E R E C T I O N M A N U A L
STEAM TURBINE
500 MW
(KWU DESIGN)
DOCUMENT NO. TS-T1-08
Bharat Heavy Electricals Limited
POWER SECTOR
TECHNICAL SERVICES (HQ)
NOIDA
STEAM TURBINE
500 MW
ERECTION
Bharat Heavy Electricals Limited Rev 00, 7-98
E R E C T I O N M A N U A L
STEAM TURBINE
500 MW
(KWU DESIGN)
DOCUMENT NO. TS-T1-08
Bharat Heavy Electricals Limited
POWER SECTOR
TECHNICAL SERVICES (HQ)
NOIDA
STEAM TURBINE ERECTION MANUAL 500 MW (KWU DESIGN)
Document No.
TS-T1-08
Copy No Revision 00
Prepared by Name
1 SK Gupta, DGM, PS-WR, Nagpur
2 RK Mathur, Sr. Manager, PS-NR, Noida
3 Pratap Singh, DGM, PS-ER, Calcutta
4 PK Ramesh, Proj. Mgr., PS-SR, Madras
5 S. Bhattacharya, DGM, STE /FES, Hardwar
6 Ajay Sengupta, Sr.Manager, PS-Q, Noida
7 NK Bansal ,DGM, PS-TS(HQ), Noida
8 AK Sinha, Sr. Manager, PS-TS(HQ), Noida
9 NS Tomar, Manager, PS-TS(HQ), Noida
Approved By Baboo Ram, GM (TS & Q), PS-TS(HQ), Noida
Issued By Baboo Ram, GM (TS & Q), PS-TS(HQ), Noida
Issued to
Date of Issue Controlled
Information
Copy
FOREWORD
I am glad that Power Sector - Technical Services ( Head Quarters),
Noida has brought out this erection manual of 500 MW steam
turbine (KWU design) being produced by BHEL. This manual lays
emphasis on site optimisation techniques which aims at uniform
erection practices, improvement in quality, reduction in time cycle
and saving in cost.
I am sure, this manual will form the basis for site erection activities
so that the organisation can derive full benefit out of this. It is
needless to emphasize that upgrading of technology is a continuous
process and we have to review our methods of working and make
suitable changes, wherever required.
(K P Mathur) New Delhi Executive Director (PEM & TS)
PREFACE
The Erection Manual for 500 MW Steam Turbine (KWU design)
manufactured by BHEL for Thermal Power Stations has been
prepared by a team of BHEL engineers having long experience in
Erection & Commissioning, Design, Quality control of steam turbines.
This dedicated team has been drawn from regional erection group,
designed department of manufacturing units, PS-Q & TS-HQ,
Noida.
The manual carries general description of steam turbine, erection
procedure, special instruction, general instructions, and various
other technical instructions with an intention to establish an uniform
approach for erection of steam turbine.
The Erection Manual provides broad based guide line for erection of
steam turbine. Product standard, technical circulars & BHEL
drawings for the specific project will precede the instructions and
guidelines furnished in this manual. Project specific document will
be generated by region concerned. This document is generated as a
standard Erection Manual for 500 MW fixed pedestal type steam
turbine with spring loaded foundation.
The work done by TASK FORCE is commendable. Feed-back and
suggestions are welcome for the improvement of this Erection
Manual to bringing down the cycle time with quality.
BHEL reserves the right to suggest alternative procedure if
necessity arises at site due to local site conditions .
(BABOO RAM)
NOIDA GENERAL MANAGER(TS&Q)
STEAM TURBINE
500 MW
ERECTION
CODIFICATION FOR INSTRUCTION
NUMBER
Bharat Heavy Electricals Limited Rev 00, 7-98
page 1 of 3
The following codification system is used for numbering of instructions and the codification of Log Sheets is as per FQA document.
XX X - XX XX XX X Alpha Numeric Numeric Numeric Numeric Alpha Type of Instruction System Instruction No System Designation Rating of Main Equipment Type of Manual Product Code
1.1 PRODUCT CODE
B Boiler
BA Boiler Aux.
T Turbine
TA Turbine Aux.
G Generator
GA Generator Aux
P Power Plant Piping
CI C&I
1.2 TYPE OF MANUAL
STEAM TURBINE
500 MW
ERECTION
CODIFICATION FOR INSTRUCTION
NUMBER
Bharat Heavy Electricals Limited Rev 00, 7-98
page 2 of 3
1 Erection
2 Commissioning
3 Service
1.3 RATING OF MAIN EQUIPMENT
01 200/210 MW
02 120 MW
03 110 MW
04 60 MW
05 30 MW
06 100 MW
07 235 MW
08 500 MW KWU Design
09 210 MW KWU Design
10 120 MW KWU Design
11 60 MW KWU Design
12 70 MW KWU Design
13 Industrial Units
14 210 MW Tower Type Concrete Pylem
15 210 MW Tower Type Steel Structure
16 500 MW Tower Type Once through
17 250 MW
18 CCP
STEAM TURBINE
500 MW
ERECTION
CODIFICATION FOR INSTRUCTION
NUMBER
Bharat Heavy Electricals Limited Rev 00, 7-98
page 3 of 3
1.4 SYSTEM DESIGNATION
SNO DESCRIPTION
1. TECHNICAL DATA
2. INSTRUCTION FOR HANDLING AND STORAGE OF TURBINE
3. ERECTION SEQUENCE
4. ERECTION PROCEDURE
5. GROUTING PROCEDURE
6. ASSEMBLY OF IP MODULE AT SITE
7. SEALING AND ANTISEIZING COMPOUNDS
8. CRITICAL ACTIVITIES
9. SPRING LOADED FOUNDATION
10. ERECTION OF PIPING
11. SPECIFICATION FOR GAS HEATING DEVICE
12. SPECIFICATION FOR BREECH NUT HEATING DEVICE
13. SPECIFICATION FOR THERMAL INSULATION
1.5 TYPE OF INSTRUCTION
G General
T Technical
L Log Sheet
C Check List
0sep.doc
INDEX
STEAM TURBINE
500 MW
ERECTION
CONTENTS
Bharat Heavy Electricals Limited Rev 00, 7-98
page 1 of 1
SNO DESCRIPTION INSTRUCTION NO
1 TECHNICAL DATA
T 1-08 -0101G
2 INSTRUCTION FOR HANDLING AND STORAGE OF TURBINE
T 1-08 -0202G
3 ERECTION SEQUENCE
T 1-08 -0303G
4 ERECTION PROCEDURE
T 1-08 -0404G
5 GROUTING PROCEDURE
T 1-08 -0505G
6 ASSEMBLY OF IP MODULE AT SITE
T 1-08 -0606G
7 SEALING AND ANTISEIZING COMPOUNDS
T1-08 -0707G
8 CRITICAL ACTIVITIES
T 1-08 -0808G
9 SPRING LOADED FOUNDATION
T 1-08 -0909G
10 ERECTION OF PIPING
T 1-08 -1010G
11 SPECIFICATION FOR GAS HEATING DEVICE
T 1-08 -1111G
12 SPECIFICATION FOR BREECH NUT HEATING DEVICE
T 1-08 -1212G
13 SPECIFICATION FOR THERMAL INSULATION
T1-08 -1313G
0sep.doc
TECHNICAL DATA
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 1 of 9
LOAD
RATED 500 MW
MAX. UNDER VALVE WIDE OPEN (VWO) CONDITION 524.2
CONSTRUCTION
THREE CYLINDER REHEAT CONDENSING TURBINE 500 MW
SINGLE FLOW HP TURBINE WITH 17 REACTION STAGES TYPE H30-100-2
DOUBLE FLOW IP TURBINE WITH 12 REACTION STAGES PER FLOW
TYPE M30-63
DOUBLE FLOW LP TURBINE WITH 6 REACTION STAGES PER FLOW
TYPE N30-2X10
2 MAIN STOP AND CONTROL VALVES TYPE EV320-1
2 REHEAT STOP AND CONTROL VALVES TYPE IV560
1 SWING CHECK VALVE IN COLD REHEAT LINE MAKE
DN-800 BHEL,TIRUCHY
2 BYPASS STOP AND CONTROL VALVES DN-320
EXTRACTION SWING CHECK VALVES :
EXTRACTION-1 : NO VALVE -
EXTRACTION-2 : 1 SWING CHECK VALVE WITH ACTUATOR MAKE
DN-800 BHEL,TIRUCHY
EXTRACTION-3 : 1 SWING CHECK VALVE WITH ACTUATOR & 1 SWING CHECK VALVE WITHOUT ACTUATOR
MAKE
DN-500 BHEL,TIRUCHY
EXTRACTION-4.1 : 2 SWING CHECK VALVE WITH ACTUATOR MAKE
DN-500 BHEL,TIRUCHY
EXTRACTION-4.2 : 2 SWING CHECK VALVE WITH ACTUATOR MAKE
DN-500 BHEL,TIRUCHY
EXTRACTION-5 : 1 SWING CHECK VALVE WITH ACTUATOR & 1 SWING CHECK VALVE WITHOUT ACTUATOR
MAKE
DN-400 BHEL,TIRUCHY
EXTRACTION-6 : NO VALVE
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 2 of 9
SPEED
RATED SPEED 50.0 /S
SPEED LIMITATION IN LOAD & STATION AUX. LOAD OPERATION
MAX. SPEED, NO TIME LIMITATION MIN. SPEED, NO TIME LIMITATION
PERMISSIBLE FOR A MAXIMUM OF 2 HRS. DURING THE LIFE OF LP BLADING SPEED BELOW SPEED ABOVE
: :
: :
524.2 51.5 /S 47.5 /S
47.5 /S 51.5 TO 60 /S
SPEED EXECUTION RANGE AT OPERATION WITHOUT LOAD* : 6.7 TO 47.5 /S
STANDARD OVER SPEED TRIP SETTING : MAX. 55.5 /s
* THIS SPEED RANGE SHOULD BE PASSED THROUGH IN ONE SMOOTH OPERATION TO AVOID ENDANGERING THE BLADES DUE TO RESONANCE
STEAM PRESSURES
RATED* LONG TIME
OPERATION
SHORT TIME
OPERATION
INITIAL STEAM 166.7 166.7 20.7 BAR
BEFORE 1st HP DRUM STAGE 154.4 163.4 169.9 BAR
HP CYLINDER EXHAUST 44.9 52.0 57.4** BAR
IP CYLINDER STOP VALVE INLET 40.3 46.7 55.2** BAR
EXTRACTION 6 44.9 52.0 57.4 BAR
EXTRACTION 5 17.5 22.2 22.2 BAR
EXTRACTION 4 7.2 8.7 8.7 BAR
EXTRACTION 3 2.58 3.2 3.2 BAR
EXTRACTION 2 1.329 1.66 1.66 BAR
EXTRACTION 1 0.257 0.41 0.41 BAR
LP CYLINDER EXHAUST 0.1013 0.3 0.3 BAR
* THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACK
PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS. ** THE SAFETY VALVES MUST BE SET SO THAT THESE SHORT TIME VALUES ARE NOT EXCEEDED.
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 3 of 9
LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT.
SHORT TIME OPERATION : PERMISSIBLE MOMENTARY VALUE. THE AGGREGATE DURATION OF SUCH SWINGS MUST NOT EXCEED 12 HOURS IN ANY ONE YEAR. ALL PRESSURES ARE ABSOLUTE PRESSURES
LOW VACUUM TRIP, STANDARD SETTING
HYDRAULIC LOW VACUUM TRIP : 0.3 BAR
ELECTRICAL LOW VACUUM TRIP : 0.3 BAR
HYDRAULIC LOW VACUUM TRIP BYPASS OPERATION : 0.6 BAR
SEAL STEAM SUPPLY SYSTEM
PRESSURE IN SEAL STEAM HEADER (ABOVE ATMOSPHERIC) : 35 MBAR
AXIAL SHIFT
ALARM TRIP
* 0.5 mm * 1 mm
* DIRECTION OF ROTATION ANTI CLOCK WISE WHEN VIEWED FROM FRONT PEDESTAL TOWARDS THE GENERATOR
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 4 of 9
STEAM TEMPERATURES
RATED
VAL.
ANNUAL
MEAN
VALUE
LONG TIME
VALUE
(WITHIN
ANNUAL
MEAN
VAL.)
400 h
PER
ANNUM
80 h PER
ANNUM
MAX. 15
MIN IN
INDIVIDUA
L CASE
INITIAL STEAM 536.0 546.O 552.O 566.0 OC
IP CYLINDER STOP VALVE INLET 536.0 546.3 552.0 566.0 OC
RATED
VALVE *
LONG
TIME
OPERATI
ON
80 h PER
ANNUM
MAX. 15
MIN IN
INDIVIDU
AL CASE
IN
SPECIAL
CASES
AT NO
LOAD
HP CYLINDER EXHAUST 340.0 360.0 440.0 500.0** OC
EXTRACTION 6 340.0 360.0 440.0 500.0** OC
EXTRACTION 5 413.9 421.9 459.9 OC
EXTRACTION 4 292.1 304.1 346.4 OC
EXTRACTION 3 187.3 195.3 242.3 OC
EXTRACTION 2 128.3 139.3 184.3 OC
EXTRACTION 1 66.5 86.5 136.5 OC
LP CYLINDER EXHAUST 46.1 70.0 70.0 OC
LONG TIME OPERATION : UPPER LIMIT VALUE, PERMISSIBLE WITHOUT TIME LIMIT.
* THESE VALUES CORRESPOND TO 500 MW LOAD WITH 3% MAKE-UP AND 0.1013 BAR BACK PRESSURE WITH ALL HEATERS IN SERVICE AND RATED STEAM CONDITIONS.
** ONLY VALID FOR THE NO LOAD PERIOD WITH HIGH REHEAT PRESSURE AFTER TRIP-OUT FROM FULL LOAD OPERATION. FOR INDIVIDUAL CASE APPROX. 15 MINUTES
THE TURBINE IS IMMEDIATELY RE-LOADED OR THE BOILER IMMEDIATELY REDUCED TO MINIMUM LOAD IF NO LOAD OPERATION IS MAINTAINED.
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 5 of 9
CASING TEMPERATURES
WALL TEMPERATURES ALARM
AT
MACHINE MUST BE
SHUT DOWN AT
HP TURBINE CASING EXHAUST 480 500 OC
OUTER CASING OF LP CYLINDER 90 110 OC
PERMISSIBLE DIFFERENTIAL TEMP. BETWEEN PARALLEL STEAM SUPPLY LINES :
NO TIME LIMITATION : 17 OC
SHORT TIME PERIOD (15 MIN.) : 28 OC
IN THE HOTTEST LINE THE LIMITATIONS INDICATED FOR INITIAL STEAM & REHEAT TEMP. MUST NOT BE EXCEEDED.
SPRAY WATER TO LP TURBINE MUST BE SWITCHED ON AT 90O C.
TEMPERATURES DIFFERENCE ALARM
AT
MACHINE MUST BE
SHUT DOWN AT
DIFFERENCE BETWEEN UPPER & LOWER
CASING HALVES HP TURBINE. MIDDLE
* 90 * 100 OC
LP TURBINE. FRONT * 30 * 45 OC
LP TURBINE. REAR * 30 * 45 OC
FEEDWATER HEATER OUT OF SERVICE
OPERATION WITH FEEDWATER HEATER OUT OF SERVICE MAIN STEAM
FLOW Kg/s
LOAD
MW
EXTRACTION A6 = 0 395 500
EXTRACTION A5 = 0 421 500
EXTRACTION A3 = 0 423 500
EXTRACTION A2 = 0 425 500
EXTRACTION A1 = 0 423 500
EXTRACTION A6, A5 = 0 400 525
OUTPUT LIMIT DURING TESTING WITH AUTOMATIC TURBINE TESTER
TESTING OF MAIN STEAM STOP & CONTROL VALVE 400 M W
TESTING OF HRH STEAM STOP & CONTROL VALVE 200 - 500 M W
MOTORING :
MOTORING IS THE CONDITION IN WHICH THE TURBINE IS DRIVEN BY THE GENERATOR AT RATED SPEED WITH THE STOP & CONTROL VALVES CLOSED. IN THIS OPERATING MODE, CERTAIN TURBINE COMPONENTS ARE HEATED UP BY WINDAGE POWER IN THE BLADING. TO PREVENT HEAT-UP BEYOND PERMISSIBLE TEMPERATURES, MOTORING MUST NOT BE ALLOWED TO CONTINUE FOR LONGER THAN ONE MINUTE. IF THE CONDENSER LOW VACUUM LIMIT OF 0.3 BAR IS EXCEEDED, MOTORING MUST NOT BE ALLOWED TO CONTINUE FOR MORE THAN 4 SECONDS.
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 6 of 9
BEARING TEMPERATURES
ALARM
AT
MACHINE MUST BE
SHUT DOWN AT
OPERATION TEMPERATURE BELOW 75 O
C 90 120 OC
OPERATION TEMPERATURE 75 TO 85 OC 100 120
OC
OPERATION TEMPERATURE 85 TO 90OC 110 120
OC
OPERATION TEMPERATURE ABOVE 90OC 115 120
OC
VIBRATION
ABSOLUTE BEARING
HOUSING VIBRATION
ABSOLUTE SHAFT
VIBRATION
STANDARD ALARM SETTING 30 m ABOVE NORMAL LEVEL*
m
MAXIMUM ALARM SETTING 35 120 m
LIMIT VALUE FOR TRIPPING 45 200 m
* THE NORMAL LEVEL IS REPRODUCIBLE VIBRATIONAL BEHAVIOUR TYPICAL FOR THE MACHINE AND
DEPENDENT ON THE OPERATING CONDITIONS, VIBRATION READINGS INDICATED IN CONTROL ROOM ARE HALF PEAK. THE ABOVE VALUES ARE ALSO GIVEN IN HALF PEAK.
WEIGHTS
HP TURBINE, COMPLETELY ASSEMBLED : 94.6 T
IP TURBINE. TOP HALF OUTER CASING : 25.7 T
IP TURBINE, TOP HALF INNER CASING, COMPLETE WITH BLADING : 15.5 T
LP TURBINE. TOP HALF OUTER CASING COMPLETE : 42.6 T
LP CYLINDER, TOP HALF OUTER SHELL OF INNER CASING, COMPLETE WITH BLADING, STATIONARY BLADE CARRIERS & DIFFUSER
: 38.5 T
HP TURBINE ROTOR, COMPLETE WITH BLADING : 16.3 T
IP TURBINE ROTOR, COMPLETE WITH BLADING : 23.1 T
LP TURBINE ROTOR, COMPLETE WITH BLADING : 85.8 T
MAIN STOP & CONTROL VALVE, COMPLETE WITH SERVO MOTORS, WITHOUT BEND & PIPE SECTION
: 20.9 T
REHEAT STOP & CONTROL VALVE, COMPLETE WITH SERVO MOTORS, WITHOUT BEND & PIPE SECTION
: 32.2 T
ALL WEIGHTS HAVE BEEN CALCULATED WITH SAFETY ALLOWANCES. SLINGS
CHOSEN MUST PROVIDE SUFFICIENT SECURITY.
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 7 of 9
OIL SUPPLY
MAIN OIL TANK, RATED CAPACITY : 25/40 Cu . M
Ist OIL FILLING (ESTIMATED) : 47.5 Cu . M
FLUSHING OIL QUANTITY (ESTIMATED) : 28.5 Cu . M
OIL COOLER FOR OPERATION, NUMBER : 1 NO.
OIL COOLER FOR RESERVE, NUMBER : I NO.
OIL TEMP. AT COOLER OUTLET, UNIT IN OPERATION
MIN.
NORMAL
MAX.
: : :
38 45 47
OC
OIL TEMP. AT COOLER OUTLET, UNIT SHUT DOWN
MAX.
:
75
OC
TEMP. RISE OF OIL IN BEARINGS
NORMAL
MAX.
: :
20 25
OC
ESTIMATED OIL REQUIREMENTS OF BEARINGS :
BEARING 1(HP TURBINE, FRONT PEDESTAL) : 0.8 dm3/S
BEARING 2 : 15.4 dm3/S
BEARING 3 : 4.1 dm3/S
BEARING 4 : 8.6 dm3/S
GENERATOR FRONT BEARING : 7.92 dm3/S
GENERATOR REAR BEARING : 7.92 dm3/S
EXCITER BEARING : 0.70 dm3/S
1 DUPLEX OIL FILTER FOR BEARING OIL (FULL FLOW) : 200 mm
DUPLEX OIL FILTER . TYPE - 2.62.9. SIZE 355/750. MAKE : BOLL & KIRCH
FILTRATION PARTICLE SIZE OF DUPLEX FILTER ELEMENT : 37 m
FILTRATION PARTICLE SIZE OF MAIN OIL TANK FILTER
ELEMENT
: 250 m
SAFETY VALVE IN JACKING OIL SYSTEM, SETTING
MAX.
: 200 BAR
PRESSURE LIMITING VALVE IN JACKING OIL SYSTEM,
SETTING
: 100 BAR
1 DUPLEX OIL FILTER FOR JACKING OIL : 25 mm
FILTRATION PARTICLE SIZE OF JACKING OIL FILTER : 37 m
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 8 of 9
OIL PUMPS
MAIN OIL
PUMP
AUXILIARY
OIL PUMP
DC
EMERGENCY
OIL PUMP
JACKING
OIL PUMP
QUANTITY 1 2 1 AC : 2 DC : 1
MAKER BHEL KSB KSB TUSHAKO
TYPE 97.22 dm3/S ETA-150-
50VVL ETA-100-
33VVL SDF80
CAPACITY
(RATED)
75 89.25 30 1.53 dm3/s
DISCHARGE
PRESSURE
(GAUGE)
8.6 6.2 2.3 178 BAR
SPEED 50 24.75 24.3 49.42 /s
DRIVE TURBINE AC MOTOR DC MOTOR AC MOTOR
DC MOTOR
STEAM TURBINE
500 MW
ERECTION
TECHNICAL DATA
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0101G Page No. 9 of 9
CONTROL FLUID SUPPLY
CONTROL FLUID TANK, RATED CAPACITY : 10/16 Cu . M
Ist FLUID FILLING (ESTIMATED) : 15 Cu . M
FLUSHING FLUID QUANTITY (ESTIMATED) : 10 Cu . M
CONTROL FLUID COOLER FOR OPERATION, NUMBER : 1 NO.
CONTROL FLUID COOLER FOR RESERVE, NUMBER : I NO.
CONTROL FLUID MAINTENANCE EQUIPMENT :
GEAR PUMP
MANUFACTURER
TYPE
: :
STEIMEL
BGK 2-24R
FLUID FLOW : 0.28 dm3/S
GAUGE PRESSURE : 3.06 at
SPEED : 25 S-1
MOTOR POWER : 0.75 KW
2 EARTH FILTERS
MANUFACTURER
TYPE
: :
ROTRING PYG5-350
EARTH FILLING MESH : 140 Kg
1 FINE MESH FILTER
MANUFACTURER
TYPE
: :
ROTRING
S-1800-14-TUY
FILTRATION PARTICLE SIZE : 3-5 m
FILTER MATERIAL : COTTON
CONTROL FLUID SUPPLY SYSTEM
A FIRE RESISTANT FLUID IS USED FOR THE CONTROL SYSTEM
0sep.doc
INSTRUCTIONS FOR
HANDLING &
STORAGE OF TURBINE
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 1 of 11
1. SCOPE
The document covers all steam turbine components and provides the handling, inspection and storage instructions for large steam turbine components at site. A strict adherence to these instructions is necessary to avoid damages during handling and storage at site.
2. HANDLING OF EQUIPMENT :
2.1. In any kind of rigging work it is necessary to strictly observe the safety precautions, since even the slightest negligence and non observance of the rules may result in accidents, which may cause damage to equipment or injury to men.
2.2. The site for the rigging work involving lifting and conveying of loads should be well lighted. The loads must not be lifted unless the crane operator can see clearly the signals given by the rigger.
2.3. The positions where the slings are to be put, are marked on the packages and on the drawings. While lifting/handling these packages/equipment, the slings should only be put at the proper places.
2.4. The slings of the proper sizes and lengths should only be used for handling the equipment/packages. The angle between the two arms of the sling at the crane hook should be small (depending upon the dia of the sling) so as to have proper loading of the sling.
