ABC Chemical Complex Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification

Transcript of ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering...

Page 1: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 1

Hazardous Liquid Pipelines

ABC Company

ABC Chemical Complex

Engineering Specification

Page 2: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 2

Hazardous Liquid Pipelines

1.0 SCOPE– Covers the design, materials, fabrication,

construction, inspection, testing, operations, maintenance, and safety aspects of hazardous liquid pipeline systems

– Also covers the components including, but not limited to, pipe, relief devices, valves, fittings, flanges, bolting, gaskets, hangars, and supports.

Page 3: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 3

Hazardous Liquid Pipelines

EXCLUSIONS– Auxiliary piping such as water, air, steam,

lubricating oil, gas, and fuel– Pressure vessels, heat exchangers, pumps,

meters, and other equipment not in scope– Petroleum refinery, natural gasoline, gas

processing, ammonia, carbon dioxide processing, and bulk plant piping covered in the scope of ASME/ANSI B31.3, Plant Piping.

Page 4: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 4

Hazardous Liquid Pipelines

Exclusions (Continued)– Gas transmission and distribution piping

systems covered under ASME/ANSI B31.8– Piping at or below 15 psi– Piping above 15 psi if design temperature is

below -20oF or above 250oF– Design and fabrication of proprietary items of

equipment, apparatus, or equipment

Page 5: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 5

Hazardous Liquid Pipelines

INTENT– Provide engineering specifications for safe

construction, operation, maintenance, and inspection of ABC hazardous liquid pipelines

– Shall meet or exceed the requirements in ASME/ANSI B31.4 and DOT 49CFR195

– Not retroactive for existing pipelines which shall be inspected and tested to the Code used in original design and construction.

Page 6: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 6

Hazardous Liquid Pipelines

3.0 PIPING SYSTEMS DEFINITIONS– General Terms (14)

– Piping Systems (20)

– Pressure Relief Stations and Regulators (3)

– Valves (2)

– Pipe and Piping Terms (2)

– Dimensional Terms (3)

– Mechanical Properties (5)

– Steel Pipe (3)

Page 7: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 7

Hazardous Liquid Pipelines

4.0 DESIGN, FABRICATION, OPERATION, AND TESTING TERMS– Uprating (1)– Pressure Terms (8)– Temperature Terms (3)– Stress Terms (5)

Page 8: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 8

Hazardous Liquid Pipelines

5.0 MATERIALS AND EQUIPMENT– Acceptable Materials and Specifications– Marking– Material Specifications

» Steel Pipe

» Fittings

– Transportation of Line Pipe– Conditions for Reuse of Line Pipe

Page 9: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 9

Hazardous Liquid Pipelines

6.0 WELDING– Welding Terms

– Preparation for Welding» Safe Practices in Cutting and Welding

» Welding Processes and Filler Metal

» Welding Qualifications

» Qualification Records

» Material Limitations

» Welder Requalification Requirements

» Qualification Records (WPS, PQR, Welder)

Page 10: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 10

Hazardous Liquid Pipelines

7.0 Design Conditions– Provides a set of standards covering

» Specifications for, and selection of, equipment and piping components

» Acceptable methods of making branch connections

» Provisions for temperature changes

» Approved methods for support and anchorage of exposed and buried piping systems.

Page 11: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 11

Hazardous Liquid Pipelines

Design Conditions (Continued)– Exclusions

» Pipe Materials (Section 5)» Welding Procedures (Section 6)» Installation and Testing of Piping Systems

– Special Engineering Stresses Not Specifically Covered in Specification

» River crossings, inland coastal water areas, bridges, areas of heavy traffic, long self-supported spans, unstable ground, vibration, earthquake, thermal, etc.

