25.875 OT
-
Upload
p-allen-samuel-ignatius -
Category
Documents
-
view
212 -
download
0
Transcript of 25.875 OT
-
8/11/2019 25.875 OT
1/11
Unlined canal Offtake : 2R
at Km : 1.325
Discharge (required) = 0.1020 cumecs Discharge (provided) = 0.107 OKV = 0.971 OK
Full supply depth (d) = 0.35 m Vo
Bed width (b) = 0.50 m Manning's rugosity coefficient (n) = 0.03
Side slopes ( Inner) = 1.5 :1
( Outer) = 2.0 :1
Bed fall = 1 in 1500 OR 0.00067
Area = 0.500 + 0.35 x 1.5 x 0.35
= 0.359 Sq.m
P = 0.50 + 2 x 1.803 x 0.35
= 1.76 m
R = A
P
= 0.359 = 0.204 m
1.762
V = 1 X 0.2042/3
X 0.000670.5
0.030
= 0.298 m/sec
Q = V x A
= 0.298 x 0.35875
= 0.107 cumecs
Vo = 0.530 x d0.52
m/sec
Vo = 0.530 x 0.3500.52
= 0.307 m/sec
V = 0.298 = 0.971
Vo 0.307
GUNDLAKAMMA RESERVOIR PROJECT2. DESIGN OF OFF-TAKE CHANNEL
0.350 m :1
1.5
Bed width
0.50 m
3 245932249.xls.ms_office
-
8/11/2019 25.875 OT
2/11
1) HYDRAULIC PARTICULARS
1 Ayacut Ha 41100 400
2 Discharge (Required/Designed) Cumecs 19.383 / 19.540 0.1360
3 Bed width m 10.10 0.70
4 Full Supply Depth m 2.00 0.35
5 Free board m 0.90 0.45
6 Side slopes (Inner) - 1.50 :1 1.50 :1
(Outer) 2 :1 2 :1
7 Bed fall - 1 in 5000 1 in 2000
8 Velocity m/s 0.746 0.3250
9 Value of 'n' - 0.0250 0.0250
10 Top width of banks L/R m 7.000 / 4.00 4.200 / 2.00
11 C.B.L. m + 453.325 + 453.925
12 F.S.L. m + 455.325 + 454.275
13 T.B.L. m + 456.225 + 454.725
14 G.L. m + 456.065 + 456.065
2) DESIGN OF O.T.CHANNEL
Assume the section - x 0.350 m
Area - 1.500
= 0.42875 m2
Perimeter - + 1.803 x 2 x 0.350
= 1.962 m
Hydraulic Radius (R) - A/P = 0.429 / 1.962
0.2185 m
R2/3
- = 0.3628 m
Velocity - V = 1/ 0.025 x 0.3628 x 0.022361
= 0.3245
Discharge - Q = 0.4288 x 0.3245
= 0.1391 > 0.1360
HENCE O.K.
V0= 0.53 x 0.350= 0.30704
V/V0= 0.3245 / 0.3070
= 1.0569 (1.1 to 0.9)
3) DRIVING HEAD:
FSL in the parent channel = 455.325 m
3/4 of FSD = 1.500
3/4 of FSL = + 454.825
3/4 FSL in the Offtake channel = + 454.275 m
Driving head = 454.825 - 454.275
So, Consider the driving head = 0.5500 m
4) AREA OF VENT WAY
Q = Cd A Sqrt (2g h) (for circular vent ) Cd = 0.75
Q Cd A S t (2 h) (f R t l t t)
DESIGN OF OFF-TAKE SLUICE FOR 12 L MAJOR @ Km 25.875
0.7
( 0.7 + x 0.35 ) x 0.350
Main Canal O.T 12 L
DescriptionSl Particulars ofUnit
0.7
0.52
-
8/11/2019 25.875 OT
3/11
Q = OT Discharge = 0.1360 Cumecs
h = Driving head considered = 0.5500 m
A = Area of vent way
Cd = Coefficient of discharge = 0.750
In this case "Provide circular type vent"
0.136 = 0.750 x A x Sqrt (2 x 9.81 x
= 0.750 x A x Sqrt 10.791= 2.464 x A
Area of vent (A) = 0.136
2.464
A = 0.055 Sqm
The minimum dia . Of pipe = 0.300 m
Dia meter of pipe required (d) = Sqrt(4x0.055/pi)
= 0.265 m
= 265.20 mm
Provide 300 mm minimum with ferrule of 265 mm @ the first pipe joint.
