[7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

download [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

of 9

Transcript of [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    1/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 1 of 9

    Date : 17. OCT. , 2013

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    PROJECT NO. : 7T04

    PROJECT NAME : ERC Refinery Project

    COMPANY : Egyptian Refining Company (TAKRIR) S.A.E.

    SITE : Mostorod, Egypt

    13 17.OCT, 2013 Revised as Noted S.S.Kim B.G.Min S.M.Hong K.H.Min

    12 15.MAY, 2013 Revised as Noted S.S.Kim B.G.Min S.M.Hong K.H.Min

    11 09.APR, 2013 Revised as Noted S.S.Kim B.G.Min S.M.Hong K.H.Min

    10 10.APR, 2009 Revised as Noted S.S.Kim B.G.Min H.J.Lee S.S.Ahn

    0 25.FEB, 2009 For Approval S.S.Kim B.G.Min H.J.Lee S.S.Ahn

    REV. DATE DESCRIPTION PREPD CHKD CHKD APPR

    (P/M)

    REVD DATE

    CONTRACTOR COMPANY

    SEOUL, KOREA

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    2/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 2 of 9

    Date : 17. OCT. , 2013

    TABLE OF CONTENTS

    1 SCOPE -------------------------------------------------------------------------------- 3

    2 MATERIALS ------------------------------------------------------------------------ 4

    3 GENERAL --------------------------------------------------------------------------- 4

    4 FABRICATION --------------------------------------------------------------------- 4

    5 WELDING --------------------------------------------------------------------------- 5

    6 PREHEATING ---------------------------------------------------------------------- 7

    7 POSTWELD HEAT TREATMENT --------------------------------------------- 8

    8 INSPECTION ----------------------------------------------------------------------- 9

    9 PRESSURE LEAK TESTING ---------------------------------------------------- 9

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    3/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 3 of 9

    Date : 17. OCT. , 2013

    1

    SCOPE

    1.1This Procedure covers the minimum requirements for fabrication, inspection and testing of piping made

    from C-1/2Mo, chromium-molybdenum alloy steels, 12Cr stainless and austenite stainless steels of the 18-8

    type for the ERC Project job site construction, Mostorod, Egypt.

    1.2The SUBCONTRACTOR shall comply with all the specification and procedure requirements unless a

    change or deviation is approved by CONTRACTORs and COMPANYs representative in writing.

    1.3DEFINITION

    - COMPANY ; ERC( Egyptian Refining CO.,) and PMC (Project Management Consultancy; Worley

    Parsons)

    - CONTRACTOR ; GS E & C ( GS Engineering & Construction CO.,)

    - SUBCONTRACTOR ; The Party(s) which carry(s) out all or part of Design, Procurement, Installation,

    and Testing of the piping system as specified by CONTRACTOR.

    1.4RELATED CODES AND SPECIFICATION AND PROCEDURE

    The following code and specification are applicable.

    ASME B31.3 : Process Piping

    ANSI/ASME B 1.20.1 : Pipe Threads, General Purpose

    ASME/ANSI B 16.5 : Pipe Flanges and Flanged Fittings

    ASME Boiler and Pressure Vessel Code, Section V

    7T04-MP-00-TS-004 : Piping Material Specification and classes

    7T04-MP-00-TS-012 : Piping Support

    7T04-MP-00-TS-013 : Fabrication and Installation Detail Drawings for STD Piping

    Support

    7T04-CS-00-TS-001 : Painting

    7T04-CS-00-TS-003 : Pipe Welding and Welding Inspection

    7T04-CS-00-TS-016 : Field Pressure Testing of Piping

    7T04-CS-00-PC-009 : Piping Construction Works

    7T04-CS -00-PC-013 : Piping Pre-Fabrication

    7T04-CS -00-PC-016 : Socket and Seal Welding of Small Piping Component

    7T04-QA -00-PC-007 : Field Inspection and Test plan

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    4/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 4 of 9

    Date : 17. OCT. , 2013

    7T04-QA-00-PC-004 : PMI Procedure

    2 MATERIALS

    2.1All materials shall be as shown on the drawings and specifications. No material substitution shall be made

    without written approval by CONTRACTORs and COMPANYs representative.

    2.2When materials are supplied by the SUBCONTRACTOR, prior to commencement of fabrication, material

    test report, chemical analyses results and material certificates shall be submitted for approval.

    2.3Welding electrodes, filler wire and consumable inserts shall be in accordance with Specification 7T04-CS-

    00-TS-003. Use of non-conforming electrodes must be authorized by CONTRACTOR.

