31-bridgedesign
-
Upload
marioestructura -
Category
Documents
-
view
222 -
download
0
Transcript of 31-bridgedesign
-
7/28/2019 31-bridgedesign
1/67
1
Part 1
Introduction To Bridge Design
-
7/28/2019 31-bridgedesign
2/67
2
How Do Bridge Engineers DecideOn What Type Of Bridge To Build?
Bridge Survey flood plain cross sections inspection reports existing bridge (scour, etc) water elevations photos existing roadway profile
Geotechnical Report soil / geological formations slopes and grading foundation problems soil prop.s - phi angles etc
Factors affecting choice of superstructure location, city or rural span length vertical clearance maintainability
environmental concerns transportation to site issues costFactors affecting choice of substructure location and geometry subsoil conditions height of column
-
7/28/2019 31-bridgedesign
3/67
3
Bridge Design ProcessPreliminary Design Process
Bridge Survey Geotechnical Report1. Determine the most
economical type structure andspan arrangement
2. Hydraulic Analysis3. Preliminary Cost Estimate4. Foundation Borings5. Determine Foundation Type
Final Design Process
Top to Bottom Design (twice) Design methods per AASHTO and
MoDOT Bridge Manual Analysis via
computations
spreadsheets computer programs Detail plans are produced by technicians
(Micro-Station) Plans are checked Quantities computed Special Provisions written Plans are advertised for bidding Low Bid Contractor builds the bridge
-
7/28/2019 31-bridgedesign
4/67
4
Types of SuperstructuresBridges are often referred to by their superstructure types.The superstructure system of members carry the roadway over a crossingand transfer load to a substructure.
Superstructures are categorized by; Support type (simply supported or continuous) Design type (slab on stringer, slab, arch. Rigid frame, etc) Material type (steel, concrete, timber)
-
7/28/2019 31-bridgedesign
5/67
5
Slab on Stringer Bridges
Most common type of bridge in Missouri. Consist of a deck, resting on the girders. The deck distributes the
loads transversely to the girders.
The girders carry the loads longitudinally (down the length of the
bridge) to the supports, (abutments and intermediate bents).
Concrete
Deck Girder
Prestressed I Girder Prestressed Double Tee
Prestressed Box
Steel
Plate Girder
Wide Flange
Steel Box Girder
-
7/28/2019 31-bridgedesign
6/67
6
I - GIRDER
BULB TEE
Prestressed Girders
-
7/28/2019 31-bridgedesign
7/67
7
Prestressed Concrete I-Girder
-
7/28/2019 31-bridgedesign
8/67
8
Prestressed Concrete I-Girder Bridge
-
7/28/2019 31-bridgedesign
9/67
9
Prestressed Concrete Panels
-
7/28/2019 31-bridgedesign
10/67
10
Prestressed Double Tee Girders
-
7/28/2019 31-bridgedesign
11/67
11
Steel Plate Girder / Wide Flange Beam / Box Beam
-
7/28/2019 31-bridgedesign
12/67
12
Steel Plate Girder Bridge
-
7/28/2019 31-bridgedesign
13/67
13
Slab BridgesIn slab bridges the deck itself is the structural frame or the entire deck is a thin
beam acting entirely as one primary member. These types are used wheredepth of structure is a critical factor.
Typical Slab Bridges : Concrete Box Culverts Solid Slabs Voided Slabs
-
7/28/2019 31-bridgedesign
14/67
14Box Culvert
Triple Box Culvert
-
7/28/2019 31-bridgedesign
15/67
15
Voided Slab Bridge
-
7/28/2019 31-bridgedesign
16/67
16Solid Slab
Voided Slab Bridge
-
7/28/2019 31-bridgedesign
17/67
17
SubstructuresThe substructure transfers the superstructure loads to the foundations.End Abutments Integral Abutment - girders on beam supported by piles, girders concreted into the
diaphragm Non-Integral Abutment - diaphragms of steel cross-frames, uses expansion devices Semi-Deep Abutment - used when spanning divided highways to help shorten span Open C.C. Abutment - beam supported by columns and footings, rarely usedIntermediate bents Open Concrete Bent - beams supported by columns and footings (or drilled shafts)
either a concrete diaphragm (Pre-Stressed Girder) or steel diaphragm (Plate Girder)This is the most common type of Pier MoDOT uses.