Page 12: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 12

Hazardous Liquid Pipelines

Allowable Stress Values– S = 0.72 x E x SMYS, psi (MPa)

where 0.72 = design factor

E = weld joint factor, normally 1

– Allowable stress values shall be determined for » Used pipe or new/used pipe of unknown or ASTM 120

specifications» Pipe which is cold worked to meet SMYS and reheated

to 600oF or higher shall be 75% of applicable stress value

Page 13: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 13

Hazardous Liquid Pipelines

Allowable Stress Values (Continued)– In shear shall not exceed 45% SMYS– In bearing shall not exceed 90% SMYS– Structural supports and restraints shall not

exceed 66% SMYS– Structural supports and restraints of unknown

piping specifications shall be assigned an SMYS of 24,000 psi or less

Page 14: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 14

Hazardous Liquid Pipelines

Limits of Calculated Stresses Due to Sustained Loads and Thermal Expansion– Internal Pressure Stresses– External Pressure Stresses– Allowable Expansion Stresses– Additive Longitudinal Stresses– Additive Circumferential Stresses Due to

Occasional Loads

Page 15: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 15

Hazardous Liquid Pipelines

Limits of Calculated Stresses Due to Occasional Loads– Operation

» Sum of longitudinal stresses produced by pressure, live and dead loads, and occasional loads, i.e. wind and earthquake shall not exceed 80% SMYS

– Test» Stress due to test conditions are not subject to above

limitations

Page 16: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 16

Hazardous Liquid Pipelines

Limitations on Design Pressure, P– Shall not exceed 85% of mill test pressure– Alternatively, shall not exceed 85% of field test

pressure if mill tests are not available Limitations on SMYS

– Used pipe from Company stock with known specifications may be assigned full S value

– An S value = 24,000 psi shall be assigned to pipe with unknown specifications

Page 17: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 17

Hazardous Liquid Pipelines

Additional Requirements for Nominal Wall Thickness, t– Shall not be reduced to less than 90% of the design

thickness under any circumstances

Allowances– Corrosion (Not required if corrosion controlled)

– Threading and Grooving

– Weld Joint Factors

– Wall Thickness and Defect Tolerances

Page 18: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 18

Hazardous Liquid Pipelines

Straight Pipe Under Internal Pressure– Design wall thickness of steel pipe shall be

calculated by the following equationt = PiD/2S

where Pi=internal design gage pressure

D=outside diameter of pipe, in.

S=applicable allowable stress value, psi

Page 19: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 19

Hazardous Liquid Pipelines

Additional Pressure Design Considerations– Flanges, Reducers, Fittings, Elbows, Bends,

and Intersections– Closures

» Quick Opening Closures» Closure Fittings» Closure Heads» Fabricated Closures» Bolted Blind Flange Connections

Page 20: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 20

Hazardous Liquid Pipelines

Expansion and Flexibility– Means of Providing Flexibility– Amount of Expansion– Properties

» Coefficient of Thermal Expansion

(6.5x10-6in./in./oF)

» Modulus of Elasticity (29x106 psi)

» Poisson’s Ratio (0.3 for steel)

Page 21: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 21

Hazardous Liquid Pipelines

Design of Pipe Supporting Elements Combined Stress Calculations

– Restrained Pipelines– Unrestrained Pipelines– Analysis

» Basic Assumptions and Requirements

Page 22: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 22

Hazardous Liquid Pipelines

8.0 CONSTRUCTION– Construction Specifications

– Inspection Provisions

– Right-of-Way

– Handling, Hauling, Stringing, and Storing

– Damage to Fabricated Items and Pipe

– Ditching

– Welding

– Tie In

Page 23: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 23

Hazardous Liquid Pipelines

CONSTRUCTION (Continued)– Installation of Pipe in Ditch

– Backfilling

– Hot Taps

– Restoration of Right-of-Way and Cleanup

– Special Crossings

– Block and Isolating Valves

– Mainline Valves

– Scraper Traps

Page 24: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 24

Hazardous Liquid Pipelines

CONSTRUCTION (Continued)– Line Markers

– Corrosion Control

– Pump Station, Tank Farm, and Terminal Construction

– Storage and Working Tankage

– Electrical Installations

– Liquid Metering

– Liquid Strainers and Filters

Page 25: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 25

Hazardous Liquid Pipelines

9.0 INSPECTION – General

» Shall assure compliance with material, construction, welding, assembly, and testing requirements of ABC Specifications, ASME/ANSI B31.4 and DOT 49CFR 195