So, provide 1 vents of 0.300 m
Therefore the area of vent provided = 0.071 Sqm > 0.055 Sqm HENCE OK
5 HOIST PLATFORM LEVEL (HPL)
(A) Hoist platform level = Sill level + twice height of gate + 0.3 + 0.15
Height of gate = 0.30 m
Hoist plotform level = 453.925 + 2 x 0.30 + 0.05
+ 0.3 + 0.15
Hoist plotform level = + 455.075 m
FSL in the parent channel = + 455.325 m
(B) Hoist plotform level = FSL + 0.3
= 455.325 + 0.3
= + 455.625 m
Therefore, Provide the hoist platform level (HPL) = + 455.63 m
Provide Width of platform = 1.200 m
4 LENGTH OF BARREL
Length of barrel Required = 0.60 + 1.5 (TBL/GL - HPL) + TW + 2/1.5 (TBL/GL - d/s Hwl) + 0.6/0.45
Assume Level of D/s head wall = m
Length of barrel = 0.6 + 1.500 x 456.225 - 455.625 + 7.000
+ 2 x 456.225 - 455.725 + 0.5
= 0.6 + 0.9 + 7.000 + 1.000
+ 0.5
Length of barrel = 10.0000 m
Provide 4 no.s of 2.500 m length pipes
Length of barrel provided = 10.000 m HENCE OK
5) PROTECTION WORK
Provide 5 m length of Lining in CC M10 on D/S of of structure in the O.T Channel
and the same for 5 m length on either side of U/S transition to the side of Parent channel
6) UPSTERAM TRANSITION
Th l l f U/S l d i Pl tf l l (Pl tf idth / id l )
0.5500 )
+ 455.7250
-
8/11/2019 25.875 OT
4/11
The length of U/S transition (or) The Horizontal length of U/S sloped wing
= (level of U/S sloped wing - CBL of parent channel) * side slope
= 1.500 x + 454.825 - 453.325
= 2.250 m
Providing length of transition 1 in 3 flare
Outer width of transition = barrel width +( 2 x horizontal length of U/s sloped wing / flare)
= 0.300 + 2 x 2.250
3
= 1.800 m
say 1.800 m
7) DOWNSTERAM TRANSITION
Barrel / Pipes width = 0.300 m
Bed width of O.T channel = 0.70 m
Providing length of transition in 1 in 5 flare
The length of D/S transition = 5 x 0.70 - 0.3
2
= 1.0 m
However provide , a cistern of 2.000 x 2.00 m size
from which the offtake channel runs
-
8/11/2019 25.875 OT
5/11
GL = ######## m
TBL of Parent canal = ######## m Dia of pipe = 300 mm
Platform level = ######## m Thickness of pipe = 30.00 mm FSL parent channel = ######## m Caulking space = 16.00 mm
Sill of OT = ######## m Collar thickness = 30.00 mm
CBL of Parent channel = ######## m Collar length = 150.00 mm
GL = ######## m
length of barrel 10.00 m
0.900 Bank Width 4.000 m 4.000
1.200 + 456.225 TBL
0.45 0.6
0.15 2.0001.5 : 1 2.0 : 1
Platform level #######
2.27
FSL #######
Pial Wall
#######
+ 453.955 0.03
Parent channel 1 2 0.3 3 4#######
CBL ########
1.2 2.5 2.5 2.5 2.5
3.(ii). LINE DIAGRAM OF OFFTAKE SLUICE (CIRCULAR TYPE VENT)
7
-
8/11/2019 25.875 OT
6/11
1. DESIGN OF HEAD WALL (U/S)
= t
1.5:1 = t
W6 +
+
+
Taking moments about A (Stresses in concrete)
W1 x x
W2 x x x
W3 x x x
W6 x x x
Pv x x x
Ph x x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = < REVISE THE SEC
= x ( 1 + 6 ) = t/sq.m.
Min. Stress = x ( 1 - 6 ) = t/sq.m.
