Why Commercial Equipment Finance Suppliers Should Offer Financing
2016 Commercial and Industrial Standard Offer … › en-us › Documents › 2016...2016 Commercial...
Transcript of 2016 Commercial and Industrial Standard Offer … › en-us › Documents › 2016...2016 Commercial...
2016 Commercial and Industrial
Standard Offer Program
Program Manual
Version 16.0
December 2015
For program inquiries, contact:
Yolanda Slade
Standard Offer Program Manager
CenterPoint Energy
1111 Louisiana
9th Floor
Houston, TX 77002 [email protected]
Nexant Inc. Standard Offer Program Administrator
1331 Lamar Street, Suite 1575
Houston, TX 77010
Updates to this manual and program enrollment materials will be provided at
https://centerpoint.anbetrack.com/
Program Manual v 16 Table of Contents
2016 Commercial Standard Offer Program
CenterPoint Energy Table of Contents - 2 -
CenterPoint Energy
2016 C&I Standard Offer Program
Table of Contents
PROGRAM GUIDELINES & PARTICIPATION ...................................................................................... 6 SECTION 1.
1. GENERAL PROGRAM GUIDELINES ..................................................................................................... 7
1.1 INTRODUCTION ........................................................................................................................................ 7
1.2 BACKGROUND .......................................................................................................................................... 7
1.3 PROGRAM GOALS ..................................................................................................................................... 8
1.4 2016 INCENTIVE TABLE ........................................................................................................................... 8
1.5 KEY CHANGES FOR 2016 .......................................................................................................................... 9
1.6 ELIGIBILITY ........................................................................................................................................... 10
1.7 INCENTIVES ............................................................................................................................................ 17
2. PARTICIPATION PROCESS .................................................................................................................. 18
2.1 OVERVIEW ............................................................................................................................................. 18
2.2 PHASES OF PARTICIPATION .................................................................................................................... 18
2.3 OTHER INFORMATION ............................................................................................................................ 27
MEASUREMENT AND VERIFICATION GUIDELINES FOR RETROFIT PROJECTS .................................. 30 SECTION 2.
3. INTRODUCTION TO MEASUREMENT AND VERIFICATION FOR RETROFIT PROJECTS ...... 31
3.1 OVERVIEW ............................................................................................................................................. 31
3.2 MEASUREMENT APPROACHES ................................................................................................................ 31
3.3 STEPS IN THE M&V PROCESS ................................................................................................................. 33
4. MEASUREMENT GUIDELINES FOR LIGHTING EFFICIENCY AND CONTROLS ....................... 34
4.1 OVERVIEW ............................................................................................................................................. 34
4.2 PRE-INSTALLATION M&V ACTIVITIES ................................................................................................... 34
4.3 POST-INSTALLATION M&V ACTIVITIES ................................................................................................. 35
4.4 OPERATING HOURS ................................................................................................................................ 36
4.5 CONTROLS ............................................................................................................................................. 41
4.6 CALCULATION OF DEMAND AND ENERGY SAVINGS ............................................................................... 42
5. MEASUREMENT GUIDELINES FOR REPLACEMENT OF COOLING EQUIPMENT ................... 44
5.1 OVERVIEW ............................................................................................................................................. 44
5.2 DEEMED SAVINGS FOR COOLING EQUIPMENT ........................................................................................ 44
5.3 SIMPLIFIED MEASUREMENT FOR COOLING EQUIPMENT ......................................................................... 52
5.4 FULL MEASUREMENT FOR COOLING EQUIPMENT .................................................................................. 55
6. MEASUREMENT GUIDELINES FOR CONSTANT LOAD MOTOR MEASURES ............................ 61
Program Manual v 16 Table of Contents
2016 Commercial Standard Offer Program
CenterPoint Energy Table of Contents - 3 -
6.1 OVERVIEW ............................................................................................................................................. 61
6.2 PRE-INSTALLATION MEASUREMENT ACTIVITIES ................................................................................... 62
6.3 POST-INSTALLATION MEASUREMENT ACTIVITIES ................................................................................. 63
6.4 CALCULATION OF PEAK DEMAND AND ENERGY SAVINGS ..................................................................... 64
7. PRESCRIPTIVE PROGRAM: PREMIUM EFFICIENCY MOTORS ................................................... 66
7.1 QUALIFYING EQUIPMENT ....................................................................................................................... 66
7.2 SAVINGS CALCULATIONS ....................................................................................................................... 66
8. MEASUREMENT GUIDELINES FOR VARIABLE SPEED DRIVES ON CONSTANT BASELINE
MOTOR MEASURES........................................................................................................................................ 68
8.1 OVERVIEW ............................................................................................................................................. 68 8.2 HVAC VARIABLE FREQUENCY DRIVE (VFD) ON AIR HANDLER UNIT (AHU) SUPPLY FANS DEEMED
METHOD........................................................................................................................................................... 69
9. MEASUREMENT GUIDELINES FOR APPLICATION OF WINDOW FILMS .................................. 70
9.1 OVERVIEW ............................................................................................................................................. 70
9.2 PRE-INSTALLATION M&V ACTIVITIES ................................................................................................... 70
9.3 POST-INSTALLATION M&V ACTIVITIES ................................................................................................. 71
9.4 CALCULATION OF ENERGY SAVINGS ...................................................................................................... 71
10. MEASUREMENT AND VERIFICATION FOR GENERIC VARIABLE LOADS ................................ 74
10.1 OVERVIEW ............................................................................................................................................. 74
10.2 PRE-INSTALLATION M&V ACTIVITIES ................................................................................................... 74
10.3 POST-INSTALLATION M&V ACTIVITIES ................................................................................................. 76
10.4 CALCULATION OF DEMAND AND ENERGY SAVINGS ............................................................................... 77
10.5 PROJECT-SPECIFIC M&V ISSUES............................................................................................................ 79
11. MEASUREMENT AND VERIFICATION USING BILLING ANALYSIS AND REGRESSION
MODELS ............................................................................................................................................................ 80
11.1 OVERVIEW ............................................................................................................................................. 80
11.2 BASELINE AND POST-RETROFIT DATA COLLECTION .............................................................................. 80
11.3 CALCULATION OF ENERGY SAVINGS: MULTIVARIATE REGRESSION METHOD ....................................... 81
11.4 PROJECT SPECIFIC M&V ISSUES ............................................................................................................ 83
12. MEASUREMENT AND VERIFICATION USING CALIBRATED SIMULATION ANALYSIS ......... 84
12.1 OVERVIEW ............................................................................................................................................. 84
12.2 BASELINE AND POST-RETROFIT DATA REQUIREMENTS ......................................................................... 85
12.3 CALCULATION OF ENERGY SAVINGS ...................................................................................................... 85
12.4 PROJECT-SPECIFIC M&V ISSUES............................................................................................................ 90
MEASUREMENT AND VERIFICATION GUIDELINES FOR NEW CONSTRUCTION PROJECTS ............... 91 SECTION 3.
13. INTRODUCTION TO MEASUREMENT AND VERIFICATION FOR NEW CONSTRUCTION
PROJECTS ........................................................................................................................................................ 92
13.1 OVERVIEW ............................................................................................................................................. 92
13.2 MEASUREMENT APPROACHES ................................................................................................................ 92
13.3 DEVELOPING PROJECT-SPECIFIC M&V PLANS ...................................................................................... 94
Program Manual v 16 Table of Contents
2016 Commercial Standard Offer Program
CenterPoint Energy Table of Contents - 4 -
14. MEASUREMENT GUIDELINES FOR LIGHTING EFFICIENCY AND CONTROLS ....................... 95
14.1 OVERVIEW ............................................................................................................................................. 95
14.2 PRE-INSTALLATION M&V ACTIVITIES ................................................................................................... 95
14.3 POST-INSTALLATION M&V ACTIVITIES ................................................................................................. 96
14.4 OPERATING HOURS ................................................................................................................................ 98
14.5 CALCULATION OF DEMAND AND ENERGY SAVINGS ............................................................................. 104
15. MEASUREMENT GUIDELINES FOR HIGH-EFFICIENCY COOLING EQUIPMENT.................. 106
15.1 OVERVIEW ........................................................................................................................................... 106
15.2 DEEMED SAVINGS FOR COOLING EQUIPMENT ...................................................................................... 106
15.3 SIMPLIFIED M&V FOR COOLING EQUIPMENT ...................................................................................... 113
15.4 FULL MEASUREMENT FOR COOLING EQUIPMENT ................................................................................ 115
16. MEASUREMENT GUIDELINES FOR CONSTANT LOAD MOTOR MEASURES .......................... 121
16.1 OVERVIEW ........................................................................................................................................... 121
16.2 PRE-CONSTRUCTION ACTIVITIES ......................................................................................................... 121
16.3 POST-CONSTRUCTION ACTIVITIES ....................................................................................................... 122
16.4 CALCULATION OF MOTOR OPERATING HOURS .................................................................................... 123
16.5 CALCULATION OF PEAK DEMAND AND ENERGY SAVINGS ................................................................... 123
17. PRESCRIPTIVE PROGRAM: PREMIUM EFFICIENCY MOTORS ................................................. 124
17.1 QUALIFYING EQUIPMENT ..................................................................................................................... 124
17.2 SAVINGS CALCULATIONS ..................................................................................................................... 124
18. MEASUREMENT AND VERIFICATION FOR GENERIC VARIABLE LOADS .............................. 126
18.1 OVERVIEW ........................................................................................................................................... 126
18.2 DOCUMENTING BASELINE CHARACTERISTICS...................................................................................... 126
18.3 DOCUMENTING POST-CONSTRUCTION CHARACTERISTICS ................................................................... 128
18.4 CALCULATION OF DEMAND AND ENERGY SAVINGS ............................................................................. 128
18.5 PROJECT-SPECIFIC M&V ISSUES.......................................................................................................... 130
19. MEASUREMENT AND VERIFICATION USING CALIBRATED SIMULATION ANALYSIS ....... 131
19.1 OVERVIEW ........................................................................................................................................... 131
19.2 SOFTWARE SELECTION ......................................................................................................................... 132
19.3 DEVELOPING A CALIBRATED SIMULATION STRATEGY ......................................................................... 132
19.4 DATA COLLECTION .............................................................................................................................. 132
19.5 BUILDING SIMULATION MODELS ......................................................................................................... 133
19.6 PROJECT-SPECIFIC M&V ISSUES.......................................................................................................... 136
APPENDIX ................................................................................................................................... 138 SECTION 4.
A. STANDARD COOLING EQUIPMENT TABLES ..................................................................................... 139
B. TABLE OF STANDARD MOTOR EFFICIENCIES TABLE ................................................................... 150
C. DEEMED DEMAND AND ENERGY SAVING FOR VFD ON AHU SUPPLY FANS ............................. 152
D. CENTRAL WATTAGE TABLE ................................................................................................................. 155
E. EM&V SAMPLING GUIDELINE .............................................................................................................. 227
Program Manual v 16 Table of Contents
2016 Commercial Standard Offer Program
CenterPoint Energy Table of Contents - 5 -
F. PROGRAM AND M&V DEFINITIONS .................................................................................................... 229
G. M&V EXAMPLE ........................................................................................................................................ 233
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 6 -
Program Guidelines & Participation Section 1.
This document describes the CenterPoint Energy 2016 C&I Standard Offer Program. It includes
information about the program eligibility requirements, incentive payments, and the participation process.
The information included in this Program Manual is also available on the program Web site at
https://centerpoint.anbetrack.com/
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 7 -
1. General Program Guidelines
1.1 Introduction
The 2016 C&I Standard Offer Program was developed by CenterPoint Energy to provide incentives for
the installation of a wide range of measures that reduce peak demand and save energy in non-residential
facilities. Incentives are paid on the basis of deemed savings or verified demand and energy savings that
occur at CenterPoint Energy commercial and industrial customers’ facilities. This program has been
developed to comply with Texas’ energy efficiency goals.
Participants in the 2016 C&I Standard Offer Program must meet minimum eligibility criteria, comply
with all program rules and procedures, submit documentation describing their projects, and enter into a
Standard Agreement with CenterPoint Energy.
Chapter 1 provides a general introduction to the C&I Standard Offer Program, including an overview of
program features and guidelines, and background information. Chapter 2 provides more detail on the
program process, and project savings measurement and verification (M&V) requirements. All program
information, including application materials, will be available on the World Wide Web at the C&I
Program Web site, https://centerpoint.anbetrack.com/. The program will accept proposed project
applications starting January 4, 2016 until program incentives are fully reserved. The first day to
submit a project is January 4, 2016 at 8:00 am CDT. No Large Commercial projects will be eligible for
submittal without complete on line application and receipt of 5% deposit.
1.2 Background
In 1999, the Texas Legislature passed Senate Bill 7 (SB7), which restructures the state's electric utility
industry. The bill requires each investor-owned electric utility to reduce Texas customers' energy
consumption by a minimum of 10% of the utility's annual growth in demand each year. Utilities must
achieve this goal through standard offer programs or limited target market transformation programs that
will result in reduced energy consumption.
In March of 2000, the Public Utilities Commission of Texas (PUCT) passed Substantive Rule §25.181,
which implements the energy efficiency goal of SB7. Interested parties, the state's investor-owned
utilities, and PUCT staff then developed templates for energy efficiency programs that were adopted and
are offered and administered throughout Texas by the investor-owned utilities.
In September of 2007, House Bill 3693 set new Energy Efficiency Goals for electric utilities in Texas.
The bill requires each investor-owned electric utility to reduce Texas customers' energy consumption by a
minimum of 30% of the utility's annual growth in 2014. Utilities must achieve this goal through standard
offer programs or limited target market transformation programs that will result in reduced energy
consumption.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 8 -
1.3 Program Goals
While the main goal of the program is to reduce peak demand at CenterPoint Energy distribution
customer sites and reach the demand reduction goals established by Senate Bill 1125 there are secondary
program goals that are reflected in the program rules and procedures, including:
Encourage private sector delivery of energy efficiency products and services.
Encourage customer energy and bill savings.
Stimulate investment in efficient technologies most likely to reduce CenterPoint Energy’s peak
capacity requirements during 2016.
Create a simple and streamlined program process, to stimulate strong program participation from
energy service providers.
Minimize the burden of M&V requirements associated with standard offer programs by offering
deemed or simple savings calculations for many measures.
Diversify portfolio to include non-traditional measures which hardly or never appear in the program.
1.4 2016 Incentive Table
CenterPoint Energy’s C&I Standard Offer Program provide standard incentive based on the type of
measure. The standard variable incentive rates are listed in Table 1 below.
Table 1. Standard Variable Incentive Rates
Measure Type $/kW $/kWh
Lighting – Fluorescent, HID, CFL,
Screw in LED1
105 0.03
Lighting – LED (non-screw in) 180 0.06
Cooling – DX units 265 0.10
Cooling – Chiller 285 0.11
Motor 180 0.07
VFD 180 0.07
Window film 175 0.06
Roofing 240 0.09
All other measures 175 0.06
1 Screw in LEDs are “plug-and-play” lamps that do not require replacement of the whole fixture to install. Examples
are Edison base fixtures, pin base fixtures, or fluorescent LED replacements that do not remove the ballast.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 9 -
1.5 Key Changes for 2016
To reflect the changes in the Technical Resource Manual (TRM) and general program recommendations,
as advised by the Public Utility Commission of Texas (PUCT), there are several key changes in the
program rules and procedures for 2016 comparing with the previous year’s programs, which include:
Audit and application corrections will no longer be a part of the project review. Any input in audits
(workbooks) and applications is the sole responsibility of the Project Sponsor
Project Sponsors are required to give 48 hour notice to CenterPoint Energy before the start of
installation of any measure in the Program. This can be accomplished by entering a work schedule in
eTrack. Failure to provide required notification will result in project forfeiture
Added two additional LED qualification organizations for LED retrofits—Lighting Design Labs
(LDL) and DOE LED Lighting Facts
Chiller projects are required to show proof of chiller purchase within 30 days of project approval
Removed fluorescent to fluorescent lamp replacement projects with no ballast change out (known as
relamping) from consideration under the program.
Changes to remain in effect are as follows:
All deposit checks must be mailed by authorized postal service. Checks should be addressed to:
Loretta Battles, 1111 Louisiana, Houston, TX 77002
Multiple sponsor requested inspections (of any type) will result in charge to Project Sponsor; unless
there is a CNP/designee inspection error.
The additional inspection rate will be $250 The calculated amount will be deducted from the
anticipated deposit return.
Small projects will have a milestone method to avoid project cancellations
After submittal, an email will be sent for follow up documentation, there will be 5 days to
respond, after which, there will be 1 phone call to request information with a 5 day response
window. At the end of the 10th day, a final email will be sent noting the project cancellation date
if information is not received in 5 days.
Installation completion before the submittal of an application is disqualified for incentives.
Variable incentive rates for LED lighting, non-LED lighting, chiller, DX Units, Motor, VFD, and
building envelop. Fixed incentive rates for all other measures.
LED installs will receive incentive by type; screw in and non-screw in, see incentive table for
appropriate rates
Project Sponsors will submit a screenshot, showing the model number, of a LED fixture on the
DesignLights Consortium™ , Lighting Design Labs (LDL), DOE LED Lighting Facts, or Energy
Star© qualified product list as secondary documentation to the cut sheets.
Standard T8 becomes minimum efficiency requirement for post retrofit lighting fixtures.
Recycling of lamps for lighting projects is required. A certificate indicating the quantity and building
the lamps were removed from is required in order for incentives to be paid out.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 10 -
For commercial HVAC measures, the baseline for the “Early Retirement” project will be set by the
age of the replaced system, while the baseline efficiency for the “Replacement on Burnout” and “New
Construction” is set by the Federal or manufacturer Standard.
Part load efficiency levels of the new cooling equipment, whenever applicable standard is available,
will be required.
All projects will require a copy of the final installation invoice. No project will be incentivized more
than 50% of installed cost.
LED projects shall require at least one of the following:
Energy Star © qualified
NEEP DesignLights Consortium™ qualified
Lighting Design Lab qualified
DOE LED Lighting Facts qualified
Cut sheets, square footage and all pertinent documents are due at the time of project submittal
1.6 Eligibility
1.6.1 Project Sponsor
Any entity that installs eligible energy efficiency measures at a facility with non-residential electricity
distribution service provided by CenterPoint Energy is eligible to participate in the 2016 C&I Standard
Offer Program as a Project Sponsor. Eligible Project Sponsors may include:
National or local energy service companies (ESCOs).
Local contractors.
National or local companies that provide energy-related services or products (such as lighting or
HVAC equipment).
Commercial property developers.
Design/build firms.
Architectural and engineering firms.
Individual customers who install measures in their own facilities.
To ensure that the program’s incentive budget is allocated to projects that are likely to meet with success,
all Project Sponsors will be required to demonstrate a commitment to fulfilling program objectives and
competency in completing projects. Project Sponsors will be required to submit the following
information as part of the program process:
A description of the Project Sponsor firm, including relevant experience, areas of expertise and
references. A work plan that covers the design, implementation, operation, and management of the
project.
A refundable application deposit.
Upon request, the following must be made available:
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 11 -
Proof of applicable insurance, licenses, and permits2.
Evidence of good credit.
CenterPoint Energy will also consider a Project Sponsor’s performance in past or current CenterPoint
Energy’s energy efficiency programs. A poor performance history may jeopardize a Project Sponsor’s
acceptance for participation in the 2016 C&I Standard Offer Program.
The following requirements must be noted for all sponsors:
CenterPoint Energy will conduct correspondence only with representatives from the Project
Sponsor’s organization listed in the Standard Offer Contract
A representative of the Project Sponsor must register as the primary contact in the online database
system ETrack.
No more than 5 representatives per company may have logins in the ETrack website
Absolutely no third party companies will act as an intermediary for correspondence between
CenterPoint Energy and the Project Sponsor
1.6.2 Host Customer
Customers located within CenterPoint Energy’s service territory may qualify to participate in the program
if they are:
any commercial and industrial customer taking service at a metered point of delivery at a distribution
voltage (<69 kVA) under an electric utility’s tariff during the prior calendar year or
a non-profit customer or
a government entity or
an educational institution
Large Commercial Customer: Owns or operates a single site with a total maximum peak demand of
more than 100 kW or multiple sites with a combined maximum peak demand greater than 250 kW
Small Commercial Customer: Owns or operates a single site with a total maximum peak demand of
less than 100 kW or multiple sites with a combined maximum peak demand no greater than 250 kW
Participant customers may host a project developed by a qualified Project Sponsor or choose to sponsor a
project independently. The host customer’s responsibilities include:
A 5% refundable deposit will be required with each Large Commercial application.
Entering into an agreement with the selected Project Sponsor.
Providing reasonable access to project facilities for inspection both before and after project
completion.
1.6.3 Project
A project is defined as a set of proposed or installed measures at an eligible site or combination of sites.
All projects must meet the following requirements:
For Large Commercial customers, each project of one site must provide a total estimated peak
demand reduction of at least 20 kW or annual energy savings of at least 120,000 kWh, and each
2 Not required of customers who install measures in their own facilities.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 12 -
project of multiple sites must provide at total estimated peak demand reduction of at least 50 kW or
annual energy savings of at least 300,000 kWh. This limitation is included to ensure that projects
contribute to the primary program goal of reducing peak demand and to minimize the administrative
costs associated with smaller projects.
If the measures and sites proposed are all similar, one project may involve the installation of measures
at multiple customer sites. For example, installation of measures at a chain of department stores may
include more than one customer site, but may constitute a single project. These sites would share a
common M&V plan. All sites and measures must be installed before the first payment will be made.
There are advantages and disadvantages to bundling project sites in this manner. Contact the program
administrator for more information.
For projects with incentives paid on the basis of verified demand and energy savings, peak demand
savings must be measured within the peak demand period. M&V of energy savings may continue for
up to 12 months and carry into the following year.
Comprehensive projects that include a range of measure types are encouraged.
New construction projects must demonstrate compliance with local, state or federal codes, whichever
is more stringent. Projects using the Energy Cost Budget Method to demonstrate code compliance
will be considered for program participation on a case-by-case basis.
1.6.4 Small Commercial Projects
Projects for Small Commercial facilities are expected to have a reduced scope of work. As such, the
participation requirements in the program are simpler and outlined in this section. Small commercial
projects:
Must include facilities with a maximum peak demand of less than 100 kW (or 250 kW combined
for multiple sites in the same project).
Do not have a minimum savings requirement.
Are not required to submit a deposit to CenterPoint Energy when submitting an application.
Are limited to deemed savings calculations only.
Require Sponsors to answer CenterPoint Energy inquiries in a timely manner, typically 5 days.
Failure to respond within the time period may result in cancellation of the project.
Must complete project within the program year.
1.6.5 General Project Deliverable Requirements
The following presents the minimum deliverables needed from the Sponsors in order to fully complete a
project. This list is presented in order and should be used as a guideline for any next steps in a project.
CenterPoint, at its discretion, may make changes to this section anytime during the program year or
require more information from a Sponsor on a specific project.
Sponsors indicate in eTrack that they have read and understand the current program manual.
Upload any vendor forms (tax documents, etc.) to eTrack.
Sign the CenterPoint Energy participation contract agreeing to the terms of SOP. This is not done
by eTrack and will be sent by email.
Complete an application in eTrack.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 13 -
Sponsors are required to ensure any project savings information is accurate. For example,
Sponsors should audit the lamp counts and wattages for any lighting project to ensure accuracy.
Failure to comply with this rule may result in reduction of the deposit returned or incentives.
Send the project deposit to CenterPoint Energy (Large Commercial projects only). The deposit is
5% of the requested incentives and is fully refundable if a majority of the savings is realized.
Upload the project documentation to eTrack. Projects require any cutsheets, calculation tools,
lamp qualifications, and M&V plans to be uploaded for CenterPoint review.
Receive project approval letter from CenterPoint Energy via email. Projects must not start
installation until this letter is received by the Sponsor.
Sign and return the PA authorization form included in the project approval letter.
Enter the work schedule in eTrack. Access to current equipment and new materials should be
onsite ready for CenterPoint Energy inspection.
During the inspection, a representative of the building should be available to sign an inspection
form indicating the inspection took place.
Complete installation of measures and notify CenterPoint Energy in eTrack when installation is
complete.
If needed, conduct any M&V.
Be available for a post-installation inspection.
Submit invoices and lamp recycling certificates.
It is imperative that Sponsors follow the above steps during the project process. Failure to adhere these
steps may result in adjustments to the project incentives or cancellation of the project and forfeiture of the
deposit.
1.6.6 Measure
Most energy-efficiency measures in retrofit or new construction applications that reduce electric energy
consumption and peak demand are eligible for the C&I Standard Offer Program. CenterPoint Energy does
not specify eligible measures in order to provide Project Sponsors flexibility in packaging services.
Therefore, Project Sponsors may propose the inclusion of any measure in their project that meets the
following requirements:
Measure may produce a measurable and verifiable electric demand reduction during the peak
period(s) or may reduce electricity consumption, or may produce both peak demand and energy
savings.
Measure must produce savings through an increase in energy efficiency or a substitution of another
energy source for electricity supplied through the transmission and distribution grid.
Measure must exceed minimum equipment standards as established in the Program Manual (located
in manual Appendices).
Measures may provide for self-generation through the use of renewable technologies, such as
Solar
Wind
Geothermal
Hydroelectric
Wave/tidal
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 14 -
Biomass
At least 75% occupancy ratio of the building is required.
Projects involving combined heat and power (CHP) will be reviewed on a case-by-case basis for
qualification by CenterPoint Energy
The following measures are excluded from consideration in the program:
Measures that involve plug loads, e.g. office equipment.
Measures that rely on changes in customer behavior and require no capital investment.
Measures that achieve savings through equipment maintenance, recommissioning or operational
changes, without an equipment efficiency upgrade.
Measures that result in negative environmental or health effects.
Measures that involve fuel-switching to electric.
Measures that receive an incentive through any other energy efficiency program offered by
CenterPoint Energy.
In general, project incentives will be paid only for energy and demand savings directly related to end-use
equipment installed as part of the project. Measures that generate savings from interactive effects between
end-use equipment will be considered on a case-by-case basis. The exception is that savings due to
interactive effects between lighting and a space-cooling measure are eligible based on a stipulated value
in cases where lighting measures have been installed in a cooled space as part of the project.
Table 2 Provides examples of eligible measures. CenterPoint Energy will consider any measures that are
not listed in Table 2 for program eligibility on a case-by-case basis.
Table 2. Examples of Eligible Measures and Projects
Eligible Measure Applicable M&V Methodology*
Chiller replacement Deemed, Simplified, Full
Packaged cooling unit replacement Deemed, Simplified, Full
Constant air to variable air-side conversions Simplified, Full
Fan and pump motor efficiency upgrades Deemed, Simplified, Full
Fan and pump variable speed drive (VSD) installations Simplified, Full
Heat pipes, enthalpy wheel and other forms of energy recovery Simplified, Full
High-efficiency fluorescent lighting that replaces less efficient
lighting Deemed, Simplified
Exterior lighting under a roof/ceiling (e.g. loading dock) Deemed
Exterior lighting, e.g. parking lot Deemed,
Lighting controls to reduce operating hours Deemed, Simplified
CFLs with hard-wired ballasts or permanent socket conversions Deemed, Simplified
Air cooling and refrigeration compressor replacement Simplified, Full
Refrigerated case doors Simplified, Full
Motor-efficiency upgrades Deemed, Simplified, Full
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 15 -
Cogeneration projects Simplified, Full
Renewable technologies (solar, wind, tidal, geothermal, etc) Simplified, Full
Fuel switching from electric to gas (net energy use must decrease,
e.g. gas-fired booster heaters in dishwashers) Simplified, Full
Cooling towers Simplified, Full
*M&V method must be approved by CenterPoint Energy
Examples of ineligible measures include:
Screw-in CFLs with no socket conversion
Delamping
Electric equipment with decoupled self-generation
Fuel switching to electric
Load reductions caused by building vacancies, decreased production, or other changes in occupant
characteristics or behavior
Measures that decrease building plug loads, such as computer inactivity time-out controls
Load shifting
Operations & Maintenance measures such as filter change-outs in air-handling units, cleaning of
cooling coils, etc
1.6.7 Efficiency Standards
The C&I Standard Offer Program is designed to encourage electric energy-efficiency improvements that
go above and beyond the efficiency gains typically achieved in retrofit or replacement projects.
Consequently, energy and demand savings credit will be based only on reductions that exceed current
industry accepted minimum efficiency standards, if such standards apply. In cases where standards do not
exist, savings credit will be based on improvements relative to a customer’s energy use prior to
participating in the program.
Cooling Equipment
If the project is to replace the burnout cooling equipment with new equipment, the baseline efficiency
level will be current City of Houston Commercial Energy Conservation Code or Federal Standard
whichever is more stringent.
If the project is to replace the early-retired cooling equipment with more efficient equipment, the baseline
efficiency will be the applicable ASHRAE 90.1 efficiency standard of the year when the replaced system
is manufactured.
Lighting Equipment
Post-retrofit systems using T-12 electronic ballasts or standard T8 electronic ballasts are not eligible for
incentives and all post-retrofit technologies must use reduced wattage T-8 systems or high performance
T-8 systems and meet the High Performance and Reduced Wattage lamp and ballast efficiency
specifications developed by the Consortium for Energy Efficiency (CEE) as published on the CEE
website. This will be a requirement for all T8 systems.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 16 -
LED fixtures are required to be on the DesignLights Consortium™ , Lighting Design Labs (LDL), DOE
LED Lighting Facts, or Energy Star© qualified product list.
The lighting fixtures which will be ineligible for incentives are listed in Table 3 below.
Table 3. Ineligible Lighting Fixtures
Incandescent
Screw-in CFL w/o socket conversion
T8 (non-CEE) w/ Magnetic Ballast
T8 (non-CEE) w/ Electric Ballast
T12
HPS, Mercury Vapor - all wattages
PSMH (Pulse Start Metal Halide) fixtures less than 500
watts
Standard MH probe-start fixtures
Table 4 and Table 5 list applicable baseline standards for Retrofit and New Construction projects.
Regardless of whether the project is a retrofit or a new construction application, the newly installed
equipment must exceed the current City of Houston C&I Energy Conservation Code, in order to qualify
for incentives.
Table 4. Baseline equipment efficiency standards for Retrofit projects
Equipment Type Applicable Baseline Standard
Cooling Equipment - (Early
Retirement)
Applicable ASHRAE 90.1 Efficiency Standard of the year
when replaced system is manufactured
Lighting Table of Standard Fixture Wattages (based on EISA 2007,
EPAct 2005 and PUCT Rule)
Motors ASHRAE 90.1m-1995
Building Envelope IECC 2003
Table 5. Baseline equipment efficiency standard for New Construction projects
Equipment Type Efficiency Requirement
Cooling Equipment
(Replance on Burnout, New
Construction) Current City of Houston Commercial Energy
Conservation Code or Federal Standard whichever is
more stringent
Lighting
Motors
Building Envelope
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 17 -
1.7 Incentives
1.7.1 Available Budgets
CenterPoint Energy has an incentive budget for the C&I Standard Offer Program each calendar year. The
yearly incentive budget as well as updates on available funding will be published on the program Web
site at https://centerpoint.anbetrack.com/.
1.7.2 Incentive Limitations
Maximum Sponsor Incentives
To ensure that incentives are available to multiple energy efficiency service providers, no Project
Sponsor, or combination of affiliated Project Sponsors, may reserve or receive more than 20% of the total
C&I Standard Offer Program incentive budget in a given budget year. An individual Project Sponsor may
be party to multiple applications as long as the total incentive from all such applications does not exceed
the 20% limit.
1.7.3 Payments
For projects using only deemed savings, requiring no M&V activities beyond installation, the Project
Sponsor is eligible to receive 100% of the project incentive payment after the project is installed and
approved by CenterPoint Energy.
For all other projects, M&V activities must be completed, documented, and accepted before the Project
Sponsor will receive the remaining incentive payment, based on the one-year verified savings.
CenterPoint Energy will pay the Project Sponsors in two installments: the Installation Payment and the
Performance Payment. After each project is installed and approved by CenterPoint Energy, the Project
Sponsor will receive an initial payment of 40% of the total estimated project incentive payment. This
initial “Installation Payment” will be calculated as follows:
𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 𝑃𝑎𝑦𝑚𝑒𝑛𝑡 ($) = 40% × [(𝑘𝑊𝑠𝑎𝑣𝑒𝑑 × $/𝑘𝑊) + (𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 × $/𝑘𝑊ℎ)]
This “Performance Payment” may be up to 60% of the total estimated incentive payment, and will be
calculated as follows:
𝑃𝑒𝑟𝑓𝑜𝑟𝑚𝑎𝑛𝑐𝑒 𝑃𝑎𝑦𝑚𝑒𝑛𝑡 ($)
= 60% × [(𝑘𝑊𝒔𝒂𝒗𝒆𝒅,𝒗𝒆𝒓𝒊𝒇𝒊𝒆𝒅 × $/𝑘𝑊) + (𝑘𝑊ℎ𝒔𝒂𝒗𝒆𝒅,𝒗𝒆𝒓𝒊𝒇𝒊𝒆𝒅 × $/𝑘𝑊ℎ)] − 𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 𝑃𝑎𝑦𝑚𝑒𝑛𝑡
Maximum incentive payment
Under no circumstances will CenterPoint Energy make a total incentive payment (i.e., the sum of the
Installation Payment and the Performance Payment) that is more than 100% of the total estimated
incentive payment specified in the Project Authorization, regardless of measured savings achieved. If,
however, M&V activities indicate that the measured savings are less than the estimated savings, the total
incentive payment will be less than the payment estimated in the Project Authorization.
𝑃𝑒𝑟𝑓𝑜𝑟𝑚𝑎𝑛𝑐𝑒 𝑃𝑎𝑦𝑚𝑒𝑛𝑡 ($) + 𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑎𝑡𝑖𝑜𝑛 𝑃𝑎𝑦𝑚𝑒𝑛𝑡 ($) ≤ 100% 𝑜𝑓 𝑃𝑟𝑜𝑗𝑒𝑐𝑡 𝐴𝑢𝑡ℎ𝑜𝑟𝑖𝑧𝑎𝑡𝑖𝑜𝑛 𝐿𝑖𝑚𝑖𝑡($)
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 18 -
Deposits
Application deposits are equal to 5% of approved Project Application (PA) incentive estimates and must
be submitted prior to application submittal. A project deposit is refunded in full for projects that meet
75% of their contracted incentive goal. Application deposits are discussed further in Chapter 2:
Participation Process.
1.7.4 Special Incentive Cases
Projects involving fuel switching measures require special consideration when calculating incentives.
Fuel Switching Measures
Projects involving fuel switching (i.e., electric chillers to gas or absorption chillers) are eligible for the
program, provided the project results in overall lower energy costs, lower energy consumption, and the
installation of high-efficiency equipment. Incentive payments will be based on the electric demand
savings and energy savings of the project, adjusted by the amount of new fuel consumption. Refer to the
M&V Guidelines, Section II, Chapter 5, to determine how to calculate fuel switching demand and energy
savings. For all fuel switching projects, it will be the responsibility of the Project Sponsor to establish the
baselines, which must be approved by CenterPoint Energy, and will be considered on a case by case basis.
As mentioned before, fuel switching to electric is not an eligible retrofit measure.
2. Participation Process
2.1 Overview
This chapter provides information on participating in the CenterPoint Energy 2016 C&I Standard Offer
Program including the program process, required submittals, milestones, and deposits. Participants may
submit applications on January 4, 2016 at 8:00 am CDT on a first-come, first-served basis. Please note
that the 5% deposit check has to be received prior to submittal of a Large Commercial project.
CenterPoint Energy will continue to accept applications for the program until all funds have been
committed. After this time, submitted applications will be placed on a waiting list. Projects on a waiting
list will not automatically be carried over into the next program year.
2.2 Phases of Participation
Participation in the C&I Standard Offer Program involves seven basic phases:
1. Register as a Project Sponsor with CenterPoint Energy and set up a user account for the on-line
application system, ETrack.
2. Submit a Deposit in order for CenterPoint Energy to screen the potential project for eligibility
and tentatively reserve incentive funding.
3. Prepare and submit a Project Application (PA), with necessary supporting documentation, i.e. cut
sheets, square footage.
4. Sign a Project Authorization for each approved project.
5. Install the project and notify CenterPoint Energy when installation is complete
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 19 -
6. For measurement and verification (M&V) projects, submit an Installation Report (IR) to receive
an initial incentive payment. Please note that installation completion before the submittal of the
application will not qualify for the incentive.
a. For deemed savings projects, the total incentive will be paid once CenterPoint Energy
approves the installation based on the requirements of the program.
7. Conduct M&V activities and submit a Savings Report (SR) in order to receive the final energy
and demand savings incentive payment.
A discussion of the requirements of each phase can be found below.
Figure 1 Shows a graphical representation of the process.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 20 -
Project SponsorCenterPoint Energy
Register as Project Sponsor On-line
Identify Project & Negotiate with Host
Customer
Submit Deposit—5% of Requested
Incentive (Large Commercial Projects
Only)
Submit Project Application (PA): cut
sheets, square footage, calculator files,
LED qualifications, M&V plans
Sign and Return Project Authorization
(7 days)
Notify CenterPoint of Installation Start
(2 days before start)
Install Measures
Installation of Measures Complete
(Lighting: 3 months, Other: 6 months)
Conduct M&V Activities
Submit M&V Data to eTrack
PA Approval or Rejection
(Up to 45 days)
Pre-installation inspection
(at CenterPoint’s discretion)
Reserve Incentive Funding
Prepare Project Authorization
Post-installation inspection
IRSR Approval or Rejection
(Up to 45 days)
Installation Payment (~40%)
Review M&V Data
(Typically 15 days)
Performance Payment (~60%)
Installation Inspection
(at CenterPoint’s discretion)
Enter Work Schedule on eTrack
Notify CenterPoint about Completion
of Installation in eTrack
Deemed Savings Only
Incentive Payment (100%)
Installation Approval or Rejection
(Up to 45 days)
Post-installation inspection
Notify CenterPoint about Completion
of Installation in eTrack
M&
V S
avin
gs
On
ly
Figure 1. 2016 C&I Program Process Diagram (*all days are calendar days)
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 21 -
2.2.1 Project Sponsor Registration
Project Sponsors must register with CenterPoint Energy to gain access to the on-line application system,
ETrack. Project Sponsors may go on-line to register at any time. The User Guide for the on-line
application system, ETrack, can be found in Appendix G of this Program Manual.
For the on-line registration process, be prepared to provide the following information:
Project Sponsor Company,
Project Sponsor Company’s Federal Tax ID,
Project Sponsor Company’s Parent Company (if applicable),
Project Sponsor Company’s Parent Company Federal Tax ID (if applicable),
The Designated Primary Contact for the Project Sponsor Company,
The Designated Primary Contact’s Information (Address, Phone, Fax, e-mail), and
A Phone Number for the Project Sponsor Company (if different from Primary Contact).
Description of the Project Sponsor firm, including relevant experience, areas of expertise, and total
number of employees. Description may include references, customer affidavits, or other evidence of
Project Sponsor's competency from previous projects.
Descriptions and references for at least three comparable projects, including information about the
year the projects were undertaken, the services provided, and the estimated and actual performance of
the energy-efficiency equipment.
Evidence that the Project Sponsor possesses all applicable licenses3 (Hard Copy should also be
provided upon request).
Evidence that the Project Sponsor possesses all required insurance (Hard Copy should also be
provided upon request).
Evidence of Project Sponsor’s good credit (Hard Copy should also be provided upon request).
Disclosure of any legal judgments entered against the Project Sponsor in the previous two years, as
well as a current list of pending litigation filed by or against the Project Sponsor.
After completing the on-line portion of the registration process, the required “hard copy” information
must be submitted to the C&I Program Administrator within ten days of the on-line registration in order
to qualify to receive program incentives.
2.2.2 Project Application
To assess projects for eligibility and to tentatively reserve incentive funding for the project, Project
Sponsors must submit a Project Application (PA) using ETrack to participate in the 2016 C&I Standard
Offer Program. This application provides a more detailed description of the project including more
precise descriptions of the projects energy efficiency measures, customer sites, estimated demand and
3 Not required of customers who install measures in their own facilities.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 22 -
energy savings, and estimated incentive payments based on a detailed engineering study and site audit.
This application requires the following information, submitted by the Project Sponsor:
Identification of the host CenterPoint Energy customer site(s). The 22 digit customer ESI ID should
be included to verify service territory. CenterPoint Energy’s ESI ID will be
100890xxxxxxxxxxxxxxxx. (Must input full 22 digit number). It is mandatory that project
sponsors submit the ESI-ID for all host-customer sites as part of the PA phase.
Description of the proposed set of energy-efficiency measures and estimated completion date.
Estimated demand and/or energy savings for each proposed measure and associated incentives
requested.
Brief work plan for project design, M&V approach, implementation, operation, and management,
including the anticipated project timeline.
Deposit
The existing and proposed equipment inventories, including equipment counts, equipment
efficiencies, and equipment nameplate data. Program equipment survey forms have been provided as
standard templates to be used to complete the Project Application and can be downloaded from the
website.
Projects involving lighting measures require submission of product information sheets (cut sheets) for
the new lamps, ballasts, and fixtures. The submitted cut sheets must clearly illustrate the lamp type,
lamp wattage and the ballast factor for a specific lamp/ballast combination. In addition, recycling
records lamps is required. For cooling and refrigeration measures, documentation of the full load
efficiency at standard Air-Conditioning and Refrigeration Institute (ARI) conditions must be
submitted.
Building occupancy and equipment operating schedules. At least 75% occupancy ratio of the building
is required.
Engineering calculations estimating energy and demand savings based on the efficiency of the
proposed equipment compared to that of new, minimum-standard efficiency equipment.
A proposed project-specific M&V plan describing how the Project Sponsor will measure and verify
energy and demand savings, the methods for calculating actual savings, and a schedule for conducting
and reporting on M&V activities is required, submitted as a separate document. In some cases, pre-
installation M&V activities may be required to accurately estimate savings. In general, it is
recommended that the Project Sponsor use the M&V guidelines described in Section II or III,
however the Sponsor may choose to develop an alternative approach. The alternative approach must
be described in detail. In either case, the M&V plan must be approved by CenterPoint Energy before
the Project Application can be approved. If a Sponsor chooses the Deemed Savings method, an M&V
plan is not required.
Updated work plan for project design, implementation, operation, and management, including the
anticipated project timeline.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 23 -
Additionally, the Agreement between the Project Sponsor and Customer, signed by both parties, must
be submitted as part of the Project Application. The Agreement template can be downloaded from
the website.
Starting from the date when the PA is submitted on ETrack, project sponsor has up to 14 calendar days to
modify the submitted application without affecting the deposit. Incentive estimates in the Installation
Report may exceed the original submittal only when there is remaining program budget and no projects
have been placed on a waitlist for program participation.
Upon receiving all the documents and information listed above, Project Applications will be reviewed on
a first-come, first-served basis until all incentive funding has been committed. CenterPoint Energy will
review the eligibility of the proposed measures, the accuracy of the savings estimates, and the
comprehensiveness of the M&V plan. CenterPoint Energy may request clarification of or additional
information about any item in the application. Project Sponsors will have ten working days to respond to
such requests. If the clarification or additional information is not forthcoming, CenterPoint Energy may
choose to discontinue its evaluation of the application. A typical review cycle, including the inspection,
for Project Applications is 25 days for measures eligible to use deemed savings for establishing project
savings, and 45 days for measures requiring full-scale M&V methods.
Upon PA approval, CenterPoint Energy will reserve the appropriate amount of incentive funds for the
project and prepare a Project Authorization.
If program incentives are fully reserved when the deposit was submitted, the project will be put on a
waitlist in the order of when the deposit was submitted on ETrack. The deposit will not be cashed until
the project becomes active and will be voided if the project does not get to the active list during the
program year. When additional program incentives become available, the projects on the waitlist will be
activated in order. The projects on the waitlist may not begin the installation, or else it will automatically
disqualify the projects from receiving program incentives.
Deposit
The Project Sponsor is required to submit a deposit equal to 5% of the reserved incentive for any Large
Commercial project. The deposit shall be in the form of a check or money order. The deposit is
refundable to the Contract Holder upon approval of the Savings Report, provided the project achieves a
minimum percentage of the contracted savings. All Large Commercial projects will be required to
submit the deposit along with the Project Application. In the event that the Program is sold out,
and the project has been placed on the waitlist, CenterPoint Energy will immediately cash the
check with the Project Sponsor’s permission and understanding that it will be 100% refunded
should the project not reach active status.
Pre-Installation Inspection
As part of the Project Application review process, CenterPoint Energy may conduct an inspection of the
project site at its discretion to verify the baseline conditions documented in the Project Application (PA).
CenterPoint Energy will use the required eTrack work schedule to contact the Project Sponsor and
complete the inspection after receipt of a complete PA. The installation inspection requires the presence
of at least one representative of the Project Sponsor who is familiar with the project and the facility so
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 24 -
that all parties can identify any discrepancies. Additionally, all new materials to complete the job must be
onsite for lighting only projects. The inspection will verify the following information:
Equipment survey accuracy. For most measures, the inspector verifies the accuracy of the baseline
equipment quantity and nameplate information. For lighting measures, a statistically significant
sample size will be selected for the inspection. Variables used in determining the sample include a
Sponsor confidence factor, number of sites in the project, and line item values submitted on the
survey. The requirement for acceptance is that the total error of the installed demand of the sample
must be within 5 % of the total demand submitted on the survey form.
M&V plan appropriateness for the measure, and performance of any necessary M&V activities.
All existing equipment listed in the Project Application is still in place and operational.
New equipment installation, or preparation for installation, has not begun.
If electrical measurements are necessary, the Project Sponsor is required to perform any disruptions in
equipment operation, the opening of any electrical connection boxes, or the connection of current and
power transducers. If the inspection cannot be completed in a timely manner because the representative(s)
is unfamiliar with the facility or project, the project site will fail the inspection. If a project site fails the
initial inspection, the Project Sponsor must pay the cost incurred by CenterPoint Energy for any
subsequent inspections.
If the proposed equipment has been installed before the pre-installation inspection, then the Project
Application will be rejected and will not qualify for the incentive.
Project Authorization
Once the Project Application has been approved, the customer shall receive a Project Authorization. The
Project Authorization defines the specifics of the project, including measures to be installed, project
installation schedule, and estimated incentive amount.
The Project Authorization and the approved Project Application become attachments to the Standard
Agreement. The Project Sponsor and CenterPoint Energy must sign the Project Authorization before
project construction may begin.
Installation Notice
Before installation of measures begins, Project Sponsors must notify CenterPoint the date the installation
will commence. Sponsors are required to notify CenterPoint a minimum of 48 hours before the start of
installation.
At its discretion, CenterPoint may conduct an onsite inspection during the 48 hour notification to verify
the new equipment being installed. The inspection process will follow the pre-installation inspection
guidelines outlined above. As such, the Project Sponsor or a building representative is required to be at
the facility for the inspection. CenterPoint will inform the Project Sponsor if such an inspection will take
place after receiving the installation notice.
Failure of notification may result in the cancellation of the project and the forfeiture of the project
deposit.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 25 -
2.2.3 Installation Report
Upon project installation, Project Sponsors must submit an Installation Report (IR) using ETrack. The
project must be installed, and the IR must be submitted within three (3) months of PA approval for
lighting-only projects and six (6) months for all other projects, unless a different construction schedule
has been submitted by the Project Sponsor and approved by CenterPoint Energy. Project Sponsors should
plan to submit Installation Reports for all projects no later than December 1, 2016. The IR updates any
information proposed in the Project Application that has now been finalized after completion of the
project. The IR typically includes the following information:
A customer certification form indicating that the project was installed. This form can be downloaded
from the website.
Recycling receipt. If you install new lamps and ballasts, then the disposal records of the lamps are
required.
Updated equipment survey forms must be submitted to reflect the removed and/or actual installed
equipment inventories, including equipment counts, equipment efficiencies, and equipment nameplate
data if it differs from the information submitted with the Project Application. If there were no changes
the Project Sponsor may refer to the forms submitted with the Project Application.
Updates to building occupancy and equipment operating schedules to reflect changes if they differ
from the information provided with the Project Application. Please note that at least 75% occupancy
ratio of the building is required.
Updated engineering calculations estimating energy and demand savings based on the efficiency of
the actual installed equipment compared to that of new, minimum-standard efficiency equipment if it
differs from the information provided with the Project Application.
A final project-specific M&V plan describing how the Project Sponsor will measure and verify
energy and demand savings, the methods for calculating actual savings, and a schedule for conducting
and reporting on M&V activities.
Incentive estimates in the Installation Report may exceed the amount reserved during the Project
Application phase only when there is remaining program budget and no projects have been placed on a
waitlist for program participation.
Post-Installation Inspection
CenterPoint Energy will conduct a post-installation inspection of the project site within 30 days of the
receipt of a complete IR. The post-installation inspection requires the presence of at least one
representative of the Project Sponsor who is familiar with the project and the facility. The inspection shall
verify that:
The equipment specified in the IR has been installed and is operating as described. For most
measures, the inspector verifies the accuracy of the equipment quantity and nameplate information.
For lighting measures the inspection sample is determined using the same concept as the pre-
inspection methodology and the requirement for acceptance is that the total error of the installed
demand of the sample must be within 5 % of the total demand submitted on the survey form.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 26 -
The Project Sponsor is conducting the M&V activities in accordance with the approved M&V Plan.
If electrical measurements are necessary, the Project Sponsor is required to perform any disruptions in
equipment operation, the opening of any electrical connection boxes, or the connection of current and
power transducers. If the inspection cannot be completed in a timely manner because the representative(s)
is unfamiliar with the facility or project, the project site will fail the inspection. If a project site fails the
initial inspection, the Project Sponsor must pay the cost incurred by CenterPoint Energy for any
subsequent inspections.
A typical review cycle for Installation Reports, including the inspection, is 45 days. Upon IR approval,
the Project Sponsor will receive notice from CenterPoint Energy that the Installation Payment will be
processed. This payment is 40% of the incentive approved in the IR.
2.2.4 Measurement and Verification
M&V procedures will vary in detail and rigor depending on the measures installed. For each installed
measure, the chosen procedures will depend upon the predictability of equipment operation, the
availability of evaluation data from previous programs, and the benefits of the chosen M&V approach
relative to its cost.
Demand savings will be calculated as the maximum, one-hour average demand reduction that occurs
when the newly installed system is operating at peak conditions during the summer or winter period. The
summer period is defined as weekdays, between the hours of 1 P.M. and 7 P.M. from June 1 until
September 30, excluding holidays. The winter period is defined as weekdays, between the hours of 6
A.M. to 10 A.M. and 6 P.M. to 10 P.M. from December 1 to February 28, excluding holidays. Energy
savings are defined as energy savings over the course of one 12-month period. Energy and demand
savings must be either calculated using pre-approved deemed (stipulated) savings, simplified M&V
procedures, or a detailed measurement and verification plan.
Project-specific M&V procedures may be classified according to three distinct approaches that represent
increasing levels of detail and rigor.
Deemed savings: Savings values are stipulated based on engineering calculations using typical
equipment characteristics and operating schedules developed for particular applications, without on-
site testing or metering. This approach is designed for use with lighting efficiency and controls
projects, window film applications, cool roof installations, and most cooling equipment projects.
Simplified M&V: Savings values are based on engineering calculations using typical equipment
characteristics and operating schedules developed for particular applications, with some short-term
testing or simple long-term metering. For example, energy and demand savings from high-efficiency
constant load motor installations can be determined using the simplified approach by comparing rated
efficiencies of high-efficiency equipment to standard equipment, and using kW spot-metering and
simple long-term kWh metering.
Full M&V: Savings are estimated using a more detailed method than in the deemed savings or
simplified M&V approaches through the application of metering, billing analysis, or computer
simulation. These methods will need to be developed in accordance with the 2001 International
Performance Measurement and Verification Protocol (IPMVP), which represents the starting point for
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 27 -
standard industry practice. Project Sponsors will need to adapt the guidelines set forth in the IPMVP
to their specific projects when developing the M&V plan required for program participation.
The time required to complete M&V activities will range from less than a month up to 12 months,
depending on the approach chosen.
M&V plans are not required for projects that use deemed savings for estimating all peak demand and
energy savings. By choosing deemed savings, Project Sponsors agree to follow the procedures set-forth in
this Program Manual to determine project savings. For all other projects, a detailed savings estimate and a
viable M&V plan must be submitted in order for an incentive to be paid. Project Sponsors are responsible
for conducting all M&V activities for the project; however, CenterPoint Energy will work with the
Project Sponsor to facilitate M&V planning as necessary.
Please refer to Section 2 of the Program Manual for M&V guidelines for retrofit projects. Section 3 of the
Program Manual contains M&V guidelines for new construction projects. The program Web site also
offers information about the M&V procedures used to determine energy and peak demand savings for this
program.
2.2.5 Savings Report
After all M&V activities are complete, the Project Sponsor will submit a Savings Report (SR)
documenting the project’s measured demand and energy savings using ETrack. For projects using only
deemed savings, the Project Sponsor may submit the Savings Report at the same time as the Installation
Report. Upon approval of the Savings Report, the Project Sponsor will be notified by CenterPoint Energy
that the final payment will be processed. After the Savings Report is approved, the application deposit
shall be refunded. The amount of the refund is based on the percentage of the estimated incentive
payment, specified in the Project Authorization, actually received by the Project Sponsor. The following
table is used to determine the amount of the refund.
Table 6. Application Deposit Refund
Percent of Estimated Incentive
Payment Received
Percent of Deposit
Refunded
75%+ 100%
50%-74.9% 50%
0%-49.9% 0%
2.3 Other Information
2.3.1 Correspondence and Submittals
Project Sponsors will submit most project information to CenterPoint Energy using ETrack, the Web-
based project application system. Some required submittals, including the signed Host Customer
Agreement must be sent to CenterPoint Energy in hard copy only. CenterPoint Energy must receive
required hard copy project files within five (5) business days of receipt of the on-line submittal. Questions
or comments about the program may also be submitted by e-mail.
Table 7 Summarizes the addresses for application submittals and correspondence.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 28 -
Table 7. Addresses for electronic and hard copy submittals and correspondence
Submittal type Mechanism Address or location
Program Related Questions or
Comments e-mail [email protected]
On-line System Related Questions
or Comments e-mail [email protected]
Project Application, Installation
Report, Savings Report ETrack https://centerpoint.anbetrack.com
Supplemental electronic submittals
(including calculation forms,
inventory forms, raw data, disposal
records, recycling receipts)
ETrack https://centerpoint.anbetrack.com
Hard Copies (excluding lengthy
support documents) or letter
correspondence—excluding deposit
checks
U.S. Mail or
ground
courier
Yolanda Slade
CenterPoint Energy
1111 Louisiana St, 9th Floor
Houston, TX 77002
Deposit Checks
U.S. Mail or
ground
courier
Loretta Battles
CenterPoint Energy
1111 Louisiana St, 9th Floor
Houston, TX 77002
2.3.2 Confidentiality
CenterPoint Energy’s C&I Standard Offer Program is subject to oversight by the Public Utility
Commission of Texas (PUCT), which may request a copy of any program materials that CenterPoint
Energy receives. Sensitive company and project information submitted by the Project Sponsor to
CenterPoint Energy, such as financial statements, will be treated confidentially to the fullest extent
possible, and will not be provided directly to outside parties other than the PUCT. CenterPoint Energy
will have no liability to any Project Sponsor or other party as a result of public disclosure of any
submittals.
CenterPoint Energy plans to list the participating Project Sponsors on its program Web site. The
information to be listed on the Web site will include the Project Sponsor's company name, address, and
telephone number. If your company participates in the 2016 C&I Standard Offer Program, this
information will appear on CenterPoint Energy's energy efficiency Web site at
http://www.centerpointenergy.com.
2.3.3 Participation Costs
CenterPoint Energy will not reimburse any Project Sponsor for any costs incurred by participating in the
C&I Standard Offer Program, including costs of reviewing the Standard Agreement or preparing the
Project Application. The application deposit shall be refunded upon approval of the Savings Report and
shall be prorated based on the performance of the project. CenterPoint Energy will retain the application
deposit in the event that a project is not completed.
Program Manual v 16 Program Guidelines and Participation
2016 Commercial Standard Offer Program
CenterPoint Energy Section 1 - 29 -
2.3.4 Submission of False Information
CenterPoint Energy reserves the right to discontinue its evaluation of all submittals from any Project
Sponsor who submits false, misleading, or incorrect information.
2.3.5 Internet Sites
The C&I Standard Offer Program Web site at https://centerpoint.anbetrack.com/ will serve as the primary
source for all updated program information and materials. The Web site will include:
Information that describes the program process and requirements.
Status updates on program funding available and committed.
Downloadable program manual and M&V guidelines.
A link to the 2016 on-line project application system, ETrack.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 30 -
Measurement and Verification Guidelines Section 2.
for Retrofit Projects
This section includes detailed information about the measurement and verification (M&V) requirements
of the 2016 CenterPoint Energy C&I Standard Offer Program, as well as guidance for Project Sponsors
on how to prepare and execute an M&V plan. These requirements and guidelines are specific to retrofit
projects.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 31 -
3. Introduction to Measurement and Verification for Retrofit Projects
3.1 Overview
In the 2016 C&I Standard Offer Program, the demand and energy savings resulting from a project are
determined through measurement and verification (M&V) activities. The M&V methods appropriate for a
given measure will depend on the equipment type, operational predictability, and complexity involved in
the retrofit. The M&V guidelines provided in the following sections vary in detail and rigor, but fall into
three general categories:
Deemed approach
Simplified Measurement approach
Full Measurement approach
The measurement methods presented in this section define how the project sponsors will calculate system
impacts from energy efficiency projects. Project sponsors will document pre and post measurement
activities, as defined in this manual, to illustrate savings impacts. The Measurement guidelines define
measurement procedures covering several of the anticipated energy-efficiency measures (EEMs) that will
be installed as part of the Energy Efficiency Programs. The simplified and full measurement approaches
must adhere to the standards of the 2007 International Performance Measurement and Inspection
Protocol (IPMVP). Table 8 lists the available measurement methods for the measures.
Table 8. Energy Efficiency Measure vs. Measurement Approach
3.2 Measurement Approaches
CenterPoint Energy has outlined three distinct M&V approaches, representing increasing levels of detail
and rigor - deemed approach, simplified measurement, and full measurement. One of these three
approaches must be taken for all C&I Standard Offer Program projects. The most appropriate method will
depend upon the availability of evaluation data from previous programs for particular measures, the
predictability of equipment operation, and the benefits of the method relative to the costs associated with
the particular M&V method chosen.