2.5. The turbine rotors and cylinder covers (in assembled condition are lifted by the use of special lifting devices supplied by BHEL. The use of these lifting devices facilitates correct slinging and maintain horizontal position of the components. These devices, after use, should be properly stored and conserved so as to ensure that they do not get damaged during storage. Before using them, they should be thoroughly inspected.
2.6. The work related to handling of the loads (packages or equipment) by crane or by other hoisting mechanism should be entrusted to trained riggers only. If the rigger/operator is not sure of the weight of the item/package (load) to be handled, he must ask for the required information before handling the equipment.
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 2 of 11
2.7. The rigger and the crane operator should see that the hook and the ropes of the crane occupy vertical position, before hoisting the load. Dragging of the load by slanting ropes is not allowed. The center of gravity of the load should be aligned with the vertical axis of the crane hook.
2.8. The eye bolts, 'D' shackles, turn buckles, and wire ropes of suitable sizes should only be used for handling of the equipment. Before using, they should be thoroughly inspected to their full threads, so as to avoid any chance of slipping then the load comes on them.
2.9. Before giving a signal to lift the load, the rigger must check and ensure that there are no loose parts or tools on the load, which might fall during lifting. Then the load must be lifted 100 or 200 mm high for checking the uniformity of sling tensioning and reliability of lashing. If it is necessary to rearrange the sling lengths, the load must be lowered and then the slings rearranged.
2.10. Before horizontal conveyance of the load the rigger must see that the load has been lifted to a height at least 0.5 M above the tallest object, on the path of the load. While the load is being conveyed, the rigger must accompany it and see that it is not moved above any person. Prior to lowering the load the rigger should examine the ground on which the load will be, lowered and make sure that these is no risk of falling or slipping of the load.
2.11. If any one of the personnel present during lifting or lowering of the load detects some defect of the crane or sling of notices some conditions jeopardizing the lifting or lowering operation, he must give a signal for emergency grounding of the package or components.
2.12. Smooth lifting and transportation of equipment must be ensured. Shocks and jerks should be avoided.
2.13. All lifting devices, slings must be properly conserved after use and periodically inspected and tested.
2.14. In the turbines having diaphragms, it is prohibited to handle diaphragms by putting slings in between the blades. For handling the welded diaphragms, special lifting devices is supplied by BHEL and the cast diaphragms are handled by putting the eye bolts, for which the provision of threads holes have been made in the diaphragms.
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 3 of 11
2.15. While handling the bearings, it is prohibited to put the sling across the rabbit surface of the bearings. Threaded holes have been provided; in which the eye bolts have to be put for handling of the bearings.
2.16. While handling the cylinders, it must be ensured that the slings or any other material does not get rubbed at their horizontal and vertical parting planes or at any other machined surface.
2.17. The handling of the long components such as longitudinal girder, endwall etc. should be done with extra care. When they are placed on the floor, in addition to the end supports, few extra supports at the intermediate positions must be provided.
2.18. While handling LP rotor with free standing blades, care must be taken to ensure that no force is exerted on the free standing blades to avoid collapsing of clamping pieces under blade root.
3. MARKINGS ON PACKING CASES
3.1. Various symbols are marked on the packing cases as per 0456.001 to facilitate storage and handling of the crates and protection of equipment inside.
4. INSPECTION
4.1. Before storing the equipment it should be opened for visual examination or the internal packing, protective coating and condition of the equipment. Any damage to packing and conservation should be immediately rectified.
4.2. It is necessary to carryout first inspection within three weeks of arrival of the consignment. Thereafter, all the equipment should be inspected once in every three months to insure that the conservation is intact. During rainy season, the inspection should be done once in a month. At any time, if any original conservation is found damaged, it should be reconserved as per relevant conservation instructions No. ST 33004.
4.3. While inspecting the packages containing rotors, special care should be taken to check the journals. In case of slightest sign of pitting on the journals and thrust collar, immediate steps for rectification should be taken and equipment reconserved as per relevant conservation instructions.
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 4 of 11
5. STORAGE
5.1. All steam turbine equipment should be accommodated in the designated place of storage immediately after arrival at destination. This is very essential particularly during the rainy season.
5.2. Store houses fall into the following categories
TYPE OF CONDITIONS STORE
HOUSE TEMP. RELATIVE
HUMIDITY
ARRANGEMENT
'P' +50
C to
500
C
< 70 % Totally enclosed, rain proof, ventilated and dry with cemented floor.
'Q' upto 50
0 C
- Roofed area with walls (of brick / asbestos/ GI sheet ) around and cemented / pucca hard floor.
'R' - - Raised platform with shed of asbestos / GI sheet / water proof tarapaulin.
'S' - - Raised Platform.
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 5 of 11
5.3. The platforms and store-houses should be built up in conformity with the fire prevention rules and standards. Complete storage area especially the ‘R’ & ‘S’ catagory must be adequately fenced & protected against theft & pilferage.
5.4. These store houses and areas around them should have proper drainage facility for the sub-soil, surface and rain water. The water should not be allowed to stand or get accumulated in these areas, especially where the material has been stored.
5.5. Store house should be provided with proper ventilation facilities.
5.6. Level should be maintained for all the packages and equipment and should be uniformly supported to avoid distortion. The long packages should be supported at intermediate places also, so as to avoid sagging during storage.
5.7. Store houses should preferably be equipped with proper lifting devices to ensure normal handling of equipment.
5.8. Small and medium size parts can be kept on shelves with proper identification tags.
5.9. Packages upto 5 tones can be placed on upon the other upto 2.5m in height using required number of wooden spacers 50 mm thick. In doing so, lighter packages would be laid upon heavier once to avoid any damage to lower packages.
5.10. Articles weighing more than 5 tones should be laid in a single tier.
5.11. For heavier components under ‘Q’, the roof/walls may be constructed/fabricated after placement of the component on cemented/pucca hard floor.
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 6 of 11
STORAGE OF STEAM TURBINE COMPONENTS
SNO. DESCRIPTION OF THE COMPONENT TYPE OF
STORAGE
1. FOUNDATION BOLT Q
2. EMBEDDED PARTS (ADDITIONAL) R
3. COMPONENTS OF BASE PLATE ASSLY. Q
4. BASE PLATE LP CASING R
5. LP OUTER CASIONG R
6. LONGITUDINAL GIRDER (LEFT & RIGHT) R
7. LP FRONT WALL (TS&GS) R
8. LP SHAFT SEALING (FRONT & REAR) Q
9. AUXILIARIES OF TURBINE Q
10. HP/IP BEARING PEDESTAL Q
11. HP/IP BEARING PEDESTAL ASSEMBLY PARTS Q
12. IP/LP PEDESTAL ASSEMBLY Q
13. LP/GEN. PEDESTAL Q
14. BEARING PEDESTAL PARTS Q
15. FRONT BEARING PEDESTAL Q
16. LIFTING BEAM R
17. LP CASING EXTRACTION A1 R
18. LP EXTRACTION A2 R
19. LP EXTRACTION A3 R
20. LP EXTRACTION PIPE SHEATHING R
21. INNER GUIDE PLATE DIFFUSER R
22. DIFFUSER (UPPER & LOWER HALVES) R
23. LP INNER-OUTER CASING (VH) Q
24. LP INNER CASING ASSEMBLY (LH & VH) Q
25. HEATING DEVICE Q
26. LP CASING ASSEMBLY Q
27. LP INNER CASING ASSEMBLY (FASTENER) Q
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 7 of 11
28. INNER GUIDE PLATE DIFFUSER (GS) R
29. LP ROTOR Q
30. IP TURBINE Q
31. IP TURBINE PARTS Q
32. IP INLET PIPES Q
33. HP TURBINE Q
34. HP INLET ASSEMBLY Q
35. HP EXHAUST ELBOW Q
36. HPT RELATED PARTS Q
37. FRAME FOR SUSPENSION (ESV) R
38. SUSPENSION OF VALVE (ESV) Q
39. ESV & CV CASING WITH VALVE Q
40. ESV SERVOMOTORS WITH LIMIT SWITCH Q
41. HP CONTROL VALVE SERVOMOTORS Q
42. SUSPENSION OF VALVE (IV) Q
43. IV & CV CASING WITH VALVE Q
44. IV SERVOMOTORS WITH LIMIT SWITCH Q
45. IP CONTROL VALVE SERVOMOTORS Q
46. FRAME FOR SUSPENSION (IV) R
47. IV SERVOMOTORS WITH LIMIT SWITCH Q
48. STEAM BLOWING & HYD. TEST DEVICE Q
49. TOOLS FOR GOVERNING SYSTEM Q
50. SUSPENSION OF LPB VALVE Q
51. WATER INJECTION VALVES Q
52. CHEST LPB WITH STOP & CONTROL VALVE q
53. LPB STOP VALVE SERVOMOTOR Q
54. LPB CONTROL VALVES SERVOMOTORS Q
55. INJR. FOR SUCTION PIPE NB 350 R
56. INJR. FOR SUCTION PIPE NB 300 R
57. MAIN OIL TANK R
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 8 of 11
58. MAIN OIL TANK & NOZZLE ASSEMBLY R
59. OIL STRAINER Q
60. LEVEL MONITOR INSTALLATION Q
61. INSTRUMENTS Q
62. LEAKAGE / DIRTY FLUID TANK R
63. VARIABLE ORIFICES & THROTTLE Q
64. CONTROL FLUID TANK R
65. CONTROL FLUID TANK NOZZLE ARRANGEMENT R
66. EXPANSION TANK R
67. FILTER & PR. DAMPING DEVICES Q
68. CROSS AROUND PIPE R
69. SUPPORT FOR CAP R
70. CHANGE OVER VALVE R
71. RATING & MONOGRAM PLATES Q
72. OIL STRIPER R
73. HOUSING FOR HRH STEAM STRAINER R
74. HOUSING FOR MAIN STEAM STRAINER R
75. MS & HRH STR.HSG GASKET Q
76. STEAM STRAINER MS Q
77. STEAM STRAINER HRH Q
78. COMPENSATOR Q
79. TURBINE CONTROL LPB / SUPPLY RACK Q
80. TEMPERATURE & PRESSURE CONNECTIONS Q
81. PR. TRANSMITTERS BAR. PROBES THERMOCOUPLES
Q
82. TRANSMITTERS & JUNCTION BOXES Q
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 9 of 11
STORAGE & PRESERVATION OF COMPONENTS OF
TURBOGENERATOR, EXCITER AND SYSTEMS SNO. DESCRIPTION OF THE COMPONENT TYPE OF
STORAGE
1. EMBEDDED PARTS R
2. FOUNDATION PARTS R
3. WOUND STATOR WITH GAS COOLERS Q
4. TURNION FOOT PLATES Q
5. ROTOR Q
6. ASSEMBLY OF PIPE CONTROL FOR GAS COOLERS R
7. END SHIELDS Q
8. FAN SHIELD, GEN VVIEW HEADER ASSEMBLY R
9. TERMINAL BUSHING AND HEADER ASSEMBLY Q
10. BEARING WITH BRUSH GEAR Q
11. SEAL BODY Q
12. TEMP. CONNECTION Q
13. CASING FOR TURNIONS R
14. ERECTION MATERIALS Q
15. ERECTION DEVICES R
16. SHAFT SEALS Q
17. SEAL RINGS Q
18. ADOPTING RING Q
19. AUXILIARY BEARING Q
20. CENTRIFUGAL FAN Q
21. CARBON DIOXIDE VAPOURISER Q
22. FILTER O.C.P. Q
23. EXPANSION TANK R
24. OIL SEPARATOR R
25. PRE CHAMBER R
26. S.O.S.T. R
27. SEAL OIL UNIT Q
28. HYDROGEN DISTRIBUTION R
29. CARBON DIOXIDE DISTRIBUTION R
30. VALVES FOR AUXILIARY SYSTEMS P
31. GAS UNITS Q
32. FLEXIBLE LEADS Q
STORAGE & PRESERVATION OF COMPONENTS OF HEAT
EXCHANGERS
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 10 of 11
SNO. DESCRIPTION OF THE COMPONENT TYPE OF
STORAGE
PRODUCT : CONDENSER
1. BOTTOM PLATE S
2. LOWER DOM WALL S
3. SIDE WALL S
4. WATER CHAMBER Q
5. UPPER DOM WALL S
6. STIFFENING PIPES S
7. STIFFENING RODS S
8. TUBE SUPPORT PLATE R
9. WATER BOX R
10. AIR EXTRACTION PIPING R
11. HOTWELL S
12. SPRING ELEMENTS R
13. LOOSE ITEMS Q
14. INSTRUMENTS Q
15. CONDENSER TUBES (STAINLESS STEEL) R
16. CONDENSER TUBES (NON-FERROUS) Q
17. VACUUM PUMP Q
18. EJECTOR R
19. AIR MEASURING DEVICE Q
PRODUCT : HEATER
1. GLAND STEAM CONDENSER R
2. STAND PIPE Q
3. INSTRUMENTS Q
4. DRAIN COOLER R
5. L.P.HEATERS R
PRODUCT : COOLER
1. OIL COOLER R
2. CONTROL FLUID COOLER R
3. STATOR WATER COOLER R
4. HYDROGEN COOLER Q
5. EXCITER AIR COOLER Q
6. INSTRUMENTS / LOOSE ITEM Q
STEAM TURBINE
500 MW
ERECTION
INSTRUCTIONS FOR HANDLING &
STORAGE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0202G Page No. 11 of 11
MAXIMUM PERMISSIBLE LOADING FOR WIRE ROPES IN KG.
NOMINAL SINGLE DOUBLE CORD WITH INCLUDED ANGLE OF
DIA (d) OF
ROPES mm CORD
0o 45
o 90o 120
o
9 522 1044 965 738 522
12 1170 2340 2070 1580 1170
18 2150 4300 4000 3060 2150
24 3850 7700 2100 5400 3850
30 6200 12400 11500 8800 6200
36 9000 18000 16600 12700 9000
42 12200 24400 22600 17300 12200
48 16000 32000 29500 22600 16000
54 20200 40400 37300 28500 20200
60 24900 49800 46000 35200 24900
66 30100 60200 55700 42600 30100
72 35800 71600 66200 50700 35800
78 42100 84200 77700 59500 42100
84 48800 97600 90200 69000 48800
90 56000 112000 103500 79200 56000
96 63700 127400 117700 90000 63700
102 71900 143800 132900 101700 71900
108 81000 162000 149700 114500 81000
114 89900 179800 166100 127100 89900
120 99700 199400 184300 141100 99700
0sep.doc
ERECTION SEQUENCE
STEAM TURBINE
500 MW
ERECTION
ERECTION SEQUENCE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0303G Page No. 1 of 7
ERECTION SEQUENCE
(For 500 MW Fixed pedestal type Turbine with spring loaded foundation)
1. Cleaning and checking of Turbine and Generator foundations as per the transverse
and longitudinal axis including their elevation.
2. Prepare and install LP base plates, HP front pedestal, HP rear pedestal, LP front
pedestal, LP rear pedestal along with their anchor bolts and anchor plates.
3. Provisionally align and level all the pedestal and LP base plates as per the
transverse and longitudinal axis including their elevation.
4. Matching of anchor plates of pedestal and LP base plates to ensure their perfect
seating.
5. Finally align and level HP front, HP rear, LP front and LP rear pedestals along with
LP base plates as per the transverse and longitudinal axis including their
elevation and catenary as per the design.
6. Prepare and install steel bars for LP casing centralising keys in foundation slab as
per the required center line .
7. Weld locating ring of LP front pedestal and steel bars of LP front and LP rear
centralising keys.
8. Prepare shuttering and grouting of the pedestals and LP base plates including
anchor plates of HP rear pedestal.
9. Prepare, install, align/ level both the LP girder along with their carrier plates.
10. Prepare , install and assemble LP front and rear end walls with the LP girders.
11. Level / align LP outer casing lower half as per the transverse and longitudinal axis
of the machine.
STEAM TURBINE
500 MW
ERECTION
ERECTION SEQUENCE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0303G Page No. 2 of 7
12. Install permanent packers of LP outer casing including their radial and axial keys.
13. Prepare and install LP inner outer casing along with gusset plates in position
14. Align LP inner outer casing lower half and level it. Install LP casing parting plane
platform .
15. Prepare and install LP front and LP rear lower half shaft seals housing and align it
provisionally.
16. Prepare and install LP rotor along with their bellows in position.
17. Align LP rotor radially and axially in position and record free run out of rotor.
18. Record/ Ensure radial and axial clearances of the LP casing including rotor float
including fitting of final axial keys of the LP inner casing .
19. Box up LP inner inner casing and heat tighten the parting plane bolts.
20. Box up LP inner outer casing .
21. Prepare and place HP module in position on temporary packers.
22. Transfer the load of HP rotor on bearings from the transport device and align it
radially and axially.
23. Check free run out of HP rotor on journal and coupling face including its float.
24. Prepare and place IP module in position on temporary packers. (In case IP module
is sent to site in disassembled condition, refer Instruction T1-08-0606G.
25. Loading of IP rear end of the shaft on bearing and removal of transport device.
26. Provisionally align HP , IP and LP rotor .
27. Couple HP / IP rotor on temporary Bolts and align rotor / casing radially and axially.
28. Record/ Ensure IP rotor float by shifting HP casing axially.
STEAM TURBINE
500 MW
ERECTION
ERECTION SEQUENCE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0303G Page No. 3 of 7
29. Conduct Horn drop test of HP casing without any radial and axial keys and pipe
lines.
30. Conduct Horn drop test of IP casing without IP inlet upper half pipe lines.
31. Assembly of breech nut of HP casing and Main Steam Stop & Control valve
assembly.
32. Erection of Reheat Stop & Control valve assembly.
33. Weld IP inlet upper half pipe and record Horn drop values without radial-axial keys.
34. Alignment of HP/IP/LP rotors and their coupling on temporary bolts including its
couple runout.
35. Swing check of HP rotor on its front end with temporary alternate bolt tightened on
HP/IP coupling .
36. MOP alignment and its doweling.
37. Reaming/honing of HP/IP and LP/IP coupling including fitting of final coupling bolts.
38. Fixing of axial position of shaft and assembly of thrust bearing including its colour
matching.
39. Roll check of HP/IP casing and fixing of radial and axial keys of the casing (Casing
final packers need not to be put at this stage).
40. Assembly of bearings and checking of all clearances including fittings of side pads
of bearing, yoke keys etc.
41. Turbovisory works in all the pedestal i.e. assembly and calibration of thrust bearing
axial shift, LP rotor expansions pick up, Hall generator and thermocouples of
bearing .
42. Preparations of the bearing for oil flushing.
STEAM TURBINE
500 MW
ERECTION
ERECTION SEQUENCE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0303G Page No. 4 of 7
43. Oil flushing of the machine and normalizing the bearing after oil flushing.
44. Preparation and floating of TG deck as per Instruction No. T1-08-0909G.
45. Decoupling of HP / IP, LP/IP, LP/Gen., Gen./Exciter coupling and rechecking of
alignment/catenary after floating of TG deck spring.
46. Final tightening of HP/IP, IP/LP , LP/Generator and Generator / Exciter coupling
after correcting the alignment including their couple run out and swing check of
rotor on HP Front and exciter rotor.
47. Checking /Correction of LP shaft seal clearance after floating of TG deck with CW
pump in operation and water in the hot well of condenser upto operating level.
48. Roll check of HP, IP casing in up and down direction only with TG deck in floating
condition and CW pump in operation including water in hot well upto normal level.
49. Assembly of final packers of the HP, IP casing after completing the roll check in up
and down direction.
50. Recording of final Horn drop of HP and IP casing after completing the welding of
HP inlet, HP exhaust , IP inlet and Cross around piping.
51. Preparation and boxing up of LP casing after competing the full Roll check of LP
casing and fitting of final casing packers and radial keys.
52. Barring gear.
STEAM TURBINE (500 MW)ERECTION
ERECTION SEQUENCE
Bharat Heavy Electricals LimitedRev 00, 7-98
Ti-08-0303GPage NO.5 of 7
ERECTION SEQUENCE BAR CHART OF 500 MW TG WITHSPRING LOADED FOUNDATIONACTIVITY WEEK . -- 0 1 2 3 . . . 7 . . 10 11 12 13 14 " " 17 ,. " 20 21 22 23 24 " .. 27 .. " 30 31 32 33 34 .. .. 27 38 30 .. 41 42 43---- - ------- - --- - - --- ---- --- --- 1-------
1 Cleaning and checking of Turbine and Generator foundations as per the
transverse and longitudinal axis including their elevation.----1----- ----- f-- -- -- - .-
2 Prepare and install LP base plates, HP front pedestal, HP rear pedestal, LP front
pedestal, LP rear pedestal along with their anchor bolts and anchor plates.-
--------- -- -- -- -_. - - - -3 Provisionallyalignand levelallthe pedestal and LPbase plates as per the
transverse and longitudinalaxis includingtheir elevation.--
--4 Matching of anchor plates of pedestaland LP base platesto ensure their perfect
seating.-
---------- - ------ __on - - - 1--- - - I-- ---- -- I---5 Finallyalign and level HP front, HP rear, LP front and LP rear pedestalsalongwith LP base plates as per the transverseand longitudinalaxis including their -elevationand catenaryas per the design. n- -- 1-----r-- e--------------- . ----------------------- --- ---- _n_n ---- .-- ------- --. -- .--- -- ---.-
6 Prepareand install steel bars for LP casing centralising keys in foundationslabas per the requiredcenter line.
-1- ----------------------------- - ---- ---- -- 1---.- -.- ------- ------- - --- - -- --- 1- -- -- -.- I----7 Weld locating ring of LP front pedestaland steel bars of LP front and LP rear
centralising keys.-
1--- --8 Prepare shuttering and grouting of the pedestals and LP base plates including
anchor plates of HP rear pedestal.--------- --------------- -- --- --- -- . ---.- - -- .-. --- m ---- ---- --- --. n-- --.- --- -- --- -- -m 1---- -- _n_--- - .- ---- -- I---- - -- -.- ... no_-g Prepare, install,align/level both the LP girder alongwith their carrier plates.
. ----- - -- -- --10 Prepare, install and assemble LP front and rear endwalls with the LP girders.
- ----- -- -- --- --- 1---1----_no.-11 Level/ align LP outer casing lowerhalf as per the transverseand longitudinal -
axis of the machine. .- - +--- -- --- --- -- I--12 Install permanentpackers of LP outer casing including their radial and axialkeys. -
--_---__0- -- - .---- - -- -- I--- -- -- 1---- - n-13 Prepareand install LP inner outer casing alongwith gusset plates in position I--- f-- _-_0_-- -.-- 1----f--- r-- - - 014 Align LP inner outer casing lower half and level it. Install LP casing parting plane .
e.'em____._--_n_----_o_--_o_--- -- ---- ------ - _n_--- - ---- --- --- I--- 1------ - - -- -- -15 Prepare and install LP front and LP rear lower half shaft seals housing and align
I
-it proiirlally:.___-- ----------- -_._--- ____00- ----- ----- - - -0.._-. - ----- -- -- -0__----- - - - ----
16 Prepare and install LP rotor along with their bellows in position. -
STEAM TURBINE (500 MW)ERECTION
ERECTION SEQUENCE
ACTIVITY WEEK. - -> 0
:E;~:::~f~:';:~~:::":~:~~;::~;g~~~;;'::;""including fitting of final axial keys of the LP inner casing.
19 Box up LP inner inner casing and heat tighten the parting plane bolts.
20 Box up LP inner outer casing.
21 Prepare and place HP module in position on temporary packers~ +._+-+-+-I-J--22 Transfer the load of HP rotor on bearings from the transport device and align it
radially and axially.
23 ICheck free run out of HP rotor on journal and coupling face including-its float.
.,-~-'~ 'I 'J. '~.'~-81---'-+-~~I-~'j '~j."jn~'I-"I.'8-L::1 '8j ~~-~L'j.:~L"L2<l~l~" "I 281:101"'I ", '" '" '" '" '" 311381,., .., '" '" "I... - .. ,--.- .--
~1 'r--t--t t---I-t-~.---
---+--1--1--1----
'-~-=~[]~n..~It"---.--.-
Ad.-
1-+.-+--4-.
