1,800 × 5 × $1.90) $17,100

Problem 3The Hawaii Co. has made the following information available for its production facility for June 2011. Fixed overhead was estimated at 19,000 machine hours for the production cycle. Actual machine hours for the period were 18,900, which generated 3,900 units.

Material purchased (80,000 pieces) P314,000Material quantity variance P6,400 UMachine hours used (18,900 hours)VOH spending variance P50 UActual fixed overhead P60,000

8

Actual labor cost P40,120Actual labor hours 5,900

Hawaii’s standard costs are as follows:

Direct material 20 pieces @ P4 per pieceDirect labor 1.5 hours @ P6 per hourVariable overhead

(applied on a machine hour basis) 4.8 hours @ P2.50 per hourFixed overhead

(applied on a machine hour basis) 4.8 hours @ P3 per hour

Determine the following items:a. material purchase price varianceb. standard quantity allowed for materialc. total standard cost of material allowedd. actual quantity of material usede. labor rate variancef. standard hours allowed for laborg. total standard cost of labor allowedh. labor efficiency variancei. actual variable overhead incurredj. standard machine hours allowedk. variable overhead efficiency variancel. budgeted fixed overheadm. applied fixed overheadn. fixed overhead spending varianceo. volume variancep. total overhead variance

ANSWER:a. actual material cost $314,000

actual pieces at standard cost (80,000 × $4) 320,000material purchase price variance $ 6,000 F

b. 3,900 units × 20 pieces per unit = 78,000 standard quantity allowed

c. total standard cost of material (78,000 × $4) $312,000

d. standard cost of actual material used$312,000 + $6,400 U quantity variance $318,400$318,400 $4 = 79,600 actual pieces used

e. actual labor cost $40,1205,900 actual DLHs × $6 35,400labor rate variance $ 4,720 U

f. 3,900 units × 1.5 standard hours per unit 5,850 SHA

g. 5,850 SHA × $6 $35,100

h. actual hours × standard rate (from e) $35,400standard cost of labor allowed (from g) 35,100labor efficiency variance $ 300 U

i. actual machine hours × standard VOH rate (18,900 × $2.50) $47,250VOH spending variance 50 Uactual VOH $47,300

j. 3,900 units × 4.8 standard hours per unit = 18,720 MH allowed

k. standard hours allowed (from j) × standard VOH rate

9

(18,720 × $2.50) $46,800actual machine hours × standard rate (from i)

(18,900 × $2.50) 47,250variable overhead efficiency variance $ 450 U

l. 19,000 machine hours × $3 $57,000

m. 3,900 units × 4.8 hours per unit × $3.00 $56,160

n. actual fixed overhead $60,000budgeted fixed overhead (from l) 57,000fixed overhead spending variance $ 3,000 U

o. budgeted fixed overhead (from l) $57,000applied fixed overhead (from m) 56,160volume variance $ 840 U

p. total actual overhead $107,300[$60,000 + $47,300 (from i)]

total applied overhead (18,720 SHA × $5.50) 102,960Total overhead variance $ 4,340 U

Problem 4

The following information is available for Raxco for the current year:

Standard:Material X: 3.0 pounds per unit @ P4.20 per poundMaterial Y: 4.5 pounds per unit @ P3.30 per poundClass S labor: 3 hours per unit @ P10.50 per hourClass US labor: 7 hours per unit @ P8.00 per hour

Actual:Material X: 3.6 pounds per unit @ P4.00 per pound (purchased and used)Material Y: 4.4 pounds per unit @ P3.25 per pound (purchased and used)Class S labor: 3.8 hours per unit @ P10.60 per hourClass US labor: 5.7 hours per unit @ P7.80 per hourRaxco produced a total of 45,750 units.

REQUIRED: (1) Compute the material price, mix, and yield variances (round to the nearest peso).