Chapter Energy Efficiency Measure Measurement Approaches
Provided
4 Lighting Efficiency and Controls Deemed and Simplified
5 Cooling equipment retrofits Deemed , Simplified and Full
5 Complex, Multiple & Interactive Measures Full
6 Motor retrofits Deemed, Simplified and Full
9 Window films Deemed
10 Generic Variable Loads Full
11 Various – billing analysis using regression models Full
12 Various – computer modeling and simulation Full
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 32 -
3.2.1 Deemed Approach
Deemed approach refer to a savings estimation approach that does not require short-term testing or long-
term metering. Instead, demand and energy savings are stipulated based on evaluation data from past
DSM programs or other publicly available industry data. The data are used to make assumptions about
typical operating characteristics, manufacturer’s nameplate efficiency data, and types of equipment likely
to be installed. The deemed savings M&V approach is appropriate for energy efficiency measures for
which savings are relatively certain, such as lighting efficiency.
3.2.2 Simplified Measurement
A simplified measurement approach may involve short-term testing, but relies primarily on
manufacturer’s efficiency data and pre-set savings calculation formulas. Simplified methods can reduce
the need for extensive field monitoring or performance testing. For example, pre-retrofit chiller demand
and energy may be extrapolated for one-to-one chiller replacements by measuring energy, flow, chill
water supply and return temperatures of the new chiller. Manufacturer curves for kW and tonnage of the
old chiller are then compared to the metered data (tonnage) to extrapolate the consumption of the old
chiller.
CenterPoint Energy, or its contractor, may collect the monitoring data onsite during the post-installation
inspection. In cases where this is necessary, the Sponsor is required to have any logging equipment
operational until the inspection takes place. It is the responsibility of the Sponsor to have the required
equipment and personnel to gather the data from any logging equipment.
3.2.3 Full M&V
The full measurement approach estimates demand and energy savings using a higher level of rigor than
the deemed or metered measurement approaches through the application of computer simulation. Any full
measurement methods other than computer simulation should be developed in accordance with the 2007
International Performance Measurement and Inspection Protocol (IPMVP) and be approved by
CenterPoint Energy. In general, projects involving full measurement must submit a project-specific
measurement plan. At a minimum, the plan should address the following (from the 2007 IPMVP):
1. Describe the project site and the project; include information on how the project saves energy and
which key variables affect the realization of savings.
2. Describe the Measurement method to be used.
3. Indicate who will conduct the Measurement activities and prepare the Measurement analyses and
documentation.
4. Define the details of how calculations will be made. For instance: “List analysis tools, such as
DOE-2 computer simulations, and/or show the equations to be used.” A complete “path” should
be defined indicating how collected survey and metering/monitoring data will be used to calculate
savings. All equations should be shown.
5. Specify what metering equipment will be used, who will provide the equipment, its accuracy and
calibration procedures. Include a metering schedule describing metering duration and when it will
occur, and how data from the metering will be validated and reported. Include data formats.
Electronic, formatted data read directly from a meter or data logger are recommended for any
short-or long-term metering.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 33 -
6. Define what key assumptions will be made about significant variables or unknowns. For instance:
“actual weather data will be used, rather than typical-year data,” or “fan power will be metered
for one full year for two of the six supply air systems.” Describe any stipulations that will be
made and the source of data for the stipulations.
7. Define how any baseline adjustments will be made.
8. Describe any sampling method that will be used, what are included, sample sizes, documentation
on how sample sizes were selected, and information on how random sample points will be
selected.
9. Indicate how quality assurance will be maintained and replication confirmed.
3.3 Steps in the M&V Process
Table 9 highlights the basic steps required during the M&V process for most retrofit projects under this
program.
Table 9. Steps in the M&V process
Step M&V Activity Performed by:
1 Develop a site-specific M&V plan Sponsor
2 Ensure that the M&V plans adhere to the IPMVP guidelines CenterPoint Energy
2 Conduct a pre-installation equipment survey Sponsor
3 Conduct a pre-installation inspection CenterPoint Energy
4 Install retrofit equipment Sponsor
5 Conduct a post-installation equipment survey Sponsor
6 Conduct a post-installation inspection CenterPoint Energy
7 Execute the M&V plan (conduct M&V activities if
necessary) Sponsor
8 True-up savings, based on M&V results Sponsor
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 34 -
4. Measurement Guidelines for Lighting Efficiency and Controls
4.1 Overview
The lighting projects covered by this M&V procedure are lighting efficiency measures that may include
the replacement of existing lamps and ballasts with new energy efficient lamps and ballasts. For these
types of projects, demand savings are based on coincident-load factors and changes in lighting load as
determined using standard lighting fixture wattage values listed in the CenterPoint Energy Table of
Standard Fixture Wattages (see Appendix C). To determine energy savings, the Sponsor should establish
operating hours using one of two methods:
Deemed Hours – Operating hours have been established for certain building types (See Table 16).
Metered Hours – Energy savings are determined by metering pre- or post-installation operating
hours using defined sampling techniques.
For lighting efficiency measures installed in electrically cooled spaces, demand and energy savings are
also given for lighting-HVAC system interaction. These savings are equal to various percentages of the
lighting demand savings and energy savings depending on the building types and temperatures.
Evaporative or alternate fuel system credits for electricity savings must be based on Full M&V results.
In addition to determining operating hours, the Project Sponsor is required to conduct pre- and post-
installation equipment surveys. The Project Sponsor should fill out and submit survey results in the
Retrofit Lighting Survey Form using fixture codes provided in the Table of Standard Fixture Wattages.
CenterPoint Energy or its contractor will conduct pre- and post-installation inspections to verify the
reported baseline and retrofit conditions, respectively.
4.2 Pre-Installation M&V Activities
4.2.1 Pre-Installation Equipment Survey
Prior to installing the lighting retrofit, the Project Sponsor conducts a pre-installation equipment survey,
to be submitted as part of the Project Application. The purpose of the pre-installation equipment survey is
to inventory all existing lighting equipment, and to propose the replacement equipment to be installed.
This survey should provide the following information about all fixtures: room location, fixture, lamp, and
ballast types, lighting controls, area designations, counts of operating and non-operating fixtures, and type
of control device. Surveys should include all baseline lighting fixtures and controls, regardless of whether
they will be retrofitted. Fixture wattages are based on the fixture codes listed in the Table of Standard
Fixture Wattages. This information should be tabulated electronically in the Retrofit Lighting Survey
Form.
4.2.2 Non-operating fixtures
The number of non-operating baseline fixtures will be limited to 10% of the total fixture count per
facility. If, for example, more than 10% of the total number of fixtures is inoperative, the number of
inoperative fixtures beyond 10% will be assumed to have a baseline fixture wattage of zero. Thus, the
total baseline demand for the project will be adjusted accordingly.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 35 -
4.2.3 Pre-Installation Inspection
CenterPoint Energy or its contractor may conduct a pre-installation inspection to verify that the Sponsor
has properly documented the baseline. The criterion for baseline acceptance is that the installed demand
of the inspected sample must be within 5% of the demand reported on the Retrofit Lighting Survey
Form. If the error exceeds 5%, the Sponsor is allowed to resubmit corrected lighting tables. If the project
fails the initial inspection due to incorrect survey forms, the Project Sponsor will bear the cost of
subsequent inspections.
The operating hours of the baseline lighting system are assumed to be the same as those of the post-
retrofit lighting system and are not measured as part of the pre-installation M&V activities.
4.2.4 Installation Inspection
CenterPoint Energy or its designee may conduct an inspection after the Sponsor sends the installation
notice. The criterion for acceptance remains the same as the pre-installation inspection but will also
include surveying the equipment to be installed. If the project fails inspection due to incorrect survey
forms or not having materials or necessary equipment on site for the install, the Project Sponsor will bear
the cost of subsequent inspections.
Not having the equipment to be installed on-site will result in the failure of the inspection and will
require an additional inspection to take place.
4.3 Post-installation M&V Activities
4.3.1 Post-Installation Equipment Survey
The Sponsor is required to conduct a post-installation lighting equipment survey as part of the Installation
Report. The purpose of the post-installation equipment survey is to inventory the actual, as-built post-
retrofit equipment. Fixture wattages shall be based on the Table of Standard Fixture Wattages. In the IR,
the proposed equipment information listed in the approved Project Application shall be updated to reflect
the actual post-retrofit conditions and equipment found during the survey after installation. Any
equipment listed in the approved Project Application that was not in fact replaced should remain in the
lighting equipment inventory – in this case, simply copy the pre-retrofit information to the post-retrofit
columns.
4.3.2 Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify that the retrofit
was installed as reported. In most cases, CenterPoint Energy or its contractor will inspect statistically
significant samples taken from the entire lighting population. The criterion for acceptance is that installed
demand of the inspected sample must be within 5% of the demand reported on the post-installation
Retrofit Lighting Survey Form. If the error exceeds 5%, CenterPoint Energy will inform the Sponsor
that the submitted lighting survey must be corrected and resubmitted, citing the major cause of the errors
found.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 36 -
4.3.3 Lamp Recycling Certificates
The CenterPoint Energy requires recycling of lamps for lighting projects in order for the incentive to be
paid. A certificate indicating the quantity, type, and building the lamps were removed from must be
uploaded to eTrack as proof of the recycling effort. CenterPoint Energy may require Sponsors to account
for any large discrepancies between any counts in the recycling certificate and the lighting calculation
tool.
Failure to recycle retrofitted lamps can result in project cancellation.
4.4 Operating Hours
4.4.1 Deemed Hours
The Deemed Hours Method uses predetermined annual operating hours and co-incidence factors, the
interactive demand and energy savings factors as listed in Table 10. If this table does not accurately
characterize the building type, then the Project Sponsor should refer to the Stipulated Hours Method or
the Metered Hours Method section for the appropriate Measurement techniques to calculate operating
hours.
The Public Utility Commission of Texas (PUC) approved the revision of existing measurement &
verification guidelines for lighting measures for energy efficiency programs in the latest version of the
Texas Technical Reference Manual, and the updated building lighting operating hours and associated
coincidence factors are listed in the table below.
Table 10. Deemed Operating Hours, Co-incidence Factors for Select Building Types
Building Type
Annual
Operating
Hours
Coincidence
Factor
Education:K-12, w/o Summer Session 2,777 47%
Education: College, University, Vocational, Day
Care, and K-12 w/ summer session
3,577 69%
Food Sales - Non-24-Hour Supermarket/Retail 4,706 95%
Food Sales - 24 Hour Supermarket/Retail 6,900 95%
Food Service – Fast food 6, 188 81%
Food Service – Sit-down Restaurant 4,368 81%
Health Care (Out-patient) 3,386 77%
Health Care (In-patient) 5,730 78%
Lodging (Hotel/Motel/Dorm), Common Areas 6,630 82%
Lodging (Hotel/Motel/Dorm), Rooms 3,055 25%
Manufacturing 5,740 73%
Multi-family Housing, Common Areas 4,772 87%
Nursing and Resident Care 4,271 78%
Office 3,737 77%
Outdoor (street & parking) 3,996 0% (61%
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 37 -
winter peak)
Parking Structure 7,884 100%
Public Assembly 2,638 56%
Public Order and Safety 3,472 75%
Religious 1,824 53%
Retail (Excluding Malls and Strip Centers) 3,668 90%
Retail (Enclosed Mall) 4,813 93%
Retail (Strip shopping and non-enclosed mall) 3,965 90%
Service (Excluding Food) 3,406 90%
Warehouse (Non-refrigerated) 3,501 77%
Warehouse (Refrigerated) 3,798 84%
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 38 -
Table 11. Interactive Demand and Energy Factors
Building Type Interactive
Demand Factor
Normal Temps.
(> 41°F)
Interactive
Energy Factor
Normal
Temps. (>
41°F)
Interactive
Demand Factor
Medium Temps.
(33-41°F)
Interactive
Energy Factor
Medium Temps.
(33-41°F)
Interactive
Demand
Factor Low
Temps.
(-10-10°F)
Interactive
Energy
Factor Low
Temps.
(-10-10°F)
Education: K-12, w/o Summer Session 10% 5% 25% 25% 30% 30%
Education: College, University, Vocational,
Day Care, and K-12 w/ Summer Session
10% 5% 25% 25% 30% 30%
Food Sales: Non 24-hour
Supermarket/Retail
10% 5% 25% 25% 30% 30%
Food Sales: 24-hour Supermarket/Retail 10% 5% 25% 25% 30% 30%
Food Service: Fast Food 10% 5% 25% 25% 30% 30%
Food Service: Sit-down Restaurant 10% 5% 25% 25% 30% 30%
Health Care: Out-patient 10% 5% 25% 25% 30% 30%
Health Care: In-patient 10% 5% 25% 25% 30% 30%
Lodging (Hotel/Motel/Dorm): Common
Areas
10% 5% 25% 25% 30% 30%
Lodging (Hotel/Motel/Dorm): Rooms 10% 5% 25% 25% 30% 30%
Manufacturing 10% 5% 25% 25% 30% 30%
Multi-family Housing: Common Areas 10% 5% 25% 25% 30% 30%
Nursing and Resident Care 10% 5% 25% 25% 30% 30%
Office 10% 5% 25% 25% 30% 30%
Outdoor 0% 0% 0% 0% 0% 0%
Parking Structure 0% 0% 0% 0% 0% 0%
Public Assembly 10% 5% 25% 25% 30% 30%
Public Order and Safety 10% 5% 25% 25% 30% 30%
Religious 10% 5% 25% 25% 30% 30%
Retail: Excluding Malls & Strip Centers 10% 5% 25% 25% 30% 30%
Retail: Enclosed Mall 10% 5% 25% 25% 30% 30%
Retail: Strip Shopping &Non-enclosed Mall 10% 5% 25% 25% 30% 30%
Service (Excluding Food) 10% 5% 25% 25% 30% 30%
Warehouse: Non-refrigerated 10% 5% 25% 25% 30% 30%
Warehouse: Refrigerated 25%1 10% 5% 25% 25% 30% 30%
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 39 -
4.4.2 Metered Hours
The Metered Hours Method involves monitoring a statistically significant sample of fixtures to determine
operating hours. This involves developing a sampling plan to monitor the average operating hours for
each lighting usage group. The Project Sponsor should conduct all meter installation, retrieval and data
analysis. When performing the pre-installation activities associated with this Measurement approach,
Project Sponsors should organize the equipment into usage groups—collections of equipment with
similar operating schedules and functional uses. For instance, although a site's open office lighting may
have the same annual hours of operation as the private office lighting, the two have different functional
uses. In this case, a change in the operating hours of the private office lights due to the installation of an
occupancy sensor would not be relevant to the operating hours of the open office lights. Therefore, private
offices and open office areas should be assigned to separate usage groups.
Table 12 Illustrates the recommended minimum number of usage groups, specific to each project site.
Table 12. Suggested Minimum Numbers of Usage Groups for Project Site Types
Building Type
Minimum
Number of
Usage Groups
Examples of Usage Group types
Office Buildings 6 General offices, private offices, hallways, restrooms,
conference, lobbies, 24-hr
Education (K-12) 6 Classrooms, offices, hallways, restrooms, admin,
auditorium, gymnasium, 24-hr
Education
(College/University)
6 Classrooms, offices, hallways, restrooms, admin,
auditorium, library, dormitory, 24-hr
Hospitals/ Health
Care Facilities
8 Patient rooms, operating rooms, nurses station, exam
rooms, labs, offices, hallways
Retail Stores 5 Sales floor, storeroom, displays, private office, 24-hr
Manufacturing 6 Manufacturing, warehouse, shipping, offices, shops, 24-
hr
Other 10 N/A
The Project Sponsor will conduct short-term metering of the operating hours for a random sample of
fixtures in each usage group. For facilities with little variation in weekly operating schedules (such as
offices), monitoring shall be conducted for each selected circuit for a recommended minimum of two to
four weeks. Monitoring should not occur during significant holidays or vacations. If a holiday or vacation
falls within the monitoring period, the duration should be extended for as many days as that holiday or
vacation. For facilities where operating hours vary seasonally, monitoring should be conducted for a
minimum period during each season.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 40 -
The required sample sizes for each usage group are listed in Table 13. Note: because light loggers
sometimes fail, over sampling is recommended. Light loggers should be calibrated prior to installation to
verify that the light loggers are functioning properly. In the event that there are multiple fixtures on a
single circuit breaker (e.g., warehouse), then the Project Sponsor will coordinate with CenterPoint Energy
to determine number of samples required.
Table 13. Monitoring Sample Size
Population of Lines in Usage Group Sample Size
n <4 3
5<=n<8 5
9<=n<12 6
13<=n<20 7
21<=n<70 8
71<=n<300 10
n>300 11
* Sample sizes assume a confidence interval of 80%, precision of 20%, and a coefficient of variation (cv) of 0.5 for
the populations indicated
4.4.3 Calculation of Average Operating Hours
For each usage group, the Project Sponsor should extrapolate results from the monitored sample to the
population to calculate the average annual lighting operating hours. Simple, unweighted averages of
operating hours should be calculated for each usage group as listed in the following equations. The
Project Sponsor should use these average operating hours to calculate the energy savings for each
respective usage group.
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑢 = ∑
𝐻𝑜𝑢𝑟𝑠𝑜𝑛 ,𝑖
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖× 8760𝑛
𝑖=1
𝑛
Where:
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑢 = Average annual operating hours for usage group u
𝐻𝑜𝑢𝑟𝑠𝑜𝑛 ,𝑖 = Operating hours observed during the metering period for circuit i
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖 = Total number of hours in the metering period for circuit i
𝑛 = Number of metered circuits in usage group u
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 41 -
4.4.4 Calculation of Average Co-incidence Factor
The equation listed below illustrates the calculation of average on-peak demand coincidence factor (CF)
for a usage group. Note that demand savings are only allowed for lighting fixtures that will be in
operation on weekdays between the hours of 1 PM and 7 PM during the months of June through
September.
𝐶𝐹𝑢 =
∑ [𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑜𝑛,𝑖
𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖]𝑛
𝑖=1
𝑛
Where:
𝐶𝐹𝑢 = = Peak-demand coincidence factor for usage group u
𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑜𝑛,𝑖 = Operating hours observed during peak in the metering period for circuit i
𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖 = Total number of peak demand hours in the metering period for circuit I
𝑛 = Number or metered circuits in usage group u
4.5 Controls
The addition of controls such as occupancy sensors and day lighting are measures eligible for the
program. Energy Savings resulting from reduced operating hours can be claimed with the installation of
controls. There are two paths that the Project Sponsor may take to claim savings
4.5.1 Deemed Control Savings
This method requires the use of the deemed hours from Table 10 and a Power Adjustment Factor (PAF) and
Energy Adjustment Factor (EAF) from Table 14. If values from these tables do not accurately characterize the
building type and operation, then the Project Sponsor must refer to Metered Control Savings Method
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 42 -
Table 14. List of Power Adjustment Factors and Energy Adjustment Factors*
Control Type Sub-Category Control Codes EAF PAF
None n/a None 0.00 0.00
Occupancy n/a OS 0.24 0.24
Daylighting
(Indoor)
Continuous dimming DL-Cont
0.28 0.28 Multiple step dimming DL-Step
ON/OFF DL-ON/OFF
Outdoor n/a Outdoor 0.00 0.00
Personal Tuning n/a PT 0.31 0.31
Institutional Tuning n/a IT 0.36 0.36
Multiple/Combined Types Various combinations Multiple 0.38 0.38
*EAFs and PAFs are adapted from the latest version of the TRM.
4.5.2 Metered Control Savings
If the project is ineligible for deemed savings and/or the Project Sponsor prefers to monitor Operating
Hours to claim achievable savings, the Metered Hours Method must be followed to determine operating
hours (Refer to Pages 7-9 of the 2007 International Performance Measurement and Inspection Protocol).
If the project involves the addition of lighting controls to a building that does not fall under the deemed
category and the stipulated method is inadequate to determine pre-operating hours, then pre- and post-
installation metering may be required to determine pre- and post-operating hours.
4.6 Calculation of Demand and Energy Savings
Appended below are equations relating to peak demand and energy savings calculations. These
calculations are embedded in the Retrofit Lighting Survey Form.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = ∑ (((𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × 𝑘𝑊𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × (1 − 𝑃𝐴𝐹) × 𝐶𝐹)𝑝𝑟𝑒
𝑛
𝑖=1
− (𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × 𝑘𝑊𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × (1 − 𝑃𝐴𝐹) × 𝐶𝐹 )𝑝𝑜𝑠𝑡
) × (1 + 𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟1) )
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑ (((𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × 𝑘𝑊𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × (1 − 𝐸𝐴𝐹𝑖) × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑖)𝑝𝑟𝑒
𝑛
𝑖=1
− (𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × 𝑘𝑊𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × (1 − 𝐸𝐴𝐹𝑖) × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑖 )𝑝𝑜𝑠𝑡
) × (1 + 𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟2))
Where:
𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) = Number of fixtures in line item i (pre or post)
𝑘𝑊(𝑓𝑖𝑥𝑡𝑢𝑟𝑒 𝑖)= Deemed fixture wattage from standard wattage table for fixture type listed in line item i
(pre or post).
𝐶𝐹𝑖 = Coincident demand factor based on input in line item i (Deemed, Stipulated or Metered)
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 43 -
𝑃𝐴𝐹𝑖 = Power adjustment factors based on controls type on input in line item I (Deemed, or Metered)
𝐸𝐴𝐹𝑖 = Energy adjustment factors based on controls type on input in line item I (Deemed, or Metered)
𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟1 = If space is conditioned, value is referred to Table 11. If unconditioned, value is 0.
𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟2= If space is conditioned, value is referred to Table 11. If unconditioned, value is 0.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 44 -
5. Measurement Guidelines for Replacement of Cooling Equipment
5.1 Overview
Cooling equipment retrofits involve the replacement of the existing equipment with high-efficiency
equipment. This chapter presents both a deemed savings approach and a full approach to the measurement
and inspection of savings from the retrofit of cooling equipment. In general, the measurement methods
described in this chapter can be used for projects involving the one-for-one change-out of cooling
equipment. Potential qualifying equipment includes:
Unitary air conditioners (DX, air-cooled, evaporative, or water-cooled)
Heat pumps (air-cooled, evaporative, or water-cooled)
Chillers (air-cooled centrifugal, water-cooled centrifugal, air-cooled screw, etc.)
Compressors (centrifugal, screw, reciprocating)
Fuel switching from electric to gas engine-driven cooling equipment
The retrofits must have the following characteristics:
The newly installed electric cooling equipment capacity must be within 80% to 120% of the replaced
electric cooling equipment capacity.
The newly installed electric cooling equipment must not be redundant, backup or off –peak use only
equipment.
No additional measures are being installed that directly affect the operation of the cooling equipment
(i.e., control sequences, cooling towers, and condensers).
If the proposed retrofit does not meet these requirements, refer to the Full Measurement guidelines for
appropriate Measurement techniques.
The baseline efficiency used in the savings calculation for replace-on-burnout of Unitary ACs, Heat
Pumps, and Room ACs is either ASHRAE 2007/2010 or the Federal Manufacturer Standard. Baseline
efficiency for Chillers and Packaged Terminal Air Conditioners and Heat Pumps is either IECC 2009 or
ASHRAE 90.1-1999 (for water-cooled chillers). Efficiency values from this standard can be found in the
Standard Cooling Equipment Tables under the heading “Baseline Performance Standard”, Appendix A of
the Appendices to M&V Guidelines found at the end of this document.
Early retirement is an available option for projects involving chilled water systems and package or split
unitary air-conditioners and heat pumps that involve replacement of a working system. Baseline
efficiency will be estimated according to the capacity, type (e.g. for unitary systems, whether package or
split, heat pump or air conditioner), and the year of manufacture of the replaced system and can be found
in the Standard Cooling Equipment Tables in Appendix A.
5.2 Deemed Savings for Cooling Equipment
The deemed savings approach to Measurement for cooling equipment is applicable to both one-for-one
equipment replacement as well as equipment replacement involving a change in equipment type, e.g.,
changing from air-cooled DX units to a water-cooled chiller. An air-cooled to water-cooled equipment
measure requires an additional step to account for the auxiliary devices to support a water-cooled chiller.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 45 -
The deemed savings methodology is incorporated in an Excel spreadsheet, available to Project Sponsor,
which calculates savings values based on user inputs. For replacements involving, changes in equipment
type, the calculations must be done manually. The efficiency of the installed equipment must exceed
the efficiency as listed under the current City of Houston Commercial Energy Code or Federal
Standard whichever is more stringent for the appropriate equipment type and capacity.
Projects that are eligible to use the deemed savings approach must meet the following requirements:
The existing and proposed cooling equipment are electric.
The Cooling Equipment is not used for process loads.
Coefficients are listed in Table A.1- 8 for the type of building in which the retrofit occurs and the type
of equipment involved.
The building falls into one of the categories described in Table 15
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 46 -
Table 15. Building Descriptions for Use in the Air-Conditioning Equipment Deemed Savings
Building Type Principal Building Activity Definition Detailed Business Type Examples
Education
College
Buildings used for academic or technical
classroom instruction, such as elementary,
middle, or high schools, and classroom
buildings on college or university campuses.
Buildings on education campuses for which the
main use is not classroom are included in the
category relating to their use. For example,
administration buildings are part of "Office,"
dormitories are "Lodging," and libraries are
"Public Assembly."
1) College or University
2) Career or Vocational Training
3) Adult Education
Primary School 1) Elementary or Middle School
2) Preschool or Daycare
Secondary School
1) High School
2) Religious Education
Food Sales Convenience
Buildings used for retail or wholesale of food. 1) Gas Station with a Convenience Store
2) Convenience Store
Supermarket 1) Grocery Store or Food Market
Food Service Full-Service Restaurant Buildings used for preparation and sale of food
and beverages for consumption.
1) Restaurant or Cafeteria
Quick-Service Restaurant 1) Fast Food
Healthcare
Hospital Buildings used as diagnostic and treatment
facilities for inpatient care.
1) Hospital
2) Inpatient Rehabilitation
Outpatient Healthcare
Buildings used as diagnostic and treatment
facilities for outpatient care. Medical offices
are included here if they use any type of
diagnostic medical equipment (if they do not,
they are categorized as an office building).
1) Medical Office
2) Clinic or Outpatient Health Care
3) Veterinarian
Large Multifamily Midrise Apartment
Buildings containing multifamily dwelling
units, having multiple stories, and equipped
with elevators.
No sub-categories collected.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 47 -
Building Type Principal Building Activity Definition Detailed Business Type Examples
Lodging
Large Hotel Buildings used to offer multiple
accommodations for short-term or long-term
residents, including skilled nursing and other
residential care buildings.
1) Motel or Inn
2) Hotel
3) Dormitory, Fraternity, or Sorority
4) Retirement Home, Nursing Home, Assisted
Living, or other Residential Care
5) Convent or Monastery
Nursing Home
Small Hotel/Motel
Mercantile
Stand-Alone Retail
Buildings used for the sale and display of
goods other than food.
1) Retail Store
2) Beer, Wine, or Liquor Store
3) Rental Center
4) Dealership or Showroom for Vehicles or
Boats
5) Studio or Gallery
Strip Mall Shopping malls comprised of multiple
connected establishments.
1) Strip Shopping Center
2) Enclosed Malls
Office
Large Office
Buildings used for general office space,
professional office, or administrative offices.
Medical offices are included here if they do not
use any type of diagnostic medical equipment
(if they do, they are categorized as an
outpatient health care building).
1) Administrative or Professional Office
2) Government Office
3) Mixed-Use Office
4) Bank or Other Financial Institution
5) Medical Office
6) Sales Office
7) Contractor’s Office (e.g. Construction,
Plumbing, HVAC)
8) Non-Profit or Social Services
9) Research and Development
10) City Hall or City Center
11) Religious Office
12) Call Center
Medium Office
Small Office
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 48 -
Building Type Principal Building Activity Definition Detailed Business Type Examples
Public Assembly Public Assembly
Buildings in which people gather for social or
recreational activities, whether in private or
non-private meeting halls.
1) Social or Meeting (e.g. Community Center,
Lodge, Meeting Hall, Convention Center,
Senior Center)
2) Recreation (e.g. Gymnasium, Health Club,
Bowling Alley, Ice Rink, Field House, Indoor
Racquet Sports)
3) Entertainment or Culture (e.g. Museum,
Theater, Cinema, Sports Arena, Casino, Night
Club)
4) Library
5) Funeral Home
6) Student Activities Center
7) Armory
8) Exhibition Hall
9) Broadcasting Studio
10) Transportation Terminal
Religious Worship Religious Worship
Buildings in which people gather for religious
activities, (such as chapels, churches, mosques,
synagogues, and temples).
No sub-categories collected.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 49 -
Building Type Principal Building Activity Definition Detailed Business Type Examples
Service Service
Buildings in which some type of service is
provided, other than food service or retail sales
of goods.
1) Vehicle Service or Vehicle Repair Shop
2) Vehicle Storage/Maintenance
3) Repair Shop
4) Dry Cleaner or Laundromat
5) Post Office or Postal Center
6) Car Wash
7) Gas Station with no Convenience Store
8) Photo Processing Shop
9) Beauty Parlor or Barber Shop
10) Tanning Salon
11) Copy Center or Printing Shop
12) Kennel
Warehouse Warehouse
Buildings used to store goods, manufactured
products, merchandise, raw materials, or
personal belongings (such as self-storage).
1) Refrigerated Warehouse
2) Non-refrigerated warehouse
3) Distribution or Shipping Center
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2 - 50 -
5.2.1 Pre –Installation Measurement Activities
Proof of Equipment Purchase
Sponsors must submit, within 30 days of the application approval, documentation showing the new
equipment is on order and should be delivered within the timeframe of the SOP.
Pre-Installation Equipment Survey
The goals of the pre-installation site survey are to identify the cooling equipment, establish the retrofit
type (whether it will be replace-on-burnout or early retirement) and establish the baseline efficiency. The
information collected should include: equipment type, year, make/model, rated capacity, rated efficiency,
and an assessment of its working condition.
The baseline efficiency is established according to the retrofit type: for replace-on-burnout projects,
baseline efficiencies are determined by recent Federal or manufacturing standards, and are published in
Tables A1 through A8.
The baseline efficiency listed in the Standard Cooling Equipment Table in Appendix A. The baseline
efficiency is equal to the more efficient of the two values. The goals of the pre-installation survey are to
identify the cooling equipment and establish the baseline efficiency. The information collected should
include: equipment type, year, make/model, rated capacity, rated efficiency. The Project Sponsor should
record information about the cooling equipment in the deemed savings spreadsheet.
Pre-Installation Inspection
CenterPoint Energy or its contractor will conduct a pre-installation inspection to verify that the Project
Sponsor has properly documented the baseline. Demolition or removal of existing equipment and/or
installation of new equipment cannot commence until the pre-installation inspection is completed and
CenterPoint Energy has executed the Project Authorization.
5.2.2 Post-Installation Measurement Activities
Post-Installation Equipment Survey
Once the retrofit is complete, the Project Sponsor conducts and submits a post-installation equipment
survey. The survey should include: installed equipment type, year, make/model, rated capacity, and rated
efficiency and pertinent information about the cooling equipment recorded in the deemed savings
spreadsheet. The Project Sponsor must submit manufacturer’s documentation of the rated efficiency of all
newly installed cooling equipment, based upon ARI test conditions. This documentation will be in the
form of manufacturer cut sheets or factory performance test results that document the part load
performance of the equipment.
Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify that the
equipment was installed as reported and is documented accurately.
5.2.3 Calculation Methodology
Appended below are equations relating to the first year peak demand and energy savings calculations.
These calculations are embedded in the pertinent CenterPoint Energy Cooling Equipment Form. For a
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 51 -
more detailed look into projects that require multi-year savings please refer to the Texas Technical
Reference Manual for the 2016 Program Year.
For Split Systems/Package AC and HP:
𝑬𝒏𝒆𝒓𝒈𝒚 𝑺𝒂𝒗𝒊𝒏𝒈𝒔 [𝒌𝑾𝒉𝒔𝒂𝒗𝒊𝒏𝒈𝒔] = 𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑪 + 𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑯
𝑷𝒆𝒂𝒌 𝑫𝒆𝒎𝒂𝒏𝒅 [𝒌𝑾𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑪] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆
𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝑪−
𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕
𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅,𝑪) × 𝑪𝑭 ×
𝟏 𝒌𝑾
𝟏, 𝟎𝟎𝟎 𝑾
𝑬𝒏𝒆𝒓𝒈𝒚 (𝑪𝒐𝒐𝒍𝒊𝒏𝒈) [𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑪] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆
𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝑪−
𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕
𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅,𝑪) × 𝑬𝑭𝑳𝑯𝑪 ×
𝟏 𝒌𝑾
𝟏, 𝟎𝟎𝟎 𝑾
𝑬𝒏𝒆𝒓𝒈𝒚 (𝑯𝒆𝒂𝒕𝒊𝒏𝒈) [𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑯] = (𝑪𝒂𝒑𝑯,𝒑𝒓𝒆
𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝑯−
𝑪𝒂𝒑𝑯,𝒑𝒐𝒔𝒕
𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅,𝑯) × 𝑬𝑭𝑳𝑯𝑯 ×
𝟏 𝒌𝑾𝒉
𝟑, 𝟒𝟏𝟐 𝑩𝒕𝒖
For chillers:
𝑷𝒆𝒂𝒌 𝑫𝒆𝒎𝒂𝒏𝒅 [𝒌𝑾𝑺𝒂𝒗𝒊𝒏𝒈𝒔] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆 × 𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆 − 𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕 × 𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅) × 𝑪𝑭
𝑬𝒏𝒆𝒓𝒈𝒚 𝑺𝒂𝒗𝒊𝒏𝒈𝒔 [𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆 × 𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆 − 𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕 × 𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅) × 𝑬𝑭𝑳𝑯𝑪
Where:
CapC/H,pre = Rated equipment cooling/heating capacity of the existing equipment at AHRI
standard conditions
CapC/H,post = Rated equipment cooling/heating capacity of the newly installed equipment at
AHRI standard conditions
ηbaseline,C = Cooling efficiency of existing equipment (ER) or standard equipment
(ROB/NC)
ηinstalled,C = Rated cooling efficiency of the newly installed equipment (Must exceed baseline
efficiency standards)
ηbaseline,H = Heating efficiency of existing equipment (ER) or standard equipment
(ROB/NC)
ηinstalled,H = Rated heating efficiency of the newly installed equipment (Must exceed baseline
efficiency standards)
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 52 -
Note: For split system/packaged AC replacements use EER for kW savings calculations and SEER/IEER
and COP for kWh savings calculations. The COP expressed for units > 5.4 tons is a full-load COP. Heating
efficiencies expressed as HSPF will be approximated as a seasonal COP and should be converted using the
following equation:
𝐂𝐎𝐏 =𝐇𝐒𝐏𝐅
𝟑. 𝟒𝟏𝟐
CF = Summer peak coincidence factor for appropriate climate zone, building type, and
equipment type (Table 10 and Table 11 in Appendix A)
EFLHC/H = Cooling/heating equivalent full-load hours for appropriate climate zone, building
type, and equipment type [hours] (Table 10 and Table 11 in Appendix A)
5.3 Simplified Measurement for Cooling Equipment
The simple M&V procedure for electric-to-electric cooling equipment replacement involves collecting
one year of post-consumption kWh data. To determine demand savings, the maximum equipment
demand that occurs during the utility peak hours must be measured. This can be accomplished with
continuous demand metering or spot metering during peak conditions.
5.3.1 Pre –Installation Measurement Activities
Proof of Equipment Purchase
Sponsors must submit, within 30 days of the application approval, documentation showing the new
equipment is on order and should be delivered within the timeframe of the SOP.
Pre-Installation Equipment Survey
The goals of the pre-installation site survey are to identify the existing equipment, evaluate its schedule of
use, and establish the baseline efficiency or coefficient of performance (COP). The Project Sponsor will
conduct a survey of all the existing cooling equipment for buildings with a central plant, regardless of
whether they will be retrofitted. The information collected should include: equipment type, year,
make/model, rated capacity, rated efficiency, operating schedule, and operating sequence. Record the
equipment information in the Cooling Equipment Inventory Form.
The baseline efficiency is determined by comparing the rated efficiency of the existing unit to the
minimum efficiency listed in the Standard Cooling Equipment Table, which are based on ASHRAE 90.1-
1989, provided in Appendix A. The baseline efficiency is equal to the more efficient of the two values.
Pre-Installation Inspection
CenterPoint Energy or its contractor will conduct a pre-installation inspection to verify that the Project
Sponsor has properly documented the baseline. Demolition or removal of existing equipment and/or
installation of new equipment cannot commence until the pre-installation inspection is completed and
CenterPoint Energy has executed the Project Authorization.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 53 -
Pre-Installation Monitoring
The simple M&V procedure for electric-to-electric cooling equipment replacements does not require pre-
installation monitoring of existing equipment. The existing equipment efficiency is determined from the
Standard Cooling Equipment Tables, Appendix A. The existing equipment load and operating schedule
are assumed to be the same as those of the post-retrofit equipment.
The simple M&V procedure for electric-to-gas cooling equipment replacement does require pre-
installation monitoring of the existing equipment. The maximum demand (measured for a one-hour
period) that coincides with the utility peak demand period must be determined, through spot
measurements or continuous metering. The annual energy usage of the existing equipment must also be
established through measurements, or predicted by a method approved by CenterPoint Energy.
5.3.2 Post-Installation Measurement Activities
Post-Installation Equipment Survey
Once the retrofit is complete, the Project Sponsor conducts and submits a post-installation equipment
survey. The survey should include: installed equipment type, year, make/model, rated capacity, and rated
efficiency and pertinent information about the cooling equipment recorded in the deemed savings
spreadsheet. The Project Sponsor must submit manufacturer’s documentation of the rated efficiency of all
newly installed cooling equipment, based upon ARI test conditions. This documentation will be in the
form of manufacturer cut sheets or factory performance test results that document the part load
performance of the equipment.
Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify that the
equipment was installed as reported and is documented accurately.
Post-Installation Monitoring
Two basic steps comprise the necessary post-retrofit M&V monitoring activities for electric-to-electric
cooling equipment replacements:
1. Measure the maximum demand (measured for a one hour period) that occurs between the hours
of 1 PM and 7 PM on weekdays during the months of June through September. This can be
accomplished with continuous demand metering (at 15-minute intervals) or a spot measurement
during peak conditions.
2. Collect twelve months of post-installation consumption (kWh) data.
For electric-to-gas fuel switching cooling equipment replacements, twelve months of post-installation gas
usage is required in the simple M&V procedure. If the new gas-engine chiller included installation of new
electric auxiliary equipment, such as a condenser water pump and cooling tower fan, the peak demand
and annual energy consumption for this additional equipment must be metered and subtracted from the
chiller savings.
5.3.3 Calculation Methodology
Appended below are equations relating to peak demand and energy savings calculations. These
calculations are embedded in the pertinent CenterPoint Energy Cooling Equipment Form.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 54 -
Electric to Electric Equipment Replacements
Demand savings are allowed only for new equipment that will be in operation during the peak periods.
Peak demand and energy savings are calculated according to Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 × (𝐶𝑂𝑃𝑝𝑜𝑠𝑡
𝐶𝑂𝑃𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒− 1)
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊ℎ𝑚𝑒𝑡𝑒𝑟𝑒𝑑 × (𝐶𝑂𝑃𝑝𝑜𝑠𝑡
𝐶𝑂𝑃𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒− 1) × (
𝐶𝐷𝐷(65)𝑇𝑀𝑌
𝐶𝐷𝐷(65)𝑚𝑒𝑡𝑒𝑟𝑒𝑑)
Where:
𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = maximum metered 15-minunte cooling equipment demand during the utility peak-demand
period, kW
𝑘𝑊ℎ𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = summed metered cooling equipment energy use for one year, kWh
𝐶𝑂𝑃𝑝𝑜𝑠𝑡=installed cooling equipment coefficient-of-performance at ARI design conditions
𝐶𝑂𝑃𝑏𝑎𝑠𝑙𝑖𝑛𝑒= baseline cooling equipment coefficient-of-performance from Appendix A
𝐶𝐷𝐷(65)𝑇𝑀𝑌=cooling degree days (base 65 F) for a typical meteorological year for the National Climatic
Data Center station nearest the site. The value is available in Appendix A, Table A.9
𝐶𝐷𝐷(65)𝑚𝑒𝑡𝑒𝑟𝑒𝑑= cooling degree days (base 65 F) determined for the metered period for the National
Climatic Data Center station nearest the site. The value is determined by CenterPoint
Energy based on the metering period start and stop dates.
Electric to Gas Equipment Replacements (Fuel switching)
Demand savings are allowed only for equipment that operates during the peak periods. Peak demand
savings are calculated according to Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 − 𝑘𝑊𝑛𝑒𝑤 𝑒𝑞𝑢𝑖𝑝
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 − 𝑘𝑊𝑛𝑒𝑤 𝑒𝑞𝑢𝑖𝑝 − 𝐵𝑇𝑈𝑔𝑎𝑠 × (1
10,500)
Where:
𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = maximum metered 15-minunte cooling equipment demand during the utility peak-demand
period, kW
𝑘𝑊𝑛𝑒𝑤 𝑒𝑞𝑢𝑖𝑝 = maximum demand of any new electric auxiliary equipment installed with the gas engine
chiller measured during the utility peak-demand period, kW
𝑘𝑊ℎ𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = summed metered cooling equipment energy use for one year, kWh
𝑘𝑊ℎ𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = Annual energy usage of any new electric auxiliary equipment installed with the gas engine
chiller measured or predicted, kWh
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 55 -
𝐵𝑇𝑈𝑔𝑎𝑠 = Measured annual post-retrofit gas consumption
5.4 Full Measurement for Cooling Equipment
The Full Measurement procedure for electric-to-electric cooling equipment replacement or savings
realized at the cooling equipment, due to control strategies, VAV modifications, building shell
improvements, etc, requires a building simulation. Any full measurement methods other than computer
simulation should be developed in accordance with the 2007 International Performance Measurement and
Inspection Protocol (IPMVP) and be approved by CenterPoint Energy. Computer Simulation Analysis for
measurement and verification of energy savings is used when the energy impacts of the energy efficiency
measures (EEMs) are too complex1 or too costly to analyze with traditional M&V methods. Situations
where computer-based building energy simulations may be appropriate include:
The EEM is an improvement or replacement of the building energy management or control system.
There is more than one EEM and the degree of interaction between them is unknown or too difficult
or costly to measure.
The EEM involves improvements to the building shell or other measures that primarily affect the
building load (e.g., thermal insulation, low-emissivity windows).
The M&V method described here is based, in part, on Option D of the 2007 International Performance
Measurement and Verification Protocol (IPMVP). Valuable insights on computer simulation analysis can
be found in the IPMVP. The Project Sponsor should take the following steps in performing Computer
Simulation Analysis M&V:
1. Work with CenterPoint Energy and its contractor to define a strategy for creating a calibrated
building simulation model in the project-specific M&V plan.
2. Collect the required data from utility bill records, architectural drawings, site surveys, and direct
measurements of specific equipment installed in the building.
3. Adapt the data and enter them into the program’s input files.
4. Run the simulation program for the “base” building model. The base building is the existing
building without the installed EEMs. The base building should comply with minimum state and
federal energy standards.
5. Calibrate the base model by comparing its output with measured data. The weather data for the
base model should be the actual weather occurring during the metering period. Refine the base
building model until the program’s output is within acceptable tolerances of the measured data.
6. Run the calibrated base model using typical weather data to normalize the results.
7. Repeat the process for the post-installation model. Calibration of the retrofit model, if done,
should use data collected from site surveys (to validate that all of the equipment and systems are
installed and operating properly) and possibly spot short-term or utility metering.
8. Estimate the savings. Savings are determined by subtracting the post-installation results from the
baseline results using typical conditions and weather. The savings estimates and simulation
results will be reviewed and verified by CenterPoint Energy or its contractor.
These steps are described in more detail in the following sections.
1 Wolpert, J.S. and J. Stein, “Simulation, Monitoring, and the Design Assistance Professional,” 1992 International Energy and
Environment Conference.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 56 -
5.4.1 Baseline and Post-Retrofit Data Requirements
Simulation Software
To conduct Calibrated Simulation Analysis M&V, it is recommended that the Project Sponsor use the
most current version available of the DOE-2.1E hourly building simulation program. For projects with
small projected incentive payments, the Project Sponsor may use other models if the model can be shown
to adequately model the project site and the EEMs can be calibrated to a high level of accuracy, and the
calibration can be documented.
Weather Data
Calibrating a computer simulation of a real building for a specific year requires that actual weather data
be used in the analysis. Actual weather data should be collected from a source such as National Climatic
Data Center (NCDC) weather station data. The physical location of the weather station should be the
closest available to the project site. These data should be translated into weather data files that are
compatible with DOE-2. The project-specific M&V plan should specify which weather data sources will
be used. Typical weather data used in the calculation of energy savings should be either Typical
Meteorological Year (TMY2) or TMY3 data types, obtained from the National Renewable Energy
Laboratory (NREL).
Develop a Calibrated Simulation Strategy
The following are issues that either the Project Sponsor or CenterPoint Energy will need to address in
order to define the simulation approach:
Define the existing building. In general, the existing building represents the building, as it exists
prior to installation of EEMs by the Project Sponsor.
Define the baseline building. The baseline building represents the existing building but with baseline
equipment efficiencies as specified by state or federal standards.
Define the post-installation building. The post-installation building represents the building with the
project-related EEMs installed.
Define the calibration data interval. The building models should be calibrated using hourly, daily,
or monthly data. Calibrations to hourly or daily data are preferred to monthly data, since the former is
more accurate than the latter, due to more comparison points. If monthly project site billing data is
used, then spot or short-term data collection for calibrated key values may be used.
Specify spot and short-term measurements to be taken of building systems. These measurements
augment the whole-building data and enable the modeler to accurately characterize building systems.
Spot and short-term measurements are valuable, but may add significant cost and time to the project.
Employ an experienced building modeling professional. Although new simulation software
packages make much of the process easier, a program’s capabilities and real data requirements are not
fully understood by inexperienced users. Employing inexperienced users for this purpose will result
in inefficient use of time in data processing, and in checking and understanding of simulation results.
Building Data Collection
The main categories of data to be collected for the building and proposed EEMs are described below.
Building plans. The Project Sponsor should obtain as-built building plans. If as-built plans are not
available, the Project Sponsor should work with the building owner to define alternative sources.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 57 -
Utility bills. The Project Sponsor should collect a minimum of twelve consecutive months
(preferably 24 months), with applicable dates of utility bills for the months immediately before
installation of the EEMs. The billing data should include monthly kWh consumption and peak electric
demand (kW) for the month. Fifteen minute or hourly data are also desired for calibration. The
Project Sponsor should determine if building systems are sub-metered, and collect these data if
available. If hourly data are required to calibrate the simulation, but no data are available, metering
equipment may need to be installed to acquire hourly data.
Conduct on-site surveys. CenterPoint Energy or its contractor will assist the Project Sponsor to
identify the necessary data to be collected from the building. The Project Sponsor should visit the
building site to collect the data. CenterPoint Energy or its contractor may accompany the Project
Sponsor during the building survey. Data that may be collected include:
HVAC systems - primary equipment (e.g. chillers and boilers): capacity, number, model and
serial numbers, age, condition, operation schedules, etc.
HVAC systems - secondary equipment (e.g., air handling units, terminal boxes):
characteristics, fan sizes and types, motor sizes and efficiencies, design flow rates and static
pressures, duct system types, economizer operation and control
HVAC system controls, including location of zones, temperature set-points, control set-points
and schedules, and any special control features
Building envelope and thermal mass: dimensions and type of interior and exterior walls,
properties of windows, and building orientation and shading from nearby objects
Lighting systems: number and types of lamps, with nameplate data for lamps and ballasts,
lighting schedules, etc.
Plug loads: summarize major and typical plug loads for assigning values per zone
Building occupants: population counts, occupation schedules in different zones
Other major energy consuming loads: type (industrial process, air compressors, water heaters,
elevators), energy consumption, schedules of operation, etc.
Interview operators. The Project Sponsor may choose to interview the building operator. Building
operators can provide much of the above listed information, and also indicate if any deviation in the
intended operation of building equipment exists.
Make spot measurements. The Project Sponsor may find it necessary to record power draw on
certain circuits (lighting, plug load, HVAC equipment, etc.) to determine actual equipment operation
power.
Conduct short-term measurements. Data-logging monitoring equipment may be set up to record
system data as they vary over time. These data reveal how variable load data changes with building
operation conditions such as weather, occupancy, daily schedules, etc. These measurements may
include lighting systems, HVAC systems and motors. The period of measurement should be from one
to several weeks.
Obtain weather data. For calibration purposes, representative site weather data should be obtained
for a nearby NCDC site.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 58 -
Base Building Simulation Models
Once all necessary information is collected, the Project Sponsor should input the simulation data into
DOE-2 code to create the base building model. The modeler should refine the model to obtain the best
representation of the base building. Where possible, the modeler should use measured data and real
building information to verify or replace the program’s default values.
Minimum Energy Standards
The baseline model should comply with minimum state and federal energy standards with respect to the
following:
Baseline equipment/systems models should not include devices (e.g., lamps and ballasts) that are not
allowed to be installed under current regulations.
Baseline equipment models should meet prescriptive efficiency standards requirements for affected
equipment.
Baseline calculations do not have to comply with performance compliance methods that require the
project site to meet an energy budget.
If the existing conditions of the EEMs do not comply with minimum state and federal standards, the
modeler should calibrate the simulation model with the building as it currently exists, and then modify the
existing building model to reflect the baseline efficiencies. This modified, or baseline building is then
used as the base case for computing energy savings.
5.4.2 Calibration
After the base building model has been created and debugged, the modeler should make a comparison of
the energy flows and demand projected by the model to that of the measured utility data. All utility billing
data should be used in the analysis, electric as well as heating fuels, such as natural gas. The modeler may
use either monthly utility bills, or measured hourly data to calibrate the model when available. The
calibration process should be documented to show the results from initial runs and what changes were
made to bring the model into calibration. Statistical indices are calculated during the calibration process to
determine the accuracy of the model. If the model is not sufficiently calibrated, the modeler should revise
the parameters of the model and recalculate the statistics.
Hourly Data Calibration
In hourly calibration, two statistical indices are required to declare a model “calibrated”: monthly mean
bias error (MBE) and the coefficient of variation of the root mean squared error (CV (RMSE))2.
Equations related with the calculation of MBE and CV (RMSE) is listed below. The acceptable tolerances
for these values when using hourly data calibration are shown in Table 16.
𝑀𝐵𝐸 (%) =∑ (𝑀 − 𝑆)ℎ𝑟𝑚𝑜𝑛𝑡ℎ
∑ 𝑀ℎ𝑟𝑚𝑜𝑛𝑡ℎ × 100
2 Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Great Energy Predictor Shootout: Overview and
Discussion of Results,” ASHRAE Transactions Technical Paper, Vol. 100, pt. 2, June, 1994
Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Results of the 1993 Great Energy Predictor Shootout
to Identify the Most Accurate Method for Making Hourly Energy Use Predictions,”: ASHRAE Journal, pp. 72-81, March, 1994
Haberl, J. and S. Thamilseran, “Predicting Hourly Building Energy Use: The Great Energy Predictor Shootout II, Measuring
Retrofit Savings – Overview and Discussion of Results, ASHRAE Transactions, June, 1996.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 59 -
Where:
𝑀ℎ𝑟 = the measured kWh for any hour during the month
𝑆ℎ𝑟 = the simulated kWh for any hour during the month
𝐶𝑉𝐸 (𝑅𝑀𝑆𝐸𝑚𝑜𝑛𝑡ℎ) =√∑ (𝑀 − 𝑆)2
ℎ𝑟 × 𝑁ℎ𝑟 𝑚𝑜𝑛𝑡ℎ
∑ 𝑀ℎ𝑟𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀ℎ𝑟 = the measured kWh for any hour during the month
𝑆ℎ𝑟 = the simulated kWh for any hour during the month
𝑁ℎ𝑟 = the number of hours in the month
Table 16. Acceptable Tolerances for Hourly Data Calibration
Value
MBEmonth 10%
CV(RMSEmonth) 30%
Monthly Data Calibration
Comparing energy use projected by simulation to monthly utility bills is straightforward. First the model
is developed and run using weather data that corresponds to the monthly utility billing periods. Next
monthly-simulated energy consumption and monthly measured data are plotted against each other for
every month in the data set. Equations calculating the error in the monthly and annual energy
consumption are given below. The acceptable tolerances for these values when using monthly data
calibration are shown in Table 17.
𝐸𝑅𝑅𝑚𝑜𝑛𝑡ℎ(%) =(𝑀 − 𝑆)𝑚𝑜𝑛𝑡ℎ
𝑀𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀𝑚𝑜𝑛𝑡ℎ = the measured kWh for the month
𝑆𝑚𝑜𝑛𝑡ℎ = the simulated kWh for the month
𝐸𝑅𝑅𝑦𝑒𝑎𝑟 = ∑ 𝐸𝑅𝑅𝑚𝑜𝑛𝑡ℎ
𝑦𝑒𝑎𝑟
Table 17. Acceptable Tolerances for Monthly Data Calibration
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 60 -
Value
ERRmonth 25%
ERRyear 15%
5.4.3 Post-Installation Models
After the measures are installed, a post-installation model can be prepared. The post-installation model
should usually be the baseline model with the substitution of new energy-efficient equipment and
systems. This new model should also be calibrated and documented. The possible calibration mechanisms
are:
Using site survey data to validate that all of the specified equipment and systems are installed, have
the nameplate data used in the model, and are operating properly.
Using spot and/or short-term metering data to calibrate particular model modules of equipment,
systems or end-uses.
Using utility (15 minute, hourly, or monthly) metering data to calibrate the model, as was done with
the pre-installation model.
The above mentioned post-installation model calibration mechanisms are not necessarily mutually
exclusive. If the first two mechanisms are used the model can be calibrated soon after measure
installation. If the last mechanism is used then the model can only be calibrated after sufficient (e.g., 12
months) billing data are available. In some instances the post-installation model should be the only model
calibrated. This can occur when the baseline project site cannot be easily modeled due to significant
changes during the 12 months prior to the new measures being installed and thus the recent billing data
are not representative.
5.4.4 Detailed Energy Savings Calculations
Energy savings are determined from the difference between the outputs of the baseline and post-
installation models. Savings are determined with both models using the same conditions (weather,
occupancy schedules, etc.). To calculate savings, the energy consumption projected by the post-
installation model is subtracted from energy consumption projected by the baseline model. Energy
savings are calculated by the following equation.
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊ℎ𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 − 𝑘𝑊ℎ𝑝𝑜𝑠𝑡
Where:
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year.
𝑘𝑊ℎ𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 =The kilowatt-hour consumption of the baseline building operating under the same
conditions (weather, operation and occupancy schedules, etc.) as the post-installation
building.
𝑘𝑊ℎ𝑝𝑜𝑠𝑡 = The kilowatt-hour consumption of the post-installation building operating under the same
conditions (weather, operation and occupancy schedules, etc.) as the baseline building.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 61 -
6. Measurement Guidelines for Constant Load Motor Measures
6.1 Overview
This measurement and verification (M&V) method is appropriate for projects involving existing motors
serving a constant load being replaced with higher efficiency motors of equal or lesser capacity
(horsepower). The rated efficiency of the new motor must exceed the minimum efficiency standard
defined in the Table of Standard Motor Efficiencies in Appendix B to be eligible for the program.
Potential retrofit equipment includes:
Constant load chilled water, hot water, or condenser water pumps
Constant speed exhaust, return, and supply fans without dampers or pressure controls
Single-speed cooling tower fans
Constant load industrial processes
Similar capacity, constant speed, energy efficiency motors
Smaller, constant speed, energy efficiency motors when the existing motor is oversized
These M&V procedures are not appropriate for motor change outs that are accompanied by:
Changes in operating schedule
Changes in operating hours
Changes in flow rate
Changes in motor controls (except VSDs)
If the proposed retrofit does not meet the constant load requirements, or involves scheduling or
operational changes, refer to the Full M&V Guidelines for Generic Variable Loads in Chapter 10 for
appropriate M&V techniques.
Rebates are available for the installation of premium efficiency motors. Deemed savings are
calculated by completing the Premium Efficiency Motor Form.
In the C&I Standard Offer Program, the calculation of demand and energy savings for motor
replacements is based on the baseline and post-installation kW, the difference in efficiency of the baseline
and new motors, and the motor operating hours. The operating hours are assumed the same for existing
and new motors. The baseline motor efficiency is based on the minimum efficiency rating defined by the
Table for Standard Motor Efficiencies in Appendix B. The Table of Standard Motor Efficiencies is
categorized by motor size and rotation speed. The baselines for motors whose efficiencies are not listed in
the table will be determined on a case-by-case basis by CenterPoint Energy. The project sponsor must
provide demonstrable proof that energy efficiency was a key criterion in the motor-selection process in
order to qualify for incentives. No incentive payments are made for replacement motors with efficiencies
equal to or less than the baseline efficiency. In addition to having a higher efficiency than baseline
motors, all new motors should meet minimum equipment standards as defined by state and federal law.
The recommended M&V approach for motors includes some or all of the following data collection
activities:
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 62 -
Compiling inventories for existing and new motors
Short-term metering of existing motors to verify constant loading (if warranted)
Spot metering of all existing and new motors
Short-term metering of a sample of the new motors to determine operating hours
6.2 Pre-Installation Measurement Activities
The M&V steps that characterize the existing motors are:
1. Pre-installation equipment survey (to be conducted by the Sponsor)
2. Spot measurement of demand (kW), and short-term metering of existing motors, where needed
(to be conducted by the Sponsor)
3. Pre-installation inspection (to be conducted by CenterPoint Energy or its contractor)
6.2.1 Pre-Installation Equipment Survey
The Sponsor should conduct a pre-installation survey to inventory the equipment to be replaced and
record data about each motor in the Motor and VFD Inventory Form. Motor location and corresponding
facility mechanical plans should be included with the survey submittal as part of the Project Application.
At a minimum, the surveys should include the following for each existing motor:
Motor name
Load served
Motor location
Operating schedule
Equipment manufacturer
Nameplate data including model, horsepower, and speed
The baseline motor efficiency should be determined from the Table of Standard Motor Efficiencies based
on the existing motor data provided in the Project Application. The baselines for motors whose
efficiencies are not listed in the table will be determined on a case-by-case basis by CenterPoint Energy.
The project sponsor must provide demonstrable proof that energy efficiency was a key criterion in the
motor-selection process.
Any M&V activities that need to be conducted prior to the demolition of existing equipment (i.e., short-
term measurements) should take place at this time. Demolition of existing equipment and/or
installation of new equipment cannot begin until baseline M&V activities are completed, the pre-
installation inspection is completed, and CenterPoint Energy has approved the Project Application
and issued a Project Authorization.