– Qualification of Inspectors» Inspection personnel shall be qualified by training

and experience to the criteria in API 570

Page 26: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 26

Hazardous Liquid Pipelines

Inspection Services– Right-of-way and

grading– Ditching– Line up and pipe

surface inspection– Welding– Coating– Cathodic protection– Tie-in and lowering

– Backfilling & cleanup

– Pressure testing

– Station construction

– River crossings

– Electrical installation

– Radiography

– Corrosion control» external

» internal

Page 27: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 27

Hazardous Liquid Pipelines

Inspection Services– Backfilling & cleanup– Pressure testing– Station construction– River crossings– Electrical installation– Radiography– Corrosion control

» external» internal

Page 28: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 28

Hazardous Liquid Pipelines

Type and Extent of Examination Required– Visual

» Material-mechanical damage

» Permanent records: Location of pipe, wall thickness, type, specification, and manufacturer

– Construction» Surface defects: before coating operation and during

lowering-in and backfilling operations

» Pipe swabbing operation

Page 29: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 29

Hazardous Liquid Pipelines

» Proper alignment and condition of weld joint surface before welding

» Inspect stringer bead for cracks» Remove irregularities on weld cap to prevent

coating damage» Inspect all repairs, changes, or replacements prior to

backfilling operation» Inspect fit of pipe to ditch prior to backfilling» Inspect backfilling operations for quality and

compaction of backfill, placement of material for erosion control, and possible coating damage

Page 30: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 30

Hazardous Liquid Pipelines

» Inspect cased crossings during installation to assure that the carrier pipe is supported, sealed, and insulated from the casing

» Inspect piping components other than pipe to insure damage-free condition and proper installation

Page 31: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 31

Hazardous Liquid Pipelines

Supplementary Types of Examination– Weld inspection and testing

» Complete in accordance with ABC Specs and ASME/ANSI B31.4

– Weld defect and repair» Complete in accordance with ABC Specs and

ASME/ANSI B31.4

– Coatings» Use ABC Specs and ASME/ANSI B31.4

Page 32: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 32

Hazardous Liquid Pipelines

9.2 TESTING– Testing of Fabricated Items

– Testing After New Construction» Systems or Parts of Systems

» Testing Tie-Ins

» Testing Controls and Protective Equipment

– Hydrostatic Testing of Internal Pressure Piping» Hydrotest to 1.25 times the internal design pressure for at least

four (4) hours

» Use API 1110 for guidance in hydrostatic tests

Page 33: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 33

Hazardous Liquid Pipelines

» Treat hydrotest water with a bactericide and corrosion inhibitor

» Relieve excess pressure during the test as required

» Hydrotesting with gas or nonvolatile hydrocarbons is not permitted on ABC projects without written permission from Company management

– Leak Testing» Reduce hydrotest pressure to design pressure and

hold for an additional eight (8) hours

Page 34: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 34

Hazardous Liquid Pipelines

Qualification Tests for Pipe– Visual Examination

– Bending Properties

– Determination of Wall Thickness

– Determination of Weld Joint Factor

– Weldability

– Determination of Yield Strength

– Minimum Yield Strength Value

– Records

Page 35: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 35

Hazardous Liquid Pipelines

10.0 Operation and Maintenance Plans and Procedures

– Written detailed plans and training programs for employees

– Plan for external and internal corrosion control– Written emergency plan– Plan for reviewing changes in conditions

affecting the integrity and safety of the piping system.

Page 36: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 36

Hazardous Liquid Pipelines

– Liaison with local authorities and other pipeline operators to prevent excavation accidents.

– Procedures to analyze all failures and accidents to determine the cause and prevent recurrence.

– Record system to administer the plans and procedures.

