Semi-annual Environmental Monitoring Report
Project Number: 40540-017 June 2019
South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2 - Tranche 1
This Semi-annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
Environmental Monitoring Report _______________________________________________________________________ Project Number: 40540-014 Semi-Annual Report June 2019
3592/3593-BAN: SASEC ROAD CONNECTIVITY PROJECT-2 Prepared by Roads and Highways Department (RHD) for the People’s Republic of Bangladesh and the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Government of the People’s Republic of Bangladesh Ministry of Road Transport and Bridges Road Transport and Highways Division
Roads and Highways Department
Semi-Annual ENVIRONMENTAL MONITORING REPORT Of
SASEC Road Connectivity Project-2 (ADB Loan 3592/3593-BAN)
Reporting Period: January- June 2019 Submitted on: June 2019
Project Implementation Consultant:
Korea Consultants International Co., Ltd. (South Korea),
in joint venture with
Chodai Co., Ltd. (Japan),
H.P. Gauff Ingenieure GmbH & Co. KG-JBG (Germany),
Lea Associates South Asia Private Limited (India),
SOOSUNG ENGINEERING CO. LTD. (South Korea),
in association with
BCL Associates Limited (Bangladesh),
BETS Consulting Services Ltd. (Bangladesh),
Development Technical Consultants Pvt. Ltd. (Bangladesh),
Philkoei International, Inc. (Philippines)
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN i
Acronyms and Abbreviations iii
Currency Equivalents iii
Weights and Measures iii
1 Executive Summary iv
2 Introduction 1
2.1 Background of the Project 1
2.2 Objectives of the Project 2
2.3 Purpose of the Report 2
2.4 Locations of the Project Roads 3
3 Technical Description of the Project Road 6
3.1 Scope of Works 6
3.2 Project Components and Design 6
3.3 Construction and Maintenance Contracts 7
3.4 Present status of WP Contracts Signing 7
3.5 Project Cost, Estimates and Quoted Prize of WPs 8
4 Environmental Characteristics of the Project 10
5 Environmental Monitoring Relationships with Contractors, Owner and Lender 11
6 Project Status and ongoing Activities of Work Packages 12
7 Compliance with Environmental Related Project Covenants 13
7.1 Compliance with Loan Agreement 13
7.2 Compliance with Project Administration Manual 14
7.3 Compliance with Contract 15
8 Environmental Monitoring Requirements 17
8.1 Environmental Monitoring 17
8.2 Environmental Monitoring Framework 17
8.3 Methodology for Environmental Monitoring in Construction Supervision 18
8.4 Contractor’s Environmental Monitoring Procedures 19
8.5 Consultant’s (PIC) Environmental Monitoring Work Protocol 19
8.6 Contractor’s Health and Safety Management and Monitoring 20
8.7 Institutional Arrangement, Capacity Building and Grievance Redress Mechanism 20
8.8 Compliance with Environmental Management Plan (EMP) 25
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN ii
8.9 EMP Implementation Schedule 31
9 Result of Environmental Monitoring and Compliance Measures 34
9.1 Environmental Safeguard Compliance 34
9.2 Training on Safeguards, Core labor Standards 34
9.3 Forthcoming EMP Actions 34
9.4 Key Environmental Issues and Related Action Plan 34
9.5 Conclusion and Recommendation 34
List of Tables Table 1. Project Components and Description of Design Plan of Project Road 6 Table 2. List of Work Packages of Project 7 Table 3. Present status of WP Contracts Signing 7 Table 4. Estimated Budget and Quoted Rate for EMP of the Lowest Bidders 8 Table 5. Loan Covenant related to Environmental Safeguard, ADB 13 Table 6. Compliance with Project Administration Manual 14 Table 7. Identified IECs of the Project Areas with types of Impacts and Duration 26 Table 8. Environmental Monitoring Plan 27 Table 9. EMP Implementation Schedule of SASEC Road Connectivity Project-2 32 Table 10. Environmental Management Plan for Elenga-Hatikamrul Road 36
List of Figures
Figure 1. Elenga- Hatikamrul-Rangpur Project Road ....................................................................... 3 Figure 2. Project Road from Elenga to Hatikamrul ........................................................................... 4 Figure 3. Project Road ends at Modern Bus Stop in Rangpur District ............................................. 5 Figure 4. Coordination Flow Chart .................................................................................................. 22 Figure 5. Flow chart of Grievance Redress Mechanism of the Project .......................................... 25
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN iii
Acronyms and Abbreviations
ADB Asian Development Bank DOE Department of Environment DC Deputy Commissioner EA Executing Agency ECA Environmental Conservation Act ECC Environmental Clearance Certificate ECR Environmental Conservation Rules EIA Environmental Impact Assessment EMP Environmental Management Plan EMP Environmental Monitoring Report GOB Government of Bangladesh GRC Grievances Redress Committee IECs Important Environmental Components IEE Initial Environmental Examination PIC Project Implementing Consultant ROU Road Operation Unit RRTC Road Research and Training Centre SASEC South Asian Sub-regional Economic Cooperation SES Socioeconomic Survey
Currency Equivalents
(As of 4 February’ 2019) Currency Unit – Bangladesh Taka (BDT)
BDT 1.00 = $0.0119164 $1.00 BDT 83.9179
Weights and Measures 1ha (Hectare) = 10000sq.m (square meter)
Or 2.47 Acre Or 247 Decimal
1 Acre = 100 Decimal 1 km (kilometer) = 1000 m (Meter)
1 Metric Ton = 1000 kg (kilogram)
NOTE In this report, "$" refers to US dollars.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN iv
1 Executive Summary
1. The Project, ADB Loan 3592/3593-BAN has, as its major component, SASEC Road
Connectivity Project-2, Improvement of ELENGA-HATIKAMRUL-RANGPUR Road to
a 4 Lane Highway. The project is deemed as Category B in ADB safeguard policy
2009, while in Bangladesh Environmental Conservation Rule 1997 categorized the
project as Red. The contracted work is being undertaken via “design Checking and
construction” arrangement with the Contractors of the eight Working Packages and
being supervised by the Project Implementation Consultant (PIC) or Engineer, (Korea
Consultants International Co., Ltd. (South Korea) with joint venture and in association
partners.
2. The scope of works includes detailed design, earthworks, pavement construction,
construction of new bridges and rehabilitation of old bridges, drainage, structures,
link/roadside improvements and installation of road furniture such as signs and safety
barriers. A total of 26 bridges and 161 culverts will be rehabilitated and/or
reconstructed. In addition, construction of three flyovers, 39 underpass, 68 bus bays,
11 pedestrian overpass etc. will be constructed.
3. Construction supervision by the Korea Consultants International Co., Ltd. (South
Korea) consortium is being undertaken under FIDIC the environmental supervision
and monitoring scopes. Environmental compliance of the Contractor’s civil works will
be monitored by the International Environmental Specialist with field coordination with
four National Environmental Specialists of the PIC.
4. Within the period each Contractor is obligated to perform the necessary measures to
mitigate environmental issues as part of his implementation activities. In addition,
instrumental measurements are to be done in accordance with agreed schedule and
locations in compliance with the EIA/EMP particularly the Environmental Monitoring
Plan of the Technical Specification of the Tender Document. The periodic
measurements of water quality, noise/vibration and air quality will be carried out for all
Work Packages. The results of these will be submitted regularly to the Engineer in
accordance with agreed schedule. The Engineer likewise, as part of his tasks, will
monitor the environmental aspects of the project and reviews the environmental
mitigating performance of the Contractors. The international and national
environmental specialists will monitor the environmental aspects of the project road
through site visits of the project roads and a number of facilities, reviewing
Contractors’ CEMP. Monthly Environmental Monitoring report prepared by the
contractors and approved, as well as follow up the contractors environmental
management compliances will be carried out during construction, operation and
maintenance activities.
5. All contractors will execute all civil works including EMP as per specification and
terms and conditions of the Contract.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN v
6. The number of grievances recorded, resolved and the outcomes are to be
displayed/disclosed in the PIU offices, as applicable and to be reported in the next
Semi-Annual Environmental Monitoring Report of the SASEC Road Connectivity
Project-2.
7. The international and national environmental specialists of the PIC will monitor the
environmental aspects through Environmental Monitoring Checklist of all project
activities. Based on the field visits, analysis would be done on compliance in lieu with
specific scope of on works as defined in the respective Contract Packages and
prevailing field condition.
8. This Semi-Annual Environmental Monitoring Report covers the period from January
2019 to June 2019 and presenting the environmental issues encountered in the
project. Construction works of SASEC Road Connectivity Project-2 is under
implementation at preliminary stage, since the commencement of all Contractor’s field
activities under eight Work Packages are not started, only four packages are being in
progress. Thus, the environmental monitoring yet to be started. The compliance
measures will be described in the upcoming Semi-Annual EMR based on the Actual
Observation of Monitoring Results.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 1
2 Introduction
2.1 Background of the Project
9. Improvement of 190.4 kilometres of ELENGA-HATIKAMRUL-RANGPUR Project Road
under the South Asian Sub-regional Economic Cooperation (SASEC) Road
Connectivity Project-2 is being financed by the Asian Development Bank (ADB). The
improvement of this project road to a 4 Lane Highway has been designed under the
framework of Regional Cooperation and Integration Project (RCIP) to develop Trans-
Asian Highway (TAH) connectivity with South Asian and many Asian countries. The
Government of Bangladesh is emphasizing on improved connectivity between each
part of the country. In line with this objective the GOB announced its National Land
Transport Policy in 2004 defining long term (20 years) Road Master Plan (RMP). The
RMP has identified many feasible and priority projects. One of priority roads identified
is the Elenga-Hatikamrul-Rangpur (HER) Highway. This road is a vital link in the
national highway network and forms a part of the Asian Highway Network
complementing the government plans to increase trade with neighbouring countries.
10. SASEC Road Connectivity Project-2: Improvement of 190.4 kilometres of ELENGA-
HATIKAMRUL-RANGPUR project road, is approved by the ECNEC on September 6,
2016. Implementation Period is from: September 2016 - August 2021. Feasibility study
and detailed design for this project was completed in 2015 with Technical Assistance
of ADB under Sub-regional Road Transport Project Preparatory Facility.
11. Contract was signed with Project Implementation Consultants (PIC), Korea
Consultants International Co., Ltd. (South Korea), in joint venture with Chodai Co. Ltd.
(Japan), H.P. Gauff Ingenieure GmbH & Co. KG-JBG (Germany), Lea Associates
South Asia Private Limited (India), SOOSUNG ENGINEERING CO. LTD. (South
Korea), in association with BCL Associates Limited (Bangladesh), BETS Consulting
Services Ltd. (Bangladesh), Development Technical Consultants Pvt. Ltd.
(Bangladesh), Philkoei International, Inc. (Philippines) on 25 October 2018. The PIC is
mobilized in January 2019. The project comprises eight road improvement packages
and one interchange construction package.
12. Under the project, a team of Consultants has mobilized on 27 January 2019 and
started working as Project Implementation Consultants (PIC) to provide professional
and expert support in design review of project roads, construction supervision, and
design of Hatikamrul Interchange, establishment of Road Operation Unit (ROU) and
Road Research and Training Centre (RRTC).