ANSWER: Standard: X 3.0/7.5 = 40%

Y 4.5/7.5 = 60%

Actual:X 3.6 × 45,750 × $4.00 = $ 658,800Y 4.4 × 45,750 × $3.25 = 654,225

$1,313,025$43,005 F price

Actual × Standard Prices:X 3.6 × 45,750 × $4.20 = $ 691,740Y 4.4 × 45,750 × $3.30 = 664,290

$1,356,030 $16,470 U mix

Standard Qty. × Actual Mix × Standard Prices:X 40% × 366,000* × $4.20 = $ 614,880Y 60% × 366,000 × $3.30 = 724,680

$1,339,560 $83,722 U yield

Standard x Standard:

10

X 40% × 343,125** × $4.20 = $ 576,450Y 60% × 343,125 × $3.30 = 679,388

$1,255,838

*(45,750 × 8 = 366,000)**(45,750 × 7.5 = 343,125)

(2) Compute the labor rate, mix, and yield variances (round to the nearest peso).

ANSWER: Standard:S 3/10 = 30% Actual: S 3.8/9.5 = 40% US 7/10 = 70% US 5.7/9.5 = 60%

Actual × Actual Prices:S 3.8 × 45,750 × $10.60 = $1,842,810US 5.7 × 45,750 × $7.80 = 2,034,045

$3,876,855 $34,770 F rate

Actual × Standard Prices:S 3.8 × 45,750 × $10.50 = $1,825,425US 5.7 × 45,750 × $ 8.00 = 2,086,200

$3,911,625 $108,656 U mix

Standard Qty. × Actual Mix × Standard Prices:S 30% × 434,625* × $10.50 = $1,369,069US 70% × 434,625 × $ 8.00 = 2,433,900

$3,802,969 $200,156 F yield

Standard × Standard:S 30% × 457,500** × $10.50 = $1,441,125US 70% × 457,500 × $ 8.00 = 2,562,000

$4,003,125

*(45,750 × 9.5 = 434,625)**(45,750 × 10 = 457,500)

Problem 5Saksena Corp. produces a product using the following standard proportions and costs of material:

Cost PerPounds Pound Amount

Material A 50 P5.00 P250.00Material B 40 6.00 240.00Material C 60 3.00 180.00

150 4.4667 P670.00Standard shrinkage (33 1/3%) 50 ______Net weight and cost 100 6.70 P670.00

A recent production run yielding 100 output pounds required an input of:

Cost PerAmount Pound

Material A 40 P5.15Material B 50 6.00Material C 65 2.80

11

Required: Material price, mix, and yield variances.

12

ANSWER:

MATERIAL PRICE VARIANCE

MATERIAL A ($5.15 – 5.00) × 40 = $ 6 UMATERIAL B ($6.00 – 6.00) × 50 = 0MATERIAL C ($2.80 – 3.00) × 65 = 13 F

$ 7 F

ACT Q ACT Q STD QACT MIX STD MIX STD MIX

STD P STD P STD P

MIX VARIANCE YIELD VARIANCE

A 40 × $5 = $200 51 2/3 × $5 = $258.33 50 × $5 = $250B 50 × $6 = $300 41 1/3 × $6 = $248.00 40 × $6 = $240C 65 × $3 = $195 62 × $3 = $186.00 60 × $3 = $180

$695 $692.33 $670

$2.67 UNF $22.33 UNF

Problem 6Sample Company began business early in January, 2011, using a standard costing for its single product. With standard capacity set at 10,000 standard productive hours per month, the following standard cost sheet was set up for one unit of product:

Direct material—5 pieces @ P2.00 P10.00Direct labor (variable)—1 sph @ P3.00 3.00 Manufacturing overhead:

Fixed—1 sph @ P3.00 P3.00Variable—1 sph @ P2.00 2.00 5.00

Fixed costs are incurred evenly throughout the year. The following unfavorable variances from standard costs were recorded during the first month of operations:

Material price P 0Material usage 4,000Labor rate 800Labor efficiency 300Overhead volume 6,000Overhead budget (2 variance analysis) 1,000

Required: Determine the following: (a) fixed overhead budgeted for a year; (b) the number of units completed during January assuming no work in process at January 31; (c) debits made to the Work in Process account for direct material, direct labor, and manufactuirng overhead; (d) number of pieces of material issued during January; (e) total of direct labor payroll recorded for January; (f) total of manufacturing overhead recorded in January.

