A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS)...
-
Upload
darleen-campbell -
Category
Documents
-
view
213 -
download
0
Transcript of A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS)...
![Page 1: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/1.jpg)
A Two-Tier Work Force StrategyA Two-Tier Work Force Strategy
Richard L. TuckerRichard L. Tucker
Center for Construction Industry Studies
(CCIS)
Center for Construction Industry Studies
(CCIS)
CPI Conference 2001
![Page 2: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/2.jpg)
A Two-Tier Work Force StrategyA Two-Tier Work Force Strategy
Richard Tucker
Center for Construction Industry Studies
Richard Tucker
Center for Construction Industry Studies
CPI Conference 2001
![Page 3: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/3.jpg)
AgendaAgenda
• Center for Construction Industry Studies
• Work Force Issues
• The Two-Tier Concept
• Tier II
• A Necessary Element: Metrics
• Path Forward
• Center for Construction Industry Studies
• Work Force Issues
• The Two-Tier Concept
• Tier II
• A Necessary Element: Metrics
• Path Forward
![Page 4: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/4.jpg)
Center for Construction
Industry Studies
Center for Construction
Industry Studies
![Page 5: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/5.jpg)
Center forConstruction Industry Studies
Center forConstruction Industry Studies
• Established in 1996
• Funding from Sloan Foundation
• Strong CII Interface
• Research Thrust Areas
• Established in 1996
• Funding from Sloan Foundation
• Strong CII Interface
• Research Thrust Areas
http://www.ce.utexas.edu/org/ccis/
http://www.ce.utexas.edu/org/ccis/
![Page 6: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/6.jpg)
CCIS Thrust AreasCCIS Thrust Areas
• Fully Integrated and Automated Project Processes (FIAPP)
• Owner/Contractor Work Structure (OCWS)
• Technology (Construction Methods)
• Construction Work Force
• Fully Integrated and Automated Project Processes (FIAPP)
• Owner/Contractor Work Structure (OCWS)
• Technology (Construction Methods)
• Construction Work Force
![Page 7: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/7.jpg)
Work Force IssuesWork Force Issues
![Page 8: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/8.jpg)
Two Tier Concept Evolution
Previous - Many Studies by Many Groups
May 2000 - CCIS Work Force Steering Committee
February 2001 - Tier II Workshop- Tier II Metrics Development
June 2001 - CCIS Work Force Steering Committee (Tier II)
- CII Research Team 182 (Tier I)- CII BM&M (Construction Success)
July 2001 - Tier II Workers Workshop
August 2001 - CII Annual Conference
September 2001 - CPI Conference
Future - Pilot Projects
Previous - Many Studies by Many Groups
May 2000 - CCIS Work Force Steering Committee
February 2001 - Tier II Workshop- Tier II Metrics Development
June 2001 - CCIS Work Force Steering Committee (Tier II)
- CII Research Team 182 (Tier I)- CII BM&M (Construction Success)
July 2001 - Tier II Workers Workshop
August 2001 - CII Annual Conference
September 2001 - CPI Conference
Future - Pilot Projects
![Page 9: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/9.jpg)
Work Force Steering Committee
Dan Bennet NCCER
David Bush Adena Corporation
Keith Byrom Zachry Construction Corp.
Randy Evans BE&K
Ned Givens CII
Ken Hedman Bechtel
Jim Jeffress DuPont
Ted Kennedy BE&K
Doug McCarron United Brotherhood of Carpenters and Joiners of America
Jim Mortell Cherne Contracting Corp.
James Slaughter S&B Engineers and Constructors
Kent Underwood Solutia Inc.
Lowell Wiles Williams Group International
Dan Bennet NCCER
David Bush Adena Corporation
Keith Byrom Zachry Construction Corp.
Randy Evans BE&K
Ned Givens CII
Ken Hedman Bechtel
Jim Jeffress DuPont
Ted Kennedy BE&K
Doug McCarron United Brotherhood of Carpenters and Joiners of America
Jim Mortell Cherne Contracting Corp.
James Slaughter S&B Engineers and Constructors
Kent Underwood Solutia Inc.