13. This report is prepared by the Project Implementation Consultants providing services
to the Roads and Highways Department (RHD) under the Asian Development Bank,
ADB Loan Project Loan; Project No.: 3592/3593-BAN). The loan is effective from 3
January 2018, L-3592/3593-BAN.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 2
2.2 Objectives of the Project
14. The Elenga-Hatikamrul-Rangpur Highway is an important part of SASEC Corridor,
Asian Highway, BIMSTEC Corridor & SAARC Highway Figure 1. The existing 2-lane
highway is inadequate for carrying passengers and goods between Dhaka and 16
northern districts of Bangladesh. Increasing the capacity of this highway is crucial for
sustainable development of the country. The road is two lanes with no shoulders and
no provision for slow moving vehicular traffic (SMVT) or non-motorized traffic (NMT).
There are capacity constraints caused by congested junctions, markets, and
community areas. Presence of several unsafe sharp bends and movement of slow-
moving traffic (like rickshaw, rickshaw-van, ‘Koriman’, ‘Nosiman’, etc.) on the same
lanes with heavy vehicles make the existing undivided 2-lane highway prone to risk of
frequent road accidents. Therefore, in order to enhance sub-regional connectivity,
increase passenger and cargo carrying capacity and to ensure road safety, a project
for upgrading the existing 190.4 kilometres road to a 4-lane highway with a provision
of separate SMVT lanes, flyovers at business junctions, and overpasses at some
intersections including ROU and RRTC has been undertaken. In addition the project
will bring national and sub-regional connectivity, accessibility to land ports, sea ports,
EPZs, EZs, tourism zones, promoting economic growth with reduction of poverty in the
country.
2.3 Purpose of the Report
15. This Semi-Annual Environmental Safeguard Monitoring Report covers the period
from January 2019 to June 2019, in compliance with the environmental scope of the
construction supervision. The upgrading of the project road will have its associated
environmental impacts that require due consideration in project design for its
mitigation and management, based on detailed Environmental Impact Assessment
(EIA)1. The EIA is carried out for the Elenga- Hatikamrul Road section to determine
the likely significant environmental changes due to the project’s associated activities
and formulated mitigation measures in the Environmental Management Plan (EMP) to
avoid, minimize, or compensate the identified adverse impacts during implementation
phases of the project.
16. The main purpose of this environmental monitoring is to ensure the implementation of
environmental mitigation measures of the EMP during the construction and
maintenance phases according to the Technical Specifications of the Bidding
Documents of all Work Packages. Also to comply the full requirement of the
Environmental Clearance Certificate (ECC) approved by the Department of
Environment) and ADB’s Safeguard Policy Statement, 2009 for timely completion of
the project as environmentally sound and sustainable.
1 EIA, Elenga–Hatikamrul Road. Subproject, Subregional Transport Project Preparatory Facility (SRTPPF)
Road Component: Package-1. Technical Assistance for SRTPPF March 2015, (ADB Loan 2688-BAN),
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 3
Figure 1. Elenga- Hatikamrul-Rangpur Project Road
2.4 Locations of the Project Roads
17. The EHR road passes through Tangail, Sirajganj, Bogra, Gaibandha and Rangpur
Districts. The Elenga-Hatikamrul road located north of Tangail District and starts at
Elenga Junction (N 24°20'22" and E 89°55'28") near the intersection of N4 and N405
and ends at 200m apart from Modern More of Rangpur city. The beginning of this road
joins the N4 and then follows the N405 at end of SASEC-I. At Chainage 83+081
the Bangabandhu Bridge started and at west side of this bridge Chainage is 90+700
of the project road. The road passes Hatikamrul (24°25'8.97"N and 89°33'6.97"E) of
Sirajganj district and then passes up to Rangpur district and Figure 2 and Figure 3
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 4
shows the project location. The road is a standard two-lanes highway (two 3.65m
lanes, paved shoulders each 1.5m and verges each 1.0m).The road condition is
varying in different section. Pavement crack is one the main problem for this road.
There are several sub-standard horizontal curves. Road passes through Bogra town
and several Upzila (sub-District) towns, market and developed areas like: Elenga,
Koddar moor, Hatikamrul, Sherpur, Mokamtola, Gobindoganj, Polashbari, Pirgonj,
Mithapukur, etc. The Length of the road is 190.4km and the average width of the
carriageway is 7.3m.
Figure 2. Project Road from Elenga to Hatikamrul
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 5
Figure 3. Project Road ends at Modern Bus Stop in Rangpur District
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 6
3 Technical Description of the Project Road
3.1 Scope of Works
18. The works include according to Employer’s Requirements in the Technical
Specifications2 of bidding document as follows.
• Site clearance and dismantling of obstructions, utilities, etc. before commencement
of work;
• Settling-out the Works;
• Demolition of exiting pavement, where necessary;
• Construction of new road embankment and pavement;
• Construction and maintenance of diversion roads/structures for maintaining
uninterrupted traffic flow;
• Supply and placing of road furniture;
• Construction of bridge/culverts and flyovers;
• Dismantling existing structures in whole or in part and reconstruction/rehabilitation of
structures in whole or in part;
• Protection utilities and services and adjoining property; and
• Maintenance of existing road.
3.2 Project Components and Design
19. Project comprises eight road improvement packages and one interchange
construction package. The scope of works includes detailed design, earthworks,
pavement construction, construction of new bridges and rehabilitation of old bridges,
drainage, structures, link/roadside improvements and installation of road furniture such
as signs and safety barriers. A total of 26 bridges and 161 culverts will be rehabilitated
and/or reconstructed. In addition, construction of three flyovers, 39 underpass, 68 bus
bays, pedestrian overpass etc. will be constructed under eight Working package and
Hatikamrul Intersection. The components of the project and design of the project are
presented in Table 1.
Table 1. Project Components and Description of Design Plan of Project Road Project Components
Description of Design
Main Carriageway 190.4 kilometres of existing 2-lane undivided road will be upgraded to 4-lane divided highway.
SMVT Separate lanes will be provided on both sides for Slow Moving Vehicular Traffic (SMVT
Interchange One (1500 meters) at Hatikamrul
Flyovers Three (3) flyovers, total 2635 meters
• Elenga: 1538.61 meters
• Kodda Moor: 395.64 meters
• Gobindoganj: 700.75 meters
Railway Overpass: 1 No, 411 meters
Bridge: 26 nos. total 1461.39 meters
Culvert: 161 nos. total 1102 meters
Underpass: 39 nos.
2 Biding document for ICB No. SASEC-II/ICB/MP-2/WP 08 (LOT 2) Volume 2 of 5, Scope of works (Section-6;
Employer’s Requirements (ERQ); Technical Specifications (Particular)
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 7
Foot Over bridge: 11 nos. total 397 meters
Land Acquisition 198.94 hectares
ROU
Road Operation Unit (ROU) for axle load control, road incident response and other road operational activities on the corridor.
RRTC
A Road Research and Training Center (RRTC) for Roads and Highways Department.
3.3 Construction and Maintenance Contracts
20. There are eight (8) road improvement packages under the project, each comprising
two phases as follows.
• Part 1- Construction Phase: 4-laning of existing 2-lane highway along with separate SMVT lanes and structures; and
• Part 2- Maintenance Phase: Performance-Based Maintenance of the road constructed in Part-1 for 6 years.
21. In addition, there is separate package for construction of Hatikamrul Interchange,
establishment of ROU and RRTC. The project comprises of eight Work Packages for
the civil works contracts. The list of Work Packages with lengths is presented in Table
2.
Table 2. List of Work Packages of Project Work Packages No. Road Sections Length (km)
WP-05 Elenga to East Side of Bangabandhu Bridge 13.6
WP-06: West Side of Bangabandhu Bridge to Hatikamrul 19.8
WP-07: Hatikamrul to Mirzapur 28.3
WP-08: Mirzapur to Banani (Bogra) 22.5
WP-09: Banani (Bogra) to Mokamtala 25.3
WP-10: Mokamtala to Polashbari 29.9
WP-11: Polashbari to Borodargah Bus Stand 27.2
WP-12: Borodargah Bus Stand to Rangpur 23.8
WP-13: Hatikamrul Interchange (1500 m) including ROU and RRTC
1.50
3.4 Present status of WP Contracts Signing
Table 3. Present status of WP Contracts Signing
Work Package Contract Status Summary Physical Activities
WP05 WP-05 is in process
to award
WP06 NTP issued on 2nd
April 2019
Established base camp, engineer’s facilities & BMs, setout
centre line, preparation of shop drawings for plan-profile,
commenced confirmatory sub-soil investigations.
WP07 NTP issued on 4th
March 2019
Established base camp, engineer’s facilities & BMs, setout
centre line, preparation of shop drawings for plan-profile,
commenced confirmatory sub-soil investigations.
WP08 NTP issued on 4th
March 2019
Established base camp, engineer’s facilities & BMs, setout
centre line, preparation for confirmatory sub-soil
investigations.
WP09 NTP issued on 4th Established base camp, engineer’s facilities & BMs, setout
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 8
March 2019 centre line, preparation for confirmatory sub-soil
investigations & shop drawings of plan-profile.
WP10 Contract Signed on
4th April 2019
Established of BMs is in progress.
WP11 Contract Signed on
4th April 2019
The PIC RE & Surveyor mobilized to site & the Contractor’s
personnel will be mobilized soon.
WP12 Contract Signed on
4th April 2019
Established of BMs is in progress.
Hatikamrul
Intersection
The PIC design team visited site & a conceptual design
presented in March ’19. The Topo & Traffic survey
completed & the data sent to design team (in Korea). The
preliminary design is in progress. The Design Team will
again visit the site and present design to the Client in late
May 2019.
RRTC & ROU The PIC team (Operation & Management Specialist and
Asset Management Specialist) visited site, meeting with the
Client & a conceptual business models presented in early
April ’19. The PIC team is now preparing the business model
of RRTC & ROU in corporating the feedback from the Client.
The Team will again visit the site and present business
model to the Client in late May 2019.
3.5 Project Cost, Estimates and Quoted Prize of WPs
22. The total cost during the implementation period to be BDT 1,189,901.21, of which BDT
254,404.80 will be bearded by the GoB and BDT 935,496.41 by the development
partner ADB. The loan agreement signed on 22 November 2017. The estimated
budget and lowest quoted Rate of the lowest Bidders of eight WPs for the EMP are
exhibited in Table 4.
23. The evaluated lowest Bidders quoted amount for the implementation of EMP are
found very poor and unrealistic. Three Bidders’ (WP5, WP8 and WP10) Rate amount
are less more than 90% of the estimated amount. Only quoted rate of WP6 is less
than 48% and the rest are less than 80% amount of the estimated amount.
Table 4. Estimated Budget and Quoted Rate for EMP of the Lowest Bidders
Work Packages Estimated Price Lowest Evaluated Bidder's Quoted Price
Quoted amount less than estimated amount (%)
WP5 12,350,000 200,000 98.38
WP6 13850000 7,150,000 48.38
WP7 18,900,000 2,000,000 89.42
WP8 18,900,000 1,500,000 92.06
WP9 18,900,000 2,000,000 89.42
WP10 12,350,000 1,146,043 90.72
WP11 13,385,000 1,904,499 85.77
WP12 12,350,000 1,371,721 88.89
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 9
24. It reveals that, the Bidders’ might be overlooked the environmental importance and
requirement of ADB safeguard policy and national environmental regulations. The
EMP is not a main item of the project, only supporting item. So, the individual rate for
single item is not considerable rather the total project cost, and the contractors quoted
their rate accordingly. But the contractors have quoted the rate of different items
individually keeping in mind that the whole works to be done properly.
