ESI Scop ing Study Pro ject Management P lan, Version [1.0]
ESI SCOPING STUDY
PROJECT MANAGEMENT PLAN
Project No : 2
Author : Koko’s Team
Owner : MegITS
Date : 6th May 2014
Version : [1.0]
Status : Final
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 2 o f 28
Document Authors Name Student ID Title
Angga Junaimi 628407 Acting Project Manager
Fajar Aggoro 592300 Acting Subject-matter expert
Piki Pahlisa 591326 Acting Subject-matter expert
Widyanto Eko Nugroho 614571 Acting Subject-matter expert
Version Release History Version Version Description Date of Release
1.0 This is the final version of the Project Management Plan
06/05/2014
Distribution List Name Department/Business Unit Name Department/Business Unit
Jacob Verne MegITS Robert Ops ExGov
Tony Piza MegITS PMO Zoltan Hulls ExGov
Ben Louey MegITS PMO David Riddle Consultant
Song Wu MegaCorp
Approval Signatures Title Name Signature Date
ExGov CEO Hayden Nonce
ExGov GM Operations Robert Ops
MegITS Asia-Pacific Executive Officer-Projects Tony Piza
Project Manager Freda Grill
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 3 o f 28
Table of Contents 1 INTRODUCTION ................................................................. 5
1.1 PURPOSE ......................................................................................................... 5 1.2 BACKGROUND .................................................................................................. 5 1.3 RELATED DOCUMENTS ...................................................................................... 6
2 PROJECT OBJECTIVES AND SCOPE ............................................ 6 2.1 PROJECT OBJECTIVES ....................................................................................... 6 2.2 PROJECT SCOPE ............................................................................................... 6 2.3 PROJECT SUCCESS CRITERIA ............................................................................. 7
3 DELIVERABLES .................................................................. 7 4 APPROACH, SCHEDULE AND TASK PLAN ...................................... 8
4.1 PROJECT APPROACH ......................................................................................... 8 4.2 PROJECT SCHEDULE ......................................................................................... 9
4.2.1 Milestones ............................................................................................... 9 4.2.2 Critical Path ............................................................................................ 9
4.3 STAGE DESCRIPTIONS .................................................................................... 10 4.4 WORK PACKAGE DESCRIPTIONS ...................................................................... 11
5 PROJECT ORGANISATION AND RESOURCE PLAN ........................... 13 5.1 PROJECT ORGANISATION ................................................................................ 13 5.2 RESOURCING PLAN ......................................................................................... 14
6 COST SCHEDULE .............................................................. 18 7 ASSUMPTIONS, CONSTRAINTS, DEPENDENDENCIES ....................... 18
7.1 ASSUMPTIONS ............................................................................................... 18 7.2 DEPENDENCIES .............................................................................................. 18
8 RISKS ......................................................................... 19 9 QUALITY ASSURANCE AND CONTROL ....................................... 21
9.1 QUALITY GOALS ............................................................................................. 21 9.2 QUALITY MANAGEMENT ORGANISATION ........................................................... 21 9.3 QUALITY MANAGEMENT PROCESS .................................................................... 22
10 GOVERNANCE ................................................................. 23 10.1 GOVERNANCE ORGANISATION AND TERMS OF REFERENCE ................................. 23 10.2 SIGN-OFF AND ACCEPTANCE PROCESS ............................................................. 24
11 APPENDIX ..................................................................... 25
List of Tables
Table 1 Project Scope .......................................................................................................... 7 Table 2 Deliverables ............................................................................................................ 8 Table 3 Main tasks and durations .......................................................................................... 9 Table 4 Critical Path ............................................................................................................ 9 Table 5 Correlation between the project stages, deliverables and milestones ............................ 10 Table 6 Resourcing Plan ..................................................................................................... 17 Table 7 Weekly Cost Estimation .......................................................................................... 18 Table 8 Risk Register ......................................................................................................... 20 Table 9 Quality Management Process ................................................................................... 22 Table 10 Governance Organisation ...................................................................................... 23 Table 11 Meeting Arrangement ........................................................................................... 24
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 4 o f 28
Table 12 Sign-off Authority ................................................................................................ 24
List of Figures
Figure 1 ESI Scoping Study Project Summary ......................................................................... 5 Figure 2 Project Organisation.............................................................................................. 13 Figure 3 Quality Management Organization .......................................................................... 21
List of Appendix
Appendix A - Glossary ....................................................................................................... 25 Appendix B – Key Stakeholders .......................................................................................... 25 Appendix C – Detailed Project Schedule ............................................................................... 25 Appendix D – Detailed Costs .............................................................................................. 26 Appendix E - Risk Rating Definition ..................................................................................... 26 Appendix F - Risk Classification Definition ............................................................................ 27 Appendix G - Risk rating for WBS tasks ............................................................................... 27 Appendix H – Details of WBS .............................................................................................. 27
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 5 o f 28
•ESI Project Charter •Megacorp, MegITS and
ExGov skills database •Steering Commitee
considerations •ExGov contracts and key
clients
Inputs
•Interview & observation •Working notes •Briefing & Meeting •Negotiation •Workshop •SME judgment •PMBOK Guide •Gantt Chart
Tools/Methods •ESI Project Manajement Plan
Output
1 I N T R O D U C T I O N 1 . 1 P u r p o s e The purpose of this document is to describe the project management plan (PMP) for conducting
the Scoping Study (SS) of ExGov Systems Integration (ESI) Project. The broad view to manage SS
project will be presented through the elaboration of scope, time, resource, cost, quality and risk
management. This document includes the description of work breakdown structure (WBS) as the
premise for defining a consistent plan across the project’s deliverables, schedule, staff allocation,
budget and risk register. This document also functions as a concession between the project team
and key stakeholders regarding the required effort to realize SS project completion.