6.2.2 Spot and Short-term Measurement of Existing Motors
To establish the baseline kW, the Sponsor must conduct spot measurements of the power draw of the
existing motors. If the constant load criterion cannot be verified by visual inspection, then short-term
metering of the power draw or current (amperes) of the existing motors may also be required.
The verification of constant motor loading by short-term metering is warranted in situations where the
effect of piping, valves, controls, or processes on motor load is uncertain. A motor load is considered to
be constant if 90% of all non-zero observations are within 10% of the running average kW. If short-
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 63 -
term metering demonstrates that the proposed retrofit does not meet the constant load definition, then the
Sponsor should refer to the Full M&V Guidelines for Generic Variable Loads in Chapter 10 for
appropriate M&V techniques.
To compensate for the variations in spot measurements that occur even in constant-load motors, the
Sponsor may need to develop normalization factors for groups of like motors serving similar loads. A
normalization factor is the ratio of a motor’s average current (from short-term metering) to its spot
measured current. CenterPoint Energy may require the use of a normalization factor for projects with a
group or groups of identical motors.
The minimum efficiency standard for the existing motor type is listed in the Table of Standard Motor
Efficiencies. If the efficiency of the existing motor is greater than or equal to the minimum efficiency
standard, then the baseline demand is equal to the spot measured value. If not, then the baseline demand is
calculated according to Equation below.
𝑘𝑊𝑝𝑟𝑒 =
𝜂𝑝𝑟𝑒
𝜂𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒× 𝑘𝑊𝑝𝑟𝑒,𝑚𝑒𝑡𝑒𝑟𝑒𝑑
Where:
𝜂𝑝𝑟𝑒=existing motor efficiency
𝜂𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 = standard minimum motor efficiency
𝑘𝑊𝑝𝑟𝑒,𝑚𝑒𝑡𝑒𝑟𝑒𝑑= spot measured existing motor demand, kW
6.2.3 Pre-Installation Inspection
CenterPoint Energy will conduct a pre-installation inspection to verify that the existing condition is as
reported in the pre-installation equipment survey in the Project Application. CenterPoint Energy will
require the Sponsor to make any necessary corrections to the Project Application based upon the results of
the inspection.
Demolition of existing equipment and/or installation of new equipment cannot begin until the pre-
installation inspection is completed and CenterPoint Energy has approved the Project Application
and issued a Project Authorization.
6.3 Post-Installation Measurement Activities
The M&V steps that characterize the new motors are:
1. Post-installation equipment survey (to be conducted by the Sponsor)
2. Spot measurements of the power draw (one-hour average values) of all the new motors (to be
conducted by the Sponsor)
3. Post-installation inspection (to be conducted by CenterPoint Energy or its contractor)
4. Short-term metering of operating hours for a sample of existing motors (to be conducted by the
Sponsor)
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 64 -
6.3.1 Post-Installation Equipment Survey
The Sponsor shall conduct a post-installation equipment survey and record data about each motor in the
Motor and VFD Inventory Form. The survey shall reflect the actual, as-built conditions of the project.
The post-installation survey will be included in the Installation Report.
6.3.2 Spot Measurements of Motor Demand
The Sponsor must conduct spot measurements of the power draw (one-hour average values) of each new,
high-efficiency motor in order to establish the post-installation demand. The Sponsor will report the
measured kW as part of the Installation Report.
6.3.3 Post-Installation Inspection
Once CenterPoint Energy receives the Installation Report for the motor project, CenterPoint Energy or its
contractor will conduct a post-installation inspection to verify that the equipment specifications are
correctly reported in the Installation Report. CenterPoint Energy will require the Sponsor to make any
necessary corrections to the Installation Report based upon the results of the inspection.
6.3.4 Short-Term Metering of Motor Operating Hours
Baseline motor operating hours are assumed to be the same as post-installation operating hours, and
should be determined after new motor installation. Short-term metering is used to determine both pre- and
post-installation operating hours.
After CenterPoint Energy approves the Installation Report, the Sponsor should begin short-term metering
of motor operating hours. The metering must be conducted for a minimum period of one week, or a
sufficient amount of time to capture the full range of operation. The motor annual operating hours are
calculated from the metering data according to Equation below.
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙 =𝐻𝑜𝑢𝑟𝑠𝑜𝑛
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑× 8760
Where:
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙 = Average annual operating hours
𝐻𝑜𝑢𝑟𝑠𝑜𝑛 = Operating hours observed during the metering period
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = Total number of hours in the metering period
For projects in which a large number of equal-sized motors with the same application and operating
schedule will be replaced, metering may be conducted on a sample of the motors and the results
extrapolated to the applicable population. If this approach is adopted, CenterPoint Energy will assist the
Sponsor in selecting the motors to be metered.
The Sponsor should include electronic copies of the unprocessed data files as part of the Savings Report.
6.4 Calculation of Peak Demand and Energy Savings
Demand savings are calculated for equipment that operates during the summer or winter peak period,
which is defined as weekdays between the hours of 1 p.m. and 7 p.m. from June 1 through September 30
during summer and weekdays between the hours of 6 a.m. to 10 a.m. and 6 p.m. to 10 p.m. from
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 65 -
December 1 through February 28 during winter. The peak demand savings and energy savings are
calculated according to Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑝𝑟𝑒 − 𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑒𝑡𝑒𝑟𝑒𝑑
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑠𝑎𝑣𝑒𝑑 × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙
Where:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = The kilowatt savings realized during the year
𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑒𝑡𝑒𝑟𝑒𝑑= Spot Measured New Motor Demand, kW
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year
The Sponsor reports the peak demand and energy savings to CenterPoint Energy in the project Savings
Report.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 66 -
7. Prescriptive Program: Premium Efficiency Motors
7.1 Qualifying Equipment
The installed premium efficiency motor must meet the NEMA efficiency standards listed in the table
below.
NEMA Full Load Efficiencies (%)
HP 1,200 RPM 1,800 RPM 3,600 RPM
ODP TEFC ODP TEFC ODP TEFC
1 82.50% 82.50% 85.50% 85.50% 77.00% 77.00%
1.5 86.50% 87.50% 86.50% 86.50% 84.00% 84.00%
2 87.50% 88.50% 86.50% 86.50% 85.50% 85.50%
3 88.50% 89.50% 89.50% 89.50% 85.50% 86.50%
5 89.50% 89.50% 89.50% 89.50% 86.50% 88.50%
7.5 90.20% 91.00% 91.00% 91.70% 88.50% 89.50%
10 91.70% 91.00% 91.70% 91.70% 89.50% 90.20%
15 91.70% 91.70% 93.00% 92.40% 90.20% 91.00%
20 92.40% 91.70% 93.00% 93.00% 91.00% 91.00%
25 93.00% 93.00% 93.60% 93.60% 91.70% 91.70%
30 93.60% 93.00% 94.10% 93.60% 91.70% 91.70%
40 94.10% 94.10% 94.10% 94.10% 92.40% 92.40%
50 94.10% 94.10% 94.50% 94.50% 93.00% 93.00%
60 94.50% 94.50% 95.00% 95.00% 93.60% 93.60%
75 94.50% 94.50% 95.00% 95.40% 93.60% 93.60%
100 95.00% 95.00% 95.40% 95.40% 93.60% 94.10%
125 95.00% 95.00% 95.40% 95.40% 94.10% 95.00%
150 95.40% 95.80% 95.80% 95.80% 94.10% 95.00%
200 95.40% 95.80% 95.80% 96.20% 95.00% 95.40%
7.2 Savings Calculations
The savings are calculated based on Equations below. The motor incentive form applies these equations
automatically to calculate savings for installation of premium efficiency motors.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 0.746 × ℎ𝑝 × %𝐿𝑜𝑎𝑑 × 𝐶𝐹 × (1
𝜂𝐸𝑃𝐴𝐶𝑇−
1
𝜂𝑁𝐸𝑀𝐴)
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑠𝑎𝑣𝑒𝑑 × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = The kilowatt savings realized during the year
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year
ℎ𝑝 =The horsepower of the motor
%𝐿𝑜𝑎𝑑 =Stipulated %load of the motor
𝐶𝐹 =Stipulated coincident factor
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 67 -
𝜂𝐸𝑃𝐴𝐶𝑇=Baseline efficiency standard. Based on 1992 EPACT standards
𝜂𝑁𝐸𝑀𝐴=New motor efficiency standard. Based on NEMA premium efficiency standards
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙= Stipulated Operating hours. Different values for C&I applications
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 68 -
8. Measurement Guidelines for Variable Speed Drives on Constant Baseline
Motor Measures
8.1 Overview
Installing variable-speed drive (VSD) controllers on motors that serve a constant baseline load requires a
modified motor M&V procedure. Potential retrofit projects that might include VSDs include:
Converting constant air volume (CAV) systems to variable air volume (VAV)
Retrofitting central chiller plants
Replacing standard efficiency electric motors with high efficiency models
Motors that are scheduled for the installation of VSDs follow the same Pre-Installation Measurement
Activities described in chapter 6. If the efficiency of the existing motor is greater than or equal to the
minimum listed in the Table of Standard Motor Efficiencies, then the baseline demand is equal to the spot
measured value; if not, then it is calculated.
After the VSD and/or associated project retrofit has been installed, the Sponsor will again Post-
Installation Measurement Activities. The Post-installation equipment survey and the Post-
installation inspection procedures are the same as described earlier in this chapter.
After CenterPoint Energy has conducted a post-installation inspection and approved the project
Installation Report, the Sponsor should begin short-term metering1 of the power draw (kW) of the
motor/VSD combination (this accounts for the VSD demand/energy usage). The data must be recorded at
intervals of 15 minutes or less. However, averaged one-hour values are used in the calculation of demand
and energy savings. For calculating peak demand, the metering must occur during one of the peak
periods.
The duration of the metering period must be sufficient to capture the full range of motor operation. If the
motor load varies only on a daily basis and not seasonally, then a metering period of one week is
generally sufficient. If the motor load or operating hours vary with weather or other seasonal parameters
(e.g., production schedules, school calendars), then at least two weeks of metering during each operating
period is generally necessary. For example, if the motor serves cooling equipment, then the metering
should occur for at least two weeks during the winter months and two weeks during the summer months.
The metering data are used to determine three values:
Peak period demand (kW): Equal to the maximum-recorded peak period demand (one hour average
values, where the summer peak period is defined as weekdays, between the hours of 1 PM and 7 PM,
from June 1 through September 30 and the winter peak period is defined as weekdays, from 6 AM to
10 AM and 6 PM to 10PM, from December 1 through February 28).
Average demand (kW): Equal to the average recorded demand. For motors with seasonal load
patterns, the average demand should be weighted according to the relative length of each seasonal
period (see VSD example).
1 Long-term monitoring may be required for motors with non-uniform or unpredictable load patterns.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 69 -
Annual operating hours: Calculated from the metering data. For motors with seasonal load patterns,
the annual operating hours should be weighted according to the relative length of each seasonal
period.
For projects in which a large number of equal-sized motors with the same application and operating
schedule will be replaced, M&V may be conducted on a sample of the motors and the results extrapolated
to the applicable population. If this approach is adopted, the utility Program Manager will select the
motors to be metered.
The peak demand savings and energy savings are calculated according to Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑝𝑟𝑒 − 𝑘𝑊𝑝𝑒𝑎𝑘 𝑝𝑒𝑟𝑖𝑜𝑑
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = (𝑘𝑊𝑝𝑟𝑒 − 𝑘𝑊𝑝𝑜𝑠𝑡 𝑎𝑣𝑒) × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙
Where:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = The kilowatt savings realized during the year
𝑘𝑊𝑝𝑒𝑎𝑘 𝑝𝑒𝑟𝑖𝑜𝑑= Spot measured new motor demand in peak period, kW
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year
𝑘𝑊𝑝𝑜𝑠𝑡 𝑎𝑣𝑒= Measured averaged post-installation motor kW
8.2 HVAC Variable Frequency Drive (VFD) on Air Handler Unit (AHU) Supply
Fans deemed method
This deemed method is applicable for the installation of VFDs on existing AHU supply fans. This
measure accounts for the interactive air-conditioning demand saving during the utility defined peak
period.
The baseline is a centrifugal supply fan with a single-speed motor, a direct expansion (DX) air
conditioning (AC) unit, and VAV boxes. The motor is a standard efficiency motor based on ASHRAE
Standard 90.1-2004 or other specific standards. The AC unit has standard cooling efficiency based on
ASHRAE 90.1-2004. The part-load fan control is either an outlet damper, inlet damper or inlet guide
vane.
The high efficiency condition is an installation of a VFD on an AHU supply fan. The existing damper or
inlet guide vane will be removed or set completely open permanently after installation. The VFD will
maintain a constant static pressure by adjusting fan speed and delivery the same amount of air as the
baseline condition. Deemed demand and Energy savings will be calculated based on Appendix C.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 70 -
9. Measurement Guidelines for Application of Window Films
9.1 Overview
The installation of window films decreases the window shading coefficient and reduces the solar heat
transmitted to the building space. During months when perimeter cooling is required in the building, this
measure decreases cooling energy use.
The simplified M&V guidelines developed for this measure are applicable for window films applied to
south- and west-facing windows only. The measure demand and energy savings are calculated based on
the window-film area, change in shading coefficient, and cooling equipment efficiency. Savings for
window film measures are determined using the Window Film Worksheet, available on the CenterPoint
Energy C&I Standard Offer Program Web site at https://centerpoint.anbetrack.com/.
The following steps comprise the simplified M&V procedure for window-film installations.
1. Collect data characterizing the existing south and west windows including: shading coefficient,
type of interior shading devices, and presence of exterior shading from buildings or other
obstacles. Identify the type and rated efficiency of the cooling equipment in the building.
2. Document the installed window-film shading coefficient and window application area for the
south and west windows.
3. Based on the characteristics of the existing windows, newly installed window-films, and cooling
equipment; determine the annual demand and energy savings using the window-film calculation
spreadsheet.
9.2 Pre-Installation M&V Activities
9.2.1 Pre-Installation Site Survey
The goal of the pre-installation site survey is to identify the existing south and west window
characteristics. At a minimum, the surveys should include the following data for the south and west
windows:
Existing window description
Existing window shading coefficient
Window area by cardinal orientation
Description of interior shading devices
If applicable, an estimate of combined window-interior shading coefficient determined from 1997
ASHRAE Fundamentals, Chapter 29, Tables 24-29
Description of exterior shading
Description of building cooling equipment
This information will be included as part of the Project Application (PA). For window film measures, the
PA should be submitted after the project site has been identified. Submitting the PA prior to site
identification could result in significant under or over estimation of savings since variations in window
area and shading characteristics between sites are large.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 71 -
9.2.2 Pre-Installation Inspection
After the PA is submitted, CenterPoint Energy or its contractor will conduct a pre-installation inspection
to verify that the Sponsor has properly documented the baseline characteristics of the building, including
window area by orientation, shading devices, and cooling equipment type. The M&V administrator will
inform the Project Sponsor of any necessary corrections to be made to the pre-installation survey based on
the results of the inspection. Removal or demolition of existing shading devices and equipment or
installation of new films, shading devices, and equipment cannot commence until the pre-installation
inspection is completed.
9.3 Post-Installation M&V Activities
9.3.1 Post-Installation Survey
The Sponsor should provide manufacturer’s data for the window films, specifically the National
Fenestration Rating Council (NFRC) shading coefficient for the installed window films. The area of the
window films applied for each different solar orientation must also be specified. These data are required
as part of the Installation Report (IR).
9.3.2 Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify the documented
characteristics of the building, windows, shading, cooling equipment, and window films. The M&V
administrator will inform the Project Sponsor of any necessary corrections to be made to the pre-
installation survey based on the results of the inspection. If the project is comprised of many small
installations, CenterPoint Energy will inspect a randomly selected sample of the window-film
installations completed by the Sponsor.
9.4 Calculation of Energy Savings
The window film demand and energy savings result from a reduction in demand and energy use of
cooling equipment. Use the Window Film Worksheet to calculate savings. The savings estimates rely on
tabulated values of solar heat gain factors (SHGF) as published in the 1997 ASHRAE Fundamentals,
Chapter 29, and Table 17. The ASHRAE data represent the amount of solar radiation that is transmitted
through single-pane clear glass for a cloudless day at 32o N Latitude for the 21
st day of each month by
hour of day and solar orientation. The solar gain values are translated to electric energy savings by
considering the cooling equipment efficiency. In the calculation, the cooling equipment efficiency equals
the rated efficiency of the installed equipment or the ASHRAE Standard 90.1-1989 minimum cooling
equipment efficiency (see the Standard Cooling Equipment Tables – Appendix A), whichever is more
efficient.
To determine the coincident, peak summer demand savings associated with window films, the highest,
hourly, ASHRAE SHGF value that occurs during the summer peak period is identified for each of the
south and west building orientations. The available data nearest the CenterPoint Energy service territory
are presented in Table 18. The building demand savings are determined from the maximum of these peak
SHG values for the applicable window orientations.
To determine cooling energy savings associated with window films, the ASHRAE SHGF data are
aggregated into daily totals for weekdays during the months of April through October. These totaled,
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 72 -
SHG values are presented in Table 18. In the table, orientations that are symmetrical relative to the
southern sky have the same SHGF values.
Table 18. Solar Heat Gain Determined for 32°N Latitude
Orientation Solar heat gain, a.k.a
SHG (Btu/ft2-year)
Peak hour solar heat
gain, a.k.a. SHGF
(Btu/hr-ft2-year)
SE 158,844 25
SSE 134,794 26
S 120,839 44
SSW 134,794 106
SW 158,844 164
WSW 169,696 196
W 163,006 198
WNW 139,615 170
NW 107,161 117
The data from Table 18 are used to determine the demand and energy savings associated with the window
film measure using the equations below. Equation below presents the demand savings calculation.
Demand savings are determined for the window orientation that results in the highest savings. Demand
savings by orientation are not additive.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = max𝑖
𝐴𝑓𝑖𝑙𝑚,𝑖 × 𝑆𝐻𝐺𝐹𝑖 × (𝑆𝐶𝑝𝑟𝑒,𝑖 − 𝑆𝐶𝑝𝑜𝑠𝑡,𝑖)
𝐶𝑜𝑛𝑣𝑒𝑟𝑠𝑖𝑜𝑛 𝐹𝑎𝑐𝑡𝑜𝑟 × 𝐶𝑂𝑃
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑𝐴𝑓𝑖𝑙𝑚,𝑖 × 𝑆𝐻𝐺𝑖 × (𝑆𝐶𝑝𝑟𝑒,𝑖 − 𝑆𝐶𝑝𝑜𝑠𝑡,𝑖)
𝐶𝑜𝑛𝑣𝑒𝑟𝑠𝑖𝑜𝑛 𝐹𝑎𝑐𝑡𝑜𝑟 × 𝐶𝑂𝑃
𝑛
𝑖=1
Where:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = The peak kilowatt savings realized during the year
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year
𝐴𝑓𝑖𝑙𝑚,𝑖= Area of window film applied to orientation 𝑖, ft2
𝑆𝐻𝐺𝐹𝑖= Peak solar heat gain factor for orientation 𝑖 of interest from Table 18 on vertical glazing at 32N
latitude, Btu/hr-ft2-yr
𝑆𝐻𝐺𝑖= Peak solar heat gain for orientation 𝑖 of interest from Table 18 on vertical glazing at 32N latitude,
Btu/ft2-yr
𝑆𝐶𝑝𝑟𝑒,𝑖= Shading coefficient for existing glass/interior-shading device applied to orientation 𝑖
𝑆𝐶𝑝𝑜𝑠𝑡,𝑖= Shading coefficient for new glass/interior-shading device applied to orientation 𝑖
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 73 -
𝐶𝑂𝑃= Cooling equipment COP or SEER based on ASHRAE Standard 90.1-1989 or actual COP of
equipment, whichever is greater
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 74 -
10. Measurement and Verification for Generic Variable Loads
10.1 Overview
Projects that improve the efficiency of end-uses that exhibit variable energy demand or operating hours
may require continuous post-installation metering to measure and verify energy savings. Examples of
such projects include:
Upgrading building automation systems
Installing new industrial process equipment or systems
Comprehensive chiller plant modifications, including chillers, cooling towers, pumps, etc.
The use of continuous metering for measurement and verification (M&V) of variable loads normally
involves four steps:
1. Surveying the pre-installation system(s). As with all M&V methods, the Sponsor must audit
existing systems to document relevant components (e.g., piping and ductwork diagrams, control
sequences, and operating parameters).
2. Establishing a baseline model (e.g., an equation that determines energy use when key independent
variables are known). All, or a representative sample, of the existing systems should be metered
to establish regression-based equations or curves for defining baseline system energy use as a
function of appropriate variables (e.g., weather or cooling load). Adjustments may be required for
the models to comply with minimum energy efficiency standards.
3. Monitoring post-installation energy use and/or independent variables e.g., weather. Monitoring
can be done continuously throughout a full year or for representative periods of time during each
performance year.
4. Determining the savings by subtracting the post-installation energy use from the baseline energy
use (as indicated in the baseline model).
Most energy retrofits can be monitored and savings verified using this method. However, there are
retrofits that cannot be quantitatively verified using continuous post-installation metering, such as
window tinting.
The M&V method described here is based on Option B of the 2007 International Performance
Measurement and Verification Protocol (IPMVP). Valuable insights on this method can be found in the
IPMVP.
10.2 Pre-Installation M&V Activities
To establish the baseline operating characteristics of the existing systems, the following steps are taken:
1. The Sponsor conducts a pre-installation equipment survey.
2. CenterPoint Energy and/or its contractor conduct a pre-installation inspection.
3. The Sponsor conducts any necessary M&V activities.
4. The Sponsor develops a baseline energy consumption model based on metered system data.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 75 -
10.2.1 Pre-Installation Equipment Survey
The Sponsor is required to conduct a pre-installation equipment survey, to be submitted as part of the
Project Application. The purpose of the pre-installation equipment survey is to inventory all existing
equipment to be affected by a project, and to propose the replacement equipment to be installed. For each
piece of equipment, the survey should list (as applicable): location, manufacturer, model number, rated
capacity, energy use factors (such as voltage, rated amperage, MBtu/hr, fixture wattage), nominal
efficiency, the load served, and any independent variables that affect system energy consumption.
10.2.2 Pre-Installation Inspection
CenterPoint Energy or its contractor will conduct a pre-installation inspection to verify that the Sponsor
has properly documented the baseline equipment. If significant errors are found in the survey, CenterPoint
Energy will inform the Sponsor that the submitted survey (which is a part of the Project Application)
must be corrected and resubmitted.
10.2.3 Pre-Installation Data Collection
Before making any efficiency modifications to existing equipment, the Sponsor must monitor the
following variables simultaneously:
Independent variables that affect energy use. Examples of such data are ambient temperature,
control outputs, flow rate, cooling tons, and building occupancy.
System energy consumption. Energy demand (e.g., kW) of the equipment to be affected by the
project metered over a representative time period sufficient to document the full range of system
operation.
Typically, metering observations should be made in 15-minute intervals, unless the Sponsor can
demonstrate that longer intervals are sufficient and CenterPoint Energy approves such intervals.
If multiple, identical equipment components or systems are to be modified (e.g., multiple heating boilers),
the M&V plan may specify metering of only a statistical sampling of the equipment.
In some cases, a dependent variable may serve as an accurate proxy for energy demand and may be
monitored in lieu of energy metering. Examples of dependent variables that may be used as a proxy for
energy include amperes and rotating equipment speed. If proxy variables are used, the Sponsor must show
that the proxy variable is representative of the actual demand.
10.2.4 Baseline Model Development
The energy use of most projects will be influenced by independent variables. For such projects, a model
must be developed (typically using regression techniques) that links independent-variable data to energy
use. The methodologies for creating such a model must be included in the Project Application and
approved by CenterPoint Energy.
The results of energy-input metering and variable(s) monitoring will be used to establish the pre-
installation relationship between these quantities. This relationship will be known as the “System
Baseline Model” and will probably be presented in the form of an equation. Regression analysis is
typically used to develop such an equation, although other mathematical methods may be approved. If
regression analysis is used, it must be demonstrated that that the model is statistically valid.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 76 -
The criteria for establishing statistical validity of the model are:
The model makes intuitive sense; e.g., the explanatory variables are reasonable, and the coefficients
have the expected sign (positive or negative) and are within an expected range (magnitude).
The modeled data represent the population.
The model’s form conforms to standard statistical practice and modeling techniques for the system in
question.
The number of coefficients is appropriate for the number of observations.
The T-statistic for each term in the regression equation is equal to at least 2 (indicates with 95%
confidence that the associated regression coefficient is not zero). The regression R2 is at least 80%.
All data entered into the model are thoroughly documented and model limits (range of independent
variables for which the model is valid) are specified.
Raw data used in model development must be submitted with the Project Application or Installation
Report. CenterPoint Energy or its contractor will make a final determination on the validity of models and
monitoring plans and may request additional documentation, analysis, or metering as necessary.
10.2.5 Compliance with Energy Standards
The baseline model must comply with all applicable federal and state energy standards and codes. If any
existing equipment that will be part of the project does not meet the applicable standards, the Sponsor
must document how the baseline model will be adjusted to account for the standards. It is possible that
two baseline models will be developed – an existing system baseline model and a minimum-standard
system baseline model. In general, however, the M&V plan should document how baseline values are in
compliance, or will be adjusted to comply, with the following:
Baseline equipment characterization should meet prescriptive efficiency standards requirements for
affected equipment
The baseline does not have to comply with performance compliance methods that require the project
site to meet an energy budget.
Demand and energy savings should be calculated with the incorporation of minimum state and federal
energy efficiency standards or codes into the determination of baseline energy use.
10.3 Post-Installation M&V Activities
To establish the post-installation operating characteristics of the affected systems, the following steps are
taken:
1. The Sponsor conducts a post-installation equipment survey.
2. CenterPoint Energy and/or its contractor conduct a post-installation inspection.
3. The Sponsor conducts any necessary M&V activities.
10.3.1 Post-Installation Equipment Survey
The Sponsor is required to conduct a post-installation equipment survey to be submitted as part of the
Installation Report. The purpose of this equipment survey is to document the equipment that was actually
installed as part of a project. For each piece of equipment, the survey should list (as applicable): location,
manufacturer, model number, rated capacity, energy use factors (such as voltage, rated amperage,
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 77 -
MBtu/hr, wattage), nominal efficiency, the load served, and any independent variables that affect system
energy consumption.
10.3.2 Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify that the
Sponsor has properly documented the installed equipment. After the inspection, CenterPoint
Energy will either accept or reject the Installation Report based on the inspection results and
project review.
10.3.3 Post-Installation Data Collection
After the retrofit, the Sponsor must monitor one or both of the following variables simultaneously:
Independent variables that affect energy use. Examples of such data are ambient temperature,
control outputs, flow rate, cooling tons, and building occupancy.
System energy consumption. Energy demand (e.g., kW) of the equipment to be affected by the
project metered over a representative time period sufficient to document the full range of system
operation.
The variable(s) that must be monitored will depend on the savings calculation methodology used for the
retrofit, as described further in the next section. Note that the same guidelines for pre-installation data
collection should be followed for all post-installation data collection.
10.4 Calculation of Demand and Energy Savings
There are two approaches for calculating demand and energy savings from generic variable load projects.
Both approaches require pre- and post-installation metering. The pre-installation metering includes short-
term measurements of equipment demand and metering of independent variables. The pre-installation
metering is necessary to develop the baseline energy use model.
For the post-installation monitoring, the first approach requires continuous metering of demand and
independent variables. The second approach relies on short-term measurements of demand and
continuous metering of independent variables. The two methods are summarized below.
1. Short-term, pre-installation metering of demand and independent variables to develop baseline
model. Continuous measurement of post-installation demand and the independent variables used
in the baseline model. Post-installation variable data are used with the baseline model to calculate
baseline energy use.
2. Short-term, pre-installation metering of demand and independent variables to develop baseline
model. Short-term, post-installation metering of demand and independent variables to develop
post-installation model. Continuous measurement of post-installation variables. Post-installation
variable data are used with the baseline and post-installation models to calculate baseline and
post-installation energy use.
10.4.1 First Approach: Metering Post-Installation Energy Use & Variables
To calculate energy savings using the first approach, the Sponsor will monitor demand and the same
independent variables that were used to develop the System Baseline Model after installing the project.
The Sponsor will then compare metered post-installation energy use with pre-installation energy use as
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 78 -
estimated by inputting the post-installation monitored independent variables into the System Baseline
Model. Demand and energy savings will be calculated using the following equations:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑝𝑟𝑒,𝑚𝑎𝑥 − 𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑(𝑘𝑊𝑝𝑟𝑒,𝑖– 𝑘𝑊𝑝𝑜𝑠𝑡−𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑,𝑖)
𝑛
𝑖=1
Where:
𝑘𝑊𝑝𝑟𝑒,𝑚𝑎𝑥 = Maximum, pre-installation equipment demand occurring during utility peak coincident load
period
𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥 = Maximum, post-installation equipment demand occurring during utility peak coincident
load period
𝒌𝑾𝒑𝒓𝒆,𝒊= Baseline kW calculated from Baseline Model and corresponding to same time interval 𝒊, system
output, weather, etc., conditions as 𝒌𝑾𝒑𝒐𝒔𝒕,𝒊
𝒌𝑾𝒑𝒐𝒔𝒕−𝒎𝒆𝒂𝒔𝒖𝒓𝒆𝒅,𝒊= Measured kW obtained through continuous or representative period, post-installation
metering
10.4.2 Second Approach: Metering Post-Installation Variables
To calculate energy savings using the second approach, the Sponsor must first develop a Post-Installation
System Model for use as a proxy for direct post-installation energy use measurement. Then, the Sponsor
monitors the relevant independent variables and uses that data to estimate post-installation energy use.
Note that the development of the Post-Installation System Model is subject to the same requirements
outlined for development of the Baseline System Model. Once the post-installation energy use is
estimated, energy savings over the course of a single observation interval will be calculated using the
following equations:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑝𝑟𝑒,𝑚𝑎𝑥 − 𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑(𝑘𝑊𝑝𝑟𝑒,𝑖– 𝑘𝑊𝑝𝑜𝑠𝑡,𝑖)
𝑛
𝑖=1
Where:
𝑘𝑊𝑝𝑟𝑒,𝑚𝑎𝑥 = Maximum, pre-installation equipment demand occurring during utility peak coincident load
period
𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥 = Maximum, post-installation equipment demand occurring during utility peak coincident
load period
𝒌𝑾𝒑𝒓𝒆,𝒊= Baseline kW calculated from Baseline Model and corresponding to same time interval 𝒊, system
output, weather, etc., conditions as 𝒌𝑾𝒑𝒐𝒔𝒕,𝒊
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 79 -
𝑘𝑊𝑝𝑜𝑠𝑡,𝑖 = Post-installation kW calculated from Post-Installation Model and corresponding to the
measured time interval; measured system output, measured weather variables, etc. in the post-
installation period
For a particular observation interval, the monitored data must be applied to the Baseline System Model
and to the Post-Installation Model to determine the baseline-system energy and post-installation system
energy input. The modeled-system post-installation is then subtracted from the baseline energy input
value. Energy savings are determined by multiplying this difference by the length of the observation
interval.
10.5 Project-Specific M&V Issues
Specific M&V issues that need to be addressed for generic variable load projects include:
Determination of post-installation metering approach -- i.e., monitoring of energy use or post-
installation variables.
Modeling methodology for Baseline System Model(s) and Post-Installation Model (if used).
How minimum energy efficiency standards will be defined for the Baseline System Model?
Identification of appropriate variables.
Duration of baseline and post-installation monitoring.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 80 -
11. Measurement and Verification Using Billing Analysis and Regression
Models
11.1 Overview
Billing analysis involves the use of regression models with historical utility billing data (kW and kWh) to
calculate annual demand and energy savings. In general, billing analysis is used with complex equipment
retrofits and controls projects. Examples of the types of projects where billing analysis may be employed
include the installation of an energy management control system (EMCS), and a comprehensive building
retrofit involving multiple types of energy efficiency measures (EEMs).
Billing analysis provides retrofit performance verification for projects where whole-facility baseline and
post-installation data are available. Billing analysis usually involves collection of historical whole-facility
baseline energy use data and a continuous measurement of the whole-facility energy use after measure
installation. Baseline and periodic inspections of the equipment may also be warranted. Energy
consumption is calculated by developing statistically representative models (multivariate regression
models) of historical whole-facility energy consumption (kWh).
The M&V method described here is based, in part, on Option C of the 2001 International Performance
Measurement and Verification Protocol (IPMVP). Valuable insights on utility bill analysis can be found
in the IPMVP.
11.2 Baseline and Post-Retrofit Data Collection
Collecting and validating data, as well as ensuring alignment of data start and end dates are important
elements of billing analysis. Data types and some data analysis protocols are discussed below.
11.2.1 Data Types
As input to the multivariate regression models, billing data provide the basis for calibrating models and
post-installation energy use. Site data provide a means for controlling changes in energy use not
associated with measure installation. These data elements are discussed below.
Monthly Energy Billing Data. There are typically two types of monthly energy billing data; total
energy usage for the month, or energy usage aggregated by time-of-use periods. While either type of
data can be used with a regression model, time-of-use is preferable as it provides more insight into
usage patterns.
Interval Demand Billing Data. This type of billing data records the average demand for a given
interval (e.g., 15 minutes) associated with the billing period.
Site Data. Site data provide the information necessary to account for either changes in or usage of
energy consumption that is not associated with the retrofit equipment. Typical site data that can be
incorporated in regression models include weather parameters, occupancy, facility square footage and
operating hours. These data are typically used to help define the independent variables that explain
energy consumption or change associated with equipment other than the equipment installed as part
of an EEM.
11.2.2 Data Analysis Protocols
The following are some of the required data analysis protocols:
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 81 -
Baseline Energy Consumption. This regression analysis requires at least 12 months’ worth of data
prior to the date of installation. However, if energy consumption is sensitive to weather or other
highly variable factors, then at least 24 months’ worth of data are required.
Post-installation Energy Consumption. This regression analysis requires at least nine months, and
preferably twelve months of data after the date of installation to determine impacts for the first year.
Outliers. Outliers are data beyond the expected range of values (e.g., a data point more than two
standard deviations away from the average of the data). However, the elimination of outliers should
be explained. It is not sufficient to eliminate a data point because it is beyond the expected range of
values. If there is reason to believe that the data point is abnormal because of specific mitigating
factors, then it can be eliminated from the analysis. Nevertheless, if a reason for the unexpected data
point cannot be found, it should be included in the analysis. Outliers should be defined based on
“common sense” as well as common statistical practice. Outliers can be defined in terms of
consumption changes and actual consumption levels.
11.3 Calculation of Energy Savings: Multivariate Regression Method
Multivariate regression is an effective technique that controls for non-retrofit-related factors that affect
energy consumption. If the site data (all relevant explanatory variables, such as weather, occupancy, and
operating schedules) are available and/or collected, the technique should result in more accurate and
reliable savings estimates than a simple comparison of pre- and post-installation energy consumption.
The use of the multivariate regression approach is dependent on and limited by the availability of site and
billing data. The decision to use a regression analysis technique should be based on the availability of this
information. Thus, on a project-specific basis, it is critical to investigate the EEM dependent and
independent variables that have direct relationships to energy use. Data need to be collected for these
variables in a suitable format over a significant period of time.
Separate models may be proposed that define pre-installation energy use and post-installation energy use
with savings equal to the difference between the two equations. It is assumed, however, that a single
“savings” model will be simpler and generate more reliable estimates since it is also based on more data
points.
11.3.1 Overview of the Regression Approach
Regression models should be developed that describe pre-installation and post-installation energy use for
the affected site (or sites), taking into account all explanatory variables.
For projects with time-of-use utility billing data, the regression models should yield savings by hour or
critical time-of-use period. For projects with only monthly consumption data, the models should be used
to predict monthly savings.
11.3.2 Standard Equation for Regression Analysis
In the regression analysis, utility billing data (monthly or hourly) on a project-specific basis are used to
develop the models for comparing the pre-installation energy use to post-installation energy use. After
adjusting for non-retrofit-related factors in the models, the models’ energy use difference is defined as the
gross performance impact of the EEMs.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 82 -
The regression equations should be specified so as to yield as much information as possible about savings
impacts. For example, with hourly data, it should be possible to estimate the savings impacts by time of
day, day of week, month, and year. With only monthly data, however, it is only possible to determine the
effects by month or year. Data with a frequency lower than monthly should not be used under any
circumstances.
11.3.3 Independent Variables
Independent variables that affect energy consumption should be specified for use in the regression
analysis. These variables can include weather, occupancy patterns, and operating schedules.
If the multivariate regression models discussed above incorporate weather in the form of heating degree-
days (HDD) and/or cooling degree-days (CDD), the following issues must be considered:
The use of the building “temperature balance point” for defining degree-days versus an arbitrary
degree-day temperature base.
The relationship between temperature and energy use that tends to vary depending upon the time of
year. For example, a temperature of 55F in January has a different implication for energy usage than
the same temperature in August. Thus, seasonality should be addressed in the model.
11.3.4 Testing Statistical Validity of Models
The statistical validity of the final regression model should be tested by the Sponsor and CenterPoint
Energy or its contractor and should demonstrate the following:
The model makes intuitive sense; e.g., the independent variables are reasonable, and the coefficients
have the expected sign (positive or negative) and are within an expected range (magnitude).
The modeled data are representative of the population.
The form of the model conforms to standard statistical practice.
The number of coefficients is appropriate for the number of observations (approximately no more
than one explanatory variable for every five data observations).
The T-statistic for all key parameters in the model is at least 2 (95% confidence that the coefficient is
not zero).
The model is tested for possible statistical problems and, if present, appropriate statistical techniques
are used to correct for them.
All data input to the model are thoroughly documented, and model limits (range of independent
variables for which the model is valid) are specified.
11.3.5 Compliance with Energy Standards
When using billing analysis methods, the baseline should comply with minimum state and federal energy
standards with respect to the following:
Baseline equipment/systems should not include devices (e.g., lamps and ballasts) that are not allowed
to be installed under current regulations.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 83 -
Baseline equipment should meet prescriptive efficiency standards requirements for affected
equipment.
Surveys and analysis correction methods (potentially outside of the model) should be documented in
a project-specific M&V plan.
The baseline does not have to comply with performance compliance methods that require the facility
to meet an energy budget.
11.3.6 Detailed Calculation Issues
The details of the savings calculations are dependent on such issues as:
The use of hourly versus monthly utility meter billing data
The format of the data (e.g., corresponding to same time interval as the billing data) and availability
of all relevant data for explanatory variables
The amount of available energy consumption data
The use of actual or typical data to calculate savings
Compliance with energy standards when calculating baseline energy use. Energy savings should be
calculated with the incorporation of minimum state and federal energy efficiency standards or codes
into the determination of baseline energy use.
11.4 Project Specific M&V Issues
When billing analysis methods are used, the project specific M&V plan should address, in addition to
other topics generic to all M&V methods, the following:
How billing data covering an adequate period of time should be used to calculate savings in the
performance year?
How the baseline will be adjusted in order to have the baseline meet minimum energy standards?
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 84 -
12. Measurement and Verification Using Calibrated Simulation Analysis
12.1 Overview
Computer Simulation Analysis for measurement and verification of energy savings is used when the
energy impacts of the energy efficiency measures (EEMs) are too complex1 or too costly to analyze with
traditional M&V methods. Situations where computer-based building energy simulations may be
appropriate include:
The EEM is an improvement or replacement of the building energy management or control system.
There is more than one EEM and the degree of interaction between them is unknown or too difficult
or costly to measure.
The EEM involves improvements to the building shell or other measures that primarily affect the
building load (e.g., thermal insulation, low-emissivity windows).
Conducting simulation analysis is a time-consuming task. In some instances, the high costs of conducting
simulation analysis may not justify this type of M&V. Also, building simulation software programs are
not capable of modeling every conceivable building and equipment or control EEM.
The M&V method described here is based, in part, on Option D of the 2001 International Performance
Measurement and Verification Protocol (IPMVP). Valuable insights on computer simulation analysis can
be found in the IPMVP.
The Sponsor should take the following steps in performing Computer Simulation Analysis M&V:
1. Work with CenterPoint Energy and its contractor to define a strategy for creating a calibrated
building simulation model in the project-specific M&V plan.
2. Collect the required data from utility bill records, architectural drawings, site surveys, and direct
measurements of specific equipment installed in the building.
3. Adapt the data and enter them into the program’s input files.
4. Run the simulation program for the “base” building model. The base building is the existing
building without the installed EEMs. The base building should comply with minimum state and
federal energy standards.
5. Calibrate the base model by comparing its output with measured data. The weather data for the
base model should be the actual weather occurring during the metering period. Refine the base
building model until the program’s output is within acceptable tolerances of the measured data.
6. Run the calibrated base model using typical weather data to normalize the results.
7. Repeat the process for the post-installation model. Calibration of the retrofit model, if done,
should use data collected from site surveys (to validate that all of the equipment and systems are
installed and operating properly) and possibly spot, short-term, or utility metering.
1 Wolpert, J.S. and J. Stein, “Simulation, Monitoring, and the Design Assistance Professional,” 1992 International Energy and
Environment Conference.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 85 -
8. Estimate the savings. Savings are determined by subtracting the post-installation results from the
baseline results using typical conditions and weather. The savings estimates and simulation
results will be reviewed and verified by CenterPoint Energy or its contractor.
These steps are described in more detail in the following sections.
12.2 Baseline and Post-Retrofit Data Requirements
12.2.1 Simulation Software
To conduct Calibrated Simulation Analysis M&V, it is recommended that the Sponsor use the most
current version available of the DOE-2.1E hourly building simulation program. For projects with small
projected incentive payments, the Sponsor may use other models if the model can be shown to adequately
model the project site and the EEMs, can be calibrated to a high level of accuracy, and the calibration can
be documented.
12.2.2 Weather Data
Calibrating a computer simulation of a real building for a specific year requires that actual weather data
be used in the analysis. Actual weather data should be collected from a source such as National Climatic
Data Center (NCDC) weather station data. The physical location of the weather station should be the
closest available to the project site. These data should be translated into weather data files that are
compatible with DOE-2. The project-specific M&V plan should specify which weather data sources will
be used.
Typical weather data used in the calculation of energy savings should be either Typical Meteorological
Year (TMY) or TMY2 data types, obtained from the National Renewable Energy Laboratory (NREL).
12.3 Calculation of Energy Savings
12.3.1 Develop a Calibrated Simulation Strategy
The following are issues that either the Sponsor or CenterPoint Energy will need to address in order to
define the simulation approach:
Define the existing building. In general, the existing building represents the building, as it exists
prior to installation of EEMs by the Sponsor.
Define the baseline building. The baseline building represents the existing building but with baseline
equipment efficiencies as specified by state or federal standards.
Define the post-installation building. The post-installation building represents the building with the
project-related EEMs installed.
Define the calibration data interval. The building models should be calibrated using hourly, daily
or monthly data. Calibrations to hourly or daily data are preferred, since they are generally more
accurate than calibrations to monthly data because there are more points to compare. If monthly
project site billing data are used then spot or short term data collection for calibrated key values may
be used.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 86 -
Specify spot and short-term measurements to be taken of building systems. These measurements
augment the whole-building data and enable the modeler to accurately characterize building systems.
Spot and short-term measurements are valuable, but may add significant cost and time to the project.
Employ an experienced building modeling professional. Although new simulation software
packages make much of the process easier, a program’s capabilities and real data requirements are not
fully understood by inexperienced users. Employing inexperienced users for this purpose will result
in inefficient use of time in data processing, and in checking and understanding of simulation results.
12.3.2 Building Data Collection
The data required for simulating a real building are voluminous. The main categories of data to be
collected for the building and proposed EEMs are described below.
Building plans. The Sponsor should obtain as-built building plans. If as-built plans are not available,
the Sponsor should work with the building owner to define alternative sources.
Utility bills. The Sponsor should collect a minimum of twelve consecutive months (preferably 24
months), with applicable dates of utility bills for the months immediately before installation of the
EEMs. The billing data should include monthly kWh consumption and peak electric demand (kW) for
the month. Fifteen minute or hourly data are also desired for calibration. The Sponsor should
determine if building systems are sub-metered, and collect these data if available. If hourly data are
required to calibrate the simulation, but no data are available, metering equipment may need to be
installed to acquire hourly data.
Conduct on-site surveys. CenterPoint Energy or its contractor will assist the Sponsor to identify the
necessary data to be collected from the building. The Sponsor should visit the building site to collect
the data. CenterPoint Energy or its contractor may accompany the Sponsor during the building
survey. Data that may be collected include:
HVAC systems - primary equipment (e.g. chillers and boilers): capacity, number, model and
serial numbers, age, condition, operation schedules, etc.
HVAC systems - secondary equipment (e.g. air handling units, terminal boxes):
characteristics, fan sizes and types, motor sizes and efficiencies, design flow rates and static
pressures, duct system types, economizer operation and control
HVAC system controls, including location of zones, temperature set-points, control set-points
and schedules, and any special control features
Building envelope and thermal mass: dimensions and type of interior and exterior walls,
properties of windows, and building orientation and shading from nearby objects
Lighting systems: number and types of lamps, with nameplate data for lamps and ballasts,
lighting schedules, etc.
Plug loads: summarize major and typical plug loads for assigning values per zone
Building occupants: population counts, occupation schedules in different zones
Other major energy consuming loads: type (industrial process, air compressors, water heaters,
elevators), energy consumption, schedules of operation, etc.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 87 -
Interview operators. The Sponsor may choose to interview the building operator. Building operators
can provide much of the above listed information, and also indicate if any deviation in the intended
operation of building equipment exists.
Make spot measurements. The Sponsor may find it necessary to record power draw on certain
circuits (lighting, plug load, HVAC equipment, etc.) to determine actual equipment operation power.
Conduct short-term measurements. Data-logging monitoring equipment may be set up to record
system data as they vary over time. These data reveal how variable load data changes with building
operation conditions such as weather, occupancy, daily schedules, etc. These measurements may
include lighting systems, HVAC systems and motors. The period of measurement should be from one
to several weeks.
Obtain weather data. For calibration purposes, representative site weather data should be obtained
for a nearby NCDC site.
12.3.3 Base Building Simulation Models
Once all necessary information is collected, the Sponsor should input the simulation data into DOE-2
code to create the base building model. The modeler should refine the model to obtain the best
representation of the base building. Where possible, the modeler should use measured data and real
building information to verify or replace the program’s default values.
Minimum Energy Standards
The baseline model should comply with minimum state and federal energy standards with respect to the
following:
Baseline equipment/systems models should not include devices (e.g. lamps and ballasts) that are not
allowed to be installed under current regulations.
Baseline equipment models should meet prescriptive efficiency standards requirements for affected
equipment.
Baseline calculations do not have to comply with performance compliance methods that require the
project site to meet an energy budget.
If the existing conditions of the EEMs do not comply with minimum state and federal standards, the
modeler should calibrate the simulation model with the building as it currently exists, and then modify the
existing building model to reflect the baseline efficiencies. This modified, or baseline building is then
used as the base case for computing energy savings.
Calibration
After the base building model has been created and debugged, the modeler should make a comparison of
the energy flows and demand projected by the model to that of the measured utility data. All utility billing
data should be used in the analysis, electric as well as heating fuels, such as natural gas. The modeler may
use either monthly utility bills, or measured hourly data to calibrate the model when available.
The calibration process should be documented to show the results from initial runs and what changes
were made to bring the model into calibration. Statistical indices are calculated during the calibration
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 88 -
process to determine the accuracy of the model. If the model is not sufficiently calibrated, the modeler
should revise the parameters of the model and recalculate the statistics.
Hourly Data Calibration
In hourly calibration, two statistical indices are required to declare a model “calibrated”: monthly mean
bias error (MBE) and the coefficient of variation of the root mean squared error (CV(RMSE))2.
𝑀𝐵𝐸 (%) =∑ (𝑀 − 𝑆)ℎ𝑟𝑚𝑜𝑛𝑡ℎ
∑ 𝑀ℎ𝑟𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀ℎ𝑟 = the measured kWh for any hour during the month
𝑆ℎ𝑟 = the simulated kWh for any hour during the month
𝐶𝑉𝐸 (𝑅𝑀𝑆𝐸𝑚𝑜𝑛𝑡ℎ) =√∑ (𝑀 − 𝑆)2
ℎ𝑟 × 𝑁ℎ𝑟 𝑚𝑜𝑛𝑡ℎ
∑ 𝑀ℎ𝑟𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀ℎ𝑟 = the measured kWh for any hour during the month
𝑆ℎ𝑟 = the simulated kWh for any hour during the month
𝑁ℎ𝑟 = the number of hours in the month
The acceptable tolerances for these values when using hourly data calibration are shown in Table 19.
Table 19. Acceptable Tolerances for Hourly Data Calibration
Value
MBEmonth 10%
CV(RMSEmonth) 30%
Monthly Data Calibration
Comparing energy use projected by simulation to monthly utility bills is straightforward. First the model
is developed and run using weather data that corresponds to the monthly utility billing periods. Next
monthly-simulated energy consumption and monthly measured data are plotted against each other for
every month in the data set. Equations below calculate the error in the monthly and annual energy
2 Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Great Energy Predictor Shootout: Overview and
Discussion of Results,” ASHRAE Transactions Technical Paper, Vol. 100, pt. 2, June, 1994
Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Results of the 1993 Great Energy Predictor Shootout
to Identify the Most Accurate Method for Making Hourly Energy Use Predictions,”: ASHRAE Journal, pp. 72-81, March, 1994
Haberl, J. and S. Thamilseran, “Predicting Hourly Building Energy Use: The Great Energy Predictor Shootout II, Measuring
Retrofit Savings – Overview and Discussion of Results, ASHRAE Transactions, June, 1996.
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 89 -
consumption. The acceptable tolerances for these values when using monthly data calibration are shown
in Table 20.
𝐸𝑅𝑅𝑚𝑜𝑛𝑡ℎ(%) =(𝑀 − 𝑆)𝑚𝑜𝑛𝑡ℎ
𝑀𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀𝑚𝑜𝑛𝑡ℎ = the measured kWh for the month
𝑆𝑚𝑜𝑛𝑡ℎ = the simulated kWh for the month
𝐸𝑅𝑅𝑦𝑒𝑎𝑟 = ∑ 𝐸𝑅𝑅𝑚𝑜𝑛𝑡ℎ
𝑦𝑒𝑎𝑟
Table 20. Acceptable Tolerances for Monthly Data Calibration
Value
ERRmonth 25%
ERRyear 15%
12.3.4 Post-Installation Models
After measure installation a post-installation model can be prepared. The post-installation model should
usually be the baseline model with the substitution of new energy-efficient equipment and systems. This
new model should also be calibrated and documented. The possible calibration mechanisms are:
Using site survey data to validate that all of the specified equipment and systems are installed, have
the nameplate data used in the model, and are operating properly.
Using spot and/or short-term metering data to calibrate particular model modules of equipment,
systems or end-uses.
Using utility (15 minute, hourly or monthly) metering data to calibrate the model, as was done with
the pre-installation model.
The above mentioned post-installation model calibration mechanisms are not necessarily mutually
exclusive. If the first two mechanisms are used the model can be calibrated soon after measure
installation. If the last mechanism is used then the model can only be calibrated after sufficient (e.g., 12
months) billing data are available.
In some instances the post-installation model should be the only model calibrated. This can occur when
the baseline project site cannot be easily modeled due to significant changes during the 12 months prior to
the new measures being installed and thus the recent billing data are not representative.
12.3.5 Detailed Energy Savings Calculations
Energy savings are determined from the difference between the outputs of the baseline and post-
installation models. Savings are determined with both models using the same conditions (weather,
Program Manual v 16 Measurement and Verification Guidelines for Retrofit Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 2. - 90 -
occupancy schedules, etc.). To calculate savings, the energy consumption projected by the post-
installation model is subtracted from energy consumption projected by the baseline model.
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑(𝑘𝑊𝑝𝑟𝑒,𝑖– 𝑘𝑊𝑝𝑜𝑠𝑡,𝑖)
𝑛
𝑖=1
Where:
𝒌𝑾𝒑𝒓𝒆,𝒊= Baseline kW calculated from Baseline Model and corresponding to same time interval 𝒊, system
output, weather, etc., conditions as 𝒌𝑾𝒑𝒐𝒔𝒕,𝒊
𝑘𝑊𝑝𝑜𝑠𝑡,𝑖 = Post-installation kW calculated from Post-Installation Model and corresponding to the
measured time interval; measured system output, measured weather variables, etc. in the post-
installation period
12.4 Project-Specific M&V Issues
Specific M&V issues that need to be addressed in the project-specific M&V plan and that are related to
this M&V method include:
Which version of DOE-2 will be used, the supplier of the program, and what if any pre- and post-
processors will be used?
Baseline building description (age square footage, location, etc.) including a description of building
systems to be replaced.
Description of any building operation conditions (set-points, schedules, etc.) that are affected by the
EEMs.
Documentation of compliance for the baseline model with state and federal standards.
Documentation of the calibrated simulation strategy and project procedure, including differences in
calibration parameters between the existing and post-installation cases.
A summary of the building data to be collected and sources (e.g., site surveys, drawings).
Identification of spot and short-term measurements to be made.
Selection of the calibration data interval (should be hourly or monthly).
Identification and source of weather data used (NCDC weather station or typical weather data).
Identification of the statistical calibration tolerances and graphical techniques to be used.
Indication of who will do the simulation analysis and calibration.
Specification of format for documentation.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 91 -
Measurement and Verification Guidelines Section 3.
for New Construction Projects
This section includes detailed information about the measurement and verification (M&V) requirements
of the 2016 C&I Standard Offer Program, as well as guidance for Project Sponsors on how to prepare and
execute an M&V plan. These requirements and guidelines are specific to New Construction projects.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 92 -
13. Introduction to Measurement and Verification for New Construction
Projects
13.1 Overview
In the 2016 C&I Standard Offer Program (SOP), the demand and energy savings resulting from a project
are determined through measurement and verification (M&V) activities. The M&V methodology
appropriate for any given project depends on the equipment type, operational predictability, and project
complexity.
Project Sponsors should use the M&V approaches presented here as the basis for developing a
methodology for measuring and verifying the demand and energy savings associated with their projects.
A Project Sponsor may recommend an alternative approach; however, any alternative must be approved
by CenterPoint Energy and adhere to the 2001 International Performance Measurement and Verification
Protocol (IPMVP), upon which these approaches are based (with the exception of deemed savings
approaches, discussed below). Table 21 lists the available measurement methods for the measures.
Table 21. Energy Efficiency Measure vs. Measurement Approach
13.2 Measurement Approaches
The M&V guidelines provided in the following sections vary in detail and rigor, but fall into three general
categories:
Deemed savings estimates
Simplified M&V approaches
Full M&V approaches
The most appropriate approach depends on the availability of evaluation data from previous programs for
particular measures, the predictability of equipment operation, and the benefits of the approach relative to
the costs associated with that approach.
13.2.1 Deemed Savings
In deemed savings approaches, the demand and energy savings associated with particular measures are
based on values stipulated by CenterPoint Energy for factors such as operating hours, efficiencies, and
coincidence factors. These values result from analyses of evaluation data from past demand-side
management programs or other industry data. The deemed savings approach is appropriate for equipment
Chapter Energy Efficiency Measure Measurement Approaches
Provided
14 Lighting Efficiency and Controls Deemed and Simplified
15 High-efficiency cooling equipment Deemed, Simplified and Full
16 High-efficiency motors—constant load Simplified and Full
18 Generic Variable Loads Full
19 Various – computer modeling and simulation Full
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 93 -
installations for which savings are relatively certain, such as high-efficiency lamps or high performance
windows. With deemed savings, the Project Sponsor is not required to perform short-term testing or long-
term metering.
13.2.2 Simplified M&V
A simplified M&V approach may involve short-term testing or simple long-term metering, but relies
primarily on manufacturer’s efficiency data and pre-established savings calculation formulas. Simplified
methods can reduce the need for some field monitoring or performance testing. For example, the energy
and demand savings associated with a high-efficiency constant load motor are determined by comparing
the rated efficiency of the specified, high-efficiency motor to that of a standard motor, and then
conducting spot-metering of the motor's demand and long-term metering of the energy consumption.
CenterPoint Energy, or its contractor, may collect the monitoring data onsite during the post-installation
inspection. In cases where this is necessary, the Sponsor is required to have any logging equipment
operational until the inspection takes place. It is the responsibility of the Sponsor to have the required
equipment or personnel to gather the data from any logging equipment.
13.2.3 Full M&V
The full measurement approach estimates demand and energy savings using a higher level of rigor than
the deemed or metered measurement approaches through the application of computer simulation. Any full
measurement methods other than computer simulation should be developed in accordance with the 2007
International Performance Measurement and Inspection Protocol (IPMVP) and be approved by
CenterPoint Energy. In general, projects involving full measurement must submit a project-specific
measurement plan. At a minimum, the plan should address the following (from the 2007 IPMVP):
1. Describe the new construction project; include information on how the specified equipment
exceeds applicable standards.
2. Describe the Measurement method to be used.
3. Indicate who will conduct the Measurement activities and prepare the Measurement analyses and
documentation.
4. Define the details of how calculations will be made. For instance: “List analysis tools, such as
DOE-2 computer simulations, and/or show the equations to be used.” A complete “path” should
be defined indicating how collected survey and metering/monitoring data will be used to calculate
savings. All equations should be shown.
5. Specify what metering equipment will be used, who will provide the equipment, its accuracy and
calibration procedures. Include a metering schedule describing metering duration and when it will
occur, and how data from the metering will be validated and reported. Include data formats.
Electronic, formatted data read directly from a meter or data logger are recommended for any
short-or long-term metering.
6. Define what key assumptions will be made about significant variables or unknowns. For instance:
“actual weather data will be used, rather than typical-year data,” or “fan power will be metered
for one full year for two of the six supply air systems.” Describe any stipulations that will be
made and the source of data for the stipulations.
7. Define how any baseline adjustments will be made.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 94 -
8. Describe any sampling method that will be used, what is included, sample size, documentation on
how sample size was selected, and information on how random sample points will be selected.
9. Indicate how quality assurance will be maintained and replication confirmed.
13.3 Developing Project-Specific M&V Plans
Table 22 highlights the basic steps required during the M&V process for most new construction projects
under this program.