25. The project is a mega project of the country and it is related to construction 190.4 km
roads with construction of major infrastructures like bridge, culverts, flyovers,
underpasses, buildings etc. In this circumstances, the contractors are to execute all
works including EMP accordingly to specification, terms and condition of the tender
agreements, whatever their quoted amount.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 10
4 Environmental Characteristics of the Project 26. Based on previous IEE/EIA studies of the project and the ADB Environmental
Safeguards Policy (2009), the project falls under environmental Category B3, meaning
– with limited impact to the existing environment and Red Category according to
Bangladesh Environmental Conservation Rule (ECR), 1997. As part of the
requirements as per the GOB /ADB guidelines, the EIA document was produced for
the project, which served as the guidelines for the environmental management and
monitoring during construction period. Technically, the EIA provides guidance to the
environmental measures needed to prevent and/or mitigate negative environmental
effects associated with the project implementation, as well as provides a detailed
description of the direct and indirect environmental effects during conducting of the
construction.
27. Due to existing road with settlement, the area near the project road has limited flora
and much of the trees and vegetation on slopes and ROW has been depleted as the
trees were cut down and used as fuel. The fauna along the project road is rather low,
aside from the commonly existing species in the country and no important, rare,
endangered, or protected bird species or habitats are found within the Project Corridor
and according to EIA.
3 ADB’s Safe Guard Category – Category B The proposed project’s potential adverse environmental impacts are site-
specific, few if any of them are irreversible, and in most cases mitigation measures can be designed more readily than for category A projects. An initial environmental examination (IEE), including an EMP, is required.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 11
5 Environmental Monitoring Relationships with Contractors, Owner and
Lender 28. The Owner or Employer of the project is the Ministry of Road Transport and Bridges.
The Lender is the Asian Development Bank providing financial assistance to the
Owner in constructing this road project. The KCI with joint venture partners is the PIC
or the Engineer acts as the Owner’s/Employers representative that supervises the
Contractors in the entire road project.
29. Out of 190.4 kilometres of HER project Road, 157 km is owned by RHD and the rest
33.4 km is owned by Bangladesh Bridge Authority4. The road section from Elenga-
Hatikamrul 33.4 km serves as the approach road of Bangabandhu Bridge and
managed by the Bangladesh Bridge Authority (BBA). After the completion of civil
works for upgrading the section, BBA will be responsible for environmental monitoring
during the operation and maintenance of Elenga-Hatikamural section, while the rest of
project roads by RHD.
30. In terms of the environmental management and monitoring, the appointed Contractors
of all work Packages are responsible in enforcing the Contractor’s Construction
Environmental Management Plan (CEMP) among his sub-contractors and suppliers.
Any environmental instructions regarding the project are first communicated to the
main Contractor to be relayed for compliance to the sub-contractors. The Contractor of
each working package is the overall responsible for compliance in the project.
4 The Aid Memoire 09-12 November 2015 (DPP, page 233-234)
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 12
6 Project Status and ongoing Activities of Work Packages 31. CEMP of WP 6, 7, 8 & 9 were submitted to PIC. Environment team has reviewed
those CEMP and with their comments send back to them. The overall physical
progress of the project in minimum, since all contractors of eight Work Package are
yet to be mobilized in the field.
32. Draft IEE of Road Research and Training Centre (RRTC) was prepared by PIC.
33. Draft IEE of Hatikamrul Interchange was prepared by PIC.
34. All the contractors will be submitted their monthly Compliance Monitoring Report after
the engagement of their Environment Management Officer (EMO)/Environmental
Specialist (ES) based on implementing the Environmental Management on their
specific Construction Sites during the Total Contract Period.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 13
7 Compliance with Environmental Related Project Covenants
7.1 Compliance with Loan Agreement
35. The project specific covenants related to Environmental Safeguard as presented in
loan agreements is shown in Table 5.
Table 5. Loan Covenant related to Environmental Safeguard, ADB
Sche
dule
Para
No. Description
Status of
Compliance
5 4 Environment. The Borrower shall cause the Project Executing Agency to (a) ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with (i) all applicable laws and regulations of the Borrower relating to environment, health and safety; (ii) the Environmental Safeguards; and (iii) all measures and requirements set forth in the IEE, the EMP, and (iv) any corrective or preventative actions set forth in a Safeguards Monitoring Report and (b).ensure, or cause the project executing agencies to ensure, that works do not comments until and unless environmental clearance, satisfactory in form and contain to ADB, in respect of the relevant site has been received from the department of Environment.
EIA including EMP was submitted to Department of Environment in 2014. Environmental Clearance for the project was obtained from Department of Environment on 15 July 2014 whereas, the construction commenced in January 2018
5 9 The Borrower shall ensure or cause the Project Executing Agencies to ensure that all bidding documents and contracts for Works contain provisions that require contractors to:
EMP has been made a part of bidding document and accordingly is a part of contract agreement. Necessary budgetary provision has been made in the Bill of Quantities of the civil work contract for environmental management by the contractor.
(a) comply with the measures and requirements relevant to the contractor set forth in the IEE/EIA, the EMP, the RPs (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set forth in the Safeguards Monitoring Report;
(b) make available a budget for all such environmental and social measures;
(c) provide the Project Executing Agency with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE/ EIA, the EMP, and the RP
(d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and
(e) Reinstate pathways, other local infrastructure, and agricultural land to at least their pre-Project condition upon the completion of construction.
5 10 Safeguards Monitoring and Reporting: The Borrower shall cause the Project Executing Agency to do the following:
Semi-annual Environmental monitoring report for January to June
(a) submit-annual annual Environmental monitoring report in accordance with the requirement of the SPS for category
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 14
Sche
dule
Para
No. Description
Status of
Compliance
“B” projects, and semiannual Safeguards Monitoring Reports in respect of the social impacts of the project, to ADB and disclose relevant information from such reports to affected people promptly upon submission;
2018 has been submitted. Social monitoring report January to June 2018 was also submitted (b) if any unanticipated environmental and/or social risks and
impacts arise during construction, implementation or operation of the Project that were not considered in the IEEs, the EMPs, and the RPs, promptly inform ADB of the occurrence of such risks or impacts, with a detailed description of the event and proposed corrective action plan; and
(c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMPs, or the RPs promptly after becoming aware of the breach.
7.2 Compliance with Project Administration Manual
36. The project specific covenants related to Environmental Safeguard in connection with
Project Administrative Manual is shown in Table 6.
Table 6. Compliance with Project Administration Manual
Clause Provision Compliance
35 (a) Environment: The project has been categorized as environment category “A”. Therefore separate IEE and EIA reports including EMPs have been prepared for the project components. The EMP for each project component will be updated and made more site specific during the detailed design works and attached to the respective contract documents. The responsibilities of respective parties and agencies on implementing the environmental safeguards are given below:
1) PIU, RHD: Ensure that all environment safeguard requirements as stated in the IEE and EIA and loan covenants for the RHD building and the Elenga Hatikamrul Rangpur Road are complied with. Submission of annual environmental monitoring reports for each subproject to ADB for disclosure on the ADB website.
Complied
2) PIU, BLPA: Ensure that all environment safeguard requirements as stated in the IEE and EIA and loan covenants for the land ports are complied with. Submission of annual environmental monitoring reports to ADB for disclosure on the ADB website.
Complied
3) Social and Environment Circle, RHD: Implementation and monitoring of the requirements of the IEE, EIA including EMP for the HER road and RHD building. Preparation of semi-annual environmental monitoring reports for each of the sub projects based on the periodic monitoring reports prepared at the site level by the PIC.
Ongoing
4) Safeguards Focal Persons, BLPA: Implementation and Ongoing
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 15
Clause Provision Compliance
monitoring of the requirements of the EIA and EMP for the RHD building and HER road. Preparation of annual environmental monitoring reports for each of the sub projects and submission to ADB and disclosure on the ADB website. Preparation of semi-annual environmental monitoring reports based on the periodic monitoring reports prepared at the site level by the PIC.
5) Environmental Focal Person, Project site, RHD/BLPA: Day to day monitoring of site level implementation of the EMP. Review and approval of weekly/monthly environmental monitoring checklists or reports.
Ongoing
6) Environmental Specialist, PIC: Periodic site level monitoring, provision of technical advice, on the job training etc. to the contractor to enable smooth implementation of the EMP. Updating the EMP as necessary together and in consultation with the contractor. Preparation of monitoring checklists/reporting formats to be completed on a weekly/monthly basis. Submit the completed checklists/reports to the environmental focal person from RHD/BLPA at the site level. Provide necessary technical support to the environmental focal person at the site level as well as the department level for RHD and BLPA.
Ongoing
7) Contractor: Implementation of the EMP. Updating of the EMP when necessary together with and in consultation with the PIC Environmental Specialist.
Updating of EMP is in progress addressing additional scope of work
36 An initial coordination cum training workshop carried out during the pre- construction stage for the RHD staff, BLPA staff, PIUs, PIC and contractors.
Complied
7.3 Compliance with Contract
37. According to scope of works5, Employer’s Requirements; Technical Specifications the
Contractor shall take all reasonable steps to protect the environment (both on and off
the Site) and to limit damage and nuisance to people and property resulting from
pollution, noise, vibration and other results of his operations. The Contractor shall
ensure that emissions, surface discharges and effluent from the Contractor’s activities
shall not exceed the values stated in the Specification or prescribed by Applicable
Laws.
38. The Contractor shall comply with all applicable national environmental laws and
regulations. The Contractor shall (a) establish an operational system for managing
environmental impacts, (b) carry out all of the monitoring and mitigation measures set
forth in the Environmental Impact Assessment (EIA) and the Environmental
5 Biding document for ICB No. SASEC-II/ICB/MP-2/WP 08 (LOT 2) Volume 2 of 5, Scope of works (Section-6;
Employer’s Requirements; Technical Specifications -
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 16
Management Plan (“EMP’) attached in Tender Documents, Section 6: Employer’s
Requirements, (ERQ) and (c) allocate the budget required to ensure that such
measures are carried out. More particularly, the Contractor shall comply with (i) the
measures and requirements set forth in the EIA and the EMP; and (ii) any corrective
or preventative actions set out in safeguards monitoring reports. The Contractor shall
also comply with all reasonable requests of the national and local authorities
responsible for enforcing environmental controls. The Contractor shall confine his
work within the limits of the Site to the maximum practicable extent and avoid undue
interference with existing lands use adjacent to the Site. Within 28 days of the
Commencement Date the Contractor shall submit a detailed Construction
Environmental Management Plan (CEMP) or Site Specific Environmental
Management Plan (SSEMP) based on the EMP of the EIA for the Engineer’s approval
showing how he intends to comply with environmental laws and regulations and other
specific environmental requirements prescribed in the Contract. Work shall not
commence on the Site until the plan has been accepted by the PIC/Engineer and is
being implemented.
39. The contractors will comply the Environmental Management Plan with environmental
laws and regulations and other specific environmental requirements prescribed in the
Contract during construction and maintenance period. The Contractor shall submit
monthly and quarterly Environmental Monitoring and Management reports to the PIC
and Employer, which are duly followed up by the Engineer, PIC.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 17
8 Environmental Monitoring Requirements
8.1 Environmental Monitoring
40. Environmental monitoring is an essential tool for environmental management as it
provides the basic information for rational management decisions. The purpose of the
monitoring program is to ensure that the envisaged purposes of the project are
achieved and result in desired benefits to the target population. To ensure the
effective implementation of the mitigation measures, it is essential that an effective
monitoring program be designed and carried out. Compliance monitoring will be
conducted in accordance with the Environmental Management Plan (EMP) provided in
the EIA report.