----..-. .--I--. .-I--~---
.---4 + 4"---~-' .t:.t-I-.( +~-~--24 IPrepareand placeIf' modliiE!inpositionontemporarYpackers.125Ii..oadingOrlPrearendoftheshafton bearingandremovalOftranportdevice.'-
-I-t-.t---,-c
--' '---'- r-~-
- -.4 .---.---.- I-+-
1. -- .. \---.---..----.---.-----.----- --+---1---1--1--
~
.
no_
-
-- -
.
--
t
-
"J
--
'l
' -
~
---
l
---
-.-~
-
tllil' -
-
-
l.t
I J26 Provisionallyalign HP ,IP and LP rotor. -- . - --
:: ~~:;~~~:~;'=;~~=;~~~'...;~:':~~- =; ;;-: =~ =;-- d--lJ;-H++-+-+-,-C<-~uct Horn drop test of HP casing without any radial and axialkeys and pipe
lines.
30 Conduct Horn drop test of IP casing without IP inlet upper half pipe lines.
31 Assembly of breach nut of Main Steam stop & ControlValve
I~ Erection of ReheatStop & Controvalveassembly. -:~~~==-===--=--t11:-ttt~I--1---1---1-- --.---.--33 Weld IP inlet upper half pipe and record Horndrop valueswithout radial.axial
keys.34lAlignment of HPiiPiLP rotorsand their couplingontemporarY boits-jnciudjng~s-"
couple runout.
35 ISwing check of"HProtoronltsfrontend with temporary alterriate bolt tightened
on HP liP coupling.36 IMOP alignment and its dowelling.
---
1-+-
-- -.-.--
-~-1--
L---
1~--1
~-+--+--+ I +---I I---
------.--
. I--+---
+~-t-t--~-++--I--j.-t-.+---l-t--1l tj-+-+~ ~.-- . --- ---+--.------
--" I--I"--~!---It:" ~-~.--._.
.
+--I-.++---! --I I I I 1~---I t--l I--+-+--+ t.~--
Bharat Heavy Electricals LimitedRev 00, 7-98
Ti-08-0303G
Page NO.6 of 7
STEAM TURBINE (500 MW)ERECTION
ERECTION SEQUENCE
Bharat Heavy Electricals LimitedRev 00, 7-98
Ti-08-0303GPage NO.7 of 7
ACTIVITY WEEK --. 0 1 2 3 4 . . 7 . . ,. 11 12 13 14 " ,. 17 ,. " 20 21 22 23 24 ,. ,. 27 28 28 .. 31 32 S3 34 ,. ,. 27 ,. " 40 41 42 .,
37 Reaming/honing of HP/IP and LP/IP coupling including fitting of final coupling
.- -.
bolts.--
38 Fixing of axial position of shaft and assemblyof thrust bearing including its....
colour matching.-
39'.. .- -.. I- -
Roll check of HP/IP casing and fixing of radial and axialkeys of the casing(Casing final packers need not to be put at this stage).
40 Assembly of bearings and checking of all clearances including fittings of sidepads of bearing,yoke keys etc.
--
41 Turbovisory works in all the pedestal i.e. assemblyand calibrationof thrustbearing axial shift,LP rotor expansionspick up, Hall generatorand -thermocouples of bearing.
42 Preparationsof the bearing for oil flushing. -43
.--- -..Oil flushing of the machine and normalizing the bearing after oil flushing.
44 Preparation and floating of TG deck as per the laid down procedure.
.-._- -45 Decouplingof HP/IP, LP/IP,LP/Gen.,GenJExcitercouplingandrecheckingof
alignment/catenaryafter floating of TG deck spring.-
46 Final tightening of HP/IP, IP/LP , LP/Generatorand Generator/ Excitercouplingafter correcting the alignment including their couple run out and swing check of
--rotor on HP Front and exciter rotor.
47 Checking /Correction of LP shaft seal clearance after floating of TG deck withCW pump in operationand water in the hot well of condenserupto operatinglevel. -
48 Roll check of HP, IP casing in up and down directiononly with TG deck in -floating condition and CW pump in operationIncludingwater in hot well uptonormal level. .
49 Assembly of final packers of the HP, IP casing after completingthe roll check inup and down direction.
50 Recording of final Horn drop of HP and IP casing after completing the welding of -HP inlet,HP exhaust, IP inlet and Cross aroundpiping.
51 Preprationand boxing up of LP casing after competingthe Roll check of LP -casing and fitting of final casing packers and radial keys.
52 Barring gear. -
0sep.doc
ERECTION PROCEDURE
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 1 of 24
1. CHECKING OF FOUNDATION BEFORE CASTING
1.1. Customer to provide, center line and elevation point.
1.2. Check positioning of all the inserts and fixed points with respect to center line in transverse and longitudinal direction as per BHEL Hardwar drawings.
1.3. Check elevation of all points.
1.4. Check verticality of all the pipe sleeves with the help of plumb.
1.5. Ensure proper locking of all the insert and fixed points before grouting.
1.6. Ensure leveling on the fixed points of LP girder and LP rear pedestal.
1.7. Preserve machined surfaces of all the fixed points against any damages due to Improper handling.
1.8. Ensure proper flatness of the bottom seating plate of all the inserts.
1.9. Ensure proper stiffeners in all the vertical and horizontal embedment provided for various purposes like hangers and supports etc.
1.10. Ensure proper cleaning of the area before casting.
1.11. Remove all unwanted material.
NOTE: In case of spring loaded TG deck refer Installation Instruction
No. T1-08-0909G prior to positioning of inserts etc.
2. CHECKS DURING CASTING/POURING OF CONCRETE
2.1. Casting of foundation\TG deck should be carried out immediately after inspection of the foundation\TG deck i.e. within 3-4 days after final inspection to avoid any disturbance to the inserts and fixed point.
2.2. Ensure no disturbance to the insert etc. during pouring of concrete while vibrators are used.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 2 of 24
2.3. About 15-20 mm extra concrete may be left on top on all the pedestals and LP base plate area for chipping/cleaning purpose at a later date.
2.4. Close all the pipe sleeve from top to avoid entry of concrete inside. Alternately the pipe sleeve should be filled with sand.
3. CHECKING OF FOUNDATION AFTER CASTING
3.1. Clean complete foundation and remove all shuttering etc.
3.2. Ensure there is no loose concrete layer in the region where the pedestal and base plates are to be laid. No repair should be done in this region without consulting the turbine erection engineer.
3.3. Cover all the opening before checking any dimensional measurement to avoid any accident.
3.4. Establish a suitable longitudinal axis considering the fixed point of the LP rear pedestal and various pipe sleeves / inserts.
3.5. Establish a transverse axis as 90 degree with the help of the odolite.
3.6. Measure pitching/elevation of all the inserts and fixed points.
3.7. Measure elevation of all foundation on different pedestal and LP base plate area.
3.8. Check level of LP rear pedestal fixed points and if required correction may be carried out.
4. PREPARATION OF FOUNDATION FOR PLACEMENT OF
PEDESTALS AND BASE PLATES:
4.1. Foundation are to be cleaned and loose concrete are to be chipped off.
4.2. Maintain elevation of foundation to ensure correct thickness of non-shrink grout.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 3 of 24
4.3. A reference point for elevation in respect of machine center line (equivalent to LP rear pedestal) is to be maintained at a proper place. This point is to be preserved with proper protection. For making reference point a one side ground plate of about 200 x300 x20 mm may be used. This may be welded on a I-beam near Generator. The ground position of the plate is to be kept on top side and all elevation are to be transferred from this point with the help of water level jar. A correct elevation reading is to be punched on this plate. This reference point is to be used only during the turbine erection period.
4.4. Clean and deburr piping sleeves of the foundation on ID/OD of the pipe.
4.5. Ensure all corners of the foundation remains perfect during chipping of extra concrete of foundation.
5. PLACEMENT OF PEDESTALS
5.1. Open and clean the pedestal.
5.2. Ensure there is no paint/oil on bottom face of the pedestal sole plate.
5.3. Ensure there is no paint on inside surface or the pedestal and if required sand blasting may be carried out at site.
5.4. Ensure correct fitting/clearance of locating rings of LP rear pedestal.
5.5. The half bore error of pedestals is punched by manufacturing unit however in case it is not there, measure and punch half bore error of pedestal in left/right side of the pedestal. If the error is nil then this may be punched as zero-zero.
5.6. Ensure that the pedestal parting plane is feeler tight after tightening all the parting plane bolts. If required, colour matching may be carried out but scraping/cutting is to be done on upper half cover only.
5.7. Check proper colour contact of spherical/cylindrical supports of the bearing with the pedestal.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 4 of 24
5.8. Check contact between spherical Torus piece of bearing and spherical/cylindrical seat. In case of any variation in contact no scraping/cutting to be carried out at site and this may be referred to manufacturing unit. Also refer T1-08-0808G. Check centering of individual bearing w.r.t. pedestal seal bores by fixing pianowire on individual pedestal.
5.9. Ensure cleanliness of all pedestal oil lines. Close opening of oil lines of pedestal to avoid any foreign material entering in these pipe lines during erection at site.
5.10. Weld MOP suction and discharge pipe lines in HP front pedestal as per the drawing before placement.
5.11. Assemble protection sheet in the foundation bolt holes of pedestals.
5.12. Assemble anchor bolts along with anchor plate of the pedestals. Ensure that there is good contact available to the backing plate with the foundation. If required colour matching/grinding may be carried out to achieve the contact.
5.13. Assemble protection sheet in the anchor bolt hole from bottom side of HP rear pedestal foundation to avoid entry of grout metal.
5.14. Ensure level of both anchor plate of H.P. rear pedestal with 70-90 mm gap for filling of grouting concrete.
5.15. Adjust height of the Anchor Bolts as specified in the drawing.
6. PLACEMENT OF LP BASE PLATE, OVER THE
FOUNDATION :
6.1. Clean all the four base plates.
6.2. Mark/punch center line on the base plate as per drawing.
6.3. Ensure proper cleaning of base plate on bottom side.
6.4. Put identification marks on each base plate to avoid any mistake in positioning of the same.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 5 of 24
6.5. Do colour matching of all the eight nos. carrier plate on both the faces.
6.6. Match LP base plate with the individual carrier plate.
6.7. Place all the four base plates in position along with their leveling screws and foundation bolts.
6.8. Provisionally align and level all the four base plates.
6.9. Assemble protection sheet in the foundation bolt holes.
7. ALIGNMENT OF PEDESTALS AND LP BASE PLATES
7.1. Provisionally align and level all the four pedestals including LP base plates with reference to the earlier marked longitudinal and transverse axis. The elevation reference is to be taken from the already positioned plate for this purpose.
7.2. Align and level LP rear pedestal and set the elevation as per machine center line.
7.3. Use piano wire arrangement with micrometer for centering of pedestal bore and use water level jar for setting of elevation. Use measuring tape to maintain pitching of the bearing from one pedestal to another. Pedestals are to be set in level condition on both longitudinal and transverse direction. Align and level HP front, HP rear and LP front pedestals. Elevation of the pedestals are to be set as per catenary of the machine considering the half bore error of the pedestal if any.
7.4. Align and level, LP base plates. Elevation of LP base plate is to be kept higher than the rear pair of LP base plate in line with catenary of rotor.
7.5. After alignment of LP rear pedestal weld the locating rings as mentioned in the drawing.
7.6. During welding of locating ring, ensure that there is no movement in the pedestal in any of the direction.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 6 of 24
8. GROUTING OF PEDESTALS AND LP BASE PLATES
8.1. Fill 3 to 8 mm washed Pea-gravel in all the anchor bolts sleeves. These gravel are necessary to give damping effect to the anchor bolts during operation of the machine.
8.2. Seal anchor bolts holes after filling of gravel to avoid any entry of grout metal. Medical tape may be used for sealing of these anchor bolt holes.
8.3. Clean foundation with compressed air.
8.4. Make shuttering of all the pedestal and LP base plates. Use thick polythene sheet inside the shuttering to give better finish and avoid moisture absorption by shuttering.
8.5. Shuttering should be made with maximum care to avoid any leakage of grout concrete. All sides of the shuttering are to be sealed either with some sealing compound or with thick mixture of grout material to avoid leakage of grout material.
8.6. Foundation are to be kept wet for about 6 hrs. before grouting.
8.7. Non shrinkage cement duly approved by BHEL is to be used for grouting of the pedestals and base plate.
8.8. Use fresh stock of the grouting material only and check the strength of the material before use.
8.9. During grouting, the mixture has to be poured from one end only and it has to flow to opposite end to avoid any blockage of air pocket.
8.10. Water curing is to be carried out for about 10 days duration.
8.11. All anchor bolts are to be stretched minimum after 21 days of grouting.
8.12. HP, IP & LP module placement work can be taken up after 24 hours of grouting of the pedestal and base plates.
8.13. For individual pedestal and base plate, grout mixture should be poured in one lot only.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 7 of 24
9. PLACEMENT OF HP MODULE IN POSITION
9.1. Ensure matching of all the four palms of the module where it is resting on the pedestals.
9.2. Ensure matching and parallelity of front and rear key block of the HP casing.
9.3. Assemble all four jacking screw of HPC and ensure their free movement.
9.4. Clean journals and coupling of the HP rotor.
9.5. Record journal dia, coupling hole sizes and spigot dia of HP rotor.
9.6. Lift module in level condition and place it in position by keeping it 3 to 5 mm toward front pedestal side.
9.7. During placement of module use temporary packers similar to permanent and additionally support it by four jacking screws.
9.8. Ensure load on all four packers with the help of some additional shims if required.
9.9. Install temporary radial and axial keys of the casing.
9.10. Prepare HP rotor for alignment (Ref. section 20 before placing the IP module.
10. PLACEMENT OF IP MODULE IN POSITION
10.1. Ensure matching of all the four palms of the module where it is resting on the pedestals.
10.2. Ensure matching and parallelity of front and rear key block of IP casing.
10.3. Assemble all four jacking screws of IP casing and ensure their free movement. If these jacking screw holes are provided with the bolts from factory then same are to be removed before placement of module.
10.4. Clean IP rotor on both sides including coupling and journal.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 8 of 24
10.5. Record spigot /recess, journal dia, and coupling hole sizes.
10.6. Lift the module in level condition and place the module in position by moving about 7 to 8 mm towards generator end. Use temporary packers for placement of module in position and additionally support the module with jacking screws.
10.7. Ensure load on all four packers with the help of some additional shims if required.
10.8. Provisionally align the casing on front and rear pedestal bore. Install temporary radial and axial keys of the casing with some shims.
10.9. Prepare IP rotor for alignment (Ref. section 20).
NOTE: In case IP module is sent to site in disassembled condition, refer
Instruction T1-08-0606G.
11. ASSEMBLY OF LP MODULE
This assembly can be divided in following sub assemblies:
11.1. Assembly of girder and end walls.
11.2. Assembly of LP inner inner and LP inner outer casing lower half.
11.3. Assembly / welding of LP outer casing.
Before starting assembly of LP casing in position, following works are also to be completed : - Positioning and welding of LP casing centering pin of front and rear side. - Positioning of key block of LP casing axial keys. - Positioning of all internal of condenser.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 9 of 24
12. POSITIONING AND WELDING OF LP CASING
CENTERING PIN
Two nos. centering pins are to be located below LP front and LP rear pedestal. Necessary pipe along with two sq. end plates are already provided in the foundation to take the radial load of the LP casing:
12.1. Plumb the center line from LP front and LP rear pedestal bore on both side over the square plate of the foundation.
12.2. Establish accurate position of the pin and put a punch mark at a required height and mark a circle and a controlling circle over all the four sq. Plates.
12.3. Dia of the circle must be equal to pin dia. A template equivalent to pin dia has to be made for this purpose with about 20 mm thick plate and a welded pipe for using as an handle. The template dia must be very accurate and same may be made on machine.
12.4. Make precise hole with gas cutting/grinding to match template on all four embedded plate. Ensure that the template is fitted with minimum clearance and hole center are perfect as per marking.
12.5. Drill hole of about 10 mm dia on one of square plate of LP front and on one plate of LP rear for air venting to avoid cracks during welding.
12.6. Insert both the pins and carry out the welding as per laid down procedure. Before welding set correct axial position of the pins.
12.7. Insert key block on both the pins and weld their locking ring also. Ensure proper clearances in key block before welding of its locking ring.
12.8. Preheating of 200 degree Celsius or more to be achieved before any welding. Dye penetrate test on root run and after final welding is to be carried out.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 10 of 24
13. ASSEMBLY OF GIRDER AND END WALL
13.1. Colour match side matching flange of girder with the surface plate.
13.2. Colour match seating flange of girder where it rests over the LP base plate.
13.3. Match and ensure parallality of axial key ways of girder.
13.4. Colour match side flanges of end wall.
13.5. Match and ensure parallality of key block of end wall.
13.6. Place left and right girder with carrier plate, spacer and lubrite packer on LP base plate.
13.7. Provisionally align and level the girders. Set height of the girder equivalent to machine center line maintaining catenary of the machine with the help of water level jar arrangement.
13.8. Assemble locking plate of the front and rear end wall to facilitate its assembly with the girders.
13.9. Assemble front and rear end wall with the girders and ensure perfect parting plane level during tightening.
13.10.Align, level LP outer casing and ensure contact of packers by colour matching/machining of spacer height.
13.11.Install LP casing radial and axial keys.
13.12.Assemble inner outer casing axial key blocks on left and right side of girder and dowel them.
13.13.Lock with tack welding all the vertical joint bolts.
13.14.Put a seal weld run between girder and end wall joint all around except on top face.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 11 of 24
13.15.Weld girder and end wall parting plane joint with argon welding. Before welding make a V groove with the help of a chisel and allow the projection of material on surface. Do not make the groove by grinding.
13.16.Do colour matching with a surface plate on all four corner where argon welding have been carried out.
14. ASSEMBLY OF LP INNER INNER AND LP INNER OUTER
CASING LOWER HALF
The LP inner inner casing lower half is received from factory in assembled condition with LP inner outer casing lower half.
14.1. Clean the casing and check all the threaded holes.
14.2. Do colour matching on all four corners of the casing where it rest over the girder.
14.3. Colour match all eight carrier plates of inner casing on both side.
14.4. Assemble all carrier plates on girder and do the colour matching with individual carrier plate.
14.5. Prepare Gusset plate of front and rear side with temporary radial keys for fitting in LP inner casing.
14.6. Level and lift LP inner outer casing and assemble/weld both the gusset plates with the help of some temporary support.
14.7. Lower the casing in position over the carrier plates fitted with spacer and lubrite packer.
14.8. Provisionally align the casing radially and axially.
14.9. Support the gusset plate with the help of screw jack (about 10-15 tons) on front and rear side by taking support from condenser stiffeners. Screw jack is to be unscrewed after box-up.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 12 of 24
14.10.Adjust the height of the LP inner outer casing as per center line of the machine and then level it with the help of water level jar arrangement.
14.11.Ensure that all the eight packers have good contact. Loading of each packer is to be ensured.
14.12.Lower the casing by about 2 mm on all the eight packers with the help of shims for placement of LP rotor to avoid any fauling during placement of rotor.
14.13.Fit and weld all gusset plate stiffener pipes except pipe between LP inner outer casing and condenser. Do not make any weld connection between condenser and any of these stiffeners till neck welding of the condenser is over.
15. PLACEMENT OF LP ROTOR
15.1. Measure journal dia, spigot dia and coupling hole sizes.
15.2. Ensure centering of temporary bearing support in the LP front pedestal for placement of LP rotor.
15.3. Place LP rear bearing in position.
15.4. Prepare shaft seal compensator along with gaskets (Gasket to be installed in fully ring shape only ) and position them on LP rotor with the help of supplied supports of compensator.
15.5. Lift LP rotor with the supplied lifting beam in perfectly level condition and place it in position. During lowering of rotor ensure radial clearance with the help of long feeler gauges in the LP casing.
16. WELDING OF LP OUTER CASING
The welding of LP outer cover is to be carried out before placement of LP Rotor in position to avoid damage to the rotor.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 13 of 24
16.1. Colour match and remove all high spots of the matching flange of the LP outer casing.
16.2. Ensure good contact between parted diffuser of LP front and LP rear cover.
16.3. Colour match and remove all the high spots of the parted diffuser/vertical face to ensure good contact with the compensator at a later stage.
16.4. Colour match and remove all burrs and high spots from parting plane of LP outer casing.
16.5. Side flange of LP front and rear cover are to be ensured in right angle to achieve good contact with their matching flanges.
16.6. Place LP front LP rear cover along with parted diffuser and ensure feeler tight joint after tightening the parting plane bolts. The joint must be feeler tight just after normal tightening of bolts. Do not over tighten parting plane bolts.
16.7. Ensure matching of parted diffuser face on both side of LP casing. If necessary colour matching may be carried out to achieve a feeler tight joint.
16.8. Drill/ream all the parting plane holes as per drawings and install all dowel pins.
16.9. After fixing of LP front and rear cover measure the dimension for positioning of both the center flanges. The dimension are to be recorded in such a way that there is no clearance after fitting of center flanges in position on both side with the LP front and rear cover. The center flanges are supplied in extra length on both sides from the factory and final length are to be maintained at site only.
16.10.Drill/ream dowel pin holes in center flanges and install all dowel pins in position. Ensure drilling and reaming of all dowel pin holes to equal depth.
16.11.Fit both the center pieces of the cover in position.
16.12.Achieve the fitting clearances for welding as per laid down procedure.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 14 of 24
16.13.Weld/lock LP upper half flange with respect to lower half casing with the help of metal cleats to minimise the distortion during welding of LP cover. The cleats may be welded at an interval of about one meter distance.
16.14.Carry out the welding as per the following welding procedure.
17. WELDING PROCEDURE
17.1. Tack weld the crowned seam joint. permanently welding approx. 100 mm at the generator end of the joint.
17.2. Opposite tack welded radial joint 2, permanently weld approx. 100 mm of the crowned seam joint, pos. 1, staggering the two weld ends to ensure a perfect transition when the crowned seam joint is finish welded.
17.3. Tack weld the crowned seam joint at regular intervals with a tack of 5T and pitch of 25T.
17.4. When welding radial joint 2, shell plates 1 & 2, tacked together, rest on but are not tacked to the retaining strip in the region of joint 1, so that any shrinkage occurring during welding of seam 2 is not obstructed.
17.5. The tacking & welding sequence applies for all shells courses.
17.6. Weld radial seam at TE according to welding sequence plan.
17.7. Align, adjust and tack weld radial seam at GE.
17.8. Weld radial seam at GE according to welding sequence plan.
17.9. Weld crowned seam joint.
17.10.Align shell courses on joint strips and tack weld,
17.11.Weld on joint strips from center & ends of shell plate.
17.12.Insert pins in top half casing, release top half casing and lift to insert and tack filler piece between joint strips.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 15 of 24
17.13.Unbolt top half casing and lift in order to weld and finish - machine filler pieces in the region of the joint surface.
17.14.Check welds according to specifications.
18. ALIGNMENT AND COUPLING OF LP-IP & HP ROTOR
LP rotor is to be aligned on pedestal seal bore and LP inner outer casing is to be centralised in such a way that enough clearances are available to LP rotor, during alignment. Now this alignment activity of all the three rotor can be divided as below :
18.1. Preparation of HP rotor for alignment.
18.2. Preparation of IP rotor for alignment.
18.3. Preparation of LP rotor for alignment.
18.4. Alignment of LP-IP & HP rotors.
18.5. Reaming, honing of the coupling holes.
18.6. Balancing of coupling bolts weight.
19. PREPARATION OF HP ROTOR FOR ALIGNMENT
19.1. Align HP rotor with reference to front and rear pedestal seal bore reading. If required move complete HP module along with the rotor.
19.2. Fix temporary radial and axial key of the casing on both front and rear side of the casing. Remove HP front upper half transportation device.
19.3. Lift module by 0.20 mm on front side by putting additional shims in front packers.
19.4. Insert HP front bearing in position.
19.5. Reduce 0.20 mm shims gradually and ensure about 0.10 mm load on the rotor. If required further lower the front side of the module to achieve the loading on bearing by about 0.10 mm.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 16 of 24
19.6. Remove HP front lower half transport device gradually and ensure no movement between HP casing and rotor. If necessary adjust shims of HP casing front packers.