Lowell Wiles Williams Group International
![Page 10: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/10.jpg)
Work Force Academic EffortWork Force Academic Effort
Richard TuckerCarl HaasJohn Borcherding
Richard TuckerCarl HaasJohn Borcherding
Bob GloverBill Kelly
Stephen Thomas
Bob GloverBill Kelly
Stephen Thomas
FacultyFaculty
Nicole BalliErin CannonJorge Castañeda-MazaSoon-Woong Chang
Nicole BalliErin CannonJorge Castañeda-MazaSoon-Woong ChangChristine AlemanyRebecca BurlesonLynn Ann CarleyJason EickmannJorge GomarPaul Goodrum
Christine AlemanyRebecca BurlesonLynn Ann CarleyJason EickmannJorge GomarPaul Goodrum
Current Student
s
Current Student
s
Former Student
s
Former Student
s
Derek EdwardLizabeth HowardKamel SaidiDavid Shields
Derek EdwardLizabeth HowardKamel SaidiDavid ShieldsAlexander OeyMike PappasAna Maria RodriguezJulien SaillardAlgernon StanleyKevin Terrien
Alexander OeyMike PappasAna Maria RodriguezJulien SaillardAlgernon StanleyKevin Terrien
![Page 11: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/11.jpg)
Causes, Effect & Solutions
WORKER SHORTAGEWORKER SHORTAGE
Low PayLow PayPoor
EnvironmentPoor
Environment
Poor Career Path
Poor Career Path Transient
NatureTransient
Nature
More MoneyMore Money
Foreign WorkersForeign Workers
Automation/TechnologyAutomation/Technology
Poor ImagePoor
Image
Step Chang
e
Step Chang
e
![Page 12: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/12.jpg)
Causes, Effect & Solutions
WORKER SHORTAGEWORKER SHORTAGE
Low PayLow Pay
Poor Career Path
Poor Career Path
Poor ImagePoor
Image
Step Chang
e
Step Chang
e
![Page 13: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/13.jpg)
Construction Labor Wages
Source: Business Statistics of the United States, Fifth Edition, 1999.
Original sources: U.S. Department of Labor, Bureau of Labor StatisticsU.S. Department of Commerce, Bureau of the Census
Construction vs. Manufacturing Wages 1970-2000Non-supervisory workers. Average hourly wages.
(1982-84=100)
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
1970 1975 1980 1985 1990 1995 2000
Av
era
ge
ho
url
y w
ag
es
(19
82
-84
=1
00
)D
oes
no
t in
clu
de
frin
ge
ben
efit
s
Construction Manufacturing
![Page 14: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/14.jpg)
Industry Image
![Page 15: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/15.jpg)
Industry Image
![Page 16: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/16.jpg)
Industry Image
![Page 17: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/17.jpg)
Initiatives
• Motivation programs
• Incentives
• Day-care centers
• In-house training/ progression programs
• High-performance work teams/worker empowerment
• Prefabrication/ pre-assembly
• Metrics-based productivity
• Motivation programs
• Incentives
• Day-care centers
• In-house training/ progression programs
• High-performance work teams/worker empowerment
• Prefabrication/ pre-assembly
• Metrics-based productivity
• Overtime/expense pay
• Vocational schools/early recruitment
• Information technology usage
• Foreman computer usage
• Career path
• Benefits
• Industry Image
• Recruitment
• Overtime/expense pay
• Vocational schools/early recruitment
• Information technology usage
• Foreman computer usage
• Career path
• Benefits
• Industry Image
• Recruitment
![Page 18: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/18.jpg)
The Two-Tier Concept(A Step Change
Approach)
The Two-Tier Concept(A Step Change
Approach)
![Page 19: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/19.jpg)
Work Force Needs
TimeTime
Work Force Needs
Work Force Needs
TotalTotalTier ITier I
Unstructured
Unstructured
Tier IITier II
![Page 20: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/20.jpg)
Two-Tier Concept
Worker Profile
Tier I Tier II
Workers' Technical Skills Average Above Average
Workers' Management Skills N/A Selected
Career Path N/A Planned
Training Task Oriented Multi-skilled
Management Supervision High Moderate
Crew Flexibility Reduced High