8.2 Environmental Monitoring Framework
41. The environmental monitoring framework for the project is based on the construction
supervision ToR, GCC/PCC, Technical specifications, project ECC requirement for the
project and ADB guidelines. The Technical Specification Indicates the clauses are as
follows to be complied by the contractors
42. Division 1: General and site facilities6
Part-1 Construction Phase Work Specification 1.7 Health and Safety 1.8 Safety Relating to Temporary Structures 1.9 Safety Relating to Navigable Water Ways 1.10 Environmental Management 1.10.2 Compliance with Environmental Laws and Regulations 1.10.3 Avoidance of nuisance 1.10.4 Air Quality 1.10.5 Monitoring of Dust (TSP) Levels 1.10.6 Action on Construction Dust (TSP) Levels 1.10.7 Water Quality Management 1.10.8 Water Quality Monitoring (Measured parameters shall include, Suspended Solids (SS), Biological oxygen demand (BOD), Dissolved oxygen (DO), Fecal coliform and Oil and grease levels) 1.10.9 Noise and Vibration Control
1.10.10 Noise Monitoring and Control 1.10.11 Vibration Monitoring and Control 1.10.11.2 Permitted Vibration Level: Location Peak Particle Velocity 1.10.11.12 Reduction of Construction Operation Impacts 1.10.11.13 Environmental Management System 1.10.11.14 Environmental Management Officer (EMO) 1.10.11.15 EMO’s Lines of Communications 1.10.11.16 Environmental Report
1.10.11.17 Environmental Management Meetings, etc.
6 Biding document for ICB No. SASEC-II/ICB/MP-2/WP 08 (LOT 2) Volume 2 of 5, Section 6: General and
Site Facilities, Bidding Document
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 18
Part-2 Maintenance Phase Work Specification 7.2 Compliance with Environmental Laws and Regulations 7.3 Avoidance of nuisance 7.4 Air Quality 7.5 Water Quality Management 7.6 Noise and Vibration Control 7.7 Vibration Monitoring and Control 7.1.1 General 7.7.2 Permitted Vibration Level 7.7.3 Vibration Monitoring 7.8 Environmental Management Plan 7.9 Environmental Report 7.10 Breaches Environmental Management Plan 7.11 Environmental Management Meeting 7.12 Environmental Inspections 7.13 Assistance to the Engineer and Employer
43. The contractor must act in accordance with Environmental Management Plan (EMP),
which has been prepared for this project and included as the Employer’s
Requirements (ERQ). The Contractor shall be solely responsible for any remedial or
mitigation measures and precautions to avoid any nuisance or disturbance arising
from the execution of project activities.
8.3 Methodology for Environmental Monitoring in Construction Supervision
44. As stipulated in the Contract for the project, the Contractor would adhere to the
requirements of the environmental aspects of the contract document particularly in the
General Conditions of Contract (FIDIC) clauses as follows:
4.8 – Safety Procedure 4.18 – Protection of Environment 4.15 – Access Route 4.24 – Fossils 6.7 – Health & Safety
45. In addition, detailed requirements are presented in the General Specifications for
Protection of Environment particularly, General, Borrow Pits for Embankment
Construction, Quarry Operations, Control of Soil Erosion, Sedimentation and Water
Pollution, Pollution from Hot-Mix Plants and Batching Plants, Substances Hazardous
to Health, Use of Nuclear Gauges, Care during Execution of Works and Environmental
Monitoring.
46. The Health and safety incudes Safety Equipment, Health Measures, Health and
Safety Unit, Site Induction, Cooperation with Health Authorities and Other Health and
Safety Measures.
47. Arrangement for Traffic during construction includes passage of traffic along a part of
the Existing Carriageway under Improvement, passage of traffic along a temporary
diversion, traffic safety and control, maintenance of diversions, etc.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 19
48. The contractors will implement own Site Specific Environmental Management Plan
(SSEMP) or CEMP as appended in recommendation of EIA to form part of the
contractual requirements
“The Contractor shall prepare a SSEMP to meet the requirements of this EMP. Specifically the SSEMP shall contain sections relating to:
• Management of Physical Environment - Soils - Water - Air
• Management of Ecological Environmental - Flora - Fauna - Protected Areas
• Management of Economic Characteristics - Infrastructure - Transport - Land Use - Agriculture
• Management of Social and Cultural Resources - Communities, Health and Education Facilities - Historical and Cultural Areas - Noise
49. In addition, the SSEMP shall contain specific Environmental Management Plans as
Table 10 relating to the following:
• Borrow Pit Management Plan
• Air Quality Management Plan
• Water Quality Management Plan
• Noise Management Plan
• Waste Management Plan
• Emergency Response Plan
• Dust Suppression Plan
• Site Plan
• Health and Safety Plan”
50. Each section shall describe the precise location of the required mitigation / monitoring,
the persons responsible for the mitigation / monitoring, the schedule and reporting
methodology. The SSEMP/ CEMP must be submitted within 28 days of the contract
award and construction cannot commence until the SSEMPs are approved by the
Engineer.
8.4 Contractor’s Environmental Monitoring Procedures
51. In accordance with the EIA, and the accompanying Environmental Monitoring Plan
(EMP), the Contractor is required to undertake parametric measurements and
observations on air quality, water quality, noise and socio-cultural resources.
Locations for the measurements were initially identified in the EIA.
8.5 Consultant’s (PIC) Environmental Monitoring Work Protocol
52. Under the guidance of the International Environment Specialist, the Contractor
initiated environmental monitoring which involved measurements of parameters in
water quality, air quality, noise, and socio cultural resources. Findings and results of
the Contractor’s monitoring activities are incorporated in the monthly and quarterly
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 20
reports which were submitted to the Engineer. This work is also being verified by the
local environmental specialist who goes to the site on periodic basis to perform his
own environmental monitoring.
8.6 Contractor’s Health and Safety Management and Monitoring
53. As provided in Clause on Health and Safety of the General Specifications the
Contractor has the following responsibilities:
▪ To ensure that all Subcontractors and their personnel participate fully in the actions prescribed in this Clause for the health and safety of the workers.
▪ To provide, and ensure the utilization of, appropriate safety equipment for all Contractors’ Personnel
▪ To take all reasonable precautions to prevent unauthorized entry to the Site and to protect members of the public from any activity under his control.
▪ To notify the Engineer immediately of any unsafe incidents or accidents which result in death, serious bodily injury or are likely to lead to incapacity to persons for more than three days
▪ To take all measures necessary to safeguard the health, including Sexually Transmitted Infection (STI) and HIV/AIDS, safety and welfare of Contractor’s Personnel and workers, maintain records concerning accidents including identified STI and HIV/AIDS persons at the site
▪ To establish a Health and Safety Unit, and shall appoint responsible members to act full-time as Safety Officer
▪ To have regular meetings, at least monthly, with local health authorities/facilities, workers and project personnel.
▪ To provide adequate lighting (including sufficient back-up facilities in the event of failure) wherever any work is to be carried out at night to ensure that the Works can be carried out safely.
▪ To provide an adequate number of latrines and other sanitary arrangements at areas of the Site where work is in progress.
▪ To ensure that the Works are left in a safe condition, in the event that the Contractor temporarily closes down site operations seasonally or for any other reason.
54. As stated above, in case of accident, the Contractor is to be submitted brief summary
about the accidents as part of the monitoring activities for the previous month.
8.7 Institutional Arrangement, Capacity Building and Grievance Redress
Mechanism
55. Institutional Arrangement: The Environmental Management Plan (EMP)
implementation requires an organization support structure in the form of organizational
requirements, training needs and plan, and information management system. Different
departments will be involved during implementation of the project. Contractor is
responsible for implementation of EMP during works and Construction Supervision
Consultant is primarily responsible for supervision of monitoring of the implementation
of the EMP. RHD will be supported by the Engineer for advising and assisting RHD in
quality and capacity enhancement and independent quality monitoring. Contractor will
be responsible for implementation of EMP during work activities stage. Relevant
departments responsible for implementation and supervision of proposed mitigation
and monitoring measures are given in the EMP.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 21
56. Within the monitoring period, the Engineer’s environmental specialists (international
and national), especially after their deployment, will carry out the tasks of
environmental monitoring and management for the construction phase generally
based on the Consultant’s original Terms of Reference as guidelines, such as (i)
Incorporate EMP provisions into the regular inspection documentation prepared for the
supervision team; (ii) Provide advice and support, on site and in the Executing Agency
office for the EMP compliance; (iii) Periodically review monitoring reports and identify
any adaptations or improvements necessary in order to ensure that the EMP is being
properly implemented; (iv) preparation of monthly environmental progress reports for
the initial 3 years, and Semi-Annual Environmental Monitoring Report (v) In the final
stages of construction, review the EMP monitoring provisions and establish the
monitoring system for the operational phase of the project; and (vi) Assist with the
production of manuals, booklets, brochures and pamphlets for public awareness
related to the environmental management.
57. Since very few project’s construction works are on-going and the international and
national environmental specialists are not mobilized in IPC team. For actual follow
through, the international environmental specialist will coordinate with the CS Project
Director/ who in turn corresponds formally to the Contractor’s Project Manager.
Instructions will be issued to the Contractor’s Environmental Officer and Health &
Safety Officer for appropriate action. During field audit, international and national
environmental specialists will conducts joint inspections with the Contractor’s
Environmental Officer and Health & Safety Office. Communication between the Client,
Contractors and Consultants (PIC) shall be established according to the following
coordination Flow Chart.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 22
Figure 4. Coordination Flow Chart
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 23
58. Capacity Building: In Bangladesh, the environmental assessment process is
established, but environmental awareness and capability for implementation of EMP in
infrastructure projects are still developing. The RHD has some officers in the Social
and Environmental Circle (SEC) they are delegated on environmental and
resettlement issues of the projects. The delegated officers have responsibility to bring
environmental issues to the notice of senior management. Typically, the delegated
officers have been moved to different departments due to promotions and operational
needs after about every three (3) years, and they move on to other engineering
departments in RHD. Thus, Social and Environmental Circle (SEC) of RHD is not
directly involved with this SASEC-II project implementation, but has more
administrative responsibility to ensure environmental compliance, to check
environmental assessments documents prepared by consultants and has a general
role to increase environmental awareness for RHD management. In the PIC,
international and four national Environmentalists being working and they are
delegated to monitor environmental monitoring and ensure compliance of the EMP.
For the capacity building, some trainings regarding the environmental management of
the project are essential for the concern officers/ professional of the project
implementation unit (PIU) and SEC of RHD. The following trainings are essential to be
conducted in national level as well as international level:
• Environmental Management Plan (EMP)
• Environmental Planning & Implementation
• National and Legal Environmental laws
• Environmental and Social Safeguards Operation Guidelines of ADB, WB, JICA etc.
and basic difference among them
• Environmental Monitoring & Modelling
• Environmental Health, Logistic & Safety
• Land acquisition, Resettlement Policy & Practices
• NOC process of DoE and importance
59. The training course duration, methodology, tools and context will be international
standard and based on the respective institutional curriculums.
60. Grievance Redress Mechanism: To facilitate the resolution of affected people’s
concerns, complaints, and grievances about the social and environmental
performance of the project, a Grievance Redress Mechanism (GRM) will be
established in PIU through formation of a Grievance Redress Committee (GRC),
which aims to provide a time bound and transparent mechanism to voice and resolve
social and environmental concerns. The Social and Environmental Circle (SEC) of
RHD may involve to make the public aware of the GRM through public awareness
campaigns. The project information brochure will include information on the GRM and
shall be widely disseminated throughout the project area by the Environmental
Specialist/Engineer with support by the RP Implementing NGO.