1 . 2 B a c k g r o u n d ESI Project Preview
Based on the ESI project charter, the project objectives are to apply corporate standards,
centralized IT governance and efficient business process (BP) in the ExGov working environment
by adopting Megacorp ERP systems and upgrading ExGov IT infrastructure.
SS Project Preview
SS project is a planning phase of the ESI project so that the result of SS is to formulate an ESI
PMP as summarized in Figure 1. SS PMP is required to identify relevant risks in the early stage. As
a subset of ESI project, SS project also considers the authority and expectation of ESI’s key
stakeholders. SS project will provide a comprehensive review of ExGov business processes using
relevant methods for gathering data such as interview, observation, standardized working notes
(checklist). The communication techniques such as briefing, meeting, negotiation and workshop
will be conducted to ensure key stakeholders engagement. The involvement of subject-matter
experts (SME) during the project is an approach to produce a qualified ESI PMP.
Figure 1 ESI Scoping Study Project Summary
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 6 o f 28
1 . 3 R e l a t e d D o c u m e n t s This document must be used in conjunction with the following related documents, where the
information in this document address similar issues in the related documents, then this document
takes precedence:
a. ESI Project Charter as authorized by the Steering Committee
b. ESI Steering Committee minutes of the meeting
c. ExGov contracts, especially the ones that are related to key clients of ExGov and their access
to ExGov legacy systems and/or applications
2 P R O J E C T O B J E C T I V E S A N D S C O P E 2 . 1 P r o j e c t O b j e c t i v e s The aim of the project is to obtain sufficient information to develop the ESI PMP and to socialize the ESI project objectives towards ExGov key staff.
The SS project offers business benefits as follows:
a. Accurate estimation of the required effort to define the ESI project scope, cost, resource and time management.
b. Factual assessment of ExGov IT literacy to define ESI project’s training requirement.
c. Early identification of ESI project’s challenges to reduce the uncertainty that might affect ESI project performance.
d. Increase a positive response from the ExGov staff to support the upcoming ESI project completion.
The SS project will be performed within 6 weeks, commencing from 25 August 2014 to 3 October 2014 with the budget of $223,550.
2 . 2 P r o j e c t S c o p e The SS project scope includes 6 main tasks of work breakdown structure (WBS) to formulate ESI
PMP as described in the Table 2, Reviewing Business Process, Reviewing IT Services Delivery,
Analysing Systems Integration and Developing ESI PMP. The Reviewing BP task will focus on
investigating ExGov business processes affected by ERP modules implementation, namely Finance,
Purchasing, Work Management, Payroll/Timesheeting, Warehousing and Asset Management. This
task will take place in ExGov’s offices within the Victoria State which comprise of Head Office in
Melbourne, Warehouse in Richmond and 3 Regional offices (RO) in Warrnabool (RO1), Melbourne
(RO3) and Albury (RO5). The sampling RO are chosen from 15 ExGov’s Regional offices because
those three represent a full coverage of ExGov‘s business/services.
WBS ID
WBS 1st Level Task Location Coverage
1 Planning Head office SS PMP development
2 Reviewing Business Process
Head office Finance, Purchasing, Payroll, Timesheeting processes
Warehouse Purchasing, Timesheeting, Warehousing, Asset Management processes
RO1 Work Management process
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 7 o f 28
WBS ID
WBS 1st Level Task Location Coverage
RO3 Purchasing and Work Management processes
RO5 Work Management process
3 Reviewing IT Services Delivery
Head office Legacy systems (data, applications and infrastructure) and the transition handling for related technology
4 Analysing Systems Integration
Head office Working notes consolidation and analysis
5 Developing ESI PMP Head office Drafting and finalization of ESI PMP
Table 1 Project Scope
2 . 3 P r o j e c t S u c c e s s C r i t e r i a The success of the project will be defined by the following criteria:
a. Meetings arrangement can be conducted as scheduled that will lead to on time and on budget project performance.
b. The information gathered covers all sampling locations and 100% comply with the checklists and work-packages provided.
c. Increase 30% of positive perception of ESI project across ExGov organization.
3 D E L I V E R A B L E S The following table presents the list of the project deliverables
Deliverable Definition Time Approval Authority Description
ESI SS PMP (Including checklist designed, work-packages and meeting arrangement)
The term of reference for conducting the scoping study of ESI Project.
During the Planning task
Project Management Office (PMO)
- Prepared by Project Manager assisted by an SME.
- Approved if the scope is suitable within the given constraint on budget and time.
BP Review working notes (including checklists filled comments and potential issues which are useful for developing ESI PMP)
The documentation provided by the project team assigned for the data gathering process regarding ExGov business process.
During the Reviewing BP task
Project Manager
- The project team will submit the working notes to to be reviewed by PM.
- As scheduled, PM will check the completeness and adequacy of data gathered .
IT Service Delivery working notes (including checklists filled comments and potential issues which are useful for developing ESI PMP)
The documentation as results of the review of ExGov’s legacy data and application.
During the Reviewing IT Services Delivery task
Project Manager
- The project team will submit the working notes to to be reviewed by PM.
- As scheduled, the PM will check the completeness and adequacy of data gathered.
Technology Transition Plan (TTP)
The documentation as results of the review of ExGov’s legacy IT infrastructure and the effort required to migrate into the new infrastructure.
During the Reviewing IT Services Delivery task
Project Manager
- The specialist assigned will formulate and submit the working notes and TTP to be reviewed by PM.
- As scheduled, the PM will check the completeness and adequacy of data gathered.
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 8 o f 28
Deliverable Definition Time Approval Authority Description
ESI PMP
The final deliverable of the scoping study project that will be used as a guidance to start the ESI Project. It is a result the analysis of business process, IT services delivery and system integration.
