49 Sites NOC Received
-
Upload
debraj-roy -
Category
Documents
-
view
218 -
download
0
Transcript of 49 Sites NOC Received
-
8/12/2019 49 Sites NOC Received
1/5
New Site ID NOC Received
Date
FDN
Completion
Date
TWR
Completion
Date
Status
KLKT-RIL-0439 10-Jan-14 1-Aug-13 FDN Comp
KLKT-RIL-0701 10-Jan-14 9-Dec-13 21-Dec-13 FDN+TWR Comp
KLKT-RIL-0347 15-Jan-14 HOLD Before FDN
KLKT-RIL-1470 15-Jan-14 18-Dec-13 FDN Comp
KLKT-RIL-0515 2-Jan-14 24-Dec-13 5-Jan-14 FDN+TWR CompKLKT-RIL-0579 16-Jan-14 HOLD
KLKT-RIL-0699 7-Jan-14 HOLD
KLKT-RIL-1074 16-Jan-14 10-Dec-13 21-Dec-13 RFE1 Offered
KLKT-RIL-1073 16-Jan-14 19-Nov-13 13-Jan-14 FDN+TWR Comp
KLKT-RIL-1071 7-Jan-14 HOLD
KLKT-RIL-0604 7-Jan-14 HOLD
KLKT-RIL-1040 7-Jan-14 14-Nov-13 HOLD After FDN
KLKT-RIL-0059 16-Jan-14 HOLD
KLKT-RIL-0973 7-Jan-14 26-Nov-13 8-Jan-14 FDN+TWR Comp
KLKT-RIL-1105 16-Jan-14 16-Dec-13 FDN Comp
KLKT-RIL-0692 8-Jan-14 5-Jul-13 20-Nov-13 RFE1 Offered
KLKT-RIL-0708 3-Jan-14 19-Jul-13 FDN Comp
KLKT-RIL-0788 3-Jan-14 2-Sep-13 HOLD After FDN
KLKT-RIL-0816 11-Jan-14 HOLD
KLKT-RIL-1143 15-Jan-14 22-Aug-13 31-Aug-13 RFE1 Offered
KLKT-RIL-0678 15-Jan-14 20-Nov-13 HOLD After FDN
KLKT-RIL-1107 15-Jan-14 22-Oct-13 HOLD After FDN
KLKT-RIL-0406 8-Jan-14 5-Aug-13 14-Jan-14 FDN + TWR Comp
KLKT-RIL-0334 10-Jan-14 1-Jan-14 15-Jan-14 FDN + TWR Comp
KLKT-RIL-0608 9-Jan-14 HOLD
KLKT-RIL-0319 3-Jan-14 WIP
KLKT-RIL-1638 15-Jan-14 HOLD
KLKT-RIL-1647 15-Jan-14 7-Aug-13 HOLD After FDNKLKT-RIL-1611 15-Jan-14 HOLD
KLKT-RIL-1643 13-Jan-14 1-Aug-13 26-Sep-13 RFE1 Offered
KLKT-RIL-1610 9-Jan-14 HOLD
KLKT-RIL-1757 10-Jan-14 4-Sep-13 30-Sep-13 RFE1 Offered
KLKT-RIL-1741 10-Jan-14 22-Aug-13 FDN Comp
KLKT-RIL-1431 6-Jan-14 11-Dec-13 22-Dec-13 RFE1 Offered
KLKT-RIL-1398 6-Jan-14 30-Aug-13 FDN Comp
KLKT-RIL-1436 6-Jan-14 11-Sep-13 FDN Comp
KLKT-RIL-1326 6-Jan-14 2-Sep-13 HOLD AFTR FDN
KLKT-RIL-1395 6-Jan-14 11-Oct-13 28-Oct-13 RFE1 Offered
KLKT-RIL-1361 6-Jan-14 HOLD
KLKT-RIL-1323 6-Jan-14 HOLD
KLKT-RIL-1397 6-Jan-14 HOLD
KLKT-RIL-0020 7-Jan-14 29-Aug-13 8-Jan-14 FDN+TWR Comp
KLKT-RIL-0975 7-Jan-14 13-Nov-13 30-Nov-13 FDN+TWR Comp
KLKT-RIL-0022 7-Jan-14 24-Sep-13 6-Nov-13 RFE1 Offered
KLKT-RIL-0828 7-Jan-14 HOLD
KLKT-RIL-1006 7-Jan-14 29-Oct-13 HOLD After FDN
KLKT-RIL-0383 7-Jan-14 24-Nov-13 25-Dec-13 FDN+TWR Comp
-
8/12/2019 49 Sites NOC Received
2/5
KLKT-RIL-1466 2-Jan-14 8-Jan-14 FDN Comp
KLKT-RIL-1770 2-Jan-14 WIP
KLKT-RIL-1213 15-Jan-14 25-Dec-13 16-Jan-13 FDN+TWR Comp
-
8/12/2019 49 Sites NOC Received
3/5
Remarks
er. Neighbour has damaged the shuttering. GD made in the Local PS. Police protection required
tion Complete, 9 Mtr delta is not yet ready to deliver, expected by 15.01.14
paid & we have approached, he is not allowing to start due to his own problem. Intimated ro FO Ratan Seth
uired, local objection, LL is asking for the NOC copy as local objection is there
Local Objection. Task force visited.
Regd Agreement required.
NOC required. NOC copy given and Informed EIC.
LL not interested to install tower
RFE1 Offered
iljala PS, which has been tried to submit on 14.01.14. But PS refused to receive. They want all relevant docs. Need to d
alth hazard. Councilor objecting the site cons mentioning health hazard/radiation issue.
NOC Required. NOC Copy given yesterday
NOC Required. NOC Copy given yesterday
Narrow space for GBM, no road for trailer and crane entry
NOC Required.
Excv Wip
NOC Required
NOC Required. NOC Copy given yesterdayLL is asking for NOC
Local Objection was there. Trying with NOC
RFE1 Offered
Local Objection
RFE1 Offered
ached on 09.01.14, bu LL didnt allow start the work & asked for 1L as security deposit. Informed to RE TL Ratan Setth &
ntioned in the NOC, LL is not allowing to start the work, to be visited & convinced the LL
tion material, even they have tried to damage the vehicle. Intimated to RE TL Ratan Setth. Need to discuss.
C required, now LL is not allowing to start as they have some internal family problem
ner has asked for 2-3 days. He is expecting some local issue may arise, he will try to solve proactively. Discussed with J
-
8/12/2019 49 Sites NOC Received
4/5
Excv started
-
8/12/2019 49 Sites NOC Received
5/5
iscuss & provide.
tried to convince but failed
yanta Saha & Mr. Saurabh GHoshal. Need to take call on 16.01.14