61. For this project, the GRC will be organized within the Tangail, Sirajganj, Bogra,
Gaibandha and Rangpur administrative areas. Prior to start of construction, BR
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 24
representative will meet with UNO or Upazila Chairman along with the local
Mayor/Chairman to request each to nominate committee member, who could form part
of GRC and meet when the complaint are received. The GRC will be two tier as Local
level and Project level as follows;
Local Level Project Level
• Project Manager, CRG Chair
• Deputy Project Manager
• Upzila Parishad Chainman or Senior Representative of District, GRC Committee member
• Female member of concerned wards, Committee member
• Environmental Monitoring Officer, Contractors
• Project Director, CRG Chair
• Deputy Project Director, GRC Committee member
• APD, GRC Committee member
• Team Leader of PIC, GRC
Committee member
• Representative of Department of
Environment (DoE) Committee
member
62. In order to function effectively, the GRC will have five permanent members, with the
DoE representative replacing the local NGO for purely environmental issues and a
female representing the affected people. In order to convene a GRC meeting a
quorum of three people will be required. Further, the GRC would only be convinced if
direct communication between the contractor, the complainant and the engineer
cannot solve the issue quickly. Once the complaint reaches the GRC, then the GRC
has two weeks to render a decision, based on discussion with both parties involved.
The GRC will be used as the third step when filling a complaint. The following are
steps for GRM of the project.
Step 1- The complaints will be advised to first attempt to settle the complaints through direct communication with the person or by a phone, and call to the local BR office. If the discussion with the complaint/ community is successful, the contractor will be responsible for undertaking corrective measures as defined in the grievance decision and recording decision and filing that with BR, via the Engineer/contractor or the BR. Step 2- Should the complaint not be addressed within a week; the next level is to notify the Upazila office and BR of the under solved issue. The Upazila official will then communicate either to the contractor or BR and solution will be discussed with the complaint within one working week. If more time is required, the Upazila or BR should directly communicate directly with the complaint describing the reason of the delay. Step 3- If step 2 fail to resolve the issue within two weeks of the receipt of the complaint the GRC should be formed and a formal hearing undertaken. At this point, a decision must be rendered within two weeks or the complaint concerned will be deemed correct and immediate and mitigate action will be required and fully executed within five days of the end of the two week period. Step 4- If step 3 fails to resolve the issue, the complaint may proceed to legal arbitration. The verdict of the judiciary will be final. In case communities and individuals who believe that they are adversely affected by project interventions may submit complaints to existing project-level GRM. This procedure and monitoring report will be reported to ADB in quarterly basis.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 25
Figure 5. Flow chart of Grievance Redress Mechanism of the Project
8.8 Compliance with Environmental Management Plan (EMP)
63. On the basis of identification the environmental impacts and recommended mitigation
measures linked with the EHR project activities, an EMP has been prepared in the
EIA, which will be followed at the pre-construction, construction and operation stages.
While preparing the EMP, medium and significant impacts are taken into consideration
to recommend possible mitigation measures. A mitigation measure will be considered
as successful when it complies with the Environmental Quality Standards (EQS),
policies, legal requirements set by ADB SPS, 2009 and DoE environmental guidelines
and other relevant GoB legal requirements. In absence of DoE’s own EQS, other
relevant international or other recognized organization’s quality standard will be
applied. In the EIA study, an Environmental Monitoring Plan (EMoP) are prepared to
be followed during implantation phases of the Project based on identified Important
Environmental Components (IECs) with types of impacts and duration in Table 7.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 26
Table 7. Identified IECs of the Project Areas with types of Impacts and Duration Project Phase
Activity Environmental Components
Important Types of Impacts
Significances of Impact
Duration Of Impact
Pre- Construction Phase
Climate Change Adverse, Direct Low Long term Loss of Trees Adverse, Direct Low Medium term Land Acquisition Adverse, Direct Localized, Low Short term Loss of Structure Adverse, Direct Low Long term Educational, Cultural, Religious/Historical sites
Adverse, Direct
Localized, Low
Short term
Public Utility Adverse, Direct Localized, Low Short term Construction Phase
Hydrology Adverse, Direct Minor, Reversible
Short term
Drainage and Flood Adverse, Direct Minor, Reversible
Short term
Soil Erosion and Siltation Adverse, Direct Localized, Reversible
Short term
Soil Contamination Adverse, Direct Minor, Reversible
Short term
Noise Adverse, Direct Localized, Reversible
Short term
Air Adverse, Direct Localized, Reversible
Short term
Groundwater Minor Low Short term Surface Water Adverse, Direct Localized,
Reversible Medium term
Waste Pollution Adverse, Direct Localized, Reversible
Short term
Dredging Adverse, Indirect Localized, Low Short term Flora Adverse, Indirect Moderate,
Reversible Medium term
Wild Life Adverse, Direct Localized, Reversible
Short term
Fisheries Adverse, Direct Localized, High Short term Traffic Congestion Adverse, Direct Moderate,
Reversible Short term
Income and Employment Beneficial, Direct Localized, Moderate
Short term
Cultural and Religious Sites Adverse, Direct Localized, Reversible
Short term
Educational Institutions, Health Facilities
Adverse, Direct Localized, Reversible
Short term
Occupational Health & Safety
Adverse, Direct Minor, Reversible
Short term
Operation Phase
Soil Erosion and Quality Adverse, Direct Localized Short term Flora Positive, Direct Localized Long term Noise Adverse, Direct Localized Persistent Air Adverse, Direct Localized Persistent Water Quality Adverse, Direct Minor,
Reversible Persistent
64. Environmental monitoring of the Contractors activities will be conducted by the
national and International Environmental Specialists regularly with the representative
of the Contractor. The output of the monitoring will be compiled and reflected in the
Checklist. This Checklist will serves as the basis of the Contractor’s final
environmental safeguard compliance for the project.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 27
Table 8. Environmental Monitoring Plan Environmental Components
Parameters/ Units Standards/ Guidelines
Location Monitoring Period Frequency/Sampling, No/ year
Responsibilities
Implementation Supervision
PRE-CONSTRUCTION STAGE Dredged materials Test parameters: Lead (Pb),
Cadmium (Cd), Chromium (Cr), Copper (Cu), Zinc (Zn), Manganese (Mn), Arsenic (As), Selenium (Se), and Mercury (Hg)
Government of Bangladesh (GoB) and international standard
Proposed dredging sites Once prior to start dredging
Contractor RHD/Construction Supervision Consultant (CSC)
Air Quality Test parameters: H2S, SOx, NOx, CO, CO2, TVOC, SPM, PM10
Air quality standard by DOE, Bangladesh
Major road intersections Once Contractor RHD/CSC
Noise Level Test parameters: dB(A) Noise Pollution Control Rules (2006)
Major Road Intersections and inhabited locations and sensitive areas
Once Contractor RHD/CSC
Water Quality Test parameters: Surface water pH, TDS, EC, TSS, Fe, NH3 – N, Cl2, DO, COD, BOD5,
Surface water quality standard by DOE, Bangladesh
Surface water near project site
Once Contractor RHD/CSC
Test parameters: Groundwater: pH, Mn, As, Fe, Cl-, Total hardness, TC, FC
Groundwater quality
standard by DOE, Bangladesh
Groundwater near project site
Once Contractor RHD/CSC
Wildlife Wildlife habitat and movement None Specific Areas alongside the road alignment
Once Contractor RHD/CSC
Tree felling Monitoring activities outlined in RP; Check whether proper compensation as mentioned in RP is received by PAPs.
Inspection ROW along the alignment During tree felling and site clearing operations
Contractor/ NGOs/RHD
RHD/CSC
CONSTRUCTION STAGE Air Quality Test parameters: H2S, SOx,
NOx, CO, CO2, TVOC, SPM, PM10
Air quality standard by DOE, Bangladesh
Hot mix plant, concrete mixing plant/stone crushers at construction sites
2/year per site for 2 years
Contractor RHD\CSC
Dust Dust control Air quality standard by DOE,
Construction site and ROW along the alignment
Regularly Contractor RHD\CSC
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 28
Environmental Components
Parameters/ Units Standards/ Guidelines
Location Monitoring Period Frequency/Sampling, No/ year
Responsibilities
Implementation Supervision
Bangladesh
Noise Level dB(A) Noise Pollution Control Rules (2006)
Construction sites and inhabited locations and sensitive areas
2/year per site for 2 years
Contractor RHD\CSC
Water Quality Test parameters Surface water: pH, TDS, EC, TSS, Fe, NH3 –
N, Cl2, DO, COD, BOD5, Oil &
Greases
Water quality standard by MoEF, Bangladesh
Surface water near project site
2/year per site for 2 years
Contractor RHD\CSC
Test parameters: Groundwater:
pH, Mn, As, Fe, Cl-, Total
hardness, TC, FC
Water quality standard by MoEF, Bangladesh
Drinking water to made available to construction camps and ground water near project site
2/year per site for 2 years
Contractor RHD\CSC
Soil Erosion Visual check for Soil erosion and siltation
None Specific All major water bodies Once during rainy seasons of the construction period.
Contractor RHD\CSC
Drainage congestion
▪ Check drainage plan implemented correctly ▪ Conduct regular inspection
Monitoring Construction site
Weekly during monsoon
Contractor RHD\CSC
Soil Pollution ▪ Check liquid waste is carried out by experienced personnel and in proper way ▪ Careful and proper handling of oil and other hazardous liquids
Monitoring Construction Yard, dumping site
Regularly Contractor RHD\CSC
Wildlife Wildlife habitat and movement None Specific Areas alongside the road alignment
Quarterly Contractor RHD\CSC
Fisheries Impact on fish productivity, breeding and spawning
None Specific
All major water bodies
Once in a year Contractor RHD\CSC
Waste
▪ Check storage, transportation, disposal, handling of hazarders waste
Monitoring Construction Yard, dumping site
Weekly Contractor RHD\CSC
▪ Waste and effluents to be collected and disposed safely from all camps. ▪ Wastes and garbage from bridges construction sites to be disposed safely
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 29
Environmental Components
Parameters/ Units Standards/ Guidelines
Location Monitoring Period Frequency/Sampling, No/ year
Responsibilities
Implementation Supervision
Health and Safety ▪ Check quality of food & accommodation at construction camp; ▪ Check safe water supply, hygienic toilet at camps, construction of drain at camp sites;
▪ Check toilets are close to construction site and separate toilet for female workers; ▪ First Aid Box with required tools & medicines; ▪ The heavy construction material to handled and stored safely putting due care on public safety; ▪ Heavy construction materials at bridges construction sites to be stored and handled safely; and ▪ Check of personal protective equipment (PPE) for worker at the sites
Monitoring Construction site and labor camp
Regularly Contractor RHD\CSC
Operation Stage
Tree Plantation
Check that the planted trees are maintained as mentioned in tree plantation plan
Inspection to ensure proper plantation with proper species
Along the road Regular during June/July
RHD RHD\DOE
Air Quality
Test parameters: H2S, SOx,
NOx, CO, CO2, TVOC, SPM,
PM10
Air quality standard by DOE, Bangladesh
Major Road Intersections
1site/year for 3 years RHD RHD\DOE
Noise Level dB(A) Noise Pollution Control Rules (2006)
Major Road Intersections and inhabited locations and sensitive areas
1site/year for 3 years RHD RHD\DOE
Water Quality Test parameters Surface water: Water quality Surface water near project 1site/year for 3 years RHD RHD\DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 30
Environmental Components
Parameters/ Units Standards/ Guidelines
Location Monitoring Period Frequency/Sampling, No/ year
Responsibilities
Implementation Supervision
pH, TDS, EC, TSS, Fe, NH3 –
N, Cl2, DO, COD, BOD5, Oil &
Greases
standard by MoEF, Bangladesh
site
Test parameters: Groundwater:
pH, Mn, As, Fe, Cl-, Total
hardness, TC, FC
Water quality standard by MoEF, Bangladesh
Groundwater near project site
1site/year for 3 years RHD RHD\DOE
Accident and Public Safety
Record of accidents, different level of disabilities/fatalities.