During the Developing ESI PMP task
Steering Committee
After completing ESI Scoping Study, the PM will submit the ESI PMP to Steering Committee to be approved.
Table 2 Deliverables
4 A P P R O A C H , S C H E D U L E A N D TA S K P L A N 4 . 1 P r o j e c t A p p r o a c h The project applies the following approaches:
1. One team focuses on one process at each location during the data gathering process. This
approach will allow the project team assigned to gain a comprehensive knowledge of the
corresponding business process. This approach will not require an additional knowledge
sharing throughout the teams so it allows the team members to be assigned to another
data gathering process afterwards.
2. A standardized documentation will be designed and used to capture all related issues that
should be covered in Project Management Planning. This approach will allow the PM to
conduct quality assurance towards the data gathering process in a proper manner and has
an audit trail to the related project team member.
3. The PM will review the work of each team to assess the adequacy of information gathered.
The review is aimed to ensure that the ESI PMP development is supported by sufficient and
qualified information. Considering the time and budget constraint, this review is scheduled
during (not in the end of) the data gathering process. The PM can anticipate the possibility
of gaining more information and this can be provided by the team members in the rest of
the process, thus there is no extension time required to complete the process. In addition,
a SME is also hired to assist the PM in reviewing all information gathered.
4. This project is developed in risk-based awareness environment that will be correspond tasks
describe in WBS. The SS project risk management will comprise of risk identification, risk
analysis and risk response which will be summarized in a risk register matrix with ratings and
classification as defined in Appendix E. This approach will guide the action required to
monitor and control the particular risk. In addition, the risk management plan for the
upcoming ESI project will be designed and performed in the same manner. Tasks performed
on SS project, such as Analysing System Integration and Developing ESI PMP will contribute
to the development of risk management plan as part of ESI PMP.
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 9 o f 28
4 . 2 P r o j e c t S c h e d u l e The project schedule will be summarized in Table 2 while the detail of the schedule will be presented in Appendix C.
Task Start Finish
Planning 18 August 2014 22 August 2014
Reviewing Business Process 25 August 2014 18 September 2014
Reviewing IT Services Delivery 26 August 2014 29 September 2014
Analysing Systems Integration 19 September 2014 23 September 2014
Developing ESI PMP 23 September 2014 03 October 2014
Table 3 Main tasks and durations
4.2.1 Milestones
The project milestones are as follows:
a. Planning Completion : 22 August 2014
b. BP Review Completion : 18 September 2014
c. ESI PMP Sign-off : 3 October 2014
4.2.2 Critical Path The critical path is determined by considering tasks duration, availability of human resources and budget. Critical path reflects the risks entailed on particular tasks. The tasks should be managed carefully to meet time constraints. The list of the project critical path is presented in the following table:
WBS ID Task Start Finish Duration
(days)
1 Planning 18/08/2014 22/08/2014 5
2.3 Reviewing Purchasing Business Process (BP) 26/08/2014 05/09/2014 9
2.4 Reviewing Timesheeting BP 26/08/2014 10/09/2014 12
2.5 Reviewing Work Management BP 26/08/2014 18/09/2014 18
2.6 Reviewing Payroll BP 26/08/2014 15/09/2014 3
2.7 Reviewing Finance BP 26/08/2014 11/09/2014 4
2.9 Reviewing Asset Management BP 04/9/2014 05/09/2014 2
2.10 Reviewing Warehousing BP 08/09/2014 11/09/2014 4
3 Reviewing IT Services Delivery Review 26/09/2014 29/09/2014 25
4 Analyzing Systems Integration 19/09/2014 23/09/2014 3
5 Developing ESI PMP 23/09/2014 03/10/2014 9
Table 4 Critical Path
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 10 o f 28
4 . 3 S t a g e D e s c r i p t i o n s The correlation between the project stages, deliverables and milestones is as follows:
Stage Description Deliverables and
Milestones
Planning PM and two SMEs develop ESI SS PMP by identifying
tasks, resources, budget, time, communication plan and
risks of ESI SS.
Milestone 1:
Planning completion on 22
August 2014
Deliverables:
- The ESI SS PMP
- Checklists
- Work packages
- Meeting arrangement
Executing:
Data Gathering
- Business Analysts (BA) will capture the important data
of ExGov’s current BP in the sampling locations. The
data will be collected through interview, observation
and document review.
- The database experts will identify and analyse the
current ExGov IT data structure and a BA will review
ExGov’s IT service delivery process through interviews
with ExGov’s IT staff, IT document review and
observation.
- The technology Analyst will conduct data gathering
and then analyse the current ExGov’s IT
infrastructure. The data will be collected through
interview with IT staff, document review and
observation.
Milestone 2:
BP review completion on
18 September 2014
Deliverables:
BP Review working notes
Executing:
ESI PMP
Development
The core team consists of a PM and two SME consolidate
and analyse all work notes to define scope, tasks,
resources and risks for the ESI PMP draft then it will be
reviewed by QA specialist.
Rework of ESI PMP draft will be needed to provide the
final draft of ESI PMP. The PM will request approval
from SC and PMO.
Deliverables:
- IT Service Delivery
working notes
- The ESI PMP
Monitoring:
- Monitoring
Deliverables
- Conducting
quality assurance
The PM will monitor the task performance and its
working notes as scheduled during the task
implementation. In addition, the PM and SMEs will
perform quality assurance over each the final deliverable
(the ESI PMP).
Temporary Deliverables:
- working notes review
- the ESI PMP draft
Closing:
Closing Meeting
The meeting scheduled to be held at the end of the
project. It will involve PM, SME and Steering Committee.
Milestone 3:
ESI PMP sign-off on 3
October 2014.