Taking moments about B (Stresses on soil)
W1 x x
W2 x x x
W3 x x x
W4 x x
W5 x x
W6 x x x
Pv x x x
Ph x x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = > HENCE OK
= x ( 1 + 6 ) = t/sq mMax comp Stress 18 16 x 0 323 14 102
2.35 /6 0.392 0.323
27.2 18.16 1.498
1.498 2.350 0.323
Sv 18.16
SM 27.202
---
0.360 3.642 3.642 2.100 10.015 1.15 11.517
0.1031 3.642 3.642 2.100 2.871
2.820 1.175 3.314
2.100
1.961.150 2.375 2.100 0.50 2.868 0.683
5.985
1.150 2.375 2.400 0.50 3.28 1.067 3.496
0.600 2.375 2.400 3.420 1.750
Load ParticularsForce
V HMoment
1.750 1.750
12.63 x 0.393
1.750 1.750
1.75 /6 0.292
Max. comp. Stress 12.63 x 0.393
16.008
16.0 12.63 1.268
1.268 1.750 0.393
0.1031
SV 12.63
3.142 3.142 2.100
7.453 0.950 7.0810.3596 3.142 3.142 2.100
0.767 2.513
1.150 2.375 2.100 0.500 2.868 0.383 1.1
1.150 2.375 2.400 0.500 3.28
L.A. MomentV H
3.420 1.450 4.959
unit wt of concrete 2.400
455.625
W3
2.100
W4 W1
1.7500.50
W5
W2
0.30 1.150 0.600
unit wt of earth
0.30 453.25
2.350 452.750
ParticularsForce
2.375
0.77
0.767 1.150 2.100
Load
0.600 2.375
0.3550.500 0.926 0.383
2.137
0.300 3.142
0.767 1.150 0.683 0.633
0.297
2.350 0.500 2.400
8. DESIGN OF HEAD WALLS, WINGS AND RETURNS
0.9262.100 0.50
1.979
---
SM
0.393
16.939
-2.507
L.A.
0.15
2.400
-
8/11/2019 25.875 OT
7/11
2. DESIGN OF WING WALLS (U/S)
= t
= t
+
+
+
Taking moments about A (Stresses in concrete)
W1 x x
W2 x x x
W3 x x x
Pv x x x
Ph x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = < REVISE THE SEC
= x ( 1 + 6 ) = t/sq.m.
Min. Stress = x ( 1 - 6 ) = t/sq.m.
Taking moments about B (Stresses on soil)
W1 x x
W2 x x x
W3 x x x
W4 x x
W5 x x
Pv x x x
Ph x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = > HENCE OK
= x ( 1 + 6 ) = t/sq.m.
0.600
0.60
3.4
2.400
0.50
0.165
/6 0.100
1.57
1.575
1.575
2.400
2.100
0.6725.02
0.600
Max. comp. Stress
0.672 1.200
1.20
0.100
0.500 1.575 2.400
Sv 5.024
1.440 0.6
0.072
/6 0.200 0.072
5.694
1.200 1.200
5.02 x 0.072
0.83 1.006
3.374SM
---
1.200 0.500
0.134 2.075 2.075 2.100 1.212
0.992 0.15 0.149
0.864
0.0384 2.075 2.075 2.100 0.347
0.100 0.50
0.300 1.575 2.100
0.367
0.333
0.650
0.056
L.A. MomentV H
1.229
0.19 0.07
1.890
Load ParticularsForce
10.552
0.600 0.600
2.44 x 0.159 -2.404
0.159
1.121 2.44 0.459
Max. comp. Stress 2.44 x 0.159
S M 1.121
0.7 0.630 0.44
0.459 0.600 0.159
S V 2.444
0.134 1.575 2.100
0.033 0.006
0.0384 1.575 1.57 2.100 0.2 ---
0.100 1.575 2.100 0.500 0.2
0.662
0.100 1.575 2.400 0.500 0.2 0.067 0.013
0.500 1.575 2.400 1.9 0.350
Load ParticularsForce
L.A. MomentV H
2.100
0.600
W5
1.200 452.75
0.50
0.300.300
454.825
unit wt of earth
unit wt of concrete 2.400
W3
W4 W1
W2
453.250.100 0.500
1.575
-
8/11/2019 25.875 OT
8/11
3. DESIGN OF HEAD WALL (D/S)
= t
2:1 = t
W6 +
+
+
Taking moments about A (Stresses in concrete)
W1 x x
W2 x x x
W3 x x x
W6 x x x
Pv x x x
Ph x x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = < REVISE THE SEC
= x ( 1 + 6 ) = t/sq.m.
Min. Stress = x ( 1 - 6 ) = t/sq.m.
Taking moments about B (Stresses on soil)
W1 x x
W2 x x xW3 x x x
W4 x x
W5 x x
W6 x x x
Pv x x x
Ph x x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = > HENCE OK
= x ( 1 + 6 ) = t/sq.m.