Pile Cap Bent - beams supported by piling (HP or C.I.P.) and are used when the
column height is less than 15 feet and usually in rural areas. Hammer Head Bent - single oval or rectangular column and footing. Spread footings - are used when rock or soil can support the structure. Pile footings - rectangular c.c. supported by HP or Cast in Place piles Drilled Shafts - holes drilled into bedrock filled with concrete
-
7/28/2019 31-bridgedesign
18/67
18
Integral End Abutment
-
7/28/2019 31-bridgedesign
19/67
19
Semi-Deep End Abutment
-
7/28/2019 31-bridgedesign
20/67
20
Prestressed I-girder intermediate bent
-
7/28/2019 31-bridgedesign
21/67
21
Steel girders with open intermediate bent diaphragms
-
7/28/2019 31-bridgedesign
22/67
22
Footing
Pile Cap Column Footing
-
7/28/2019 31-bridgedesign
23/67
23
Column Footing
-
7/28/2019 31-bridgedesign
24/67
24
Preliminary Design
Bridge location Hydraulic design to determine required
bridge length and profile grade Bridge type selection
-
7/28/2019 31-bridgedesign
25/67
25
Stream Gage Data
-
7/28/2019 31-bridgedesign
26/67
-
7/28/2019 31-bridgedesign
27/67
27
Q = discharge (cfs or m 3/s)k c = constant (1.0 for English units or
0.00278 for metric units)C = Runoff Coefficient
I = Rainfall Intensity (in/hr or mm/hr) A = Drainage Area (acres or hectares)
Rational Method
A I C k Q c
-
7/28/2019 31-bridgedesign
28/67
28
Drainage Area Delineation
-
7/28/2019 31-bridgedesign
29/67
29
n1 n2 n3
LeftOverbank
RightOverbank
Channel
Stream Valley Cross-sections
-
7/28/2019 31-bridgedesign
30/67
30
Mannings Equation
03
2486.1S R A
nQ
n = Roughness CoefficientA = AreaR = Hydraulic Radius = A / PP = Wetted Perimeter S = Hydraulic Gradient (channel slope)
-
7/28/2019 31-bridgedesign
31/67
31
n1 n2 n3
LeftOverbank
RightOverbank
Channel
Stream Valley Cross-sections
-
7/28/2019 31-bridgedesign
32/67
32
Energy Equation
Elevation
1 2
DatumElevation
Pressure
Pressure
Velocity
Velocity
HeadlossEGL
HGL
z 1 z 2
y1
y2
V 12 /2g
V 22 /2g
hl
l h g V
y z g
V y z
22
2
222
2
111
-
7/28/2019 31-bridgedesign
33/67
33
Constriction of Valley by Bridge
Opening Length
Bridge Deck/Roadway
-
7/28/2019 31-bridgedesign
34/67
34
Encroachment by Roadway Fill
Flood elevationbefore encroachmenton floodplain
Fill Fill
Bridge Opening Encroachment
Backwater
Encroachment
-
7/28/2019 31-bridgedesign
35/67
35
Backwater
Normal Water Surface
Water Surface through Structure
Affect of Bridge on Flood
ElevationsDesign High Water Surface (DHW)
-
7/28/2019 31-bridgedesign
36/67
36
Part 2
Slab Design
-
7/28/2019 31-bridgedesign
37/67
37
Geometry & Loads
16k 16k
Deck Weight = Width x Thickness x Unit Weight
1 ft x (8.5in x12 in/ft) x 150 lb/cf = 106 lb/ft
-
7/28/2019 31-bridgedesign
38/67
38
-
7/28/2019 31-bridgedesign
39/67
39
-
7/28/2019 31-bridgedesign
40/67
40
Design Moment
MDL1 = wS 2/10 = 0.106 x 8 2 / 10 = 0.678 MDL2 = wS 2/10 = 0.035 x 8 2 / 10 = 0.224 MLL = 0.8(S+2)P/32 = 0.8(8+2)(16)/32 = 4 M Imp = 30% x M LL = 1.2 M
u= 1.3[0.678+0.224+1.67(4+1.2)] = 12.4
Design For 12.4 k-ft/ft
-
7/28/2019 31-bridgedesign
41/67
41
Statics, Moment, Shear, Stress?
-
7/28/2019 31-bridgedesign
42/67
42
Reinforced Concrete Design Basic Equations For Moment Utilize Whitney
Stress Block ConceptDesign Moment = Capacity
12.4 k-ft/ft = f As f y(d-a/2) f = 0.90
Compression = Tension0.85f c ba = A s f y
Two Simultaneous Equations, Two Unknowns (a & A s)
d
c
Comp.