Table 22. Steps in the M&V process
Step M&V Activity Performed by:
1 Develop a site-specific M&V plan Sponsor
2 Ensure that the M&V plans adhere to the IPMVP guidelines CenterPoint Energy
3 Conduct a pre-installation equipment survey Sponsor
4 Install equipment Sponsor
5 Conduct a post-installation equipment survey Sponsor
6 Conduct a post-installation inspection CenterPoint Energy
7 Execute the M&V plan (conduct M&V activities if
necessary) Sponsor
8 True-up savings, based on M&V results Sponsor
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 95 -
14. Measurement Guidelines for Lighting Efficiency and Controls
14.1 Overview
The lighting projects covered by this M&V procedure are lighting efficiency measures that may include
the replacement of existing lamps and ballasts with new energy efficient lamps and ballasts. For these
types of projects, demand savings are based on coincident-load factors and changes in lighting load as
determined using standard lighting fixture wattage values listed in the CenterPoint Energy Table of
Standard Fixture Wattages (see Appendix C). To determine energy savings, the Sponsor should establish
operating hours using one of two methods:
Deemed Hours – Operating hours have been established for certain building types (See Table 16).
Metered Hours – Energy savings are determined by metering pre- or post-installation operating
hours using defined sampling techniques.
For lighting efficiency measures installed in electrically cooled spaces, demand and energy savings are
also given for lighting-HVAC system interaction. These savings are equal to various percentages of the
lighting demand savings and energy savings depending on the building types and temperatures.
Evaporative or alternate fuel system credits for electricity savings must be based on Full M&V results.
In addition to determining operating hours, the Project Sponsor is required to conduct pre- and post-
installation equipment surveys. The Project Sponsor should fill out and submit survey results in the New
Construction Lighting Survey Form using fixture codes provided in the Table of Standard Fixture
Wattages. CenterPoint Energy or its contractor will conduct a post-installation inspection to verify the
installation of the specified equipment.
14.2 Pre-Installation M&V Activities
14.2.1 Pre-Installation Equipment Survey
Prior to installing the lighting measures, the Project Sponsor prepares a pre-installation equipment
specification sheet by filling out a New Construction Lighting Survey Form. The Project Sponsor submits
this information as part of the Project Application. The pre-installation equipment specification should
provide the following information about all proposed fixtures: room location, fixture, lamp, and ballast
types, area designations, counts of fixtures, and type of control device. Surveys should include all
proposed lighting fixtures and controls. The Project Sponsor must include estimates of the amount of
lighting that will be provided by task lamps and other moveable lighting sources. Fixture wattages are
based on the fixture codes listed in the Table of Standard Fixture Wattages. This information should be
tabulated electronically in the New Construction Lighting Survey Form. Once the Project Sponsor enters
all fixtures into the form, the form calculates what the building’s installed interior lighting load will be.
Some types of lighting fixtures are exempt from inclusion in the interior lighting demand calculation.
Project Sponsors should list exempt fixtures in the separate sheet provided in the New Construction
Lighting Survey Form. Exempt fixtures are fixtures that provide lighting that is in addition to general,
ambient lighting, have separate control devices, and are installed in one of the following applications4:
4 Reference: ASHRAE 90.1-1999, Section 9.3.1.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 96 -
Display or accent lighting that is an essential element for the function performed in galleries,
museums, and monuments.
Lighting that is integral to equipment or instrumentation and is installed by its manufacturer.
Lighting specifically designed for use only during medical or dental procedures and lighting integral
to medical equipment.
Lighting integral to both open and glass enclosed refrigerator and freezer cases.
Lighting integral to food warming and food preparation equipment.
Lighting for plant growth or maintenance.
Lighting in spaces specifically designed for use by the visually impaired.
Lighting in retail display windows, provided the display area is enclosed by ceiling-height partitions.
Lighting in interior spaces that have been specifically designated as a registered interior historic
landmark.
Lighting that is an integral part of advertising or directional signage.
Exit signs.
Lighting that is for sale or lighting educational demonstration systems.
Lighting for theatrical purposes, including performance, stage, and film and video production.
Athletic playing areas with permanent facilities for television broadcasting.
Casino gaming areas.
14.3 Post-installation M&V Activities
14.3.1 Post-Installation Equipment Survey
The Project Sponsor is required to conduct a post-installation lighting equipment survey as part of the
Installation Report. The purpose of the post-installation equipment survey is to inventory the actual, as-
built equipment. Inventory information should be tabulated electronically in the New Construction
Lighting Survey Form. Fixture wattages shall be based on the Table of Standard Fixture Wattages. Once
the Project Sponsor enters all fixtures into the survey form, the form calculates the buildings installed
interior lighting load.
14.3.2 Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify that the measures
were installed as reported. In most cases, CenterPoint Energy or its contractor will inspect statistically
significant samples taken from the entire lighting population. The criterion for acceptance is that the error
in the installed demand of the sample must be within 5% of the demand reported on the post-installation
lighting equipment inventory form. If the error exceeds 5%, CenterPoint Energy will inform the Project
Sponsor that the submitted lighting survey must be corrected and resubmitted, citing the major cause of
the errors found.
14.3.3 Lighting Power Allowance
Demand savings are based on the difference between a project’s installed lighting load, compared to the
maximum, code-specified lighting power allowance. To calculate the maximum code-allowed lighting
power allowance for a building, multiply the maximum lighting power density for the appropriate
building type, as listed in Table 23, by the gross lighted floor area of the building. If a lighting measure is
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 97 -
planned for a building type not listed in Table 23, choose the building type that is most similar in
function. If a lighting measure is planned for a building with mixed usages, e.g. a high rise building with
retail space and office space, choose the building type that represents the largest portion of the floor
space.
Table 23. Lighting Power Densities by Building Type5
Building Type Lighting Power
Density (W/ft2)
Building Type (cont.) Lighting Power
Density (W/ft2)
Education:K-12, w/o Summer
Session
1.20 Parking Structure 0.30
Education: College, University,
Vocational, Day Care, and K-12
w/ summer session
1.20 Public Assembly 1.17
Food Sales - Non-24-Hour
Supermarket/Retail
1.50 Public Order and Safety 1.07
Food Sales - 24 Hour
Supermarket/Retail
1.50 Religious 1.30
Food Service – fast food 1.40 Retail (Excluding Malls
and Strip Centers)
1.50
Food Service – Sit-down
Restaurant
1.30 Retail (Enclosed Mall) 1.50
Health Care (Out-patient) 1.00 Retail (Strip shopping
and non-enclosed mall)
1.50
Health Care (In-patient) 1.20 Service (Excluding Food) 0.90
Lodging (Hotel/Motel/Dorm),
Common Areas
1.00 Warehouse (Non-
refrigerated)
0.80
Lodging (Hotel/Motel/Dorm),
Rooms
1.00 Warehouse
(Refrigerated)
0.80
Manufacturing 1.30 Outdoor Uncovered
Parking Area: Zone 1
0.04
Multi-family Housing, Common
Areas
0.70 Outdoor Uncovered
Parking Area: Zone 2
0.06
Nursing and Resident Care 1.20 Outdoor Uncovered
Parking Area: Zone 3
0.1
Office 1.05 Outdoor Uncovered
Parking Area: Zone 4
0.13
5 current City of Houston Commercial Energy Conservation Code
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 98 -
Outdoor Lighting Zone Description
1
Developed areas of national parks, state parks, forest land, and
rural areas
2
Areas predominantly consisting of residential zoning,
neighborhood business districts, light industrial with limited
nighttime use and residential mixed use areas
3 All other areas
4
High-activity commercial districts in major metropolitan areas
as designated by the local land use planning authority
14.4 Operating Hours
14.4.1 Deemed Hours
The Deemed Hours Method uses predetermined annual operating hours and co-incidence factors as listed
in Table 24. If this table does not accurately characterize the building type, then the Project Sponsor
should refer to the Stipulated Hours Method or the Metered Hours Method section for the appropriate
Measurement techniques to calculate operating hours.
Table 24. Deemed Operating Hours, Co-incidence Factors for Select Building Types
Building Type Annual
Operating Hours
Coincidence
Factor
Education:K-12, w/o Summer Session 2,777 47%
Education: College, University, Vocational, Day
Care, and K-12 w/ summer session
3,577 69%
Food Sales - Non-24-Hour Supermarket/Retail 4,706 95%
Food Sales - 24 Hour Supermarket/Retail 6,900 95%
Food Service – Fast food 6, 188 81%
Food Service – Sit-down Restaurant 4,368 81%
Health Care (Out-patient) 3,386 77%
Health Care (In-patient) 5,730 78%
Lodging (Hotel/Motel/Dorm), Common Areas 6,630 82%
Lodging (Hotel/Motel/Dorm), Rooms 3,055 25%
Manufacturing 5,740 73%
Multi-family Housing, Common Areas 4,772 87%
Nursing and Resident Care 4,271 78%
Office 3,737 77%
Outdoor (street & parking) 3996 0% (61%
winter peak)
Parking Structure 7,884 100%
Public Assembly 2,638 56%
Public Order and Safety 3,472 75%
Religious 1,824 53%
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 99 -
Building Type Annual
Operating Hours
Coincidence
Factor
Retail (Excluding Malls and Strip Centers) 3,668 90%
Retail (Enclosed Mall) 4,813 93%
Retail (Strip shopping and non-enclosed mall) 3,965 90%
Service (Excluding Food) 3,406 90%
Warehouse (Non-refrigerated) 3,501 77%
Warehouse (Refrigerated) 3,798 84%
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 100 -
Table 25. Interactive Demand and Energy Factors
Building Type Interactive
Demand Factor
Normal Temps.
(> 41°F)
Interactive
Energy Factor
Normal Temps.
(> 41°F)
Interactive
Demand Factor
Medium Temps.
(33-41°F)
Interactive
Energy Factor
Medium Temps.
(33-41°F)
Interactive
Demand
Factor Low
Temps.
(-10-10°F)
Interactive
Energy
Factor Low
Temps.
(-10-10°F)
Education: K-12, w/o Summer Session 10% 5% 25% 25% 30% 30%
Education: College, University, Vocational,
Day Care, and K-12 w/ Summer Session
10% 5% 25% 25% 30% 30%
Food Sales: Non 24-hour
Supermarket/Retail
10% 5% 25% 25% 30% 30%
Food Sales: 24-hour Supermarket/Retail 10% 5% 25% 25% 30% 30%
Food Service: Fast Food 10% 5% 25% 25% 30% 30%
Food Service: Sit-down Restaurant 10% 5% 25% 25% 30% 30%
Health Care: Out-patient 10% 5% 25% 25% 30% 30%
Health Care: In-patient 10% 5% 25% 25% 30% 30%
Lodging (Hotel/Motel/Dorm): Common Areas 10% 5% 25% 25% 30% 30%
Lodging (Hotel/Motel/Dorm): Rooms 10% 5% 25% 25% 30% 30%
Manufacturing 10% 5% 25% 25% 30% 30%
Multi-family Housing: Common Areas 10% 5% 25% 25% 30% 30%
Nursing and Resident Care 10% 5% 25% 25% 30% 30%
Office 10% 5% 25% 25% 30% 30%
Outdoor 0% 0% 0% 0% 0% 0%
Parking Structure 0% 0% 0% 0% 0% 0%
Public Assembly 10% 5% 25% 25% 30% 30%
Public Order and Safety 10% 5% 25% 25% 30% 30%
Religious 10% 5% 25% 25% 30% 30%
Retail: Excluding Malls & Strip Centers 10% 5% 25% 25% 30% 30%
Retail: Enclosed Mall 10% 5% 25% 25% 30% 30%
Retail: Strip Shopping &Non-enclosed Mall 10% 5% 25% 25% 30% 30%
Service (Excluding Food) 10% 5% 25% 25% 30% 30%
Warehouse: Non-refrigerated 10% 5% 25% 25% 30% 30%
Warehouse: Refrigerated 25%1 10% 5% 25% 25% 30% 30%
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 101 -
14.4.2 Metered Hours
The Metered Hours Method involves monitoring a statistically significant sample of fixtures to determine
operating hours. This involves developing a sampling plan to monitor the average operating hours for
each lighting usage group. The Project Sponsor should conduct all meter installation, retrieval and data
analysis. When performing the post-installation activities associated with this Measurement approach,
Project Sponsors should organize the equipment into usage groups—collections of equipment with
similar operating schedules and functional uses. For instance, although a site's open office lighting may
have the same annual hours of operation as the private office lighting, the two have different functional
uses. In this case, a change in the operating hours of the private office lights due to the installation of an
occupancy sensor would not be relevant to the operating hours of the open office lights. Therefore, private
offices and open office areas should be assigned to separate usage groups. Table 26 illustrates the
recommended minimum number of usage groups, specific to each project site.
Table 26. Suggested Minimum Numbers of Usage Groups for Project Site Types
Building Type
Minimum
Number of
Usage Groups
Examples of Usage Group types
Office Buildings 6 General offices, private offices, hallways, restrooms,
conference, lobbies, 24-hr
Education (K-12) 6 Classrooms, offices, hallways, restrooms, admin,
auditorium, gymnasium, 24-hr
Education
(College/University)
6 Classrooms, offices, hallways, restrooms, admin,
auditorium, library, dormitory, 24-hr
Hospitals/ Health Care
Facilities
8 Patient rooms, operating rooms, nurses station, exam
rooms, labs, offices, hallways
Retail Stores 5 Sales floor, storeroom, displays, private office, 24-hr
Manufacturing 6 Manufacturing, warehouse, shipping, offices, shops,
24-hr
Other 10 N/A
The Project Sponsor will conduct short-term metering of the operating hours for a random sample of
fixtures in each usage group. For facilities with little variation in weekly operating schedules (such as
offices), monitoring shall be conducted for each selected circuit for a recommended minimum of two to
four weeks. Monitoring should not occur during significant holidays or vacations. If a holiday or vacation
falls within the monitoring period, the duration should be extended for as many days as that holiday or
vacation. For facilities where operating hours vary seasonally, monitoring should be conducted for a
minimum period during each season.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 102 -
The required sample sizes for each usage group are listed in Table 27.
Note: because light loggers sometimes fail, over sampling is recommended. Light loggers should be
calibrated prior to installation to verify that the light loggers are functioning properly. In the event that
there are multiple fixtures on a single circuit breaker (e.g., warehouse), then the Project Sponsor will
coordinate with CenterPoint Energy to determine number of samples required.
Table 27. Monitoring Sample Size
Population of Lines in Usage Group Sample Size
n <4 3
5<=n<8 5
9<=n<12 6
13<=n<20 7
21<=n<70 8
71<=n<300 10
n>300 11
* Sample sizes assume a confidence interval of 80%, precision of 20%, and a coefficient of variation (cv) of 0.5 for
the populations indicated
14.4.3 Calculation of Average Operating Hours
For each usage group, the Project Sponsor should extrapolate results from the monitored sample to the
population to calculate the average annual lighting operating hours. Simple, unweighted averages of
operating hours should be calculated for each usage group as listed in the following equations. The
Project Sponsor should use these average operating hours to calculate the energy savings for each
respective usage group.
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑢 = ∑
𝐻𝑜𝑢𝑟𝑠𝑜𝑛 ,𝑖
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖× 8760𝑛
𝑖=1
𝑛
Where:
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑢 = Average annual operating hours for usage group u
𝐻𝑜𝑢𝑟𝑠𝑜𝑛 ,𝑖 = Operating hours observed during the metering period for circuit i
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖 = Total number of hours in the metering period for circuit i
𝑛 = Number of metered circuits in usage group u
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 103 -
14.4.4 Calculation of Average Co-incidence Factor
The equation listed below illustrates the calculation of average on-peak demand coincidence factor (CF)
for a usage group. Note that demand savings are only allowed for lighting fixtures that will be in
operation on weekdays between the hours of 1 PM and 7 PM during the months of June through
September or from 6 AM to 10 AM and 6 PM to 10PM, from December 1 through February 28.
𝐶𝐹𝑢 =
∑ [𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑜𝑛,𝑖
𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖]𝑛
𝑖=1
𝑛
Where:
𝐶𝐹𝑢 = = Peak-demand coincidence factor for usage group u
𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑜𝑛,𝑖 = Operating hours observed during peak in the metering period for circuit i
𝐻𝑜𝑢𝑟𝑠𝑝𝑒𝑎𝑘 𝑚𝑒𝑡𝑒𝑟𝑒𝑑,𝑖= Total number of peak demand hours in the metering period for circuit I
𝑛 = Number or metered circuits in usage group u
14.4.5 Deemed Control Savings
This method requires the use of the deemed hours from Table 24 and a Power Adjustment Factor (PAF) and
Energy Adjustment Factor (EAF) from Table 28. If values from these tables do not accurately characterize the
building type and operation, then the Project Sponsor must refer to Metered Control Savings Method
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 104 -
Table 28. List of Power Adjustment Factors*
Control Type Sub-Category Control Codes EAF PAF
None n/a None 0.00 0.00
Occupancy n/a OS 0.24 0.24
Daylighting
(Indoor)
Continuous dimming DL-Cont
0.28 0.28 Multiple step dimming DL-Step
ON/OFF DL-ON/OFF
Outdoor n/a Outdoor 0.00 0.00
Personal Tuning n/a PT 0.31 0.31
Institutional Tuning n/a IT 0.36 0.36
Multiple/Combined Types Various combinations Multiple 0.38 0.38
*PAFs are adapted from latest version of the TRM.
14.4.6 Metered Control Savings
If the project is ineligible for deemed savings and/or the Project Sponsor prefers to monitor Operating
Hours to claim achievable savings, the Metered Hours Method must be followed to determine operating
hours (Refer to Pages 7-9 of the 2007 International Performance Measurement and Inspection Protocol).
If the project involves the addition of lighting controls to a building that does not fall under the deemed
category and the stipulated method is inadequate to determine pre-operating hours, then pre- and post-
installation metering may be required to determine pre- and post-operating hours.
14.5 Calculation of Demand and Energy Savings
Appended below are equations relating to peak demand and energy savings calculations. These
calculations are embedded in the Retrofit Lighting Survey Form.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = ∑ ((𝑃𝐷𝑖
1000× 𝐴𝑖) − (𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × 𝑘𝑊𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) )
𝑝𝑜𝑠𝑡 × (1 − 𝑃𝐴𝐹𝑖) )
𝑛
𝑖=1
× 𝐶𝐹𝑖 × (1 + 𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟1)
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑ ([(𝑃𝐷𝑖
1000× 𝐴𝑖) − (𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) × 𝑘𝑊𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) )
𝑝𝑜𝑠𝑡× (1 − 𝐸𝐴𝐹𝑖)] × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙,𝑖)
𝑛
𝑖=1
× (1 + 𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟2)
Where:
𝑃𝐷𝑖=Power Density in line item i, w/ft2
𝐴𝑖=Gross lighted floor area of line item i, ft2
𝑁𝑓𝑖𝑥𝑡𝑢𝑟𝑒(𝑖) = Number of fixtures in line item i
𝑘𝑊(𝑓𝑖𝑥𝑡𝑢𝑟𝑒 𝑖)= Deemed fixture wattage from standard wattage table for fixture type listed in line item i.
𝐶𝐹𝑖 = Coincident demand factor based on input in line item i (Deemed, Stipulated or Metered)
𝑃𝐴𝐹𝑖 = Power adjustment factors based on controls type on input in line item I (Deemed, or Metered)
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 105 -
𝐸𝐴𝐹𝑖 = Energy adjustment factors based on controls type on input in line item I (Deemed, or Metered)
𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟1 = If space is conditioned, value is referred to Table 25. If unconditioned, value is 0.
𝐴𝐶 𝑓𝑎𝑐𝑡𝑜𝑟2= If space is conditioned, value is referred to Table 25. If unconditioned, value is 0.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 106 -
15. Measurement Guidelines for High-Efficiency Cooling Equipment
15.1 Overview
Cooling equipment measures must involve the installation of equipment that exceeds current energy
efficiency standards. This chapter presents both a deemed savings approach and a simplified approach to
the measurement and verification of savings from the installation of high-efficiency cooling equipment.
High-efficiency equipment for which savings may be measured using the methods described in this
chapter includes:
Unitary air conditioners (DX, air-cooled, evaporative, or water-cooled)
Heat pumps (air-cooled, evaporative, or water-cooled)
Chillers (air-cooled centrifugal, water-cooled centrifugal, air-cooled screw)
Compressors (centrifugal, screw, reciprocating)
The projects should have the following characteristics:
Documented cooling load calculations for the affected facility.
The scope of the project for which incentives are requested is limited to individual pieces of
equipment, e.g. two 500-ton chillers, and not entire building systems.
If the proposed installation does not meet these requirements, refer to the Full Measurement guidelines for
appropriate Measurement techniques.
The applicable baseline efficiency values are from ASHRAE Standard 90.1-1999/2007/2010, or IECC
2009; these values are provided in the Standard Cooling Equipment Tables in Appendix A of this
document. The applicable column in the Standard Cooling Equipment Tables is titled “Minimum
Performance Standard”.
15.2 Deemed Savings for Cooling Equipment
The deemed savings approach to M&V for cooling equipment as part of new construction is available to
sponsors. The deemed savings methodology is incorporated in an Excel spreadsheet, available to
sponsors, which calculates savings values based on user inputs. The spreadsheet was developed as a tool
to assist sponsors with the deemed savings method. Manual calculations using Equations below are
acceptable as well.
Projects that are eligible to use the deemed savings approach must meet the following requirements:
The existing and proposed cooling equipment are electric.
The Cooling Equipment is not used for process loads.
Coefficients are listed in Table A.1-8 for the type of building in which the retrofit occurs and the type
of equipment involved.
The building falls into one of the categories described in Table 29
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 107 -
Table 29. Building Descriptions for Use in the Air-Conditioning Equipment Deemed Savings
Building Type Principal Building Activity Definition Detailed Business Type Examples
Education
College
Buildings used for academic or technical
classroom instruction, such as elementary,
middle, or high schools, and classroom
buildings on college or university campuses.
Buildings on education campuses for which the
main use is not classroom are included in the
category relating to their use. For example,
administration buildings are part of "Office,"
dormitories are "Lodging," and libraries are
"Public Assembly."
1) College or University
2) Career or Vocational Training
3) Adult Education
Primary School 1) Elementary or Middle School
2) Preschool or Daycare
Secondary School
1) High School
2) Religious Education
Food Sales Convenience
Buildings used for retail or wholesale of food. 1) Gas Station with a Convenience Store
2) Convenience Store
Supermarket 1) Grocery Store or Food Market
Food Service Full-Service Restaurant Buildings used for preparation and sale of food
and beverages for consumption.
1) Restaurant or Cafeteria
Quick-Service Restaurant 1) Fast Food
Healthcare
Hospital Buildings used as diagnostic and treatment
facilities for inpatient care.
1) Hospital
2) Inpatient Rehabilitation
Outpatient Healthcare
Buildings used as diagnostic and treatment
facilities for outpatient care. Medical offices
are included here if they use any type of
diagnostic medical equipment (if they do not,
they are categorized as an office building).
1) Medical Office
2) Clinic or Outpatient Health Care
3) Veterinarian
Large Multifamily Midrise Apartment
Buildings containing multifamily dwelling
units, having multiple stories, and equipped
with elevators.
No sub-categories collected.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 108 -
Building Type Principal Building Activity Definition Detailed Business Type Examples
Lodging
Large Hotel Buildings used to offer multiple
accommodations for short-term or long-term
residents, including skilled nursing and other
residential care buildings.
1) Motel or Inn
2) Hotel
3) Dormitory, Fraternity, or Sorority
4) Retirement Home, Nursing Home, Assisted
Living, or other Residential Care
5) Convent or Monastery
Nursing Home
Small Hotel/Motel
Mercantile
Stand-Alone Retail
Buildings used for the sale and display of
goods other than food.
1) Retail Store
2) Beer, Wine, or Liquor Store
3) Rental Center
4) Dealership or Showroom for Vehicles or
Boats
5) Studio or Gallery
Strip Mall Shopping malls comprised of multiple
connected establishments.
1) Strip Shopping Center
2) Enclosed Malls
Office
Large Office
Buildings used for general office space,
professional office, or administrative offices.
Medical offices are included here if they do not
use any type of diagnostic medical equipment
(if they do, they are categorized as an
outpatient health care building).
1) Administrative or Professional Office
2) Government Office
3) Mixed-Use Office
4) Bank or Other Financial Institution
5) Medical Office
6) Sales Office
7) Contractor’s Office (e.g. Construction,
Plumbing, HVAC)
8) Non-Profit or Social Services
9) Research and Development
10) City Hall or City Center
11) Religious Office
12) Call Center
Medium Office
Small Office
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 109 -
Building Type Principal Building Activity Definition Detailed Business Type Examples
Public Assembly Public Assembly
Buildings in which people gather for social or
recreational activities, whether in private or
non-private meeting halls.
1) Social or Meeting (e.g. Community Center,
Lodge, Meeting Hall, Convention Center,
Senior Center)
2) Recreation (e.g. Gymnasium, Health Club,
Bowling Alley, Ice Rink, Field House, Indoor
Racquet Sports)
3) Entertainment or Culture (e.g. Museum,
Theater, Cinema, Sports Arena, Casino, Night
Club)
4) Library
5) Funeral Home
6) Student Activities Center
7) Armory
8) Exhibition Hall
9) Broadcasting Studio
10) Transportation Terminal
Religious Worship Religious Worship
Buildings in which people gather for religious
activities, (such as chapels, churches, mosques,
synagogues, and temples).
No sub-categories collected.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 110 -
Building Type Principal Building Activity Definition Detailed Business Type Examples
Service Service
Buildings in which some type of service is
provided, other than food service or retail sales
of goods.
1) Vehicle Service or Vehicle Repair Shop
2) Vehicle Storage/Maintenance
3) Repair Shop
4) Dry Cleaner or Laundromat
5) Post Office or Postal Center
6) Car Wash
7) Gas Station with no Convenience Store
8) Photo Processing Shop
9) Beauty Parlor or Barber Shop
10) Tanning Salon
11) Copy Center or Printing Shop
12) Kennel
Warehouse Warehouse
Buildings used to store goods, manufactured
products, merchandise, raw materials, or
personal belongings (such as self-storage).
1) Refrigerated Warehouse
2) Non-refrigerated warehouse
3) Distribution or Shipping Center
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 111 -
15.2.1 Pre-Installation M&V Activities
Proof of Equipment Purchase
Sponsors must submit, within 30 days of the application approval, documentation showing the new
equipment is on order and should be delivered within the timeframe of the SOP.
Pre-Installation Site Survey
Prior to installing the cooling equipment measures, the Project Sponsor prepares a pre-installation
equipment specification sheet by filling out the deemed savings spreadsheet. The deemed savings
spreadsheet is available for downloading from the program Web site,
http://www.centerpointefficiency.com. The deemed savings spreadsheet requires the Project Sponsor to
input information about the equipment and the specified equipment’s type, size, make/model and
efficiency. The Project Sponsor submits the deemed savings spreadsheet as part of the Project
Application.
Pre-Installation Site Inspection
A pre-construction site inspection is generally not required, but in some cases – such as projects involving
additions to existing facilities – this inspection may be requested at CenterPoint Energy’s discretion.
15.2.2 Post-Installation M&V Activities
Post-Installation Equipment Survey
Once the construction project is complete, the Project Sponsor revises the deemed savings spreadsheet as
necessary to reflect as-built conditions. An updated copy of the deemed savings spreadsheet should be
included with the Installation Report.
The Project Sponsor must submit manufacturer’s documentation of the rated efficiency of all installed
cooling equipment, based upon ARI test conditions. This documentation will be in the form of
manufacturer cut sheets or factory performance test results that document the full load performance of the
equipment.
Post-Installation Inspection
CenterPoint Energy or its contractor will conduct a post-installation inspection to verify that the
equipment was installed as reported and is documented accurately.
15.2.3 Calculation Methodology
Appended below are equations relating to peak demand and energy savings calculations. These
calculations are embedded in the pertinent CenterPoint Energy Cooling Equipment Form.
For Split Systems/Packaged AC and HP:
𝑬𝒏𝒆𝒓𝒈𝒚 𝑺𝒂𝒗𝒊𝒏𝒈𝒔 [𝒌𝑾𝒉𝒔𝒂𝒗𝒊𝒏𝒈𝒔] = 𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑪 + 𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑯
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 112 -
𝑷𝒆𝒂𝒌 𝑫𝒆𝒎𝒂𝒏𝒅 [𝒌𝑾𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑪] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆
𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝑪−
𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕
𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅,𝑪) × 𝑪𝑭 ×
𝟏 𝒌𝑾
𝟏, 𝟎𝟎𝟎 𝑾
𝑬𝒏𝒆𝒓𝒈𝒚 (𝑪𝒐𝒐𝒍𝒊𝒏𝒈) [𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑪] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆
𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝑪−
𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕
𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅,𝑪) × 𝑬𝑭𝑳𝑯𝑪 ×
𝟏 𝒌𝑾
𝟏, 𝟎𝟎𝟎 𝑾
𝑬𝒏𝒆𝒓𝒈𝒚 (𝑯𝒆𝒂𝒕𝒊𝒏𝒈) [𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔,𝑯] = (𝑪𝒂𝒑𝑯,𝒑𝒓𝒆
𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝑯−
𝑪𝒂𝒑𝑯,𝒑𝒐𝒔𝒕
𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅,𝑯) × 𝑬𝑭𝑳𝑯𝑯 ×
𝟏 𝒌𝑾𝒉
𝟑, 𝟒𝟏𝟐 𝑩𝒕𝒖
For chillers:
𝑷𝒆𝒂𝒌 𝑫𝒆𝒎𝒂𝒏𝒅 [𝒌𝑾𝑺𝒂𝒗𝒊𝒏𝒈𝒔] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆 × 𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆 − 𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕 × 𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅) × 𝑪𝑭
𝑬𝒏𝒆𝒓𝒈𝒚 𝑺𝒂𝒗𝒊𝒏𝒈𝒔 [𝒌𝑾𝒉𝑺𝒂𝒗𝒊𝒏𝒈𝒔] = (𝑪𝒂𝒑𝑪,𝒑𝒓𝒆 × 𝜼𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆 − 𝑪𝒂𝒑𝑪,𝒑𝒐𝒔𝒕 × 𝜼𝒊𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅) × 𝑬𝑭𝑳𝑯𝑪
Where:
CapC/H,pre = Rated equipment cooling/heating capacity of the existing equipment at AHRI
standard conditions
CapC/H,post = Rated equipment cooling/heating capacity of the newly installed equipment at
AHRI standard conditions
ηbaseline,C = Cooling efficiency of existing equipment (ER) or standard equipment
(ROB/NC)
ηinstalled,C = Rated cooling efficiency of the newly installed equipment (Must exceed baseline
efficiency standards)
ηbaseline,H = Heating efficiency of existing equipment (ER) or standard equipment
(ROB/NC)
ηinstalled,H = Rated heating efficiency of the newly installed equipment (Must exceed baseline
efficiency standards)
Note: For split system/packaged AC units use EER for kW savings calculations and SEER/IEER and COP
for kWh savings calculations. The COP expressed for units > 5.4 tons is a full-load COP. Heating
efficiencies expressed as HSPF will be approximated as a seasonal COP and should be converted using the
following equation:
𝐂𝐎𝐏 =𝐇𝐒𝐏𝐅
𝟑. 𝟒𝟏𝟐
CF = Summer peak coincidence factor for appropriate climate zone, building type, and
equipment type (Table 10 and Table 11 in Appendix A)
EFLHC/H = Cooling/heating equivalent full-load hours for appropriate climate zone, building
type, and equipment type [hours] (Table 10 and Table 11 in Appendix A)
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 113 -
15.3 Simplified M&V for Cooling Equipment
The simplified M&V procedure for cooling equipment involves collecting one year of consumption data
after the project is complete. To determine demand savings for new electric cooling equipment, the
maximum demand that occurs during the utility peak hours must be measured. This can be accomplished
with continuous demand metering or spot metering during peak conditions.
For gas engine-driven cooling equipment, the Sponsor must establish a “baseline” peak demand and
annual energy usage for a similarly sized electric chiller serving the exact same load. This can be done
two ways. The Sponsor can provide a year of measured data for a same size electric chiller installed in an
exactly identical facility, or with a computer model. The same requirements for any model discussed
elsewhere in this manual apply in this case. The Sponsor must establish the baseline to the satisfaction of
CenterPoint Energy.
15.3.1 Pre-Construction M&V Activities
Proof of Equipment Purchase
Sponsors must submit, within 30 days of the application approval, documentation showing the new
equipment is on order and should be delivered within the timeframe of the SOP.
Equipment Survey
As part of the application process, the Project Sponsor provides an inventory of all specified cooling
equipment by filling out the Cooling Equipment Inventory Form, available for downloading from the
program Web site at http://www.centerpointefficiency.com. The information provided should include:
equipment type
year
make/model
rated capacity
rated efficiency
operating schedule
operating sequence
Site Inspection
A pre-construction site inspection is generally not required, but in some cases—such as projects involving
additions to existing facilities—this inspection may be requested at CenterPoint Energy's discretion.
15.3.2 Post-Installation M&V Activities
Equipment Survey
After construction is complete, the Project Sponsor provides an updated Cooling Equipment Inventory
Form to CenterPoint Energy as part of the Installation Report (IR). This survey must include the same
information itemized above, and be accompanied by a description of the cooling equipment and its
location as well as mechanical design drawings.
The Project Sponsor also submits manufacturer documentation of the rated efficiency of all installed
cooling equipment, based on ARI test conditions. This documentation should be in the form of
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 114 -
manufacturer cut sheets or factory performance test results that show the full load performance of the
equipment.
Site Inspection
Either CenterPoint Energy or its contractor conducts a post-construction inspection to verify that the
specified equipment has been installed as reported and has been documented accurately.
Performance Monitoring
To verify the energy consumption (kWh) impacts of the higher efficiency cooling equipment, the Project
Sponsor collects consumption data, continuously, for a 12-month period. To verify the impacts on
demand (kW), the Project Sponsor measures demand for a one-hour period either through continuous
demand metering (at 15-minute intervals) or with spot measurements, conducted between the hours of 1
PM and 7 PM on weekdays during the months of June through September.
For electric-to-gas fuel switching cooling equipment, twelve months of post-installation gas usage is
required in the simple M&V procedure. In situations where the “baseline” equipment and new
construction equipment are not similar (water-cooled vs. air-cooled), the Sponsor must account for the
peak demand and annual energy usage of any auxiliary equipment.
15.3.3 Calculation of Demand and Energy Savings
High-efficiency Cooling Equipment
Project Sponsors can claim demand savings only for equipment that operates on weekdays between the
hours of 1 PM and 7 PM, Monday through Friday, during the months of June through September.
Peak demand and energy savings are calculated according to Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 × (𝐶𝑂𝑃𝑝𝑜𝑠𝑡
𝐶𝑂𝑃𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒− 1)
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊ℎ𝑚𝑒𝑡𝑒𝑟𝑒𝑑 × (𝐶𝑂𝑃𝑝𝑜𝑠𝑡
𝐶𝑂𝑃𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒− 1) × (
𝐶𝐷𝐷(65)𝑇𝑀𝑌
𝐶𝐷𝐷(65)𝑚𝑒𝑡𝑒𝑟𝑒𝑑)
Where:
𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = maximum metered 15-minunte cooling equipment demand during the utility peak-demand
period, kW
𝑘𝑊ℎ𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = summed metered cooling equipment energy use for one year, kWh
𝐶𝑂𝑃𝑝𝑜𝑠𝑡=installed cooling equipment coefficient-of-performance at ARI design conditions
𝐶𝑂𝑃𝑏𝑎𝑠𝑙𝑖𝑛𝑒= baseline cooling equipment coefficient-of-performance from Appendix A
𝐶𝐷𝐷(65)𝑇𝑀𝑌=cooling degree days (base 65 F) for a typical meteorological year for the National Climatic
Data Center station nearest the site. The value is available in Appendix A, Table A.9
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 115 -
𝐶𝐷𝐷(65)𝑚𝑒𝑡𝑒𝑟𝑒𝑑= cooling degree days (base 65 F) determined for the metered period for the National
Climatic Data Center station nearest the site. The value is determined by CenterPoint
Energy based on the metering period start and stop dates.
15.4 Full Measurement for Cooling Equipment
The Full Measurement procedure for electric-to-electric cooling equipment replacement or savings
realized at the cooling equipment, due to control strategies, VAV modifications, building shell
improvements, etc, requires a building simulation. Any full measurement methods other than computer
simulation should be developed in accordance with the 2007 International Performance Measurement and
Inspection Protocol (IPMVP) and be approved by CenterPoint Energy. Computer Simulation Analysis for
measurement and verification of energy savings is used when the energy impacts of the energy efficiency
measures (EEMs) are too complex1 or too costly to analyze with traditional M&V methods. Situations
where computer-based building energy simulations may be appropriate include:
The EEM is an improvement or replacement of the building energy management or control system.
There is more than one EEM and the degree of interaction between them is unknown or too difficult
or costly to measure.
The EEM involves improvements to the building shell or other measures that primarily affect the
building load (e.g., thermal insulation, low-emissivity windows).
The M&V method described here is based, in part, on Option D of the 2007 International Performance
Measurement and Verification Protocol (IPMVP). Valuable insights on computer simulation analysis can
be found in the IPMVP. The Project Sponsor should take the following steps in performing Computer
Simulation Analysis M&V:
9. Work with CenterPoint Energy and its contractor to define a strategy for creating a calibrated
building simulation model in the project-specific M&V plan.
10. Collect the required data from utility bill records, architectural drawings, site surveys, and direct
measurements of specific equipment installed in the building.
11. Adapt the data and enter them into the program’s input files.
12. Run the simulation program for the “base” building model. The base building is the existing
building without the installed EEMs. The base building should comply with minimum state and
federal energy standards.
13. Calibrate the base model by comparing its output with measured data. The weather data for the
base model should be the actual weather occurring during the metering period. Refine the base
building model until the program’s output is within acceptable tolerances of the measured data.
14. Run the calibrated base model using typical weather data to normalize the results.
15. Repeat the process for the post-installation model. Calibration of the retrofit model, if done,
should use data collected from site surveys (to validate that all of the equipment and systems are
installed and operating properly) and possibly spot short-term or utility metering.
16. Estimate the savings. Savings are determined by subtracting the post-installation results from the
baseline results using typical conditions and weather. The savings estimates and simulation
results will be reviewed and verified by CenterPoint Energy or its contractor.
1 Wolpert, J.S. and J. Stein, “Simulation, Monitoring, and the Design Assistance Professional,” 1992 International Energy and
Environment Conference.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 116 -
These steps are described in more detail in the following sections.
15.4.1 Baseline and Post-Retrofit Data Requirements
Simulation Software
To conduct Calibrated Simulation Analysis M&V, it is recommended that the Project Sponsor use the
most current version available of the DOE-2.1E hourly building simulation program. For projects with
small projected incentive payments, the Project Sponsor may use other models if the model can be shown
to adequately model the project site and the EEMs, can be calibrated to a high level of accuracy, and the
calibration can be documented.
Weather Data
Calibrating a computer simulation of a real building for a specific year requires that actual weather data
be used in the analysis. Actual weather data should be collected from a source such as National Climatic
Data Center (NCDC) weather station data. The physical location of the weather station should be the
closest available to the project site. These data should be translated into weather data files that are
compatible with DOE-2. The project-specific M&V plan should specify which weather data sources will
be used. Typical weather data used in the calculation of energy savings should be either Typical
Meteorological Year (TMY2) or TMY3 data types, obtained from the National Renewable Energy
Laboratory (NREL).
Develop a Calibrated Simulation Strategy
The following are issues that either the Project Sponsor or CenterPoint Energy will need to address in
order to define the simulation approach:
Define the baseline building. The baseline building represents the building with baseline equipment
efficiencies as specified by state or federal standards.
Define the post-installation building. The post-installation building represents the building with the
project-related EEMs installed.
Define the calibration data interval. The building models should be calibrated using hourly, daily,
or monthly data. Calibrations to hourly or daily data are preferred to monthly data, since the former is
more accurate than the latter, due to more comparison points. If monthly project site billing data is
used, then spot or short-term data collection for calibrated key values may be used.
Specify spot and short-term measurements to be taken of building systems. These measurements
augment the whole-building data and enable the modeler to accurately characterize building systems.
Spot and short-term measurements are valuable, but may add significant cost and time to the project.
Employ an experienced building modeling professional. Although new simulation software
packages make much of the process easier, a program’s capabilities and real data requirements are not
fully understood by inexperienced users. Employing inexperienced users for this purpose will result
in inefficient use of time in data processing, and in checking and understanding of simulation results.
Building Data Collection
The main categories of data to be collected for the building and proposed EEMs are described below.
Building plans. The Project Sponsor should obtain as-built building plans. If as-built plans are not
available, the Project Sponsor should work with the building owner to define alternative sources.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 117 -
Utility bills. The Project Sponsor should collect a minimum of twelve consecutive months
(preferably 24 months), with applicable dates of utility bills for the months immediately before
installation of the EEMs. The billing data should include monthly kWh consumption and peak electric
demand (kW) for the month. Fifteen minute or hourly data are also desired for calibration. The
Project Sponsor should determine if building systems are sub-metered, and collect these data if
available. If hourly data are required to calibrate the simulation, but no data are available, metering
equipment may need to be installed to acquire hourly data.
Conduct on-site surveys. CenterPoint Energy or its contractor will assist the Project Sponsor to
identify the necessary data to be collected from the building. The Project Sponsor should visit the
building site to collect the data. CenterPoint Energy or its contractor may accompany the Project
Sponsor during the building survey. Data that may be collected include:
HVAC systems - primary equipment (e.g. chillers and boilers): capacity, number, model and
serial numbers, age, condition, operation schedules, etc.
HVAC systems - secondary equipment (e.g., air handling units, terminal boxes):
characteristics, fan sizes and types, motor sizes and efficiencies, design flow rates and static
pressures, duct system types, economizer operation and control
HVAC system controls, including location of zones, temperature set-points, control set-points
and schedules, and any special control features
Building envelope and thermal mass: dimensions and type of interior and exterior walls,
properties of windows, and building orientation and shading from nearby objects
Lighting systems: number and types of lamps, with nameplate data for lamps and ballasts,
lighting schedules, etc.
Plug loads: summarize major and typical plug loads for assigning values per zone
Building occupants: population counts, occupation schedules in different zones
Other major energy consuming loads: type (industrial process, air compressors, water heaters,
elevators), energy consumption, schedules of operation, etc.
Interview operators. The Project Sponsor may choose to interview the building operator. Building
operators can provide much of the above listed information, and also indicate if any deviation in the
intended operation of building equipment exists.
Make spot measurements. The Project Sponsor may find it necessary to record power draw on
certain circuits (lighting, plug load, HVAC equipment, etc.) to determine actual equipment operation
power.
Conduct short-term measurements. Data-logging monitoring equipment may be set up to record
system data as they vary over time. These data reveal how variable load data changes with building
operation conditions such as weather, occupancy, daily schedules, etc. These measurements may
include lighting systems, HVAC systems and motors. The period of measurement should be from one
to several weeks.
Obtain weather data. For calibration purposes, representative site weather data should be obtained
for a nearby NCDC site.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 118 -
Base Building Simulation Models
Once all necessary information is collected, the Project Sponsor should input the simulation data into
DOE-2 code to create the base building model. The modeler should refine the model to obtain the best
representation of the base building. Where possible, the modeler should use measured data and real
building information to verify or replace the program’s default values.
Minimum Energy Standards
The baseline model should comply with minimum state and federal energy standards with respect to the
following:
Baseline equipment/systems models should not include devices (e.g., lamps and ballasts) that are not
allowed to be installed under current regulations.
Baseline equipment models should meet prescriptive efficiency standards requirements for affected
equipment.
Baseline calculations do not have to comply with performance compliance methods that require the
project site to meet an energy budget.
If the existing conditions of the EEMs do not comply with minimum state and federal standards, the
modeler should calibrate the simulation model with the building as it currently exists, and then modify the
existing building model to reflect the baseline efficiencies. This modified, or baseline building is then
used as the base case for computing energy savings.
15.4.2 Calibration
After the base building model has been created and debugged, the modeler should make a comparison of
the energy flows and demand projected by the model to that of the measured utility data. All utility billing
data should be used in the analysis, electric as well as heating fuels, such as natural gas. The modeler may
use either monthly utility bills, or measured hourly data to calibrate the model when available. The
calibration process should be documented to show the results from initial runs and what changes were
made to bring the model into calibration. Statistical indices are calculated during the calibration process to
determine the accuracy of the model. If the model is not sufficiently calibrated, the modeler should revise
the parameters of the model and recalculate the statistics.
Hourly Data Calibration
In hourly calibration, two statistical indices are required to declare a model “calibrated”: monthly mean
bias error (MBE) and the coefficient of variation of the root mean squared error (CV(RMSE))2.
Equations related with the calculation of MBE and CV (RMSE) is listed below. The acceptable tolerances
for these values when using hourly data calibration are shown in Table 30.
𝑀𝐵𝐸 (%) =∑ (𝑀 − 𝑆)ℎ𝑟𝑚𝑜𝑛𝑡ℎ
∑ 𝑀ℎ𝑟𝑚𝑜𝑛𝑡ℎ × 100
2 Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Great Energy Predictor Shootout: Overview and
Discussion of Results,” ASHRAE Transactions Technical Paper, Vol. 100, pt. 2, June, 1994
Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Results of the 1993 Great Energy Predictor Shootout
to Identify the Most Accurate Method for Making Hourly Energy Use Predictions,”: ASHRAE Journal, pp. 72-81, March, 1994
Haberl, J. and S. Thamilseran, “Predicting Hourly Building Energy Use: The Great Energy Predictor Shootout II, Measuring
Retrofit Savings – Overview and Discussion of Results, ASHRAE Transactions, June, 1996.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 119 -
Where:
𝑀ℎ𝑟 = the measured kWh for any hour during the month
𝑆ℎ𝑟 = the simulated kWh for any hour during the month
𝐶𝑉𝐸 (𝑅𝑀𝑆𝐸𝑚𝑜𝑛𝑡ℎ) =√∑ (𝑀 − 𝑆)2
ℎ𝑟 × 𝑁ℎ𝑟 𝑚𝑜𝑛𝑡ℎ
∑ 𝑀ℎ𝑟𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀ℎ𝑟 = the measured kWh for any hour during the month
𝑆ℎ𝑟 = the simulated kWh for any hour during the month
𝑁ℎ𝑟 = the number of hours in the month
Table 30. Acceptable Tolerances for Hourly Data Calibration
Value
MBEmonth 10%
CV(RMSEmonth) 30%
Monthly Data Calibration
Comparing energy use projected by simulation to monthly utility bills is straightforward. First the model
is developed and run using weather data that corresponds to the monthly utility billing periods. Next
monthly-simulated energy consumption and monthly measured data are plotted against each other for
every month in the data set. Equations calculating the error in the monthly and annual energy
consumption are given below. The acceptable tolerances for these values when using monthly data
calibration are shown in Table 31.
𝐸𝑅𝑅𝑚𝑜𝑛𝑡ℎ(%) =(𝑀 − 𝑆)𝑚𝑜𝑛𝑡ℎ
𝑀𝑚𝑜𝑛𝑡ℎ × 100
Where:
𝑀𝑚𝑜𝑛𝑡ℎ = the measured kWh for the month
𝑆𝑚𝑜𝑛𝑡ℎ = the simulated kWh for the month
𝐸𝑅𝑅𝑦𝑒𝑎𝑟 = ∑ 𝐸𝑅𝑅𝑚𝑜𝑛𝑡ℎ
𝑦𝑒𝑎𝑟
Table 31. Acceptable Tolerances for Monthly Data Calibration
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 120 -
Value
ERRmonth 25%
ERRyear 15%
15.4.3 Post-Installation Models
After the measures are installed, a post-installation model can be prepared. The post-installation model
should usually be the baseline model with the substitution of new energy-efficient equipment and
systems. This new model should also be calibrated and documented. The possible calibration mechanisms
are:
Using site survey data to validate that all of the specified equipment and systems are installed, have
the nameplate data used in the model, and are operating properly.
Using spot and/or short-term metering data to calibrate particular model modules of equipment,
systems or end-uses.
Using utility (15 minute, hourly, or monthly) metering data to calibrate the model, as was done with
the pre-installation model.
The above mentioned post-installation model calibration mechanisms are not necessarily mutually
exclusive. If the first two mechanisms are used the model can be calibrated soon after measure
installation. If the last mechanism is used then the model can only be calibrated after sufficient (e.g., 12
months) billing data are available. In some instances the post-installation model should be the only model
calibrated. This can occur when the baseline project site cannot be easily modeled due to significant
changes during the 12 months prior to the new measures being installed and thus the recent billing data
are not representative.
15.4.4 Detailed Energy Savings Calculations
Energy savings are determined from the difference between the outputs of the baseline and post-
installation models. Savings are determined with both models using the same conditions (weather,
occupancy schedules, etc.). To calculate savings, the energy consumption projected by the post-
installation model is subtracted from energy consumption projected by the baseline model. Energy
savings are calculated by the following equation.
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊ℎ𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 − 𝑘𝑊ℎ𝑝𝑜𝑠𝑡
Where:
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year.
𝑘𝑊ℎ𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 =The kilowatt-hour consumption of the baseline building operating under the same
conditions (weather, operation and occupancy schedules, etc.) as the post-installation
building.
𝑘𝑊ℎ𝑝𝑜𝑠𝑡 = The kilowatt-hour consumption of the post-installation building operating under the same
conditions (weather, operation and occupancy schedules, etc.) as the baseline building.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 121 -
16. Measurement Guidelines for Constant Load Motor Measures
16.1 Overview
This chapter presents the simplified M&V approach for projects involving the installation of constant load
motors with efficiency ratings higher than those required by the applicable energy efficiency standard.
Examples of qualifying equipment include:
Constant load chilled water, hot water, or condenser water pumps
Constant speed exhaust, return, and supply fans without dampers or pressure controls
Single-speed cooling tower fans
Constant load industrial processes
Similar capacity, constant speed, energy efficiency motors
Project Sponsors should not use this approach if factors utilized to derive savings vary throughout the
year. Examples may include schedule changes and load changes.
If the project does not meet the above requirements, please refer to Chapter 18 for the appropriate M&V
approach.
Demand and energy savings for motor installations are based on post-construction peak demand (kW), the
motor operating hours, and the difference in efficiency between baseline and higher-efficiency motors.
The peak demand period is defined as weekdays, between the hours of 1 PM and 7 PM, from June 1
through September 30 (excluding holidays) or weekdays, from 6 AM to 10 AM and 6 PM to 10PM, from
December 1 through February 28. The operating hours are assumed to be the same for both baseline and
higher-efficiency motors.
Prescriptive rebates are available for the installation of premium efficiency motors. Savings values
can be obtained by completing the Premium Efficiency Motor Form.
Baseline motor efficiencies are listed in the Standard Motor Table in Appendix B of this document, which
is based on ASHRAE Standard 90.1m-1995. The Standard Motor Table is categorized by motor size and
rotation speed. The baselines for motors whose efficiencies are not listed in the table will be determined
on a case-by-case basis by CenterPoint Energy. The project sponsor must provide demonstrable proof that
energy efficiency was a key criterion in the motor-selection process in order to qualify for incentives. No
incentive payments are made for replacement motors with efficiencies equal to or less than the baseline
efficiency. In addition to having a higher efficiency than baseline motors, all new motors should meet
minimum equipment standards as defined by state and federal law.
16.2 Pre-Construction Activities
16.2.1 Equipment Survey
Project Sponsors should use the Motor and VSD Inventory form to record the following information for
each specified high-efficiency motor:
Motor name
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 122 -
Load served
Motor location
Operating schedule
Equipment manufacturer
Nameplate data including model, horsepower, and speed
16.2.2 Site Inspection
A pre-construction site inspection is generally not required, but in some cases—such as projects involving
additions to existing facilities—this inspection may be requested at CenterPoint Energy's discretion.
16.3 Post-Construction Activities
16.3.1 Equipment Survey
The Project Sponsor provides a post-construction equipment survey, similar to the pre-construction
equipment survey, to CenterPoint Energy as part of the Installation Report. The updated Motor and VSD
Inventory Form reflects the actual, as-built conditions of the project.
16.3.2 Motor Demand Measurement
The Project Sponsor performs spot measurements of the power draw (one-hour average values) of all the
high-efficiency motors installed, and includes these measurements in the Installation Report.
16.3.3 Calculation of Baseline Motor Demand
Equation below is used to determine what the demand would have been had a lower efficiency motor
been specified for installation.
𝑘𝑊𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 =
𝜂𝑝𝑟𝑒
𝜂𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒× 𝑘𝑊 𝑚𝑒𝑡𝑒𝑟𝑒𝑑
Where:
𝜂𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑒𝑑=specified motor efficiency
𝜂𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒 = standard minimum motor efficiency
𝑘𝑊𝑚𝑒𝑡𝑒𝑟𝑒𝑑= spot measured existing motor demand, kW
16.3.4 Site Inspection
After CenterPoint Energy receives an Installation Report, either CenterPoint Energy or its contractor
conducts a post-construction site inspection to verify that the equipment specifications have been
correctly reported by the Project Sponsor in the Installation Report. CenterPoint Energy will require the
Project Sponsor to make any necessary corrections to the Installation Report based on the results of the
inspection.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 123 -
16.4 Calculation of Motor Operating Hours
After CenterPoint Energy approves the Installation Report, the Project Sponsor begins short-term
metering of motor operating hours. The metering must be conducted for a minimum period of one week,
or an amount of time sufficient to capture the full range of operation. Equation below is used to calculate
the annual operating hours using the metered data.
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙 =𝐻𝑜𝑢𝑟𝑠𝑜𝑛
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑× 8760
Where:
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙 = average annual operating hours
𝐻𝑜𝑢𝑟𝑠𝑜𝑛 = operating hours observed during the metering period
𝐻𝑜𝑢𝑟𝑠𝑚𝑒𝑡𝑒𝑟𝑒𝑑 = total number of hours in the metering period
16.5 Calculation of Peak Demand and Energy Savings
Project Sponsors can claim demand savings only for equipment that operates on weekdays between the
hours of 1 PM and 7 PM, Monday through Friday, from June 1 through September 30 (excluding
holidays).
Peak demand and energy savings are calculated according to Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑝𝑟𝑒 − 𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑒𝑡𝑒𝑟𝑒𝑑
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑠𝑎𝑣𝑒𝑑 × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙
Where:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = The kilowatt savings realized during the year
𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑒𝑡𝑒𝑟𝑒𝑑= Spot Measured New Motor Demand, kW
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year
The Sponsor reports the peak demand and energy savings to CenterPoint Energy in the project Savings
Report.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 124 -
17. Prescriptive Program: Premium Efficiency Motors
17.1 Qualifying Equipment
The installed premium efficiency motor must meet the NEMA efficiency standards listed in the table
below.
NEMA Full Load Efficiencies (%)
HP 1,200 RPM 1,800 RPM 3,600 RPM
ODP TEFC ODP TEFC ODP TEFC
1 82.50% 82.50% 85.50% 85.50% 77.00% 77.00%
1.5 86.50% 87.50% 86.50% 86.50% 84.00% 84.00%
2 87.50% 88.50% 86.50% 86.50% 85.50% 85.50%
3 88.50% 89.50% 89.50% 89.50% 85.50% 86.50%
5 89.50% 89.50% 89.50% 89.50% 86.50% 88.50%
7.5 90.20% 91.00% 91.00% 91.70% 88.50% 89.50%
10 91.70% 91.00% 91.70% 91.70% 89.50% 90.20%
15 91.70% 91.70% 93.00% 92.40% 90.20% 91.00%
20 92.40% 91.70% 93.00% 93.00% 91.00% 91.00%
25 93.00% 93.00% 93.60% 93.60% 91.70% 91.70%
30 93.60% 93.00% 94.10% 93.60% 91.70% 91.70%
40 94.10% 94.10% 94.10% 94.10% 92.40% 92.40%
50 94.10% 94.10% 94.50% 94.50% 93.00% 93.00%
60 94.50% 94.50% 95.00% 95.00% 93.60% 93.60%
75 94.50% 94.50% 95.00% 95.40% 93.60% 93.60%
100 95.00% 95.00% 95.40% 95.40% 93.60% 94.10%
125 95.00% 95.00% 95.40% 95.40% 94.10% 95.00%
150 95.40% 95.80% 95.80% 95.80% 94.10% 95.00%
200 95.40% 95.80% 95.80% 96.20% 95.00% 95.40%
17.2 Savings Calculations
The savings are calculated based on Equations below. The motor incentive form applies these equations
automatically to calculate savings for installation of premium efficiency motors.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 0.746 × ℎ𝑝 × %𝐿𝑜𝑎𝑑 × 𝐶𝐹 × (1
𝜂𝐸𝑃𝐴𝐶𝑇−
1
𝜂𝑁𝐸𝑀𝐴)
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑠𝑎𝑣𝑒𝑑 × 𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙
Where:
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = The kilowatt savings realized during the year
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = The kilowatt-hour savings realized during the year
ℎ𝑝 =The horsepower of the motor
%𝐿𝑜𝑎𝑑 =Stipulated %load of the motor
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 125 -
𝐶𝐹 =Stipulated coincident factor
𝜂𝐸𝑃𝐴𝐶𝑇=Baseline efficiency standard. Based on 1992 EPACT standards
𝜂𝑁𝐸𝑀𝐴=New motor efficiency standard. Based on NEMA premium efficiency standards
𝐻𝑜𝑢𝑟𝑠𝑎𝑛𝑛𝑢𝑎𝑙= Stipulated Operating hours. Different values for C&I applications
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 126 -
18. Measurement and Verification for Generic Variable Loads
18.1 Overview
High-efficiency end-use systems that exhibit variable energy demand or operating hours may require
continuous metering to measure and verify energy savings. Examples of such projects are constructions
that involve:
building automation systems
industrial process equipment or systems
chiller plant optimization, including chillers, cooling towers, pumps, etc.
The use of continuous metering for measurement and verification (M&V) of variable loads normally
involves four steps:
1. Reviewing the pre-construction system(s). As with all M&V methods, the Project Sponsor must
review plans and specifications to document relevant components (e.g., piping and ductwork
diagrams, control sequences, and operating parameters).
2. Establishing a baseline model (e.g., an equation that determines energy use when key independent
variables are known). All, or a representative sample, of the systems should be modeled to
establish regression-based equations or curves for defining baseline system energy use as a
function of appropriate variables (e.g., weather or cooling load).
3. Monitoring energy use and/or independent variables such as weather. Monitoring can be done
continuously throughout a full year or for representative periods of time during each performance
year.
4. Determining the savings by subtracting the post-construction energy use from the baseline energy
use (as indicated in the baseline model).
The M&V method described here is based on Option B of the 2007 International Performance
Measurement and Verification Protocol (IPMVP). More details on this method can be found in the
IPMVP.
