  • 8/12/2019 49 Sites NOC Received

    1/5

    New Site ID NOC Received

    Date

    FDN

    Completion

    Date

    TWR

    Completion

    Date

    Status

    KLKT-RIL-0439 10-Jan-14 1-Aug-13 FDN Comp

    KLKT-RIL-0701 10-Jan-14 9-Dec-13 21-Dec-13 FDN+TWR Comp

    KLKT-RIL-0347 15-Jan-14 HOLD Before FDN

    KLKT-RIL-1470 15-Jan-14 18-Dec-13 FDN Comp

    KLKT-RIL-0515 2-Jan-14 24-Dec-13 5-Jan-14 FDN+TWR CompKLKT-RIL-0579 16-Jan-14 HOLD

    KLKT-RIL-0699 7-Jan-14 HOLD

    KLKT-RIL-1074 16-Jan-14 10-Dec-13 21-Dec-13 RFE1 Offered

    KLKT-RIL-1073 16-Jan-14 19-Nov-13 13-Jan-14 FDN+TWR Comp

    KLKT-RIL-1071 7-Jan-14 HOLD

    KLKT-RIL-0604 7-Jan-14 HOLD

    KLKT-RIL-1040 7-Jan-14 14-Nov-13 HOLD After FDN

    KLKT-RIL-0059 16-Jan-14 HOLD

    KLKT-RIL-0973 7-Jan-14 26-Nov-13 8-Jan-14 FDN+TWR Comp

    KLKT-RIL-1105 16-Jan-14 16-Dec-13 FDN Comp

    KLKT-RIL-0692 8-Jan-14 5-Jul-13 20-Nov-13 RFE1 Offered

    KLKT-RIL-0708 3-Jan-14 19-Jul-13 FDN Comp

    KLKT-RIL-0788 3-Jan-14 2-Sep-13 HOLD After FDN

    KLKT-RIL-0816 11-Jan-14 HOLD

    KLKT-RIL-1143 15-Jan-14 22-Aug-13 31-Aug-13 RFE1 Offered

    KLKT-RIL-0678 15-Jan-14 20-Nov-13 HOLD After FDN

    KLKT-RIL-1107 15-Jan-14 22-Oct-13 HOLD After FDN

    KLKT-RIL-0406 8-Jan-14 5-Aug-13 14-Jan-14 FDN + TWR Comp

    KLKT-RIL-0334 10-Jan-14 1-Jan-14 15-Jan-14 FDN + TWR Comp

    KLKT-RIL-0608 9-Jan-14 HOLD

    KLKT-RIL-0319 3-Jan-14 WIP

    KLKT-RIL-1638 15-Jan-14 HOLD

    KLKT-RIL-1647 15-Jan-14 7-Aug-13 HOLD After FDNKLKT-RIL-1611 15-Jan-14 HOLD

    KLKT-RIL-1643 13-Jan-14 1-Aug-13 26-Sep-13 RFE1 Offered

    KLKT-RIL-1610 9-Jan-14 HOLD

    KLKT-RIL-1757 10-Jan-14 4-Sep-13 30-Sep-13 RFE1 Offered

    KLKT-RIL-1741 10-Jan-14 22-Aug-13 FDN Comp

    KLKT-RIL-1431 6-Jan-14 11-Dec-13 22-Dec-13 RFE1 Offered

    KLKT-RIL-1398 6-Jan-14 30-Aug-13 FDN Comp

    KLKT-RIL-1436 6-Jan-14 11-Sep-13 FDN Comp

    KLKT-RIL-1326 6-Jan-14 2-Sep-13 HOLD AFTR FDN

    KLKT-RIL-1395 6-Jan-14 11-Oct-13 28-Oct-13 RFE1 Offered

    KLKT-RIL-1361 6-Jan-14 HOLD

    KLKT-RIL-1323 6-Jan-14 HOLD

    KLKT-RIL-1397 6-Jan-14 HOLD

    KLKT-RIL-0020 7-Jan-14 29-Aug-13 8-Jan-14 FDN+TWR Comp

    KLKT-RIL-0975 7-Jan-14 13-Nov-13 30-Nov-13 FDN+TWR Comp

    KLKT-RIL-0022 7-Jan-14 24-Sep-13 6-Nov-13 RFE1 Offered

    KLKT-RIL-0828 7-Jan-14 HOLD

    KLKT-RIL-1006 7-Jan-14 29-Oct-13 HOLD After FDN

    KLKT-RIL-0383 7-Jan-14 24-Nov-13 25-Dec-13 FDN+TWR Comp

  • 8/12/2019 49 Sites NOC Received

    2/5

    KLKT-RIL-1466 2-Jan-14 8-Jan-14 FDN Comp

    KLKT-RIL-1770 2-Jan-14 WIP

    KLKT-RIL-1213 15-Jan-14 25-Dec-13 16-Jan-13 FDN+TWR Comp

  • 8/12/2019 49 Sites NOC Received

    3/5

    Remarks

    er. Neighbour has damaged the shuttering. GD made in the Local PS. Police protection required

    tion Complete, 9 Mtr delta is not yet ready to deliver, expected by 15.01.14

    paid & we have approached, he is not allowing to start due to his own problem. Intimated ro FO Ratan Seth

    uired, local objection, LL is asking for the NOC copy as local objection is there

    Local Objection. Task force visited.

    Regd Agreement required.

    NOC required. NOC copy given and Informed EIC.

    LL not interested to install tower

    RFE1 Offered

    iljala PS, which has been tried to submit on 14.01.14. But PS refused to receive. They want all relevant docs. Need to d

    alth hazard. Councilor objecting the site cons mentioning health hazard/radiation issue.

    NOC Required. NOC Copy given yesterday

    NOC Required. NOC Copy given yesterday

    Narrow space for GBM, no road for trailer and crane entry

    NOC Required.

    Excv Wip

    NOC Required

    NOC Required. NOC Copy given yesterdayLL is asking for NOC

    Local Objection was there. Trying with NOC

    RFE1 Offered

    Local Objection

    RFE1 Offered

    ached on 09.01.14, bu LL didnt allow start the work & asked for 1L as security deposit. Informed to RE TL Ratan Setth &

    ntioned in the NOC, LL is not allowing to start the work, to be visited & convinced the LL

    tion material, even they have tried to damage the vehicle. Intimated to RE TL Ratan Setth. Need to discuss.

    C required, now LL is not allowing to start as they have some internal family problem

    ner has asked for 2-3 days. He is expecting some local issue may arise, he will try to solve proactively. Discussed with J

  • 8/12/2019 49 Sites NOC Received

    4/5

    Excv started

  • 8/12/2019 49 Sites NOC Received

    5/5

    iscuss & provide.

    tried to convince but failed

    yanta Saha & Mr. Saurabh GHoshal. Need to take call on 16.01.14