None Specific
Thought out the project section
---------- RHD RHD
Soil Erosion
Visual check for soil erosion and siltation
None Specific
All major water bodies
After first precipitation
RHD RHD
Soil Quality Heavy metals None Specific At each construction camp post restoration of construction camp site
Once at each construction site
RHD RHD\DOE
Wildlife
Wildlife habitat and movement
None Specific
Areas alongside the road alignment
Quarterly RHD RHD\DOE
Fisheries Impact on fish productivity breeding and spawning
None Specific All major water bodies End of First year of Operation
RHD RHD\DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 31
8.9 EMP Implementation Schedule
65. An implementation schedule of EMP has been sketched based on the environmental
components during the construction and operation of the project. Since project is likely
to have impact on various components of environment, a comprehensive EMP
implementation schedule covering terrestrial and aquatic ecology, soil erosion,
drainage congestion, tree plantation, air quality, noise, and vibration are provided.
Monitoring Plan has been separately suggested for pre-construction, construction and
operation phase. The Implementation Schedule of SASEC II: Improvement of Elenga-
Hatikamrul-Rangpur Road to a 4-lane Highway is presented in Table 9.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 32
Table 9. EMP Implementation Schedule of SASEC Road Connectivity Project-2
Environmental
Issue
EMP Time Line Pre-
Construction (6months)
Construction Phase (24months)
Operation Phase (36months)
Technical Support Updating of environmental guidelines & performance indicators
Flora
Tree cutting along the RoW
Compensatory afforestation (Minimum 1:2)
Drainage Congestion
Provision of adequate opening Monitoring analysis of drainage congestion
Erosion, Sedimentation & Soil
River bank protection measures Soil conservation Monitoring of soil erosion
Land Compensation against land acquisition Landscaping on approach road and service areas
Slope/ Embankment protection at approach Road
Turfing of embankment with grasses and herbs
Embankment protection of the approach road Water & Drinking Water Supply
Monitoring of Surface Water Quality Monitoring of Ground Water Quality & Levels Installation of oil and grease traps at construction sites
Construction of soak pits at construction yards & camps
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 33
Environmental
Issue
EMP Pre- Construction (6months)
Construction Phase
(24months)
Operation Phase (36months)
rehabilitation sites
Ensuring arsenic free drinking water for construction camps
Air Quality & Dust Management
Monitoring of Ambient Air Quality
Water Spraying/ Watering
Construction Safety Provision of PPEs
Health Issues Health Check-up Camps
Noise Quality and Barriers
Monitoring of Noise & Vibration
Monitoring of Tree Felling & Plantation
Maintenance of tree Provision of Noise Barriers
Establishments Construction Stage
Training Environmental training & Awareness
Management Information System
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 34
9 Result of Environmental Monitoring and Compliance Measures
9.1 Environmental Safeguard Compliance
66. Construction works of SASEC Road Connectivity Project-2 is under implementation at
preliminary stage, since the commencement of the all Contractor’s under eight Work
Package are not started, only four packages are being in progress. Thus, the
environmental safeguard compliance monitoring yet to be started. The compliance
measures will be described in the upcoming Semi- Annual EMR based on the Actual
Observation of Monitoring Results.
9.2 Training on Safeguards, Core labor Standards
67. The training for WPs 7, 8 and 9 was held on 23 April 2019 in Bogura. It was
participated by 54 (52 males and 2 females). The training for WP-06 was held on 24
April 2019 in RHD’s Banglow House in Hatikamrul and was participated by 23 (21
males and 2 females). The Training for WP 5, 10 to 13 will be scheduled in August
2019. The training on 23-24 April 2019 was participated by project Implementers at
the field level (project sites) including representatives from the RHD’s Project
Implementation Unit (PIU), PIC technical team at the site (resident engineers, site
engineers, and national safeguards and social development specialists); and
Contractors’ Personnel (from project manager down to foreman level); and the INGO
(SAMAHAR) staff at the field level.
9.3 Forthcoming EMP Actions
68. Within the period each Contractor is obligated to perform the necessary measures to
mitigate environmental issues as part of his implementation activities. In addition,
instrumental measurements are to be done in accordance with agreed schedule and
locations in compliance with the Environmental Monitoring Plan. The Engineer, PIC
likewise, as part of his tasks, will monitor the environmental aspects of the project and
reviews the environmental mitigating performance of the Contractors. The
international and national environmental specialists of PIC will monitor the
environmental aspects of the project road through conducting site visits the project
roads and a number of facilities, reviewing Contractors’ CEMP/ SSEMP and Monthly
and Quarterly Environmental Monitoring report prepared by the EMO of contractors
and approved, as well as follow up the contractors environmental management
compliances performances during construction activities.
9.4 Key Environmental Issues and Related Action Plan
69. Complaints and Response System: During construction activities the records will be
kept by PIU’s of all grievances received, including contact details of complainant, date
the complaint was received, nature of grievance, agreed corrective actions and
the date these were affected and final outcome.
9.5 Conclusion and Recommendation
70. All contractors will execute all civil works including EMP as per specification and
terms and conditions of the Contract.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 35
71. The number of grievances recorded, resolved and the outcomes are to be displayed/
disclosed in the PIU offices, as applicable and to be reported in the next Semi Annual
Environmental Monitoring Report of the SASEC Road Connectivity Project-2.
72. The international and national environmental specialists of the PIC will monitor the
environmental aspects through Environmental Monitoring Checklist of all project
activities. Based on the field visits, analysis would be done on compliance in lieu with
specific scope of on works as defined in the respective Contract Packages and
prevailing field condition.
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 36
Table 10. Environmental Management Plan for Elenga-Hatikamrul Road Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
DESIGN/PRE-CONSTRUCTION STAGE
Climate Change
Changes in climate and long term impacts on the environment
Consider climate change study output for design of alignment and bridge height (see section 5.3 for details).
Throughout the project areas
Design Consultants (DC)
RHD
Topography ▪ Change in topography due to construction-related structures such as bridges, embankments, etc.; and
▪ Visual changes to topography.
▪ Restoration of previous structures if possible.
▪ Provision for tree plantation in the design (see appendix E for tree plantation plan).
Throughout the project areas
Design Consultants (DC)
RHD
Removal of Trees
Cutting of 31450 trees of different species.
▪ Minimize the tree cutting by selecting road widening option based on technical and tree laws consideration. ▪ Trees should not be cut prior the permission
from Forest Department. ▪ Afforestation shall be done at the ratio of 1:2 ▪ A total of minimum 62,900 tree saplings will
be planted (see appendix E for tree plantation plan).
▪ For social forestry afforestation ratio shall be as per the consultation with tree owner.
▪ Raised Median will be planted with grasses and shrubs which may not attain height more than two meters. This planting could provide an effective protection against night glare besides beautifying the area;
▪ The compact plantation will be done on both sides;
▪ The indigenous trees most suited to the tract will be planted;
▪ If a tree of rare species is growing within
the ROW and is required to be removed, it will not be felled but uprooted and transplanted in close consultation with the Forest
Throughout the project areas
Design Consultants (DC)
RHD
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 37
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
Department; ▪ An awareness campaign targeted on the
neighborhood farmers will be carried to popularize the planting of trees, and saplings should be provided on subsidized costs
Land Acquisition
▪ Loss of 8.87 ha of land where agricultural land is 5.47 ha; ▪ Resettlement of Affected Persons (APs).
▪ All efforts shall be made in finalization of alignment to reduce productive land requirement
▪ Careful alignment and route selection by the designer to minimize resettlement;
▪ Developing proper judicious compensation package for affected persons;
▪ Prior to site works, payment of fair compensation to affected people based on the Land Acquisition and Resettlement Plan shall be made.
Throughout the project areas
RHD/Design Consultants (DC)
RHD
Dwellings, Commercial Buildings and Industrial Structures
▪ A few numbers of homesteads have to be acquired throughout the road alignment.
▪ Some markets and shops will also be relocated.
▪ Need to compensate for the loss of land, house, trees, structures, crops, wage Income, etc.
▪ To ensure similar or better living conditions for project affected persons (PAPs).
Throughout the project areas
RHD/Design Consultants (DC)
RHD
Educational Institution, Religious Structure, Culturally Sensitive Structures
Educational, religious, and cultural institutions in the PIA will be directly and indirectly affected from the project activities.
▪ The project implementation should take into consideration construction of the alignment or making provision of allocating alternative land and financial resources (for rehabilitation of the Madrasah, Mosque and the Educational institution falling within the alignment). ▪ Provision should be made of, at least, two rows of trees along the RoW of the alignment and suitable noise barriers to absorb the noise and vibration to be caused by vehicle movement.
Throughout the project areas.
RHD/Design Consultants (DC)
RHD
Public Utility Inconvenience caused by ▪ Provision in the design and budget for Throughout RHD/Design RHD
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 38
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
disruption of public utilities
the relocation of the existing utility infrastructures wherever required; and
▪ All public utilities (e.g. water pipes, gas line, power/ telephone lines likely to be affected by the proposed project road expansion will be relocated well ahead of time before the actual commencement of the construction work.
the project areas Consultants (DC)
CONSTRUCTION STAGE
Hydrologic Regime
▪ Temporary drainage blockage, especially at small bridges, culverts, service areas, and construction sites.
▪ Increased flood risk from more rapid and higher levels of runoff
▪ Provision of drains to take design flows; ▪ Wastes should not be disposed near any
water body. All waste depending on its characteristics, should be disposed of in a controlled manner.
Bridge and culvert sites
Contractor RHD/ Supervision Consultants (SC)
Drainage ▪ Drainage congestion due to waste/sediment disposal and construction of road embankment;
▪ Erosion and subsequent deposition in the adjacent crop fields.
▪ Regular cleaning of channels to avoid choking.
Drainage structure sites
Contractor RHD/SC
Soil Erosion and Siltation
▪ Soil erosion due to construction activities, earthworks, cut and fill operations and from stockpiles
▪ Adopt good construction practices. ▪ Replanting with native varieties of trees and
shrubs ▪ Construction schedule for bridges during non-
monsoon season. ▪ Turfing of embankments to protect slopes. ▪ Earth stockpiles to be provided with gentle
slopes ▪ Vegetate road embankments and road
cuttings with fast growing crop and a native seed mix immediately after fill placement to
The full length of the road alignment
Contractor RHD/SC
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 39
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
prevent scour and to encourage stabilization. ▪ Use stone pitching or riprap at appropriate
places especially around overpasses, bridges, culverts.
Soil Compaction and Contamination
▪ Compaction of soil due to movement
of vehicles and equipment ▪ Contamination of soil due to
leakage/spillage of oil, bituminous and non-bituminous debris
▪ Construction vehicles, machinery, and equipment to be stationed in the designated ROW to avoid compaction.