19.7. During loading of bearing always ensure that the rotor is not fouling inside the casing with the shaft seals. This may be ensured by checking with feeler gauge also.
19.8. Check axial position of HP rotor in front side on left; right and top position from the rotor reference point to the HPC as given in the shop protocol.
19.9. Insert and load the bearing in HP rear end in similar way as carried out in case of HP front end and record axial position of rotor as per shop protocol.
19.10.Lock axially HP rotor with some fixture along with the arrangement of jacking screw for movement of rotor. This fixture may be mounted on rear pedestal. Before locking of rotor ensure axial position of the shaft.
19.11.Center HP shaft with reference to HP casing front and rear spigot. If necessary, move the casing readily to achieve the centering. A fixture can be fabricated at site for mounting the dial gauge on both the end of the rotor to check the centering of the shaft.
19.12.Use thick oil during rotation of shaft on the bearing.
19.13.Protect bearing from any of the dust particles. It is recommended to place upper half of bearing in position to avoid dust and any other damage to the shaft journal.
19.14.Realign the rotor shaft with respect to pedestal seal bore and if necessary adjust the shims below spherical support of the bearing.
19.15.Care should be taken during alignment that radial and axial clearances between rotor and casings does not get bridged.
19.16.Check HP rotor radial run out on journal and coupling.
19.17.Check axial run out on thrust collar and both the coupling faces of HP rotor.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 17 of 24
19.18.Check axial float of the rotor. Compare values with shop protocol values. (Ref. T1-08-0802G). Deviations to be reported to Manufacturing Unit.
20. PREPARATION OF IP ROTOR FOR ALIGNMENT
The IP module is also to be prepared in line with the HP module. However as IP rotor is provided with one side bearing and opposite side is coupled with the HP rotor without a bearing, extra care is necessary during alignment of rotor in IP casing. The additional point which are to be taken care are explained below :
20.1. Place IP rotor rear end on bearing similar to the HP rotor and remove transportation device.
20.2. Provisionally align HP/IP rotors and couple on temporary bolts by moving both the modules. During coupling of the rotors, the transportation device of IP front end is also to be taken out.
20.3. Check axial position of rotor w.r.t. IP casing and adjust as per shop protocol.
20.4. Check centering of IP rotor front and rear end w.r.t. IP casing (similar to the HP rotor centering check).
20.5. Check float of the IP rotor. Compare values with the shop protocol values. (Ref. T1-08-0802G). During checking of float ensure HP casing is not fouling with HP rotor. If required HP casing may be moved axially for this purpose.
20.6. Check facial runout on IP rear coupling face and radial runout on journals and couplings.
21. PREPARATION OF LP ROTOR FOR ALIGNMENT
21.1. Provisionally align LP rotor in pedestal seal bore placing the front end of shaft on auxiliary bearing and rear end on bearing.
21.2. Align LP inner outer casing radially with the help of long feeler gauges and install temporary radial keys in the gusset plate.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 18 of 24
21.3. Record all the radial and axial clearances of the LP casing without coupling the LP-IP rotor. Variation if any in radial or axial clearances are to be corrected/approved at this stage.
21.4. Remove shims from the front end of auxiliary bearing and keep rotor on lifting tackle.
21.5. Record radial run out of LP rotor coupling and journal and axial run out of the coupling faces of the both end.
21.6. Record float of the LP rotor by moving the LP inner outer casing lower half.
21.7. After ensuring the radial and axial run out of the LP rotor the LP inner outer casing can be boxed up. Parting plane bolts of LP inner-inner casing are to be heat tightened.
22. ALIGNMENT OF HP, IP AND LP ROTORS
22.1. Ensure radial and axial runout of all the three rotors are individually in order. If necessary individual rotor module can be taken out for correction of coupling face runout. Any variation on radial runout of rotor is to be referred to the factory.
22.2. Match coupling faces of two rotor as per the axial face reading of the rotor. Ensure that the higher point of the rotor coupling face and lower point of another rotor coupling face are matched together. This is to be compared with shop protocol also.
22.3. Preliminary align radially and axially all the three rotors and shift them in spigot along with the casing to avoid fouling of rotor inside the casing.
22.4. During alignment achieve left and right movement of the rotor with the help of shims in spherical / torus piece of the bearing. The up and down movement of the rotor is to be achieved with the help of shims in the cylindrical/spherical support of the bearing . The adjustment of shims in the bearing should be within the permissible limits only.
22.5. Ensure during alignment that the catenary of the shaft is maintained.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 19 of 24
22.6. Check/record spigot clearance of HP-IP and LP-IP rotors by actually moving them in spigot.
22.7. Install four nos. supplied bolts along with one/two pins in HP-IP and LP-IP coupling. Hand tighten the coupling bolts by keeping a gap of > 1.00 mm in coupling faces for alignment.
22.8. Rotate the rotor system and record the coupling gap at 90 Deg. interval on left, right and top position. Ensure that the coupling, bolts and pins remain free while recording the gap of the coupling for the alignment purposes.
22.9. Check swing check value of the HP rotor with alternate bolts in position. The above value must be within the prescribed limit only otherwise a correction must be carried out at site in consultation with designer.
22.10.Ensure free movement of rotor on their bearing. Do not rotate the rotor if it is tight during its rotation.
22.11.Ensue that the coupling holes are properly aligned to avoid unnecessary enlargement of holes.
22.12.Ensure HP-IP-LP rotor radial run out after tightening with alternate clearance bolts. Release the couplings for reaming / honing of couplings.
22.13. In case of spring loaded TG decks, refer alignment procedure T1-08-0909G
23. REAMING / HONING OF COUPLING
23.1. Ensure that there is no disturbance on coupling during reaming/honing operation.
23.2. First ream/hone two opposite holes of the coupling and install two pins/bolts with sliding fit and then take up all other holes.
23.3. Enlarge coupling holes to the minimum possible diameter and try to make all the holes to same dia.
23.4. Ensure that the finished holes are straight and there is no banana shape. This can be ensured by checking hole with a straight ground finish pin having 0.02/0.03 mm clearance.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 20 of 24
23.5. The length of the pin should be equal to the bolt length. In case, few holes have gone considerably over size during reaming/honing at site/works, do not enlarge all the holes. As a special case in such cases these few holes may be left as oversize.
23.6. Ensure that the holes during reaming/honing are perfectly finished as ground bore and size obtained should be within 0.005 mm. Ensure all the coupling bolts are fitted within 0.02/0.03 mm clearance with sliding fit and bolts are to be ground within an accuracy of 0.005 mm.
23.7. Coupling bolts are not to be hammered in the holes and these are to be fitted with thumb pressure only.
23.8. Do not decouple the coupling in any case without ensuring the fitting of all the coupling bolts.
24. BALANCING OF COUPLING BOLTS
After fitting the coupling bolts in all the holes these are to be balanced within 5 gms accuracy and an accurate balance which can take a load of about 20 kg. may be used. During balancing of coupling bolts following points are to be taken care.
24.1. Final balancing of the coupling bolts are to be done along with the coupling nut of individual bolt.
24.2. If all the coupling bolt hole sizes are same before/after reaming and honing then all the bolts can be kept of equal weight.
24.3. If necessary adjust the weight of the bolts by machining the metal from the bolt head.
24.4. When the holes of the coupling are of different sizes then it must be seen that whether excess enlargement have been done at site or works. In such cases if excess cutting have been done at site in a particular hole then coupling bolt with excess weight are to be used. The amount of excess weight must be equivalent to the excess enlargement of hole at site. If a particular hole of excess dia. is noticed from factory then it is assured that the particular rotor is balanced with excess dia hole and there is no need of providing excess weight bolt at site.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 21 of 24
25. COLOUR MATCHING OF THRUST BEARING
After completion of reaming/honing and preliminary tightening of the coupling bolts, the colour matching of the thrust bearing pad have to be carried out with respect to the thrust collar of the HP Rotor. During colour matching a good contact on all the pads of front and rear side are to be ensured with respect to rotor collar by moving the rotor in +/- direction during its hand rotation. Following points are to be taken care during colour matching.
25.1. Thrust bearing must be axially locked with the help of axial keys during the colour matching of the pads. Axial keys to be fitted while finalising the alignment of thrust bearing with rotor collar without pads.
25.2. Few drops of oil is to be put on journal portion of the thrust bearing during rotation of rotor to ensure that the oil is not entering in pad portion of the bearing.
25.3. Colour is to be applied on the thrust collar of the rotor.
25.4. If necessary move the spherical support of the bearing pedestal to ensure the equal thickness of the pads before fittment of axial keys of the bearing.
25.5. During moving of the spherical support in front or rear direction ensure that there is no left - right movement to the support otherwise that may cause misalignment of the bearing.
25.6. After colour matching of the thrust pad the axial zero position of the rotor is achieved and this can be taken for all other future reference for setting of axial position of HP, IP & LP casing.
25.7. HP, IP and LP lower casing are to be set axially after fixing the axial position of the rotor and their final axial keys can be installed at this stage.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 22 of 24
26. ALIGNMENT OF HP, IP & LP CASING
After completion of colour matching of the thrust bearing pads the casing alignment work can be taken up. The following points are to be taken care while aligning HP, IP and LP casing.
26.1. The roll check have to be carried out in HP, IP and LP casing to ensure the correct radial clearances of the casing.
26.2. TG deck springs are to be kept in floating condition while recording the roll check of LP casing. However the roll check of HP/IP casing may be carried out before floating of TG deck for fitting of their radial keys but up and down roll check of HP/IP casings are to be done with TG deck in floating condition as per the procedure TS/ST/ 01/0008/00/96.
26.3. Ensure that there is no obstruction in the movement of LP inner casing due to welding of any of extraction piping. The one of the joint of extraction piping may be left free till completion of roll check of the casing.
26.4. The welding of steam inlet pipes between LP inner casing and LP girders are to be taken up after completion of roll check of the casing.
26.5. HP, IP and LP casing are to be fitted with final packers and axial key immediately after the roll check. During fitting of casing axial keys and palm packers ensure proper contact on lubrite coating of the keys/packers to avoid any damage of these coating during operation of the machine,
26.6. After completion of fitting of final keys and packers only the casing are to be cleared for further works of welding of various pipe lines.
26.7. The gland steam, balancing leak of lines, steam inlet and exhaust pipes are to be welded with HP casing after fitting of final axial keys and packers of the casing.
26.8. Center HP rotor w.r.t. casing front and rear spigots. Compare the readings with shop protocol and record the readings.
26.9. Offset center line of the HP, IP & LP casing w.r.t. respective rotor center line as per recommended logsheet.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 23 of 24
26.10.Check/record LP diffusers centering readings after roll check of the casing.
26.11.Before roll check of LP casing all the stiffener pipe welding work must be completed. Refer T1-08-0909G.
27. FINAL TIGHTENING OF COUPLINGS
In case of spring loaded foundation after completing all other works the HP / IP , IP/LP , LP/GEN , GEN/EXCITER couplings are to be reopened and realigned after completing the reaming /honing . The rotors alignment are to be checked with TG deck in floating condition as per the laid down procedure. After checking of alignment /catenary the final couplings are to be tightened including their coupled run out and swing check of rotors on HP front and Exciter end of the shaft.
28. BOXING UP OF LP INNER INNER AND LP INNER OUTER
CASING
The boxing up of LP inner inner and LP inner outer casing can be taken up before starting the alignment of HP-IP & LP rotor for coupling work. The following points are to be taken care before/during boxing up of these two casings.
28.1. Ensure matching of all the parting plane holes, fitting of cap nuts and accessibility of spanner .
28.2. Ensure feeler tightness of the parting plane joint of both the casing.
28.3. Check/record all the radial and axial clearances of the casing.
28.4. Ensure proper cleanliness of the LP inner inner and LP inner outer casing.
28.5. Ensure adequate clearance between LP inner inner casing and LP inner outer casing to avoid any obstruction during expansion of the LP inner casing inside the LP inner outer casing during operation of machines.
STEAM TURBINE
500 MW
ERECTION
ERECTION PROCEDURE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0404G Page No. 24 of 24
29. BOXING UP OF LP OUTER CASING
During the boxing up of the LP outer casing following points are to be taken care.
29.1. Roll check of LP inner casing including the fitting of key, packers etc. must be finished.
29.2. All the works must be finished inside the LP casing before boxing up of LP casing including LP extraction pipe line works.
29.3. Ensure matching of all parting plane holes and feeler tightness of the joint before boxing up of the casing.
29.4. Ensure feeler tightness of bursting diaphragm flange joint before boxing up of the casing.
29.5. Ensure proper assembly of parting plane rubber cord.
30. FINAL HORN DROP CHECK
After completing the welding of HP inlet, HP exhaust, IP inlet, IP exhaust and other piping of HP/IP casing the final horn drop readings are recorded as per the laid down procedure mentioned in the manual for horn drop check. However the IP casing horn drop is also to be recorded with IP inlet upper half pipe welded with casing alone.
0sep.doc
GROUTING PROCEDURE
STEAM TURBINE
500 MW
ERECTION
GROUTING PROCEDURES
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-0505G Page No. 1 of 4
Grouting of turbine base plates, bearing pedestals, foundation frame with shrink-free
grouting compound is intended to ensure uniform transmission of the force and
vibration of the TG unit to the foundation.
Caution: Preparations for grouting, and grouting must be carried out with great care as it is no
longer possible to check and rectify the parts once they have been grouted.
CONBEXTRA GP-II or equivalent should be used as grouting compound. Further
details on the grouting depths, mixing time, quantity of water to be mixed, should be
refereed from the manufacturers brochures.
PROCEDURE
The foundation should be thoroughly cleaned. All foundation bolt holes should be filled
with pea-gravels and covered at the top to avoid entry and sticking of grouting
materials with the bolts.
NOTE:- Remove all rust preventive paints, grease etc. from surfaces by wire brushes
to ensure proper adhesion of the grouting compound.
SETTING UP OF SHUTTERING
Set up shuttering from suitable material in box like manner around the foundation plates
and secure it firmly.
NOTE:- Shuttering must be sealed well to prevent the liquid grouting compound from
running out. This can be done by using paste of grout materials and allowing it sets.
STEAM TURBINE
500 MW
ERECTION
GROUTING PROCEDURES
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-0505G Page No. 2 of 4
As the grouting compound remains workable for a limited time, to prevent air bubbles, it
must be poured from one side only. For this, a large size filling heaped should be used.
PREPARATION OF GROUT MIX Following measure must be taken before commencing mixing and grouting due to
limited time that the grouting compound remains workable.
Keep the foundation moist for at least 6 hours before the grouting.
-Set up mixers in the immediate vicinity of the foundation plates. The capacity of the
mixers, should be adequate to cope with the quantity of mixed cement required at a
time. Two or more mixers are required for grouting of bearing pedestal foundation
frame.
-Store the grouting compound next to mixer.
- Ensure that the compound is well within its expiry date.
-Provide the water hose and measuring pans near the mixers.
-Ensure uninterrupted power supply to the mixers and EOT Crane for handling the
ready mix.
-Provide adequate workmen for grouting.
-Ensure six empty cubes for filling the grout for strength testing. This is to be done as
per recommended FQP
STEAM TURBINE
500 MW
ERECTION
GROUTING PROCEDURES
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-0505G Page No. 3 of 4
-Take 80 % of the required water quantity first in the mixture. Then add gradually the
grout, ensuring that no lumps are found. It is desirable to add five or six large sizes
stones to break any lumps. Finally add the balance quantity of water and mix for at-
least another five minutes
This mixture is then taken into through heaped mesh. The hopper must be big enough
to make the full quantity of grout.
Than pour the grout with a hose through the filling hopper until the desired height is
achieved on the opposite side. (Flow may be accelerated by moving the grout in the
filling nozzles underneath the plates with chains or material strips.) This should be done
only if it is permitted by the grout supplier.
CAUTIONS
1. Do not use concrete vibrator.
2. Pour grout from one side only so that no air bubbles remains entrapped in the
grouting compound.
3. Due to short workability times, never mix more grouting compound at one time than
is required for one plate or volume to be grouted.
4. Pour in one continuous operation, without interruption.
5. Do not install any woven steel fabric reinforcing mats beneath the foundation plates.
6. It is desirable that in hot weather the grouting is done in the evening so that ambient
temperature is low during the initial setting time.
7. Water should be clean and free from dissolved chlorides, as these weaken the
grout.
8. In case during the grouting operations heavy leakage is observed from the shuttering
that cannot be plugged during the grouting operation, and the level of grout has
fallen below the base plate level, it is desirable to wash out the complete grout. The
operation should be repeated after the shuttering has been rectified.
STEAM TURBINE
500 MW
ERECTION
GROUTING PROCEDURES
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-0505G Page No. 4 of 4
NOTE:- After at-least 72 hours setting time, work may be commenced on pre-
tensioning of the foundation both.
After the grouting compound has set (approximately. 24 hours after grouting), remove
all shuttering and smooth off the excess grout. The grouting compound is subjected to
compressive forces only. Resultant hair cracks are insignificant with regard to TG
stability. These can be avoided by covering the exposed areas of grout by polythene
sheets to avoid excess loss of moisture during initial setting.
0sep.doc
ASSEMBLY OF
IP MODULE
AT SITE
STEAM TURBINE
500 MW
ERECTION
ASSEMBLY PROCEDURE OF
IP MODULE AT SITE
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0606G
Page No. 1 of 4
1. ASSEMBLY PROCEDURE OF IP MODULE
Due to oversize dimension of the IP module (M30 - 63) and its limitation in
transportation from Hardwar to site, the same will be dispatched to site in dismantled
condition in various packages after completing the shop assembly at Hardwar. First
the complete assembly of IP module will be done at works except the heat tightening of
parting plane bolts of IP inner and IP outer casing. Afterward complete casing will be
dismantled and dispatched to site.
The above machines are equipped with the spring loaded foundation deck. As a
general requirement initially all the turbine and generator rotors will be aligned/coupled
without floating the TG deck. The coupling will be opened and again re-aligned after
floating of the TG deck which is generally done after erecting all the components of
Turbine -Generator including their piping etc.
2. ASSEMBLY PROCEDURE AT SITE :
2.1. Place IP outer casing lower half in position after its cleaning over the
pedestals by supporting it on the Jacking screws at four corners of
casing. Additionally support the casing on temporary packers with the
pedestals also.
2.2. Align IP outer casing radially with the help of piano wire keeping the HP
rear and IP front pedestals seal as reference. Install temporary radial
keys of the IP outer casing with the pedestal.
2.3. Clean and install IP inner casing lower half along with its radial keys (Drg.
No. 0-106-01-27500 item No. 25) of front and rear end. During placement
STEAM TURBINE
500 MW
ERECTION
ASSEMBLY PROCEDURE OF
IP MODULE AT SITE
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0606G
Page No. 2 of 4
of inner casing support it on its four nos. Jacking screws. (Drg no. 0-106-
01-27500# 18). After placement of inner casing install its axial keys (drg
N. 0-106-01-27500 # 20). Before placement of inner casing install its
thermocouple, parting plane studs (drg N. 0-106-01-27500 # 33 & 34 ).
Seal ring of inlet insert & extraction line (drg N. 0-106-01-27500 #
3,4,9,10,13,14 ).
2.4. Place IP inner casing upper half in position and tighten alternate parting
plane bolts. During this process the heat tightening the bolts are not
necessary as this is required for ensuring the feeler tight parting plane
joints of the IP inner casing. The IP inner casing packers are also to be
installed during tightening of the P/P bolts and load of the inner casing is
to be transferred on these casing packers (drg N0-106-01-27500 # 17) fter
taking the load on the packers release the jacking screws of the IP
casing.
2.5. Loosen IP inner casing parting plane bolts and remove IP inner casing
upper half. Before loosening the IP inner casing parting plane bolts
support inner casing again on its four jacking screws and ensure that the
parting plane level of lower half inner casing is not disturbed and remain
same as it was kept after tightening of parting plane bolts with load on its
four packers.
2.6. Place IP rotor in position after its cleaning. The front end of the rotor is to
be placed over segment (drg N. 0-106-01-27500 # 21) and rear end of the
rotor on its bearing. During placement of IP rotor ensure that the rotor is
free on its seal fins of IP inner casing and necessary the IP outer casing
may be lowered on its rear end.
STEAM TURBINE
500 MW
ERECTION
ASSEMBLY PROCEDURE OF
IP MODULE AT SITE
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0606G
Page No. 3 of 4
2.7. Provisionally align and couple HP/IP/LP/ Generator rotors and complete
reaming /honing of the coupling including swing check etc. Before
rotation of IP rotor remove segment (drg N. 0-106-01-27500 # 21).
2.8. Set axial position of the IP rotor as per the zero position of the thrust
bearing and set axial position of the IP outer casing as per Hardwar
protocol on front and rear end of the IP outer casing.
2.9. Align radially IP outer casing with reference to the IP rotor on front and
rear glands. Recheck/correct axial position of the IP casing.
2.10. Assemble IP inner casing upper half end tighten the alternate parting
plane bolts to ensure feeler tight joint.
2.11. Do roll check of IP inner casing by moving the IP outer casing in left/right
direction and IP inner casing itself in up/down direction with the help of
inner casing jacking screws by removing the inner casing packers.
Ensure / compare roll check values with shop records.
2.12. Check IP rotor axial float in IP inner casing and compare with shop
protocol.
2.13. Loosen IP inner casing bolts and remove IP inner casing upper half.
2.14. Decouple and lift IP rotor for assembly of rear end shaft seals of IP
casing. The front end of the seals may also be assembled now of
afterward with the IP rotor in position.
STEAM TURBINE
500 MW
ERECTION
ASSEMBLY PROCEDURE OF
IP MODULE AT SITE
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0606G
Page No. 4 of 4
2.15. Place IP rotor in position and provisionally couple it with HP rotor on
temporary bolts. The IP rotor may not be coupled at its rear end with the
LP rotor at this stage.
2.16. Assemble and heat tighten IP inner casing upper half as per required
elongation of parting plane bolts. Install seal rings of inlet insert and
extraction pipe on IP inner casing upper half (drg N. 0-106-01-27500 #
1,2,7,8,11,12). The taper pins of IP inner casing parting planes are to be
removed before placement of IP outer casing upper half after the heat
tightening of IP inner casing bolts.
2.17. Assemble IP outer casing upper half and tighten the parting plane bolts to
ensure feeler tight joints. The heat tightening of the bolts are not to be
done now. Before placement of IP outer casing upper half assemble
casing shaft seals of front & rear end also.
2.18. Do roll check & float of completely assemble IP turbine and compare it
with factory protocol.
2.19. Heat tighten IP outer casing parting plane bolts to required values, and
carry out final roll check and float of completely assembled turbine.
NOTE : These are general instructions for the assembly of IP
module M 30 - 63 at site. However, depending on the site
conditions the same may be suitably reviewed, if necessary.
0sep.doc
SEALING &
ANTISEIZING COMPOUNDS
STEAM TURBINE
500 MW
ERECTION
SEALING & ANTISEIZING
COMPOUNDS
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0707G Page No. 1 of 1
SEALING & ANTISIEZING COMPOUNDS
SNO LOCATION FEATURES RECOMMENDED
COMPOUND
01 JOINT PLANE OF HPT IPT & VALVE CASINGS, GLAND BOXES & STRAINER HOUSINGS, BREECH NUT MATING FACE.
METAL TO METAL JOINT IN HIGH TEMPERATURE ZONE
BIRKOSIT
STAG B
MAGNESITE COMPOUND OF BHEL BHOPAL
02 JOINT PLANE OF LP OUTER CASING (WITHOUT RUBBER SEALING CHORD).
METAL TO METAL JOINT IN LOW TEMPERATURE ZONE
HOLDITE
LOCTITE 574
03 JOINT PLANE OF BEARING PEDESTALS, MOP CASING, VALVE SERVOMOTOR.
METAL TO METAL JOINT IN OIL ENVIRONMENT
HYLOMER
GOLDEN HERMETITE
VICTOR SHELLAC
04 THREADED FASTNERS INCLUDING, BREECH NUT THREADS, KEYS, PACKERS, DOWEL PINS U & I - SEAL RINGS IN HIGH TEMPERATURE ZONE.