ANSWER:

a. $3 × 10,000 × 12 = $360,000

b. $6,000/$3 = 2,000 under 10,000 – 2,000 = 8,000 units

13

c. DM = 8,000 × $10 = $80,000, DL = 8,000 × $3 = $24000, MOH = 8,000 × $5 = $40,000

d. STD Q = 40,000 (X – 40,000) × $2 = $4,000 unf, X = 42,000 pieces issued

e. $24,000 + $800 + $300 = $25,100

f. $40,000 + $6,000 + $1,000 = $47,000

Problem 7A firm producing one product has a budgeted overhead of P100,000, of which P20,000 is variable. The budgeted direct labor is 10,000 hours.

Required: Fill in the blanks.

a. VolumeProduction Flexible Budget Applied Variance

120% ____________ ____________ ____________

100% ____________ ____________ ____________

80% ____________ ____________ ____________

60% ____________ ____________ ____________

b. What is the budget variance at the 80 percent level if the actual overhead incurred is P87,000?

ANSWER:

TOTAL COST EQUATION = $80,000 FIX + 20,000 ($2) variable10,000 per unit

a. A = $80,000 + (12,000 × $2) = $104,000B = $80,000 + (10,000 × $2) = $100,000C = $80,000 + ( 8,000 × $2) = $ 96,000D = $80,000 + ( 6,000 × $2) = $ 92,000

APPLICATION RATE = $100,000 10,000 UNITS = $10/unit

b. BUDGET VARIANCE = ACTUAL FOH – BUDGETED FOH$9,000 FAV = $87,000 – $96,000

Problem 8Berry Co. manufactures a product effective in controlling beetles. The company uses a standard cost system and a flexible budget. Standard cost of a gallon is as follows:

Direct material:2 quarts of A P144 quarts of B 16

Total direct material P30

Direct labor:2 hours 16

14

Manufacturing overhead 12Total P58

The flexible budget system provides for P50,000 of fixed overhead at normal capacity of 10,000 direct labor hours. Variable overhead is projected at P1 per direct labor hour.

Actual results for the period indicated the following:

Production: 5,000 gallonsDirect material:

A 12,000 quarts purchased at a cost of P7.20/quart; 10,500 quarts used B 20,000 quarts purchased at a cost of P3.90/quart; 19,800 quarts used

Direct labor: 9,800 hours worked at a cost of P79,380Overhead: Fixed P48,100

Variable 21,000Total overhead P69,100

Required: 1. What is the application rate per direct labor hour, the total overhead cost equation, the

standard quantity for each material, and the standard hours?2. Compute the following variances:

a. Total material price varianceb. Total material quantity variancec. Labor rate varianced. Labor efficiency variancee. MOH volume variancef. MOH efficiency varianceg. MOH spending variance, both fixed and variable

ANSWER:

1. App rate = $6/DLHTOHC = $50,000 + $1/DLHStd O (A) 5,000 × 2 = 10,000 (B) 5,000 × 4 = 20,000Std Hrs. 5,000 × 2 = 10,000

2. a. 1. ($7.20 – $7.00) × 12,000 = $2,400 U 2. ($3.90 – $4.00) × 20,000 = 2,000 F

$ 400 U

b. 1. (10,500 – 10,000) × $7.00 = $3,500 U2. (19,800 – 20,000) × $4.00 = 800 F

$2,700 U

c. $79,380 – (9,800 × $8) = $980 U

d. (9,800 – 10,000) × $8 = $1600 F

e. (10,000 – 10,000) × $5 = 0

f. (9,800 – 10,000) × $1 = $200 F

g. Fix Spd $48,100 – $50,000 = $1,900 FVar Spd $21,000 – (9,800 × $1) = $11,200 U

15

MULTIPLE CHOICE

1. A total variance is best defined as the difference between totala. actual cost and total cost applied for the standard output of the period.b. standard cost and total cost applied to production.c. actual cost and total standard cost of the actual input of the period.d. actual cost and total cost applied for the actual output of the period.