    3 GENERAL

    3.1Alloy piping shall be fabricated, inspected and tested in accordance with ANSI B31.3 Code for Process

    Piping, unless otherwise specified in this Procedure.

    3.2The reference of Procedure Carbon Steel Piping,(7T04-CS-00-PC-008), Piping Construction Works,(7T04-

    CS-00-PC-009) and Specification for Field Pressure Test of Piping,(7T04-CS-00-TS-016), also apply to the

    alloy materials covered by this specification, except as otherwise specified herein.

    3.3Stainless steel Pre-Fabrication including material handing and storing shall be well separated for other steel

    pre-fabrication works. Tool and equipment to be used shall be suitable for stainless steel and shall not be

    used on any other materials.

    4 FABRICATION

    4.1Edge Preparation

    4.1.1 Edge preparation for welding shall be by machine cutting wherever practicable. If flame cutting is

    employed, alloy steels shall be preheated at 149-315 . After cutting, the heat-affected zone shall be

    ground or machined off for a distance not less than 3mm.

    Flame cutting for stainless steel is not allowed.

    13

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    5/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 5 of 9

    Date : 17. OCT. , 2013

    4.1.2

    End preparation of groove for butt welding shall be as shown in Figure 4.1.2

    Figure 4.1.2 Groove Design Tolerances for Use without Consumable Inserts

    4.2Bending

    Neither hot nor cold bending shall be performed on alloy steel or stainless steel piping without special

    written approval by CONTRACTOR and COMPANY. Normally, approved manufactured fittings shall be

    employed in conformance with the piping specifications.

    5 WELDING

    5.1

    Qualification of Welders

    5.1.1 All welders shall be qualified in accordance with Specification 7T04-CS-00-TS-003.

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    6/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 6 of 9

    Date : 17. OCT. , 2013

    5.1.2 When a welder is to be qualified to weld austenitic stainless steels, carbon steel pipe may be used for

    the test, but welding must be done with the same electrodes, filler wire and inserts required for the

    pipe fabrication.

    5.2 Welding Process & Electrodes

    5.2.1 Welding Process and electrodes shall be in accordance with Specification 7T04-CS-00-TS-003.

    5.2.2 Where is no specified for filler wire, it is acceptable use wires or welding rods of the same nominal

    composition as the base material.

    5.2.3 In welding alloy materials with low-hydrogen electrodes, it is essential that electrodes be stored in hot

    boxes and be kept dry at all times. When working on field welds, portable hot boxes shall be used at

    each welding location. Only a few electrodes at a time shall be taken from the hot box for welding.

    5.2.4

    Extreme care shall be taken not to mix up different alloy electrodes. Each portable hot box shallcontain only one type of electrode. Before any alloy electrodes are used approval from

    CONTRACTORs Inspector shall be obtained.

    5.2.5 When alloy electrodes are placed in the large stationery hot box, each type of electrode shall be in its

    original container or in a separate metal box or compartment with the electrode identification clearly

    marked on it.

    5.3 Welding Technique

    5.3.1 When pipe is in the horizontally-fixed position, welding shall be uphill. In GTAW of the first pass, the

    head of the torch shall be positioned perpendicular to the joint, and the arc shall not exceed 3.2mm.

    5.3.2 To start the root pass, the electrode shall be held stationary until a white globule appears on the

    surface of the pool. After this occurs, the torch shall be moved at such a speed as to maintain the white

    bubble at the arc point, generally 50-75mm per min.

    5.3.3

    If the arc is broken while making the root pass, welding shall be started about 2.5mm in back of where

    the weld was terminated to fuse the crater, which normally contains defects.

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    7/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 7 of 9

    Date : 17. OCT. , 2013

    5.3.4

    When completing the root run the white bubble shall be maintained until there is an overlap of about

    6mm from the start of the weld. The bubble must then the welded out of the pool by moving the torch

    towards the side of the prepared joint to the outside wall of the pipe where the arc is broken.

    5.3.5 The argon flow rate for the welding torch shall be sufficient to prevent oxidation and porosity. Good

    protection shall be provided against wind to assure that there is no loss of the shielding gas during

    welding.

    5.4

    Argon Back Purge

    5.4.1 An argon back purge shall be used during GTAW. The pipe shall be scaled for the purge with heavy

    cardboard dams unless otherwise specified. Generally a flow rate of about 4 to 6 liters per minute is

    required. The required amount depends upon the sealing condition. Inadequate purging will result in

    oxidation and a rough appearance of the weld internally, which are not acceptable.