HIGH TEMPERATURE
( < 350c) ANTISIEZING
MOLYKOTE P37
OKS 255
05 THREADED FASTNERS, KEYS, PACKERS, DOWEL PINS IN LOW TEMP. ZONE, COUPLING BOLTS SEAL SEGMENTS, HP/IP CASING PALM PACKERS, HP FRONT & REAR BEARING PEDESTAL PACKERS (OTHER THAN SELF LUBRICATED LUBRITE PACKERS).
LOW TEMPERATURE
( < 350c) ANTISIEZING
MOLYKOTE D 21
OKS 511
MGS 400
NOTE: NO COMPOUND IS TO BE APPLIED ON SELF LUBRICATED LUBRITE PACKERS.
0sep.doc
CRITICAL ACTIVITIES
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 1of 40
1. ASSEMBLY OF BEARING AT SITE
1.1. GENERAL DESCRIPTION
The KWU design machine are supplied with four bearings out of which three are
the journal bearing and one is combined thrust and journal bearing on H.P.
rear end of the shaft. All the turbine bearing are self aligning type and they
adjust themselves as per the catenary of the machine.
The function of a journal bearing is to support the turbine shaft , but the
thrust bearing support the shaft as well as work as a fix point for the turbine
shaft. The contact arrangements between bearing and bearing supports are of
two types i.e. sphere to sphere in HP front and HP rear bearing and torus to
cylindrical in other bearings.
The bearings are supplied to site after ensuring their contact at works. During
erection all the bearing are supplied to site in aligned and assemble condition in
their individual pedestal from the works. After alignment of the bearing in
their pedestal the seat of the bearing are doweled before dispatch to site.
In case of Thrust and Journal bearing the seat of the bearing neither doweled
from the works nor it is recommended to be doweled at site. The bearings
need preparation before placement of module in position at site. This can be
done even before the placement of pedestal in position for grouting.
1.2. ASSEMBLY PROCEDURE
1.2.1. After opening the pedestal remove and clean the bearing including its spherical/ cylindrical seat.
1.2.2. Remove oil guard ring and its duct and keep them in proper place for their storage at site.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 2of 40
1.2.3. Handle bearing carefully to avoid any damage to the babbit and its torus/spherical piece. During storage at site avoid direct loading of bearing on its torus. A thick rubber seat may be used during handling of bearing at site on its torus.
1.2.4. Ensure 0.03 feeler tightness on bearing parting plane. In case of any variation the matter may be referred to designers.
1.2.5. Measure bore dia of the bearing and journal dia at site and ensure the oil clearances. If any discrepancy is observed , designer may be referred.
1.2.6. Ensure torus/spherical contact with their seats at site. While checking the contact the seat may be bolted with their pedestal. In case variation contact from their specified diagrams are noticed then following may be carried out at site:-
In case of torus to cylindrical seats the line contact are recommended by designers. If these lines are not straight and are in angle then the bearing may be rejected straight way and sent to works for rectification. These line contact may be in a width of about 20 mm throughout on its seat leaving with area on both sides. The contact may be wide in Center and then gradually reducing on sides. In case there is no contact is achieved in the center and only sides are having contact then a feeler gap may be recorded in bottom. In case if the bottom is tight to a feeler of 0.03 mm the bearing may be accepted at site without doing any rectification.
In a reverse case the contact are achieved in center only though the 0.03 feeler is not going in the side. The bearing may be still accepted at site. In case if the feeler is going in the bottom or in sides by 0.03 mm. the bearing are not accepted at site and can be sent back for the rectification to the works. Similarly if the contact are intermittent on its seat but in a straight line and no feeler is going the bearing may be accepted. In case of very wide contact also the bearing may be sent back for the rectification. While checking these contact very light color may be put on torus of the bearing. Before sending back the bearing to the works the matter may be referred to designers and their concurrence is to be obtained. No scrapping/lapping is recommended in these bearing for improvement of the contact.
In case of spherical to spherical bearing the contacts are called in the center like a moon shape. In these bearings even full contact may be accepted. But in case if there are contact on sides
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 3of 40
and a feeler gap is noticed on center then the bearing may not be accepted.
In such cases if the gap is upto 0.03 mm then the matching/lapping may be carried out at site. But in case of higher gap the matter may be referred to designers. In case of reverse case if the feeler gap of 0.03 is noticed on both sides of the bearing the bearing may not accepted at site and matter may be referred to designers.
1.2.7. Before checking the contact between torus and its seat ensure that the seat is feeler tight to 0.03 mm without tightening of any bolts with the pedestal. If necessary this may be corrected with consultation of designers. Similarly ensure contact between torus\ spherical piece with bearing and in case of variation the matter be referred to designers and no correction is to be carried out at site without the approval of manufacturing unit.
1.2.8. Before checking the contact between torus/spherical piece with bearing and in case of variation the matter may be referred to designers and no correction is to be carried out at site without their recommendations.
1.2.9. The sizes of all the shims may be punched in bearing body and spherical/torus piece of the bearing. The number of shims are to be limited to 3-4 numbers only even after complete alignment of machine. A protocol for number of shims may be prepared.
1.2.10.Torus/spherical should not have any radial movement over its bearing. This can be seen after opening the torus from the bearing.
1.2.11. Check jacking oil lines of the bearing and clean them thoroughly. Ensure jacking oil lines fittings also for their male female threads etc otherwise this may create the oil leakage through these lines during operation of the machine. The jacking oil pocket in the bearing may be checked if necessary they may be corrected at site as per the drawings.
1.2.12. When ever JOP is not available, use always thick oil during rotation of shaft over bearing.The type of oil may be used as servo cylinder 1000 grade of IOC.
1.2.13.After installation of bearing in position the oil clearances may be checked after few rotation of the shaft. But the final oil clearances are to be checked after final coupling of the shaft. In case of variation in side oil clearances no cutting of babbitt metal is permitted at site. Any variation in clearances may be counter
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 4of 40
checked by measuring journal / bearing bore dia. Bearing bore dia is to be measured by assembling and tightening of top & bottom halves of bearing.
1.2.14.In case of skew side oil clearances, the investigation may be carried out, if necessary consult manufacturing unit.
1.2.15.Ensure good contact between journal and babbitt metal of the bearing in the center. Any minor high spot may be removed from the babbitt metal while checking with blue color. Ensure full contact of shaft over the jacking oil pocket also.
1.2.16.Always cover rotor journal with the upper half bearing to avoid entry of any sand particles etc. in the bearing . During pouring of oil the upper bearing may be removed and replaced back after the pouring of oil.
1.2.17.After completing the reaming/honing and final tightening of coupling bolts the work of bearing side pad, yoke keys and oil guard fitting may be taken up.
1.2.18.Before starting the side pad and top keys ensure that the bearing is perfectly level on parting plane. Ensure that the gap for the side pads are parallel otherwise these are to be made by cutting/scrapping.
1.2.19.After fitting of the bearing cap if the gap for the radial top keys are in taper a proper correction is to be made here. The bearing cap may also be repositioned to achieve the parallelity of the key way. The cap may be re-doweled after repositioning it but no taper are to be left on these area. If repositioning of cap is not helping then the cutting may be carried out in bearing cap.
1.2.20.The gap for the top packer of bearing may also be checked. In case of any taper the same is to be corrected by cutting on bearing cap. Sometime the size of this packer comes to very low i.e. even below 5.00 mm. This may be corrected by matching the cap and size for this packer may be kept around 6.00 mm.
1.2.21.On all these bearing cap key a proper fitting and clearances are to be maintained during assembly. These key of proper material are to be only used and no welding deposits are permitted here. The new key may be made at site by EN-24 material if correct key are not available at site.
1.2.22.Use of local made shims in bearing may be avoided and shims supplied from the works with proper cutting of holes are to be
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 5of 40
used. Ensure drawing requirement of maximum adjustment at site by + 0.3mm in shim size from manufactured condition.
1.2.23.A proper care should be given during fitting of bearing oil guard ring otherwise it causes the oil leakage during operation of the machine through pedestals. Parting plane joint of oil guard ring and duct should be feeler tight and no elongation of holes on these area may be permitted.
1.2.24.The bearing parting plane bolt are to be tightened to required torque only no other method of tightening of these bolts may be used.
1.2.25.Adjustment of shims between spherical/torus and bearing body is limited to +0.30 mm in up and down and left, right direction. this margin may be left for emergency work during overhauling of the machine any adjustment during erection and normal overhauling may be done by adjusting shims between spherical/cylindrical seat and pedestal base only. For left and right adjustment the complete pedestal of HP front and HP rear may be moved with the help of their radial keys.
The above discussed points were common for Journal bearing and combined thrust and journal bearing. Now some specific points are detailed here for the assembly of combined Thrust and Journal bearing:
Remove all the thrust pads before placement of bearing in
position and store them in a proper place.
Pressure proper fitting of babbitt metal liner in the bearing body
including necessary pinch in the fitting of its liner.
During alignment of rotor along the bearing with respect to the
shaft by moving spherical seat of the bearing radially and
axially.
No elongation of holes are to be carried out in spherical sat of
the bearing for the purpose of its alignment.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 6of 40
Before deciding axial position of the bearing the axial position of the
rotor is to be determined. If necessary the H.P. rear pedestal as a
whole may be shifted axially to ensure correct position of the
thrust bearing.
Align the thrust bearing in such a way that the thrust pad gap
achieved are prallel and no difference are noticed in front and rear
pad thicknesses.
Movement in the thrust pad should be ensured and a difference in
thickness of packers including shims should be with in + 0.10 mm
may be permitted on front and rear pad sizes in exceptional cases.
After ensuring the perfect alignment of the bearing the axial keys
are fitted after assembly of upper half bearing. These axial keys
are to be fitted in perfect parallel slots without any clearances.
The keys are to be fitted in such a way that there is no movement
to the bearing during fitting of these axial keys. Necessary dial
gauges are to be installed on bearing during fitting of these keys.
After completion of axial key works of the bearing the thrust pads
may be fitted in the bearing with a clearance of about 0.10/0.15
mm.
Before fitting of pads in the bearing ensure that there dimension
are made parallel to suit the front and rear slot size of the bearing
(size between thrust collar and bearing body).
Ater fitting of pads in the bearing ensure their free movement
over the bearing.
Install lower half bearing in position along with their pads and put
very small quantity of oil on journal then rotate the rotor and put
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0801G Page No. 7of 40
blue color on the thrust collar of the rotor on both front and rear
side.
Install upper half bearing along with all pads and fix their axial keys.
Rotate the rotor and move + direction axially with the help of
wooden planks. Remove both halves of the bearing and see the
blue contact on thrust pads. If necessary some cutting may be
carried out on the pads to achieve the color contact. This
exercise may be repeated few times to achieve the blue contact
Ensure a float of 0.30 + 0.10mm during color matching of the
thrust pads. If necessary the minor adjustment of shims may be
carried out in the bearing pads.
Before installation of thrust bearing along with thrust pads in
position the both halves may be bolted out side and their pads
may be checked for color contact over a surface plate also in
front and rear both sides. This will reduce the time cycle while
carrying out the color contact of the bearing with the rotor.
During overhauling of the unit the bearing contact are to be
rechecked and need correction. In case of torus to cylindrical
type of bearing if the contact are not satisfactory then the
bearing and its seat may be remachined at works. In spherical
to spherical bearing the variation in contact if noticed can
be corrected by matching/lapping at site. Sometimes the
heavy pitting marks are also noticed on same of the bearing and
these need correction by machining it.
-- --- -- - - - --
STEAM TURBINE500 MW CRITICAL ACTIVITIES \
(ASSEMBLYOF BRG. AT SITE) I81 ERECTION
BEARING CONTACTS
1.0 SPHERICAL TO SPHERICAL SEATS
1. 1 I
1.2
No feeler should go in the sides.
-- Correct contact.
This contact may be accepted ifthe bottom gap is not more than
.' 0.03mm & scrappingllapping is-- to be done to achieve the
contact in center before fitting. the bearing in position.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801 G
Page No. 80f 40
111STEAM TURBINE500 MW CRITICAL ACTIVITIES
(ASSEMBLY OF BRG. AT SITE)ERECTION
BEARING CONTACTS
2.0 TORUS TO CYLINDER/CAL SEATS
2.1
I
II
~ -. ~___L------ I- - - - - - - - - - - . -- -----=-~::--=' =+--:.=---=_-:...~-
II
I
2.2
"'l,
,I
I- - -1- - -
I
-- Correct contact.
WRONG CONTACTFee/er is going in center
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801 G
Page No. 90f 40
STEAM TURBINE500 MW CRITICAL. ACTIVITIES
(ASSEMBLY OF BRG.A T SITE)IIERECTION
BEARING CONTACTS
1.3
When some feeler gapis noticed in sides thensuch contact will benoticed in center. Thiscontact can not besent for remachining toworks along with itsseat.
1.4
:--====:_--J ~
========~=======:_~~------.~_::.-~== = =-4=:-=-=~-:= .=.=- --
:=r:------- - - - - - - -- - - - ...::.=.------.---- ----
Almost full contact maybe accepted but nofeeler should go incenter or sides.
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0801 GPage No.1 Oaf40
----------
II STEAMTURBINE500 MW CRITICAL ACTIVITIES
(ASSEMBLYOF BRG. AT SITE)ERECTION
BEARING CONTACTS
2.3
--
I
I
I
~ --- - ==-=~ii-~~:-- - -'--=====
I
(I
2.4
2.5
2.6
.. \. - - - - - - - - - -- -.f: -==7-; ii"-=-- :r=":. ~~~ ~ ~ ~~~~7-
""":=~-~~--=':i~~-~ _~_~~'-I-
~~~~~::~~~~~~~~:~=~
Contact is at an angleand cannot be accepted.
Intermittent contactobtained but no feeler isgoing. This may beaccepted.
Contact is not exactly asper the drawing but it isin straight line and narrowin center also. This canbe accepted at site.
Contact is very wide andcannot be accepted atsite.
Bharat Heavy Electricals Limited'Rev 00, 7-98
T1-08-0801 G
Page No. 11of 40
I
II
-':.-- ...-:: I -.:.- -"fg - -I- -f-t -- - --- -- ..- -,."-- I .' .
I
I
I
II
w-__--___L--__------ - ==:-::=_-:_- - -III
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(BUMP CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0802G Page No. 12of 40
2. BUMP TEST
The axial clearance check is determined after radial clearance
measurement has been completed.
In this case the shaft is shifted in the “+” and “-” directions from its
operating position and the dimensions with the shaft in limit position are
measured using a depth gauge.
Note: Enter the measured values ( actual dimensions ) on the record sheet
and compare them with the specified dimensions.
If the deviations from the specified dimensions is greater then the
permitted tolerances, the manufacturer must be consulted.
Note : Based on the readings of bump check, axial position of the shaft wrt
casing is not to be altered.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ROLL CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0803G Page No. 13of 40
3. ROLL CHECK
3.1. GENERAL DESCRIPTION
In KWU machine the minimum radial clearances HP, IP and LP casing are
measured by actually by moving the casing radially at site while rotor is rotated
by hand. This is a very accurate and fast method of measuring the minimum
radial clearance of any of the casing.
The major variation in these reading may cause vibration in the machine
and obstruction in barring gear operation etc. Such facilities are not available
in many other designs of machine and causes longer duration in erection and
overhauling of the units.
After completing the alignment of rotors the casing alignments are carried out by
roll check method but equal importance should also be given to the centering of
HP and IP casing.
The centering of casing may not be fully sacrificed in comparison of rolling
test readings and a compromise between these two readings should be made.
The rolling test should be carried out in cold machine only.
3.2. PROCEDURE
ROLL CHECK OF HP AND IP CASING
3.2.1. Alignment and coupling of HP-IP and LP rotors are to be completed before starting the rolling test of the casing in normal case but this can be done without coupling of LP rotor also.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ROLL CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0803G Page No. 14of 40
3.2.2. Centering of the casing on HP front, HP rear IP front and IP rear spigot are also to be completed before starting of the rolling test. These readings can be compared as per the factory protocol also. Fix temporary radial and axial keys of the casing before rolling test of casing. During dialing on spigot a proper care should be taken that the dials are properly mounted over the fixture and the fixture fabricated at site is strong enough to give the correct readings. The point dial indicator may be used here for the better results of the dial readings.
3.2.3. All the four jacking screw of HP and IP casing are to installed along with dial gauges for monitoring of up and down, and left and right movement of the casing.
3.2.4. One number hydraulic jack on each corner of the casing along with a spanner on each corner for jacking screw are also to be made available.
3.2.5. During erection of machine the turbine rotor are generally rotated by hand with the help of periphery holes on coupling. Two pipes of about 1250 mm long along with a pin to suit the dia of periphery may be used for rotating the rotor shaft. The initial jerk to the rotor is given by the help of crane and it is further rotated by these pipes through periphery holes of the coupling. During overhauling generally the jacking oil system is available and the rotation of rotors are achieved with the hand barring of the machine.
3.2.6. Before starting the rolling check it should be ensured that the rotor shaft is absolutely free on manual rotation/hand barring as the case may be. During manual rotation two persons are to be employed for this work and during hand barring only one person is enough.
3.2.7. Always use thick oil for rotation of rotor over bearing in absence of jacking oil system. The type oil may be servo cylinder 1000 grade (IOC) oil.
3.2.8. During the rolling test the temporary casing packers are to be fitted with about 1.00 mm shims.
3.2.9. During the rolling test of any one of the casing the same is lifted first on all four corners in a step of 0.05 mm with the help of hydraulic jack and jacking screw. The rotor is also rotated manually side by side with the lifting of casing. The rotation of
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ROLL CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0803G Page No. 15of 40
rotor and lifting of casing continued till it becomes little bit tight on the seals of the casing
After this the casing is lowered by about 0.05mm and rotor is
rotated again if it is completely free. In case the rotor is still tight on
its manual rotation the casing is further lowered by 0.05 mm on
all four corners. After ensuring the freeness of rotor it is again
rotated and casing is lifted simultaneously on front end till the
rotor rotation becomes tight on seals portion of the casing.
As soon as the shaft becomes tight the lifting of casing and
rotation of shaft is stopped and dial readings on front end are
recorded. The average lift on front end of the casing is the bottom
clearance on front end of the casing.
After this the casing on front end is lowered by 0.05 mm and
freeness of rotor is ensured. In case it is still tight the casing is
further lowered by 0.05 mm. On front end and the freeness of
rotor is achieved. Now the rear end of the casing are lifted similar
to front end and bottom clearance of rear end are recorded . After
recording the bottom clearance of front and rear end of
individual casing the casing is lowered with the help of hydraulic
jacks and jacking screws to its original zero-zero position.
Repeat similar operation of rotating the rotor and lowering the
casing on front and rear end for deciding the top clearance in front
and rear end of the casing. Before starting the rolling test in
downward direction of the casing remove about 1.00 mm shims
from each packer of the casing, but kept the casing on
hydraulic jacks and jacking screws on its original position. The
casing is again brought back to its original position by
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ROLL CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0803G Page No. 16of 40
installation of the shims back to the packers of the casing after
recording the top clearances of the casing.
After recording the up and down rolling test values the radial
keys of the casing are removed and again rolling test for left
and right direction are done similar to up and down. During this
process the radial dial on the casing are also installed. After
this check the casing is brought back to its zero position in radial
direction also.
After completing the rolling test readings of one of the HP/IP
casing in up/downand left/right direction the clearances are
readjusted as required at site in radial direction by moving the
casing with the help of temporary radial key or shims on the casing
packers. The casing is then locked on four corners and final
dial readings of spigot are recorded on front and rear end.
Immediately after this the final radial key of the casing are fixed
and the locked of the casing are released for fitting of the final
casing packers. The final spigot dial reading are repeated and
confirmed with the earlier readings.
3.2.10.After doing the full rolling test and fixing of a final radial keys and packers of one of the casing the rolling test of another casing is done including the fitting of final keys and packers.
3.2.11.Necessary offset in the radial clear-ance is also kept before fitting of final packers of the casing toward the lift of the shaft during operation of the unit.
3.2.12.No inlet and outlet pipes are to be welded with the casing till completion of rolling test and installation of final keys and packer of the casing.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ROLL CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0803G Page No. 17of 40
3.2.13.Radial clearance of the casing are to be ensured with reference to the factory supplied protocol also.
3.2.14.After fitting of final keys and packers of the casing the final spigot dial values of HP front, HP rear, IP front and IP rear casing are to be recorded for future reference in the protocol.
3.2.15.The horn drop readings are also to be checked after the fitting of final packer of the casing.
3.2.16.In case of IP casing the roll test readings are to be taken with the IP front end rear shaft scales. The spigot dial readings are also to be taken over the spigot of shaft seales.
3.2.17.During rolling test of the HP and IP casing if the rotor is rotated over the jacking oil then the adjustment of readings are to adjusted for the lift of the rotor also.
3.2.18.Four numbers 1.00 mm undersize packers for HP & IP casing may be made during erection and supplied to customers as T&P items for further roll test during overhauling of the unit. If any taper is left on final packers of the casing then these four packers may be made to similar taper also.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(ROLL CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0803G Page No. 18of 40
3.3. ROLLING TEST OF L.P. INNER CASING
3.3.1. The rolling test of L.P. inner casing is done similar to the HP or IP casing but both side joints of L.P. inlet bellows are kept free or bellow itself are not positioned at all, till completion of rolling test. But during overhauling the rolling test is done with already welded bellows.
3.3.2. Rolling test of L.P. inner casing is done after the neck welding of condenser andstiffener pipes inside the condenser. This include the welding of stiffener pipes of L.P. casing and gusset plates also.
3.3.3. After rolling test of the casing the final radial keys of the Gusset block and casing packers on all four corners are installed.
3.3.4. Necessary offset in the radial clearances of the casing is also kept before fitting of final L.,P. inner casing packers.
3.3.5. Radial clearances of the casing are to be ensured to the design values. In case of any variation the matter may be referred to the designers.
3.3.6. If the rotor is rotated on jacking oil then the rolling test readings are to be adjuted for the lift of the rotor also.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(CATENARY AND ALIGNMENTS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0804G Page No. 19of 40
4. CATENARY AND ALIGNMENTS
4.1. General Description
The catenary of the machine is very important for a turbine and Generator
assembly to achieve proper alignment of various rotors and loading on their
bearing. Any deviation may lead to various operational problem in the
machine like high shaft vibration, high bearing vibration, high babbitt metal
temperature of the bearing etc. To avoid these problems it is necessary to
maintain the catenary of the machine during erection and subsequent
realignment/overhaul of the unit. Many times it is observed that though the
alignment of rotors are within limit but the catenary as a whole get deviated
from the prescribed design value of the machine. In order to avoid such
derivation a need is felt to devise a procedure which shall ensure rotors
alignment alongwith proper catenary of the machine.
During first few years of the operation of the unit the possibility to the
disturbance of the catenary are much more due to settlement of the foundation
frame.
In each overhaul of the unit the catenary of the machine is to be corrected.
The L.P. front and L.P. rear pedestal are directly grouted here without any
separate base plate. As such any correction on lifting or lowering. These
pedestals are not very convenient so if necessary the rotor may be lifted or
lowered with respect to pedestal seal bore and required catenary may be
achieved. In extreme cases these pedestals may be even regrouted during
major overhauls of the unit to correct the catenary of the machine.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(CATENARY AND ALIGNMENTS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0804G Page No. 20of 40
4.2. Procedure
4.2.1. Install a bench mark plate near L.P. rear pedestal as height of the machine center line with the consultation of civil Engrs at site. A plate of 200 m.m x 300 m.m size with 20 m.m thickness machined/ground on top side may be welded over a I Beam or a channel in level condition. This plate is to be installed very carefully as this will be a future reference for setting up the all elevation of the machine.
4.2.2. Record half bore error of all the four pedestals and confirm the readings with the factory records also. The half bore error may be checked in both upper half and lower half of the pedestal and same may be punched on both halves in left and right side for all future references of the machine.
4.2.3. During alignment of pedestal at the time of grouting with conbextra cement set the height of the pedestals as per required catenary of the machine considering +value for the half bore error of the pedestals. While setting the height of the pedestals it should be kept in mind that the height for the center of the pedestal bore are to be kept as per the catenary of the machine not the parting plane of the pedestal.