Worker Profile
Tier I Tier II
Workers' Technical Skills Average Above Average
Workers' Management Skills N/A Selected
Career Path N/A Planned
Training Task Oriented Multi-skilled
Management Supervision High Moderate
Crew Flexibility Reduced High
ElementElement
![Page 21: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/21.jpg)
Two-Tier Concept
Tier I Project Approach- Limited worker skills
- Task training
- High level of supervision/management
Tier II Project Approach- Better, fewer workers
- Worker management skills
- HPWT management approach
Tier I Project Approach- Limited worker skills
- Task training
- High level of supervision/management
Tier II Project Approach- Better, fewer workers
- Worker management skills
- HPWT management approach
![Page 22: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/22.jpg)
HypothesisHypothesis
Unstructured
(Current)
Unstructured
(Current)
00 10101010
1010
Construction Phase Success Index
Construction Phase Success Index
Tier IITier IIImplementation
IndexImplementation
Index
Tier ITier IImplementation
IndexImplementation
Index
![Page 23: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/23.jpg)
Concurrent Efforts
CIIBM&M
“ConstructionSuccess”
CIIBM&M
“ConstructionSuccess”
CCIS“Tier II”
CCIS“Tier II”
CIIRT 182“Tier I”
CIIRT 182“Tier I”
![Page 24: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/24.jpg)
Tier I
• More and less skilled workers
• Task training
• Limited craft flexibility
• Shorter individual craft time on a project
• More detailed supervision
• “White collar” administration (planning, purchasing, scheduling, etc.)
• Minimal worker loyalty to firm/project/ industry
• More and less skilled workers
• Task training
• Limited craft flexibility
• Shorter individual craft time on a project
• More detailed supervision
• “White collar” administration (planning, purchasing, scheduling, etc.)
• Minimal worker loyalty to firm/project/ industry
![Page 25: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/25.jpg)
Tier IITier II
![Page 26: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/26.jpg)
Tier II Strategy Objectives
• Comparable or lower costs
• Better quality
• Better safety
• Better schedule
• Better productivity
• More predictability
• Less administration/supervision
• Fewer workers/less turnover on a project
• Higher company/project loyalty
• Less attrition of workers (career path)
• Comparable or lower costs
• Better quality
• Better safety
• Better schedule
• Better productivity
• More predictability
• Less administration/supervision
• Fewer workers/less turnover on a project
• Higher company/project loyalty
• Less attrition of workers (career path)
![Page 27: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/27.jpg)
Typical Worker Activity
30%
Support Work
30%
Support Work
50%
Direct Work
50%
Direct Work
20%
Delays
20%
Delays
Support WorkSupport Work
Direct WorkDirect Work
DelaysDelays
CurrentCurrent Tier IITier II
![Page 28: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/28.jpg)
Tier II Strategy Characteristics
• Higher compensation for workers (wages & duration on site)
• Fewer workers on site (less peak and turnover)
• Different journeyman/helper mix
• Higher worker craft skills (certified)
• Multiskilled workers (certified)
• Administration-skilled workers (certified) (computers, planning, scheduling, controls, etc.)
• Less supervision/higher worker autonomy
• Appropriate management approach (certified)
• Higher compensation for workers (wages & duration on site)
• Fewer workers on site (less peak and turnover)
• Different journeyman/helper mix
• Higher worker craft skills (certified)
• Multiskilled workers (certified)
• Administration-skilled workers (certified) (computers, planning, scheduling, controls, etc.)
• Less supervision/higher worker autonomy
• Appropriate management approach (certified)
![Page 29: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/29.jpg)
How to Accomplish?How to Accomplish?