    5.4.2 When GTAW is used for field welds, where it is not practical to purge the entire line, a small opening

    shall be made in the fusible insert at the top of the weld to permit argon purge gas to enter the pipe.The dams shall be positioned prior to fitting up the pipe, and they shall be located about 150mm from

    the weld to prevent burning, melting, or other damage to dams from the heat of welding. Whenever

    preheating is used, this distance should be increased to keep the metal temperature at the dam no

    higher than 150 .

    6 PREHEATING

    6.1Unless otherwise specified, molybdenum or chromium-molybdenum steels and 12Cr stainless steels shall be

    preheated at 200-315 for all welding, includi ng tacking and repair welding. Preheating shall be performed

    by torch heating with propane burners is acceptable provided that the temperature is maintained properly.

    Any preheating shall be applied as all round as possible, avoid hot spot. The preheat temperature shall be

    kept the same as preheating temperature during welding. Thus, when torch heating is used, there must be

    available for each weld either two burners with their own gas supply or one burner connected to a manifold-

    gas-supply system.

    6.2The preheat temperature shall be checked with temperature indicating crayons, such as Tempilsticks. The

    welder or welder's helper shall have the crayons with him at all times during welding, and he shall check the

    temperature frequently to ensure that the preheat temperature requirements are met. In addition, the

    SUBCONTRACTOR shall assign one person the sole responsibility of ensuring that preheat requirements

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    8/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 8 of 9

    Date : 17. OCT. , 2013

    are met at all times. It is essential that preheating be carried out faithfully to avoid cracking and other

    problems which could result in failure.

    7 POSTWELD HEAT TREATMENT

    7.1The post-weld heat treatment shall be in accordance with Specification 7T04-CS-00-TS-003.

    7.2

    Alloy Steels and Ferritic Stainless Steels

    7.2.1 Molybdenum or chromium-molybdenum steels and 12Cr stainless steels shall be heat treated after

    welding, as indicated in ANSI B31.3. Heating and cooling rates shall be 167 maximum per hour

    from, or to 316 .

    7.2.2 Heat treating shall be done with electric resistance or induction coils. The complete heat-treating cycle

    shall be indicated on a chart from a multipoint recorder. For temperature measurements, at least two

    thermo-couples shall be attached to each weld 180 degrees apart using an Inconel-type electrode, suchas Incoweld A, or Inconel filler wire with GTAW.

    7.2.3 Preferably, the welded joint shall be heat treated immediately after welding without allowing the

    metal to cool below the minimum preheat temperature.

    7.2.4 After welding 5Cr-1/2Mo Steel or higher ferritic alloy steels, the weld shall be allowed to cool to the

    200-315 preheat temperature range before final postweld heat treatment is applied.

    7.2.5 When the intermediate treatment is used, temperature indicating crayons shall be used to ensure that

    heating is within the specified range.

    7.2.6 Prior to hydrostatic testing, the full postweld heat treatment shall be performed with exception of

    hydro test vents and drains shall be postweld heat treatment after hydro test.13

    13

  • 8/9/2019 [7T04-CS-00-PC-011] Procedure for Alloy Steel Piping_Rev

    9/9

    CONSTRUCTION PROCEDURE

    FOR

    ALLOY STEEL PIPING

    Doc No : 7T04-CS-00-PC-011

    Rev. : 13

    Page : 9 of 9

    Date : 17. OCT. , 2013

    8

    INSPECTION

    8.1All Non-Destructive Examination shall be in accordance with Specification 7T04-CS-00-TS-003 and

    Reference Procedure 7T04-CS-00-PC-009.

    8.2NDE

    8.2.1 Welds shall be radiographed shall be as specified for specification 7T04-CS-00-TS-003 Table 1 extent

    of NDE of pipe work welds.

    8.2.2 Normally radiographic examination of alloy steels shall be performed after the completion of weldto

    permit repairs to be made prior to the final heat treatment. All repaired areas shall also be

    radiographed.

    8.3Hardness Testing

    The hardness of all alloy steels shall be checked by CONTRACTOR for conformance with ANSI B31.3.The maximum Brinell Hardness of the weld or heat-affected zone shall be 225 for C-1/2Mo and 1-1/4Cr -

    1/2Mo steel and 241 for higher alloy steels.

    8.4PMI (Positive Material Identified)

    8.4.1 PMI shall be performed in accordance with PMI Procedure (7T04-QA-00-PC-004).

    8.4.2 PMI is intended to avoid the risk of receiving incorrect materials and missing material in fabrication

    shop or construction site and ensure the correct materials used in the proper places.

    9 PRESURE LEAK TESTING

    9.1Prior to initial operation, all installed piping system shall be pressure leak tested in accordance with

    Specification 7T04-CS-00-TS-016.

    13

    13

    13