4.2.4. For better results four water level jar connected to each other with a polythene pipe may be installed on each pedestal. The D.M., water may be used here and leakage through polythene tubes should be avoided fully while making the connections. These jars may be fabricated at site by about 125 mm. dia pipe with a plate welded in bottom and then machined for better seating on pedestal base. The height of the jar may be kept as about 175 mm. A depth micrometer installed and clamped over a magnetic base is also required for measurement of the water level in the jar. The micrometer point is to be made very sharp by grinding it. Here the magnetic base of the 0-10mm dial gauge may be used.
4.2.5. .During measurement of water level in the jar the micrometer is to be kept approximately in center of the jar. The micrometer along with the magnetic base to be transferred from one pedestal to another pedestal very carefully so there is no disturbance to the height of the micrometer. All the necessary care are to be taken during this measurement i.e. there should not be any air bubble in
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(CATENARY AND ALIGNMENTS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0804G Page No. 21of 40
the polythene pipe and the polythene pipe should be kept as stationary.
4.2.6. While finalizing the catenary of the machine these measurements are to be repeated 3-4 times in a day at different intervals to avoid any possibility of the error.
4.2.7. The height of the L.P. rear pedestal is the reference point for setting the height of all other pedestal and L.P. base plates. The L.P. rear pedestal height is to be first made with the benchmark plate as per the center line of the machine with the help of water level jar.
4.2.8. The benchmark plate is to be preserved for all future references.
4.2.9. The catenary is to be counter checked after grouting all the pedestals as well as after final alignment of the rotors. The final value of the catenary may be worked out as center of the shaft on each pedestal bore after taking the final seal bore readings. The final catenary should match with the design value of the catenary otherwise a necessary correction may be carried out.
4.2.10.After ensuring the required catenary of the machine the coupling alignments are to be made as parallel coupling.
4.2.11.The value of the catenary given over the drawing are theoretical value calculated by the designers but due to the human error in site measurements some time the correct coupling alignment are not achieved then an alternate method for checking of catenary may also be used i.e. optical measurement method or a method by which direct journal heights are taken on each bearing in place of pedestal height.
4.2.12.For measurements of direct journal height a special fixture is to be fabricated and necessary information about it can be separately given by PS-TS if such necessity arises.
5. HORN DROP TEST
5.1. General description
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(HORN DROP TEST)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 22of 40
By horn drop test the loading of the casing on each corner is determined. The
horn drop test is repeated at various stages in individual casing i.e. first
without connection of any pipe lines the horn drop readings are recorded then it
is compared after welding of inlet, outlet and extraction pipe lines etc. The horn
drop readings are very important in HP & IP casing. First the proper horn drop
readings are made without connection of any pipe lines and then the reading
are taken after welding of all pipe lines on HP & IP casing. As such the
influence of these major pipe lines are notices on each corner of HP/IP
casing by comparing the horn drop test readings. The horn drop test will
indicate the quality of work during assembly/welding of pipe lines with the HP &
IP casing.
This is a very important check and may cause serious problem in operation of
the machine like high vibration in the machine failure of barring gear in hot/cold
machine, obstruction during expansion of machine etc. In horn drop test a drop
is measured on an individual corner of the casing with the help of a dial
indicator by removing the support of individual corner and then it is compared
with the opposite corner. As such this gives an indication of indifferent loading
of the casing. In Russian design machine the value of direct dynoxmetre
loadings are recorded in place of this horn drop test.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(HORN DROP TEST)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 23of 40
5.1.1. Procedure
5.1.2. After placement of HP and IP casing on four temporary packers ensure that the each corner of the casing is loaded on temporary packer and if necessary the shims may be given on packer for loading of the casing. The load of shaft is also taken on transport device during this stage.
5.1.3. After transferring the load of the rotor on bearing and ensuring the casing centering with respect to shaft the horn drop check may be carried out.
5.1.4. Before taking the horn drop reading ensure that the enough clearance is available on front & rear portion of the shaft with their seals in the casing inside. After completing the centering of the casing the some may be lifted by 0. 20 mm on all four corners by providing shims. This will help in avoiding the touching of seals with the rotor during the horn drop test readings.
5.1.5. No adjustment on packer of the HP front and HP rear pedestals are to be carried out after taking the horn drop test of the casing In case if any adjustment is carried out on these pedestal packers then horn drop test are to be repeated again.
5.1.6. No piping may be connected to HP & IP casing till initial horn drop readings are over. The piping work should not be postponed for want of horn drop the only thing the last joint with HP/IP casing may be left free till completion of horn drop check.
5.1.7. While recording the horn drop readings the casing must be absolutely free and even the radial and axial key of front and rear portion of the casing are either to be removed fully or these are to be made completely free by removing their shims etc. Actually during this stage of erection only temporary axial and radial keys are fitted in the casing and even they carry some shims also. Before making the casings free on axial and radial key portion the dial gauges are to be installed to monitor the movement of the casing on radial and axial direction. Immediately after the completion of the horn drop test these keys/shims may be installed back and centering of casing may be rechecked before further works.
5.1.8. In HP casing the initial horn drop test may be done even after fitting of breach nut assembly and HP exhaust elbow of both sides.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(HORN DROP TEST)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 24of 40
5.1.9. In IP casing the initial horn drop test may also be done after fitting of IP inlet pipe lower half assembly but this pipe of upper half casing should not be fitted till completion of the horn drop test.
5.1.10.All the four Jacking screw and hydraulic jack on each corner of the casing are to be installed for the horn drop test readings. A dial indicator is also to be installed on each corner of the casing for measuring the drop of the casing.
5.1.11.After initial centering of the casing the each corner packer may be fitted with a shim of about 1 mm. for further adjustment during the horn drop test.
5.1.12.During the horn drop test the individual packer of the casing is removed and the load of that corner is supported over the jacking screw of the casing. Now gradually the jacking screw is also relieved with the help of hydraulic jack on that corner and drop reading is recorded. This is repeated for each corner of the casing. In case of variation in left and right side reading the drop is adjusted by + adjustment of shims from left to right side or vise-versa. No subtraction / addition in shim sizes from outside is done here and only the shims are adjusted from left to right or vise versa till equal loading are achieved in left/right side of individual casing. The sizes of these casing packers are recorded after completion of horn drop to avoid any confusion at a later date while fitting the final packers.
5.1.13.While recording the horn drop readings the drop on each individual corner may be controlled with the help of Jacking screw so that during this test the casing is not touching with the shaft in gland portion of the seals at all and enough clearance is left there to avoid damage to the seals inside the casing.
5.1.14.During the initial horn drop the best reading within 0.05/0.06 may be achieved by fine adjustment of the packer shims. The comparison in horn drop value should always be made in left and right side only of an individual casing.
5.1.15.In case of HP casing the drop on rear end is so high that unless the casing is locked on diagonally opposite end the horn drop check is not possible. Therefore while recording drop on HP rear end the front end of the casing diagonally opposite to it should be locked with casing clamp. The pedestal is also required to be locked on all four side with its sole plate with the help of the clamps. In case of IP casing no locking of any corner of the casing is necessary during the horn drop test.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(HORN DROP TEST)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 25of 40
5.1.16.The final packers on HP & Ip casing are installed only after completing the rolling test of these casing., The horn drop reading for an individual casing may be recorded after the fixing of final packers also. If necessary a fine adjustment may be carried out at this stage to achieve correct value of the horn drop reading.
5.1.17.After completing the welding of all pipe lines with the casing , the horn drop readings are repeated again for comparison with the earlier readings. These readings are taken along with its radial and axial keys of the casing.
5.1.18.During this stage exactly this can not be defined that how much variation is permitted on these values of horn drop readings., But this variation will indicate the influence of the piping load on the HP/IP casing caused due to welding/connection of various pipe lines with the casing. The variation in horn drop readings are permitted as long as sufficient positive loading is there on each corner of the casing. But if any corner of the casing is fully unloaded/heavily loaded then there is no choice left and pipe lines are to be corrected by dismantling it and making again a free joint with the casing.
5.1.19.During variation of horn drop reading no correction is to be made on casing packers by adjustment of shims etc. The variation at this stage is caused due to the piping pull/push only so if any correction is required then the same may be carried out in piping joints and support etc. And any adjustment in piping supports can be carried out only after disconnecting the pipe line with the casing. Even some time it is necessary to cut the individual or more piping joint for correction of horn drop readings.
5.1.20.The variation in horn drop reading of left and right side of a casing may be permitted upto a difference of 50%.
5.1.21.The horn drop readings are not taken for L.P. inner outer casing due to its fabricated structure and the parting plane of the casing are leveled on four corner with the help of water level jar arrangements.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(SWING CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 26of 40
6. SWING CHECK
6.1. GENERAL DESCRIPTION
The swing check is the measurement of radial throw caused due to
coupling face geometric form of the two rotor coupled together. This is
measured on opposite end of the coupling and at the free end of the rotor. The
higher swing check value may cause higher shaft vibration, higher bearing
shell temperature etc. The value of swing check depends on axial runout of
coupling faces, the diameter of the coupling and the length of the rotor. During
the machining of rotors in the works some tolerances are permitted by
Designer's on the coupling faces of the rotor resulting to some swing check
values. The maximum swing check values permitted caused due to the
above tolerance for different diameter and length of the rotor can be
worked out from the enclosed graph. However it is recommended to keep the
minimum swing check values for better results during operation of the machine.
In a multi rotor Turbine-Generator system it is essential to measure the swing
check value in both extreme end and where the weight of the rotors are light.
For example 200/210 M.W. KWU machine with Russian Generator and
static excitation system the swing check values are measured on HP rotor front
end only. In 500 M.W. machine the swing check values are measured in H.P.
front end and on exciter rear end. After having general experience of number of
200 MW & 500 MW units, a necessity is felt to measure swing check value on IP
rotor front end also for better results during operation of the units. This can be
done initially during erection with temporary coupling bolts on LP-IP coupling
before reaming/honing of coupling. Any variation in swing check values may be
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(SWING CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 27of 40
corrected without any hesitation during erection of machine. Any compromise
at erection stage may cause serious problem during operation of the unit and
any correction becomes much more tedious a later stage. The correction may
be carried out either by interchanging the coupling position or by correcting
the coupling faces by scrapping/cutting in consultation of Designers.
6.2. PROCEDURE
6.2.1. Before placement of Module/Rotor in position the coupling faces of all the rotors are to be measured for concavity/convexity of their coupling faces. This can be checked with the help of a thin rectangular light weight straight edge. No convexity is permitted on these coupling faces however a concavity of about 0.03/0.04 mm is permitted. In case of any variation the matter may be referred to manufacturing units.
6.2.2. After placement of individual Module/Rotor the coupling faces are to be measured for axial runout before taking up alignment of various rotors. The HP rotor rear coupling face can be measured after placing it on both of its bearing. The IP rotor faces are to be measured after placing IP rear end on bearing and front end on lifting tackle. Similarly L.P. rotor, may be placed on bearing on its rear end and front end supported on lifting tackle. Any variation on axial runout on coupling faces for more then the 0.02 mm. may be referred to Designer's before taking up further works.
6.2.3. After completing final alignment of various rotor they are to be coupled with temporary bolts, considering their axial runout/geometric form of the coupling faces.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(SWING CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 28of 40
6.2.4. During coupling with temporary bolts the higher plane of one of the rotor face is to be coupled with lower plane of another coupling face of the rotor.
6.2.5. During coupling on temporary bolts the uniform tightening on all the four temporary bolts are to be ensured otherwise it will disturb the swing check value of the rotor.
6.2.6. First IP-LP coupling is to be made with temporary bolts and swing check on IP rotor front end is recorded. After this only HP-IP rotor is to be coupled with temporary bolts and the swing check value on HP front rotor is recorded.
6.2.7. During swing check of IP rotor its front end is to be supported on lifting tackle without making any connection between HP-IP rotor.
6.2.8. While recording swing check of HP rotor the front end of the rotor is to be supported on lifting tackle.
6.2.9. During swing check the lifting tackle are to be fitted properly. The tie rod of lifting tackle should be ensured for correct fitting of its spherical bearing and Molykote should be applied on these spherical bearing for their free movement. These spherical bearing should not obstruct the movement of shaft radially during checking of its swing check value.
6.2.10.After taking the load of the rotor on lifting tackle ensure that the rotor is not disturb radially due to fitting of lifting tackle.
6.2.11.During checking of swing check measure radial movement of rotor on parting plane and rotate the rotor either on jacking oil with hand barring or with the help of E.O.T crane with thick oil on bearings. Avoid jerk during rotation of rotor while recording the swing check values.
6.2.12.After ensuring the swing check values as per the graph with on temporary coupling bolts, the HP-IP and LP-IP coupling may be cleared for reaming / honing of the coupling holes. Any variation need correction of the coupling before reaming/honing of the holes.
6.2.13.The final swing check value of HP front rotor is to be recorded after fitting/ elongation of all the coupling bolts of HP-IP & LP-IP rotors. Any variation in readings may be referred to the Designer's. For improvement of the swing check values, the indifferent tightening and non-sequential
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(SWING CHECK)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0806G Page No. 29of 40
6.2.14.During checking of swing check readings, the initial few rotations are to be given to the rotor to avoid initial sag and then only the readings are to be recorded.
6.2.15.Similar method is to be adopted while checking the swing check value of the exciter except the rotor is hanged on the suitable size of sling in place of the lifting tackle.
6.2.16.While recording the swing check initially with temporary bolts for HP & IP rotor, the fitting of eight number temporary bolts are preferred in place of four bolts on the coupling.
IISTEAM TURBINE500 MW CRITICAL ACTIVITIES
(SWING CHECK)
ERECTION
10 .2. t4
/I 11
DE?M ?ADIAL RUN OUT Ai.n. i/1 00 "'~.
f9 10 %1 U 26 d ~ 31.
0",'M.
tOOO~- - ~ 4 6 a t'
5
~
900 36
&00
sa
40
41
44
7
48
S1
51
~
64
11.
'00 8D
8.M'oil141. -\U't1&.~
!CO .C) j, , 6 1 ~
I
,~.""
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-0806G
Page No. 300f 40
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0807G Page No. 31of 40
7. COUPLINGS & ALIGNMENTS OF ROTORS
7.1. GENERAL DESCRIPTION
The coupling on turbine shaft are generally rigid coupling but in case of L.P.
rotor sometime the coupling head are shrunk fit and remachined. The basic
function of any coupling is to connect two or more shaft together to form a
shaft assembly. The number of shaft mainly depend upon the rating of the
machine.
A very high accuracy is required during manufacturing of these rotor shaft
at works. The axial runout on the coupling face may not exceed 0.02 mm.
and an additional check is also made at works/site to ensure that the geometry
of the entire coupling surface does not deviate by more then the 0.02 mm.
except the concavity on the coupling face which is permitted upto 0.03/0.04
mm.
The radial and axial alignment of the various shafts are to be completed
before their coupling and alignments are to be done in such a way that the
entire shaft assembly follow the continuous deflection curve given over the
drgs. for a particular machine. The coupling checks determines both the radial
and axial position of the two adjacent coupling flanges relative to one another.
The radial measurement are performed on the circumference of the
couplings and the axial measurement are performed on outer most diameter
of the coupling. During coupling of the two shafts it should be ensured that the
no stresses are exerted as a results of the coupling each other shaft.
After completion of the alignment and coupling of the shaft the casings are
aligned radially and axially. Here equal importance is given to the radial & axial
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0807G Page No. 32of 40
alignment of stationary parts to avoid any rubbing during operation of the
machine due to expansion of stationary and rotary parts.
During the alignment of two coupling both are to be turned in same direction
and by the same amount when the measurement are taken to avoid the
influence of the axial & radial runout present in the shaft caused due to the
machining.
7.2. PROCEDURE
7.2.1. Before placement of module/rotor in position check and record the coupling hole and journal dia of the shaft.
7.2.2. Check coupling faces for the concavity/convexity with the help of a thin rectangular straight edge before placement of module/rotor in position.
7.2.3. Check spigot and recess of the coupling and ensure their fitting before placement in position.
7.2.4. Place the module/rotor in position and check the radial runout of journal and axial runout of the coupling faces independently of each shaft. During checking of radial and axial runout of the shaft place H.P. rotor on both of its bearing and IP/LP rotor one end on its bearing and another end on the lifting tackle. The radial and axial face runout on the shaft should be within 0.02 mm accuracy. Any variation may not be permitted here and matter may be referred to the designer's.
7.2.5. The HP,IP & LP rotor are aligned together and then their couplings are made. After fully completion of HP/IP & IP/LP coupling with tightening of their final bolts the complete shaft is cleared for Generator rotor alignment.
7.2.6. During initial alignment of HP/IP & IP/LP rotor the radial checks are generally done with the help of depth micrometer and axial gap are measured with the slip gauges. After completion of the radial alignment the rotor are inserted in their spigot even with some minor variation in their axial gap values.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0807G Page No. 33of 40
7.2.7. During final alignment only the axial gap values are checked at 90o on four places by rotating both the rotor together and average of these four reading are taken. The radial alignment reading along with axial gaps are necessary wherever the effective spigot are not existing in two couplings i.e. in case of LP - Gen coupling the radial dial reading are also taken.
7.2.8. Avoid rotation of two shaft in their spigot. If necessary these may be rotated after taking out from their spigot.
7.2.9. During alignment of shafts the adjustment of shims in bearing torus may be fully avoided. The margin of + 0.30 mm. in height & left/right direction may be kept for emergency works only. Any adjustment during erection and normal overhauling may be done by adjusting shims between spherical/cylindrical seat and pedestal base only. For left and right adjustment the complete H.P. front and HP rear pedestal may be moved with the help of their radial keys.
7.2.10.The final packers of the pedestal and base plates are fitted before the grouting of the pedestal itself and here no adjustment is necessary during erection of the machine. But during overhauling of the machine the adjustment may be carried out in these packers for correction of catenary of the machine.
7.2.11.During alignment of rotor make HP/IP and IP/LP coupling gap parallel. After completion of final alignment no adjustment of packers and keys etc are permitted on pedestals and bearing the final alignment of HP/IP & IP/LP rotors should be checked after fitting of all the final keys and packers of the pedestals.
7.2.12.After alignment couple the HP-IP & IP-LP rotors on temporary bolts. Record coupled runout of the rotor and ensure that the coupled runout is not more then 0.03 mm. in any where in the journal as well as in coupling area. Before coupling of rotor on temporary bolts record their spigot clearances by actually moving the rotor radially.
7.2.13.During erection IP-LP swing check on IP front and HP-IP swing check on HP front are to be recorded on temporary bolts. These reading are to be ensured within the design limit.
7.2.14.Before alignment/coupling position the two shaft adjustment to each other depending upon the higher and lower point of the shaft with respect to their axial face measurement values.
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0807G Page No. 34of 40
7.2.15.The HP-IP & IP-IP coupling may be cleared for reaming/honing after ensuring the runout and swing check values of the rotors. In case of variation the cause of the error may be identified and corrected before further work of reaming and honing of the coupling.
7.2.16.During coupling of rotors two taper pins may be used for proper alignment of coupling holes so that there is minimum enlargement of holes are done at site during reaming/honing. Unnecessary enlargement of holes may be fully avoided during reaming/honing at site as this may cause serious problem at a later date during overhauling of the unit.
7.2.17.As for as possible ream/hone all the coupling bolts holes to same size. In exceptional cases only the variation in hole sizes are permitted. Each hole during honing should be checked for bananas shape with the help of a parallel ground straight pin of 0.02/0.03 undersize. No banana shape is permitted in any of the hole. The hole should be made to 0.005 mm accuracy.
7.2.18.All the coupling bolts are to be machined and ground by 0.02/0.03 mm undersize then the hole dia. These bolts are to be fitted with thumb pressure only and no additional force is recommended while fitting these bolts.
7.2.19.A very thin layer of molykote may be applied on all the coupling bolts during their fitting. The molykote should not be applied on seating face of the coupling bolts. This may cause in breaking of their locking pin during elongation of coupling bolts.
7.2.20.All the coupling bolts are to be balanced before finally fitting/tightening in position. These are to be balanced within an accuracy of 5 gms each along with their nuts. In case all these bolts are of equal size then their weight must be equal. In exceptional cases the 180o opposite bolts may be made of equal weight.
7.2.21.During tightening of coupling at any stage first tighten four bolts on 90o location. Always tighten bolts in proper sequence with 180o opposite bolts. These bolts are to be elongated to the value given over drgs.
7.2.22.During tightening of coupling the radial runout on journal and coupling may be checked at various stages during tightening of
STEAM TURBINE
500 MW
ERECTION
CRITICAL ACTIVITIES
(COUPLINGS & ALIGNMENTS
OF ROTORS)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-0807G Page No. 35of 40
bolts. The final coupled runout should not be more then 0.03 mm. on coupling and journal of the shaft.
7.2.23.After final tightening of LP-IP and HP-IP coupling the swing check value on HP front rotor is to be rechecked. In case of variation in value a proper correction is to be made with consultation of designer's. The indifferent or unsequential tightening for achieving the swing check value or coupled runout value may be fully avoided. this may cause unnecessary stresses on the coupling.
7.2.24.After completing the coupling work the casing radial and axial alignment may be done.
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-17-0808G Page No. 36of 40
Welding of steam inlet and exhaust pipe lines with HP
and IP casing
In 210 MW machine the HP Turbine is supplied with two inlet and two exhaust
flanges for connection of the pipe line.but in case of 500/250 MW HP Turbine the
casing is supplied with four inlet flanges also. As such in 200 MW machines,
only two ESV control valves are used in the system. Whereas in 500/250 MW
machines , It may be either two ESV oontrol valves or four ESV control valves to
cope with the design of the casing.
Similarly in 210 MW machines, the I.P. casing is supplied with two inlet flanges
and eight number exhaust branches or either two exhaust branches only along
with two inlet flanges. These eight number exhaust branches are distributed four
on each side of the casing and each four branches are joined together with one
common pipe while connected to L.P. casing. The 500 MW I.P. casing is similar
to the 210 MW I.P. casing but some time these are supplied with four numbers
of I.V. control valves also. The inlet lines from each two control valves are joined
together and make one connection with the I.P. casing in bottom. As such in
210 MW machines, only two I.V. control valves are used but in case of 500 MW
machines, there can be either two I.V. control valves or four I.V. control valves.
After completion of the rolling test the installation of final keys and packers of the
H.P. and I.P. casing, the same can be cleared for welding of inlet and outlet
pipelines. The main steam inlet line from main steam strainer to the control
valves and then from control valves to the H.P. casing need much more care
during erection / welding of the pipelines. Similarly the Hot Reheat lines between
two Hot Reheat strainer to the control valves and from control valves to the I.P.
casing also need equal care during erection / welding of these pipelines. These
pipelines are directly affecting the performance of the turbine during operation of
the machine and a necessity is felt to fully involve the turbine Erection Engineer
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-17-0808G Page No. 37of 40
in erection / welding of the pipelines at site along with the Piping Engineers. The
piping connection between I.P. casing to L.P. casing i.e. cross around piping also
need proper care but due to its construction with number of bellows in the
system. Present method of erection / welding much of the problems are not
faced during operation of the machine. However if proper care is not taken here
then that may cause the unnecessary loading on the various bellows of the
piping and reduction in their life. In case, if proper care is not taken during
erection / welding of MS inlet, CRH & HRH connections with HP & IP casing, a
load will be transfer from the pipe line to the casing. Which may cause vibration
in the machine, obstruction in expansion of the machine, obstruction of barring
gaer operation in hot / cold machine, higher babbit metal temperature and failure
of brg. babbit etc. during operation of the machine.
8. PROCEDURE
8.1. The following points are to be taken care while welding MS, CRH, HRH pipelines with HP & IP casing and control valves / strainers.
8.1.1. The HP & IP casings are to be cleared in all respects after fitting of final packers and axial / radial keys of the casing.
8.1.2. The ESV & IV valves are to be cleared after fitting of their servomotors and then levelling including the correct elevation etc.
8.1.3. The equivalent insulation weight is to be given on each control valve befor connection of any pipeline with the valve. The change in hanger value of the control valve is to be adjusted back by lifting the valve with the help of hangers. The control valve hanger reading should remain same as before and after installation of equivalent insulation weight on the valve. After this all the three hangers of each valve are to be locked to avoid any movement of the valve in upward direction, in case the equivalent insulation weight is removed or any of the servomotor is removed. Before starting of any welding with the control valve the valves are to be locked for their movement.