2. The term standard hours allowed measuresa. budgeted output at actual hours.b. budgeted output at standard hours.c. actual output at standard hours.d. actual output at actual hours.

3. When computing variances from standard costs, the difference between actual and standard price multiplied by actual quantity used yields a

a. combined price-quantity variance.b. price variance.c. quantity variance.d. mix variance.

4. A company wishing to isolate variances at the point closest to the point of responsibility will determine its material price variance when

a. material is purchased.b. material is issued to production.c. material is used in production.d. production is completed.

5. A company would most likely have an unfavorable labor rate variance and a favorable labor efficiency variance if

a. the mix of workers used in the production process was more experienced than the normal mix.

b. the mix of workers used in the production process was less experienced than the normal mix.

c. workers from another part of the plant were used due to an extra heavy production schedule.

d. the purchasing agent acquired very high quality material that resulted in less spoilage.

6. If actual direct labor hours (DLHs) are less than standard direct labor hours allowed and overhead is applied on a DLH basis, a(n)

a. favorable variable overhead spending variance exists.b. favorable variable overhead efficiency variance exists.c. favorable volume variance exists.d. unfavorable volume variance exists.

7. Which of the following standards can commonly be reached or slightly exceeded by workers in a motivated work environment?

Ideal Practical Expected annuala. no no nob. no yes yesc. yes yes nod. no yes no

8. A company has a favorable variable overhead spending variance, an unfavorable variable overhead efficiency variance, and underapplied variable overhead at the end of a period. The journal entry to record these variances and close the variable overhead control account will show which of the following?

16

VOH spending VOH efficiencyvariance variance VMOH

a. debit credit creditb. credit debit creditc. debit credit debitd. credit debit debit

9. Which of the following are considered controllable variances?

VOH spending Total overhead budget Volumea. yes yes yesb. no no yesc. no yes nod. yes yes no

10. The variance least significant for purposes of controlling costs is thea. material quantity variance.b. variable overhead efficiency variance.c. fixed overhead spending variance.d. fixed overhead volume variance.

11. The variance most useful in evaluating plant utilization is thea. variable overhead spending variance.b. fixed overhead spending variance.c. variable overhead efficiency variance.d. fixed overhead volume variance.

12. A favorable fixed overhead volume variance occurs ifa. there is a favorable labor efficiency variance.b. there is a favorable labor rate variance.c. production is less than planned.d. production is greater than planned.

13. The fixed overhead application rate is a function of a predetermined activity level. If standard hours allowed for good output equal the predetermined activity level for a given period, the volume variance will be

a. zero.b. favorable.c. unfavorable.d. either favorable or unfavorable, depending on the budgeted overhead.

14. Actual fixed overhead minus budgeted fixed overhead equals the a. fixed overhead volume variance.b. fixed overhead spending variance.c. noncontrollable variance.d. controllable variance.

15. Total actual overhead minus total budgeted overhead at the actual input production level equals thea. variable overhead spending variance.b. total overhead efficiency variance.c. total overhead spending variance.d. total overhead volume variance.

16. A favorable fixed overhead spending variance indicates thata. budgeted fixed overhead is less than actual fixed overhead.b. budgeted fixed overhead is greater than applied fixed overhead.c. applied fixed overhead is greater than budgeted fixed overhead.d. actual fixed overhead is less than budgeted fixed overhead.

17

18

17. An unfavorable fixed overhead volume variance is most often caused bya. actual fixed overhead incurred exceeding budgeted fixed overhead.b. an over-application of fixed overhead to production.c. an increase in the level of the finished inventory.d. normal capacity exceeding actual production levels.