18.2 Documenting Baseline Characteristics
To establish the baseline characteristics of the new-construction systems, the following steps are taken:
1. The Project Sponsor conducts a pre-construction equipment inventory.
2. Either CenterPoint Energy or its contractor conducts a pre-construction inspection, if necessary.
3. The Project Sponsor develops a baseline energy consumption model.
18.2.1 Pre-Construction Equipment Survey
The Project Sponsor is required to conduct a pre-construction equipment survey, which is part of the
Project Application. The equipment survey itemizes all specified equipment involved in the project. For
each piece of equipment, the survey should list (as applicable) the location, manufacturer, model number,
rated capacity, energy use factors (such as voltage, rated amperage, MBtu/hr, fixture wattage), nominal
efficiency, load served, and any independent variables that affect system energy consumption.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 127 -
18.2.2 Pre-Construction Inspection
A pre-construction site inspection is generally not required, but in some cases—such as projects involving
additions to existing facilities—this inspection may be requested at CenterPoint Energy's discretion.
18.2.3 Baseline Model Development
The energy use of most projects is influenced by independent variables. For such projects, the Project
Sponsor must develop a model (typically using regression techniques) that links independent-variable
data to energy use. The Project Sponsor must include an explanation of the methodologies used for
creating such a model in the Project Application for CenterPoint Energy's review.
Project Sponsors should use manufacturer-supplied performance data for equipment that meets the
minimum requirements of code to establish a relationship between independent variables and energy use.
This relationship is known as the “Baseline System Model” and will likely take the form of an equation.
Regression analysis is typically used to develop such an equation, although other mathematical methods
may be approved. If regression analysis is used, it must be demonstrated that that the model is statistically
valid.
The criteria for establishing statistical validity of the model are:
The model makes intuitive sense; that is, the explanatory variables are reasonable, and the
coefficients have the expected sign (positive or negative) and are within an expected range
(magnitude).
The modeled data represent the population.
The model’s form conforms to standard statistical practice and modeling techniques for the system in
question.
The number of coefficients is appropriate for the number of observations.
The T-statistic for each term in the regression equation is equal to at least 2 (indicates with 95%
confidence that the associated regression coefficient is not zero). The regression R2 is at least 80%.
All data entered into the model are thoroughly documented and model limits (range of independent
variables for which the model is valid) are specified.
The Project Sponsor includes the data used in model development in the Project Application or
Installation Report. Either CenterPoint Energy or its contractor makes a final determination on the
validity of models and monitoring plans and may request additional documentation, analysis, or metering.
18.2.4 Compliance with Energy Standards
The baseline model must comply with all applicable federal and state energy standards and codes. If any
existing equipment that will be part of the project (as may be the case in a new-construction addition to an
existing building) does not meet the applicable standards, the Project Sponsor must document how the
baseline model will be adjusted to account for the standards. In general, however, the M&V plan should
document that the
Baseline equipment characterization meets prescriptive efficiency standards requirements for affected
equipment (e.g., ASHRAE Standard 90.1).
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 128 -
Baseline need not comply with performance compliance methods that require the project site to meet
an energy budget.
Minimum state and federal energy efficiency standards or codes must be incorporated into the
baseline.
18.3 Documenting Post-Construction Characteristics
When construction is complete, the following steps are taken:
1. The Project Sponsor updates the equipment inventory.
2. Either CenterPoint Energy or its contractor conducts an inspection.
3. The Project Sponsor conducts any necessary data collection.
18.3.1 Post-Construction Equipment Survey
The Project Sponsor is required to conduct a post-construction equipment survey to be submitted as part
of the Installation Report. This equipment survey documents the equipment that was actually installed.
For each piece of equipment, the survey should list (as applicable) the location, manufacturer, model
number, rated capacity, energy use factors (such as voltage, rated amperage, MBtu/hr, wattage), nominal
efficiency, load served, and any independent variables that affect system energy consumption.
18.3.2 Post-Construction Inspection
Either CenterPoint Energy or its contractor conducts an inspection to verify that the Project Sponsor has
properly documented the installed equipment. After the inspection, CenterPoint Energy either accepts or
rejects the Installation Report based on the inspection results and project review.
18.3.3 Post-Construction Data Collection
The Project Sponsor must monitor one or both of the following variables simultaneously:
Independent variables that affect energy use. Examples of such data are ambient temperature,
control outputs, flow rate, cooling tons, and building occupancy.
System energy consumption. Energy demand (kW) of installed equipment, metered over a time
period representative of the full range of system operation.
The variable(s) monitored depend on the variable(s) modeled in the Baseline System Model.
18.4 Calculation of Demand and Energy Savings
There are two approaches for calculating demand and energy savings from generic variable load projects.
Both approaches require baseline modeling (as previously discussed) and post-construction metering.
The first approach requires continuous metering of demand and the independent variables used in the
baseline model. Post-construction variable data are used with the baseline model to calculate baseline
energy use.
The second approach involves developing a post-construction model from short-term metering of demand
and continuous metering of independent variables. Data from continuous metered post-construction
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 129 -
variables are then used in the baseline and post-construction models to calculate baseline and post-
construction energy use.
18.4.1 First Approach: Metering Post-Construction Energy Use and Variables
To calculate energy savings using the first approach, the Project Sponsor monitors demand and the same
independent variables that were used for the System Baseline Model. The Project Sponsor then inputs the
post-construction independent variable data to the System Baseline Model and compares post-
construction energy use with baseline energy use. Demand and energy savings, over a single observation
interval, are calculated using Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑏𝑎𝑠𝑙𝑖𝑛𝑒,𝑚𝑎𝑥 − 𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑(𝑘𝑊𝑏𝑎𝑒𝑙𝑖𝑛𝑒,𝑖– 𝑘𝑊𝑝𝑜𝑠𝑡−𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑,𝑖)
𝑛
𝑖=1
Where:
𝑘𝑊𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒,𝑚𝑎𝑥 = maximum baseline equipment demand occurring during utility peak coincident load
period
𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥 = maximum, post-installation equipment demand occurring during utility peak coincident
load period
𝒌𝑾𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝒊= baseline kW calculated from Baseline Model and corresponding to same time interval 𝒊,
system output, weather, etc., conditions as 𝒌𝑾𝒑𝒐𝒔𝒕,𝒊
𝒌𝑾𝒑𝒐𝒔𝒕−𝒎𝒆𝒂𝒔𝒖𝒓𝒆𝒅,𝒊= measured kW obtained through continuous, or representative period, post-installation
metering
18.4.2 Second Approach: Metering Post-Construction Variables
To calculate energy savings using the second approach, the Project Sponsor must first develop a Post-
Construction System Model for use as a proxy for direct post-construction energy use measurement.
Then, the Project Sponsor monitors the relevant independent variables and uses that data to estimate post-
construction energy use. Once the post-construction energy use is estimated, energy savings over the
course of a single observation interval will be calculated using the following Equations below.
𝑘𝑊𝑠𝑎𝑣𝑒𝑑 = 𝑘𝑊𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒,𝑚𝑎𝑥 − 𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑(𝑘𝑊𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒,𝑖– 𝑘𝑊𝑝𝑜𝑠𝑡,𝑖)
𝑛
𝑖=1
Where:
𝑘𝑊𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒,𝑚𝑎𝑥 = maximum, baseline equipment demand occurring during utility peak coincident load
period
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 130 -
𝑘𝑊𝑝𝑜𝑠𝑡,𝑚𝑎𝑥 = maximum, post-installation equipment demand occurring during utility peak coincident
load period
𝒌𝑾𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝒊= Baseline kW calculated from Baseline Model and corresponding to same time interval 𝒊,
system output, weather, etc., conditions as 𝒌𝑾𝒑𝒐𝒔𝒕,𝒊
𝑘𝑊𝑝𝑜𝑠𝑡,𝑖 = Post-installation kW calculated from Post-Installation Model and corresponding to the
measured time interval; measured system output, measured weather variables, etc. in the post-
installation period
For a particular observation interval, the monitored data must be applied to the Baseline System Model
and to the Post-Construction System Model to determine the baseline-system energy and post-
construction system energy input. The modeled-system post-construction is then subtracted from the
baseline energy input value. Energy savings are determined by multiplying this difference by the length of
the observation interval.
18.5 Project-Specific M&V Issues
Specific M&V issues that need to be addressed for generic variable load projects include:
Determination of post-construction metering approach—i.e., metering of energy use or post-
construction variables.
Modeling methodology for Baseline System Model and Post-Construction Model (if used).
Identification of appropriate independent variables.
Duration of post-construction metering.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 131 -
19. Measurement and Verification Using Calibrated Simulation Analysis
19.1 Overview
This section outlines the use of computer simulation analysis for measurement and verification of new
construction energy savings. Computer simulation analysis should be used when the energy impacts of
the energy efficiency measures are too complex6 or too costly to analyze with traditional M&V methods.
Computer-based building energy simulations are appropriate for constructions in which
A building energy management or control system is specified
The degree of interaction among multiple measures is either unknown or too difficult or costly to
measure.
The measures involve improvements that primarily affect building load—e.g., thermal insulation,
low-emissivity windows
Conducting simulation analysis is often a time-consuming and expensive task, and the costs associated
with this approach may be prohibitive in some instances. Also, building simulation software programs are
not always capable of modeling every type or combination of energy efficiency measures.
The approach described here is based, in part, on Option D of the 2001 International Performance
Measurement and Verification Protocol (IPMVP). More information on computer simulation analysis can
be found in the IPMVP.
This approach requires that the Project Sponsor
1. Work with CenterPoint Energy to define a strategy for creating a calibrated building simulation
model in the project-specific M&V plan.
2. Collect the required data from architectural drawings, mechanical plans, equipment schedules,
and equipment submittals.
3. Adapt the data and enter them into the program’s input files.
4. Run the simulation program for the “as-built” high-performance building model. The “as-built”
building is the newly constructed building with all energy efficiency measures installed.
5. Calibrate the model by comparing its output with measured data. The weather data for the model
should be the actual weather occurring during the metering period. Refine the model until the
program’s output is within acceptable tolerances of the measured data.
6. Run the calibrated as-built model using typical weather data to normalize the results.
7. Repeat the process for the baseline building model. The baseline building model is the newly
constructed building with specifications that reflect applicable minimum performance values
(from ASHRAE 90.1 1999 or from the minimum state and federal energy standards, whichever
are more efficient).
8. Calculate the savings by subtracting the as-built results from the baseline results. CenterPoint
Energy reviews and verifies the savings estimates and simulation results.
6 Wolpert, J.S. and J. Stein, “Simulation, Monitoring, and the Design Assistance Professional,” 1992 International Energy and
Environment Conference.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 132 -
These steps are described in more detail in the following sections.
19.2 Software Selection
CenterPoint Energy recommends that the Project Sponsor use the most current version available of the
DOE-2.1E hourly building simulation program. For projects with small projected incentive payments, the
Project Sponsor may use another program, provided that the program can be shown to adequately model
the building, the system or equipment installations can be calibrated to a high level of accuracy, and the
calibration can be documented.
19.3 Developing a Calibrated Simulation Strategy
A sound approach to measuring and verifying your savings using computer simulation analysis must
include the activities listed below. The Project Sponsor and CenterPoint Energy should confer on the best
approach to each activity.
Employ an experienced building modeling professional. Although new simulation software packages
make much of the process easier, a program’s capabilities and real data requirements are not fully
understood by inexperienced users. Employing an experienced modeler can save a significant amount
of time.
Define the baseline building. In general, the baseline building represents the building, as it would
have been built, had minimum standard equipment been installed instead of the high-efficiency
equipment.
Define the as-built building, which represents the building as it was constructed, with all the installed
high-efficiency equipment and systems.
Define the calibration interval. The as-built model should be calibrated using hourly, daily, or
monthly data. Calibrations to hourly or daily data are preferred because there are more data points to
compare. If monthly billing data are used, then spot or short-term data measurements for calibrated
key values may be used.
Specify spot and short-term measurements to be taken of building systems. These measurements
augment the whole-building data and enable the modeler to accurately characterize building systems.
Spot and short-term measurements are valuable, but may add significant cost and time to the project.
19.4 Data Collection
The volume of data required for simulating a real building is significant. The Project Sponsor needs to
collect data from the following sources:
As-built building plans. The Project Sponsor should work with the building owner to gather as-built
building plans.
Utility bills. The Project Sponsor should collect utility bills for a minimum of twelve consecutive
months following construction. The billing data should include monthly consumption (kWh) and
peak electric demand (kW), preferably in fifteen-minute or hourly intervals (for optimal calibration).
If interval data are not available, the Project Sponsor may need to arrange for the installation of
metering equipment to collect the necessary data. Also, the Project Sponsor should determine if
building systems are sub-metered, and collect these data if available.
Conduct on-site surveys and reviews of mechanical plans. CenterPoint Energy helps the Project
Sponsor establish which data must be collected. The Project Sponsor should visit the site to verify the
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 133 -
accuracy of the mechanical plan data. CenterPoint Energy may accompany the Project Sponsor
during this survey. Depending on the project, the Project Sponsor should collect data for
primary HVAC equipment (e.g. chillers and boilers): capacity, number, model and serial
numbers, operation schedules
secondary HVAC equipment (e.g., air handling units, terminal boxes): fan sizes and types,
motor sizes and efficiencies, design flow rates and static pressures, duct system types,
economizer operation and control
HVAC controls, including the location of zones, temperature set-points, control set-points
and schedules, and any special control features
building envelope and thermal mass: dimensions and type of interior and exterior walls,
properties of windows, and building orientation and shading
lighting systems: number and types of lamps, with nameplate data for lamps and ballasts,
lighting schedules
plug loads: summarize major and typical plug loads for assigning values per zone
occupancy: population counts, occupation schedules in different zones
other major energy consuming loads: type (industrial process, air compressors, water heaters,
elevators), energy consumption, schedules of operation.
Interview operators. Building operators can provide much of the above listed information and can
also inform on any deviation in the intended operation of equipment.
Make spot measurements. To determine the actual power draw of operating equipment, the Project
Sponsor may find it necessary to meter certain circuits (lighting, plug load, HVAC equipment).
Conduct short-term measurements. Data-logging equipment may be set up to record system data as
they vary over time. These measurements may involve lighting systems, HVAC systems, and motors.
The period of measurement should be from one to several weeks.
Obtain weather data. Calibrating a computer simulation of a real building for a specific year
requires the use of actual weather data in the analysis. Actual weather data should be collected from a
source such as National Climatic Data Center (NCDC) weather station data. The physical location of
the weather station should be the closest available to the project site. These data should be translated
into weather data files that are compatible with DOE-2. In the M&V plan, the Project Sponsor should
specify which weather data sources will be used.
Typical weather data used in the calculation of energy savings should be either Typical
Meteorological Year (TMY) or TMY2 data types, obtained from the National Renewable Energy
Laboratory (NREL).
19.5 Building Simulation Models
Once all necessary information is collected, the Project Sponsor inputs the data into DOE-2 code to create
the as-built model. The modeler should refine the model to obtain the best representation of the as-built
building. Where possible, the modeler should use measured data and real building information to verify or
replace the program’s default values.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 134 -
19.5.1 Calibration
After the as-built model is created and debugged, the modeler should make a comparison of the energy
flows and demand projected by the model to that of the utility data. All utility billing data should be used
in the analysis, electric as well as heating fuels, such as natural gas. The modeler may use either monthly
utility bills, or measured hourly data to calibrate the model when available.
The modeler should document the calibration process to show the results from initial runs and what
changes were made to bring the model into calibration. Statistical indices are calculated during the
calibration process to determine the accuracy of the model. If the model is not sufficiently calibrated, the
modeler should revise the parameters of the model and recalculate the statistics.
19.5.2 Hourly Data Calibration
In hourly calibration, two statistical indices are required to declare a model calibrated: monthly mean bias
error (MBE) and the coefficient of variation of the root mean squared error (CV(RMSE))7. Equations
below Error are used to calculate MBE and CV(RMSE).
MBE (%) =∑ (M − S)hrmonth
∑ Mhrmonth × 100
Where:
Mhr = the measured kWh for any hour during the month
Shr = the simulated kWh for any hour during the month
CVE (RMSEmonth) =√∑ (M − S)2
hr × Nhr month
∑ Mhrmonth × 100
Where:
Mhr = the measured kWh for any hour during the month
Shr = the simulated kWh for any hour during the month
Nhr = the number of hours in the month
The acceptable tolerances for these values when using hourly data calibration are shown in Table 32.
7 Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Great Energy Predictor Shootout: Overview and
Discussion of Results,” ASHRAE Transactions Technical Paper, Vol. 100, pt. 2, June, 1994
Kreider, J. and J. Haberl, “Predicting Hourly Building Energy Usage: The Results of the 1993 Great Energy Predictor Shootout
to Identify the Most Accurate Method for Making Hourly Energy Use Predictions,”: ASHRAE Journal, pp. 72-81, March, 1994
Haberl, J. and S. Thamilseran, “Predicting Hourly Building Energy Use: The Great Energy Predictor Shootout II, Measuring
Retrofit Savings – Overview and Discussion of Results, ASHRAE Transactions, June, 1996.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 135 -
Table 32. Acceptable Tolerances for Hourly Data Calibration
Value
MBEmonth 10%
CV(RMSEmonth) 30%
19.5.3 Monthly Data Calibration
Comparing simulated energy use to monthly utility bills is straightforward. First, the model is developed
and run using weather data that correspond to the monthly utility billing periods. Next, monthly simulated
energy consumption and monthly measured data are plotted against each other for every month in the data
set. Equations below are used to calculate the error in the monthly and annual energy consumption,
respectively.
ERRmonth(%) =(M − S)month
Mmonth × 100
Where:
Mmonth = the measured kWh for the month
Smonth = the simulated kWh for the month
ERRyear = ∑ ERRmonth
year
Table 33. Acceptable Tolerances for Monthly Data Calibration
Value
ERRmonth 25%
ERRyear 15%
19.5.4 Baseline Models
After calibrated simulation of the as-built model, the baseline model can be prepared. The baseline model
is usually the as-built model with the substitution of minimum energy standards for equipment and
systems. This new baseline model should also be documented.
19.5.5 Minimum Energy Standards
The baseline model should comply with minimum state and federal energy standards with respect to the
following:
Baseline equipment/systems should not include devices (such as lamps and ballasts) that are not
allowed under current regulations.
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 136 -
Baseline equipment models should meet prescriptive efficiency standards for affected equipment.
These requirements are found local/federal energy codes. The applicable standard requiring the
highest efficiency should be used.
Baseline calculations do not have to comply with performance compliance methods that require the
project site to meet an energy budget.
19.5.6 Detailed Energy Savings Calculations
Energy savings are determined from the difference between the outputs of the baseline and as-built
models. Savings are determined with both models using the same conditions (weather, occupancy
schedules, etc.). To calculate savings, the energy consumption projected by the as-built model is
subtracted from energy consumption projected by the baseline model.
𝑘𝑊ℎ𝑠𝑎𝑣𝑒𝑑 = ∑(𝑘𝑊𝑏𝑎𝑠𝑒𝑙𝑖𝑛𝑒,𝑖– 𝑘𝑊𝑝𝑜𝑠𝑡,𝑖)
𝑛
𝑖=1
Where:
𝒌𝑾𝒃𝒂𝒔𝒆𝒍𝒊𝒏𝒆,𝒊= Baseline kW calculated from Baseline Model and corresponding to same time interval 𝒊,
system output, weather, etc., conditions as 𝒌𝑾𝒑𝒐𝒔𝒕,𝒊
𝑘𝑊𝑝𝑜𝑠𝑡,𝑖 = Post-installation kW calculated from Post-Installation Model and corresponding to the
measured time interval; measured system output, measured weather variables, etc. in the post-
installation period
19.6 Project-Specific M&V Issues
Project Sponsors who are using the computer simulation analysis approach must include the following in
their project-specific M&V plans:
Identification of which version of DOE-2 is will be used, who will supply the program, and what, if
any, pre- and post-processors will be used.
As-built building description (age square footage, location, etc.) including a description of building
systems that have been upgraded to high-efficiency.
Description of any building operation conditions (set-points, schedules, etc.) that are affected by the
energy efficiency specifications.
Documentation of incorporation of state and federal standards in the baseline model.
Documentation of the calibrated simulation strategy and project procedure, including differences in
calibration parameters between the baseline and as-built cases.
A summary of the building data to be collected and sources (e.g., site surveys, drawings).
Identification of spot and short-term measurements to be made.
Selection of the calibration data interval (should be hourly or monthly).
Program Manual v 16 Measurement and Verification Guidelines for New Construction Projects
2016 Commercial Standard Offer Program
CenterPoint Energy Section 3. - 137 -
Identification and source of weather data used (NCDC weather station or typical weather data).
Identification of the statistical calibration tolerances and graphical techniques to be used.
Indication of who will perform the simulation analysis and calibration.
Specification of format for documentation.
Program Manual v 16 Appendix
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 138 -
Appendix Section 4.
These appendices include tables of minimum equipment efficiency standards for cooling, lighting, and
motors, as well as other supplemental information about the program. This information is also available
on the program Web site at https://centerpoint.anbetrack.com/
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 139 -
A. Standard Cooling Equipment Tables
A.1 Overview
This document contains reference data for estimating demand and energy savings for cooling equipment
in the C&I Standard Offer Program. The data are equipment efficiency standards or climate data that will
be used to develop the baseline system models and to evaluate savings for all projects under the C&I
Standard Offer Program.
Cooling equipment installed under the program must exceed the minimum new equipment efficiency
standards shown in the tables. In addition, the minimum baseline efficiencies define the baseline for
calculating energy savings. The guidelines in Section III (M&V Guidelines), Chapter 3 (Guidelines for
Cooling Equipment) describe the application of these equipment efficiency standards and coefficient
tables for estimating baseline demand and energy use and cooling equipment demand and energy savings.
For the following types of cooling equipment, baseline efficiency ratings are provided in Table A.1
through Table A.8 below:
Unitary air conditioners and heat pumps (air cooled, evaporative cooled, or water cooled)
Packaged-terminal air conditioners and heat pumps
Room air conditioners and heat pumps
Water-source and ground-water source heat pumps
Water- and air-cooled water chilling packages
Table A.1 through Table A.8 present the minimum efficiencies of particular types of cooling equipment.
The performance standard data in these tables should be used to determine the rated baseline equipment
efficiencies. The baseline for equipment for which rating conditions are not provided shall be defined as
the energy consumption of the actual existing equipment.
Table A.9 Of this document presents the cooling degree-days (CDD) for a weather station located in the
CenterPoint Energy distribution service territory. Cooling degree-day data are used to normalize metered
energy consumption to a typical meteorological year (TMY3). M&V Guideline 3 describes the
application of weather data for estimating baseline energy use and cooling equipment energy savings.
Table A.10 provides the coefficients necessary to complete the air-conditioning equipment deemed
savings calculation described in Section III, Chapter 3.
Tables A.11-13 present baselines for early retirement projects. Early retirement projects must involve
replacement of a working system. Baseline efficiency will be estimated according to the capacity, type
(package or split, heat pump or air conditioner), and year of manufacture of the replaced system. Baseline
efficiency levels for air conditioners are provided in Table A.10, and for heat pumps in Table A.11, for
systems installed between 1990 and 2007.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 140 -
A.2 Tables
Table A.1 : Standard rating conditions and minimum performance for unitary air conditioners and
heat pumps, air cooled, electric, <135,000 Btu/hr (< 11.25 tons) capacity for new construction and
replace on burnout, - Except packaged terminal and room air conditioners.
Mode
Cooling Capacity Minimum
Performance
Standard8 Btu/hr tons
Air
Conditioner
< 65,000 < 5.42 13 SEER
65,000 & < 135,000 5.42 & < 11.25 11 EER
135,000 & < 240,000 11.25 & < 20 10.8 EER
240,000 & < 760,000 20 & < 63.3 9.8 EER
760,000 63.3 9.5 EER
Heat Pump
< 65,000 < 5.42 13 SEER
65,000 & < 135,000 5.42 & < 11.25 10.8 EER
135,000 & < 240,000 11.25 & < 20 10.4 EER
240,000 20 9.3 EER
† *For all air conditioners and heat pumps larger than 5.4 tons, the minimum efficiency levels provided in this table are reduced by 0.2 from the
values published in the referenced sources, in accordance with the footnotes to those tables, allowing this reduction for systems with heating
section other than electric resistance heat.
8 Reference: Texas Resource Manual Volume 3
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 141 -
Table A.2 : Standard rating conditions and minimum performance for unitary air conditioners and
heat pumps – evaporative cooled, electric, <135,000 Btuh (< 11.25 tons) cooling capacity.
Cooling Capacity Rating indoor
air F db / F wb
Rating outdoor air
F db/F wb
Baseline
Performance
Standard9
Minimum
Performance
Standard10
Btuh tons
< 65,000 < 5.42 80/67 95/75 9.3 EER 12.1 EER
65,000 &
< 135,000
5.42
& <
11.25
80/67 95/75 10.5 EER† 11.5 EER
†
† Deduct 0.2 from the required EERs for units with a heating section other than electric resistance heat.
Table A.3: Standard rating conditions and minimum performance for water-cooled air
conditioners and heat pumps, electric, <135,000 Btuh (< 11.25 tons) capacity.
Equipment
Cooling
capacity,
BTU/h
Rating
Condition,
air F db / F
wb
Rating
Condition,
entering
water F
Baseline
Performance
Standard11
Minimum
Performance
Standard12
Water cooled heat
pumps
< 65,000 80/67
85 9.3 EER -
86 - 12.0 EER†
75 10.2 EER
65,000 and
<135,000 80/67
85 10.5 EER -
86 - 12.0 EER
Water cooled heat
pumps (Heating
Mode)
< 135,000 70/60 70 3.8 COP
68 4.2 COP
Ground water
cooled heat pumps
(Cooling Mode)
< 135,000 80/67
70 11.0 EER -
59 11.1 EER 16.2 EER
80/67 50 11.5 EER
Ground water
cooled heat pumps
(Heating Mode)
< 135,000 70/60 70 3.4 COP
70/60 50 3.0 COP 3.6 COP
Water cooled
unitary air
conditioners
< 65,000 80/67 85 9.3 EER -
86 - 12.1 EER
65,000 and
<135,000 80/67
85 10.5 EER -
86 - 11.5 EER††
† For units with capacities less than 17,000 Btu/h, the minimum efficiency is 11.2 EER.
†† Deduct 0.2 from the required EERs for units with a heating section other than electric resistance heat.
9 Reference: ASHRAE Standard 90.1-1989, Table 10-2.
10 Reference: ASHRAE Standard 90.1-1999, Table 6.2.1.A.
11 Reference: ASHRAE Standard 90.1-1989, Table 10-3 and Table 10-5.
12 Reference: ASHRAE Standard 90.1-1999, Table 6.2.1.B.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 142 -
Table A.4: Standard rating conditions and minimum performance for packaged terminal air
conditioners and heat pumps, air-cooled, electric for new construction and replace on burnout
Equipment Category Cooling
Capacity [Btuh]
Energy Conservation
Standards (Cooling)
PTAC
Standard Size
<7,000 11.7 EER
7,000-15,000 13.8 − (0.300 𝑥 𝐶𝑎𝑝
1000) EER
>15,000 9.3 EER
Non-Standard Size
<7,000 9.4 EER
7,000-15,000 10.9 − (0.213 𝑥 𝐶𝑎𝑝
1000) EER
>15,000 7.7 EER
PTHP
Standard Size
<7,000 11.9 EER
7,000-15,000 14.0 − (0.300 𝑥 𝐶𝑎𝑝
1000) EER
>15,000 9.5 EER
Non-Standard Size
<7,000 9.3 EER
7,000-15,000 10.8 − (0.213 𝑥 𝐶𝑎𝑝
1000) EER
>15,000 7.6 EER † Cap is the rated cooling capacity of the unit in Btu/h. If the unit’s capacity is greater than 15,000 Btu/h, use 15,000 Btu/h in the calculation.
Table A.5: Standard rating conditions and minimum performance for room air conditioners and
room air conditioner heat pumps, electric for new construction and replace on burnout
Category Capacity, BTUH
Minimum
Performance
Standard
(EER)13
Without reverse cycle and with
louvered sides
< 8,000 11.0
8,000 and <14,000 10.9
14,000 and <20,000 10.7
20,000 and <25,000 9.4
25,000 9.0
Without reverse cycle and
without louvered sides
< 8,000 10.0
8,000 and <11,000 9.6
11,000 and <14,000 9.5
14,000 and <20,000 9.3
20,000 9.4
With reverse cycle and with
louvered sides
< 20,000 9.8
20,000 9.3
With reverse cycle and without
louvered sides
< 14,000 9.3
14,000 8.7
13
Reference: Reference: Texas Resource Manual Volume 3
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 143 -
Table A.6: Baseline and minimum performance standards for large unitary air conditioners and
heat pumps, electric, 135,000 Btuh ( 11.25 tons) capacity except for air cooled equipment (see
Table A.1 above).
Equipment Type Cooling Capacity
Baseline
Performance
Standard14
Minimum
Performance
Standard15
Btuh tons EER EER
Water or
evaporatively cooled
air conditioners
135,000 11.25 9.6 11.0
Water or
evaporatively cooled
condensing units
135,000 11.25 12.9 13.1
† Deduct 0.2 from the required EERs for units with a heating section other than electric resistance heat.
ton
kW
EERWatt
kW
hrton
Btu
Btu
hrWatt
EERton
kWePerformanc
out
out
12
000,1
1*000,12*
1
Table A.7: Minimum performance standards for water chilling packages, electric for new
construction and replace on burnout.
Equipment Type
Cooling
Capacity
(tons)
Minimum Performance
Standard16
COP
Water cooled,
(screw, scroll)
<75 0.780 kW/ton
75 and <150 0.775 kW/ton
150 and <300 0.680 kW/ton
300 and <600 0.620 kW/ton
600 0.620 kW/ton
Water cooled
(centrifugal)
<75 0.634 kW/ton
75 and <150 0.634 kW/ton
150 and <300 0.634 kW/ton
300 and <600 0.576 kW/ton
600 0.570 kW/ton
Air Cooled
(centrifugal/ccrew/scroll)
<75 9.562 EER
75 and <150 9.562 EER
150 and <300 9.562 EER
300 and <600 9.562 EER
600 9.562 EER
ton
kW
COPBtu
kWh
hrton
Btu
Btu
Btu
COPton
kWePerformanc
in
out
out
in 517.3
412,3
1*000,12*
1
14
Reference: ASHRAE Standard 90.1-1989, Table 10-6, 17a New Federal guidelines 15
Reference: ASHRAE Standard 90.1-1999, Table 6.2.1.A and Table 6.2.1.B, 18a New Federal guidelines 16
Reference: Reference: Texas Resource Manual Volume 3
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 144 -
Table A.8: Standard rating conditions and minimum performance for water chilling packages, gas
absorption
Equipment Type Cooling
Capacity
Baseline
Performance
Standard17
(COP)
Minimum
Performance
Standard18
(COP)
Air-cooled absorption, single-effect All capacities 0.48 0.60
Water-cooled absorption, single-effect All capacities 0.60 0.70
Absorption double effect, indirect-fired All capacities 0.95 1.00
Absorption double effect, direct-fired All capacities 0.95 1.00
Table A.9: TMY3 Cooling Degree Days (base 65) for the CenterPoint Energy service territory
Weather Station CDD65
(oF day)
Houston 2,700
17
Reference: ASHRAE Standard 90.1-1999, Table 6.2.1.C. 18
Reference: ASHRAE Standard 90.1-1999, Table 6.2.1.C.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix Section
3. - 145 -
Table A.10: Deemed savings coefficients for the Houston, TX climate for various building types and
package and split DX system types.
Building Type Principal Building Activity
Package and Split DX
Air Conditioner Heat Pump
CF EFLHC CF EFLHC EFLHH
Education
College 0.85 2,175 -- -- --
Primary School 0.84 1,265 0.84 1,265 279
Secondary School 0.96 1,396 0.96 1,396 193
Food Sales Convenience 0.88 4,168 -- -- --
Supermarket 0.73 1,325 0.73 1,325 384
Food Service Full-Service Restaurant 0.86 1,881 0.86 1,881 591
Quick-Service Restaurant 0.85 1,536 0.85 1,536 316
Healthcare Hospital 0.94 4,676 0.94 4,676 1,239
Outpatient Healthcare 0.82 3,116 0.82 3,116 167
Large Multifamily Midrise Apartment 0.98 1,797 0.98 1,797 244
Lodging
Large Hotel 0.95 3,327 0.95 3,327 766
Nursing Home 0.84 2,368 -- -- --
Small Hotel/Motel 0.81 2,537 0.81 2,537 462
Mercantile Stand-Alone Retail 0.91 1,437 0.91 1,437 200
Strip Mall 0.93 1,456 0.93 1,456 182
Office
Large Office 0.88 1,903 0.88 1,903 281
Medium Office 0.75 1,357 0.75 1,357 287
Small Office 0.85 1,445 0.85 1,445 74
Public Assembly Public Assembly 0.86 2,559 -- -- --
Religious Worship Religious Worship 0.87 2,028 -- -- --
Service Service 0.87 2,429 -- -- --
Warehouse Warehouse 0.81 545 0.81 545 523
Other Other 0.73 545 0.73 545 74
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix Section 3. - 146 -
Table A.11: Deemed savings coefficients for the Houston, TX climate for various building types and
chiller system types.
Building Type Principal Building
Activity
Chiller
Air Cooled Water Cooled
Demand
Coefficients
Energy
Coefficients
Demand
Coefficients
Energy
Coefficients
Education College 0.80 1,858 0.84 2,099
Secondary School 0.78 1,297 0.82 1,726
Food Sales Supermarket -- -- 0.88 3,012
Healthcare Hospital 0.82 3,753 0.81 4,708
Lodging Large Hotel 0.76 2,690 0.82 3,475
Nursing Home 0.80 1,960 0.84 2,172
Office Large Office 0.79 1,680 0.82 2,185
Public Assembly Public Assembly 0.81 2,264 0.86 2,482
Religious Worship Religious Worship 0.83 1,474 0.84 1,594
Other Other 0.76 1,297 0.81 1,594
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 147 -
Table A.12: Baseline Efficiency of Air Conditioners Replaced via Early Retirement
Split
System
< 5.4 tons
Package
System
< 5.4 tons
All Systems
5.4 – 11.25
tons
All Systems
11.25 – 20
tons
All Systems
20 – 63.3
tons
All Systems
> 63.3. tons
(SEER) (SEER) (EER) (EER) (EER) (EER)
1990 10 9.7 8.9 8 8 7.8
1991 10 9.7 8.9 8 8 7.8
1992 10 9.7 8.9 8.3 8.3 8
1993 10 9.7 8.9 8.3 8.3 8
1994 10 9.7 8.9 8.3 8.3 8
1995 10 9.7 8.9 8.3 8.3 8
1996 10 9.7 8.9 8.3 8.3 8
1997 10 9.7 8.9 8.3 8.3 8
1998 10 9.7 8.9 8.3 8.3 8
1999 10 9.7 8.9 8.3 8.3 8
2000 10 9.7 8.9 8.3 8.3 8
2001 10 9.7 8.9 8.3 8.3 8
2002 10 9.7 10.1 9.5 9.3 9
2003 10 9.7 10.1 9.5 9.3 9
2004 10 9.7 10.1 9.5 9.3 9
2005 10 9.7 10.1 9.5 9.3 9
2006 13 13 10.1 9.5 9.3 9
2007 13 13 10.1 9.5 9.3 9
2008 13 13 10.1 9.5 9.3 9
2009 13 13 10.1 9.5 9.3 9
2010 13 13 11 10.8 9.8 9.5
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 148 -
Table A.13: Baseline Efficiency of Heat Pumps Replaced via Early Retirement
Split
System
< 5.4 tons
Package
System
< 5.4 tons
All Systems
5.4 – 11.25 tons
All Systems
11.25 – 20 tons
All Systems
20 – 63.3 tons
All Systems
> 63.3. tons
(SEER) (SEER) (EER) (EER) (EER) (EER)
1990 10 9.7 8.9 8 8 7.8
1991 10 9.7 8.9 8 8 7.8
1992 10 9.7 8.9 8.3 8.3 8.5
1993 10 9.7 8.9 8.3 8.3 8.5
1994 10 9.7 8.9 8.3 8.3 8.5
1995 10 9.7 8.9 8.3 8.3 8.5
1996 10 9.7 8.9 8.3 8.3 8.5
1997 10 9.7 8.9 8.3 8.3 8.5
1998 10 9.7 8.9 8.3 8.3 8.5
1999 10 9.7 8.9 8.3 8.3 8.5
2000 10 9.7 8.9 8.3 8.3 8.5
2001 10 9.7 8.9 8.3 8.3 8.5
2002 10 9.7 9.9 9.1 8.8 8.8
2003 10 9.7 9.9 9.1 8.8 8.8
2004 10 9.7 9.9 9.1 8.8 8.8
2005 10 9.7 9.9 9.1 8.8 8.8
2006 13 13 9.9 9.1 8.8 8.8
2007 13 13 9.9 9.1 8.8 8.8
2008 13 13 9.9 9.1 8.8 8.8
2009 13 13 9.9 9.1 8.8 8.8
2010 13 13 10.8 10.4 9.3 9.3
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 149 -
Table A.14: Baseline Efficiency of Electric Chillers Replaced via Early Retirement
Air Cooled
< 150 tons
Air Cooled
≥ 150 tons
Water Cooled
Centrifugal
<150 tons
Water Cooled
Centrifugal
> 150 to < 300
tons
Water
Cooled
Centrifugal
> 300 tons
Water
Cooled
Screw/Scroll
<150 tons
Water
Cooled
Screw/Scroll
> 150 to <
300 tons
Water
Cooled
Screw/Scroll
> 300 tons
EER EER kW/ton kW/ton kW/ton kW/ton kW/ton kW/ton
1990 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1991 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1992 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1993 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1994 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1995 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1996 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1997 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1998 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
1999 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
2000 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
2001 9.212 8.530 0.925 0.837 0.748 0.925 0.837 0.748
2002 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2003 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2004 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2005 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2006 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2007 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2008 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2009 9.554 9.554 0.703 0.634 0.576 0.79 0.718 0.639
2010 9.562 9.562 0.634 0.634 0.576 0.78 0.680 0.620
2011 9.562 9.562 0.634 0.634 0.576 0.78 0.680 0.620
2012 9.562 9.562 0.634 0.634 0.576 0.78 0.680 0.620
2013 9.562 9.562 0.634 0.634 0.576 0.78 0.680 0.620
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix Section 3. - 150 -
B. Table of Standard Motor Efficiencies Table
B.1 Overview
This document contains reference data for estimating demand and energy savings in C&I Standard Offer
Program for energy efficient motors and related measures. For motors installed under the program, the
equipment must exceed these minimum efficiency standards. In addition, the minimum efficiencies define
the baseline for calculating demand and energy savings. M&V Guideline 4 for motor measures describes
the application of these equipment efficiency standards for estimating baseline demand and energy use
and measure demand and energy savings.
B.2 Table
The efficiencies of permanently wired, poly-phase motors that are at least one horsepower in size and that
are used for fan, pumping, and conveyance applications are defined in Table B.1. Table B.1 is based on
ASHRAE Standard 90.1m-1995. Note, however, that the following motors are exempt from these
requirements:
Motors in appliances.
Refrigeration compressor motors.
Multi-speed motors.
Motors that are used as components of cooling equipment where the motors are part of the efficiency
ratings listed in the Standard Cooling Equipment Tables.
The efficiency values given in Table B.1 should be used to determine the equipment baseline. Equipment
installed under the C&I Standard Offer Program must be more efficient than the standards shown in order
to be eligible for incentives.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 151 -
Table B.1: Minimum nominal full-load motor efficiency for single speed poly-phase motors
Motor Horsepower 2-Pole 4-Pole 6-Pole 8-Pole
Open
1.0 -- 81.5 78.5 72.0
1.5 81.5 82.5 82.5 74.0
2.0 82.5 82.5 84.0 84.0
3.0 82.5 85.5 85.5 85.5
5.0 84.0 86.5 86.5 86.0
7.5 86.5 87.5 87.5 87.5
10.0 87.5 88.5 89.5 88.5
15.0 88.5 90.2 89.5 88.5
20.0 89.5 90.2 90.2 89.5
25.0 90.2 91.0 91.0 89.5
30.0 90.2 91.7 91.7 90.2
40.0 91.0 92.4 92.4 90.2
50.0 91.7 92.4 92.4 91.0
60.0 92.4 93.0 93.0 91.7
75.0 92.4 93.6 93.0 93.0
100.0 92.4 93.6 93.6 93.0
125.0 93.0 94.1 93.6 93.0
150.0 93.0 94.5 94.1 93.0
200.0 94.1 94.5 94.1 93.0
Enclosed
1.0 74.0 81.5 78.5 72.0
1.5 81.5 82.5 84.0 75.5
2.0 82.5 82.5 85.5 81.5
3.0 84.0 86.5 86.5 82.5
5.0 86.5 86.5 86.5 84.0
7.5 87.5 88.5 88.5 84.0
10.0 88.5 88.5 88.5 87.5
15.0 89.5 90.2 89.5 87.5
20.0 89.5 90.2 89.5 88.5
25.0 90.2 91.7 91.0 88.5
30.0 90.2 91.7 91.0 90.2
40.0 91.0 92.4 92.4 90.2
50.0 91.7 92.4 92.4 91.0
60.0 92.4 93.0 93.0 91.0
75.0 92.4 93.6 93.0 92.4
100.0 93.0 94.1 93.6 92.4
125.0 94.1 94.1 93.6 93.0
150.0 94.1 94.5 94.5 93.0
200.0 94.5 94.5 94.5 93.6
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix Section 3. - 152 -
C. Deemed Demand and Energy Saving for VFD on AHU Supply Fans
Table C.1 Deemed Energy and Demand Savings Values for Outlet Damper Part-Load Fan Control (Houston Weather)
HP Hosptial &
Healthcare Office-Large Office Small Education - K-12
Education - College and
University Retail
Restaurant - Fast
Food
Restaurant - Sit
Down
kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh
1 0.097 1,167 0.097 557 0.08 501 0.03 501 0.097 577 0.097 699 0.097 864 0.097 864
2 0.191 2,292 0.191 1,095 0.156 984 0.059 984 0.191 1,133 0.191 1,373 0.191 1,698 0.191 1,698
3 0.278 3,339 0.278 1,595 0.228 1,433 0.086 1,433 0.278 1,651 0.278 2,000 0.278 2,473 0.278 2,473
5 0.458 5,502 0.458 2,627 0.375 2,362 0.141 2,360 0.458 2,720 0.458 3,295 0.458 4,074 0.458 4,074
7.5 0.679 8,159 0.679 3,897 0.556 3,502 0.209 3,501 0.679 4,034 0.679 4,887 0.679 6,042 0.679 6,042
10 0.895 10,757 0.895 5,138 0.734 4,618 0.276 4,615 0.895 5,318 0.895 6,443 0.895 7,967 0.895 7,967
15 1.321 15,870 1.321 7,579 1.082 6,812 0.407 6,809 1.321 7,845 1.321 9,505 1.321 11,753 1.321 11,753
20 1.761 21,160 1.761 10,106 1.443 9,083 0.542 9,079 1.761 10,461 1.761 12,674 1.761 15,670 1.761 15,670
25 2.184 26,248 2.184 12,536 1.79 11,267 0.673 11,262 2.184 12,976 2.184 15,721 2.184 19,438 2.184 19,438
30 2.601 31,259 2.601 14,929 2.132 13,418 0.801 13,412 2.601 15,453 2.601 18,723 2.601 23,149 2.601 23,149
40 3.446 41,410 3.446 19,777 2.824 17,776 1.061 17,767 3.446 20,471 3.446 24,802 3.446 30,667 3.446 30,667
50 4.308 51,762 4.308 24,721 3.53 22,220 1.327 22,209 4.308 25,589 4.308 31,003 4.308 38,333 4.308 38,333
60 5.136 61,716 5.136 29,475 4.208 26,493 1.582 26,480 5.136 30,510 5.136 36,965 5.136 45,705 5.136 45,705
75 6.386 76,735 6.386 36,648 5.233 32,940 1.967 32,924 6.386 37,935 6.386 45,961 6.386 56,828 6.386 56,828
100 8.515 102,314 8.515 48,864 6.977 43,920 2.622 43,898 8.515 50,580 8.515 61,281 8.515 75,771 8.515 75,771
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 153 -
Table C.2 Deemed Energy and Demand Savings Values for Inlet Damper Part-Load Fan Control (Houston Weather)
HP Hosptial &
Healthcare Office-Large Office Small Education - K-12
Education - College and
University Retail
Restaurant - Fast
Food
Restaurant - Sit
Down
kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh
1 0.115 1,729 0.115 809 0.094 727 0.035 734 0.115 837 0.115 1,016 0.115 1,265 0.115 1,265
2 0.225 3,397 0.225 1,590 0.184 1,427 0.069 1,441 0.225 1,644 0.225 1,996 0.225 2,484 0.225 2,484
3 0.328 4,948 0.328 2,316 0.268 2,079 0.1 2,099 0.328 2,395 0.328 2,907 0.328 3,619 0.328 3,619
5 0.541 8,153 0.541 3,816 0.441 3,426 0.165 3,458 0.541 3,947 0.541 4,790 0.541 5,962 0.541 5,962
7.5 0.803 12,092 0.803 5,659 0.654 5,080 0.244 5,128 0.803 5,853 0.803 7,104 0.803 8,842 0.803 8,842
10 1.058 15,942 1.058 7,461 0.863 6,698 0.322 6,761 1.058 7,717 1.058 9,366 1.058 11,658 1.058 11,658
15 1.561 23,519 1.561 11,006 1.273 9,882 0.475 9,975 1.561 11,385 1.561 13,817 1.561 17,198 1.561 17,198
20 2.081 31,358 2.081 14,675 1.697 13,176 0.634 13,300 2.081 15,180 2.081 18,423 2.081 22,931 2.081 22,931
25 2.582 38,899 2.582 18,204 2.105 16,344 0.786 16,498 2.582 18,830 2.582 22,853 2.582 28,445 2.582 28,445
30 3.075 46,325 3.075 21,679 2.507 19,464 0.937 19,648 3.075 22,424 3.075 27,216 3.075 33,876 3.075 33,876
40 4.073 61,368 4.073 28,719 3.322 25,785 1.241 26,028 4.073 29,706 4.073 36,053 4.073 44,876 4.073 44,876
50 5.091 76,710 5.091 35,899 4.152 32,231 1.551 32,535 5.091 37,133 5.091 45,067 5.091 56,095 5.091 56,095
60 6.07 91,461 6.07 42,803 4.951 38,429 1.849 38,792 6.07 44,274 6.07 53,733 6.07 66,883 6.07 66,883
75 7.548 113,719 7.548 53,219 6.155 47,781 2.299 48,232 7.548 55,048 7.548 66,810 7.548 83,159 7.548 83,159
100 10.063 151,626 10.063 70,959 8.207 63,708 3.065 64,309 10.063 73,397 10.063 89,079 10.063 110,879 10.063 110,879
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 154 -
Table C.3 Deemed Energy and Demand Savings Values for Inlet Guide Vane Part-Load Fan Control (Houston Weather)
HP Hosptial &
Healthcare Office-Large Office Small Education - K-12
Education - College and
University Retail
Restaurant - Fast
Food
Restaurant - Sit
Down
kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh kW kWh
1 0.019 350 0.019 161 0.016 145 0.006 147 0.019 167 0.019 202 0.019 253 0.019 253
2 0.038 687 0.038 316 0.031 284 0.011 289 0.038 327 0.038 398 0.038 497 0.038 497
3 0.055 1,001 0.055 461 0.045 414 0.017 420 0.055 476 0.055 579 0.055 725 0.055 725
5 0.09 1,649 0.09 759 0.074 681 0.027 693 0.09 785 0.09 954 0.09 1,194 0.09 1,194
7.5 0.134 2,445 0.134 1,126 0.11 1,011 0.041 1,027 0.134 1,164 0.134 1,415 0.134 1,770 0.134 1,770
10 0.177 3,224 0.177 1,485 0.145 1,332 0.054 1,354 0.177 1,535 0.177 1,866 0.177 2,334 0.177 2,334
15 0.261 4,756 0.261 2,190 0.214 1,966 0.079 1,998 0.261 2,264 0.261 2,752 0.261 3,443 0.261 3,443
20 0.348 6,342 0.348 2,920 0.285 2,621 0.106 2,664 0.348 3,019 0.348 3,670 0.348 4,591 0.348 4,591
25 0.431 7,867 0.431 3,623 0.354 3,251 0.131 3,304 0.431 3,745 0.431 4,552 0.431 5,695 0.431 5,695
30 0.513 9,368 0.513 4,314 0.422 3,872 0.156 3,935 0.513 4,460 0.513 5,422 0.513 6,782 0.513 6,782
40 0.68 12,410 0.68 5,715 0.559 5,129 0.207 5,213 0.68 5,908 0.68 7,182 0.68 8,985 0.68 8,985
50 0.85 15,513 0.85 7,144 0.698 6,411 0.258 6,516 0.85 7,385 0.85 8,978 0.85 11,231 0.85 11,231
60 1.014 18,496 1.014 8,518 0.833 7,644 0.308 7,769 1.014 8,806 1.014 10,704 1.014 13,391 1.014 13,391
75 1.26 22,998 1.26 10,591 1.035 9,504 0.383 9,660 1.26 10,949 1.26 13,309 1.26 16,650 1.26 16,650
100 1.68 30,664 1.68 14,121 1.38 12,672 0.511 12,880 1.68 14,598 1.68 17,745 1.68 22,200 1.68 22,200
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix Section 3. - 155 -
D. Central Wattage Table
D.1 Overview
The Central Wattage Table contains reference data for estimating demand and energy savings in the C&I
Standard Offer Program for lighting measures. The Table assigns identification codes and demand values
(watts) to common fixture types (fluorescent, incandescent, HID, LED, etc.) used in commercial
applications. The Table wattage values for each fixture type are averages of various manufacturers’
laboratory tests performed to ANSI test standards. By using standardized demand values for each fixture
type, the Table simplifies the accounting procedures for lighting equipment retrofits.
CenterPoint Energy posts updated versions of the Table on the program Web site at
https://centerpoint.anbetrack.com/ as new fixtures are added. Project Sponsors should make sure that they
are working with the most recent version of the Table as they prepare Lighting Equipment Survey forms.
If a project uses a fixture type not listed in the Table, the Sponsor should request that CenterPoint Energy
add a new fixture code. The request should include all information required to uniquely identify the
fixture type and to fix its demand. If possible, the request should be supported by manufacturer’s ANSI
test data.
The Lighting Equipment Survey Form is linked to a copy of the Central Wattage Table and looks up
wattage values for fixture codes automatically. For this reason, Sponsors should use only the
identification codes included in the Table.
D.2 Table
The Table is subdivided into fixture types such as linear fluorescent, compact fluorescent, mercury vapor,
Light-emitting diode (LED) etc, with each subdivision sorted by fixture code. Each record, or row, in the
Table contains a fixture code, which serves as a unique identifier. Each record also includes a description
of the fixture, the number of lamps, the number of ballasts if applicable, and the fixture wattage. A legend
explains the rules behind the fixture codes.