8.1.4. Erection and welding of MS line upto MS strainer and HRH strainer are to be completed first including either their insulation or
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-17-0808G Page No. 38of 40
equivalent weight is to be given for their insulation weight in the lines. These lines should be in perfect floating condition on their hangers before taking up the further work of MS & HRH lines upto the ESV & IV control valves.
8.1.5. Install MS & HRH lines between strainer and control valves and weld all the inbetween joins of the pipelines except the end joints with the valves and strainers. These lines are to be erected in such a way that both the end joints remain free and parallel with the strainer and control valve after taking their load on hangers. The freeness of joints are to be ensured after giving the equivalent insulation weight of the lines.
8.1.6. Weld MS & HRH lines with the strainers and again ensure the freeness / paralalllity of MS & HRH lines with the ESV and IV control valves. Any minor variation may be readjusted on hangers to obtain the freeness of the joints with the control valve.
8.1.7. Install the MS and HRH lines between control valves and HP /IP casing . Now all the in between joints may be keeping the end joints free with the valve and the casing. The erection of these lines are to be done in such a way that freeness and parallelity of end joints are achieved after fully floating the pipe lines on their hangers. The equivalent insulation weights are also to be added during erection of these pipe lines before welding the end joints.
8.1.8. After ensuring the freeness and parallelity of the end joints between ESV control valve and HP casing , the same may be welded together. But the stress relieving of all the in -between joints of the lines are to be completed before taking up work of the above last two end joints . Similar proceedure may be followed for the lines between I V valves and IP casing also.
8.1.9. Weld left and right MS and HRH joints togethers with the HP and IP casing to avoid any left and right loading on the casing . during welding the left and right movements of casing may be monitored by installing the radial dial gauge on the casing.
8.1.10. The CRH lines are to be erected on their permanent hangers and the joint with the HP casing are to be made free /parallel after floating the pipe lines. The left and right side casing joints are to be welded together , similar to MS lines but before weling of these line the in- between joints are to be completed first . The equvalent insulation weight is also to be given on these line while checking the freeness of end joints with the HP casing.
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-17-0808G Page No. 39of 40
8.1.11.The horn drop readings are to be recorded for both HP and IP casing after copletion of the job including insulation of pipe lines and control valve etc.
8.2. SPECIAL CARE
8.2.1. If possible keep the insulation weight and servomotors on ESV and I V control valves during erection /welding of these MS & HRH lines from strainers to the valve and casing . If the above condition are fulfilled then there no need of any locking of the valves during the welding of any pipe lines.
8.2.2. The control valves hanger readings are to be measured with the inside micrometer in various stages and changes are to be monitored properly . The readings are to be measured in the following stages :-
After complete leveling of ESV and IV control valves with their
servomotors
After putting the equivalent insulation weight on the control
valves.
After readjustements of control valve height equivalent to
insulation weight.
After connection of MS &HRH lines with the strainers .
After connection of MS & HRH lines with the HP & IP casing .
After complete insulation of control valve and pipings.
STEAM TURBINE
250 MW
ERECTION
CRITICAL ACTIVITIES
(Welding of steam inlet and exhaust
pipe lines with HP and IP casing)
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-17-0808G Page No. 40of 40
8.2.3. Ensure proper clraning of MS and HRH lines between controls valve and casing as these lines are not covered in steam blowing operation . Proper care is to be taken during erection of these lines to avoid entry of foreign material.
8.2.4. The steam blowing of the MS and HRH pipe line are to be carried out after fully completing the erection /welding of lines from control valve to the HP and IP casing .
8.2.5. All the four corners of the casing may be locked with the casing clamp during welding of piping joints to avoid movement of casing radially.
8.2.6. The load of the upper half HRH pipe upto the flange supplied by turbine supplier is taken by the IP casing and by the piping hangers. This may be taken care while erecting the HRH lines.
0sep.doc
SPRING LOADED
FOUNDATION
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 1of 9
SPRING LOADED FOUNDATION
The spring support for TG foundation in our country is a new development though some of
the machines are already in operation with spring loaded foundation at various power stations.
Most of TG foundation built in Germany in last 20 years are spring loaded foundation. The
various machines in operation with BHEL supplied equipment and spring loaded foundations
are Dadri 4x210 MW , Trombay 1x500 MW, Dahanu 2 x 250 MW. Similarly the machines
which are going to come with spring loaded foundation with BHEL equipment are
Chandrapur 1 x 500 MW , Suratgarh 2x250 MW , Unchahar 2x210 MW and Vindhyachal
2x500 MW.
The spring units for all the above TG foundations are supplied by M/s GERB which they call
the GERB vibration isolation system for TG foundation.
In BHEL , we have yet to satisfy fully ourselves about the advantages of this system after
getting the feed back from various machines under operations with spring loaded foundation
though the advantage claimed by M/S GERB are listed below:
1.0 REDUCTION IN BASE MAT SITE AND ITS COST :
The vibration to the main column are isolated by the spring element resulting to small size
base mat which reduces the construction cost and time.
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 2of 9
2.0 REDUCTION IN NUMBER OF COLUMNS:
The same column of TG deck may also be used to support surrounding floors at the building ,
so that the total number of columns are reduced and the space to accommodate more
equipment is increased. This results in more rigidity of building structure of surrounding
floors and further in cost saving.
3.0 EASY HANDLING OF SETTLEMENT PROBLEMS:
Excessive settlement of column can easily be adjusted by inserting or removing shims in
spring units.
4.0 SUBSEQUENT TUNING OF THE FOUNDATION :
It is possible to tune the foundation subsequently by replacing the spring elements having
different load capacity of the springs.
5.0 EARTHQUAKE PROTECTION :
Machine will have more steadiness and stability in the event of earthquake compared to
normal foundations.
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 3of 9
INSTALLATION OF SPRING ELEMENT:
The spring element in 500MW machines and further higher rating machines are used with
visco dampers. The springs units are not supplied to site with required pre-tension values
through these are supplied with some amount of pre-tension. The required pre-tension of the
spring units are done at site before its installation in position. A special device for pre-
compression of these springs units is also supplied by spring supplier.
The shuttering of RCC slab of TG deck is furnished before installation of these spring units.
The top surface of individual column where these spring units are mounted should be within
accuracy of +00 mm to -3.00 mm. If necessary these may be corrected by chipping before
installations of the spring units. The level deviation among various columns is permitted +00
mm to -5.00 mm in total including individual column variation of +00 mm to -3.00 mm.
The bottom shuttering of pedestal must be cut over the column head for lowering the spring
units. After lowering the spring unit the cover steel plates are placed in position with
shuttering supports. An air gap of about 5.00 mm to 10.00 mm is left between cover plate
and spring units for settlement of deck during casting. The visco dampers are also filled up at
site only with visco liquids supplied by spring supplier. The filling procedure of visco liquid
is explained separately by the spring supplier.
Each spring units are placed over the resistance pad to avoid movement of the spring units
during operation of the machine. Similarly the resistance pad is given on top of the steel shim
to avoid the shifting of the shim during operation of the machine. Each spring unit is
provided with 10.00 mm of steel shim for future adjustment.
The spring units are not only pre-compressed for dead load of the machine but it is further
pre-compressed to prevent the loosening of the spring during installation of the equipment
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 4of 9
due to unforeseen additional loads. If major variation in calculation of load over the spring
units are not expected then an additional compression of 5.00 mm is sufficient for this
purpose. During installation of spring units, additional shims are provided for this 5.00 mm
additional compression and which are removed at the time of loosening of the spring
elements before final alignment of the machine. These additional shim are removed in
minimum two stages after ensuring, that all the major parts of the machine are installed and
condenser have been filled upto operating water level including CW pumps in operation for
full load condition of the machine. It is also not necessary to remove this complete 5.00 mm
shims from each spring unit and the same may vary from spring unit to spring unit depending
upon the variation of column level/elevation and variation in level of spring cover plate etc.
Refer section “Releasing of TG Deck Spring” for removal of additional shims.
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 5of 9
RELEASING OF TG DECK SPRING
The TG deck springs are released after installation of all Turbine Generator components
including piping and the condenser has to be filled up to operating level including CW pump
in operation for full load condition. The shims provided for additional compression of the
spring units are also adjusted during this stage, the final alignment of various rotors and
turbine casing are done after release of the spring unit. The Generator hydrogen cooler & LP
heater if any inside the condenser are to be filled up in cooling water space for their operating
condition before release of TG desk spring. The insulation of various casing / pipe lines
including cladding if any are also to be installed otherwise the equivalent weight is to be
incorporated before release of desk spring. All the pipe lines connected with the Turbine and
Generator should be made available on permanent hangers and supports to avoid any
additional load on the TG deck afterwards. The TG deck should also be made free all-
around to avoid any obstruction in its movement.
Many time it is not possible to wait till completion of all the works on Turbine Generator area
as required for final alignment of all the rotors for reaming / honing of the various coupling.
In such cases without releasing of the spring units the alignment of all the rotors can be done
and reaming / honing including fitting of all final coupling bolts can be completed. The
coupling bolts need not be elongated at this stage and once all other works are ready for final
alignment of rotors ,the coupling may be opened and realigned. After realignment , the
coupling bolts are to be fitted without any further reaming / honing of the coupling holes.
The radial alignment of HP, IP and LP casing i.e. rolling test of all these casing are also to be
carried out after final alignment of rotor and with the CWP in operation etc. i.e. with similar
conditions of final alignment of rotors.
During release of TG deck springs and final alignment of rotors the condenser spring is also
to be kept in floating condition considering that condenser neck welding is already done.
Similarly the condenser spring measurement should be with in + 1.00 mm otherwise the
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 6of 9
shims may be adjusted in condenser springs. No adjustment of TG deck springs or condenser
springs are permitted after final alignment of the rotors. During any subsequent adjustment of
TG deck spring the final alignment of all rotors are to be checked.
After placement of TG deck springs in locked condition with shims and resistance pad etc, an
equal air gap between 5 .00 to 10.00 mm is left between all the springs and bottom of the
steel cover plate. The exact value of air gap can be determined by the civil engineer
depending upon his experience but generally it is between 5.00 to 10.00 mm only. The form
work and support of TG deck are removed once the concrete has hardened sufficiently.
This is generally done after 28 days of casting of the deck and all load of deck is transferred
over the spring units . Afterwards TG pedestals are placed /aligned and their elevation are
maintained as per required catenary of the machine before grouting the pedestals with the
non-shrinking cements . During releasing of TG deck spring while this additional 5.00 mm
shims (for additional compression) are removed the catenary of the machine is to be achieved
within + 0.20 mm bearing No. 1&4 with the help of TG deck springs by adjusting the
shims and afterwards only the rotors alignments should be taken up. Any minor variation in
catenary left after releasing of TG deck spring may be adjusted in the spherical/cylindrical
seat of the bearings for achieving the correct alignment of the shaft.
The height of TG deck spring are taken on four corners near the springs. Here some punch
mark may be provided on all springs so that measurements are taken at the same place
always. Certain minor variations on height of the spring units are permitted , if it is required
for achieving the Catenary of the machine. The TG deck spring shims are adjusted with the
help of hydraulic jacks. Either two/four numbers hydraulic jacks are used for this purpose
which are supplied by the spring supplier. Similar methods are used for release of the spring
locking bolts also. These hydraulic jacks are group operated type and works with one
pumping unit which is electrically operated. The ready-made galvanized shims are also
supplied in required sizes alongwith spring unit in 3.00 mm and 2.00 mm thickness so an
adjustment of upto 1.00 mm is possible in spring Units.
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 7of 9
After finally release of TG deck spring and with water in condenser hotwell upto operating
level including CWP in operation then spring heights are measured on four corners for all
future reference. The sizes of the shims are also recorded for each spring. A bench mark
may also be preserved on TG floor as reference for LP rear pedestal parting plane height for
all future reference. During realignment of machine in subsequent overhauling the `catenary
of the machine are to be checked and if necessary the shims of the springs are to be adjusted
to achieve the correct catenary or at least to the old values . The catenary checking and
alignment of rotors may be done together but all major adjustment for correction of catenary
is to be done by adjusting the shims of the spring units. Any minor adjustment for alignment
may be done on bearing if it is in permissible values and margins is available on the bearings
seals bores.
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 8of 9
CONDENSER NECK WELDING IN SPRING LOADED
FOUNDATION OF 200/250/500 MW KWU
DESIGN MACHINE.
Before neck welding all the major components of the condenser are to be installed including
its tubing , water boxes, dome wall assembly and its stiffener pipe, etc. After installation of
all the major components of the condenser the spring are released i.e. condenser is floated for
welding with the Turbine.
After floating the condenser, the spring height is recorded on its four corner and further they
are pre-compressed for the value of welding shrinkage’s by an amount of 3.00 mm depending
upon the designer requirements. The required pre-compression of the condenser spring can
be done by filling the equivalent weight of the water in the hot well of condenser and then
locking the condenser spring at that position. The locking of springs can be avoided if water
is filled up to required level and level is maintained during neck welding of the condenser.
Sometime during floating of condenser an additional weight of water is filled up in
condenser depending upon the designer’s requirement.
The TG deck springs are kept in locked condition during the neck welding of the condenser.
After completing the neck welding and draining of condenser ( for equivalent value of the
pre-compression of the condenser springs) the condenser springs height are recorded and if
variation are noticed for more than +/- 1.00 mm than the necessary adjustment is to be
carried out. This can be done by adjusting the shims in the springs although if proper care is
taken during the neck welding no such variation are noticed.
STEAM TURBINE
500 MW
ERECTION
SPRING LOADED FOUNDATION
Bharat Heavy Electricals Limited
Rev 00, 7-98
T1-08-0909G
Page No. 9of 9
Further during floating of TG deck springs the condenser spring heights are also monitored
and if necessary the shims may be adjusted on condenser springs to maintain the old values of
the condenser spring at the time of floating of condenser. During subsequent overhaul of the
unit the condenser spring height alongwith TG deck spring height need a monitoring. As a
general practice whenever the TG deck spring height are checked then the condenser springs
height are also to be checked.
During floating of the condenser it is to be ensured that condenser is free all a round and
none of the pipe line are obstructing the movement of the condenser. All the connected pipe
lines of the condenser are to be ensured on permanent hangers before floating of the
condenser. The condenser neck welding is carried out as per the back-step method for which
the procedure is laid down in KWU manual of steam Turbine assembly sheet No 1-2-6330-
0001/1.
During neck welding the complete height of L.P. inner and L.P. outer casing is installed in
position.
0sep.doc
ERECTION OF PIPING
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 1 of 10
1. ERECTION OF PIPING
NOTE: These guidelines are intended to provide advice to lay and
support pipings at site, especially non-prefabricated pipes < Nb
50.
GENERAL
These guidelines apply to turbine and generator piping forming part of
the BHEL scope of supply and delivered to the site in the form of
prefabricated pipe sections and straight lengths of piping.
Generally Applicable Specifications
Prefabricated lines > Nb 50
In case of deviation the site erection engineer to decide in alternate
routing.
LAYING OF PIPES WITH ROUTING SPECIFIED IN PIPING PLAN.
Lay the lines as specified in the piping plans.
Support them at the defined points.
Cold bending method and special pipe-bending equipment should
be used for bending of pipes.
Care should be taken to ensure that the deformation is well within
the tolerance limits.
ACCOMMODATION OF MOVEMENT AND EXPANSION.
Care is to be taken to ensure the movements at pipe terminals
and thermal expansion of the pipes themselves are
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 2 of 10
accommodated by adequately long legs and expansion loops.
For lines connected to emergency stop valves (main steam valve,
stop valve, bypass valve ) allowance of 20 mm in all directions
shall be made.
Determine with the aid of the diagram (Fig. 1 & 2 ) the pipe legs
required to accommodate terminal movement and thermal
expansion.
Ensure the valid coordinate system of that power plant (Fig 13) is
adhered.
If it is not possible to obtain values for movement of the terminal
point taken from Fig 14, add a 50% safety margin to the thermal
expansion calculated for the connecting pipe Figs 3 & 4.
ASCENDING AND DESCENDING GRADIENTS
Install all lines with the ascending or descending gradients
appropriate to their function.
Lay supply lines with a constant ascending or descending gradient
- at least 5 mm/m - with at the very least a 5O slope (-90 mm/m).
Lay drain and vent lines with a descending gradient of a least 20
mm/m.
PIPE SUPPORTS
Pipe supports should not restrict pipe movements. Where spring-
loaded supports are used, the additional load or load relief exerted
by spring force on the pipeline at maximum deflection from its
unloaded position should not exceed 25% of the supported pipe
weight. (Fig. 6).
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 3 of 10
The Table (Fig. 5) gives reference values for pipe supports.
When fabricated pipe supports and guides, only flat steel pipe
clamps and aluminum clamps serve as the pipe bearing surface.
The use of round -steel shackles should be avoided in all cases.
ATTENTION: Suspension supports are to be preferred to support
from beneath. Friction points should be avoided.
2. WELD PREPARATIONS AND WELDING OF PREFABRICATED
AND NON-PREFABRICATED PIPES.
WELD PREPARATIONS
Ensure proper edge preparation as per drgs.
Remove scale, rust, paint etc. from weld joints.
WELDING
Complete welding as per WPS/drgs.
Nitrogen purging to be done wherever required.
Complete N.D.T.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 4 of 10
SPECIAL SYSTEM REQUIREMENTS
Lubricating Oil System
Match up, weld and examine the prefabricated connecting pieces
of the discharge and suction nozzles prior to the final erection of
the first bearing pedestal.
Other matching and welding work to be done when the bearing
pedestal is full assembled.
The direction of flow of the oil temperature control valve should be
ensured as indicated by markings on the valve itself.
Jacking Oil Lines
Where possible, lay jacking oil lines so as to be protected by other
lines of larger nominal diameters against being used as an aid to
climbing.
Once the line has been welded to the bearing pedestal, fit a
protection plate to protect the line in this area.
Oil Vapor extraction lines
Ensure that oil vapor extraction lines are laid with a gradient
descending constancy towards the main oil tank without low
points. A drain loop at the lower end of this line upstream from the
blowers return drains to the oil tank.
Fire Prevention
To avoid fire hazards, do not route oil lines near lines or
components at high temperature.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 5 of 10
If the laying of oil lines in these areas cannot be avoided, ensure
that no detachable connections or valves are erected directly
above high-temperature lines or components.
Control Fluid System
Single Fluid Lines
Signal fluid lines comprise all those lines in which some
kind of signal or pulse is transmitted from one point to
another (in other words, almost all fluid lines which do not
lead directly from pump via filter to component). These
includes : primary oil lines, secondary auxiliary secondary
and bypass signal fluidlines, trip, auxiliary trip, test and
return fluid lines, by[pass startup fluid lines, and water filled
(condensate-filled) impulse lines.
They do not include : turbine start-up and auxiliary start-up
oil lines, pilot fluid line (between pressure transducer and
pilot valve on Nb200 and Nb250 bypass stop valves with LP
hydraulic system).
To ensure correct functioning of signal fluid lines, lay them
with an adequate ascending or descending gradient to
prevent air pockets from forming and accumulating. A
number of different routing strategies are available for this
purpose (the control medium flows from the control
equipment) Fig. 7.
Version 1.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 6 of 10
If a line is installed from the control equipment to the load with an
ascending gradient (ascending in the direction of flow) there must
be a minimum gradient of 67 mm Fig. 7.
Version 2.
If a line is installed from the control equipment to the load with a
descending gradient (ascending gradient counter to the direction
of flow) there must be a minimum gradient of 175 mm/m Fig. 7.
If it is not possible to install the line as shown in Version 1&2, two
other strategies may be adopted (Fig.8)
Version 3.
If local conditions make it necessary to install the line with one or
more high points, each high point must be provided with
permanent venting facilities (orifices with a diameter of 1.5mm).
Fig.8.
Version 4.
If local conditions make it impossible to observe the 10OC minimum
gradient in installing a line as shown in Version-2, then reduce the
gradient required from 175 mm/m to 67 mm/m by introducing an
external supply to reverse the direction of flow Fig.8.
Installation of Damping Devices
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 7 of 10
The as-installed configuration of each damping device is indicated
in symbolic form on the system flow chart. As the flow is generally
directed via the installed orifice plate, i.e. pressing the ball
downward against the valve seat, care must be taken to interpret
the symbol correctly.
If the system flow chart indicates that the damping device should
be installed as shown in Fig.9 the flow passes via the orifice plate
(slow flow) if the damping device is to be installed the other way
around the ball is lifted away from the seat and thus permits a
rapid through - flow.
3. SEAL STEAM SYSTEM
3.1 Seal Steam Lines, valve Stem Steam Leak-Off Lines and Seal Ring
Steam Leak-Off Lines.
In laying these lines, provide sufficient compensation for thermal
expansion. The service temperature for all lines can be assumed to be
approximately 450OC. These pipes expand by approximately 6 mm/m
between the cold state (initial temperature 20OC) and the hot state.
ATTENTION : Always include a safety margin.
3.2 Leak-Off and Seal Steam Extraction Lines in the Steam Seal Casings.
Insert leak-off and seal steam lines, though the pipe penetrations in the
LP end walls before mounting the LP bearing pedestals. Connect the
lines up when the LP steam seal casings have been fully assembled.
Ensure that the lines are concentric within the penetrations to
accommodate the insulation to be installed subsequently.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 8 of 10
3.3 Pressure Sensing Line Terminals for the Seal Steam Control system
Erect the pulse lines to the pressure transducers in a manner
which will prevent the generation of fluctuating pressure pulses.
Refer Fig.12.
Lay the header, with an ascending gradient from the terminal point
to the pressure transducers, making sure that the pipe leg below
the transducers has a gradient of 30OC.
From this pipe leg, in which two Nb 25 nozzles are welded, erect
two lines 500 mm long, to the pressure gauge cutoff valves of the
pressure transducers.
NOTE: The header should not be insulated over the last 2-3m so as to
ensure that all condensation takes place below the final
connection to the transducers. Fig.12.
4. DRAIN SYSTEM
4.1 Drain Lines
All drain lines shall have as steep a gradient as possible, an all
cases at least 20 mm/m.
In erecting these lines, provide sufficient compensation for thermal
expansion. The service temperature in plant can be assumed to
be approximately 450OC.
These pipes expand by approximately 6mm/m between the cold
state (initial temperature 20 O
C) and the hot state. Determine from
the diagram (Fig.2) the minimum legs required to accommodate
movement.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 9 of 10
ATTENTION : Always include a safety margin.
On drain lines made from thick-wall piping, ensure straight pipe
sections at least 500 mm long between the drain sockets (on
casings and pipes) and the first bend in the pipe.
4. PRESSURE SENSING LINES, GENERAL
In laying these lines, observe the following:
Lines under pressure must be laid with a constant descending gradient.
Lines under vacuum must be laid with a constant ascending gradient.
The above lines must have an adequate gradient - at least 1:15 (67
mm/m) - between their connection point and the transducer rack.
Lay pressure sensing lines such that the primary cutoff valve forms an
anchor point, which entails laying the line between the connection point
and the primary cutoff (anchor point) with the sufficient flexibility to
accommodate movement of the connection point. A compensating leg
extending 1 meter in each of two planes should be provided in the
lubricating oil, control fluid and drains system on account of the minimal
terminal movement there. (Refer Fig. 10 & 11).
Locking Devices for Threaded Connections.
All Fasteners should be locked using tab washers or a suitable thread
lock adhesive.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS FOR
ERECTION OF PIPING
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1010G Page No. 10 of 10
5. DESCRIPTION OF THE COORDINATE SYSTEM
When isometric are drawn of piping, an indication of the three orthogonal
axes X, Y and Z as in Fig.3 is required.
Projections of these axes in the corresponding drgs. shall be as under :
X axis = view toward generator
Y axis = view upward generator
Z axis = view to the right
This axis designation shall be positive where no prefix is used.
A minus sign prefix shall be used to indicate the opposite direction.
0sep.doc
SPECIFICATION FOR
GAS HEATING DEVICE
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 1of 10
1. APPLICATION
This device is used during heat-tightening of cylinderjoint bolts/studs
of steam turbine to a predeterminedjoint pressure. Heating process is
carried out by sending hot oxy-acetylene gases mixed with compressed
air into the holes provided in the bolts stud. This heating causes
elongation of the studs and then the capnut of corresponding
stud is screwed down by a specified amount in hot condition to
provide a calculated joint pressure in cold condition.