18. In a standard cost system, when production is greater than the estimated unit or denominator level of activity, there will be a(n)

a. unfavorable capacity variance.b. favorable material and labor usage variance.c. favorable volume variance.d. unfavorable manufacturing overhead variance.

19. In analyzing manufacturing overhead variances, the volume variance is the difference between thea. amount shown in the flexible budget and the amount shown in debit side of the overhead

control account.b. predetermined overhead application rate and the flexible budget application rate times

actual hours worked.c. budget allowance based on standard hours allowed for actual production for the period

and the amount budgeted to be applied during the period.d. actual amount spent for overhead items during the period and the overhead amount applied

to production during the period.

20. Variance analysis for overhead normally focuses ona. efficiency variances for machinery and indirect production costs.b. volume variances for fixed overhead costs.c. the controllable variance as a lump-sum amount.d. the difference between budgeted and applied variable overhead.

21. Under the two-variance approach, the volume variance is computed by subtracting _________ based on standard input allowed for the production achieved from budgeted overhead.

a. applied overheadb. actual overheadc. budgeted fixed overhead plus actual variable overheadd. budgeted variable overhead

22. The overhead variance calculated as total budgeted overhead at the actual input production level minus total budgeted overhead at the standard hours allowed for actual output is the

a. efficiency variance.b. spending variance.c. volume variance.d. budget variance.

23. A company using very tight (high) standards in a standard cost system should expect thata. no incentive bonus will be paid.b. most variances will be unfavorable.c. employees will be strongly motivated to attain the standards.d. costs will be controlled better than if lower standards were used.

Use the following information for questions 24–27. (Round all answers to the nearest peso.)

The following July information is for Kingston Company:

Standards: Material 3.0 feet per unit @ P4.20 per foot Labor 2.5 hours per unit @ P7.50 per hour

19

Actual: Production 2,750 units produced during the month Material 8,700 feet used; 9,000 feet purchased @ P4.50 per foot Labor 7,000 direct labor hours @ P7.90 per hour

24. What is the material price variance (calculated at point of purchase)?a. 2,700 Ub. 2,700 Fc. 2,610 Fd. 2,610 U

25. What is the material quantity variance?a. 3,105 Fb. 1,050 Fc. 3,105 Ud. 1,890 U

26. What is the labor rate variance?a. 3,480 Ub. 3,480 Fc. 2,800 Ud. 2,800 F

27. What is the labor efficiency variance?a. 1,875 Ub. 938 Uc. 1,875 Ud. 1,125 U

Use the following information for questions 28–32.

Timothy Company has the following information available for October when 3,500 units were produced (round answers to the nearest peso).

Standards:Material 3.5 pounds per unit @ P4.50 per poundLabor 5.0 hours per unit @ P10.25 per hour

Actual:Material purchased 12,300 pounds @ P4.25Material used 11,750 pounds17,300 direct labor hours @ P10.20 per hour

28. What is the labor rate variance?a. 875 Fb. 865 Fc. 865 Ud. 875 U

29. What is the labor efficiency variance?a. 2,050 Fb. 2,050 Uc. 2,040 Ud. 2,040 F

30. What is the material price variance (based on quantity purchased)?a. 3,075 Ub. 2,938 U

20

c. 2,938 Fd. 3,075 F

31. What is the material quantity variance?a. 2,250 Fb. 2,250 Uc. 225 Fd. 2,475 U

32. Assume that the company computes the material price variance on the basis of material issued to production. What is the total material variance?

a. 2,850 Ub. 5,188 Uc. 5,188 Fd. 2,850 F

Use the following information for questions 33–42.