The US Energy Policy Act of 1992 (EPACT) sets energy efficiency standards that preclude certain lamps
and ballasts from being manufactured or imported into the US. Under the C&I Standard Offer Program,
all lighting equipment, including existing or baseline equipment, must be EPACT compliant. As a result,
certain lamp/ballast combinations, which are non-EPACT compliant, are assigned EPACT demand
values. Thus, a 4-foot fixture with 40-watt T-12 lamps and standard magnetic ballast has the same
demand value as a like fixture equipped with 34-watt T-12 lamps and energy efficient magnetic ballast.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 156 -
Table D.1: Central wattage table
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
CMH-100W-HIDLF HID
Ceramic Metal Halide Standard 100 1 1 109 109
CMH-100W-SCWA HID
Ceramic Metal Halide Standard 100 1 1 125 125
CMH-140W-HIDLF N HID
Ceramic Metal Halide Standard 140 1 1
(0.85 < BF < 0.95) 154 154
CMH-150W-HIDLF HID
Ceramic Metal Halide Standard 150 1 1 166 166
CMH-150W-SCWA HID
Ceramic Metal Halide Standard 150 1 1 189 189
CMH-200W-HIDLF H HID
Ceramic Metal Halide Standard 200 1 1
(0.95 < BF < 1.10) 214 214
CMH-20W-HIDLF HID
Ceramic Metal Halide Standard 20 1 1 26 26
CMH-250W-HIDLF H HID
Ceramic Metal Halide Standard 250 1 1
(0.95 < BF < 1.10) 266 266
CMH-250W-LR HID
Ceramic Metal Halide Standard 250 1 1 272 272
CMH-250W-SCWA HID
Ceramic Metal Halide Standard 250 1 1 288 288
CMH-300W-LR HID
Ceramic Metal Halide Standard 300 1 1 324 324
CMH-300W-SCWA HID
Ceramic Metal Halide Standard 300 1 1 342 342
CMH-320W-HIDLF H HID
Ceramic Metal Halide Standard 320 1 1
(0.95 < BF < 1.10) 341 341
CMH-320W-LR HID
Ceramic Metal Halide Standard 320 1 1 342 342
CMH-320W-SCWA HID
Ceramic Metal Halide Standard 320 1 1 370 370
CMH-350W-HIDLF H HID
Ceramic Metal Halide Standard 350 1 1
(0.95 < BF < 1.10) 372 372
CMH-39W-HIDLF HID
Ceramic Metal Halide Standard 39 1 1 45 45
CMH-39W-SCWA HID
Ceramic Metal Halide Standard 39 1 1 45 45
CMH-400W-HIDLF H HID Ceramic Metal Standard 400 1 1 (0.95 < BF < 426 426
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 157 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
Halide 1.10)
CMH-400W-LR HID
Ceramic Metal Halide Standard 400 1 1 425 425
CMH-400W-SCWA HID
Ceramic Metal Halide Standard 400 1 1 455 455
CMH-50W-HIDLF H HID
Ceramic Metal Halide Standard 50 1 1
(0.95 < BF < 1.10) 56 56
CMH-50W-SCWA HID
Ceramic Metal Halide Standard 50 1 1 68 68
CMH-60W-HIDLF N HID
Ceramic Metal Halide Standard 60 1 1
(0.85 < BF < 0.95) 67 67
CMH-70W-HIDLF HID
Ceramic Metal Halide Standard 70 1 1 79 79
CMH-70W-SCWA HID
Ceramic Metal Halide Standard 70 1 1 90 90
CMH-90W-HIDLF N HID
Ceramic Metal Halide Standard 90 1 1
(0.85 < BF < 0.95) 99 99
FCCFL-13W Fluorescent Cold Cathode Integral Screw-In 13 1 13 13
FCCFL-18W Fluorescent Cold Cathode Integral Screw-In 18 1 18 18
FCCFL-3W Fluorescent Cold Cathode Integral Screw-In 3 1 3 3
FCCFL-5W Fluorescent Cold Cathode Integral Screw-In 5 1 5 5
FCCFL-8W Fluorescent Cold Cathode Integral Screw-In 8 1 8 8
FCE-5W x 2L-MG Fluorescent Compact Exit 5 2 1 20 20
FCE-5W-MG Fluorescent Compact Exit 5 1 1 9 9
FCE-6W x 2L-MG Fluorescent Compact Exit 6 2 1 26 26
FCE-6W-MG Fluorescent Compact Exit 6 1 1 13 13
FCE-7W x 2L-MG Fluorescent Compact Exit 7 2 1 21 21
FCE-7W-MG Fluorescent Compact Exit 7 1 1 10 10
FCE-9W x 2L-MG Fluorescent Compact Exit 9 2 1 20 20
FCE-9W-MG Fluorescent Compact Exit 9 1 1 12 12
FCGU24-11W-IS H Fluorescent Compact GU24 11 1 1
(0.95 < BF < 1.10) 11 11
FCGU24-13W-IS H Fluorescent Compact GU24 13 1 1
(0.95 < BF < 1.10) 13 13
FCGU24-14W-IS H Fluorescent Compact GU24 14 1 1
(0.95 < BF < 1.10) 14 14
FCGU24-15W-IS H Fluorescent Compact GU24 15 1 1
(0.95 < BF < 1.10) 15 15
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 158 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FCGU24-18W-IS H Fluorescent Compact GU24 18 1 1
(0.95 < BF < 1.10) 18 18
FCGU24-19W-IS H Fluorescent Compact GU24 19 1 1
(0.95 < BF < 1.10) 19 19
FCGU24-20W-IS H Fluorescent Compact GU24 20 1 1
(0.95 < BF < 1.10) 20 20
FCGU24-23W-IS H Fluorescent Compact GU24 23 1 1
(0.95 < BF < 1.10) 23 23
FCGU24-25W-IS H Fluorescent Compact GU24 25 1 1
(0.95 < BF < 1.10) 25 25
FCGU24-26W-IS H Fluorescent Compact GU24 26 1 1
(0.95 < BF < 1.10) 26 26
FCGU24-27W-IS H Fluorescent Compact GU24 27 1 1
(0.95 < BF < 1.10) 27 27
FCGU24-32W-IS H Fluorescent Compact GU24 32 1 1
(0.95 < BF < 1.10) 32 32
FCGU24-7W-IS H Fluorescent Compact GU24 7 1 1
(0.95 < BF < 1.10) 7 7
FCGU24-9W-IS H Fluorescent Compact GU24 9 1 1
(0.95 < BF < 1.10) 9 9
FCIT9-20W-MG Fluorescent Circline T9 20 1 1 25 25
FCIT9-20W-MGPH Fluorescent Circline T9 20 1 1 20 20
FCIT9-22W x 2L-MG Fluorescent Circline T9 22 2 1 52 52
FCIT9-22W-MG Fluorescent Circline T9 22 1 1 26 26
FCIT9-22W-MGPH Fluorescent Circline T9 22 1 1 20 20
FCIT9-32W x 2L-MG Fluorescent Circline T9 32 2 1 62 62
FCIT9-32W-MG Fluorescent Circline T9 32 1 1 31 31
FCIT9-32W-MGPH Fluorescent Circline T9 32 1 1 40 40
FCIT9-40W-MG Fluorescent Circline T9 40 1 1 35 35
FCIT9-40W-MGPH Fluorescent Circline T9 40 1 1 42 42
FCM-10W-MG Fluorescent Compact Medium Base 10 1 1 10 10
FCM-11W-MG Fluorescent Compact Medium Base 11 1 1 11 11
FCM-12W-MG Fluorescent Compact Medium Base 12 1 1 12 12
FCM-13W-MG Fluorescent Compact Medium Base 13 1 1 13 13
FCM-14W-MG Fluorescent Compact Medium Base 14 1 1 14 14
FCM-15W x 2L-MG Fluorescent Compact Medium Base 15 2 1 30 30
FCM-15W x 3L-MG Fluorescent Compact Medium Base 15 3 1 45 45
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 159 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FCM-15W x 4L-MG Fluorescent Compact Medium Base 15 4 1 60 60
FCM-15W-MG Fluorescent Compact Medium Base 15 1 1 15 15
FCM-16W-MG Fluorescent Compact Medium Base 16 1 1 16 16
FCM-17W-MG Fluorescent Compact Medium Base 17 1 1 17 17
FCM-18W-IS N Fluorescent Compact Medium Base 18 1 1
(0.85 < BF < 0.95) 18 18
FCM-18W-MG Fluorescent Compact Medium Base 18 1 1 18 18
FCM-19W-MG Fluorescent Compact Medium Base 19 1 1 19 19
FCM-20W x 2L-MG Fluorescent Compact Medium Base 20 2 1 40 40
FCM-20W-MG Fluorescent Compact Medium Base 20 1 1 20 20
FCM-22W-MG Fluorescent Compact Medium Base 22 1 1 22 22
FCM-23W x 2L-MG Fluorescent Compact Medium Base 23 2 1 46 46
FCM-23W-IS N Fluorescent Compact Medium Base 23 1 1
(0.85 < BF < 0.95) 23 23
FCM-23W-MG Fluorescent Compact Medium Base 23 1 1 23 23
FCM-25W-MG Fluorescent Compact Medium Base 25 1 1 25 25
FCM-26W-IS N Fluorescent Compact Medium Base 26 1 1
(0.85 < BF < 0.95) 26 26
FCM-26W-MG Fluorescent Compact Medium Base 26 1 1 26 26
FCM-27W-IS N Fluorescent Compact Medium Base 27 1 1
(0.85 < BF < 0.95) 27 27
FCM-28W-MG Fluorescent Compact Medium Base 28 1 1 28 28
FCM-2W-MG Fluorescent Compact Medium Base 2 1 1 2 2
FCM-30W-IS N Fluorescent Compact Medium Base 30 1 1
(0.85 < BF < 0.95) 30 30
FCM-36W-IS N Fluorescent Compact Medium Base 36 1 1
(0.85 < BF < 0.95) 36 36
FCM-42W-IS N Fluorescent Compact Medium Base 42 1 1
(0.85 < BF < 0.95) 42 42
FCM-44W-IS N Fluorescent Compact Medium Base 44 1 1
(0.85 < BF < 0.95) 44 44
FCM-5W-MG Fluorescent Compact Medium Base 5 1 1 5 5
FCM-7W-MG Fluorescent Compact Medium Base 7 1 1 7 7
FCM-9W-MG Fluorescent Compact Medium Base 9 1 1 9 9
FCP-10W-MG Fluorescent Compact Pin-Based 10 1 1 15 15
FCP-12W-MG Fluorescent Compact Pin-Based 12 1 1 16 16
FCP-13W x 2L-IS H Fluorescent Compact Pin-Based 13 2 1 (0.95 < BF < 28 28
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 160 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
1.10)
FCP-13W x 2L-IS N Fluorescent Compact
Pin-Based 13 2 1
(0.85 < BF < 0.95) 30 30
FCP-13W x 2L-MG Fluorescent Compact Pin-Based 13 2 1 31 31
FCP-13W x 3L-MG Fluorescent Compact Pin-Based 13 3 1 48 48
FCP-13W-IS H Fluorescent Compact
Pin-Based 13 1 1
(0.95 < BF < 1.10) 15 15
FCP-13W-IS N Fluorescent Compact
Pin-Based 13 1 1
(0.85 < BF < 0.95) 16 16
FCP-13W-MG Fluorescent Compact Pin-Based 13 1 1 17 17
FCP-14W-MG Fluorescent Compact Pin-Based 14 1 1 18 18
FCP-15W-MG Fluorescent Compact Pin-Based 15 1 1 19 19
FCP-16W-MG Fluorescent Compact Pin-Based 16 1 1 26 26
FCP-17W x 2L-MG Fluorescent Compact Pin-Based 17 2 1 48 48
FCP-17W-MG Fluorescent Compact Pin-Based 17 1 1 21 21
FCP-18W x 2L-IS H Fluorescent Compact
Pin-Based 18 2 1
(0.95 < BF < 1.10) 38 38
FCP-18W x 2L-IS N Fluorescent Compact
Pin-Based 18 2 1
(0.85 < BF < 0.95) 38 38
FCP-18W x 2L-MG Fluorescent Compact Pin-Based 18 2 1 45 45
FCP-18W x 4L-MG Fluorescent Compact Pin-Based 18 4 1 90 90
FCP-18W-IS H Fluorescent Compact
Pin-Based 18 1 1
(0.95 < BF < 1.10) 20 20
FCP-18W-IS N Fluorescent Compact
Pin-Based 18 1 1
(0.85 < BF < 0.95) 20 20
FCP-18W-MG Fluorescent Compact Pin-Based 18 1 1 26 26
FCP-19W-MG Fluorescent Compact Pin-Based 19 1 1 24 24
FCP-20W x 2L-MG Fluorescent Compact Pin-Based 20 2 1 46 46
FCP-20W-MG Fluorescent Compact Pin-Based 20 1 1 25 25
FCP-21W-MG Fluorescent Compact Pin-Based 21 1 1 26 26
FCP-22W x 2L-MG Fluorescent Compact Pin-Based 22 2 1 48 48
FCP-22W x 3L-MG Fluorescent Compact Pin-Based 22 3 1 72 72
FCP-22W x 4L-MG Fluorescent Compact Pin-Based 22 4 1 108 108
FCP-22W-MG Fluorescent Compact Pin-Based 22 1 1 26 26
FCP-23W-MG Fluorescent Compact Pin-Based 23 1 1 27 27
FCP-24W-MG Fluorescent Compact Pin-Based 24 1 1 32 32
FCP-25W x 2L-MG Fluorescent Compact Pin-Based 25 2 1 66 66
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 161 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FCP-25W-MG Fluorescent Compact Pin-Based 25 1 1 29 29
FCP-26W x 2L-IS H Fluorescent Compact
Pin-Based 26 2 1
(0.95 < BF < 1.10) 50 50
FCP-26W x 2L-IS N Fluorescent Compact
Pin-Based 26 2 1
(0.85 < BF < 0.95) 54 54
FCP-26W x 2L-MG Fluorescent Compact Pin-Based 26 2 1 66 66
FCP-26W x 3L-MG Fluorescent Compact Pin-Based 26 3 1 99 99
FCP-26W x 6L-IS H Fluorescent Compact
Pin-Based 26 6 1
(0.95 < BF < 1.10) 150 150
FCP-26W-IS H Fluorescent Compact
Pin-Based 26 1 1
(0.95 < BF < 1.10) 27 27
FCP-26W-IS N Fluorescent Compact
Pin-Based 26 1 1
(0.85 < BF < 0.95) 28 28
FCP-26W-MG Fluorescent Compact Pin-Based 26 1 1 30 30
FCP-27W-MG Fluorescent Compact Pin-Based 27 1 1 31 31
FCP-28W x 2L-IS N Fluorescent Compact
Pin-Based 28 2 1
(0.85 < BF < 0.95) 60 60
FCP-28W x 2L-MG Fluorescent Compact Pin-Based 28 2 1 66 66
FCP-28W-IS N Fluorescent Compact
Pin-Based 28 1 1
(0.85 < BF < 0.95) 31 31
FCP-28W-MG Fluorescent Compact Pin-Based 28 1 1 35 35
FCP-2W-MG Fluorescent Compact Pin-Based 2 1 1 6 6
FCP-30W-MG Fluorescent Compact Pin-Based 30 1 1 34 34
FCP-32W x 2L-IS N Fluorescent Compact
Pin-Based 32 2 1
(0.85 < BF < 0.95) 69 69
FCP-32W x 6L-IS N Fluorescent Compact
Pin-Based 32 6 1
(0.85 < BF < 0.95) 186 186
FCP-32W-IS N Fluorescent Compact
Pin-Based 32 1 1
(0.85 < BF < 0.95) 35 35
FCP-36W-MG Fluorescent Compact Pin-Based 36 1 1 40 40
FCP-38W-MG Fluorescent Compact Pin-Based 38 1 1 46 46
FCP-40W x 2L-IS N Fluorescent Compact
Pin-Based 40 2 1
(0.85 < BF < 0.95) 72 72
FCP-40W x 2L-MG Fluorescent Compact Pin-Based 40 2 1 85 85
FCP-40W x 3L-IS N Fluorescent Compact
Pin-Based 40 3 1
(0.85 < BF < 0.95) 105 105
FCP-40W x 3L-MG Fluorescent Compact Pin-Based 40 3 1 133 133
FCP-40W-IS N Fluorescent Compact Pin-Based 40 1 1 (0.85 < BF < 43 43
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 162 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.95)
FCP-40W-MG Fluorescent Compact Pin-Based 40 1 1 46 46
FCP-42W x 2L-IS N Fluorescent Compact
Pin-Based 42 2 1
(0.85 < BF < 0.95) 94 94
FCP-42W x 8L-IS N Fluorescent Compact
Pin-Based 42 8 1
(0.85 < BF < 0.95) 314 314
FCP-42W-IS N Fluorescent Compact
Pin-Based 42 1 1
(0.85 < BF < 0.95) 45 45
FCP-42W-MG Fluorescent Compact Pin-Based 42 1 1 46 46
FCP-55W x 2L-IS N Fluorescent Compact
Pin-Based 55 2 1
(0.85 < BF < 0.95) 110 110
FCP-55W x 3L-IS N Fluorescent Compact
Pin-Based 55 3 1
(0.85 < BF < 0.95) 170 170
FCP-55W x 4L-IS N Fluorescent Compact
Pin-Based 55 4 1
(0.85 < BF < 0.95) 220 220
FCP-55W-IS N Fluorescent Compact
Pin-Based 55 1 1
(0.85 < BF < 0.95) 60 60
FCP-5W x 2L-MG Fluorescent Compact Pin-Based 5 2 1 18 18
FCP-5W-MG Fluorescent Compact Pin-Based 5 1 1 9 9
FCP-7W x 2L-MG Fluorescent Compact Pin-Based 7 2 1 21 21
FCP-7W-MG Fluorescent Compact Pin-Based 7 1 1 11 11
FCP-9W x 2L-MG Fluorescent Compact Pin-Based 9 2 1 23 23
FCP-9W x 3L-MG Fluorescent Compact Pin-Based 9 3 1 34 34
FCP-9W-MG Fluorescent Compact Pin-Based 9 1 1 12 12
FLE-2W x 2L-IS N Fluorescent Linear Exit 2 2 1
(0.85 < BF < 0.95) 5 5
FLE-6W x 2L-MG Fluorescent Linear Exit 6 2 1 18 18
FLE-6W-MG Fluorescent Linear Exit 6 1 1 9 9
FLE-8W x 2L-MG Fluorescent Linear Exit 8 2 1 24 24
FLE-8W-MG Fluorescent Linear Exit 8 1 1 12 12
FLT10-40W x 4L x 4'-2 MG Fluorescent Linear T10 40 4 4 2 45 45
FLT10-40W x 4'-MG Fluorescent Linear T10 40 1 4 1 51 51
FLT12-15W x 1.5'-MG Fluorescent Linear T12 15 1 1.5 1 19 19
FLT12-15W x 2L x 1.5'-MG Fluorescent Linear T12 15 2 1.5 1 36 36
FLT12-20W x 2L x 2'-MG Fluorescent Linear T12 20 2 2 1 50 50
FLT12-20W x 2'-MG Fluorescent Linear T12 20 1 2 1 25 25
FLT12-20W x 3L x 2'-MG Fluorescent Linear T12 20 3 2 1 62 62
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 163 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12-20W x 4L x 2'-MG Fluorescent Linear T12 20 4 2 1 100 100
FLT12-20W x 6L x 2'-MG Fluorescent Linear T12 20 6 2 1 146 146
FLT12-25W x 2L x 3'-IS N Fluorescent Linear T12 25 2 3 1
(0.85 < BF < 0.95) 50 50
FLT12-25W x 2L x 3'-IS N T4 Fluorescent Linear T12 25 2 3 1
(0.85 < BF < 0.95) 50 50
FLT12-25W x 2L x 3'-MG Fluorescent Linear T12 25 2 3 1 73 73
FLT12-25W x 2L x 3'-MG(E) Fluorescent Linear T12 25 2 3 1 66 66
FLT12-25W x 2L x 4'-IS R Fluorescent Linear
T12 25 2 4 1 (0.75 < BF <
0.85) 39 39
FLT12-25W x 2L x 4'-IS R T4 Fluorescent Linear
T12 25 2 4 1 (0.75 < BF <
0.85) 40 40
FLT12-25W x 3'-IS N Fluorescent Linear
T12 25 1 3 1 (0.85 < BF <
0.95) 26 26
FLT12-25W x 3L x 3'-MG Fluorescent Linear T12 25 3 3 1 115 115
FLT12-25W x 3'-MG Fluorescent Linear T12 25 1 3 1 42 42
FLT12-25W x 3'-MG T2 Fluorescent Linear T12 25 1 3 1 33 33
FLT12-25W x 3'-MG(E) T2 Fluorescent Linear T12 25 1 3 1 33 33
FLT12-25W x 4'-IS N Fluorescent Linear
T12 25 1 4 1 (0.85 < BF <
0.95) 25 25
FLT12-25W x 4'-IS R T2 Fluorescent Linear
T12 25 1 4 1 (0.75 < BF <
0.85) 19 19
FLT12-25W x 4'-IS R T3 Fluorescent Linear
T12 25 1 4 1 (0.75 < BF <
0.85) 20 20
FLT12-25W x 4'-IS R T4 Fluorescent Linear
T12 25 1 4 1 (0.75 < BF <
0.85) 20 20
FLT12-25W x 4L x 3'-MG(E) Fluorescent Linear T12 25 4 3 1 132 132
FLT12-30W x 2L x 3'-IS N Fluorescent Linear T12 30 2 3 1
(0.85 < BF < 0.95) 58 58
FLT12-30W x 2L x 3'-MG Fluorescent Linear T12 30 2 3 1 75 75
FLT12-30W x 2L x 3'-MG(E) Fluorescent Linear T12 30 2 3 1 74 74
FLT12-30W x 2L x 4'-MG Fluorescent Linear T12 30 2 4 1 82 82
FLT12-30W x 3'-IS N Fluorescent Linear
T12 30 1 3 1 (0.85 < BF <
0.95) 31 31
FLT12-30W x 3L x 3'-MG Fluorescent Linear T12 30 3 3 1 127 127
FLT12-30W x 3L x 3'-MG(E) Fluorescent Linear T12 30 3 3 1 120 120
FLT12-30W x 3L x 4'-2 MG Fluorescent Linear T12 30 3 4 2 133 133
FLT12-30W x 3L x 4'-MG Fluorescent Linear T12 30 3 4 1 133 133
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 164 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12-30W x 3'-MG Fluorescent Linear T12 30 1 3 1 46 46
FLT12-30W x 3'-MG T2 Fluorescent Linear T12 30 1 3 1 41 41
FLT12-30W x 3'-MG(E) T2 Fluorescent Linear T12 30 1 3 1 37 37
FLT12-30W x 4L x 3'-2 IS N Fluorescent Linear
T12 30 4 3 2 (0.85 < BF <
0.95) 116 116
FLT12-30W x 4L x 3'-MG Fluorescent Linear T12 30 4 3 1 150 150
FLT12-30W x 4L x 3'-MG(E) Fluorescent Linear T12 30 4 3 1 148 148
FLT12-30W x 4L x 4'-2 MG Fluorescent Linear T12 30 4 4 2 164 164
FLT12-30W x 4'-MG Fluorescent Linear T12 30 1 4 1 51 51
FLT12-30W x 6L x 3'-MG Fluorescent Linear T12 30 6 3 1 219 219
FLT12-30W x 6L x 3'-MG(E) Fluorescent Linear T12 30 6 3 1 198 198
FLT12-34W x 2L x 4'-2 MG(E) Fluorescent Linear T12 34 2 4 2 86 86
FLT12-34W x 2L x 4'-IS N Fluorescent Linear
T12 34 2 4 1 (0.85 < BF <
0.95) 60 72
FLT12-34W x 2L x 4'-MG Fluorescent Linear T12 34 2 4 1 72 82
FLT12-34W x 2L x 4'-MG(E) Fluorescent Linear T12 34 2 4 1 72 72
FLT12-34W x 3L x 4'-2 MG Fluorescent Linear T12 34 3 4 2 115 115
FLT12-34W x 3L x 4'-2 MG(E) Fluorescent Linear T12 34 3 4 2 115 115
FLT12-34W x 3L x 4'-IS N Fluorescent Linear
T12 34 3 4 1 (0.85 < BF <
0.95) 92 92
FLT12-34W x 3L x 4'-MG Fluorescent Linear T12 34 3 4 1 115 130
FLT12-34W x 3L x 4'-MG T2 Fluorescent Linear T12 34 3 4 1 108 123
FLT12-34W x 3L x 4'-MG(E) Fluorescent Linear T12 34 3 4 1 115 115
FLT12-34W x 3L x 4'-MG(E) T2 Fluorescent Linear T12 34 3 4 1 108 108
FLT12-34W x 4'-IS N Fluorescent Linear
T12 34 1 4 1 (0.85 < BF <
0.95) 32 32
FLT12-34W x 4L x 4'-2 MG Fluorescent Linear T12 34 4 4 2 144 164
FLT12-34W x 4L x 4'-2 MG(E) Fluorescent Linear T12 34 4 4 2 144 144
FLT12-34W x 4L x 4'-IS N Fluorescent Linear
T12 34 4 4 1 (0.85 < BF <
0.95) 120 120
FLT12-34W x 4'-MG Fluorescent Linear T12 34 1 4 1 48 48
FLT12-34W x 4'-MG(E) Fluorescent Linear T12 34 1 4 1 43 43
FLT12-34W x 4'-MG(E) T2 Fluorescent Linear T12 34 1 4 1 36 36
FLT12-34W x 6L x 4'-2 IS N Fluorescent Linear
T12 34 6 4 2 (0.85 < BF <
0.95) 186 186
FLT12-34W x 6L x 4'-MG Fluorescent Linear T12 34 6 4 1 216 234
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 165 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12-34W x 6L x 4'-MG(E) Fluorescent Linear T12 34 6 4 1 216 216
FLT12-34W x 8L x 4'-MG Fluorescent Linear T12 34 8 4 1 288 328
FLT12-34W x 8L x 4'-MG(E) Fluorescent Linear T12 34 8 4 1 288 288
FLT12-39W x 2L x 4'-IS N Fluorescent Linear
T12 39 2 4 1 (0.85 < BF <
0.95) 74 74
FLT12-39W x 2L x 4'-MG Fluorescent Linear T12 39 2 4 1 103 103
FLT12-39W x 3L x 4'-IS N Fluorescent Linear
T12 39 3 4 1 (0.85 < BF <
0.95) 120 120
FLT12-39W x 4'-IS N Fluorescent Linear T12 39 1 4 1
(0.85 < BF < 0.95) 46 46
FLT12-39W x 4'-IS N T2 Fluorescent Linear T12 39 1 4 1
(0.85 < BF < 0.95) 37 37
FLT12-39W x 4L x 4'-IS N Fluorescent Linear T12 39 4 4 1
(0.85 < BF < 0.95) 148 148
FLT12-39W x 4'-MG Fluorescent Linear T12 39 1 4 1 60 60
FLT12-39W x 4'-MG T2 Fluorescent Linear T12 39 1 4 1 52 52
FLT12-40W x 2L x 4'-MG Fluorescent Linear T12 40 2 4 1 72 96
FLT12-40W x 2L x 4'-MG(E) Fluorescent Linear T12 40 2 4 1 72 86
FLT12-40W x 3L x 4'-2 MG Fluorescent Linear T12 40 3 4 2 115 115
FLT12-40W x 3L x 4'-2 MG(E) Fluorescent Linear T12 40 3 4 2 115 115
FLT12-40W x 3L x 4'-MG Fluorescent Linear T12 40 3 4 1 115 151
FLT12-40W x 3L x 4'-MG(E) Fluorescent Linear T12 40 3 4 1 115 140
FLT12-40W x 4L x 4'-2 MG Fluorescent Linear T12 40 4 4 2 144 192
FLT12-40W x 4L x 4'-2 MG(E) Fluorescent Linear T12 40 4 4 2 144 172
FLT12-40W x 4'-MG Fluorescent Linear T12 40 1 4 1 43 55
FLT12-40W x 4'-MG T2 Fluorescent Linear T12 40 1 4 1 43 48
FLT12-40W x 4'-MG(E) Fluorescent Linear T12 40 1 4 1 43 50
FLT12-40W x 4'-MG(E) T2 Fluorescent Linear T12 40 1 4 1 36 43
FLT12-40W x 6L x 4'-2 IS N Fluorescent Linear
T12 40 6 4 2 (0.85 < BF <
0.95) 186 186
FLT12-40W x 6L x 4'-MG Fluorescent Linear T12 40 6 4 1 276 216
FLT12-40W x 6L x 4'-MG(E) Fluorescent Linear T12 40 6 4 1 258 216
FLT12-40W x 8L x 4'-MG Fluorescent Linear T12 40 8 4 1 288 384
FLT12-40W x 8L x 4'-MG(E) Fluorescent Linear T12 40 8 4 1 288 344
FLT12-50W x 2L x 5'-IS N Fluorescent Linear
T12 50 2 5 1 (0.85 < BF <
0.95) 88 88
FLT12-50W x 2L x 5'-MG Fluorescent Linear T12 50 2 5 1 128 128
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 166 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12-50W x 5'-IS N Fluorescent Linear
T12 50 1 5 1 (0.85 < BF <
0.95) 44 44
FLT12-50W x 5'-MG Fluorescent Linear T12 50 1 5 1 63 63
FLT12-55W x 2L x 6'-IS N Fluorescent Linear T12 55 2 6 1
(0.85 < BF < 0.95) 108 108
FLT12-55W x 2L x 6'-MG Fluorescent Linear T12 55 2 6 1 142 142
FLT12-55W x 2L x 6'-MG(E) Fluorescent Linear T12 55 2 6 1 122 122
FLT12-55W x 2L x 6'-RS/PRS N Fluorescent Linear
T12 55 2 6 1 (0.85 < BF <
0.95) 108 108
FLT12-55W x 3L x 6'-IS N Fluorescent Linear
T12 55 3 6 1 (0.85 < BF <
0.95) 176 176
FLT12-55W x 3L x 6'-MG Fluorescent Linear T12 55 3 6 1 202 202
FLT12-55W x 4L x 6'-IS N Fluorescent Linear
T12 55 4 6 1 (0.85 < BF <
0.95) 216 216
FLT12-55W x 4L x 6'-MG(E) Fluorescent Linear T12 55 4 6 1 244 244
FLT12-55W x 6'-IS N Fluorescent Linear T12 55 1 6 1
(0.85 < BF < 0.95) 68 68
FLT12-55W x 6'-MG Fluorescent Linear T12 55 1 6 1 76 76
FLT12-56W x 4L x 6'-MG Fluorescent Linear T12 56 4 6 1 244 244
FLT12-60W x 2L x 8'-IS N Fluorescent Linear
T12 60 2 8 1 (0.85 < BF <
0.95) 110 110
FLT12-60W x 2L x 8'-MG Fluorescent Linear T12 60 2 8 1 123 128
FLT12-60W x 2L x 8'-MG(E) Fluorescent Linear T12 60 2 8 1 123 123
FLT12-60W x 3L x 8'-IS N Fluorescent Linear
T12 60 3 8 1 (0.85 < BF <
0.95) 179 179
FLT12-60W x 3L x 8'-MG Fluorescent Linear T12 60 3 8 1 198 203
FLT12-60W x 3L x 8'-MG(E) Fluorescent Linear T12 60 3 8 1 198 198
FLT12-60W x 4L x 8'-2 IS N Fluorescent Linear
T12 60 4 8 2 (0.85 < BF <
0.95) 220 220
FLT12-60W x 4L x 8'-MG Fluorescent Linear T12 60 4 8 1 246 264
FLT12-60W x 4L x 8'-MG(E) Fluorescent Linear T12 60 4 8 1 246 246
FLT12-60W x 6L x 8'-MG(E) Fluorescent Linear T12 60 6 8 1 369 369
FLT12-60W x 8'-IS N Fluorescent Linear
T12 60 1 8 1 (0.85 < BF <
0.95) 69 69
FLT12-60W x 8'-IS N T2 Fluorescent Linear T12 60 1 8 1
(0.85 < BF < 0.95) 55 55
FLT12-60W x 8'-MG Fluorescent Linear T12 60 1 8 1 75 83
FLT12-60W x 8'-MG T2 Fluorescent Linear T12 60 1 8 1 62 64
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 167 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12-60W x 8'-MG(E) Fluorescent Linear T12 60 1 8 1 75 75
FLT12-60W x 8'-MG(E) T2 Fluorescent Linear T12 60 1 8 1 62 62
FLT12-75W x 2L x 8'-IS N Fluorescent Linear
T12 75 2 8 1 (0.85 < BF <
0.95) 110 110
FLT12-75W x 2L x 8'-MG Fluorescent Linear T12 75 2 8 1 123 172
FLT12-75W x 2L x 8'-MG(E) Fluorescent Linear T12 75 2 8 1 123 158
FLT12-75W x 3L x 8'-2 IS N Fluorescent Linear T12 75 3 8 2
(0.85 < BF < 0.95) 179 179
FLT12-75W x 3L x 8'-MG(E) Fluorescent Linear T12 75 3 8 1 198 264
FLT12-75W x 4L x 8'-2 IS N Fluorescent Linear T12 75 4 8 2
(0.85 < BF < 0.95) 220 220
FLT12-75W x 4L x 8'-MG(E) Fluorescent Linear T12 75 4 8 1 246 316
FLT12-75W x 6L x 8'-MG Fluorescent Linear T12 75 6 8 1 328 540
FLT12-75W x 6L x 8'-MG(E) Fluorescent Linear T12 75 6 8 1 328 474
FLT12-75W x 8'-IS N Fluorescent Linear
T12 75 1 8 1 (0.85 < BF <
0.95) 69 69
FLT12-75W x 8'-IS N T2 Fluorescent Linear T12 75 1 8 1
(0.85 < BF < 0.95) 55 55
FLT12-75W x 8'-MG Fluorescent Linear T12 75 1 8 1 75 90
FLT12-75W x 8'-MG T2 Fluorescent Linear T12 75 1 8 1 62 79
FLT12-75W x 8'-MG(E) Fluorescent Linear T12 75 1 8 1 75 98
FLT12-75W x 8'-MG(E) T2 Fluorescent Linear T12 75 1 8 1 62 90
FLT12HO-110W x 2L x 8'-IS N Fluorescent Linear
T12 HO 110 2 8 1 (0.85 < BF <
0.95) 173 173
FLT12HO-110W x 2L x 8'-MG Fluorescent Linear T12 HO 110 2 8 1 207 257
FLT12HO-110W x 2L x 8'-MG(E) Fluorescent Linear T12 HO 110 2 8 1 227 227
FLT12HO-110W x 3L x 8'-MG Fluorescent Linear T12 HO 110 3 8 1 319 410
FLT12HO-110W x 3L x 8'-MG(E) Fluorescent Linear T12 HO 110 3 8 1 319 381
FLT12HO-110W x 4L x 8'-2 IS N Fluorescent Linear
T12 HO 110 4 8 2 (0.85 < BF <
0.95) 346 346
FLT12HO-110W x 4L x 8'-MG Fluorescent Linear T12 HO 110 4 8 1 414 514
FLT12HO-110W x 4L x 8'-MG(E) Fluorescent Linear T12 HO 110 4 8 1 414 474
FLT12HO-110W x 8L x 8'-MG Fluorescent Linear T12 HO 110 8 8 1 828 1028
FLT12HO-110W x 8'-MG Fluorescent Linear T12 HO 110 1 8 1 121 140
FLT12HO-35W x 2L x 2'-MG Fluorescent Linear T12 HO 35 2 2 1 90 90
FLT12HO-35W x 2'-MG Fluorescent Linear T12 HO 35 1 2 1 62 62
FLT12HO-50W x 2L x 3'-MG Fluorescent Linear T12 HO 50 2 3 1 114 114
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 168 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12HO-50W x 3'-MG Fluorescent Linear T12 HO 50 1 3 1 70 70
FLT12HO-55W x 2L x 4'-MG Fluorescent Linear T12 HO 55 2 4 1 135 135
FLT12HO-55W x 3L x 4'-MG Fluorescent Linear T12 HO 55 3 4 1 215 215
FLT12HO-55W x 4L x 4'-2 MG Fluorescent Linear T12 HO 55 4 4 2 270 270
FLT12HO-55W x 4'-MG Fluorescent Linear T12 HO 55 1 4 1 80 80
FLT12HO-60W x 2L x 4'-MG Fluorescent Linear T12 HO 60 2 4 1 145 145
FLT12HO-60W x 3L x 4'-MG Fluorescent Linear T12 HO 60 3 4 1 230 230
FLT12HO-60W x 4L x 4'-2 MG Fluorescent Linear T12 HO 60 4 4 2 290 290
FLT12HO-60W x 4'-MG Fluorescent Linear T12 HO 60 1 4 1 85 85
FLT12HO-75W x 2L x 5'-IS N Fluorescent Linear
T12 HO 75 2 5 1 (0.85 < BF <
0.95) 138 138
FLT12HO-75W x 2L x 5'-MG Fluorescent Linear T12 HO 75 2 5 1 168 168
FLT12HO-75W x 2L x 5'-MG(E) Fluorescent Linear T12 HO 75 2 5 1 176 176
FLT12HO-75W x 5'-IS N Fluorescent Linear T12 HO 75 1 5 1
(0.85 < BF < 0.95) 69 69
FLT12HO-75W x 5'-MG Fluorescent Linear T12 HO 75 1 5 1 92 92
FLT12HO-75W x 5'-MG(E) Fluorescent Linear T12 HO 75 1 5 1 88 88
FLT12HO-85W x 2L x 6'-IS N Fluorescent Linear
T12 HO 85 2 6 1 (0.85 < BF <
0.95) 167 167
FLT12HO-85W x 2L x 6'-MG Fluorescent Linear T12 HO 85 2 6 1 200 200
FLT12HO-85W x 2L x 6'-MG(E) Fluorescent Linear T12 HO 85 2 6 1 194 194
FLT12HO-85W x 4L x 6'-MG(E) Fluorescent Linear T12 HO 85 4 6 1 388 388
FLT12HO-85W x 6'-MG Fluorescent Linear T12 HO 85 1 6 1 106 106
FLT12HO-95W x 2L x 8'-IS N Fluorescent Linear
T12 HO 95 2 8 1 (0.85 < BF <
0.95) 173 173
FLT12HO-95W x 2L x 8'-MG Fluorescent Linear T12 HO 95 2 8 1 207 207
FLT12HO-95W x 2L x 8'-MG(E) Fluorescent Linear T12 HO 95 2 8 1 207 237
FLT12HO-95W x 3L x 8'-MG Fluorescent Linear T12 HO 95 3 8 1 319 380
FLT12HO-95W x 4L x 8'-2 IS N Fluorescent Linear
T12 HO 95 4 8 2 (0.85 < BF <
0.95) 346 346
FLT12HO-95W x 4L x 8'-MG Fluorescent Linear T12 HO 95 4 8 1 414 454
FLT12HO-95W x 4L x 8'-MG(E) Fluorescent Linear T12 HO 95 4 8 1 414 414
FLT12HO-95W x 6L x 8'-MG Fluorescent Linear T12 HO 95 6 8 1 519 721
FLT12HO-95W x 8'-IS N Fluorescent Linear
T12 HO 95 1 8 1 (0.85 < BF <
0.95) 80 80
FLT12HO-95W x 8L x 8'-MG(E) Fluorescent Linear T12 HO 95 8 8 1 828 828
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 169 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT12HO-95W x 8'-MG Fluorescent Linear T12 HO 95 1 8 1 106 106
FLT12VHO-110W x 2L x 4'-MG Fluorescent Linear T12 VHO 110 2 4 1 252 252
FLT12VHO-110W x 3L x 4'-MG Fluorescent Linear T12 VHO 110 3 4 1 377 377
FLT12VHO-110W x 4L x 4'-2 MG Fluorescent Linear T12 VHO 110 4 4 2 484 484
FLT12VHO-110W x 4'-MG Fluorescent Linear T12 VHO 110 1 4 1 140 140
FLT12VHO-135W x 2L x 5'-MG Fluorescent Linear T12 VHO 135 2 5 1 310 310
FLT12VHO-135W x 5'-MG Fluorescent Linear T12 VHO 135 1 5 1 165 165
FLT12VHO-160W x 2L x 6'-MG Fluorescent Linear T12 VHO 160 2 6 1 330 330
FLT12VHO-160W x 6'-MG Fluorescent Linear T12 VHO 160 1 6 1 180 180
FLT12VHO-185W x 3L x 8'-MG Fluorescent Linear T12 VHO 185 3 8 1 585 585
FLT12VHO-185W x 4L x 8'-MG Fluorescent Linear T12 VHO 185 4 8 1 760 760
FLT12VHO-185W x 8'-MG Fluorescent Linear T12 VHO 185 1 8 1 205 205
FLT12VHO-195W x 2L x 8'-MG Fluorescent Linear T12 VHO 195 2 8 1 390 390
FLT12VHO-215W x 2L x 8'-MG Fluorescent Linear T12 VHO 215 2 8 1 380 440
FLT12VHO-215W x 3L x 8'-MG Fluorescent Linear T12 VHO 215 3 8 1 585 672
FLT12VHO-215W x 4L x 8'-MG Fluorescent Linear T12 VHO 215 4 8 1 760 880
FLT12VHO-215W x 8'-MG Fluorescent Linear T12 VHO 215 1 8 1 205 232
FLT12VHO-94W x 4L x 4'-2 MG Fluorescent Linear T12 VHO 94 4 4 2 420 420
FLT17-215W x 8'-MG Fluorescent Linear T17 215 1 8 1 235 235
FLT5-13W x 2L x 2'-MG Fluorescent Linear T5 13 2 2 1 26 26
FLT5-13W x 4L x 2'-MG Fluorescent Linear T5 13 4 2 1 53 53
FLT5-14W x 2L x 2'-RS/PRS H Fluorescent Linear
T5 14 2 2 1 (0.95 < BF <
1.10) 33 33
FLT5-14W x 2'-RS/PRS H Fluorescent Linear
T5 14 1 2 1 (0.95 < BF <
1.10) 18 18
FLT5-14W x 3L x 2'-2 RS/PRS H Fluorescent Linear
T5 14 3 2 2 (0.95 < BF <
1.10) 51 51
FLT5-14W x 4L x 2'-2 RS/PRS H Fluorescent Linear
T5 14 4 2 2 (0.95 < BF <
1.10) 67 67
FLT5-21W x 2L x 3'-RS/PRS H Fluorescent Linear
T5 21 2 3 1 (0.95 < BF <
1.10) 48 48
FLT5-21W x 3L x 3'-2 RS/PRS H Fluorescent Linear T5 21 3 3 2
(0.95 < BF < 1.10) 73 73
FLT5-21W x 3'-RS/PRS H Fluorescent Linear
T5 21 1 3 1 (0.95 < BF <
1.10) 25 25
FLT5-21W x 4L x 3'-2 RS/PRS H Fluorescent Linear T5 21 4 3 2
(0.95 < BF < 1.10) 96 96
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 170 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT5-24W x 4L x 2'-2 RS/PRS H Fluorescent Linear
T5 24 4 2 2 (0.95 < BF <
1.10) 105 105
FLT5-28W x 2L x 4'-RS/PRS H Fluorescent Linear
T5 28 2 4 1 (0.95 < BF <
1.10) 63 63
FLT5-28W x 3L x 4'-2 RS/PRS H Fluorescent Linear
T5 28 3 4 2 (0.95 < BF <
1.10) 96 96
FLT5-28W x 4L x 4'-2 RS/PRS H Fluorescent Linear T5 28 4 4 2
(0.95 < BF < 1.10) 126 126
FLT5-28W x 4'-RS/PRS H Fluorescent Linear
T5 28 1 4 1 (0.95 < BF <
1.10) 33 33
FLT5-28W x 4'-RS/PRS H T2 Fluorescent Linear T5 28 1 4 1
(0.95 < BF < 1.10) 32 32
FLT5-35W x 2L x 5'-RS/PRS H Fluorescent Linear
T5 35 2 5 1 (0.95 < BF <
1.10) 78 78
FLT5-35W x 4L x 5'-2 RS/PRS H Fluorescent Linear
T5 35 4 5 2 (0.95 < BF <
1.10) 157 157
FLT5-35W x 5'-RS/PRS H Fluorescent Linear T5 35 1 5 1
(0.95 < BF < 1.10) 40 40
FLT5HO-24W x 2L x 2'-RS/PRS H Fluorescent Linear T5 HO 24 2 2 1
(0.95 < BF < 1.10) 52 52
FLT5HO-24W x 2L x 2'-RS/PRS VH Fluorescent Linear T5 HO 24 2 2 1 (BF > 1.10) 54 54
FLT5HO-24W x 2'-RS/PRS H Fluorescent Linear
T5 HO 24 1 2 1 (0.95 < BF <
1.10) 27 27
FLT5HO-24W x 3L x 2'-2 RS/PRS H Fluorescent Linear
T5 HO 24 3 2 2 (0.95 < BF <
1.10) 80 80
FLT5HO-35W x 3L x 5'-2 RS/PRS H Fluorescent Linear
T5 HO 35 3 5 2 (0.95 < BF <
1.10) 119 119
FLT5HO-39W x 2L x 3'-RS/PRS H Fluorescent Linear
T5 HO 39 2 3 1 (0.95 < BF <
1.10) 86 86
FLT5HO-39W x 2L x 3'-RS/PRS VH Fluorescent Linear
T5 HO 39 2 3 1 (BF > 1.10) 85
85
FLT5HO-39W x 3L x 3'-2 RS/PRS H Fluorescent Linear
T5 HO 39 3 3 2 (0.95 < BF <
1.10) 130 130
FLT5HO-39W x 3L x 3'-RS/PRS VH Fluorescent Linear
T5 HO 39 3 3 1 (BF > 1.10) 127
127
FLT5HO-39W x 3'-RS/PRS H Fluorescent Linear
T5 HO 39 1 3 1 (0.95 < BF <
1.10) 44 44
FLT5HO-39W x 3'-RS/PRS VH Fluorescent Linear T5 HO 39 1 3 1 (BF > 1.10) 42 42
FLT5HO-39W x 4L x 3'-2 Fluorescent Linear T5 HO 39 4 3 2 (0.95 < BF < 172 172
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 171 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
RS/PRS H 1.10)
FLT5HO-39W x 4L x 3'-RS/PRS VH Fluorescent Linear
T5 HO 39 4 3 1 (BF > 1.10) 170
170
FLT5HO-49W x 10L x 4'-3 RS/PRS H Fluorescent Linear
T5 HO 49 10 4 3 (0.95 < BF <
1.10) 541 541
FLT5HO-49W x 10L x 4'-RS/PRS VH Fluorescent Linear
T5 HO 49 10 4 1 (BF > 1.10) 541
541
FLT5HO-49W x 12L x 4'-3 RS/PRS H Fluorescent Linear T5 HO 49 12 4 3
(0.95 < BF < 1.10) 648 648
FLT5HO-49W x 12L x 4'-RS/PRS VH Fluorescent Linear
T5 HO 49 12 4 1 (BF > 1.10) 648
648
FLT5HO-49W x 2L x 4'-RS/PRS H Fluorescent Linear
T5 HO 49 2 4 1 (0.95 < BF <
1.10) 109 109
FLT5HO-49W x 2L x 4'-RS/PRS H T2 Fluorescent Linear
T5 HO 49 2 4 1 (0.95 < BF <
1.10) 108 108
FLT5HO-49W x 2L x 4'-RS/PRS VH Fluorescent Linear
T5 HO 49 2 4 1 (BF > 1.10) 109
109
FLT5HO-49W x 2L x 4'-RS/PRS VH T2 Fluorescent Linear T5 HO 49 2 4 1 (BF > 1.10) 108 108
FLT5HO-49W x 3L x 4'-RS/PRS H Fluorescent Linear
T5 HO 49 3 4 1 (0.95 < BF <
1.10) 165 165
FLT5HO-49W x 3L x 4'-RS/PRS VH Fluorescent Linear T5 HO 49 3 4 1 (BF > 1.10) 165 165
FLT5HO-49W x 4L x 4'-RS/PRS H Fluorescent Linear
T5 HO 49 4 4 1 (0.95 < BF <
1.10) 216 216
FLT5HO-49W x 4L x 4'-RS/PRS VH Fluorescent Linear T5 HO 49 4 4 1 (BF > 1.10) 216 216
FLT5HO-49W x 4'-RS/PRS H Fluorescent Linear
T5 HO 49 1 4 1 (0.95 < BF <
1.10) 58 58
FLT5HO-49W x 4'-RS/PRS H T2 Fluorescent Linear T5 HO 49 1 4 1
(0.95 < BF < 1.10) 55 55
FLT5HO-49W x 4'-RS/PRS H T3 Fluorescent Linear
T5 HO 49 1 4 1 (0.95 < BF <
1.10) 55 55
FLT5HO-49W x 4'-RS/PRS H T4 Fluorescent Linear T5 HO 49 1 4 1
(0.95 < BF < 1.10) 54 54
FLT5HO-49W x 4'-RS/PRS VH Fluorescent Linear T5 HO 49 1 4 1 (BF > 1.10) 58 58
FLT5HO-49W x 4'-RS/PRS VH T2 Fluorescent Linear
T5 HO 49 1 4 1 (BF > 1.10) 55
55
FLT5HO-49W x 4'-RS/PRS VH Fluorescent Linear T5 HO 49 1 4 1 (BF > 1.10) 55 55
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 172 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
T3
FLT5HO-49W x 4'-RS/PRS VH T4 Fluorescent Linear T5 HO 49 1 4 1 (BF > 1.10) 54 54
FLT5HO-49W x 6L x 4'-2 RS/PRS H Fluorescent Linear
T5 HO 49 6 4 2 (0.95 < BF <
1.10) 330 330
FLT5HO-49W x 6L x 4'-RS/PRS VH Fluorescent Linear
T5 HO 49 6 4 1 (BF > 1.10) 330
330
FLT5HO-49W x 8L x 4'-2 RS/PRS H Fluorescent Linear T5 HO 49 8 4 2
(0.95 < BF < 1.10) 432 432
FLT5HO-49W x 8L x 4'-RS/PRS VH Fluorescent Linear T5 HO 49 8 4 1 (BF > 1.10) 432 432
FLT5HO-51W x 10L x 4'-3 RS/PRS H Fluorescent Linear
T5 HO 51 10 4 3 (0.95 < BF <
1.10) 543 543
FLT5HO-51W x 12L x 4'-3 RS/PRS H Fluorescent Linear
T5 HO 51 12 4 3 (0.95 < BF <
1.10) 648 648
FLT5HO-51W x 2L x 4'-RS/PRS H Fluorescent Linear
T5 HO 51 2 4 1 (0.95 < BF <
1.10) 111 111
FLT5HO-51W x 2L x 4'-RS/PRS H T2 Fluorescent Linear
T5 HO 51 2 4 1 (0.95 < BF <
1.10) 108 108
FLT5HO-51W x 3L x 4'-RS/PRS H Fluorescent Linear T5 HO 51 3 4 1
(0.95 < BF < 1.10) 174 174
FLT5HO-51W x 4L x 4'-RS/PRS H Fluorescent Linear
T5 HO 51 4 4 1 (0.95 < BF <
1.10) 216 216
FLT5HO-51W x 4'-RS/PRS H T2 Fluorescent Linear
T5 HO 51 1 4 1 (0.95 < BF <
1.10) 56 56
FLT5HO-51W x 4'-RS/PRS H T3 Fluorescent Linear
T5 HO 51 1 4 1 (0.95 < BF <
1.10) 19 19
FLT5HO-51W x 4'-RS/PRS H T4 Fluorescent Linear T5 HO 51 1 4 1
(0.95 < BF < 1.10) 54 54
FLT5HO-51W x 4'-RS/PRS VH Fluorescent Linear T5 HO 51 1 4 1 (BF > 1.10) 66 66
FLT5HO-51W x 6L x 4'-2 RS/PRS H Fluorescent Linear T5 HO 51 6 4 2
(0.95 < BF < 1.10) 348 348
FLT5HO-51W x 8L x 4'-2 RS/PRS H Fluorescent Linear
T5 HO 51 8 4 2 (0.95 < BF <
1.10) 432 432
FLT5HO-54W x 2L x 4'-RS/PRS H Fluorescent Linear
T5 HO 54 2 4 1 (0.95 < BF <
1.10) 117 117
FLT5HO-54W x 3L x 4'-2 RS/PRS H Fluorescent Linear
T5 HO 54 3 4 2 (0.95 < BF <
1.10) 179 179
FLT5HO-54W x 4L x 4'-2 Fluorescent Linear T5 HO 54 4 4 2 (0.95 < BF < 234 234
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 173 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
RS/PRS H 1.10)
FLT5HO-54W x 4L x 4'-RS/PRS H Fluorescent Linear
T5 HO 54 4 4 1 (0.95 < BF <
1.10) 229 229
FLT5HO-54W x 4'-RS/PRS H Fluorescent Linear T5 HO 54 1 4 1
(0.95 < BF < 1.10) 62 62
FLT5HO-54W x 4'-RS/PRS H T2 Fluorescent Linear T5 HO 54 1 4 1
(0.95 < BF < 1.10) 59 59
FLT5HO-54W x 6L x 4'-3 RS/PRS H Fluorescent Linear
T5 HO 54 6 4 3 (0.95 < BF <
1.10) 351 351
FLT5HO-80W x 2L x 5'-2 RS/PRS H Fluorescent Linear
T5 HO 80 2 5 2 (0.95 < BF <
1.10) 179 179
FLT5HO-80W x 5'-RS/PRS H Fluorescent Linear T5 HO 80 1 5 1
(0.95 < BF < 1.10) 90 90
FLT5HO-80W x 5'-RS/PRS VH Fluorescent Linear T5 HO 80 1 5 1 (BF > 1.10) 89 89
FLT8-15W x 1.5'-MG Fluorescent Linear T8 15 1 1.5 1 19 19
FLT8-15W x 2L x 1.5'-MG Fluorescent Linear T8 15 2 1.5 1 36 36
FLT8-15W x 2'-RS/PRS H Fluorescent Linear T8 15 1 2 1
(0.95 < BF < 1.10) 18 18
FLT8-15W x 2'-RS/PRS N Fluorescent Linear
T8 15 1 2 1 (0.85 < BF <
0.95) 15 15
FLT8-15W x 2'-RS/PRS VH Fluorescent Linear T8 15 1 2 1 (BF > 1.10) 22 22
FLT8-17W x 2'-IS N Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 20 20
FLT8-17W x 2'-IS N T2 Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 17 17
FLT8-17W x 2'-IS N T3 Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 16 16
FLT8-17W x 2'-IS N T4 Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 15 15
FLT8-17W x 2'-IS R Fluorescent Linear
T8 17 1 2 1 (0.75 < BF <
0.85) 17 17
FLT8-17W x 2'-IS R T2 Fluorescent Linear
T8 17 1 2 1 (0.75 < BF <
0.85) 15 15
FLT8-17W x 2'-IS R T3 Fluorescent Linear
T8 17 1 2 1 (0.75 < BF <
0.85) 14 14
FLT8-17W x 2'-IS R T4 Fluorescent Linear
T8 17 1 2 1 (0.75 < BF <
0.85) 14 14
FLT8-17W x 2'-IS(E) N Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 17 17
FLT8-17W x 2'-IS(E) R Fluorescent Linear T8 17 1 2 1 (0.75 < BF < 15 15
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 174 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.85)
FLT8-17W x 2L x 2'-IS N Fluorescent Linear T8 17 2 2 1
(0.85 < BF < 0.95) 33 33
FLT8-17W x 2L x 2'-IS N T4 Fluorescent Linear
T8 17 2 2 1 (0.85 < BF <
0.95) 31 31
FLT8-17W x 2L x 2'-IS R Fluorescent Linear
T8 17 2 2 1 (0.75 < BF <
0.85) 29 29
FLT8-17W x 2L x 2'-IS R T4 Fluorescent Linear T8 17 2 2 1
(0.75 < BF < 0.85) 28 28
FLT8-17W x 2L x 2'-IS(E) N Fluorescent Linear
T8 17 2 2 1 (0.85 < BF <
0.95) 31 31
FLT8-17W x 2L x 2'-IS(E) R Fluorescent Linear
T8 17 2 2 1 (0.75 < BF <
0.85) 29 29
FLT8-17W x 2L x 2'-RS/PRS N Fluorescent Linear
T8 17 2 2 1 (0.85 < BF <
0.95) 35 35
FLT8-17W x 2L x 2'-RS/PRS N T4 Fluorescent Linear
T8 17 2 2 1 (0.85 < BF <
0.95) 34 34
FLT8-17W x 2L x 2'-RS/PRS R Fluorescent Linear
T8 17 2 2 1 (0.75 < BF <
0.85) 28 28
FLT8-17W x 2L x 2'-RS/PRS VH Fluorescent Linear T8 17 2 2 1 (BF > 1.10) 41 41
FLT8-17W x 2L x 2'-RS/PRS VR Fluorescent Linear T8 17 2 2 1 (BF < 0.75) 25 25
FLT8-17W x 2L x 2'-RS/PRS(E) N Fluorescent Linear T8 17 2 2 1
(0.85 < BF < 0.95) 31 31
FLT8-17W x 2L x 3'-RS/PRS VH Fluorescent Linear T8 17 2 3 1 (BF > 1.10) 57 57
FLT8-17W x 2'-MG Fluorescent Linear T8 17 1 2 1 24 24
FLT8-17W x 2'-RS/PRS H Fluorescent Linear
T8 17 1 2 1 (0.95 < BF <
1.10) 18 18
FLT8-17W x 2'-RS/PRS N Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 16 16
FLT8-17W x 2'-RS/PRS N T2 Fluorescent Linear T8 17 1 2 1
(0.85 < BF < 0.95) 16 16
FLT8-17W x 2'-RS/PRS N T3 Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 17 17
FLT8-17W x 2'-RS/PRS N T4 Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 17 17
FLT8-17W x 2'-RS/PRS R Fluorescent Linear T8 17 1 2 1
(0.75 < BF < 0.85) 15 15
FLT8-17W x 2'-RS/PRS VH Fluorescent Linear T8 17 1 2 1 (BF > 1.10) 22 22
FLT8-17W x 2'-RS/PRS VR Fluorescent Linear T8 17 1 2 1 (BF < 0.75) 14 14
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 175 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-17W x 2'-RS/PRS(E) N Fluorescent Linear
T8 17 1 2 1 (0.85 < BF <
0.95) 15 15
FLT8-17W x 3L x 2'-IS H Fluorescent Linear
T8 17 3 2 1 (0.95 < BF <
1.10) 49 49
FLT8-17W x 3L x 2'-IS N Fluorescent Linear
T8 17 3 2 1 (0.85 < BF <
0.95) 47 47
FLT8-17W x 3L x 2'-IS R Fluorescent Linear
T8 17 3 2 1 (0.75 < BF <
0.85) 43 43
FLT8-17W x 3L x 2'-IS(E) N Fluorescent Linear
T8 17 3 2 1 (0.85 < BF <
0.95) 45 45
FLT8-17W x 3L x 2'-IS(E) R Fluorescent Linear T8 17 3 2 1
(0.75 < BF < 0.85) 40 40
FLT8-17W x 3L x 2'-RS/PRS H Fluorescent Linear
T8 17 3 2 1 (0.95 < BF <
1.10) 51 51
FLT8-17W x 3L x 2'-RS/PRS N Fluorescent Linear
T8 17 3 2 1 (0.85 < BF <
0.95) 52 52
FLT8-17W x 3L x 2'-RS/PRS R Fluorescent Linear T8 17 3 2 1
(0.75 < BF < 0.85) 41 41
FLT8-17W x 3L x 2'-RS/PRS VH Fluorescent Linear T8 17 3 2 1 (BF > 1.10) 59 59
FLT8-17W x 3L x 2'-RS/PRS VR Fluorescent Linear T8 17 3 2 1 (BF < 0.75) 37 37
FLT8-17W x 3L x 2'-RS/PRS(E) N Fluorescent Linear
T8 17 3 2 1 (0.85 < BF <
0.95) 47 47
FLT8-17W x 3L x 3'-RS/PRS VH Fluorescent Linear T8 17 3 3 1 (BF > 1.10) 83 83
FLT8-17W x 3'-RS/PRS VH Fluorescent Linear T8 17 1 3 1 (BF > 1.10) 30 30
FLT8-17W x 4L x 2'-IS N Fluorescent Linear
T8 17 4 2 1 (0.85 < BF <
0.95) 61 61
FLT8-17W x 4L x 2'-IS R Fluorescent Linear
T8 17 4 2 1 (0.75 < BF <
0.85) 55 55
FLT8-17W x 4L x 2'-IS(E) N Fluorescent Linear
T8 17 4 2 1 (0.85 < BF <
0.95) 59 59
FLT8-17W x 4L x 2'-IS(E) R Fluorescent Linear
T8 17 4 2 1 (0.75 < BF <
0.85) 51 51
FLT8-17W x 4L x 2'-RS/PRS N Fluorescent Linear
T8 17 4 2 1 (0.85 < BF <
0.95) 68 68
FLT8-17W x 4L x 2'-RS/PRS R Fluorescent Linear
T8 17 4 2 1 (0.75 < BF <
0.85) 57 57
FLT8-17W x 4L x 2'-RS/PRS VH Fluorescent Linear T8 17 4 2 1 (BF > 1.10) 81 81
FLT8-17W x 4L x 2'-RS/PRS VR Fluorescent Linear T8 17 4 2 1 (BF < 0.75) 48 48
FLT8-17W x 4L x 2'-RS/PRS(E) N Fluorescent Linear
T8 17 4 2 1 (0.85 < BF <
0.95) 61 61
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 176 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-17W x 4L x 3'-RS/PRS N Fluorescent Linear
T8 17 4 3 1 (0.85 < BF <
0.95) 85 85
FLT8-25W x 10L x 4'-3 RS/PRS N Fluorescent Linear
T8 25 10 4 3 (0.85 < BF <
0.95) 222 222
FLT8-25W x 10L x 4'-3 RS/PRS VH Fluorescent Linear
T8 25 10 4 3 (BF > 1.10) 280
280
FLT8-25W x 10L x 4'-3 RS/PRS VR Fluorescent Linear
T8 25 10 4 3 (BF < 0.75) 189
189
FLT8-25W x 12L x 4'-3 RS/PRS N Fluorescent Linear
T8 25 12 4 3 (0.85 < BF <
0.95) 268 268
FLT8-25W x 12L x 4'-3 RS/PRS VH Fluorescent Linear
T8 25 12 4 3 (BF > 1.10) 334
334
FLT8-25W x 12L x 4'-3 RS/PRS VR Fluorescent Linear
T8 25 12 4 3 (BF < 0.75) 229
229
FLT8-25W x 2L x 3'-2 IS R Fluorescent Linear
T8 25 2 3 2 (0.75 < BF <
0.85) 54 54
FLT8-25W x 2L x 3'-IS H Fluorescent Linear T8 25 2 3 1
(0.95 < BF < 1.10) 48 48
FLT8-25W x 2L x 3'-IS N Fluorescent Linear T8 25 2 3 1
(0.85 < BF < 0.95) 46 46
FLT8-25W x 2L x 3'-IS N T4 Fluorescent Linear T8 25 2 3 1
(0.85 < BF < 0.95) 44 44
FLT8-25W x 2L x 3'-IS R Fluorescent Linear T8 25 2 3 1
(0.75 < BF < 0.85) 46 46
FLT8-25W x 2L x 3'-IS R T4 Fluorescent Linear T8 25 2 3 1
(0.75 < BF < 0.85) 43 43
FLT8-25W x 2L x 3'-IS(E) N Fluorescent Linear T8 25 2 3 1
(0.85 < BF < 0.95) 44 44
FLT8-25W x 2L x 3'-IS(E) R Fluorescent Linear T8 25 2 3 1
(0.75 < BF < 0.85) 40 40
FLT8-25W x 2L x 3'-IS(E) R T4 Fluorescent Linear T8 25 2 3 1
(0.75 < BF < 0.85) 39 39
FLT8-25W x 2L x 3'-RS/PRS H Fluorescent Linear T8 25 2 3 1
(0.95 < BF < 1.10) 50 50
FLT8-25W x 2L x 3'-RS/PRS N Fluorescent Linear T8 25 2 3 1
(0.85 < BF < 0.95) 46 46
FLT8-25W x 2L x 3'-RS/PRS N T4 Fluorescent Linear T8 25 2 3 1
(0.85 < BF < 0.95) 45 45
FLT8-25W x 2L x 3'-RS/PRS R Fluorescent Linear T8 25 2 3 1
(0.75 < BF < 0.85) 42 42
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 177 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-25W x 2L x 3'-RS/PRS VH Fluorescent Linear T8 25 2 3 1 (BF > 1.10) 70 70
FLT8-25W x 2L x 3'-RS/PRS VR Fluorescent Linear T8 25 2 3 1 (BF < 0.75) 36 36
FLT8-25W x 2L x 3'-RS/PRS(E) N Fluorescent Linear T8 25 2 3 1
(0.85 < BF < 0.95) 43 43
FLT8-25W x 2L x 4'-IS H Fluorescent Linear T8 25 2 4 1
(0.95 < BF < 1.10) 65 65