Table 5 Correlation between the project stages, deliverables and milestones
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 11 o f 28
4 . 4 W o r k P a c k a g e D e s c r i p t i o n s The work package for WBS ID 2.2 1st Briefing of BP review Start-end Dates: 25 August 2014 Drop-dead Date: 25 August 2014 Purpose: BAs understand the purposes, requirements and quality of BP review so that BAs able to deliver a good quality data and analysis to produce ESI PMP
Steps/Approach:
1. The core team consists of PM and one SME will make a presentation about ESI SS’s goals and time frame
2. The PM will give information about the quality of data expected for the ESI SS’s data gathering
3. Documents about the checklist and work package (WP) for each BP review in each sample location will be provided by PM for BAs
4. Question and answer session will be provided for BAs in order to accommodate unclear information regarding the data gathering
Resources: 1 PM and 1 SME
Efforts: 3 hours of 4 hours (half day)
The standard to be applied: ESI SS preliminary assessment
Constraints/ Assumption:
1. All BAs are able to attend the briefing 2. All BAs have sufficient knowledge about BP and ERP system 3. All BAs have experiences doing BP reviews
Generic form of the work package for WBS ID 2.3.1 Reviewing BP Start-end Dates: 26 August – 18 September 2014 Drop-dead Date: 18 September 2014 Purpose: To capture data about BP and people associated with that BP in several in ExGov.
Steps/Approach:
1. PA will check availability of the BP key person in each sample offices 2. PA will find an alternative key person, if the first key person is not available in the BP
review time range 3. PA will creates interview schedules for BA 4. BA will study the checklist to understand the requirement data needed 5. BA conduct interviews with the key person 6. BA studies the available BP documentation in that office 7. BA conduct observation for specific BA in that office 8. BA creates work notes to document the information and data acquired from interview,
document review and observation
Resources: A team of BAs for specific BP reviews in all sample locations
Efforts:
1. Purchasing: 18 man-days in 3 locations (6 man-days /location) 2. Timesheeting: 12 man-days in 3 locations (4 man-days /location) 3. Work Management: 36 man-days in 3 locations (12 man-days /location) 4. Payroll: 6 man-days in HQ 5. Finance: 8 man-days in HQ
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 12 o f 28
6. Asset Management: 2 man-days in Warehouse 7. Warehouse: 8 man-days in Warehouse
Standard to be applied:
1. Obtain sufficient data based on the BP review checklist provided. 2. Create work notes that can be understood by other BA and PM 3. Create documentation after finish reviewing each BP in each sample location
Constraints/ Assumptions: all key persons for each BP at each sampling location will be available during ESI SS data gathering period.
The work package for WBS ID 4.2 Identifying Risks
Start-end Dates: 19 August 2014 Drop-dead Date: 23 August 2014 Purpose: To identify and understand all the risks that may influence the quality, duration and budget of the ESI project.
Steps/Approach:
1. Review all collected working notes 2. Identify risks that may arise during the ESI project 3. Estimate the impact of each risk from the brainstorming session 4. Create list order based on the likelihood and the impact of risks on the ESI project 5. Define the relevant risk response and a plan for monitoring
Resources: 1 SME.
Efforts: 2 of 3 days.
The standard to be applied: PMO standard of risk register
Constraints/ Assumption:
1. All data gathering process has finished 2. All work notes from data gathering have been collected 3. All work notes can be understood by SME responsible for the risks.
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 13 o f 28
5 P R O J E C T O R G A N I S AT I O N A N D R E S O U R C E P L A N 5 . 1 P r o j e c t O r g a n i s a t i o n
Figure 2 Project Organisation
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 14 o f 28
5 . 2 R e s o u r c i n g P l a n
Role Responsibility Skills and Knowledge Required Duration Total
Days
Utilization (% of Time)
Rate/ Day ($)
Total Cost ($)
Description
Project Manager
Responsible for developing the Scope Study Plan, managing all tasks and resources, reviewing business process, performing quality control, systems integration analysis and developing ESI PMP
x Project Management Professional (PMP)
x Expertise in planning ERP implementation
x Business IT analytical skills
18/08/2014 – 3/10/2014
35 100% 1,375 48,125 The PM also performs as a Business Analyst on reviewing Payroll and Work Management business process. In addition, PM involves in reviewing IT service delivery.
Subject Matter Expert (SME) 1
Responsible for developing the Scope Study Plan, reviewing business process (timesheeting and payroll), systems integration analysis and developing ESI PMP
x Expertise in planning ERP implementation
x Expertise in ERP-Timesheeting and Payroll Modules
x Business IT analytical skills
x Communication skills
18/08/2014 – 3/10/2014
35 100% 1,500 52,500 The skill required for timesheeting is critical for the scoping study as the skill is not available on another SME’s and BA’s.
SME 2 Responsible for reviewing business process (purchasing and finance), developing ESI PMP
x Expertise in ERP-Purchasing and Finance Management Modules
x Business IT analytical skills
x Communication skills
25/08/2014 – 11/09/2014 and 26/09/2014
15 100% 1,375 20,625 The SME is Melbourne based. If it is not available during the period, BA from Sydney will replace it. Consequently, the costs for salary and allowances will increase.
SME 3 Responsible for data conversion from ExGov
x Data warehousing x Data quality
25/08/2014
6 100% 750 4,500 Supported by two graduates
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 15 o f 28
Role Responsibility Skills and Knowledge Required Duration Total
Days
Utilization (% of Time)
Rate/ Day ($)
Total Cost ($)
Description
legacy systems to Megacorp ERP
x Data conversion and 12/09/2014 – 18/09/2014
SME 4 Responsible for developing ESI PMP and providing quality assurance as Quality Specialist
x Expertise in ERP modules
x Expertise in ERP implementation project
x Quality Assurance Professional
01/10/2014 – 02/10/2014
2 100% 3,125 6,250 Alternatively, if the SME is not available, PM could conduct teleconference with PM’s Singapore-based to examine ESI PMP.