Tens.
c = a / b1
-
7/28/2019 31-bridgedesign
43/67
43
Reinforced Concrete Design (0.85)(4ksi)(12in)(a)=(A s)(60ksi) a=1.47A s 12.4k-ft=(0.9)(A s)(60ksi)(6in-1.47A s/2)/(12in/ft) 12.4=27A s-3.31A s2
ax2+bx+c=0 a=3.31, b=-27, c=12.4, x=A s
As = [-b - (b 2 - 4ac) 1/2]/2a As = [-27 - ((-27) 2-(4)(3.31)(12.4)) 1/2]/[(2)(3.31)] As = 0.49 in 2/ft
5/8 rebar at 7.5 in centers d cComp.
Tens.
c = a / b 1
-
7/28/2019 31-bridgedesign
44/67
44
Part 3
Steel Beam Design
-
7/28/2019 31-bridgedesign
45/67
45
Simple Span Beam 50 ft span
-
7/28/2019 31-bridgedesign
46/67
46
Dead Load = Beam Weight + Deck Weight
-
7/28/2019 31-bridgedesign
47/67
47
Live Load = HS20 Truck x Distribution Factor
Distribution Factor = S/5.5
-
7/28/2019 31-bridgedesign
48/67
48
Design Moment = 2358 kip-ft
-
7/28/2019 31-bridgedesign
49/67
49
Design Shear = 214 kips
-
7/28/2019 31-bridgedesign
50/67
50
Steel Girder Design Design Moment = 2358 k-ft
Design Shear = 214 kips Limit Bending Stress
Due To Moment
Limit Shear StressDue to Shear
-
7/28/2019 31-bridgedesign
51/67
51
-
7/28/2019 31-bridgedesign
52/67
52
Girder Design Moment Of Inertia (I)
1/12bh 3+Ad 2
Parallel Axis Theorem
Section Modulus = S = I/c Stress = Moment/Section Modulus (M/S) For Strength Design Limit Stress to F y Find Shape With S > M/F y S > (2358k-ft)(12in/ft)/50ksi = 566 in 3 A W36x170 Provides 580 in 3
-
7/28/2019 31-bridgedesign
53/67
53
Part 4
Intermediate Bent Design
-
7/28/2019 31-bridgedesign
54/67
54
Load Cases
Permanent Loads: DD = Downdrag
DC = Dead LoadComponent DW = Dead Load
Wearing Surface
EH = Horizontal Earth ES = Earth Surcharge EV = Vertical Earth EL = Locked In Forces
Transient Loads: SE = Settlement
BR = Braking CE = Centrifugal Force CT = Vehicular
Collision
CV = Vessel Collision EQ = Earthquake IC = Ice Load FR = Friction
-
7/28/2019 31-bridgedesign
55/67
55
Load Cases (Cont.)
Transient Loads: LL = Live Load
IM = Dynamic Load LS = Live LoadSurcharge
PL = Pedestrian Load
WL = Wind On LiveLoad WS = Wind On
Structure
Transient Loads: TG = Temperature
Gradient TU = Uniform
Temperature CR = Creep
SH = Shrinkage WA = Water Load
-
7/28/2019 31-bridgedesign
56/67
56
Load Combinations
Load CombinationLimit State
DC
DDDWEHEV
ESEL
LLIMCEBR
PLLS WA WS WL FR
TU
CR SH TG SE
Use One of These at a Time
EQ IC CT CV
STRENGTH I(unless noted) gp 1.75 1.00 - - -- 1.00 0.50/1.20 gTG gSE -- -- -- --
STRENGTH II gp 1.35 1.00 - - -- 1.00 0.50/1.20 gTG gSE -- -- -- --STRENGTH III gp -- 1.00 1.40 -- 1.00 0.50/1.20 gTG gSE -- -- -- --STRENGTH IV gp -- 1.00 -- -- 1.00 0.50/1.20 -- -- -- -- -- --STRENGTH V gp 1.35 1.00 0.40 1.0 1.00 0.50/1.20 gTG gSE -- -- -- --EXTREME EVENT I gp gEQ 1.00 -- -- 1.00 -- -- -- 1.00 -- -- --EXTREME EVENT II gp 0.50 1.00 -- -- 1.00 -- -- -- -- 1.00 1.00 1.00
SERVICE I 1.00 1.00 1.00 0.30 1.0 1.00 0.50/1.20 gTG gSE -- -- -- --SERVICE II 1.00 1.30 1.00 -- -- 1.00 0.50/1.20 -- -- -- -- -- --
SERVICE III 1.00 0.80 1.00 -- -- 1.00 0.50/1.20 gTG gSE -- -- -- --SERVIE IV 1.00 -- 1.00 0.70 -- 1.00 0.50/1.20 -- 1.0 -- -- -- --
FATIGUE LL, IM &CE ONLY -- 0.75 -- -- -- -- -- -- -- -- -- -- --
-
7/28/2019 31-bridgedesign
57/67
57
Water (WA) Strength
M = (Pbh)(h)= Pbh 2
h
Resultant
P
C o n
t r a c t
i o n S
c o u r
1 0 0 y e a r
P i e r
S c o u r
1 0 0 y e a r
Q 100
b
M
-
7/28/2019 31-bridgedesign
58/67
58
Water (WA) - Extreme Event
(Cont.)