FLT8-25W x 2L x 4'-IS N Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 46 46
FLT8-25W x 2L x 4'-IS N T2 Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 43 43
FLT8-25W x 2L x 4'-IS N T4 Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 43 43
FLT8-25W x 2L x 4'-IS R Fluorescent Linear T8 25 2 4 1
(0.75 < BF < 0.85) 38 38
FLT8-25W x 2L x 4'-IS VH Fluorescent Linear T8 25 2 4 1 (BF > 1.10) 59 59
FLT8-25W x 2L x 4'-IS VH T2 Fluorescent Linear T8 25 2 4 1 (BF > 1.10) 56 56
FLT8-25W x 2L x 4'-IS VR Fluorescent Linear T8 25 2 4 1 (BF < 0.75) 40 40
FLT8-25W x 2L x 4'-IS VR T2 Fluorescent Linear T8 25 2 4 1 (BF < 0.75) 37 37
FLT8-25W x 2L x 4'-IS VR T4 Fluorescent Linear T8 25 2 4 1 (BF < 0.75) 37 37
FLT8-25W x 2L x 4'-IS(E) H Fluorescent Linear T8 25 2 4 1
(0.95 < BF < 1.10) 49 49
FLT8-25W x 2L x 4'-IS(E) N Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 43 43
FLT8-25W x 2L x 4'-IS(E) N T4 Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 42 42
FLT8-25W x 2L x 4'-IS(E) VR Fluorescent Linear T8 25 2 4 1 (BF < 0.75) 36 36
FLT8-25W x 2L x 4'-RS/PRS N Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 44 44
FLT8-25W x 2L x 4'-RS/PRS N T2 Fluorescent Linear T8 25 2 4 1
(0.85 < BF < 0.95) 44 44
FLT8-25W x 2L x 4'-RS/PRS VH Fluorescent Linear T8 25 2 4 1 (BF > 1.10) 58 58
FLT8-25W x 2L x 4'-RS/PRS VH T2 Fluorescent Linear T8 25 2 4 1 (BF > 1.10) 56 56
FLT8-25W x 2L x 4'-RS/PRS VR Fluorescent Linear T8 25 2 4 1 (BF < 0.75) 37 37
FLT8-25W x 2L x 4'-RS/PRS VR T2 Fluorescent Linear T8 25 2 4 1 (BF < 0.75) 38 38
FLT8-25W x 3'-IS H Fluorescent Linear T8 25 1 3 1
(0.95 < BF < 1.10) 28 28
FLT8-25W x 3'-IS H T2 Fluorescent Linear T8 25 1 3 1 (0.95 < BF < 24 24
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 178 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
1.10)
FLT8-25W x 3'-IS N Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 26 26
FLT8-25W x 3'-IS N T2 Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 23 23
FLT8-25W x 3'-IS N T3 Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 3'-IS N T4 Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 3'-IS R Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 27 27
FLT8-25W x 3'-IS R T2 Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 23 23
FLT8-25W x 3'-IS R T3 Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 22 22
FLT8-25W x 3'-IS R T4 Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 22 22
FLT8-25W x 3'-IS(E) N Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 3'-IS(E) N T2 Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 3'-IS(E) R Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 20 20
FLT8-25W x 3'-IS(E) R T2 Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 20 20
FLT8-25W x 3'-IS(E) R T3 Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 19 19
FLT8-25W x 3'-IS(E) R T4 Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 19 19
FLT8-25W x 3L x 3'-IS N Fluorescent Linear T8 25 3 3 1
(0.85 < BF < 0.95) 67 67
FLT8-25W x 3L x 3'-IS R Fluorescent Linear T8 25 3 3 1
(0.75 < BF < 0.85) 66 66
FLT8-25W x 3L x 3'-IS(E) N Fluorescent Linear T8 25 3 3 1
(0.85 < BF < 0.95) 64 64
FLT8-25W x 3L x 3'-IS(E) R Fluorescent Linear T8 25 3 3 1
(0.75 < BF < 0.85) 57 57
FLT8-25W x 3L x 3'-RS/PRS N Fluorescent Linear T8 25 3 3 1
(0.85 < BF < 0.95) 72 72
FLT8-25W x 3L x 3'-RS/PRS R Fluorescent Linear T8 25 3 3 1 (0.75 < BF < 62 62
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 179 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.85)
FLT8-25W x 3L x 3'-RS/PRS VR Fluorescent Linear T8 25 3 3 1 (BF < 0.75) 54 54
FLT8-25W x 3L x 3'-RS/PRS(E) N Fluorescent Linear T8 25 3 3 1
(0.85 < BF < 0.95) 66 66
FLT8-25W x 3L x 4'-2 IS H Fluorescent Linear T8 25 3 4 2
(0.95 < BF < 1.10) 100 100
FLT8-25W x 3L x 4'-2 IS N Fluorescent Linear T8 25 3 4 2
(0.85 < BF < 0.95) 72 72
FLT8-25W x 3L x 4'-2 IS VR Fluorescent Linear T8 25 3 4 2 (BF < 0.75) 63 63
FLT8-25W x 3L x 4'-2 IS(E) N Fluorescent Linear T8 25 3 4 2
(0.85 < BF < 0.95) 66 66
FLT8-25W x 3L x 4'-IS H Fluorescent Linear T8 25 3 4 1
(0.95 < BF < 1.10) 92 92
FLT8-25W x 3L x 4'-IS N Fluorescent Linear T8 25 3 4 1
(0.85 < BF < 0.95) 67 67
FLT8-25W x 3L x 4'-IS R Fluorescent Linear T8 25 3 4 1
(0.75 < BF < 0.85) 60 60
FLT8-25W x 3L x 4'-IS VH Fluorescent Linear T8 25 3 4 1 (BF > 1.10) 86 86
FLT8-25W x 3L x 4'-IS VR Fluorescent Linear T8 25 3 4 1 (BF < 0.75) 58 58
FLT8-25W x 3L x 4'-IS(E) H Fluorescent Linear T8 25 3 4 1
(0.95 < BF < 1.10) 71 71
FLT8-25W x 3L x 4'-IS(E) N Fluorescent Linear T8
25 3 4 1 (0.85 < BF <
0.95) 66 66
FLT8-25W x 3L x 4'-IS(E) R Fluorescent Linear T8 25 3 4 1
(0.75 < BF < 0.85) 60 60
FLT8-25W x 3L x 4'-IS(E) VR Fluorescent Linear T8 25 3 4 1 (BF < 0.75) 57 57
FLT8-25W x 3L x 4'-RS/PRS N Fluorescent Linear T8 25 3 4 1
(0.85 < BF < 0.95) 68 68
FLT8-25W x 3L x 4'-RS/PRS VH Fluorescent Linear T8 25 3 4 1 (BF > 1.10) 85 85
FLT8-25W x 3L x 4'-RS/PRS VR Fluorescent Linear T8 25 3 4 1 (BF < 0.75) 58 58
FLT8-25W x 3'-RS/PRS H Fluorescent Linear T8 25 1 3 1
(0.95 < BF < 1.10) 26 26
FLT8-25W x 3'-RS/PRS N Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 24 24
FLT8-25W x 3'-RS/PRS N T2 Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 23 23
FLT8-25W x 3'-RS/PRS N T3 Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 24 24
FLT8-25W x 3'-RS/PRS N T4 Fluorescent Linear T8 25 1 3 1 (0.85 < BF < 22 22
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 180 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.95)
FLT8-25W x 3'-RS/PRS R Fluorescent Linear T8 25 1 3 1
(0.75 < BF < 0.85) 23 23
FLT8-25W x 3'-RS/PRS VR Fluorescent Linear T8 25 1 3 1 (BF < 0.75) 20 20
FLT8-25W x 3'-RS/PRS(E) N Fluorescent Linear T8 25 1 3 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 4'-IS H Fluorescent Linear T8 25 1 4 1
(0.95 < BF < 1.10) 35 35
FLT8-25W x 4'-IS H T2 Fluorescent Linear T8 25 1 4 1
(0.95 < BF < 1.10) 33 33
FLT8-25W x 4'-IS H T3 Fluorescent Linear T8 25 1 4 1
(0.95 < BF < 1.10) 31 31
FLT8-25W x 4'-IS N Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 26 26
FLT8-25W x 4'-IS N T2 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 23 23
FLT8-25W x 4'-IS N T3 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 4'-IS N T4 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 4'-IS R Fluorescent Linear T8 25 1 4 1
(0.75 < BF < 0.85) 19 19
FLT8-25W x 4'-IS VH Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 32 32
FLT8-25W x 4'-IS VH T2 Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 29 29
FLT8-25W x 4'-IS VH T3 Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 29 29
FLT8-25W x 4'-IS VH T4 Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 28 28
FLT8-25W x 4'-IS VR Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 23 23
FLT8-25W x 4'-IS VR T2 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 20 20
FLT8-25W x 4'-IS VR T3 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 19 19
FLT8-25W x 4'-IS VR T4 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 19 19
FLT8-25W x 4'-IS(E) H Fluorescent Linear T8 25 1 4 1
(0.95 < BF < 1.10) 26 26
FLT8-25W x 4'-IS(E) N Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 23 23
FLT8-25W x 4'-IS(E) N T2 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 4'-IS(E) N T3 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 21 21
FLT8-25W x 4'-IS(E) N T4 Fluorescent Linear T8 25 1 4 1 (0.85 < BF < 21 21
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 181 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.95)
FLT8-25W x 4'-IS(E) VR T2 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 18 18
FLT8-25W x 4'-IS(E) VR T4 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 18 18
FLT8-25W x 4L x 3'-2 IS R Fluorescent Linear T8 25 4 3 2
(0.75 < BF < 0.85) 92 92
FLT8-25W x 4L x 3'-IS N Fluorescent Linear T8 25 4 3 1
(0.85 < BF < 0.95) 87 87
FLT8-25W x 4L x 3'-IS R Fluorescent Linear T8 25 4 3 1
(0.75 < BF < 0.85) 86 86
FLT8-25W x 4L x 3'-IS(E) N Fluorescent Linear T8 25 4 3 1
(0.85 < BF < 0.95) 85 85
FLT8-25W x 4L x 3'-IS(E) R Fluorescent Linear T8 25 4 3 1
(0.75 < BF < 0.85) 78 78
FLT8-25W x 4L x 3'-RS/PRS N Fluorescent Linear T8 25 4 3 1
(0.85 < BF < 0.95) 89 89
FLT8-25W x 4L x 3'-RS/PRS R Fluorescent Linear T8 25 4 3 1
(0.75 < BF < 0.85) 84 84
FLT8-25W x 4L x 3'-RS/PRS VR Fluorescent Linear T8 25 4 3 1 (BF < 0.75) 76 76
FLT8-25W x 4L x 3'-RS/PRS(E) N Fluorescent Linear T8 25 4 3 1
(0.85 < BF < 0.95) 85 85
FLT8-25W x 4L x 4'-2 IS H Fluorescent Linear T8 25 4 4 2
(0.95 < BF < 1.10) 130 130
FLT8-25W x 4L x 4'-2 IS N Fluorescent Linear T8 25 4 4 2
(0.85 < BF < 0.95) 92 92
FLT8-25W x 4L x 4'-2 IS VR Fluorescent Linear T8 25 4 4 2 (BF < 0.75) 80 80
FLT8-25W x 4L x 4'-2 IS(E) N Fluorescent Linear T8 25 4 4 2
(0.85 < BF < 0.95) 86 86
FLT8-25W x 4L x 4'-2 IS(E) VR Fluorescent Linear T8 25 4 4 2 (BF < 0.75) 74 74
FLT8-25W x 4L x 4'-IS H Fluorescent Linear T8 25 4 4 1
(0.95 < BF < 1.10) 92 92
FLT8-25W x 4L x 4'-IS N Fluorescent Linear T8 25 4 4 1
(0.85 < BF < 0.95) 87 87
FLT8-25W x 4L x 4'-IS R Fluorescent Linear T8 25 4 4 1
(0.75 < BF < 0.85) 80 80
FLT8-25W x 4L x 4'-IS VH Fluorescent Linear T8 25 4 4 1 (BF > 1.10) 111 111
FLT8-25W x 4L x 4'-IS VR Fluorescent Linear T8 25 4 4 1 (BF < 0.75) 75 75
FLT8-25W x 4L x 4'-IS(E) N Fluorescent Linear T8 25 4 4 1
(0.85 < BF < 0.95) 86 86
FLT8-25W x 4L x 4'-IS(E) R Fluorescent Linear T8 25 4 4 1 (0.75 < BF < 76 76
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 182 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.85)
FLT8-25W x 4L x 4'-IS(E) VR Fluorescent Linear T8 25 4 4 1 (BF < 0.75) 74 74
FLT8-25W x 4L x 4'-RS/PRS N Fluorescent Linear T8 25 4 4 1
(0.85 < BF < 0.95) 89 89
FLT8-25W x 4L x 4'-RS/PRS VH Fluorescent Linear T8 25 4 4 1 (BF > 1.10) 111 111
FLT8-25W x 4L x 4'-RS/PRS VR Fluorescent Linear T8 25 4 4 1 (BF < 0.75) 76 76
FLT8-25W x 4'-RS/PRS N Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 24 24
FLT8-25W x 4'-RS/PRS N T2 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 4'-RS/PRS N T3 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 23 23
FLT8-25W x 4'-RS/PRS N T4 Fluorescent Linear T8 25 1 4 1
(0.85 < BF < 0.95) 22 22
FLT8-25W x 4'-RS/PRS VH Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 31 31
FLT8-25W x 4'-RS/PRS VH T2 Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 29 29
FLT8-25W x 4'-RS/PRS VH T3 Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 28 28
FLT8-25W x 4'-RS/PRS VH T4 Fluorescent Linear T8 25 1 4 1 (BF > 1.10) 28 28
FLT8-25W x 4'-RS/PRS VR Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 21 21
FLT8-25W x 4'-RS/PRS VR T2 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 19 19
FLT8-25W x 4'-RS/PRS VR T3 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 19 19
FLT8-25W x 4'-RS/PRS VR T4 Fluorescent Linear T8 25 1 4 1 (BF < 0.75) 19 19
FLT8-25W x 6L x 3'-2 IS N Fluorescent Linear T8 25 6 3 2
(0.85 < BF < 0.95) 134 134
FLT8-25W x 6L x 3'-2 IS R Fluorescent Linear T8 25 6 3 2
(0.75 < BF < 0.85) 134 134
FLT8-25W x 6L x 4'-2 RS/PRS N Fluorescent Linear T8 25 6 4 2
(0.85 < BF < 0.95) 133 133
FLT8-25W x 6L x 4'-2 RS/PRS VH Fluorescent Linear T8 25 6 4 2 (BF > 1.10) 170 170
FLT8-25W x 6L x 4'-2 RS/PRS VR Fluorescent Linear T8 25 6 4 2 (BF < 0.75) 113 113
FLT8-25W x 6L x 4'-IS VH Fluorescent Linear T8 25 6 4 1 (BF > 1.10) 176 176
FLT8-25W x 6L x 4'-RS/PRS N Fluorescent Linear T8 25 6 4 1
(0.85 < BF < 0.95) 133 133
FLT8-25W x 6L x 4'-RS/PRS VH Fluorescent Linear T8 25 6 4 1 (BF > 1.10) 170 170
FLT8-25W x 6L x 4'-RS/PRS VR Fluorescent Linear T8 25 6 4 1 (BF < 0.75) 113 113
FLT8-25W x 8L x 4'-2 RS/PRS N Fluorescent Linear T8 25 8 4 2 (0.85 < BF < 178 178
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 183 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.95)
FLT8-25W x 8L x 4'-2 RS/PRS VH Fluorescent Linear T8 25 8 4 2 (BF > 1.10) 223 223
FLT8-25W x 8L x 4'-2 RS/PRS VR Fluorescent Linear T8 25 8 4 2 (BF < 0.75) 148 148
FLT8-28W x 10L x 4'-3 RS/PRS N Fluorescent Linear T8 28 10 4 3
(0.85 < BF < 0.95) 247 247
FLT8-28W x 10L x 4'-3 RS/PRS VH Fluorescent Linear T8 28 10 4 3 (BF > 1.10) 310 310
FLT8-28W x 10L x 4'-3 RS/PRS VR Fluorescent Linear T8 28 10 4 3 (BF < 0.75) 199 199
FLT8-28W x 12L x 4'-3 RS/PRS N Fluorescent Linear T8 28 12 4 3
(0.85 < BF < 0.95) 295 295
FLT8-28W x 12L x 4'-3 RS/PRS VH Fluorescent Linear T8 28 12 4 3 (BF > 1.10) 371 371
FLT8-28W x 12L x 4'-3 RS/PRS VR Fluorescent Linear T8 28 12 4 3 (BF < 0.75) 238 238
FLT8-28W x 2L x 3'-RS/PRS N Fluorescent Linear T8 28 2 3 1
(0.85 < BF < 0.95) 43 43
FLT8-28W x 2L x 3'-RS/PRS VH Fluorescent Linear T8 28 2 3 1 (BF > 1.10) 58 58
FLT8-28W x 2L x 3'-RS/PRS VR Fluorescent Linear T8 28 2 3 1 (BF < 0.75) 36 36
FLT8-28W x 2L x 4'-CEE ISDIM N T2 Fluorescent Linear T8 28 2 4 1
(0.85 < BF < 0.95) 47 47
FLT8-28W x 2L x 4'-IS H Fluorescent Linear T8 28 2 4 1
(0.95 < BF < 1.10) 53 53
FLT8-28W x 2L x 4'-IS N Fluorescent Linear T8 28 2 4 1
(0.85 < BF < 0.95) 49 49
FLT8-28W x 2L x 4'-IS R Fluorescent Linear T8 28 2 4 1
(0.75 < BF < 0.85) 44 44
FLT8-28W x 2L x 4'-IS VH Fluorescent Linear T8 28 2 4 1 (BF > 1.10) 65 65
FLT8-28W x 2L x 4'-IS VH T2 Fluorescent Linear T8 28 2 4 1 (BF > 1.10) 62 62
FLT8-28W x 2L x 4'-IS VR Fluorescent Linear T8 28 2 4 1 (BF < 0.75) 42 42
FLT8-28W x 2L x 4'-IS VR T2 Fluorescent Linear T8 28 2 4 1 (BF < 0.75) 41 41
FLT8-28W x 2L x 4'-IS(E) N Fluorescent Linear T8 28 2 4 1
(0.85 < BF < 0.95) 48 48
FLT8-28W x 2L x 4'-RS/PRS H Fluorescent Linear T8 28 2 4 1
(0.95 < BF < 1.10) 63 63
FLT8-28W x 2L x 4'-RS/PRS N Fluorescent Linear T8 28 2 4 1
(0.85 < BF < 0.95) 50 50
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 184 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-28W x 2L x 4'-RS/PRS N T2 Fluorescent Linear T8 28 2 4 1
(0.85 < BF < 0.95) 49 49
FLT8-28W x 2L x 4'-RS/PRS VH T2 Fluorescent Linear T8 28 2 4 1 (BF > 1.10) 62 62
FLT8-28W x 2L x 4'-RS/PRS VR Fluorescent Linear T8 28 2 4 1 (BF < 0.75) 41 41
FLT8-28W x 2L x 4'-RS/PRS VR T2 Fluorescent Linear T8 28 2 4 1 (BF < 0.75) 39 39
FLT8-28W x 3L x 3'-RS/PRS N Fluorescent Linear T8 28 3 3 1
(0.85 < BF < 0.95) 66 66
FLT8-28W x 3L x 3'-RS/PRS VH Fluorescent Linear T8 28 3 3 1 (BF > 1.10) 84 84
FLT8-28W x 3L x 3'-RS/PRS VR Fluorescent Linear T8 28 3 3 1 (BF < 0.75) 56 56
FLT8-28W x 3L x 4'-IS H Fluorescent Linear T8 28 3 4 1
(0.95 < BF < 1.10) 79 79
FLT8-28W x 3L x 4'-IS N Fluorescent Linear T8 28 3 4 1
(0.85 < BF < 0.95) 73 73
FLT8-28W x 3L x 4'-IS R Fluorescent Linear T8 28 3 4 1
(0.75 < BF < 0.85) 66 66
FLT8-28W x 3L x 4'-IS VH Fluorescent Linear T8 28 3 4 1 (BF > 1.10) 95 95
FLT8-28W x 3L x 4'-IS VR Fluorescent Linear T8 28 3 4 1 (BF < 0.75) 63 63
FLT8-28W x 3L x 4'-IS(E) N Fluorescent Linear T8 28 3 4 1
(0.85 < BF < 0.95) 72 72
FLT8-28W x 3L x 4'-RS/PRS N Fluorescent Linear T8 28 3 4 1
(0.85 < BF < 0.95) 74 74
FLT8-28W x 3L x 4'-RS/PRS VH Fluorescent Linear T8 28 3 4 1 (BF > 1.10) 98 98
FLT8-28W x 3L x 4'-RS/PRS VR Fluorescent Linear T8 28 3 4 1 (BF < 0.75) 61 61
FLT8-28W x 3'-RS/PRS N Fluorescent Linear T8 28 1 3 1
(0.85 < BF < 0.95) 22 22
FLT8-28W x 3'-RS/PRS VH Fluorescent Linear T8 28 1 3 1 (BF > 1.10) 30 30
FLT8-28W x 3'-RS/PRS VR Fluorescent Linear T8 28 1 3 1 (BF < 0.75) 20 20
FLT8-28W x 4'-IS H Fluorescent Linear T8 28 1 4 1
(0.95 < BF < 1.10) 29 29
FLT8-28W x 4'-IS N Fluorescent Linear T8 28 1 4 1
(0.85 < BF < 0.95) 27 27
FLT8-28W x 4'-IS R Fluorescent Linear T8 28 1 4 1
(0.75 < BF < 0.85) 22 22
FLT8-28W x 4'-IS VH Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 36 36
FLT8-28W x 4'-IS VH T2 Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 33 33
FLT8-28W x 4'-IS VH T3 Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 32 32
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 185 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-28W x 4'-IS VH T4 Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 31 31
FLT8-28W x 4'-IS VR T2 Fluorescent Linear T8 28 1 4 1 (BF < 0.75) 21 21
FLT8-28W x 4'-IS VR T4 Fluorescent Linear T8 28 1 4 1 (BF < 0.75) 20 20
FLT8-28W x 4'-IS(E) N Fluorescent Linear T8 28 1 4 1
(0.85 < BF < 0.95) 25 25
FLT8-28W x 4L x 3'-RS/PRS N Fluorescent Linear T8 28 4 3 1
(0.85 < BF < 0.95) 85 85
FLT8-28W x 4L x 3'-RS/PRS VR Fluorescent Linear T8 28 4 3 1 (BF < 0.75) 76 76
FLT8-28W x 4L x 4'-2 IS VR Fluorescent Linear T8 28 4 4 2 (BF < 0.75) 83 83
FLT8-28W x 4L x 4'-IS H Fluorescent Linear T8 28 4 4 1
(0.95 < BF < 1.10) 112 112
FLT8-28W x 4L x 4'-IS N Fluorescent Linear T8 28 4 4 1
(0.85 < BF < 0.95) 98 98
FLT8-28W x 4L x 4'-IS R Fluorescent Linear T8 28 4 4 1
(0.75 < BF < 0.85) 85 85
FLT8-28W x 4L x 4'-IS VH Fluorescent Linear T8 28 4 4 1 (BF > 1.10) 123 123
FLT8-28W x 4L x 4'-IS VR Fluorescent Linear T8 28 4 4 1 (BF < 0.75) 81 81
FLT8-28W x 4L x 4'-IS(E) N Fluorescent Linear T8 28 4 4 1
(0.85 < BF < 0.95) 94 94
FLT8-28W x 4L x 4'-IS(E) R Fluorescent Linear T8 28 4 4 1
(0.75 < BF < 0.85) 84 84
FLT8-28W x 4L x 4'-RS/PRS N Fluorescent Linear T8 28 4 4 1
(0.85 < BF < 0.95) 98 98
FLT8-28W x 4L x 4'-RS/PRS VH Fluorescent Linear T8 28 4 4 1 (BF > 1.10) 124 124
FLT8-28W x 4L x 4'-RS/PRS VR Fluorescent Linear T8 28 4 4 1 (BF < 0.75) 79 79
FLT8-28W x 4'-RS/PRS N Fluorescent Linear T8 28 1 4 1
(0.85 < BF < 0.95) 26 26
FLT8-28W x 4'-RS/PRS N T2 Fluorescent Linear T8 28 1 4 1
(0.85 < BF < 0.95) 25 25
FLT8-28W x 4'-RS/PRS N T3 Fluorescent Linear T8 28 1 4 1
(0.85 < BF < 0.95) 25 25
FLT8-28W x 4'-RS/PRS N T4 Fluorescent Linear T8 28 1 4 1
(0.85 < BF < 0.95) 24 24
FLT8-28W x 4'-RS/PRS VH Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 33 33
FLT8-28W x 4'-RS/PRS VH T2 Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 31 31
FLT8-28W x 4'-RS/PRS VH T3 Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 32 32
FLT8-28W x 4'-RS/PRS VH T4 Fluorescent Linear T8 28 1 4 1 (BF > 1.10) 31 31
FLT8-28W x 4'-RS/PRS VR Fluorescent Linear T8 28 1 4 1 (BF < 0.75) 22 22
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 186 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-28W x 4'-RS/PRS VR T2 Fluorescent Linear T8 28 1 4 1 (BF < 0.75) 20 20
FLT8-28W x 4'-RS/PRS VR T3 Fluorescent Linear T8 28 1 4 1 (BF < 0.75) 20 20
FLT8-28W x 4'-RS/PRS VR T4 Fluorescent Linear T8 28 1 4 1 (BF < 0.75) 20 20
FLT8-28W x 6L x 4'-2 RS/PRS N Fluorescent Linear T8 28 6 4 2
(0.85 < BF < 0.95) 146 146
FLT8-28W x 6L x 4'-2 RS/PRS VH Fluorescent Linear T8 28 6 4 2 (BF > 1.10) 186 186
FLT8-28W x 6L x 4'-2 RS/PRS VR Fluorescent Linear T8 28 6 4 2 (BF < 0.75) 122 122
FLT8-28W x 6L x 4'-IS VH Fluorescent Linear T8 28 6 4 1 (BF > 1.10) 184 184
FLT8-28W x 6L x 4'-RS/PRS N Fluorescent Linear T8 28 6 4 1
(0.85 < BF < 0.95) 146 146
FLT8-28W x 6L x 4'-RS/PRS VH Fluorescent Linear T8 28 6 4 1 (BF > 1.10) 186 186
FLT8-28W x 6L x 4'-RS/PRS VR Fluorescent Linear T8 28 6 4 1 (BF < 0.75) 122 122
FLT8-28W x 8L x 4'-2 RS/PRS N Fluorescent Linear T8 28 8 4 2
(0.85 < BF < 0.95) 196 196
FLT8-28W x 8L x 4'-2 RS/PRS VH Fluorescent Linear T8 28 8 4 2 (BF > 1.10) 248 248
FLT8-28W x 8L x 4'-2 RS/PRS VR Fluorescent Linear T8 28 8 4 2 (BF < 0.75) 158 158
FLT8-30W x 10L x 4'-3 RS/PRS N Fluorescent Linear T8 30 10 4 3
(0.85 < BF < 0.95) 270 270
FLT8-30W x 10L x 4'-3 RS/PRS VH Fluorescent Linear T8 30 10 4 3 (BF > 1.10) 337 337
FLT8-30W x 10L x 4'-3 RS/PRS VR Fluorescent Linear T8 30 10 4 3 (BF < 0.75) 215 215
FLT8-30W x 12L x 4'-3 RS/PRS N Fluorescent Linear T8 30 12 4 3
(0.85 < BF < 0.95) 323 323
FLT8-30W x 12L x 4'-3 RS/PRS VH Fluorescent Linear T8 30 12 4 3 (BF > 1.10) 403 403
FLT8-30W x 12L x 4'-3 RS/PRS VR Fluorescent Linear T8 30 12 4 3 (BF < 0.75) 257 257
FLT8-30W x 2L x 4'-IS H Fluorescent Linear T8 30 2 4 1
(0.95 < BF < 1.10) 72 72
FLT8-30W x 2L x 4'-IS N Fluorescent Linear T8 30 2 4 1
(0.85 < BF < 0.95) 54 54
FLT8-30W x 2L x 4'-IS N T4 Fluorescent Linear T8 30 2 4 1
(0.85 < BF < 0.95) 52 52
FLT8-30W x 2L x 4'-IS R Fluorescent Linear T8 30 2 4 1
(0.75 < BF < 0.85) 48 48
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 187 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-30W x 2L x 4'-IS R T4 Fluorescent Linear T8 30 2 4 1
(0.75 < BF < 0.85) 47 47
FLT8-30W x 2L x 4'-IS(E) N Fluorescent Linear T8 30 2 4 1
(0.85 < BF < 0.95) 52 52
FLT8-30W x 2L x 4'-IS(E) N T4 Fluorescent Linear T8 30 2 4 1
(0.85 < BF < 0.95) 51 51
FLT8-30W x 2L x 4'-IS(E) R Fluorescent Linear T8 30 2 4 1
(0.75 < BF < 0.85) 46 46
FLT8-30W x 2L x 4'-IS(E) R T4 Fluorescent Linear T8 30 2 4 1
(0.75 < BF < 0.85) 46 46
FLT8-30W x 2L x 4'-RS/PRS H Fluorescent Linear T8 30 2 4 1
(0.95 < BF < 1.10) 69 69
FLT8-30W x 2L x 4'-RS/PRS N Fluorescent Linear T8 30 2 4 1
(0.85 < BF < 0.95) 55 55
FLT8-30W x 2L x 4'-RS/PRS N T2 Fluorescent Linear T8 30 2 4 1
(0.85 < BF < 0.95) 54 54
FLT8-30W x 2L x 4'-RS/PRS VH T2 Fluorescent Linear T8 30 2 4 1 (BF > 1.10) 67 67
FLT8-30W x 2L x 4'-RS/PRS VR Fluorescent Linear T8 30 2 4 1 (BF < 0.75) 44 44
FLT8-30W x 2L x 4'-RS/PRS VR T2 Fluorescent Linear T8 30 2 4 1 (BF < 0.75) 43 43
FLT8-30W x 3L x 4'-2 IS H Fluorescent Linear T8 30 3 4 2
(0.95 < BF < 1.10) 111 111
FLT8-30W x 3L x 4'-2 IS N Fluorescent Linear T8 30 3 4 2
(0.85 < BF < 0.95) 83 83
FLT8-30W x 3L x 4'-2 IS R Fluorescent Linear T8 30 3 4 2
(0.75 < BF < 0.85) 78 78
FLT8-30W x 3L x 4'-IS H Fluorescent Linear T8 30 3 4 1
(0.95 < BF < 1.10) 105 105
FLT8-30W x 3L x 4'-IS N Fluorescent Linear T8 30 3 4 1
(0.85 < BF < 0.95) 79 79
FLT8-30W x 3L x 4'-IS R Fluorescent Linear T8 30 3 4 1
(0.75 < BF < 0.85) 70 70
FLT8-30W x 3L x 4'-IS VR Fluorescent Linear T8 30 3 4 1 (BF < 0.75) 66 66
FLT8-30W x 3L x 4'-IS(E) N Fluorescent Linear T8 30 3 4 1
(0.85 < BF < 0.95) 76 76
FLT8-30W x 3L x 4'-IS(E) R Fluorescent Linear T8 30 3 4 1
(0.75 < BF < 0.85) 66 66
FLT8-30W x 3L x 4'-RS/PRS N Fluorescent Linear T8 30 3 4 1
(0.85 < BF < 0.95) 81 81
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 188 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-30W x 3L x 4'-RS/PRS R Fluorescent Linear T8 30 3 4 1
(0.75 < BF < 0.85) 70 70
FLT8-30W x 3L x 4'-RS/PRS VH Fluorescent Linear T8 30 3 4 1 (BF > 1.10) 102 102
FLT8-30W x 3L x 4'-RS/PRS VR Fluorescent Linear T8 30 3 4 1 (BF < 0.75) 65 65
FLT8-30W x 4'-IS H Fluorescent Linear T8 30 1 4 1
(0.95 < BF < 1.10) 39 39
FLT8-30W x 4'-IS N Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 29 29
FLT8-30W x 4'-IS N T2 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 27 27
FLT8-30W x 4'-IS N T3 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 26 26
FLT8-30W x 4'-IS N T4 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 26 26
FLT8-30W x 4'-IS R Fluorescent Linear T8 30 1 4 1
(0.75 < BF < 0.85) 27 27
FLT8-30W x 4'-IS R T2 Fluorescent Linear T8 30 1 4 1
(0.75 < BF < 0.85) 23 23
FLT8-30W x 4'-IS R T3 Fluorescent Linear T8 30 1 4 1
(0.75 < BF < 0.85) 22 22
FLT8-30W x 4'-IS R T4 Fluorescent Linear T8 30 1 4 1
(0.75 < BF < 0.85) 22 22
FLT8-30W x 4'-IS VR Fluorescent Linear T8 30 1 4 1 (BF < 0.75) 24 24
FLT8-30W x 4'-IS(E) H Fluorescent Linear T8 30 1 4 1
(0.95 < BF < 1.10) 32 32
FLT8-30W x 4'-IS(E) N Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-30W x 4'-IS(E) N T2 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 26 26
FLT8-30W x 4'-IS(E) N T3 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 25 25
FLT8-30W x 4'-IS(E) N T4 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 25 25
FLT8-30W x 4L x 4'-2 IS H Fluorescent Linear T8 30 4 4 2
(0.95 < BF < 1.10) 144 144
FLT8-30W x 4L x 4'-2 IS N Fluorescent Linear T8 30 4 4 2
(0.85 < BF < 0.95) 108 108
FLT8-30W x 4L x 4'-2 IS R Fluorescent Linear T8 30 4 4 2
(0.75 < BF < 0.85) 96 96
FLT8-30W x 4L x 4'-IS N Fluorescent Linear T8 30 4 4 1 (0.85 < BF < 104 104
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 189 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
0.95)
FLT8-30W x 4L x 4'-IS R Fluorescent Linear T8 30 4 4 1
(0.75 < BF < 0.85) 91 91
FLT8-30W x 4L x 4'-IS(E) N Fluorescent Linear T8 30 4 4 1
(0.85 < BF < 0.95) 101 101
FLT8-30W x 4L x 4'-IS(E) R Fluorescent Linear T8 30 4 4 1
(0.75 < BF < 0.85) 88 88
FLT8-30W x 4L x 4'-RS/PRS N Fluorescent Linear T8 30 4 4 1
(0.85 < BF < 0.95) 108 108
FLT8-30W x 4L x 4'-RS/PRS VH Fluorescent Linear T8 30 4 4 1 (BF > 1.10) 134 134
FLT8-30W x 4L x 4'-RS/PRS VR Fluorescent Linear T8 30 4 4 1 (BF < 0.75) 86 86
FLT8-30W x 4'-RS/PRS N Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-30W x 4'-RS/PRS N T2 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-30W x 4'-RS/PRS N T3 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 27 27
FLT8-30W x 4'-RS/PRS N T4 Fluorescent Linear T8 30 1 4 1
(0.85 < BF < 0.95) 27 27
FLT8-30W x 4'-RS/PRS VH Fluorescent Linear T8 30 1 4 1 (BF > 1.10) 36 36
FLT8-30W x 4'-RS/PRS VH T2 Fluorescent Linear T8 30 1 4 1 (BF > 1.10) 34 34
FLT8-30W x 4'-RS/PRS VH T3 Fluorescent Linear T8 30 1 4 1 (BF > 1.10) 34 34
FLT8-30W x 4'-RS/PRS VH T4 Fluorescent Linear T8 30 1 4 1 (BF > 1.10) 34 34
FLT8-30W x 4'-RS/PRS VR Fluorescent Linear T8 30 1 4 1 (BF < 0.75) 26 26
FLT8-30W x 4'-RS/PRS VR T2 Fluorescent Linear T8 30 1 4 1 (BF < 0.75) 22 22
FLT8-30W x 4'-RS/PRS VR T3 Fluorescent Linear T8 30 1 4 1 (BF < 0.75) 22 22
FLT8-30W x 4'-RS/PRS VR T4 Fluorescent Linear T8 30 1 4 1 (BF < 0.75) 21 21
FLT8-30W x 6L x 4'-2 IS N Fluorescent Linear T8 30 6 4 2
(0.85 < BF < 0.95) 152 152
FLT8-30W x 6L x 4'-2 IS R Fluorescent Linear T8 30 6 4 2
(0.75 < BF < 0.85) 132 132
FLT8-30W x 6L x 4'-2 RS/PRS N Fluorescent Linear T8 30 6 4 2
(0.85 < BF < 0.95) 162 162
FLT8-30W x 6L x 4'-2 RS/PRS VH Fluorescent Linear T8 30 6 4 2 (BF > 1.10) 204 204
FLT8-30W x 6L x 4'-2 RS/PRS VR Fluorescent Linear T8 30 6 4 2 (BF < 0.75) 131 131
FLT8-30W x 6L x 4'-IS VH Fluorescent Linear T8 30 6 4 1 (BF > 1.10) 200 200
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 190 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-30W x 6L x 4'-RS/PRS N Fluorescent Linear T8 30 6 4 1
(0.85 < BF < 0.95) 162 162
FLT8-30W x 6L x 4'-RS/PRS VH Fluorescent Linear T8 30 6 4 1 (BF > 1.10) 204 204
FLT8-30W x 6L x 4'-RS/PRS VR Fluorescent Linear T8 30 6 4 1 (BF < 0.75) 131 131
FLT8-30W x 8L x 4'-2 RS/PRS N Fluorescent Linear T8 30 8 4 2
(0.85 < BF < 0.95) 217 217
FLT8-30W x 8L x 4'-2 RS/PRS VH Fluorescent Linear T8 30 8 4 2 (BF > 1.10) 269 269
FLT8-30W x 8L x 4'-2 RS/PRS VR Fluorescent Linear T8 30 8 4 2 (BF < 0.75) 171 171
FLT8-32W x 10L x 4'-3 RS/PRS N Fluorescent Linear T8 32 10 4 3
(0.85 < BF < 0.95) 281 281
FLT8-32W x 10L x 4'-3 RS/PRS VH Fluorescent Linear T8 32 10 4 3 (BF > 1.10) 361 361
FLT8-32W x 10L x 4'-3 RS/PRS VR Fluorescent Linear T8 32 10 4 3 (BF < 0.75) 228 228
FLT8-32W x 12L x 4'-3 RS/PRS N Fluorescent Linear T8 32 12 4 3
(0.85 < BF < 0.95) 338 338
FLT8-32W x 12L x 4'-3 RS/PRS VH Fluorescent Linear T8 32 12 4 3 (BF > 1.10) 431 431
FLT8-32W x 12L x 4'-3 RS/PRS VR Fluorescent Linear T8 32 12 4 3 (BF < 0.75) 272 272
FLT8-32W x 2L x 4'-2 IS N Fluorescent Linear T8 32 2 4 2
(0.85 < BF < 0.95) 62 62
FLT8-32W x 2L x 4'-2 IS R Fluorescent Linear T8 32 2 4 2
(0.75 < BF < 0.85) 62 62
FLT8-32W x 2L x 4'-2 RS/PRS N Fluorescent Linear T8 32 2 4 2
(0.85 < BF < 0.95) 64 64
FLT8-32W x 2L x 4'-CEE ISDIM N Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 55 55
FLT8-32W x 2L x 4'-CEE PS/PRS DIM H Fluorescent Linear T8 32 2 4 1
(0.95 < BF < 1.10) 67 67
FLT8-32W x 2L x 4'-CEE PS/PRS DIM N Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 56 56
FLT8-32W x 2L x 4'-CEE PS/PRS DIM R Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 47 47
FLT8-32W x 2L x 4'-CEE PS/PRS DIM VH Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 75 75
FLT8-32W x 2L x 4'-IS H Fluorescent Linear T8 32 2 4 1 (0.95 < BF < 77 77
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 191 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
1.10)
FLT8-32W x 2L x 4'-IS N Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 59 59
FLT8-32W x 2L x 4'-IS N T2 Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 54 54
FLT8-32W x 2L x 4'-IS N T4 Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 56 56
FLT8-32W x 2L x 4'-IS R Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 52 52
FLT8-32W x 2L x 4'-IS R T4 Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 51 51
FLT8-32W x 2L x 4'-IS VH Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 79 79
FLT8-32W x 2L x 4'-IS VH T2 Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 71 71
FLT8-32W x 2L x 4'-IS VH T3 Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 72 72
FLT8-32W x 2L x 4'-IS VR Fluorescent Linear T8 32 2 4 1 (BF < 0.75) 44 44
FLT8-32W x 2L x 4'-IS VR T2 Fluorescent Linear T8 32 2 4 1 (BF < 0.75) 45 45
FLT8-32W x 2L x 4'-IS(E) H Fluorescent Linear T8 32 2 4 1
(0.95 < BF < 1.10) 66 66
FLT8-32W x 2L x 4'-IS(E) N Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 55 55
FLT8-32W x 2L x 4'-IS(E) N T4 Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 54 54
FLT8-32W x 2L x 4'-IS(E) R Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 48 48
FLT8-32W x 2L x 4'-IS(E) R T4 Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 48 48
FLT8-32W x 2L x 4'-IS(E) VH Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 75 75
FLT8-32W x 2L x 4'-MG Fluorescent Linear T8 32 2 4 1 71 71
FLT8-32W x 2L x 4'-RS/PRS H Fluorescent Linear T8 32 2 4 1
(0.95 < BF < 1.10) 70 70
FLT8-32W x 2L x 4'-RS/PRS N Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 60 60
FLT8-32W x 2L x 4'-RS/PRS N T2 Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 56 56
FLT8-32W x 2L x 4'-RS/PRS N T4 Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 59 59
FLT8-32W x 2L x 4'-RS/PRS R Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 54 54
FLT8-32W x 2L x 4'-RS/PRS R Fluorescent Linear T8 32 2 4 1 (0.75 < BF < 53 53
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 192 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
T4 0.85)
FLT8-32W x 2L x 4'-RS/PRS VH Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 85 85
FLT8-32W x 2L x 4'-RS/PRS VH T2 Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 72 72
FLT8-32W x 2L x 4'-RS/PRS VR Fluorescent Linear T8 32 2 4 1 (BF < 0.75) 46 46
FLT8-32W x 2L x 4'-RS/PRS VR T2 Fluorescent Linear T8 32 2 4 1 (BF < 0.75) 45 45
FLT8-32W x 2L x 4'-RS/PRS(E) H Fluorescent Linear T8 32 2 4 1
(0.95 < BF < 1.10) 66 66
FLT8-32W x 2L x 4'-RS/PRS(E) N Fluorescent Linear T8 32 2 4 1
(0.85 < BF < 0.95) 57 57
FLT8-32W x 2L x 4'-RS/PRS(E) R Fluorescent Linear T8 32 2 4 1
(0.75 < BF < 0.85) 52 52
FLT8-32W x 2L x 4'-RS/PRS(E) VH Fluorescent Linear T8 32 2 4 1 (BF > 1.10) 73 73
FLT8-32W x 2L x 4'-RS/PRS(E) VR Fluorescent Linear T8 32 2 4 1 (BF < 0.75) 49 49
FLT8-32W x 3L x 4'-2 IS H Fluorescent Linear T8 32 3 4 2
(0.95 < BF < 1.10) 118 118
FLT8-32W x 3L x 4'-2 IS N Fluorescent Linear T8 32 3 4 2
(0.85 < BF < 0.95) 90 90
FLT8-32W x 3L x 4'-2 IS R Fluorescent Linear T8 32 3 4 2
(0.75 < BF < 0.85) 83 83
FLT8-32W x 3L x 4'-2 RS/PRS N Fluorescent Linear T8 32 3 4 2
(0.85 < BF < 0.95) 92 92
FLT8-32W x 3L x 4'-CEE ISDIM N Fluorescent Linear T8 32 3 4 1
(0.85 < BF < 0.95) 82 82
FLT8-32W x 3L x 4'-CEE PS/PRS DIM H Fluorescent Linear T8 32 3 4 1
(0.95 < BF < 1.10) 96 96
FLT8-32W x 3L x 4'-CEE PS/PRS DIM N Fluorescent Linear T8 32 3 4 1
(0.85 < BF < 0.95) 84 84
FLT8-32W x 3L x 4'-CEE PS/PRS DIM R Fluorescent Linear T8 32 3 4 1
(0.75 < BF < 0.85) 87 87
FLT8-32W x 3L x 4'-CEE PS/PRS DIM VH Fluorescent Linear T8 32 3 4 1 (BF > 1.10) 110 110
FLT8-32W x 3L x 4'-CEE PS/PRS DIM VR Fluorescent Linear T8 32 3 4 1 (BF < 0.75) 72 72
FLT8-32W x 3L x 4'-IS H Fluorescent Linear T8 32 3 4 1
(0.95 < BF < 1.10) 111 111
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 193 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-32W x 3L x 4'-IS N Fluorescent Linear T8 32 3 4 1
(0.85 < BF < 0.95) 87 87
FLT8-32W x 3L x 4'-IS R Fluorescent Linear T8 32 3 4 1
(0.75 < BF < 0.85) 78 78
FLT8-32W x 3L x 4'-IS R T2 Fluorescent Linear T8 32 3 4 1
(0.75 < BF < 0.85) 83 83
FLT8-32W x 3L x 4'-IS VH Fluorescent Linear T8 32 3 4 1 (BF > 1.10) 113 113
FLT8-32W x 3L x 4'-IS VH T2 Fluorescent Linear T8 32 3 4 1 (BF > 1.10) 108 108
FLT8-32W x 3L x 4'-IS(E) H Fluorescent Linear T8 32 3 4 1
(0.95 < BF < 1.10) 90 90
FLT8-32W x 3L x 4'-IS(E) N Fluorescent Linear T8 32 3 4 1
(0.85 < BF < 0.95) 83 83
FLT8-32W x 3L x 4'-IS(E) R Fluorescent Linear T8 32 3 4 1
(0.75 < BF < 0.85) 74 74
FLT8-32W x 3L x 4'-IS(E) VH Fluorescent Linear T8 32 3 4 1 (BF > 1.10) 109 109
FLT8-32W x 3L x 4'-MG Fluorescent Linear T8 32 3 4 1 110 110
FLT8-32W x 3L x 4'-RS/PRS H Fluorescent Linear T8 32 3 4 1
(0.95 < BF < 1.10) 98 98
FLT8-32W x 3L x 4'-RS/PRS N Fluorescent Linear T8 32 3 4 1
(0.85 < BF < 0.95) 93 93
FLT8-32W x 3L x 4'-RS/PRS R Fluorescent Linear T8 32 3 4 1
(0.75 < BF < 0.85) 79 79
FLT8-32W x 3L x 4'-RS/PRS VH Fluorescent Linear T8 32 3 4 1 (BF > 1.10) 110 110
FLT8-32W x 3L x 4'-RS/PRS VR Fluorescent Linear T8 32 3 4 1 (BF < 0.75) 72 72
FLT8-32W x 3L x 4'-RS/PRS(E) H Fluorescent Linear T8 32 3 4 1
(0.95 < BF < 1.10) 91 91
FLT8-32W x 3L x 4'-RS/PRS(E) N Fluorescent Linear T8 32 3 4 1
(0.85 < BF < 0.95) 85 85
FLT8-32W x 3L x 4'-RS/PRS(E) R Fluorescent Linear T8 32 3 4 1
(0.75 < BF < 0.85) 76 76
FLT8-32W x 3L x 4'-RS/PRS(E) VR Fluorescent Linear T8 32 3 4 1 (BF < 0.75) 71 71
FLT8-32W x 4'-CEE PS/PRS DIM H Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 35 35
FLT8-32W x 4'-CEE PS/PRS DIM N Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 29 29
FLT8-32W x 4'-CEE PS/PRS DIM VH Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 39 39
FLT8-32W x 4'-CEE PS/PRS DIM VR Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 24 24
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 194 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-32W x 4'-IS H Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 41 41
FLT8-32W x 4'-IS H T2 Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 33 33
FLT8-32W x 4'-IS H T3 Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 31 31
FLT8-32W x 4'-IS N Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 31 31
FLT8-32W x 4'-IS N T2 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 30 30
FLT8-32W x 4'-IS N T3 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 30 30
FLT8-32W x 4'-IS N T4 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-IS R Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 29 29
FLT8-32W x 4'-IS R T2 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 26 26
FLT8-32W x 4'-IS R T3 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 26 26
FLT8-32W x 4'-IS R T4 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 26 26
FLT8-32W x 4'-IS VH Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 41 41
FLT8-32W x 4'-IS VH T2 Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 37 37
FLT8-32W x 4'-IS VH T4 Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 36 36
FLT8-32W x 4'-IS VR Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 25 25
FLT8-32W x 4'-IS VR T2 Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 22 22
FLT8-32W x 4'-IS VR T4 Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 23 23
FLT8-32W x 4'-IS(E) H Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 32 32
FLT8-32W x 4'-IS(E) N Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-IS(E) N T2 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-IS(E) N T3 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 27 27
FLT8-32W x 4'-IS(E) N T4 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-IS(E) R Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 25 25
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 195 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-32W x 4'-IS(E) R T2 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 24 24
FLT8-32W x 4'-IS(E) R T3 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 24 24
FLT8-32W x 4'-IS(E) R T4 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 24 24
FLT8-32W x 4'-IS(E) VH Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 36 36
FLT8-32W x 4L x 4'-2 IS H Fluorescent Linear T8 32 4 4 2
(0.95 < BF < 1.10) 154 154
FLT8-32W x 4L x 4'-2 IS N Fluorescent Linear T8 32 4 4 2
(0.85 < BF < 0.95) 118 118
FLT8-32W x 4L x 4'-2 IS R Fluorescent Linear T8 32 4 4 2
(0.75 < BF < 0.85) 104 104
FLT8-32W x 4L x 4'-2 IS VH Fluorescent Linear T8 32 4 4 2 (BF > 1.10) 158 158
FLT8-32W x 4L x 4'-2 RS/PRS N Fluorescent Linear T8 32 4 4 2
(0.85 < BF < 0.95) 120 120
FLT8-32W x 4L x 4'-CEE ISDIM VH Fluorescent Linear T8 32 4 4 1 (BF > 1.10) 215 215
FLT8-32W x 4L x 4'-CEE PS/PRS DIM N Fluorescent Linear T8 32 4 4 1
(0.85 < BF < 0.95) 113 113
FLT8-32W x 4L x 4'-CEE PS/PRS DIM VH Fluorescent Linear T8 32 4 4 1 (BF > 1.10) 148 148
FLT8-32W x 4L x 4'-CEE PS/PRS DIM VR Fluorescent Linear T8 32 4 4 1 (BF < 0.75) 93 93
FLT8-32W x 4L x 4'-IS H Fluorescent Linear T8 32 4 4 1
(0.95 < BF < 1.10) 121 121
FLT8-32W x 4L x 4'-IS N Fluorescent Linear T8 32 4 4 1
(0.85 < BF < 0.95) 112 112
FLT8-32W x 4L x 4'-IS R Fluorescent Linear T8 32 4 4 1
(0.75 < BF < 0.85) 102 102
FLT8-32W x 4L x 4'-IS VH Fluorescent Linear T8 32 4 4 1 (BF > 1.10) 151 151
FLT8-32W x 4L x 4'-IS VR Fluorescent Linear T8 32 4 4 1 (BF < 0.75) 90 90
FLT8-32W x 4L x 4'-IS(E) N Fluorescent Linear T8 32 4 4 1
(0.85 < BF < 0.95) 108 108
FLT8-32W x 4L x 4'-IS(E) R Fluorescent Linear T8 32 4 4 1
(0.75 < BF < 0.85) 96 96
FLT8-32W x 4L x 4'-IS(E) VH Fluorescent Linear T8 32 4 4 1 (BF > 1.10) 142 142
FLT8-32W x 4L x 4'-MG Fluorescent Linear T8 32 4 4 1 142 142
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 196 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-32W x 4L x 4'-RS/PRS N Fluorescent Linear T8 32 4 4 1
(0.85 < BF < 0.95) 118 118
FLT8-32W x 4L x 4'-RS/PRS R Fluorescent Linear T8 32 4 4 1
(0.75 < BF < 0.85) 105 105
FLT8-32W x 4L x 4'-RS/PRS VH Fluorescent Linear T8 32 4 4 1 (BF > 1.10) 143 143
FLT8-32W x 4L x 4'-RS/PRS VR Fluorescent Linear T8 32 4 4 1 (BF < 0.75) 94 94
FLT8-32W x 4L x 4'-RS/PRS(E) N Fluorescent Linear T8 32 4 4 1
(0.85 < BF < 0.95) 111 111
FLT8-32W x 4L x 4'-RS/PRS(E) VR Fluorescent Linear T8 32 4 4 1 (BF < 0.75) 92 92
FLT8-32W x 4'-MG Fluorescent Linear T8 32 1 4 1 35 35
FLT8-32W x 4'-RS/PRS H Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 39 39
FLT8-32W x 4'-RS/PRS H T2 Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 35 35
FLT8-32W x 4'-RS/PRS H T3 Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 33 33
FLT8-32W x 4'-RS/PRS N Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 32 32
FLT8-32W x 4'-RS/PRS N T2 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 30 30
FLT8-32W x 4'-RS/PRS N T3 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 31 31
FLT8-32W x 4'-RS/PRS N T4 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 30 30
FLT8-32W x 4'-RS/PRS R Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 27 27
FLT8-32W x 4'-RS/PRS R T2 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 27 27
FLT8-32W x 4'-RS/PRS R T3 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 26 26
FLT8-32W x 4'-RS/PRS R T4 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 26 26
FLT8-32W x 4'-RS/PRS VH Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 39 39
FLT8-32W x 4'-RS/PRS VH T2 Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 37 37
FLT8-32W x 4'-RS/PRS VH T3 Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 36 36
FLT8-32W x 4'-RS/PRS VH T4 Fluorescent Linear T8 32 1 4 1 (BF > 1.10) 36 36
FLT8-32W x 4'-RS/PRS VR Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 28 28
FLT8-32W x 4'-RS/PRS VR T2 Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 23 23
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 197 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-32W x 4'-RS/PRS VR T3 Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 23 23
FLT8-32W x 4'-RS/PRS VR T4 Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 23 23
FLT8-32W x 4'-RS/PRS(E) H Fluorescent Linear T8 32 1 4 1
(0.95 < BF < 1.10) 33 33
FLT8-32W x 4'-RS/PRS(E) N Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 30 30
FLT8-32W x 4'-RS/PRS(E) N T2 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-RS/PRS(E) N T3 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-RS/PRS(E) N T4 Fluorescent Linear T8 32 1 4 1
(0.85 < BF < 0.95) 28 28
FLT8-32W x 4'-RS/PRS(E) R T2 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 26 26
FLT8-32W x 4'-RS/PRS(E) R T3 Fluorescent Linear T8 32 1 4 1
(0.75 < BF < 0.85) 25 25
FLT8-32W x 4'-RS/PRS(E) VR Fluorescent Linear T8 32 1 4 1 (BF < 0.75) 24 24
FLT8-32W x 5L x 4'-2 IS N Fluorescent Linear T8 32 5 4 2
(0.85 < BF < 0.95) 148 148
FLT8-32W x 6L x 4'-2 IS H Fluorescent Linear
T8 32 6 4 2 (0.95 < BF <
1.10) 222 222
FLT8-32W x 6L x 4'-2 IS N Fluorescent Linear T8 32 6 4 2
(0.85 < BF < 0.95) 174 174
FLT8-32W x 6L x 4'-2 IS R Fluorescent Linear T8 32 6 4 2
(0.75 < BF < 0.85) 156 156
FLT8-32W x 6L x 4'-2 IS VH Fluorescent Linear T8 32 6 4 2 (BF > 1.10) 226 226
FLT8-32W x 6L x 4'-2 IS(E) H Fluorescent Linear T8 32 6 4 2
(0.95 < BF < 1.10) 192 192
FLT8-32W x 6L x 4'-2 IS(E) N Fluorescent Linear T8 32 6 4 2
(0.85 < BF < 0.95) 164 164
FLT8-32W x 6L x 4'-2 IS(E) R Fluorescent Linear T8 32 6 4 2
(0.75 < BF < 0.85) 146 146
FLT8-32W x 6L x 4'-2 RS/PRS N Fluorescent Linear T8 32 6 4 2
(0.85 < BF < 0.95) 171 171
FLT8-32W x 6L x 4'-2 RS/PRS VH Fluorescent Linear T8 32 6 4 2 (BF > 1.10) 218 218
FLT8-32W x 6L x 4'-2 RS/PRS VR Fluorescent Linear T8 32 6 4 2 (BF < 0.75) 141 141
FLT8-32W x 6L x 4'-IS R Fluorescent Linear T8 32 6 4 1
(0.75 < BF < 0.85) 156 156
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 198 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-32W x 6L x 4'-IS VH Fluorescent Linear T8 32 6 4 1 (BF > 1.10) 215 215
FLT8-32W x 6L x 4'-RS/PRS N Fluorescent Linear T8 32 6 4 1
(0.85 < BF < 0.95) 171 171
FLT8-32W x 6L x 4'-RS/PRS VH Fluorescent Linear T8 32 6 4 1 (BF > 1.10) 218 218
FLT8-32W x 6L x 4'-RS/PRS VR Fluorescent Linear T8 32 6 4 1 (BF < 0.75) 141 141