Redd Co. uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for August when Redd made 4,500 units:

Standard:DLH per unit 2.50Variable overhead per DLH P1.75Fixed overhead per DLH P3.10Budgeted variable overhead P21,875Budgeted fixed overhead P38,750

Actual:Direct labor hours 10,000Variable overhead P26,250Fixed overhead P38,000

33. Using the one-variance approach, what is the total overhead variance?a. 6,062.50 Ub. 3,625.00 Uc. 9,687.50 Ud. 6,562.50 U

34. Using the two-variance approach, what is the controllable variance?a. 5,812.50 Ub. 5,812.50 Fc. 4,375.00 Ud. 4,375.00 F

35. Using the two-variance approach, what is the noncontrollable variance?a. 3,125.00 Fb. 3,875.00 Uc. 3,875.00 Fd. 6,062.50 U

36. Using the three-variance approach, what is the spending variance?a. 4,375 Ub. 3,625 Fc. 8,000 Ud. 15,750 U

21

37. Using the three-variance approach, what is the efficiency variance?

a. 9,937.50 Fb. 2,187.50 Fc. 2,187.50 Ud. 2,937.50 F

38. Using the three-variance approach, what is the volume variance?a. 3,125.00 Fb. 3,875.00 Fc. 3,875.00 Ud. 6,062.50 U

39. Using the four-variance approach, what is the variable overhead spending variance?a. 4,375.00 Ub. 4,375.00 Fc. 8,750.00 Ud. 6,562.50 U

40. Using the four-variance approach, what is the variable overhead efficiency variance?a. 2,187.50 Ub. 9,937.50 Fc. 2,187.50 Fd. 2,937.50 F

41. Using the four-variance approach, what is the fixed overhead spending variance?a. 7,000 Ub. 3,125 Fc. 750 Ud. 750 F

42. Using the four-variance approach, what is the volume variance?a. 3,125 Fb. 3,875 Fc. 6,063 Ud. 3,875 U

43. Actual fixed overhead is P33,300 (12,000 machine hours) and fixed overhead was estimated at P34,000 when the predetermined rate of P3.00 per machine hour was set. If 11,500 standard hours were allowed for actual production, applied fixed overhead is

a. P33,300.b. P34,000.c. P34,500.d. not determinable without knowing the actual number of units produced.

44. One unit requires 2 direct labor hours to produce. Standard variable overhead per unit is P1.25 and standard fixed overhead per unit is P1.75. If 330 units were produced this month, what total amount of overhead is applied to the units produced?

a. P990b. P1,980c. P660d. cannot be determined without knowing the actual hours worked

45. Union Company uses a standard cost accounting system. The following overhead costs and production

data are available for August:

22

Standard fixed OH rate per DLH P1Standard variable OH rate per DLH P4Budgeted monthly DLHs 40,000Actual DLHs worked 39,500Standard DLHs allowed for

actual production 39,000Overall OH variance—favorable P2,000

The total applied manufacturing overhead for August should bea. P195,000.b. P197,000.c. P197,500.d. P199,500.

46. Universal Company uses a standard cost system and prepared the following budget at normal capacity for January:

Direct labor hours 24,000Variable OH P48,000Fixed OH P108,000Total OH per DLH P6.50

Actual data for January were as follows:Direct labor hours worked 22,000Total OH P147,000Standard DLHs allowed for

capacity attained 21,000

Using the two-way analysis of overhead variances, what is the controllable variance for January?a. P3,000 Fb. P5,000 Fc. P9,000 Fd. P10,500 U

47. The following information is available from the Tyro Company:Actual OH P15,000Fixed OH expenses, actual P7,200Fixed OH expenses, budgeted P7,000Actual hours 3,500Standard hours 3,800Variable OH rate per DLH P2.50

Assuming that Tyro uses a three-way analysis of overhead variances, what is the overhead spending variance?a. 750 Fb. 750 Uc. 950 Fd. 1,500 U

48. Martin Company uses a two-way analysis of overhead variances. Selected data for the April production activity are as follows:

Actual variable OH incurred P196,000Variable OH rate per MH P6Standard MHs allowed 33,000Actual MHs 32,000

Assuming that budgeted fixed overhead costs are equal to actual fixed costs, the controllable variance for April is

23

a. P2,000 F.b. P4,000 U.c. P4,000 F.d. P6,000 F.

END

24

25