(b)10000.7VForce
2
C o n
t r a c t
i o n
S c o u r
5 0 0 y e a r
P i e r
S c o u r
5 0 0 y e a r
Q500
b
B
A (B)10000.5VForce
2
A = Of Water Depth 10 B = Sum Of Adjacent Span Length 45
Drift Mat
Pressure = C DV2/1000
CD=0.7
CD=0.5
-
7/28/2019 31-bridgedesign
59/67
59
Wind on Structure (WS)P (WS)Vert.
W
W
P (WS)Trans. H H
P (WS)Long.
P Sub.
PVert. = (20psf)(W)(L)PTrans. = (50psf)(H)(L)
PLong. = (12psf)(H)(L T)(%)
PSub. = (40psf)(b)
L = Tributary Length
LT = Total Bridge Length
% = Long. Distribution %
b = Column Or Cap Width
-
7/28/2019 31-bridgedesign
60/67
60
Wind on Live Load (WL)PTrans. = (100plf)(L)
PLong. = (40plf)(L T)(%)
L = Tributary Length
LT = Total Bridge Length% = Long. Distribution %
P (WL)Trans.P (WL)Long.
6
-
7/28/2019 31-bridgedesign
61/67
61
Int. Bent Analysis
-
7/28/2019 31-bridgedesign
62/67
62
Cap Beam - Strength Limit State
Basic Equations For Moment Utilize WhitneyStress Block Concept f M
n= f A
s f
y(d-a/2)
f = 0.90
d e c
Comp.
Tens.
c = a / b1
-
7/28/2019 31-bridgedesign
63/67
63
Cap Beam Service Limit State Crack Control
dc = Concrete Cover To Center Of Closest Bar f s = Service Tensile Stress In Reinforcement h = Overall Section Thickness
ge = 1.00 For Class 1 Exposure (Crack Width = 0.017) = 0.75 For Class 2 Exposure (Crack Width = 0.013)
)d0.7(hd
1c
cs2dc
700s
ss
e
f g
-
7/28/2019 31-bridgedesign
64/67
64
Cap Beam Service Limit State Crack Control Is Based On A Physical Model
x
h d c
f c1
f c2
f s /n
l l CrackSpacing
Primary TensionReinforcement
f c1
f c2
f s /n
f c1
f c2
f s /n
l = =16.03
s s
22c 2sd2
d c
-
7/28/2019 31-bridgedesign
65/67
65
Simplified Shear Design
LRFD f Vn = f (V c + V s + V p)(kips) f = 0.90
a Set At 90 Set: b=2.0, q =45
Results In:
vvcc db'0.0316Vf
s
)sincot(cotd AV
vyvs
af
LbsToConvertTo1000ByMultiply V c
vvcc db'2.00V f s
d AV vyvs
f
0.0
-
7/28/2019 31-bridgedesign
66/67
66
Simplifed Shear Design
Section A-A
5 -
# 6 s
( E a c h
F a c e
)
6 - #9s
6 - #9s
#5s @12 or 6 A
A
-400
-200
0
200
400
-
7/28/2019 31-bridgedesign
67/67
Column Design
Column42 Diameter
-1000
3500P (kip)
(P max)
(P min)
1800M (k-ft)
Controlling Point
Axial Load Moment Interaction Diagram
18-#9 Bars