– Procedures for abandoning pipelines– Procedures to assure public safety in pipeline

operation and maintenance

Page 37: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 37

Hazardous Liquid Pipelines

– Operation and maintenance of piping systems in conformance with ABC Specifications, ASME/ANSI B31.4, and DOT 49CFR195.

– Plan and procedure modifications as required

Page 38: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 38

Hazardous Liquid Pipelines

10.2 PIPELINE OPERATIONS AND MAINTENANCE

– Operating Pressure» The internal design pressure and pressure rating for

all components shall not be exceeded in steady state operations.

» Pressure rise due to surges shall not exceed the internal design pressure at any point in the piping system by more than 10%.

Page 39: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 39

Hazardous Liquid Pipelines

» Requalification of a piping system is required if a higher operating pressure produces a hoop stress more than 20% SMYS. Requirements in paragraph 456, ASME/ANSI B31.4 shall be followed without exception.

» Derating of a pipeline to a lower operating pressure in lieu of repair or replacement may be completed with the maximum operating pressure determined by paragraph 10.2.7, ABC Specification.

» Codes in effect during original construction shall be consulted for allowable stress and design criteria.

Page 40: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 40

Hazardous Liquid Pipelines

– Communications– Markers– Right-of-Way Maintenance– Patrolling– Pipeline Repairs

» Repairs shall be completed in accordance with ABC Specification, Repair of Pipelines.

» Allowable pipeline repairs and repair methods are summarized in B31.4 and ABC specifications.

Page 41: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 41

Hazardous Liquid Pipelines

Railroads and Highways Crossing Existing Pipelines– Use API 1102 to determine the total stress

caused by internal pressure and external loads. If new external pipe loading exceeds 0.72SMYS, Company will install mechanical reinforcement, suitable protection, or increased pipe thickness.

– Installation of uncased carrier pipe is preferred.

Page 42: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 42

Hazardous Liquid Pipelines

10.3 PUMP STATION, TERMINAL, AND TANK FARM OPERATION AND

MAINTENANCE– Pressure limiting devices, regulators, flow

controllers, relief valves, and other safety devices shall be inspected annually to determine condition and functionality.

– Inspect storage tanks in accordance with API 653.

Page 43: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 43

Hazardous Liquid Pipelines

CORROSION CONTROL EMERGENCY PLAN RECORDS

– Necessary operational data– Pipeline patrol records– Corrosion records as required by B31.4– Records for routine and/or unusual inspections– Pipeline repair records

Page 44: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 44

Hazardous Liquid Pipelines

10.7 QUALIFYING A PIPING SYSTEM FOR A HIGHER OPERATING PRESSURE

– Review initial design and previous testing

– Determine present condition by leak surveys and other field inspections, examination of maintenance and corrosion control records, or other suitable means.

– Complete necessary repairs, replacements, or alterations.

Page 45: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 45

Hazardous Liquid Pipelines

– Maximum steady state operating pressure may be increased after compliance with the previous slide and one of the following provisions:

» If the condition of the pipeline is consistent with the design and hydrotesting has been completed to a test pressure equal to or higher than required for the new steady state operating pressure, the system is approved for the higher operating pressure.

» The system is successfully hydrotested to a test pressure required for the higher operating pressure.

Page 46: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 46

Hazardous Liquid Pipelines

10.8 Abandoning a Piping System– Disconnect all facilities to be abandoned from

all transported sources, i.e., other pipelines, meter stations, control lines, and other equipment.

– Purge all facilities to be abandoned to replace the transported liquid and vapor with an inert material.

– Seal the ends of the piping system.

Page 47: ABC Chemical Complex 1 Hazardous Liquid Pipelines ABC Company ABC Chemical Complex Engineering Specification.

ABC Chemical Complex 47

Hazardous Liquid Pipelines

11.0 CORROSION CONTROL– Scope– External Corrosion Control– Internal Corrosion Control– Pipelines in High Temperature Service– Stress Corrosion and Other Phenomena– Records