Technology Analyst
Responsible for developing ESI Technology Transition Plan: provide final costings covering infrastructure, support and ERP licenses and seat costs
x Expertise in IT planning x ERP Acquisition x Communication skills
25/08/2014 – 29/09/2014
26 100% 600 15,600 Will be working closely with ExGov’s IT Team so that if the staff is not available, then the task will be performed by ExGov IT Team.
Business Analyst (BA) 1
Responsible for reviewing business process (purchasing and finance)
x Expertise in ERP-Purchasing and Finance Management Modules
x Business IT analytical skills
x Communication skills
25/08/2014 – 11/09/2014
14 100% 1,375 19,250 The BA is Sydney-based, but will be available in Melbourne during the period. Additional allowance might be required for airfares.
BA 2 Responsible for reviewing business process (work management) and systems integration analysis
x Expertise in ERP-Works Management Modules
x Business IT analytical skills
x Communication skills x Documentation skills
25/08/2014 – 18/09/2014 and 22/09/2014 – 23/09/2014
21 100% 750 15,750 The BA is Melbourne based. If it is not available during the period, BA from Sydney will replace it. Consequently, the costs for salary and
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 16 o f 28
Role Responsibility Skills and Knowledge Required Duration Total
Days
Utilization (% of Time)
Rate/ Day ($)
Total Cost ($)
Description
allowances will increase.
BA 3 Responsible for reviewing business process (work management)
x Expertise in ERP-Works Management Modules
x Business IT analytical skills
x Communication skills
13/09/2014 – 18/09/2014
12 100% 1,125 13,500 The BA is Sydney based. It requires additional budget $200ay for daily allowance and $500/week for airfares from Sydney to Melbourne (returns). In addition, the BA will not available during the weekend.
BA 4 Responsible for reviewing business process (asset management and warehousing)
x Expertise in ERP-Asset Management and Warehousing Modules
x Business IT analytical skills
x Communication skills
03/09/2014 – 11/09/2014
7 100% $750 5,250 The BA is Melbourne based. If it is not available during the period of time, it will be replaced by BA from Sydney. Consequently, the costs for salary and allowances will increase.
BA 5 Responsible for reviewing business process (warehousing)
x Expertise in ERP-Asset Management and Warehousing Modules
x Business IT analytical skills
x Communication skills
08/09/2014 – 11/09/2014
4 100% $1,125 4,500 The BA is Sydney based. It requires additional budget $200ay for daily allowance and $500/week for airfares from Sydney to Melbourne (returns). In addition, the BA will not available during the weekend.
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 17 o f 28
Role Responsibility Skills and Knowledge Required Duration Total
Days
Utilization (% of Time)
Rate/ Day ($)
Total Cost ($)
Description
Graduate 1 Responsible to support SME’s and BA’s on the business process review, systems integration analysis and ESI PMP drafting
x Basic project management
x Documentation skills x System analysis x Knowledge of enterprise
systems
26/08/2014 – 04/09/2014 and 19/09/2014 – 25/09/2014
15 100% Free - -
Graduate 2 Responsible to support SME on data conversion
x Basic project management
x Programming
12/09/2014 – 18/09/2014
5 100% Free - -
Graduate 3 Responsible to support SME on data conversion
x Basic project management
x Programming
12/09/2014 – 18/09/2014
5 100% Free - -
Table 6 Resourcing Plan
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp L td 06 May 2014 Page 18 o f 28
6 C O S T S C H E D U L E The total budget for Scoping Study of ESI Project is AU$223, 550 included contingency costs. Most
of budget will be allocated for resource costs such as salary, travel allowance, and airfare
allowance. Travel allowance within Victoria (outside Melbourne CBD) per day is AU$250, airfare
allowance (return) is AU$500, and accommodation allowance for Sydney-based staff per day is
AU$200.
Cost
Estimation Week-1 (18-22 Aug)
Week-2 (25-29 Aug)
Week-3 (1-5 Sep)
Week-4 (8-12 Sep)
Week-5 (15-19 Sep)
Week-6 (22-26 Sep)
Week-7 (29 Sep-3 Oct)
Total
Salary Cost 14,375 35,625 40,500 46,000 27,187.50 20,937.50 21,225 205,850
Travel
Allowance
- 2,000 5,600 4,800 2,800 - - 15,200
Airfare Cost - 500 500 1,000 500 - - 2,500
Total 14,375 38,125 46,600 51,800 30,487.50 20,937.50 21,225 223,550
Table 7 Weekly Cost Estimation
The detail of budget and cost will be presented in Appendix D
7 A S S U M P T I O N S , C O N S T R A I N T S , D E P E N D E N D E N C I E S 7 . 1 A s s u m p t i o n s a. The project fund will be available starting at planning stage
b. Travel allowance will be applicable for project team members who work outside of Head office/Melbourne area. In addition, Sydney-based team members will also get an additional accommodation allowance during their work in Melbourne
c. All project members will be available as scheduled (no one takes leaves at the particular time)
d. Each ExGov’s key personnel has alternate officers as the source of knowledge for data gathering, so that rescheduling of meetings and interviews can be avoided.
e. The 30% of positive perception of the project success criteria is derived from the percentage of the number of involved offices (5) to the total number of ExGov offices (17).
f. Project team member from ExGov will report the work progress to ExGov’s CIO.
7 . 2 D e p e n d e n c i e s a. The project execution starts after kick off meeting
b. System Integration Analysis task can only be commenced after the completion of BP Review and IT Service Delivery Review tasks
c. The ESI PMP Development task will be commenced after the completion of System Integration Analysis task
d. ESI PMP draft can be finalized after the workshop feedback.