▪ Haul roads to be designated along the fallow and consolidated soil areas to reduce compaction of arable land.
▪ Fuel storage and filling to be undertaken in areas with concrete surfacing, bunds and interceptor traps
▪ Oil interceptors to be provided at wash down and refueling sites
▪ Oil and grease spill and oil-soaked materials shall be sold off to authorized recyclers.
Construction sites along the full length of the project
Contractor RHD/SC
Topsoil ▪ Removal of top soil for construction from outside the RoW.
▪ Compaction of topsoil. ▪ Loss of top soil by wind
and water erosion. ▪ Covering of top soil by project works.
▪ The stockpile top surface slope to be no steeper than 2 (H):1 (V) to reduce surface runoff and enhance percolation through the mass of stored soil.
▪ Locate topsoil stockpiles outside drainage lines and protect stockpiles from erosion.
▪ Construct diversion channels and silt fences around the topsoil stockpiles to prevent erosion and loss of topsoil. ▪ Use stripped topsoil only to cover all
disturbed areas and along the proposed tree plantation sites.
▪ Rip ground surface prior to the spreading of topsoil,
▪ Limit equipment and vehicular movements to within the approved construction zone.
▪ Remove unwanted materials from topsoil such as roots of trees, rubble and waste etc.
Various construction sites throughout the road alignment
Contractor RHD/SC
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 40
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
Air Quality ▪ Dust Generation due to construction activities and transport of construction materials.
▪ Emissions from vehicles, equipment and machinery.
▪ Vehicles transporting construction material to be covered;
▪ Construction equipment to be maintained to a good standard and idling of engines discouraged.
▪ Machinery emitting visible smoke to be banned from construction sites;
▪ Contractor to prepare a dust suppression program detailing action to be taken to minimize dust generation (e.g. spraying of roads with water), and the equipment to be used.
▪ Equipping asphalt hot mix and batching plants with fabric filters or wet scrubbers to reduce dust emissions; ▪ Locate asphalt and crushing plants away from residential areas and social infrastructure such as mosques, schools and madrasas. (Refer to Table 4.20 for locations of these). Clearance should be at least 500 m and take into account the prevailing wind direction
▪ Dust masks to be provided to workers where dust hazards exist.
▪ Proper dust collection and control systems to be installed at crushers
▪ Air quality monitoring to be carried out as per the schedule in the environmental monitoring plan.
Construction sites along the full length of the project
Contractor RHD/SC/DOE
Noise and Vibration
▪ Noise from construction vehicles, equipment and machinery.
▪ Vibration caused by construction activities.
▪ Use of modern plant and equipment with appropriate muffling devices.
▪ All powered mechanical equipment and machinery to be fitted with noise abating gear such as mufflers for effective noise control, in compliance with DoE regulations.
Construction sites along the full length of the project
Contractor RHD/SC/DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 41
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
▪ Construction operations to be restricted to 0700 to 1800 hours.
▪ Locate rock crushing, concrete mixing and material shipment yards away from residential areas, schools, colleges and hospitals.
▪ Install temporary noise barriers near sensitive locations such as schools, religious places and hospitals (Refer to Table 4.20 for locations)
▪ Providing the construction workers with suitable hearing protection like ear cap, or earmuffs etc.
▪ In areas, where structures may to be affected by vibrations from construction activities, take precautions to minimize
the vibration and the resulting impact. ▪ Noise quality monitoring to be carried out as
per the schedule in the environmental monitoring plan.
Topography and Landscape
▪ Land degradation due to careless excavation from borrow area
▪ Borrow pits to be opened within the road right of way and not on agricultural land
▪ Top soil to be preserved. Borrow pits to be rehabilitated.
▪ Borrow pits opened on private land, to be either closed or converted to ponds at the completion of work as per the written direction of the landowner.
▪ Construction wastes to be used in construction activities.
Borrow areas Contractor RHD/SC
Construction Camps, Workshops and Processing Facilities
▪ Loss of plantation and vegetation. ▪ Permanent physical and
visual impact on the area. ▪ Social disturbance for
▪ Construction camps and workshops to be located away from sensitive areas and not within 500 metres of existing settlements (Refer to Table 4.20 for chainage) unless agreed to after consultation with local people.
Construction sites along the full length of the project
Contractor RHD/SC
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 42
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
nearby community ▪ Briefing and/or on-site training for the contractor’s workers on the environmental requirement of the project and the implementation of mitigation measures.
▪ Minimize vegetation loss while making site arrangements for construction camps and other facilities;
▪ Crushing plants, sites for borrow pits, asphalt hot mix and batching plants to be located clear of environmentally sensitive areas, productive land or existing settlements (Refer to Table 4.20 for locations);
▪ Construction material storage areas not to be located in sensitive areas and to be sheltered or sited within hoardings;
▪ Water and good sanitation facilities to be provided for the camps.
▪ Solid waste must not be dumped, buried or burned at or near the project site, but shall be disposed of at the nearest sanitary landfill or site having and complying with the necessary permits.
▪ The sites for camps and associated facilities shall be rehabilitated after completion of the project.
Surface Water Bodies
▪ Loss of surface water bodies and impact on fish
▪ No bituminous or hazardous materials to be used for filling of water bodies.
All water bodies along the project road (Refer to Table 4.3).
Contractor RHD/SC
Surface Water Quality
▪ Contamination of surface water by disposal of construction waste.
▪ Pollution of domestic water supplies
▪ The workforce to be trained in proper means for storage and handling of materials and chemicals;
▪ Work camps and work sites to be provided with toilets and septic tanks;
▪ Proper drainage system with sedimentation
Construction sites along the full length of the project particularly beel / lowland / pond / ditch areas
Contractor RHD/SC/DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 43
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
ponds and oil separators to be provided to cope with the rain water and oil spills.
▪ Measures to be implemented to control oil spills near water channels
▪ Washing of machinery and vehicles in surface waters to be prohibited. Sealed
washing areas shall be provided and wastewater shall be collected in a sedimentation/retention pond for treatment prior to release.
▪ Avoid or minimize damage to water channels; ▪ Conduct regular water quality monitoring
according to the determined sampling schedule;
▪ Prevent construction debris from entering drainage or irrigation canals;
▪ Construction work close to ponds or other water bodies to be minimized especially during monsoon season;
▪ Wastes to be collected, stored and taken to approve disposal sites.
(Refer to Table 4.3).
Groundwater Quality
▪ Contamination of underground water table from leachate of construction waste.
▪ Arrangements for safe drinking water to be made prior to start of work. Water for consumption to be supplied only after adequate analysis and requisite treatment.
▪ Train workers on the need for judicious use of freshwater resources.
▪ Water reserves to be protected from contamination such as construction and oily waste.
Construction sites along the full length of the project
Contractor RHD/SC/DOE
Waste Pollution ▪ Unhygienic conditions, health risk to workforce and general public at the camp site.
▪ Solid and liquid wastes to be disposed at designated sites and no waste to be disposed in productive agricultural land;
▪ Hazardous waste to be transported to nearby incineration facility;
Construction sites along the full length of the project
Contractor RHD/SC/DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 44
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
▪ Sanitary wastes generating from staff and labor camps to be disposed of in an environmentally friendly manner, i.e. provision of septic tank etc. for toilet wastes;
▪ Pavement materials from the existing road to be incorporated in the upgrading works.
Dredging and Dredged Materials
▪ River bank erosion and higher flood risk and pollution due to spilling/seepage of oil in the river.
▪ Increase in sedimentation and dispersion of pollutants in dredged material
▪ Permits/NOC to be obtained, from relevant authority such as BIWTA prior to extraction
▪ Work not to be carried out when fish are likely to be spawning or in the period between spawning and the subsequent emergence of juvenile fish. (July to September
▪ While dredging, special care to be given to prevent any spillage/seepage of oil from the dredging machines;
▪ If owners of the ponds and lands near the road alignment want to use their area for fisheries project, the contractor may collect filling materials from that area through proper contract and dredging guidelines.
▪ Dredged material from the river bank to be tested for presence of heavy metals and other pollutants before its use.
Note – some areas were tested during the preparation of EIA (refer to Table 4.2).
Dredging sites Contractor RHD/SC
Flora ▪ Loss of habitat due to tree cutting ▪ Vegetation loss due to site
preparation and construction
activities
▪ Trees suited to the tract to be planted (see Appendix E for tree plantation plan);
▪ Flowering and fruiting shrubs to be planted along the RoWs to beautify the landscape;
▪ Contractor’s personnel to be directed not to damage any vegetation such as trees or bushes.
▪ Construction vehicles, equipment and machinery to be limited to their designated areas of movement.
Construction sites along the full length
of the project
Contractor RHD/SC/FD
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 45
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
▪ Gas cylinders to be used for fuel at the camps for cooking purposes. Cutting of trees/bushes for fuel not to be allowed.
▪ Camp sites and asphalt plants to be established on waste/barren land rather than on forested or agriculturally productive land. However if such type of land is not available, it must be ensured that vegetation clearing is minimized and minimum damage is caused to the trees, undergrowth and crops.
Wildlife Hunting of wildlife and birds during construction.
▪ Wildlife Department to check and confirm that no hunting occurs;
▪ New and good condition machinery with low noise generation characteristics to be used in construction;
▪ Construction work not to be carried out at night.
▪ Borrow pits to be fenced to protect animals.
Along the road alignment
Contractor RHD/SC/DOE
Fisheries ▪ Impact on fishing activity (production, spawning and breeding grounds)
▪ Disturbance to aquatic life including migration of fish due to bridge construction.
▪ Construction not to be undertaken during high flood.
▪ Construction along the riverbanks must be avoided during the fish breeding season (July to September).
▪ Deep water channel to be maintained during bridge construction.
Water bodies throughout the road alignment (Refer to Table 4.3).
Contractor RHD/SC
Land use ▪ Land disputes, soil erosion, loss of potential cropland and vegetation, landscape degradation, and damage to road embankments.
▪ Land use change due to borrowing of earth.
▪ Land use change and loss of productive top soil.
▪ Agricultural areas not to be used as borrow areas.
▪ Land acquisition for borrow areas to be minimized. River sand to be used for embankment. Preference shall be given to borrow earth from right of way wherever feasible;
▪ Necessary permits to be obtained for any borrow pits from the competent authorities and all environmental considerations to be
Borrow areas, access roads, bypasses
DC, Contractor RHD/SC
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 46
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
ensured; ▪ Topsoil from borrow areas to be preserved
and borrow pits to be rehabilitated after completion of borrow operations ;
▪ Borrow pits to be sited on waste land and at least 500 m away from the road;
▪ Priority to be given to borrowing from humps (including from digging of wells) above the general ground level;
▪ Priority should be given to the borrowing by excavating/enlarging existing borrow areas;
Traffic ▪ Traffic jams causing inconvenience to the people
▪ Provision to be made for passing traffic during construction
▪ Traffic management shall be undertaken in coordination with the local traffic police department.
Construction sites along the full length of the project
Contractor RHD/SC
Cultural Sites ▪ Noise and dust pollution and movement of the people to the nearby schools, colleges, mosques, and graveyards etc.
▪ Timely completion of the construction work and provision for movement through or around the construction site;
▪ Workshops and storage / processing facilities and labor camp to be sited so as to maintain proper clearances from the cultural sites.