• Phase in over time
• Pilot projects for Tier I & Tier II strategies
• Assessment/monitoring of effectiveness
•Metrics
• Phase in over time
• Pilot projects for Tier I & Tier II strategies
• Assessment/monitoring of effectiveness
•Metrics
![Page 30: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/30.jpg)
A Necessary Element: Metrics
A Necessary Element: Metrics
![Page 31: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/31.jpg)
Purpose of Metric
• Measure Effectiveness
• Provide Guidance for Implementation
• Measure Effectiveness
• Provide Guidance for Implementation
![Page 32: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/32.jpg)
Expected ResultsExpected Results
Construction Success
Construction Success
Tier II Project Index(Level of Implementation)
Tier II Project Index(Level of Implementation)
00 1010
![Page 33: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/33.jpg)
Tier II Project IndexTier II Project Index
•Necessary Elements
•Quantification
•Necessary Elements
•Quantification
![Page 34: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/34.jpg)
Tier II Project IndexTier II Project Index
Worker Capabilities
Technical Skills 2.0
Management Skills 2.0
Project Execution
Information Technology Utilization 2.0
Craft Utilization 2.0
Organization 2.0
Worker Capabilities
Technical Skills 2.0
Management Skills 2.0
Project Execution
Information Technology Utilization 2.0
Craft Utilization 2.0
Organization 2.0
ValueValue
Maximum Total
Maximum Total
10.010.0
![Page 35: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/35.jpg)
Tier II Project Index
Craft Technical Skills Index* (Max = 2.0)
Craft Certification
Technical Experience
Continuous Training
Craft Technical Skills Index* (Max = 2.0)
Craft Certification
Technical Experience
Continuous Training
* For key crafts
![Page 36: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/36.jpg)
Tier II Project Index
Craft Management Skills Index* (Max = 2.0)
Administrative
Computer
Planning
Job Management
Work Record
Craft Management Skills Index* (Max = 2.0)
Administrative
Computer
Planning
Job Management
Work Record
* For key crafts
![Page 37: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/37.jpg)
Tier II Project Index
Information Technology Utilization Index (Max = 2.0)
Integrated Information Access
Hardware
Information Technology Utilization Index (Max = 2.0)
Integrated Information Access
Hardware
![Page 38: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/38.jpg)
Tier II Project Index
Craft Utilization Index (Max = 2.0)
Crew Mix
Use of Multiskilled Workers
Worker Turnover Ratio
Craft Utilization Index (Max = 2.0)
Crew Mix
Use of Multiskilled Workers
Worker Turnover Ratio
![Page 39: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/39.jpg)
Tier II Project Index
Organization Index (Max = 2.0)
Communications
High Performance Work Place
Organization Index (Max = 2.0)
Communications
High Performance Work Place
![Page 40: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/40.jpg)
Tier II Project IndexTier II Project Index
Worker Capabilities
Technical Skills 2.0
Management Skills 2.0
Project Execution
Information Technology Utilization 2.0
Craft Utilization 2.0
Organization 2.0
Worker Capabilities
Technical Skills 2.0
Management Skills 2.0
Project Execution
Information Technology Utilization 2.0
Craft Utilization 2.0
Organization 2.0
ValueValue
Maximum Total
Maximum Total
10.010.0
![Page 41: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/41.jpg)
Expected ResultsExpected Results
Construction Success
Construction Success
Tier II Project Index(Level of Implementation)
Tier II Project Index(Level of Implementation)
00 1010
![Page 42: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/42.jpg)
Work Force Needs
TimeTime
Work Force Needs
Work Force Needs
TotalTotalTier ITier I
Unstructured
Unstructured
Tier IITier II
![Page 43: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/43.jpg)
Implementation Sessions
Moderator
Randy Evans, BE&K
Moderator
Randy Evans, BE&K
![Page 44: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/44.jpg)
Implementation Sessions
Agenda:
• Elaboration of Two-Tier Concept
• Tier II Elements and Metrics
• Example Demonstration
• Participant Input
Agenda:
• Elaboration of Two-Tier Concept
• Tier II Elements and Metrics
• Example Demonstration
• Participant Input
![Page 45: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/45.jpg)
Your Duty
Come to Implementation
Session
VolunteerPilot Projects
Come to Implementation
Session
VolunteerPilot Projects
![Page 46: A Two-Tier Work Force Strategy Richard L. Tucker Center for Construction Industry Studies (CCIS) Center for Construction Industry Studies (CCIS) CPI Conference.](https://reader034.fdocuments.in/reader034/viewer/2022042821/56649dde5503460f94ad7e9c/html5/thumbnails/46.jpg)
Construction Project Improvement Conference
Construction Industry Institute
Austin, Texas
2001: A Construction Odyssey
Trends and Perspectives
2001: A Construction Odyssey
Trends and Perspectives