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp L td 06 May 2014 Page 19 o f 28
8 R I S K S The risk register represents the list of risk scenario with its probability, impact and response using root cause analysis and assumption analysis. Root
caused analysis of a risk scenario will formulate the detail of the cause (triggers), while assumption analysis will formulate consideration to determine a
score for each risk and how to address it. Some of the identified risks have already responded during the formulation of this document, therefore the list
of risk scenarios shown in the following table are the ones that still caused residual risk that need to be considered, especially the risk that classified as
‘Tiger’ risk:
No Risk Scenario
Possible Trigger(s)
Quantification Risk Response Strategy
(Avoid, Mitigate, Transfer)
Residual Risk Quantification
Probability (score)
Impact (score)
Probability (score)
Impact (score)
Classification (p x i)
1 Project team unavailable to do the assigned task
- Suddenly/ emergency leave
- Health problem - Internal conflict
High (80%)
Unpredicted occurrence of triggers
High (10)
- Increase the
effort to hire new staff
- Fail to finish the project because it is too late to hire staff
- Need to revise the schedule
- Delay of project completion
- Exceed the budget
- Assign each high risk task (Appendix G) to two or more the project team members with the same skills as co-workers and backup.
- Promote negotiation technique to overcome internal conflict
- Set an agreement with personnel providers besides PMO, such as the consultant firm and ExGov, to prepare alternate personnel.
High (80%)
Unpredicted occurrence of triggers
Medium (6)
- Need to
revise the schedule
- Delay of project completion because the high risk tasks will be performed by one personnel or a new one.
- Exceed the budget
Tiger Score: 4.8
Require close monitoring
2 The data gathered is insufficient to support
- Lack of documentation in ExGov offices
- Sampling error
Medium (60%)
Triggers can
Medium (6)
- Reduce the
- Design comprehensive checklist for data gathering by considering recommendations from
Low (25%)
Triggers can
Medium (6)
Initial impacts
Alligator Score: 1.5
Require
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 20 o f 28
No Risk Scenario
Possible Trigger(s)
Quantification Risk Response Strategy
(Avoid, Mitigate, Transfer)
Residual Risk Quantification
Probability (score)
Impact (score)
Probability (score)
Impact (score)
Classification (p x i)
Developing ESI PMP task.
- Inexperienced interviewee
- Inaccurate/ incomplete given information
be predicted quality of deliverables
- Reduce the quality of analysis
the business process owner towards the business process and personnel associated.
- Involve PMO to review the related deliverables
- Establish the subtask of monitoring deliverables in each corresponding business process review.
be controlled because there will be a point of reference for information required and appropriate people.
still applied when the risk occurs.
quality assurance due to its possibility to become ‘Tiger’ risk.
3 Negative perception of ExGov towards upcoming ESI project
- Misconception of the project team about the ESI project
- Miscommunication between the project team and ExGov personnel
High (80%)
Triggers can be easily occurred by rumours spreading
High (10)
- Lack of
support from ExGov key personnel
- Resistance from ExGov workforce
- Fail to finish the project
- Emphasize the importance of partnership environment between the project team and ExGov personnel
- Conduct briefings and meetings for the project team to have the same vision about the SS project and upcoming ESI project so that they can send accurate and positive message about the ESI project to ExGov personnel involved.
Medium (60%)
The occurrence of triggers can be reduced.
High (10)
Initial impacts still applied when the risk occurs.
Tiger Score: 6
Require close monitoring
Table 8 Risk Register
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp L td 06 May 2014 Page 21 o f 28
9 Q U A L I T Y AS S U R A N C E A N D C O N T R O L 9 . 1 Q u a l i t y G o a l s The quality goals for this project are:
1. The ESI SS PMP identifies the scope, cost, tasks, resources and risks to ensure the ESI PMP development will be conducted in the proper manners. The qualified data and analysis of the SS project, ESI PMP will have an accuracy to define scope, tasks, resources, time, and cost so that the ESI project can achieve its objectives..
2. The ultimate goal of the ESI SS project is to ensure the ESI project delivers business benefits as expected by ExGov stakeholders. The ESI SS has role to plan the ESI project so that the ESI project can deliver all the business benefits of an ERP implementation system for ExGov and to provide financial consolidation for Megacorp, because those two benefits are the reasons for conducting the ESI project.
3. The SS ESI project provides valuable inputs so that the ESI project can be delivered on budget and on time. As ExGov is a small company, having an ERP implementation that is off budget and off time will generate great risk to ExGov and will make some of the targeted business goals (cost reduction and financial integration) cannot be achieved.
9 . 2 Q u a l i t y M a n a g e m e n t O r g a n i s a t i o n The ESI project manager will do Quality Assurance (QA) processes. The BA who analyses each process have to submit reports and checklist in each week to the project manager. This following figure illustrates the Quality Management Organisation during the ESI Scoping Study:
Figure 3 Quality Management Organization
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 22 o f 28
9 . 3 Q u a l i t y M a n a g e m e n t P r o c e s s In order to achieve goals of the ESI project, the ESI SS will have several tasks as follows:
Phase Quality Objective
Process/Technique/ Testing to Achieve
Quality
Quality Metric to
Pass
Responsible Party
ESI SS PMP Development
To provide an ESI SS PMP with standards required by the PMO.
Create ESI SS PMP uses standard PMP template provided and get reviewed by the PMO.
The PMO has signed-off the ESI SS PMP.
Project Manager and PMO
Data Gathering (BP review, Technology, and Data conversion)
To ensure all the data gathering processes (BP review, technology review, data structure) are capturing the current BP, people, data and infrastructure, and providing sufficient quality data in order develop a good quality ESI PMP project.