---
2.586
0.600 0.400 2.100 0.50
0.051
0.1260.252 0.500
0.741
455.725
W3
unit wt of earth0.40
unit wt of concrete
W1
W2
3.96
453.245
Load Particulars
453.745
1.1000.50
W5
0.300 0.600 0.500
2.376
ForceL.A. Moment
V H
0.850 2.02
1.43 0.400 0.5710.600 1.980 2.400 0.500
0.200 0.250.600 1.980 2.100 0.500
2.380 2.380 2.100
1.247
0.500 0.252
4.941
0.792 2.049
0.0623
S V 6.042
0.2174 2.380 2.380 2.100
0.818 1.100 0.268
S M
1.10 /6 0.183 0.268
4.9 6.04 0.818
0.268 -2.537
Max. comp. Stress 6.04 x 0.268
1.100 1.100
Load ParticularsForce
13.522
1.100 1.100
6.04 x
0.500 1.980 2.400 2.376
L.A. MomentV H
0.600 1.980 2.400 0.50 1.430.500 0.624
1.150 2.733
0.700
0.300 2.380 2.100
0.9980.600 1.980 2.100 0.50 1.247
1.499 0.15 0.225
1.700 0.500 2.400 2.040 0.85 1.734
0.805 ---0.0623 2.480 2.480 2.100
2.808 0.992 2.7860.217 2.480 2.480 2.100
SM 9.226
9.2 9.65 0.957
Sv 9.645
0.957 1.700 0.107
1.70 /6 0.283 0.107
Max. comp. Stress 9.65 x 0.107 7.816
1 700 1 700
2.400
2.100
0.600 0.400 2.100
0.500 1.980 2.400
1.700
0.30
W4
0.200
1.980
-
8/11/2019 25.875 OT
9/11
4. DESIGN OF WING & RETURN WALLS (D/S)
= t
= t
+
+
+
Taking moments about A (Stresses in concrete)
W1 x x
W2 x x x
W3 x x x
Pv x x x
Ph x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = < REVISE THE SEC
= x ( 1 + 6 ) = t/sq.m.
Min. Stress = x ( 1 - 6 ) = t/sq.m.
Taking moments about B (Stresses on soil)
W1 x x
W2 x x xW3 x x x
W4 x x
W5 x x
Pv x x x
Ph x x
Lever arm = M / V = / = m
Eccentricity = - /2 = m
Permissible 'e' = = > HENCE OK
= x ( 1 + 6 ) = t/sq.m.
unit wt of concrete 2.400
W4 W1
W2
unit wt of earth 2.100
455.725
W3
453.745
0.8000.50
W5
0.300 0.300 0.500 0.30
MomentV H
1.400 453.245
Load Particulars
0.500 1.980 2.400 2.376
ForceL.A.
0.550 1.307
0.300 1.980 2.400 0.500 0.71 0.200 0.143
0.300 1.980 2.100 0.500 0.624 0.100 0.063
0.316 ---0.0384 1.980 1.980 2.100
1.103 0.792 0.8740.134 1.980 1.980 2.100
S M 2.387
2.4 4.03 0.593
S V 4.029
Max. comp. Stress 4.03 x 0.193 12.325
0.593 0.800 0.193
0.80 /6
0.800 0.800
4.03 x 0.193
0.1930.133
-2.254
0.800 0.800
Load ParticularsForce
L.A. MomentV H
0.500 1.980 2.400 2.376 0.850 2.02
0.71 0.500 0.3570.300 1.980 2.400 0.500.624 0.400 0.250.300 1.980 2.100 0.50
0.7 1.176
0.300 1.980 2.100
2.480 2.100
1.247 0.15 0.188
1.400 0.500 2.400 1.680
1.7170.134 2.480 2.480 2.100
---0.0384 2.480
Max. comp. Stress 7.14 x
SM
0.8 1.400 0.100
1.40 /6 0.233
7.2810.100
1.400 1.400
Sv 7.136
1.731
5.7 7.14 0.8
0.100
0.992
0.496
5.708
1.980
-
8/11/2019 25.875 OT
10/11
Sl STRESS TABLE Concrete Soil
no
1 HEAD WALL U/S
Min. Stress
2 WING WALL U/S
Min. Stress
3 HEAD WALLS D/S
Min. Stress
4 WING & RETURN
WALLS Min. Stress
3.531-2.537
7.81613.522Max. comp. Stress
2.679
Max. comp. Stress
t / Sqm
5.69410.552Max. comp. Stress
2.913-2.254
-2.507
7.28112.325
-2.404
Max. comp. Stress
1.355
t / Sqm
14.10216.939
-
8/11/2019 25.875 OT
11/11
S.NO PAGE NO
I 1
II
3
3
4
4
4
4
5
6
III
DESIGN OF OFF-TAKE (12L) @ km 17.350
GENERAL PLAN AND SECTION
DESCRIPTION
NOTE ON DESIGN FEATURES
DESIGN CALCULATIONS
1. HYDRAULIC PARTICULARS OF CANAL/OT
2. VENT WAY
3. HOIST PLATFORM LEVEL
8. DESIGN HEADWALLS, WINGS & RETURNS
DRAWINGS
4. LENGTH BARREL
5. PROTECTION WORK
6. UPSTREAM TRANSITION
7. DOWNSTREAM TRANSITION