210 x 297mm TRANSMISSION CAPITAL DELIVERY/media/Files/N/National-Grid-IR/... · Connection Project...
Transcript of 210 x 297mm TRANSMISSION CAPITAL DELIVERY/media/Files/N/National-Grid-IR/... · Connection Project...
![Page 1: 210 x 297mm TRANSMISSION CAPITAL DELIVERY/media/Files/N/National-Grid-IR/... · Connection Project National Grid is expecting to invest around £1 billion to reengineer high voltage](https://reader034.fdocuments.in/reader034/viewer/2022042309/5ed5bb3b5678bb60ef405080/html5/thumbnails/1.jpg)
210 x 297mm
September 2014
TRANSMISSION
CAPITALDELIVERYHinkley Point CConnection Project
National Grid is expecting to invest
around £1 billion to reengineer high
voltage electricity lines in the
Southwest of England. Hinkley Point C
nuclear station and a new, gas fired
station at Seabank will add 4.5GW of
new generation, driving this need.
Passing through sensitive areas of
outstanding natural beauty, the project
will involve the use of new technology
(T-pylons), underground cables (8.5km)
and existing rights of way. The Hinkley
Point C Connection Project solves a
key energy issue in an innovative way.
�
�
�
�
Collaborative design process promoting
innovative solutions to address visual
amenity and environmental considerations
Extensive planning challenges met by upfront
stakeholder engagement
National Grid’s first ‘Strategic Wider Works’
project
Planning strategies applicable to future major
infrastructure development projects
RE REORGANISING NEGOTIATING
REENGINEERING
![Page 2: 210 x 297mm TRANSMISSION CAPITAL DELIVERY/media/Files/N/National-Grid-IR/... · Connection Project National Grid is expecting to invest around £1 billion to reengineer high voltage](https://reader034.fdocuments.in/reader034/viewer/2022042309/5ed5bb3b5678bb60ef405080/html5/thumbnails/2.jpg)
210 x 297mm
Hinkley Point C Connection Project
Project map
Project timeline
Engineering our future networks
�
�
�
The T-pylon, winner of an International Competition
held in 2011 by the department of Energy and
Climate Change (DECC), the Royal Institute of British
Architects (RIBA) and National Grid, is being used on
this project
Launched to help identify what the next generation
of pylon might look like, the competition attracted
250 entries from around the world
At approximately 35m, the winning design by Danish
architects Bystrup, is around 10–15m shorter than a
traditional 400kV steel lattice pylon
Stakeholder engagement drives innovation
�
�
�
�
�
�
Under the 2008 Planning Act, the Hinkley project required
significant up-front planning and community engagement
and consultation
National Grid debuted community ‘pop-up’ shops to
communicate with stakeholders
Engagement led to the development of lower, more visually
appealing T-pylons
Plan involves using existing rights of way, new design and
underground cables in sensitive areas to reduce impact to
the community and environment
249 pylons will be removed and replaced by only 141
Learnings from this process will be applied to future
Nationally Significant Infrastructure Projects
Estimated £1 billion programme
�
�
�
�
�
�
Construction of a 57km 400kV electricity transmission
connection made up of 48.5km of overhead line (109 T-
pylons and 8.5km of underground cable)
Construction of a new 400/132kV substation at Sandford,
North Somerset
Extension of the existing 400kV substation at Seabank
Modifications to existing overhead lines at Hinkley Point
Construction of three 400kV cable sealing end (CSE)
compounds along the route of the connection
Modifications to 132kV substations at Churchill, Portishead,
Avonmouth and Seabank
2009 2010 2011 2012 2013 2014 2015
Development of plans and consultation Application Construction
Formally examine the application and make a decision
The Planning Inspectorate formally examines the application and makes a recommendation tothe Secretary of State for Energy and Climate Change – the final decision rests with them
Examination anddecision
2016–2022