Provide checklist and ensure BAs have done all checklist.
The checklist will identify all BP to be done and data needed for developing ESI PMP
Project Manager
Monitoring deliverables by reviewing all BA’s and technology’s work notes and documentation
Work notes and documentation have sufficiently captured the right BP, IT and data infrastructure.
Project Manager
Hire qualified BAs and assigned those BAs based on their expertise area.
Only hire an expert and experienced BA for specified BP in the ESI SS.
Project Manager
Interview with the right person for each certain area of data gathering
Interview the most knowledgeable person for certain areas of data gathering (BP, technology and data) in the SS time frame
Project Manager
ESI PMP Development
To provide the ESI PMP with standards required by the PMO and clearly define tasks, resources, deliverables, risks, time and budget which favours all key stakeholders.
Create ESI SS PMP uses standard PMP template provided and get reviewed by the PMO.
The PMO has signed-off the ESI PMP.
Project Manager and PMO
Conduct meeting and present the scope and strategy of ESI project, to deliver the targeted business objectives.
SC has approved and signed-off the ESI PMP.
Project Manager
Table 9 Quality Management Process
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 23 o f 28
1 0 G O V E R N A N C E 1 0 . 1 G o v e r n a n c e O r g a n i s a t i o n a n d T e r m s o f R e f e r e n c e In terms of decision-making and project governance, the responsibilities of stakeholders are described as follows:
Stakeholders Responsibilities
Steering Committee (SC)
x Reviewing and approving the scope of ESI SS x Reviewing and approving major deliverables as defined in the scope of
ESI SS x Approving budget allocation x Reviewing and approving any changes of risks, scope, schedule and
budget of ESI SS x Providing policy decisions and solutions for strategic issues x Providing direction and guidance the ESI SS x Participating in project meetings as requested by the Project Manager
Project Manager (PM)
x Reviewing and approving deliverables as defined in the scope of ESI SS
x Reporting progress of the ESI SS to SC, including cost budget performance, risks and project’s status
x Reporting any changes in regard with risks, scope, schedule and budget of ESI SS
x Coordinating all SC members and related stakeholders x Arranging meetings with SC and related stakeholders
MegITS Project Officer
x Providing database of project resources required to support ESI SS x Arranging contracts of the workforce that are hired for ESI SS
Project Management Office (PMO)
x Providing database of project resources required to support ESI SS x Arranging contracts of the workforce that are hired for ESI SS x Providing assurance that the project comply with corporate standards
EXGov Business Process Owner
x Approving deliverables (working notes) that are generated by the project teams
Table 10 Governance Organisation
Meetings arrangement to support the project governance will be conducted on the following dates:
Meetings Purposes
Kick Off Meeting
x To provide a brief description of ESI SS PMP, covering: 9 Project Teams 9 Project Activities & Milestones 9 Project Deliverables & Quality Assurance 9 Project Governance
x To ensure that related stakeholder are aware and engaged with ESI SS x To obtain commitment from the project team, PMO and ExGov
Executives for supporting ESI SS
Meetings with ExGov Key Personnel
x To obtain engagement from related key personnel for supporting ESI SS x To inform the scope of the ESI SS project and the objectives of the
upcoming ESI project
Periodic Meetings
x To deliver the progress and performance of ESI SS x To monitor and evaluate deliverables of ESI SS
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 24 o f 28
x To inform any changes of ESI SS PMP with regard to risks, scope, schedule and budget
Table 11 Meeting Arrangement
1 0 . 2 S i g n - o f f a n d A c c e p t a n c e P r o c e s s In terms of sign-off and acceptance process, the key stakeholders involved are described as follows:
Stakeholders Approval Activities
Steering Committee (SC)
x Approving the ESI SS PMP x Approving the ESI SS deliverables
Project Manager (PM)
x Reporting completion of the ESI SS to SC x Arranging sign-off meetings with SC and related stakeholders
Quality Assurance Specialist
x Providing quality assurance of ESI PMP Final Draft before it is presented to the SC
x Approving the ESI PMP Final Draft
Business Process Owner
x Providing feedback and recommendation in regard with the deliverables (ESI SS PMP) before it is presented to the SC
Table 12 Sign-off Authority
The sign-off and acceptance process will be conducted on Closing Meeting of ESI SS
03/10/2014. The purposes of this meeting are:
x To deliver the completion of ESI SS to the SC
x To monitor and evaluate deliverables of ESI SS
x To inform any changes of ESI SS PMP with regard to risks, scope, schedule and budget
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 25 o f 28
1 1 A P P E N D I X Appendix A - Glossary
Task First level decomposition of Work Breakdown Structure Stage A process of a project management (Initiating, Planning, Executing, Monitoring &
Controlling and Closing) Phase Encapsulation of tasks
Appendix B – Key Stakeholders
Key Stakeholder
Title Responsibility
Executive Sponsor
Megacorp CEO To provide ultimate guidelines based on the corporate strategic goal
Project Sponsor
Megacorp Senior Finance Executive To support the project manager by providing direction and funding
Steering Committee
MegITS CIO, ExGov CEO, MegITS Executive Officer-Projects, Megacorp Senior Finance Executive
To review and monitor the project phases, progress, issues and to approve a certain amount of expenditure.
ExGov Executives
ExGov CEO and CIO To provide insight and resources required to support the project.
Project Manager
Member of MegITS Project Office To manage the project by conducting the project phases.
Project Coordination Team
ExGov General Manager – Operations, ERP Consultant and Megacorp Accountant
To conduct the coordination meeting with steering committee and provide expertise/insight from each organization.
Megacorp IT Services (MegITS)
Megacorp subsidiary which centralises Megacorp IT function
To provide IT resources for the project.