Along the road alignment (Refer to Table 4.20 for chainage)
Contractor RHD/SC
Income and Employment
▪ Income loss due to the loss of agricultural lands, private structures and common property resources and rehabilitation of the households.
▪ Contractor as far as practicable to recruit construction workers from amongst the locals and to maintain gender equity while employing the locals.
▪ Priority shall always be given to people from amongst the project affected persons, the unemployed and lower income groups.
▪ Set aside-areas within the contractor’s camps/labor shed for local people to sell their products and to provide additional services to the workers.
Along the road alignment
Contractor RHD/SC
OHS - Workers
▪ Health risks due to unsafe working conditions
▪ Worker’s compensation insurance to be taken out for all project staff;
Construction sites along the full
Contractor RHD/SC
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 47
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
▪ Basic medical training to be given to specified work staff
▪ Basic medical service and supplies to made available for workers;
▪ Appropriate personal protective equipment (hearing protection, safety glasses, helmets, protective footwear and gloves, high visibility vests and other protective clothing) to be provided to all workers; possible.
length of the project
Noise and Vibration
The noise levels are anticipated to increase due to traffic related noise pollution; vibrations from engines and tires and mainly use of pressure horns.
▪ According to monitoring results, additional sound barriers in form of trees and hedges will be discussed with the affected people and planted if agreed;
▪ Signs for sensitive zones (health centers / educational institutions, etc.) to disallow the use of pressure horns;
▪ Enforcement and penalties against traffic rules violators;
▪ Monitoring to protect the trees.
Along the road alignment particularly in the major road intersections and densely settlement areas
RHD RHD/DOE
Air Quality Increased traffic levels and congestion will lead to air pollution levels.
▪ Ambient air quality monitoring should be carried out during operation phase;
▪ Roadside tree plantations as applicable and feasible under harsh climatic conditions;
▪ Regular road maintenance to ensure good surface condition;
▪ Regular vehicle check to control/ensure compliance with air quality standards;
▪ Enforcement and penalties against traffic rules violators.
Along the road alignment particularly in the major road intersections and densely settlement areas
RHD RHD/DOE
Water Quality ▪ Contamination of water bodies from
runoff from the roads containing oils & grease;
▪ In order to discharge rapid removal of storm-water/road runoff, cross slopes and longitudinal drainage will be provided in the design;
▪ Proper drainage system with sedimentation
Throughout the road alignment particularly in khal/lowland/ rivers/pond/ditch
RHD RHD/DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 48
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
▪ Groundwater may get polluted due to contaminated road runoff on earthen shoulders and embankments planted with grasses.
ponds and oil separators will be provided to avoid contamination by run-off and oil spills;
▪ Retention basins with reed beds provided in the design will improve the quality of polluted storm-water/road runoff;
▪ Prior to operation, an emergency response plan for spills of hazardous materials and oil will be prepared.
▪ Groundwater quality monitoring will be carried out as per schedule suggested in the Environmental Monitoring Plan.
areas
Land Use Development of commercial establishments, educational institutes etc., which may affect the land value
▪ All the facilities with the exception of restaurants and petrol/gas filling stations likely to pop up in the future will be prohibited within the RoW.
▪ The permission will be sought from the concerned authority for the development of any establishment along the project;
▪ The bridge site may also be developed as tourist spot with further beautification;
▪ The designated RoW shall be maintained free of any encroachment.
Along the road alignment particularly in the urban and densely settlement areas
RHD RHD
Wildlife Killing of animals in road accidents
▪ Raising of dense plantation of shady trees on both sides of the RoW shall provide resting, nestling and roosting habitat to the fauna and especially to the avifauna which is a major positive impact;
▪ Low width under passes with the provision of small net on the both side of the road shall be made where the animal movement is frequent.
Along the road alignment
RHD RHD/DOE
Fisheries The damage of 2 ponds, 2 ditches and disturbance to fisheries species during
▪ Provide logistic support to the PAPs of the water bodies to culture fish in other places in the PIA.
Throughout the road alignment
RHD RHD/DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 49
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
Construction of bridge & culvert over rivers and canals to build the road embankment.
▪ Consult with the local fisheries department to enrich the fisheries resources;
▪ Efforts shall be made to maintain deep
water stream for certain length on both end of the bridge.
particularly in khal/lowland and/rivers/pond /ditch
Cultural Sites Noise, vibration and whistling near to cultural sites like school, college, madrasa, health complex, temple, etc.
▪ Proper rehabilitation of the affected people and the religious and cultural monuments and structures;
▪ Noise problem can be mitigated through plantation of trees along the boundary of the cultural sites;
▪ Avoid unnecessary whistling at sensitive cultural sites.
Along the road alignment
RHD RHD
Road Safety Increase in the number of road accidents & animals kills
▪ Speed limits shall be imposed. ▪ Safety signal shall be displayed along the
road and speed limits be displayed as well as monitored especially along settlements;
▪ Traffic signs shall be provided to warn road users about speed limits, rest areas, eating establishments etc.
▪ Lanes, median, and sharp bends shall be reflectorized to improve road visibility at night time.
▪ Foot over bridge shall be provided near schools, markets, habitat areas for safe crossing of the roads
▪ Proper lighting shall be provided along the project road.
Along the road alignment particularly at road intersections
RHD RHD
OPERATION STAGE
Soil ▪ Erosion due to damage of embankment and during transportation of sand by sand miners along river
▪ Soil contamination due to accidental spillage from
▪ Turfing of embankment shall be maintained.
▪ Surveillance to protect the embankment from unauthorized accesses.
▪ Proper measures must be ensured to prevent any oil spillage and leakage from the
Along the road alignment particularly at erosion prone area
RHD RHD
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 50
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
vehicular movement. locomotives. ▪ Efforts will be made to clean the spills of oil,
toxic chemicals etc. as early as possible.
Noise and Vibration
The noise levels are anticipated to increase due to traffic related noise pollution; vibrations from engines and tires and mainly use of pressure horns.
▪ According to monitoring results, additional sound barriers in form of trees and hedges will be discussed with the affected people and planted if agreed;
▪ Signs for sensitive zones (health centers / educational institutions, etc.) to disallow the use of pressure horns;
▪ Enforcement and penalties against traffic rules violators;
▪ Monitoring to protect the trees.
Along the road alignment particularly in the major road intersections and densely settlement areas
RHD RHD/DOE
Air Quality Increased traffic levels and congestion will lead to air pollution levels.
▪ Ambient air quality monitoring should be carried out during operation phase;
▪ Roadside tree plantations as applicable and feasible under harsh climatic conditions;
▪ Regular road maintenance to ensure good surface condition;
▪ Regular vehicle check to control/ensure compliance with air quality standards;
▪ Enforcement and penalties against traffic rules violators.
Along the road alignment particularly in the major road intersections and densely settlement areas
RHD RHD/DOE
Water Quality ▪ Contamination of water bodies from runoff from the roads containing oils & grease; ▪ Groundwater may get
polluted due to contaminated road runoff on earthen shoulders and embankments planted with grasses.
▪ In order to discharge rapid removal of storm-water/road runoff, cross slopes and longitudinal drainage will be provided in the design;
▪ Proper drainage system with sedimentation ponds and oil separators will be provided to avoid contamination by run-off and oil spills;
▪ Retention basins with reed beds provided in the design will improve the quality of polluted storm-water/road runoff;
▪ Prior to operation, an emergency response plan for spills of hazardous materials and oil
Throughout the road alignment particularly in khal/lowland/rivers/pond/ditch areas
RHD RHD/DOE
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 51
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
will be prepared. ▪ Groundwater quality monitoring will be
carried out as per schedule suggested in the Environmental Monitoring Plan.
Land Use Development of commercial establishments, educational institutes etc., which may affect the land value
▪ All the facilities with the exception of restaurants and petrol/gas filling stations likely to pop up in the future will be prohibited within the RoW.
▪ The permission will be sought from the concerned authority for the development of any establishment along the project;
▪ The bridge site may also be developed as tourist spot with further beautification;
▪ The designated RoW shall be maintained free of any encroachment.
Along the road alignment particularly in the urban and densely settlement areas
RHD RHD
Wildlife Killing of animals in road accidents
▪ Raising of dense plantation of shady trees on both sides of the RoW shall provide resting, nestling and roosting habitat to the fauna and especially to the avifauna which is a major positive impact;
▪ Low width under passes with the provision of small net on the both side of the road shall be made where the animal movement is frequent.
Along the road alignment
RHD RHD/DOE
Fisheries The damage of 2 ponds, 2 ditches and disturbance to fisheries species during Construction of bridge & culvert over rivers and canals to build the road embankment.
▪ Provide logistic support to the PAPs of the water bodies to culture fish in other places in the PIA.
▪ Consult with the local fisheries department to enrich the fisheries resources;
▪ Efforts shall be made to maintain deep
water stream for certain length on both end of the bridge.
Throughout the road alignment particularly in khal/lowland and/rivers/pond /ditch
RHD RHD/DOE
Cultural Sites Noise, vibration and whistling near to cultural sites
▪ Proper rehabilitation of the affected people and the religious and cultural
Along the road alignment
RHD RHD
SASEC Road Connectivity Project-2: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 52
Environmental
Activities
Potential Impacts Mitigation Measures Approximate Location
Institutional Responsibilities
Implementation Monitoring /Supervision
like school, college, madrasa, health complex, temple, etc.
monuments and structures; ▪ Noise problem can be mitigated through
plantation of trees along the boundary of the cultural sites;
▪ Avoid unnecessary whistling at sensitive cultural sites.
Road Safety Increase in the number of road accidents & animals kills
▪ Speed limits shall be imposed. ▪ Safety signal shall be displayed along the
road and speed limits be displayed as well as monitored especially along settlements;
▪ Traffic signs shall be provided to warn road users about speed limits, rest areas, eating establishments etc.
▪ Lanes, median, and sharp bends shall be reflectorized to improve road visibility at night time.
▪ Foot over bridge shall be provided near schools, markets, habitat areas for safe crossing of the roads
▪ Proper lighting shall be provided along the project road.
Along the road alignment particularly at road intersections
RHD RHD
Source: Environmental Impact Assessment, Elenga – Hatikamrul Road Subproject, Sub-regional Transport Project Preparatory Facility (Road Component: Package-1) (ADB Loan 2688-BAN). March 2015
SASEC Road Connectivity Project-II: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 53
73. Photographs
National Environment Specialist presenting the summary of environmental
safeguard policy and EMP in Bangla language based on the key points discussed by the PIC Senior Environment Specialist (int’l).
The RHD officers, PIC Training Team and the Participants on 23 April 2019
Training for WP 7, 8 and 9 in Bogura
SASEC Road Connectivity Project-II: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 54
The RHD Officers (APDs and PMs) during the Training for
WP 7, 8 and 9 in Bogura
Training for WP 06 in Hatikamrul, with the Project Manager for WP-06, PIC,
RE, Contractor & Labor Force and INGO (SAMAHAR) Staff at the Site on 24 April 2019
SASEC Road Connectivity Project-II: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 55
PIC consultants discuss the topics related to safeguards, core labor standards,
road safety, etc.
WP-06 Project Manager (BBA) giving his message to the participants
during the training on 24 April 2019 in RHD Conference Room, Banglow House, Hatikamrul
SASEC Road Connectivity Project-II: Improvement of Elenga-Hatikamrul-Rangpur Road to a 4-lane Highway
Semi-Annual Environmental Monitoring Report, ADB Loan 3592/3593-BAN 56
: PIC’s National Environment Specialist providing additional information in Bangla