2. SCOPE OF WORK
This specification covers the broad guide lines on design,
manufacture and supply of gas heating device for the above mentioned
purpose. Scope of supply also covers associated compressed air
piping including a fine regulating valve, pressure gauge & pipe
fittings. Source for compressed air shall be made available. Similarly
oxy-acetylene cylinder with heating torch not covered under this
scope.
A measuring device for measuring the extension of stud/bolt due to
heating is also included in the scope of supply.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 2of 10
3. FUNCTIONAL REQUIREMENT AND DESIGN
INFORMATION:
3.1. Specified elongation of the stud to be achieved within 15 minutes.
3.2. a minimum clear height of 600 mm above the capnut is available
for insertion and removal of the heating device.
3.3. Separate heating device is required for each hole size of heating hole
in the stud i.e. 20,25 and 32.
3.4. Design should ensure that vent holes for release of hot gases in
outer tube remain open to atmosphere in all operating condition.
3.5. Material of all the stud is same 1 1/4 cr mo 3/4 v tib. The 0.2 proof
strength is 70 t/mm2
Thermal conductivity of above materials = 0.094 cal/cm-secoC
Specific heat -do- = 0.001 cal/kg-oC
Coefficient of linear expension = 13x10-6
3.6. Other requisite dimensional information for each heating hole size is
furnished below.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 3of 10
3.7. All dimensions in m.m.
STU
D
HOL
E
SIZE
LENGTH
OF
HEATING
HOLE
HEATING TUBE DIMENSIONS IN SIDE STUD APPROX.
MASS OF
HEAVIEST
PIECE
STUD GAUGE
LENGTH FOR
WORKING
ELONGATION
ELON
GATIO
N
LEHGTH OD x TH LENGTH DIA DIA D3
20 190 160 16 x 2.9 49 35 20 36 5 Kg 185 0.32
25 330 230 20 x 2.9 71 39.5 25 46 45 KG 325 0.53
32 565 530 25 x 2.9 79 42 32 46 85 Kg 560 0.90
4. FUNCTIONAL DESIGN
A typical outline sketches fig. No. 1 showing general arrangement of gas
heating device and fig No. 2 - measuring device are enclosed for reference
purpose.
4.1. This heating device is a portable unit. Heating should be possible in
any of the stud in assembled condition. Heating source is oxy-
acetylene gas.
4.2. Oxy-acetylene torch is ignited outside and then it is inserted in the
hole meant for it in the inlet chamber. Standard torch sizes should be
selected from the indian oxygen ltd; catalogue, suitable champing
device for holding the oxy-acetylene torch during heating process
should be provided.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 4of 10
4.3. A compressed air piping of suitable size is fixed to inlet chamber.
Compressed air inscribes the oxy-acetylene flame at the exit from inlet
chamber and led to a mixing chamber.
4.4. From mixing chamber hot gas mixture is led to heating tube through
is bond.
4.5. Heating tube is held co-axillay in the stud hole. End of heating tube
kept at a reasonable distance from end of hole in the stud.
4.6. After imparting the heat to the stud, this gas-mixture traverse back
through annulus passage between outer tube & heating tube &
released to atmosphere through vent holes in the outer tube.
4.7. A fine regulating valve on compressed air pipe line is provided to
regulate the compressed air pressure and dame is to be read on
circular pressure gauge with a range 0 to 20 ata. A proper air pressure
ensure that gas mixture reaches hole bottom with a reasonable
velocity of hot gases into atmosphere from safety consideration.
4.8. In elongation measuring device includes a simple measuring rod,
a sleeve and a depth gauge. Readings on the depth gauge showing
length if stud are recorded in cold condition before start of heating
process, and then after heat tightening again in cold condition.
The differences of these reading gives the elongation achieved.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 5of 10
5. MATERIAL OF CONSTRUCTION
While selecting the material for different components of heating device due
considerations to its operation at elevated temperature, high temperature
gradient and thermal cycling to be taken into account.
It is customary to use allow steel (CR-Mo-V or CR-Mo) to provide long life to
these component.
Measuring rod, depth gauge & sleeve material should be hardened and
tempered.
6. MECHANICAL DESIGN:
6.1. The sole responsibility of mechanical design rests with supplier
construction of the device should be robust to withstand thermal
cycling and thermal stresses. Device should be easy to install
assemble and dissemble.
6.2. Dimensional accuracy, fitting and surface finish should be as per i.s.
2102-1962 medium, i.s. 2709-64, i.s 3073-67 respectively.
6.3. Welding if used anywhere in assemgly shall be checked for crack &
defects. Defects to be rectified.
6.4. Due precaution toward operational safety must be taken.
6.5. MEASURING UNIT
6.5.1. Measuring unit consists of sleeve, depth gauge and
measuring rod. Depth gauge should have least account of 0.05
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 6of 10
mm. Depth gauge should be in general as per DIN 862. Its scale
must be case hardened.
6.5.2. Measuring rod length may be made up in two pieces. Base
piece is to have a flat circular and of 16 m.m. dia and other end
should have female threads.
6.5.3. Extension pieces should have threaded ends at both end.
6.5.4. Extension piece length correspond to 130, and 370 m.m.
6.5.5. Length of bass piece is 275 m.m.
6.5.6. All threading corresponds to M10.
6.5.7. Knurling should be done on each piece at one place.
6.5.8. Measuring sleeve should have both faces parallel and flat.
Length of sleeve should be chosen such that the difference
dimension A & C is more than 150 m.m. (see if fig. 2). Sleeve
length C should be more than dimension LR.
6.6. COMPRESSED AIR SYSTEM:
6.6.1. The hole in the inlet chamber for insertion of heating torch
should match with the standard torch shapes of Indian
Oxygen Ltd; without leaving a large clearance or causing
insertion problem.
6.6.2. A clamping device to hold the heating torch should be
provided.
6.6.3. A clamping device to hold the heating torch should be
provided.
6.6.4. Pressure gauge should be able to read the 0.5 at a
difference air pressure.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 7of 10
6.6.5. Compressed air unit should be removable and kept
seperately when not in use.
6.7. In general, there should not be any burr left on any component.
Threading done should of high standard for easy assembly &
dissembly. Scale should be flat & move vertically upward or down
ward freely.
7. DESIGNATION/IDENTIFICATION
Each gas heating device should be designated based on the stud heating
hole, 20mm, 25mm or 32mm. On the inlet chamber the torch sizes (As
per Indian Oxygen Ltd; catalogue) to be used, shall be punched. Outer tube
shall also be marked for the heating hole size. Heating tube shall also be
punched with the O.D & thickness.
Measuring red extension piece, measuring sleeve shall bear on it, the exact
length.
8. DESIGN DOCUMENT & PRE APPROVAL DOCUMENT
Minimum three copies of assembly drawing with item number, with its
nomenclature, calculations performed, material test certificate, valve
supplier test certificate, pressure gauge calibration record, and
operation manual should be submitted to EDM (ST) one month before
final despatch of the equipment for approval.
9. FUNCTIONAL TESTING & ACCEPTANCE
Supplier shall exhibit the suitability of operation of the heating device at
BHEL - works or at site (to be mutually agreed). Only after such
successful field demonstration device will be finally accepted. Suppleir has
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
GAS HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 2-97
T1-08-1111G Page No. 8of 10
to demonstrate its use & operation at his own cost. This requirement may
be waved-off for repeated order if felt necessary. If site trial show higher
time of achieving the elongation, repair replacement free of cost will be done
by suppliers.
10. PACKING & DESPATCH
10.1. Complete measuring device shall be put in a linen lined durable box.
On the lid of this box following marking be put "stud elongation
measuring device".
10.2. Complete gas heating device shall be nicely packed in a wooden box
for avoiding damage during transportation. Inside the box also,
components should be elamped suitably to avoid damage.
II I
STEAM TURBINE500 MW
II
I ERECTION
SPECIFICATIONSFOR
GAS HEATING DEVICE
I
~ESSlAE GAUGE
.
ARRANGEMENTOF GASHEATING DEVICE
Bharat Heavy Electricals LimitedRev 00, 2-97
T1-08-1111 G
Page No. 90f 10
(1IVfl"t'VPfII
STEAM TURBINE
MM 500 MW
~ I ERECTION
SPECIFICATIONSFOR
GAS HEATING DEVICE
SCALE
..
1:..J
MEASURfNG RODBASE.. PIECE
MEASURINGUNIT
Bharat Heavy Electricals LimitedRev 00, 2-97
T1-08-1111 G
Page NO.1 Oaf 10
0sep.doc
SPECIFICATION FOR
BREECH NUT HEATING
DEVICE
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
BREECH NUT HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1212G Page No. 1of 6
1. ASSEMBLY OF BREECH NUT
The breech nut assembly used in between connection of main steam inlet line and HP module. This type of connection are very useful in barrel type design of HP module and helps in very fast assembly / dismantling of the module in erection and subsequent overhaul of the unit. The number of breech nut depend upon the numbers of steam entry connection for the HP module. However there are generally two / four breech nut assemblies are used in a particular module.
A special care is must while making the breech nut assembly first time at site during erection stage. The main steam inlet line connections are welded with the HP casing inlet insert after assembly of the breech nut and no major correction of breech nut is possible unless the inlet line are cut and rewelded.
2. PROCEDURE / SPECIAL CHECKS DURING ASSEMBLY OF
BREECH NUT AT ERECTION STAGE.
2.1. Ensure cleanliness of the inlet insert and HP casing matching flanges. A feeler tight joint is to be ensured on these faces during its assembly.
2.2. Ensure that no burrs / high spots are left on threading portion of the breech nut and all the threads are very smooth.
2.3. Ensure fitting of all radial / axial dowel pins of the breech nut before its final assembly. These dowel pins causes serious problem during assembly of breech nut at site if the holes are not properly reamed and dowel pins are not fitted at works before dispatch. Many times after drilling / reaming of holes at works the sizes are taken and pins are dispatched after manufacturing without actual fitting.
2.4. Ensure compression of U seal ring before its assembly. The faces of the U-seal ring may be checked for the line contact on a surface plate.
2.5. High temperature molykote is to be used during assembly of breech nut in all the area and matching flanges of inlet insert / HP casing are to be applied with birkosite / stag-B jointly compound.
2.6. A 0.03 mm feeder tight joints are to be ensured on faces A & B from all the inspection holes of the periphery before heat tightening of the breech nut. The value of heat tightening is mentioned over the drawings.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
BREECH NUT HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1212G Page No. 2of 6
2.7. The heat tightening device supplied with the machine is to be used for heat tightening of the nut. The radial dowel pins of the breech nut are also to be locked in position to avoid their falling at a later date.
2.8. The welding works of HP casing inlet insert pipelines may be taken up after heat tightening of the breech nut.
2.9. Ensure that radial holes of breech nut are covered properly to avoid entry of any foreign material.
2.10. The tightening of breech nut is done with the help of overhead crane in both the condition i.e. during normal tightening and during heat tightening of the nut. Proper size pins are to be used on periphery holes of breech nut to avoid any damaged of periphery holes are any damaged to inside thread of breech nut.
2.11. The tightening of breech nut is done with the help of overhead crane in both the conditions i.e. during normal tightening & during heat tightening of the nut. Proper size pins are to be used on periphery holes of breech nut to avoid any damage of periphery holes are any damage to inside threads of the breech nuts.
3. DISMANTLING OF BREECH NUT DURING OVERHAULING.
A similar procedure of heating the breech nut is used for loosing it. But before the heating / loosing of breech nut the main steam inlet pipe lines need their locking to avoid any type of load transferred on the threads on the breech nut. Though perfect free joint are made during welding of the main steam inlet pipelines with the breech nut but still the problem of piping pull are phased in these area during the various reasons. Hence it is essential to lock the pipeline to avoid its movement in any of the direction. The proper welding procedure are to be used during locking of the pipelines if these are locked by welding method. After loosing of the breech nut fully the locking of pipelines are to be made free. The offset of pipelines may be recorded at this stage and any major variation in pipeline need correction by cutting / rewelding of pipelines.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
BREECH NUT HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1212G Page No. 3of 6
4. PROCEDURE/SPECIAL CHECKS DURING DISMANTLING/RE-
ASSEMBLY OF BREECH NUT IN OVERHAULING OF THE UNIT
4.1. Ensure locking of the inlet pipeline to avoid any load on the threads of the breech nut due to pull / push of the pipe line an any of the direction while opening it.
4.2. Ensure that all the radial dowel pins of the breech nut are intact before opening the nut. If any of the dowel pins are loose then the same can be removed before loosening the nut.
4.3. U-seal ring are to be ensured for their line contact and compression value before reassembly.
4.4. Ensure fitting of radial dowl pins of the breech nut. These dowel pins play a major role during its re-assembly.
4.5. Ensure parallellity of inlet insert and its alignment with the HP casing before its assembly. The pipeline hangers may be adjusted at this stage if required.
4.6. Any major variation of alignment and parallelity of pipe line are to be corrected before its assembly.
4.7. Similar procedure of assembly of breech nut may be used as explained during erection stages.
4.8. During opening and re-assembly of breech nut if any additional load is transferred due to pull / push of pipeline on breech nut threads then that may cause seizure / damage of the breech nut threads.
5. OVERHAULING OF KWU DESIGN 200 / 250 / 500 MW
TURBINE IN CASE OF SPRING LOADED FOUNDATION
In case of spring loaded foundation the alignment and catenary of HP / IP / LP /Gen. rotors are to be checked before lifting of any major component from the TG deck . During checking of the rotor alignment, the instruction issued against spring loaded foundation are to be followed. To cut short the time cycle of overhauling the rotor alignment and catenary may also be corrected at this stage itself so the further work of overhauling like removing of generator rotor, lifting of LP rotor, lifting of HP module etc. may be taken up as per the requirement. This will cut short the overhauling duration of the machine.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
BREECH NUT HEATING DEVICE
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1212G Page No. 4of 6
By following above procedure in overhauling of the unit the various works of individual casing like fitting of radial keys, axial keys, casing packers etc. may be taken up individually otherwise most of the above works are to be kept pending for alignment of the HP / IP / LP / Gen. rotors . During correction of rotors alignment the catenary of the shaft is also to be maintained. The adjustment of shims in the bearing spherical / cylindrical seat is limited by + / - 0.50 mm in pedestal seal bore values from its base values. The majority of adjustment in achieving the catenary of the shaft may be done by adjusting the shims in the TG deck spring.
II STEAM TURBINE500 MW
ERECTION
SPECIFICATIONSFOR
BREECH NUT HEATING DEVICE
I-~
"""""""""""" .. . . -. ,....................... ,.................................. ...,..
SleeveJoint with U-Section Ring Installed,
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-1212GPage No. Sof 6
. STEAM TURBINE500 MW
ERECTION
SPECIFICATIONSFOR
BREECH NUT HEATING DEVICE
------
\,-
Fig.J.C~ntact Surface, Grooves for U-Section Ring~
Bharat Heavy Electricals LimitedRev 00, 7-98
T1-08-1212G
Page No. 60f 6
0sep.doc
SPECIFICATION FOR
THERMAL INSULATION
STEAM TURBINE 500 MW ERECTION
SPECIFICATIONS
FOR THERMAL INSULATION
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1313G Page No. 1of 6
1. CONSTRUCTIONAL DETAILS AND APPLICATION PROCEDURE:
1.1. The following constructional/installation procedure shall be adopted.
1.1.1. The turbine/ valve casing surface shall be cleaned with wire
brush to remove dust, dirt and such residues. Any
contamination due to oil/grease shall be removed with suitable
solvent.
1.1.2. The holding construction shall consist of MS strips of 25 x 3 mm
which shall be secured either with nuts and bolts or tack welded
on the pads already provided on casing surface for the purpose.
The holding construction shall be separately made for top and
bottom half of the casing for ease of maintenance. Wherever,
required, additional framework of MS strips shall be provided to
impart adequate strength to the holding structure.
1.1.3. The MS Rod of 10 mm dia having length equivalent to insulation
thickness are welded on the MS frame at a pitch of 250 mm
(max.0).
1.1.4. Casing flange joint (parting plate) shall be provided with a
separation made out of Aluminium sheet ( 2 mm thick) as a
distant line between top and bottom half of the insulation.
1.1.5. All thermocouples shall be masked with sleeves made out of
Aluminium sheet for proper access during maintenance and
replacement when and where necessary.
1.1.6. Sprayed - on Rockloyd fibers (HT) shall be sprayed using
specially designed spraying equipments and accessories. The
STEAM TURBINE 500 MW ERECTION
SPECIFICATIONS
FOR THERMAL INSULATION
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1313G Page No. 2of 6
fibers shall be processed to a desired pattern and finally
conveyed to the application point by means of a hose. The
spray gun provided at the end of the hose, supplies, the lloyd
bond binder in the form of a finely distributed concentric spray.
The sprayed lloyd bond binder wraps up the fibers and the
wetted strike the surface to be insulated forming a continuous
monolithic layer. The required bulk density and the Lloyd Bond
binder proportion shall be achieved by controlling the fiber output
and lloyd Bond binder quantity. It shall be necessary to use
wooden pattas/probe for compacting the sprayed mass in
congested and other locations in order to provide required
density and thickness. Each layer shall be individually supported
with the help of wire netting and MS retainers. The surface
temperature limit shall be relaxed in restricted locations with the
above mentioned constraints.
1.1.7. The Cat-9 (Bond Seal) finishing cement plaster shall be trowel
applied all over the insulated surface with a first coat of 4-5 mm.
The final coat of Cat-9 (Bond Seal) shall be applied after
reinforcing Lloyd fabric all around the plastered surface.
1.1.8. The surface shall finally be finished with a coat of Lloyd FR pain
80/100 microns of special duty oil resistant and heat resistant
coating.
NOTE: All the pipes below turbine casing where spray type of
insulation is finished and mattresses insulation starts, shall be
finished with Cat-9 hard setting compound upto 4 mtrs. Length.
STEAM TURBINE 500 MW ERECTION
SPECIFICATIONS
FOR THERMAL INSULATION
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1313G Page No. 3of 6
1.2. INSULATION APPLICATION FOR PIPING
1.2.1. The surface of the piping shall be cleaned with wire brush to
remove dust, dirt or other such residues.
1.2.2. Likely Resin Bonded Rockloyd (LRB Mattresses) factory made
machine laid machine stitched mattresses conforming to IS :
8183 having GI Wirenetting on one side of design thickness shall
then be applied over the pipe surface.
1.2.3. Individual layer of mattresses shall not exceed 75 mm in
thickness and shall be applied ensuring snug fit with the surface.
1.2.4. The ends of wire netting at the longitudinal and circumferential
joint shall be butted together to ensure that no gap is left at the
joints and then laced with GI wire of 0.1 mm.
1.2.5. All the joints in insulation shall be properly staggered.
1.2.6. 8/10 mm thick Cat-9 (Bond Seal) finishing cement plaster shall
then be trowel applied over the LRB mattresses for piping below
the casing, upto 4 mtr. Length.
1.2.7. This shall finally be finished with the coat of Lloyd FR paint,
special duty oil resistant and heat resistant coating in thickness
of 80 / 100 microns.
STEAM TURBINE 500 MW ERECTION
SPECIFICATIONS
FOR THERMAL INSULATION
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1313G Page No. 4of 6
1.2.8. For all other pipes 0.7 mm Aluminium sheet shall be provided
duly rolled and grooved by self tapping screws.
1.3. INSULATION APPLICATION FOR ESV’S IV’S MAIN STEAM VALVE
LP BYE PASS VALVE CHESTS.
1.3.1. Above shall be insulated with sprayed Rocklloyd Fiber (HT) after
thorough cleaning with the same procedure as applicable for
cylinder casings.
1.3.2. 8 / 10 mm Cat-9 (Bond Seal), finishing cement shall then be
provided as explained in 9.6 above.
1.3.3. The insulation shall finally be finished with Lloyd FR Paint
special duty oil resistant, heat resistant compound of 80 / 100
microns thickness.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
THERMAL INSULATION
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1313G Page No. 5 of 6
NAME OF CONTRACT PAPCKAGE
THERMAL INSULATION
PACKAGE
FIELD QUALITY PLAN FOR TURBINE INSULATION
MATERIAL RECEIPT/ STORAGE/PRE-ERECTED/ ERECTION/PRE-COMMISSIONING/COMMISSIONING/POLST COMMISSIONING
EQP NO. REV. DATE PAGE
SNO CHARACTERISTICS /
ITEMS TYPE OF CHECK INSTRUMENT CLASS QUANTUM//F
REQUENCY OF CHECK
REFERENCE DOCUMENTS & ACCEPTANCE STANDARD
FORMAT OF RECORDS
REMARK
S
1. MATERIAL RECEIPT
MATERIAL RECD. AT SITE TO BE CORELALTED WITH chp/mdcc AND bATCH nO. (WHICHEVER IS APPLICABLE)
VISUAL Minor 100 Log Book Corelation of Batch No. Thickness/Size/WRT/CHP/MDCC
Sprayable granulated Mineralo Wool
-do- -do- -do- -do- IS-3677 -do-
Bonding Agent -do- -do- -do- -do- - -do-
SS Wirenetting/SS wire
-do- -do- -do- -do- IS-6528 -do-
GI Wirenetting/GI Wire
-do- -do- -do- -do- IS-280 -do-
Self Setting cement -do- -do- -do- -do- IS-9743 -do-
Oil Resistance Paint -do- -do- -do- -do- Berger Make -do-
2. IN PROCESS
Supporting os Structure
Visual Physical Minor 100 %
Surface Preparation(Physical)
-do- -do- -do- 100 % check for dirt, grease etc.
Shall be free from dirt, grease, rust, wetness etc.
Log Sheet
Spray of 1st layer of insulation and subsequent layers(Thickness of Insulation for each layer).
Thickness Thickness Gauge
Minor Three reading of each component to be taken
BHEL Engg. Approved insulation thickness schedule.
Fixing of SS wire netting/ SS wire after first layer and G.I. wirenetting/ GI wire after subsequent layers.
Visual Physical Minor 100 % SS Wirenetting/ wire shall be used wherever the temp. Is more than 400 Deg.C. GI wirenettin g/ GI wire shall be used.
Supporting of retainers
Visual Physical Minor 100 %
Finishing with Plaster Thickness Thickness Gauge
-do- Three reading on each component to be taken.
BHEL Engg. Approved insulation thickness schedule.
STEAM TURBINE
500 MW
ERECTION
SPECIFICATIONS
FOR
THERMAL INSULATION
Bharat Heavy Electricals Limited Rev 00, 7-98
T1-08-1313G Page No. 6 of 6
Oil Resistance compound painting
Covering capacity Measuring tape
-do- These reading, at the beginning of application, in Mid. Course of applications, at the end of application.
Suppliers Literatures enclosed (Annedxure-1)
3. SPRAYED OF ROCKWOOL
Mix. On Components (One per job.)
hermal conductivity BHEL APPD. lAB.
Major Two samples IS-3346 & IS-9742
T.C.
Heat Resistance -do- -do- One Samples IS-3144 & 9742 -DO-
Density Standard Template
-do- -do- BHEL Engg. Approveod bulk density schedule.
Incombustibility LAB -do- -do- IS-3144 & 9742 -DO-
Compressive strength
LAB Major One sample IS-5724 & 9742 T.C.
4. FINAL CHECKS
Completion of sprayed rockwool insulation
Total Ins. thickness Thickness gauge
Minor Random (Three readings at different pts. Of surface.)
BHEL Engg. Appd. Thick ness schedule.
Log sheet.
Hard setting cement Thickness Thickness Minor Five readings
Oil Resistant Compound
- do - Micrometer
-do- Five readings after drying
Tender Spcen. 80-100 Microse.
-do-
Surface temp. Over finished surface
Temperature Measurement/
Digital, contact.
Major`
Five readings at different pts.
BHEL Appt. Procedure Tender Spen. Data sheet).
-do-
Ambient Temp. At a dist. Of 1.5 mtr. From ccladding surface.
-do- -do- -do- Three readings at different pts.
-do- -do-
Finished insulation surface.
Visual Minor no cracks.
Note : 1. Wherever samples are drawn for testing at site, double readings must be ensure for any re-tests, if required later on. 2. Pre-Commissioning checks to be finalised with Operational Services.