Megacorp Accountant
Personnel of Megacorp Finance Department
To provide financial and accounting expertise to support the implementation of ERP Financial module
ERP Consultant Member of external ERP consulting firm (ERP Professional Services)
To support the Project Manager with ERP expertise within initiating and planning phase
ExGov Users ExGov Managerial/administration staff, Field staff
To test and utilize project outcomes.
Business Process Owner
ExGov Head of operation department
To approve the deliverables that are generated from business process review
Appendix C – Detailed Project Schedule
A02 - Final ESI Project Scope Study.mpp A02 - Final ESI Project Scope Study.pdf
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 26 o f 28
Appendix D – Detailed Costs
No Resource Name
Total Number
of Working
Days
Number of
Working Days
Outside HO
Rate/d ($)
Total Salary
Cost ($)
Total Allowance Cost *)
($)
Total Airfare
Cost ($)
Total Cost ($)
1 Freda Grille 35 6 1,375 48,125 1,500 - 49,625
2 David
Riddle
35 4 1,500 52,500 1,000 - 53,500
3 Song Wu 15 3 1,375 20,625 750 - 21,375
4 Carl Lim 14 3 1,375 19,250 750 500 20,500
5 Mona Liser 21 12 750 15,750 3,000 - 18,750
6 Georgio
Armane
7 6 750 5,250 1,500 - 6,750
7 Arnold
Gate
12 6 1,125 13,500 3,900 1,500 18,900
8 Marvin
Mitch
2 - 3,125 6,250 - - 6,250
9 Craig
Datum
6 - 750 4,500 - - 4,500
10 Fred Turk 26 - 600 15,600 - - 15,600
11 Lisa Mayer 4 4 1,125 4,500 1,800 500 6,800
12 Jason
Briggs
5 - 0 - - - -
13 Jordon
Rivers
5 - 0 - - - -
14 Jenny Fello 15 4 0 - 1,000 - 1,000
Total Cost 205,850 15,200 2,500 223,550
*) for Sydney-based Staff or working Outside HO
Appendix E - Risk Rating Definition
Rating Probability Percentage Impact Score (1-10)
Low Less than 25% likelihood of occurrence
Less than 3 Mild impact on the project
Medium 25%-75% likelihood of occurrence
3-7 Moderate impact on the project with possibility to be a bigger issue for the project
High 76%-100% likelihood of occurrence
8-10 Top priority risk because has significant impact on the project
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 27 o f 28
Appendix F - Risk Classification Definition
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 1 2 3 4 5 6 7 8 9 10
Pro
bab
ility
Impact
Kitten
Puppies Tiger
Aligator
Appendix G - Risk rating for WBS tasks
WBS 2nd Level Task
Number of Man-day
Risk Rating (High risk is over 5 Man-days)
Developing Technology Transation Plan 25 High Reviewing Works Management 12 High Reviewing Finance 8 High Reviewing Warehousing 8 High Reviewing Purchasing 6 High Reviewing Payroll 6 High Reviewing Data Conversion 5 Medium Reviewing Timesheeting 4 Medium IT Service Delivery 4 Medium Reviewing Legacy Applications 3 Low Reviewing Asset Management 2 Low
Appendix H – Details of WBS
WBS ID Task Name
1 Planning 1.1 Identifying Task 1.2 Defining resources required 1.3 Hiring staff 1.4 Developing checklist for Business Process Review 1.5 Arranging appointment 1.6 Drafting ESI SS PMP Milestone 1 Planning Completion 2 Reviewing Business Process (BP) 2.1 Kick Off Meeting
2.2 1st Briefing for BP Review (Purchasing, Financial, Payroll, Timesheeting and Works Management) and IT Services Delivery
2.3 Reviewing Purchasing BP 2.3.1 Gathering data at Head Office 2.3.2 Gathering data at Warehouse 2.3.3 Gathering data at Regional Office (RO) 3
ESI Scop ing Study Pro ject Management P lan, Version [1.0]
Megacorp LTD 6 May , 2014 Page 28 o f 28
WBS ID Task Name
2.3.4 Monitoring deliverables 2.4 Reviewing Timesheeting BP 2.4.1 Gathering data at Head Office 2.4.2 Gathering data at Warehouse 2.4.3 Gathering data at RO 3 2.4.4 Monitoring deliverables 2.5 Reviewing Work Management (WM) BP 2.5.1 Gathering data at RO 1 2.5.2 Gathering data at RO 3 2.5.3 Gathering data at RO 5 2.5.4 Monitoring deliverables 2.6 Reviewing Payroll BP 2.6.1 Gathering data at Head Office 2.7 Reviewing Finance BP 2.7.1 Gathering data at Head Office 2.7.2 Monitoring deliverables 2.8 2nd Briefing for BP Review (Warehousing and Asset Management) 2.9 Reviewing Asset Management (AM) BP 2.9.1 Gathering data at Warehouse 2.9.2 Monitoring deliverables 2.10 Reviewing Warehousing BP 2.10.1 Gathering data at Warehouse 2.10.2 Monitoring deliverables Milestone 2 BP Review Completion 3 Reviewing IT Services Delivery 3.1 Reviewing Data Conversion 3.2 Reviewing Legacy Applications 3.3 Developing Technology Transition Plan 3.4 Monitoring deliverables 4 Analyzing Systems Integration 4.1 Consolidating BP Reviews Documentation 4.2 Identifying risks 4.3 Identifying ESI PMP tasks 5 Developing ESI PMP 5.1 Drafting ESI PMP 5.1.1 Defining scope 5.1.2 Analyzing risks 5.1.3 Defining resources required 5.1.4 Defining quality assurance approach 5.2 Conducting seminar/workshop 5.3 Conducting PMP QA 6 Closing ESI SS Meeting Milestone 3 ESI PMP Sign-Off