FLT8-32W x 8L x 4'-2 IS H Fluorescent Linear T8 32 8 4 2
(0.95 < BF < 1.10) 308 308
FLT8-32W x 8L x 4'-2 IS N Fluorescent Linear T8 32 8 4 2
(0.85 < BF < 0.95) 224 224
FLT8-32W x 8L x 4'-2 IS R Fluorescent Linear T8 32 8 4 2
(0.75 < BF < 0.85) 204 204
FLT8-32W x 8L x 4'-2 IS VH Fluorescent Linear T8 32 8 4 2 (BF > 1.10) 292 292
FLT8-32W x 8L x 4'-2 RS/PRS N Fluorescent Linear T8 32 8 4 2
(0.85 < BF < 0.95) 225 225
FLT8-32W x 8L x 4'-2 RS/PRS VH Fluorescent Linear T8 32 8 4 2 (BF > 1.10) 288 288
FLT8-32W x 8L x 4'-2 RS/PRS VR Fluorescent Linear T8 32 8 4 2 (BF < 0.75) 182 182
FLT8-40W x 2L x 5'-IS H Fluorescent Linear T8 40 2 5 1
(0.95 < BF < 1.10) 80 80
FLT8-40W x 2L x 5'-IS N Fluorescent Linear T8 40 2 5 1
(0.85 < BF < 0.95) 73 73
FLT8-40W x 2L x 5'-IS N T4 Fluorescent Linear T8 40 2 5 1
(0.85 < BF < 0.95) 67 67
FLT8-40W x 2L x 5'-IS R Fluorescent Linear T8 40 2 5 1
(0.75 < BF < 0.85) 73 73
FLT8-40W x 2L x 5'-IS VH Fluorescent Linear T8 40 2 5 1 (BF > 1.10) 100 100
FLT8-40W x 2L x 5'-IS(E) N Fluorescent Linear T8 40 2 5 1
(0.85 < BF < 0.95) 72 72
FLT8-40W x 2L x 5'-IS(E) R Fluorescent Linear T8 40 2 5 1
(0.75 < BF < 0.85) 68 68
FLT8-40W x 3L x 5'-IS H Fluorescent Linear T8 40 3 5 1
(0.95 < BF < 1.10) 108 108
FLT8-40W x 3L x 5'-IS N Fluorescent Linear T8 40 3 5 1
(0.85 < BF < 0.95) 110 110
FLT8-40W x 3L x 5'-IS R Fluorescent Linear T8 40 3 5 1
(0.75 < BF < 0.85) 100 100
FLT8-40W x 3L x 5'-IS VH Fluorescent Linear T8 40 3 5 1 (BF > 1.10) 142 142
FLT8-40W x 3L x 5'-IS(E) N Fluorescent Linear T8 40 3 5 1
(0.85 < BF < 0.95) 106 106
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 199 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-40W x 4L x 5'-IS H Fluorescent Linear T8 40 4 5 1
(0.95 < BF < 1.10) 126 126
FLT8-40W x 4L x 5'-IS N Fluorescent Linear T8 40 4 5 1
(0.85 < BF < 0.95) 134 134
FLT8-40W x 5'-IS H Fluorescent Linear T8 40 1 5 1
(0.95 < BF < 1.10) 43 43
FLT8-40W x 5'-IS N Fluorescent Linear T8 40 1 5 1
(0.85 < BF < 0.95) 36 36
FLT8-40W x 5'-IS N T2 Fluorescent Linear T8 40 1 5 1
(0.85 < BF < 0.95) 36 36
FLT8-40W x 5'-IS N T3 Fluorescent Linear T8 40 1 5 1
(0.85 < BF < 0.95) 35 35
FLT8-40W x 5'-IS N T4 Fluorescent Linear T8 40 1 5 1
(0.85 < BF < 0.95) 34 34
FLT8-40W x 5'-IS R Fluorescent Linear T8 40 1 5 1
(0.75 < BF < 0.85) 43 43
FLT8-40W x 5'-IS VH Fluorescent Linear T8 40 1 5 1 (BF > 1.10) 57 57
FLT8-40W x 5'-IS VR Fluorescent Linear T8 40 1 5 1 (BF < 0.75) 29 29
FLT8-40W x 5'-IS(E) N Fluorescent Linear T8 40 1 5 1
(0.85 < BF < 0.95) 35 35
FLT8-57W x 2L x 8'-IS N Fluorescent Linear T8 57 2 8 1
(0.85 < BF < 0.95) 100 100
FLT8-57W x 8'-IS N Fluorescent Linear T8 57 1 8 1
(0.85 < BF < 0.95) 51 51
FLT8-59W x 2L x 8'-IS N Fluorescent Linear T8 59 2 8 1
(0.85 < BF < 0.95) 109 109
FLT8-59W x 2L x 8'-IS R Fluorescent Linear T8 59 2 8 1
(0.75 < BF < 0.85) 98 98
FLT8-59W x 2L x 8'-IS VH Fluorescent Linear T8 59 2 8 1 (BF > 1.10) 149 149
FLT8-59W x 2L x 8'-IS(E) N Fluorescent Linear T8 59 2 8 1
(0.85 < BF < 0.95) 105 105
FLT8-59W x 3L x 8'-2 IS H Fluorescent Linear T8 59 3 8 2
(0.95 < BF < 1.10) 240 240
FLT8-59W x 3L x 8'-2 IS VH Fluorescent Linear T8 59 3 8 2 (BF > 1.10) 216 216
FLT8-59W x 3L x 8'-IS N Fluorescent Linear T8 59 3 8 1
(0.85 < BF < 0.95) 167 167
FLT8-59W x 4L x 8'-2 IS H Fluorescent Linear T8 59 4 8 2
(0.95 < BF < 1.10) 320 320
FLT8-59W x 4L x 8'-2 IS VH Fluorescent Linear T8 59 4 8 2 (BF > 1.10) 298 298
FLT8-59W x 4L x 8'-2 IS(E) VH Fluorescent Linear T8 59 4 8 2 (BF > 1.10) 288 288
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 200 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8-59W x 4L x 8'-IS N Fluorescent Linear T8 59 4 8 1
(0.85 < BF < 0.95) 219 219
FLT8-59W x 6L x 8'-2 IS N Fluorescent Linear T8 59 6 8 2
(0.85 < BF < 0.95) 328 328
FLT8-59W x 8'-IS H Fluorescent Linear T8 59 1 8 1
(0.95 < BF < 1.10) 68 68
FLT8-59W x 8'-IS N Fluorescent Linear T8 59 1 8 1
(0.85 < BF < 0.95) 58 58
FLT8-59W x 8'-IS N T2 Fluorescent Linear
T8 59 1 8 1 (0.85 < BF <
0.95) 55 55
FLT8-59W x 8'-IS R Fluorescent Linear T8 59 1 8 1
(0.75 < BF < 0.85) 57 57
FLT8-59W x 8'-IS R T2 Fluorescent Linear T8 59 1 8 1
(0.75 < BF < 0.85) 49 49
FLT8-59W x 8'-IS VH Fluorescent Linear T8 59 1 8 1 (BF > 1.10) 71 71
FLT8-59W x 8'-IS(E) N Fluorescent Linear T8 59 1 8 1
(0.85 < BF < 0.95) 53 53
FLT8-86W x 2L x 8'-IS N Fluorescent Linear T8 86 2 8 1
(0.85 < BF < 0.95) 160 160
FLT8-86W x 3L x 8'-2 IS N Fluorescent Linear T8 86 3 8 2
(0.85 < BF < 0.95) 240 240
FLT8-86W x 4L x 8'-2 IS N Fluorescent Linear T8 86 4 8 2
(0.85 < BF < 0.95) 320 320
FLT8-86W x 8'-IS N T2 Fluorescent Linear
T8 86 1 8 1 (0.85 < BF <
0.95) 80 80
FLT8CEE-25W x 2L x 4'-CEE IS H Fluorescent Linear T8 CEE 25 2 4 1 (BF > 1.0) 56 56
FLT8CEE-25W x 2L x 4'-CEE IS H T2 Fluorescent Linear T8 CEE 25 2 4 1 (BF > 1.0) 56 56
FLT8CEE-25W x 2L x 4'-CEE IS L Fluorescent Linear T8 CEE 25 2 4 1 (BF < 0.85) 39 39
FLT8CEE-25W x 2L x 4'-CEE IS L T2 Fluorescent Linear T8 CEE 25 2 4 1 (BF < 0.85) 38 38
FLT8CEE-25W x 2L x 4'-CEE IS N Fluorescent Linear T8 CEE 25 2 4 1 (0.85 < BF < 1.0) 44 44
FLT8CEE-25W x 2L x 4'-CEE IS N T2 Fluorescent Linear T8 CEE 25 2 4 1 (0.85 < BF < 1.0) 44 44
FLT8CEE-25W x 3L x 4'-CEE IS H Fluorescent Linear T8 CEE 25 3 4 1 (BF > 1.0) 86 86
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 201 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8CEE-25W x 3L x 4'-CEE IS L Fluorescent Linear T8 CEE 25 3 4 1 (BF < 0.85) 59 59
FLT8CEE-25W x 3L x 4'-CEE IS N Fluorescent Linear T8 CEE 25 3 4 1 (0.85 < BF < 1.0) 67 67
FLT8CEE-25W x 4'-CEE IS H Fluorescent Linear T8 CEE 25 1 4 1 (BF > 1.0) 30 30
FLT8CEE-25W x 4'-CEE IS L Fluorescent Linear T8 CEE 25 1 4 1 (BF < 0.85) 19 19
FLT8CEE-25W x 4'-CEE IS N Fluorescent Linear T8 CEE 25 1 4 1 (0.85 < BF < 1.0) 23 23
FLT8CEE-25W x 4L x 4'-CEE IS H Fluorescent Linear T8 CEE 25 4 4 1 (BF > 1.0) 111 111
FLT8CEE-25W x 4L x 4'-CEE IS L Fluorescent Linear
T8 CEE 25 4 4 1 (BF < 0.85) 76 76
FLT8CEE-25W x 4L x 4'-CEE IS N Fluorescent Linear T8 CEE 25 4 4 1 (0.85 < BF < 1.0) 87 87
FLT8CEE-28W x 2L x 4'-CEE IS H Fluorescent Linear T8 CEE 28 2 4 1 (BF > 1.0) 65 65
FLT8CEE-28W x 2L x 4'-CEE IS H T2 Fluorescent Linear T8 CEE 28 2 4 1 (BF > 1.0) 62 62
FLT8CEE-28W x 2L x 4'-CEE IS L Fluorescent Linear T8 CEE 28 2 4 1 (BF < 0.85) 43 43
FLT8CEE-28W x 2L x 4'-CEE IS L T2 Fluorescent Linear T8 CEE 28 2 4 1 (BF < 0.85) 42 42
FLT8CEE-28W x 2L x 4'-CEE IS N Fluorescent Linear T8 CEE 28 2 4 1 (0.85 < BF < 1.0) 50 50
FLT8CEE-28W x 2L x 4'-CEE IS N T2 Fluorescent Linear T8 CEE 28 2 4 1 (0.85 < BF < 1.0) 47 47
FLT8CEE-28W x 3L x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 28 3 4 1 (BF > 1.0) 96 96
FLT8CEE-28W x 3L x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 28 3 4 1 (BF < 0.85) 66 66
FLT8CEE-28W x 3L x 4'-CEE IS CEE N Fluorescent Linear T8 CEE 28 3 4 1 (0.85 < BF < 1.0) 74 74
FLT8CEE-28W x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 28 1 4 1 (BF > 1.0) 33 33
FLT8CEE-28W x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 28 1 4 1 (BF < 0.85) 22 22
FLT8CEE-28W x 4'-CEE IS CEE N Fluorescent Linear T8 CEE 28 1 4 1 (0.85 < BF < 1.0) 25 25
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 202 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8CEE-28W x 4L x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 28 4 4 1 (BF > 1.0) 123 123
FLT8CEE-28W x 4L x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 28 4 4 1 (BF < 0.85) 84 84
FLT8CEE-28W x 4L x 4'-CEE IS CEE N Fluorescent Linear T8 CEE 28 4 4 1 (0.85 < BF < 1.0) 94 94
FLT8CEE-32W x 2L x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 32 2 4 1 (BF > 1.0) 73 73
FLT8CEE-32W x 2L x 4'-CEE IS CEE H T2 Fluorescent Linear T8 CEE 32 2 4 1 (BF > 1.0) 71 71
FLT8CEE-32W x 2L x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 32 2 4 1 (BF < 0.85) 48 48
FLT8CEE-32W x 2L x 4'-CEE IS CEE L T2 Fluorescent Linear T8 CEE 32 2 4 1 (BF < 0.85) 48 48
FLT8CEE-32W x 2L x 4'-CEE IS CEE N Fluorescent Linear T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 56 56
FLT8CEE-32W x 2L x 4'-CEE IS CEE N T2 Fluorescent Linear
T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 54 54
FLT8CEE-32W x 2L x 4'-CEE ISDIM CEE N Fluorescent Linear T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 55 55
FLT8CEE-32W x 2L x 4'-CEE ISDIM CEE N T2 Fluorescent Linear T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 57 57
FLT8CEE-32W x 2L x 4'-CEE PS/PRS DIM CEE H Fluorescent Linear T8 CEE 32 2 4 1 (BF > 1.0) 73 73
FLT8CEE-32W x 2L x 4'-CEE PS/PRS DIM CEE L Fluorescent Linear
T8 CEE 32 2 4 1 (BF < 0.85) 54 54
FLT8CEE-32W x 2L x 4'-CEE PS/PRS DIM CEE N Fluorescent Linear T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 62 62
FLT8CEE-32W x 2L x 4'-CEE RS/PRS CEE H Fluorescent Linear T8 CEE 32 2 4 1 (BF > 1.0) 73 73
FLT8CEE-32W x 2L x 4'-CEE RS/PRS CEE H T2 Fluorescent Linear
T8 CEE 32 2 4 1 (BF > 1.0) 72 72
FLT8CEE-32W x 2L x 4'-CEE RS/PRS CEE L Fluorescent Linear T8 CEE 32 2 4 1 (BF < 0.85) 48 48
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 203 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8CEE-32W x 2L x 4'-CEE RS/PRS CEE L T2 Fluorescent Linear T8 CEE 32 2 4 1 (BF < 0.85) 47 47
FLT8CEE-32W x 2L x 4'-CEE RS/PRS CEE N Fluorescent Linear T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 58 58
FLT8CEE-32W x 2L x 4'-CEE RS/PRS CEE N T2 Fluorescent Linear T8 CEE 32 2 4 1 (0.85 < BF < 1.0) 56 56
FLT8CEE-32W x 3L x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 32 3 4 1 (BF > 1.0) 109 109
FLT8CEE-32W x 3L x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 32 3 4 1 (BF < 0.85) 74 74
FLT8CEE-32W x 3L x 4'-CEE IS CEE N Fluorescent Linear T8 CEE 32 3 4 1 (0.85 < BF < 1.0) 84 84
FLT8CEE-32W x 3L x 4'-CEE ISDIM CEE N Fluorescent Linear T8 CEE 32 3 4 1 (0.85 < BF < 1.0) 82 82
FLT8CEE-32W x 3L x 4'-CEE PS/PRS DIM CEE H Fluorescent Linear T8 CEE 32 3 4 1 (BF > 1.0) 110 110
FLT8CEE-32W x 3L x 4'-CEE PS/PRS DIM CEE L Fluorescent Linear T8 CEE 32 3 4 1 (BF < 0.85) 79 79
FLT8CEE-32W x 3L x 4'-CEE PS/PRS DIM CEE N Fluorescent Linear T8 CEE 32 3 4 1 (0.85 < BF < 1.0) 91 91
FLT8CEE-32W x 3L x 4'-CEE RS/PRS CEE H Fluorescent Linear T8 CEE 32 3 4 1 (BF > 1.0) 110 110
FLT8CEE-32W x 3L x 4'-CEE RS/PRS CEE L Fluorescent Linear T8 CEE 32 3 4 1 (BF < 0.85) 73 73
FLT8CEE-32W x 3L x 4'-CEE RS/PRS CEE N Fluorescent Linear T8 CEE 32 3 4 1 (0.85 < BF < 1.0) 85 85
FLT8CEE-32W x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 38 38
FLT8CEE-32W x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 25 25
FLT8CEE-32W x 4'-CEE IS CEE N Fluorescent Linear
T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 29 29
FLT8CEE-32W x 4'-CEE ISDIM CEE H T2 Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 37 37
FLT8CEE-32W x 4'-CEE ISDIM CEE H T3 Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 36 36
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 204 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8CEE-32W x 4'-CEE ISDIM CEE H T4 Fluorescent Linear
T8 CEE 32 1 4 1 (BF > 1.0) 36 36
FLT8CEE-32W x 4'-CEE ISDIM CEE L T2 Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 24 24
FLT8CEE-32W x 4'-CEE ISDIM CEE L T3 Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 25 25
FLT8CEE-32W x 4'-CEE ISDIM CEE L T4 Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 24 24
FLT8CEE-32W x 4'-CEE ISDIM CEE N T2 Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 28 28
FLT8CEE-32W x 4'-CEE ISDIM CEE N T3 Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 28 28
FLT8CEE-32W x 4'-CEE ISDIM CEE N T4 Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 27 27
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE H Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 24 24
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE H T2 Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 37 37
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE H T3 Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 37 37
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE H T4 Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 36 36
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE L Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 33 33
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE L T2 Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 24 24
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE L T3 Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 24 24
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE L T4 Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 24 24
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE N Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 39 39
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE N T2 Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 29 29
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 205 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FLT8CEE-32W x 4'-CEE PS/PRS DIM CEE N T3 Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 28 28
FLT8CEE-32W x 4'-CEE RS/PRS CEE H Fluorescent Linear T8 CEE 32 1 4 1 (BF > 1.0) 39 39
FLT8CEE-32W x 4'-CEE RS/PRS CEE L Fluorescent Linear T8 CEE 32 1 4 1 (BF < 0.85) 25 25
FLT8CEE-32W x 4'-CEE RS/PRS CEE N Fluorescent Linear T8 CEE 32 1 4 1 (0.85 < BF < 1.0) 30 30
FLT8CEE-32W x 4L x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 32 4 4 1 (BF > 1.0) 142 142
FLT8CEE-32W x 4L x 4'-CEE IS CEE L Fluorescent Linear T8 CEE 32 4 4 1 (BF < 0.85) 95 95
FLT8CEE-32W x 4L x 4'-CEE IS CEE N Fluorescent Linear T8 CEE 32 4 4 1 (0.85 < BF < 1.0) 108 108
FLT8CEE-32W x 4L x 4'-CEE PS/PRS DIM CEE H Fluorescent Linear T8 CEE 32 4 4 1 (BF > 1.0) 148 148
FLT8CEE-32W x 4L x 4'-CEE PS/PRS DIM CEE L Fluorescent Linear T8 CEE 32 4 4 1 (BF < 0.85) 93 93
FLT8CEE-32W x 4L x 4'-CEE PS/PRS DIM CEE N Fluorescent Linear T8 CEE 32 4 4 1 (0.85 < BF < 1.0) 113 113
FLT8CEE-32W x 4L x 4'-CEE RS/PRS CEE H Fluorescent Linear T8 CEE 32 4 4 1 (BF > 1.0) 143 143
FLT8CEE-32W x 4L x 4'-CEE RS/PRS CEE L Fluorescent Linear T8 CEE 32 4 4 1 (BF < 0.85) 94 94
FLT8CEE-32W x 4L x 4'-CEE RS/PRS CEE N Fluorescent Linear T8 CEE 32 4 4 1 (0.85 < BF < 1.0) 111 111
FLT8CEE-32W x 6L x 4'-CEE IS CEE H Fluorescent Linear T8 CEE 32 6 4 1 (BF > 1.0) 215 215
FLT8CEE-32W x 6L x 4'-CEE ISDIM CEE H Fluorescent Linear T8 CEE 32 6 4 1 (BF > 1.0) 215 215
FUT12-34W x 2L x 2'-IS N Fluorescent U Tube
T12 34 2 2 1 (0.85 < BF <
0.95) 63 63
FUT12-34W-MG Fluorescent U Tube T12 34 1 1 43 43
FUT12-35W x 2L-MG(E) Fluorescent U Tube T12 35 2 1 72 72
FUT12-35W x 3L-MG(E) Fluorescent U Tube T12 35 3 1 115 115
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 206 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT12-35W-MG Fluorescent U Tube T12 35 1 1 72 82
FUT12-35W-MG(E) Fluorescent U Tube T12 35 1 1 43 43
FUT12-40W x 2L x 2'-IS N Fluorescent U Tube T12 40 2 2 1
(0.85 < BF < 0.95) 63 63
FUT12-40W x 2L-MG Fluorescent U Tube T12 40 2 1 72 86
FUT12-40W x 2L-MG(E) Fluorescent U Tube T12 40 2 1 72 90
FUT12-40W x 3L-MG(E) Fluorescent U Tube T12 40 3 1 115 140
FUT12-40W-MG Fluorescent U Tube T12 40 1 1 43 55
FUT12-40W-MG(E) Fluorescent U Tube T12 40 1 1 43 50
FUT8-17W x 1'-IS H Fluorescent U Tube T8 17 1 1 1
(0.95 < BF < 1.10) 20 20
FUT8-17W x 1'-IS N Fluorescent U Tube T8 17 1 1 1
(0.85 < BF < 0.95) 17 17
FUT8-17W x 1'-IS N T2 Fluorescent U Tube T8 17 1 1 1
(0.85 < BF < 0.95) 16 16
FUT8-17W x 1'-IS R Fluorescent U Tube T8 17 1 1 1
(0.75 < BF < 0.85) 14 14
FUT8-17W x 1'-IS R T2 Fluorescent U Tube T8 17 1 1 1
(0.75 < BF < 0.85) 14 14
FUT8-17W x 1'-IS VH Fluorescent U Tube T8 17 1 1 1 (BF > 1.10) 29 29
FUT8-17W x 1'-IS(E) N Fluorescent U Tube T8 17 1 1 1
(0.85 < BF < 0.95) 16 16
FUT8-17W x 1'-IS(E) R Fluorescent U Tube T8 17 1 1 1
(0.75 < BF < 0.85) 14 14
FUT8-17W x 1'-RS/PRS N Fluorescent U Tube T8 17 1 1 1
(0.85 < BF < 0.95) 18 18
FUT8-17W x 1'-RS/PRS VH Fluorescent U Tube T8 17 1 1 1 (BF > 1.10) 22 22
FUT8-17W x 1'-RS/PRS VR Fluorescent U Tube T8 17 1 1 1 (BF < 0.75) 15 15
FUT8-17W x 1'-RS/PRS(E) N Fluorescent U Tube T8 17 1 1 1
(0.85 < BF < 0.95) 17 17
FUT8-17W x 2L x 1'-IS N Fluorescent U Tube T8 17 2 1 1
(0.85 < BF < 0.95) 34 34
FUT8-17W x 2L x 1'-IS R Fluorescent U Tube T8 17 2 1 1
(0.75 < BF < 0.85) 27 27
FUT8-17W x 2L x 1'-IS VH Fluorescent U Tube T8 17 2 1 1 (BF > 1.10) 41 41
FUT8-17W x 2L x 1'-IS(E) N Fluorescent U Tube T8 17 2 1 1
(0.85 < BF < 0.95) 32 32
FUT8-17W x 2L x 1'-IS(E) R Fluorescent U Tube T8 17 2 1 1
(0.75 < BF < 0.85) 27 27
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 207 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-17W x 2L x 1'-IS(E) VH Fluorescent U Tube T8 17 2 1 1 (BF > 1.10) 40 40
FUT8-17W x 2L x 1'-RS/PRS N Fluorescent U Tube T8 17 2 1 1
(0.85 < BF < 0.95) 35 35
FUT8-17W x 3L x 1'-IS N Fluorescent U Tube T8 17 3 1 1
(0.85 < BF < 0.95) 45 45
FUT8-17W x 3L x 1'-IS R Fluorescent U Tube T8 17 3 1 1
(0.75 < BF < 0.85) 42 42
FUT8-17W x 3L x 1'-IS VH Fluorescent U Tube T8 17 3 1 1 (BF > 1.10) 60 60
FUT8-17W x 3L x 1'-IS(E) R Fluorescent U Tube T8 17 3 1 1
(0.75 < BF < 0.85) 41 41
FUT8-17W x 3L x 1'-IS(E) VH Fluorescent U Tube T8 17 3 1 1 (BF > 1.10) 58 58
FUT8-17W x 3L x 1'-RS/PRS N Fluorescent U Tube T8 17 3 1 1
(0.85 < BF < 0.95) 48 48
FUT8-17W x 3L x 1'-RS/PRS(E) N Fluorescent U Tube T8 17 3 1 1
(0.85 < BF < 0.95) 45 45
FUT8-17W x 4L x 1'-IS N Fluorescent U Tube T8 17 4 1 1
(0.85 < BF < 0.95) 61 61
FUT8-17W x 4L x 1'-IS R Fluorescent U Tube T8 17 4 1 1
(0.75 < BF < 0.85) 56 56
FUT8-17W x 4L x 1'-IS VH Fluorescent U Tube T8 17 4 1 1 (BF > 1.10) 78 78
FUT8-17W x 4L x 1'-IS(E) N Fluorescent U Tube T8 17 4 1 1
(0.85 < BF < 0.95) 61 61
FUT8-17W x 4L x 1'-IS(E) R Fluorescent U Tube T8 17 4 1 1
(0.75 < BF < 0.85) 54 54
FUT8-17W x 4L x 1'-IS(E) VH Fluorescent U Tube T8 17 4 1 1 (BF > 1.10) 77 77
FUT8-17W x 4L x 1'-RS/PRS N Fluorescent U Tube T8 17 4 1 1
(0.85 < BF < 0.95) 62 62
FUT8-17W x 4L x 1'-RS/PRS VH Fluorescent U Tube T8 17 4 1 1 (BF > 1.10) 80 80
FUT8-17W x 4L x 1'-RS/PRS(E) N Fluorescent U Tube T8 17 4 1 1
(0.85 < BF < 0.95) 61 61
FUT8-25W x 1.5'-IS H Fluorescent U Tube T8 25 1 1.5 1
(0.95 < BF < 1.10) 28 28
FUT8-25W x 1.5'-IS N Fluorescent U Tube T8 25 1 1.5 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 1.5'-IS R Fluorescent U Tube T8 25 1 1.5 1
(0.75 < BF < 0.85) 20 20
FUT8-25W x 1.5'-IS VH Fluorescent U Tube T8 25 1 1.5 1 (BF > 1.10) 37 37
FUT8-25W x 1.5'-IS(E) N Fluorescent U Tube T8 25 1 1.5 1
(0.85 < BF < 0.95) 23 23
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 208 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-25W x 1.5'-IS(E) R Fluorescent U Tube T8 25 1 1.5 1
(0.75 < BF < 0.85) 19 19
FUT8-25W x 1.5'-RS/PRS H Fluorescent U Tube T8 25 1 1.5 1
(0.95 < BF < 1.10) 28 28
FUT8-25W x 1.5'-RS/PRS N Fluorescent U Tube T8 25 1 1.5 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 1.5'-RS/PRS VH Fluorescent U Tube T8 25 1 1.5 1 (BF > 1.10) 30 30
FUT8-25W x 1.5'-RS/PRS VR Fluorescent U Tube T8 25 1 1.5 1 (BF < 0.75) 20 20
FUT8-25W x 1.5'-RS/PRS(E) N Fluorescent U Tube T8 25 1 1.5 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 2'-IS N Fluorescent U Tube T8 25 1 2 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 2'-IS R Fluorescent U Tube T8 25 1 2 1
(0.75 < BF < 0.85) 21 21
FUT8-25W x 2'-IS R T2 Fluorescent U Tube T8 25 1 2 1
(0.75 < BF < 0.85) 19 19
FUT8-25W x 2'-IS VH Fluorescent U Tube T8 25 1 2 1 (BF > 1.10) 37 37
FUT8-25W x 2'-IS(E) N Fluorescent U Tube T8 25 1 2 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 2'-IS(E) R Fluorescent U Tube T8 25 1 2 1
(0.75 < BF < 0.85) 20 20
FUT8-25W x 2'-IS(E) VH Fluorescent U Tube T8 25 1 2 1 (BF > 1.10) 37 37
FUT8-25W x 2L x 1.5'-IS N Fluorescent U Tube T8 25 2 1.5 1
(0.85 < BF < 0.95) 45 45
FUT8-25W x 2L x 1.5'-IS R Fluorescent U Tube T8 25 2 1.5 1
(0.75 < BF < 0.85) 39 39
FUT8-25W x 2L x 1.5'-IS VH Fluorescent U Tube T8 25 2 1.5 1 (BF > 1.10) 60 60
FUT8-25W x 2L x 1.5'-IS(E) N Fluorescent U Tube T8 25 2 1.5 1
(0.85 < BF < 0.95) 44 44
FUT8-25W x 2L x 1.5'-IS(E) R Fluorescent U Tube T8 25 2 1.5 1
(0.75 < BF < 0.85) 37 37
FUT8-25W x 2L x 1.5'-IS(E) VH Fluorescent U Tube T8 25 2 1.5 1 (BF > 1.10) 57 57
FUT8-25W x 2L x 1.5'-RS/PRS N Fluorescent U Tube T8 25 2 1.5 1
(0.85 < BF < 0.95) 46 46
FUT8-25W x 2L x 1.5'-RS/PRS VH Fluorescent U Tube T8 25 2 1.5 1 (BF > 1.10) 59 59
FUT8-25W x 2L x 1.5'-RS/PRS VR Fluorescent U Tube T8 25 2 1.5 1 (BF < 0.75) 36 36
FUT8-25W x 2L x 2'-IS H Fluorescent U Tube T8 25 2 2 1
(0.95 < BF < 1.10) 51 51
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 209 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-25W x 2L x 2'-IS N Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 43 43
FUT8-25W x 2L x 2'-IS N T2 Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 43 43
FUT8-25W x 2L x 2'-IS R Fluorescent U Tube T8 25 2 2 1
(0.75 < BF < 0.85) 38 38
FUT8-25W x 2L x 2'-IS VH Fluorescent U Tube T8 25 2 2 1 (BF > 1.10) 58 58
FUT8-25W x 2L x 2'-IS(E) N Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 43 43
FUT8-25W x 2L x 2'-IS(E) R Fluorescent U Tube T8 25 2 2 1
(0.75 < BF < 0.85) 38 38
FUT8-25W x 2L x 2'-RS/PRS H Fluorescent U Tube T8 25 2 2 1
(0.95 < BF < 1.10) 49 49
FUT8-25W x 2L x 2'-RS/PRS N Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 45 45
FUT8-25W x 2L x 2'-RS/PRS N T2 Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 45 45
FUT8-25W x 2L x 2'-RS/PRS N T4 Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 43 43
FUT8-25W x 2L x 2'-RS/PRS R T2 Fluorescent U Tube T8 25 2 2 1
(0.75 < BF < 0.85) 39 39
FUT8-25W x 2L x 2'-RS/PRS VH Fluorescent U Tube T8 25 2 2 1 (BF > 1.10) 59 59
FUT8-25W x 2L x 2'-RS/PRS VR Fluorescent U Tube T8 25 2 2 1 (BF < 0.75) 38 38
FUT8-25W x 2L x 2'-RS/PRS VR T2 Fluorescent U Tube T8 25 2 2 1 (BF < 0.75) 37 37
FUT8-25W x 2L x 2'-RS/PRS(E) N Fluorescent U Tube T8 25 2 2 1
(0.85 < BF < 0.95) 41 41
FUT8-25W x 2'-RS/PRS H Fluorescent U Tube T8 25 1 2 1
(0.95 < BF < 1.10) 27 27
FUT8-25W x 2'-RS/PRS N Fluorescent U Tube T8 25 1 2 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 2'-RS/PRS N T2 Fluorescent U Tube T8 25 1 2 1
(0.85 < BF < 0.95) 22 22
FUT8-25W x 2'-RS/PRS VH Fluorescent U Tube T8 25 1 2 1 (BF > 1.10) 31 31
FUT8-25W x 2'-RS/PRS VR Fluorescent U Tube T8 25 1 2 1 (BF < 0.75) 21 21
FUT8-25W x 2'-RS/PRS VR T2 Fluorescent U Tube T8 25 1 2 1 (BF < 0.75) 19 19
FUT8-25W x 2'-RS/PRS(E) N Fluorescent U Tube T8 25 1 2 1
(0.85 < BF < 0.95) 24 24
FUT8-25W x 3L x 1.5'-IS N Fluorescent U Tube T8 25 3 1.5 1
(0.85 < BF < 0.95) 65 65
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 210 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-25W x 3L x 1.5'-IS R Fluorescent U Tube T8 25 3 1.5 1
(0.75 < BF < 0.85) 61 61
FUT8-25W x 3L x 1.5'-IS VH Fluorescent U Tube T8 25 3 1.5 1 (BF > 1.10) 90 90
FUT8-25W x 3L x 1.5'-IS(E) R Fluorescent U Tube T8 25 3 1.5 1
(0.75 < BF < 0.85) 56 56
FUT8-25W x 3L x 1.5'-IS(E) VH Fluorescent U Tube T8 25 3 1.5 1 (BF > 1.10) 81 81
FUT8-25W x 3L x 1.5'-RS/PRS N Fluorescent U Tube T8 25 3 1.5 1
(0.85 < BF < 0.95) 73 73
FUT8-25W x 3L x 1.5'-RS/PRS VH Fluorescent U Tube T8 25 3 1.5 1 (BF > 1.10) 85 85
FUT8-25W x 3L x 1.5'-RS/PRS VR Fluorescent U Tube T8 25 3 1.5 1 (BF < 0.75) 58 58
FUT8-25W x 3L x 1.5'-RS/PRS(E) N Fluorescent U Tube T8 25 3 1.5 1
(0.85 < BF < 0.95) 70 70
FUT8-25W x 3L x 2'-IS N Fluorescent U Tube T8 25 3 2 1
(0.85 < BF < 0.95) 67 67
FUT8-25W x 3L x 2'-IS R Fluorescent U Tube T8 25 3 2 1
(0.75 < BF < 0.85) 57 57
FUT8-25W x 3L x 2'-IS VH Fluorescent U Tube T8 25 3 2 1 (BF > 1.10) 86 86
FUT8-25W x 3L x 2'-RS/PRS N Fluorescent U Tube T8 25 3 2 1
(0.85 < BF < 0.95) 66 66
FUT8-25W x 3L x 2'-RS/PRS VH Fluorescent U Tube T8 25 3 2 1 (BF > 1.10) 85 85
FUT8-25W x 3L x 2'-RS/PRS VR Fluorescent U Tube T8 25 3 2 1 (BF < 0.75) 58 58
FUT8-25W x 4L x 1.5'-IS N Fluorescent U Tube T8 25 4 1.5 1
(0.85 < BF < 0.95) 88 88
FUT8-25W x 4L x 1.5'-IS R Fluorescent U Tube T8 25 4 1.5 1
(0.75 < BF < 0.85) 81 81
FUT8-25W x 4L x 1.5'-IS VH Fluorescent U Tube T8 25 4 1.5 1 (BF > 1.10) 121 121
FUT8-25W x 4L x 1.5'-IS(E) N Fluorescent U Tube T8 25 4 1.5 1
(0.85 < BF < 0.95) 85 85
FUT8-25W x 4L x 1.5'-IS(E) R Fluorescent U Tube T8 25 4 1.5 1
(0.75 < BF < 0.85) 76 76
FUT8-25W x 4L x 1.5'-IS(E) VH Fluorescent U Tube T8 25 4 1.5 1 (BF > 1.10) 114 114
FUT8-25W x 4L x 1.5'-RS/PRS N Fluorescent U Tube T8 25 4 1.5 1
(0.85 < BF < 0.95) 89 89
FUT8-25W x 4L x 1.5'-RS/PRS VH Fluorescent U Tube T8 25 4 1.5 1 (BF > 1.10) 115 115
FUT8-25W x 4L x 1.5'-RS/PRS(E) N Fluorescent U Tube T8 25 4 1.5 1
(0.85 < BF < 0.95) 87 87
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 211 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-25W x 4L x 2'-IS N Fluorescent U Tube T8 25 4 2 1
(0.85 < BF < 0.95) 86 86
FUT8-25W x 4L x 2'-IS R Fluorescent U Tube T8 25 4 2 1
(0.75 < BF < 0.85) 76 76
FUT8-25W x 4L x 2'-IS VH Fluorescent U Tube T8 25 4 2 1 (BF > 1.10) 116 116
FUT8-25W x 4L x 2'-RS/PRS N Fluorescent U Tube T8 25 4 2 1
(0.85 < BF < 0.95) 87 87
FUT8-25W x 4L x 2'-RS/PRS VH Fluorescent U Tube T8 25 4 2 1 (BF > 1.10) 111 111
FUT8-28W x 2'-IS H Fluorescent U Tube T8 28 1 2 1
(0.95 < BF < 1.10) 32 32
FUT8-28W x 2'-IS N Fluorescent U Tube T8 28 1 2 1
(0.85 < BF < 0.95) 25 25
FUT8-28W x 2'-IS R Fluorescent U Tube T8 28 1 2 1
(0.75 < BF < 0.85) 22 22
FUT8-28W x 2L x 2'-IS H Fluorescent U Tube T8 28 2 2 1
(0.95 < BF < 1.10) 56 56
FUT8-28W x 2L x 2'-IS N Fluorescent U Tube T8 28 2 2 1
(0.85 < BF < 0.95) 48 48
FUT8-28W x 2L x 2'-IS N T2 Fluorescent U Tube T8 28 2 2 1
(0.85 < BF < 0.95) 47 47
FUT8-28W x 2L x 2'-IS R Fluorescent U Tube T8 28 2 2 1
(0.75 < BF < 0.85) 43 43
FUT8-28W x 2L x 2'-IS R T2 Fluorescent U Tube T8 28 2 2 1
(0.75 < BF < 0.85) 41 41
FUT8-28W x 2L x 2'-IS VR Fluorescent U Tube T8 28 2 2 1 (BF < 0.75) 41 41
FUT8-28W x 2L x 2'-RS/PRS N Fluorescent U Tube T8 28 2 2 1
(0.85 < BF < 0.95) 50 50
FUT8-28W x 2L x 2'-RS/PRS N T2 Fluorescent U Tube T8 28 2 2 1
(0.85 < BF < 0.95) 47 47
FUT8-28W x 2L x 2'-RS/PRS VH Fluorescent U Tube T8 28 2 2 1 (BF > 1.10) 62 62
FUT8-28W x 2L x 2'-RS/PRS VR Fluorescent U Tube T8 28 2 2 1 (BF < 0.75) 41 41
FUT8-28W x 2L x 2'-RS/PRS VR T2 Fluorescent U Tube T8 28 2 2 1 (BF < 0.75) 40 40
FUT8-28W x 2'-RS/PRS N Fluorescent U Tube T8 28 1 2 1
(0.85 < BF < 0.95) 26 26
FUT8-28W x 2'-RS/PRS VH Fluorescent U Tube T8 28 1 2 1 (BF > 1.10) 33 33
FUT8-28W x 2'-RS/PRS VR Fluorescent U Tube T8 28 1 2 1 (BF < 0.75) 22 22
FUT8-28W x 3L x 2'-IS H Fluorescent U Tube T8 28 3 2 1
(0.95 < BF < 1.10) 79 79
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 212 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-28W x 3L x 2'-IS N Fluorescent U Tube T8 28 3 2 1
(0.85 < BF < 0.95) 73 73
FUT8-28W x 3L x 2'-IS R Fluorescent U Tube T8 28 3 2 1
(0.75 < BF < 0.85) 64 64
FUT8-28W x 3L x 2'-IS VH Fluorescent U Tube T8 28 3 2 1 (BF > 1.10) 94 94
FUT8-28W x 3L x 2'-RS/PRS N Fluorescent U Tube T8 28 3 2 1
(0.85 < BF < 0.95) 72 72
FUT8-28W x 3L x 2'-RS/PRS VH Fluorescent U Tube T8 28 3 2 1 (BF > 1.10) 91 91
FUT8-28W x 3L x 2'-RS/PRS VR Fluorescent U Tube T8 28 3 2 1 (BF < 0.75) 58 58
FUT8-28W x 4L x 2'-IS H Fluorescent U Tube T8 28 4 2 1
(0.95 < BF < 1.10) 112 112
FUT8-28W x 4L x 2'-IS N Fluorescent U Tube T8 28 4 2 1
(0.85 < BF < 0.95) 94 94
FUT8-28W x 4L x 2'-IS R Fluorescent U Tube T8 28 4 2 1
(0.75 < BF < 0.85) 84 84
FUT8-28W x 4L x 2'-IS VH Fluorescent U Tube T8 28 4 2 1 (BF > 1.10) 125 125
FUT8-28W x 4L x 2'-RS/PRS N Fluorescent U Tube T8 28 4 2 1
(0.85 < BF < 0.95) 96 96
FUT8-28W x 4L x 2'-RS/PRS VH Fluorescent U Tube T8 28 4 2 1 (BF > 1.10) 123 123
FUT8-28W x 4L x 2'-RS/PRS VR Fluorescent U Tube T8 28 4 2 1 (BF < 0.75) 76 76
FUT8-30W x 2'-IS H Fluorescent U Tube T8 30 1 2 1
(0.95 < BF < 1.10) 30 30
FUT8-30W x 2'-IS N Fluorescent U Tube T8 30 1 2 1
(0.85 < BF < 0.95) 24 24
FUT8-30W x 2'-IS R Fluorescent
U Tube T8 30 1 2 1 (0.75 < BF <
0.85) 21 21
FUT8-30W x 2L x 2'-IS H Fluorescent
U Tube T8 30 2 2 1 (0.95 < BF <
1.10) 57 57
FUT8-30W x 2L x 2'-IS N Fluorescent
U Tube T8 30 2 2 1 (0.85 < BF <
0.95) 48 48
FUT8-30W x 2L x 2'-IS R Fluorescent
U Tube T8 30 2 2 1 (0.75 < BF <
0.85) 43 43
FUT8-30W x 2L x 2'-IS VH Fluorescent U Tube T8 30 2 2 1 (BF > 1.10) 62 62
FUT8-30W x 2L x 2'-RS/PRS H Fluorescent
U Tube T8 30 2 2 1 (0.95 < BF <
1.10) 54 54
FUT8-30W x 2L x 2'-RS/PRS N Fluorescent U Tube T8 30 2 2 1
(0.85 < BF < 0.95) 46 46
FUT8-30W x 2'-RS/PRS H Fluorescent U Tube T8 30 1 2 1
(0.95 < BF < 1.10) 30 30
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 213 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-30W x 2'-RS/PRS N Fluorescent
U Tube T8 30 1 2 1 (0.85 < BF <
0.95) 24 24
FUT8-30W x 4L x 2'-IS N Fluorescent
U Tube T8 30 4 2 1 (0.85 < BF <
0.95) 94 94
FUT8-30W x 4L x 2'-IS R Fluorescent
U Tube T8 30 4 2 1 (0.75 < BF <
0.85) 84 84
FUT8-30W x 4L x 2'-IS VH Fluorescent U Tube T8 30 4 2 1 (BF > 1.10) 123 123
FUT8-30W x 4L x 2'-RS/PRS N Fluorescent U Tube T8 30 4 2 1
(0.85 < BF < 0.95) 104 104
FUT8-31W x 2'-IS R Fluorescent U Tube T8 31 1 2 1
(0.75 < BF < 0.85) 27 27
FUT8-31W x 2L x 2'-IS R Fluorescent U Tube T8 31 2 2 1
(0.75 < BF < 0.85) 54 54
FUT8-32W x 2'-IS H Fluorescent U Tube T8 32 1 2 1
(0.95 < BF < 1.10) 35 35
FUT8-32W x 2'-IS N Fluorescent U Tube T8 32 1 2 1
(0.85 < BF < 0.95) 29 29
FUT8-32W x 2'-IS R Fluorescent U Tube T8 32 1 2 1
(0.75 < BF < 0.85) 25 25
FUT8-32W x 2'-IS VH Fluorescent U Tube T8 32 1 2 1 (BF > 1.10) 41 41
FUT8-32W x 2'-IS(E) H Fluorescent U Tube T8 32 1 2 1
(0.95 < BF < 1.10) 34 34
FUT8-32W x 2'-IS(E) N Fluorescent U Tube T8 32 1 2 1
(0.85 < BF < 0.95) 28 28
FUT8-32W x 2'-IS(E) R Fluorescent U Tube T8 32 1 2 1
(0.75 < BF < 0.85) 25 25
FUT8-32W x 2L x 2'-IS H Fluorescent U Tube T8 32 2 2 1
(0.95 < BF < 1.10) 65 65
FUT8-32W x 2L x 2'-IS N Fluorescent U Tube T8 32 2 2 1
(0.85 < BF < 0.95) 59 59
FUT8-32W x 2L x 2'-IS N T2 Fluorescent U Tube T8 32 2 2 1
(0.85 < BF < 0.95) 59 59
FUT8-32W x 2L x 2'-IS N T4 Fluorescent U Tube T8 32 2 2 1
(0.85 < BF < 0.95) 56 56
FUT8-32W x 2L x 2'-IS R Fluorescent U Tube T8 32 2 2 1
(0.75 < BF < 0.85) 52 52
FUT8-32W x 2L x 2'-IS R T4 Fluorescent U Tube T8 32 2 2 1
(0.75 < BF < 0.85) 51 51
FUT8-32W x 2L x 2'-IS VH Fluorescent U Tube T8 32 2 2 1 (BF > 1.10) 73 73
FUT8-32W x 2L x 2'-IS VR Fluorescent U Tube T8 32 2 2 1 (BF < 0.75) 48 48
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 214 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-32W x 2L x 2'-IS(E) H Fluorescent U Tube T8 32 2 2 1
(0.95 < BF < 1.10) 62 62
FUT8-32W x 2L x 2'-IS(E) N Fluorescent U Tube T8 32 2 2 1
(0.85 < BF < 0.95) 55 55
FUT8-32W x 2L x 2'-IS(E) R Fluorescent U Tube T8 32 2 2 1
(0.75 < BF < 0.85) 48 48
FUT8-32W x 2L x 2'-RS/PRS H Fluorescent U Tube T8 32 2 2 1
(0.95 < BF < 1.10) 63 63
FUT8-32W x 2L x 2'-RS/PRS N Fluorescent U Tube T8 32 2 2 1
(0.85 < BF < 0.95) 60 60
FUT8-32W x 2L x 2'-RS/PRS VH Fluorescent U Tube T8 32 2 2 1 (BF > 1.10) 74 74
FUT8-32W x 2L x 2'-RS/PRS VR Fluorescent U Tube T8 32 2 2 1 (BF < 0.75) 47 47
FUT8-32W x 2L x 2'-RS/PRS(E) N Fluorescent U Tube T8 32 2 2 1
(0.85 < BF < 0.95) 58 58
FUT8-32W x 2'-RS/PRS H Fluorescent U Tube T8 32 1 2 1
(0.95 < BF < 1.10) 32 32
FUT8-32W x 2'-RS/PRS N Fluorescent U Tube T8 32 1 2 1
(0.85 < BF < 0.95) 30 30
FUT8-32W x 2'-RS/PRS VH Fluorescent U Tube T8 32 1 2 1 (BF > 1.10) 39 39
FUT8-32W x 2'-RS/PRS VR Fluorescent U Tube T8 32 1 2 1 (BF < 0.75) 25 25
FUT8-32W x 2'-RS/PRS(E) N Fluorescent U Tube T8 32 1 2 1
(0.85 < BF < 0.95) 30 30
FUT8-32W x 3L x 2'-IS H Fluorescent U Tube T8 32 3 2 1
(0.95 < BF < 1.10) 90 90
FUT8-32W x 3L x 2'-IS N Fluorescent U Tube T8 32 3 2 1
(0.85 < BF < 0.95) 89 89
FUT8-32W x 3L x 2'-IS R Fluorescent U Tube T8 32 3 2 1
(0.75 < BF < 0.85) 78 78
FUT8-32W x 3L x 2'-IS VH Fluorescent U Tube T8 32 3 2 1 (BF > 1.10) 109 109
FUT8-32W x 3L x 2'-IS(E) N Fluorescent U Tube T8 32 3 2 1
(0.85 < BF < 0.95) 83 83
FUT8-32W x 3L x 2'-IS(E) R Fluorescent U Tube T8 32 3 2 1
(0.75 < BF < 0.85) 74 74
FUT8-32W x 3L x 2'-RS/PRS N Fluorescent U Tube T8 32 3 2 1
(0.85 < BF < 0.95) 84 84
FUT8-32W x 3L x 2'-RS/PRS VR Fluorescent U Tube T8 32 3 2 1 (BF < 0.75) 68 68
FUT8-32W x 4L x 2'-IS H Fluorescent U Tube T8 32 4 2 1
(0.95 < BF < 1.10) 121 121
FUT8-32W x 4L x 2'-IS N Fluorescent U Tube T8 32 4 2 1
(0.85 < BF < 0.95) 108 108
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 215 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
FUT8-32W x 4L x 2'-IS R Fluorescent U Tube T8 32 4 2 1
(0.75 < BF < 0.85) 96 96
FUT8-32W x 4L x 2'-IS VH Fluorescent U Tube T8 32 4 2 1 (BF > 1.10) 145 145
FUT8-32W x 4L x 2'-RS/PRS N Fluorescent U Tube T8 32 4 2 1
(0.85 < BF < 0.95) 112 112
FUT8-32W x 4L x 2'-RS/PRS VH Fluorescent U Tube T8 32 4 2 1 (BF > 1.10) 144 144
FUT8-32W x 4L x 2'-RS/PRS VR Fluorescent U Tube T8 32 4 2 1 (BF < 0.75) 88 88
HPS-1000W HID
High Pressure Sodium Standard 1000 1 1100 1100
HPS-100W HID
High Pressure Sodium Standard 100 1 130 130
HPS-150W HID
High Pressure Sodium Standard 150 1 188 188
HPS-200W HID
High Pressure Sodium Standard 200 1 250 250
HPS-250W HID
High Pressure Sodium Standard 250 1 295 295
HPS-310W HID
High Pressure Sodium Standard 310 1 365 365
HPS-350W HID
High Pressure Sodium Standard 350 1 405 405
HPS-35W HID
High Pressure Sodium Standard 35 1 46 46
HPS-360W HID
High Pressure Sodium Standard 360 1 414 414
HPS-400W HID
High Pressure Sodium Standard 400 1 465 465
HPS-50W HID
High Pressure Sodium Standard 50 1 66 66
HPS-70W HID
High Pressure Sodium Standard 70 1 95 95
HPS-750W HID
High Pressure Sodium Standard 750 1 840 840
ICH-100W Incandescent Halogen Standard 100 1 100 100
ICH-150W Incandescent Halogen Standard 150 1 150 150
ICH-150W x 2L Incandescent Halogen Mogul 150 2 300 300
ICH-250W Incandescent Halogen Mogul 250 1 250 250
ICH-300W Incandescent Halogen Mogul 300 1 300 300
ICH-35W Incandescent Halogen Standard 35 1 35 35
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 216 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
ICH-42W Incandescent Halogen Standard 42 1 42 42
ICH-45W Incandescent Halogen Standard 45 1 45 45
ICH-45W x 2L Incandescent Halogen Standard 45 2 90 90
ICH-500W Incandescent Halogen Mogul 500 1 500 500
ICH-50W Incandescent Halogen Standard 50 1 50 50
ICH-50W x 2L Incandescent Halogen Standard 50 2 100 100
ICH-52W Incandescent Halogen Standard 52 1 52 52
ICH-55W Incandescent Halogen Standard 55 1 55 55
ICH-55W x 2L Incandescent Halogen Standard 55 2 110 110
ICH-60W Incandescent Halogen Standard 60 1 60 60
ICH-72W Incandescent Halogen Standard 72 1 72 72
ICH-75W Incandescent Halogen Standard 75 1 75 75
ICH-75W x 2L Incandescent Halogen Standard 75 2 150 150
ICH-90W Incandescent Halogen Standard 90 1 90 90
ICH-90W x 2L Incandescent Halogen Standard 90 2 180 180
ICHLV-50W Incandescent Halogen Low Voltage 50 1 60 60
ICMB-100W Incandescent Non-Halogen Medium base 100 1 100 100
ICMB-100W x 2L Incandescent Non-Halogen Medium base 100 2 200 200
ICMB-110W Incandescent Non-Halogen Medium base 110 1 110 110
ICMB-116W Incandescent Non-Halogen Medium base 116 1 116 116
ICMB-120W Incandescent Non-Halogen Medium base 120 1 120 120
ICMB-125W Incandescent Non-Halogen Medium base 125 1 125 125
ICMB-130W Incandescent Non-Halogen Medium base 130 1 130 130
ICMB-135W Incandescent Non-Halogen Medium base 135 1 135 135
ICMB-150W Incandescent Non-Halogen Medium base 150 1 150 150
ICMB-15W Incandescent Non-Halogen Medium base 15 1 15 15
ICMB-15W x 2L Incandescent Non-Halogen Medium base 15 2 30 30
ICMB-160W Incandescent Non-Halogen Medium base 160 1 160 160
ICMB-170W Incandescent Non-Halogen Medium base 170 1 170 170
ICMB-200W Incandescent Non-Halogen Medium base 200 1 200 200
ICMB-20W Incandescent Non-Halogen Medium base 20 1 20 20
ICMB-20W x 2L Incandescent Non-Halogen Medium base 20 2 40 40
ICMB-25W Incandescent Non-Halogen Medium base 25 1 25 25
ICMB-25W x 2L Incandescent Non-Halogen Medium base 25 2 50 50
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 217 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
ICMB-25W x 4L Incandescent Non-Halogen Medium base 25 4 100 100
ICMB-25W x 6L Incandescent Non-Halogen Medium base 25 6 150 150
ICMB-30W Incandescent Non-Halogen Medium base 30 1 30 30
ICMB-34W Incandescent Non-Halogen Medium base 34 1 34 34
ICMB-34W x 2L Incandescent Non-Halogen Medium base 34 2 68 68
ICMB-36W Incandescent Non-Halogen Medium base 36 1 36 36
ICMB-40W Incandescent Non-Halogen Medium base 40 1 40 40
ICMB-40W x 2L Incandescent Non-Halogen Medium base 40 2 80 80
ICMB-42W Incandescent Non-Halogen Medium base 42 1 42 42
ICMB-45W Incandescent Non-Halogen Medium base 45 1 45 45
ICMB-50W Incandescent Non-Halogen Medium base 50 1 50 50
ICMB-50W x 2L Incandescent Non-Halogen Medium base 50 2 100 100
ICMB-52W Incandescent Non-Halogen Medium base 52 1 52 52
ICMB-52W x 2L Incandescent Non-Halogen Medium base 52 2 104 104
ICMB-54W Incandescent Non-Halogen Medium base 54 1 54 54
ICMB-54W x 2L Incandescent Non-Halogen Medium base 54 2 108 108
ICMB-55W Incandescent Non-Halogen Medium base 55 1 55 55
ICMB-55W x 2L Incandescent Non-Halogen Medium base 55 2 110 110
ICMB-60W Incandescent Non-Halogen Medium base 60 1 60 60
ICMB-60W x 2L Incandescent Non-Halogen Medium base 60 2 120 120
ICMB-60W x 3L Incandescent Non-Halogen Medium base 60 3 180 180
ICMB-65W Incandescent Non-Halogen Medium base 65 1 65 65
ICMB-65W x 2L Incandescent Non-Halogen Medium base 65 2 130 130
ICMB-67W Incandescent Non-Halogen Medium base 67 1 67 67
ICMB-67W x 2L Incandescent Non-Halogen Medium base 67 2 134 134
ICMB-69W Incandescent Non-Halogen Medium base 69 1 69 69
ICMB-72W Incandescent Non-Halogen Medium base 72 1 72 72
ICMB-75W Incandescent Non-Halogen Medium base 75 1 75 75
ICMB-75W x 2L Incandescent Non-Halogen Medium base 75 2 150 150
ICMB-80W Incandescent Non-Halogen Medium base 80 1 80 80
ICMB-85W Incandescent Non-Halogen Medium base 85 1 85 85
ICMB-8W Incandescent Non-Halogen Medium base 8 1 8 8
ICMB-8W x 2L Incandescent Non-Halogen Medium base 8 2 15 15
ICMB-90W Incandescent Non-Halogen Medium base 90 1 90 90
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 218 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
ICMB-90W x 2L Incandescent Non-Halogen Medium base 90 2 180 180
ICMB-93W Incandescent Non-Halogen Medium base 93 1 93 93
ICMB-95W Incandescent Non-Halogen Medium base 95 1 95 95
ICMB-95W x 2L Incandescent Non-Halogen Medium base 95 2 190 190
ICMG-1000W Incandescent Non-Halogen Mogul 1000 1 1000 1000
ICMG-100W x 3L Incandescent Non-Halogen Mogul 100 3 300 300
ICMG-100W x 4L Incandescent Non-Halogen Mogul 100 4 400 400
ICMG-100W x 5L Incandescent Non-Halogen Mogul 100 5 500 500
ICMG-120W x 2L Incandescent Non-Halogen Mogul 120 2 240 240
ICMG-135W x 2L Incandescent Non-Halogen Mogul 135 2 270 270
ICMG-1500W Incandescent Non-Halogen Mogul 1500 1 1500 1500
ICMG-150W x 2L Incandescent Non-Halogen Mogul 150 2 300 300
ICMG-150W x 3L Incandescent Non-Halogen Mogul 150 3 450 450
ICMG-2000W Incandescent Non-Halogen Mogul 2000 1 2000 2000
ICMG-200W x 2L Incandescent Non-Halogen Mogul 200 2 400 400
ICMG-250W Incandescent Non-Halogen Mogul 250 1 250 250
ICMG-300W Incandescent Non-Halogen Mogul 300 1 300 300
ICMG-300W x 4L Incandescent Non-Halogen Mogul 300 4 1200 1200
ICMG-400W Incandescent Non-Halogen Mogul 400 1 400 400
ICMG-448W Incandescent Non-Halogen Mogul 448 1 448 448
ICMG-500W Incandescent Non-Halogen Mogul 500 1 500 500
ICMG-60W x 4L Incandescent Non-Halogen Mogul 60 4 240 240
ICMG-60W x 5L Incandescent Non-Halogen Mogul 60 5 300 300
ICMG-67W x 3L Incandescent Non-Halogen Mogul 67 3 201 201
ICMG-750W Incandescent Non-Halogen Mogul 750 1 750 750
ICMG-75W x 3L Incandescent Non-Halogen Mogul 75 3 225 225
ICMG-75W x 4L Incandescent Non-Halogen Mogul 75 4 300 300
ICMG-90W x 3L Incandescent Non-Halogen Mogul 90 3 270 270
INE-10W x 2L Incandescent Non-Halogen Exit 10 2 20 20
INE-15W Incandescent Non-Halogen Exit 15 1 15 15
INE-15W x 2L Incandescent Non-Halogen Exit 15 2 30 30
INE-20W Incandescent Non-Halogen Exit 20 1 20 20
INE-20W x 2L Incandescent Non-Halogen Exit 20 2 40 40
INE-25W Incandescent Non-Halogen Exit 25 1 25 25
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 219 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
INE-25W x 2L Incandescent Non-Halogen Exit 25 2 50 50
INE-34W Incandescent Non-Halogen Exit 34 1 34 34
INE-34W x 2L Incandescent Non-Halogen Exit 34 2 68 68
INE-40W Incandescent Non-Halogen Exit 40 1 40 40
INE-40W x 2L Incandescent Non-Halogen Exit 40 2 80 80
INE-50W x 2L Incandescent Non-Halogen Exit 50 2 100 100
INE-5W Incandescent Non-Halogen Exit 5 1 5 5
INE-5W x 2L Incandescent Non-Halogen Exit 5 2 10 10
INE-6W Incandescent Non-Halogen Exit 6 1 6 6
INE-6W x 2L Incandescent Non-Halogen Exit 6 2 12 12
INE-8W Incandescent Non-Halogen Exit 8 1 8 8
INE-8W x 2L Incandescent Non-Halogen Exit 8 2 15 15
INRB-100W-INDN H Induction Remote Ballasted Standard 100 1 1
(0.95 < BF < 1.10) 107 107
INRB-120W-INDN H Induction Remote Ballasted Standard 120 1 1
(0.95 < BF < 1.10) 127 127
INRB-150W-INDN H Induction Remote Ballasted Standard 150 1 1
(0.95 < BF < 1.10) 160 160
INRB-165W-INDN H Induction Remote Ballasted Standard 165 1 1
(0.95 < BF < 1.10) 173 173
INRB-200W-INDN H Induction Remote Ballasted Standard 200 1 1
(0.95 < BF < 1.10) 210 210
INRB-250W-INDN H Induction Remote Ballasted Standard 250 1 1
(0.95 < BF < 1.10) 263 263
INRB-300W-INDN H Induction Remote Ballasted Standard 300 1 1
(0.95 < BF < 1.10) 315 315
INRB-400W-INDN H Induction Remote Ballasted Standard 400 1 1
(0.95 < BF < 1.10) 420 420
INRB-40W-INDN H Induction Remote Ballasted Standard 40 1 1
(0.95 < BF < 1.10) 45 45
INRB-500W-INDN H Induction Remote Ballasted Standard 500 1 1
(0.95 < BF < 1.10) 525 525
INRB-50W-INDN H Induction Remote Ballasted Standard 50 1 1
(0.95 < BF < 1.10) 55 55
INRB-55W-INDN H Induction Remote Ballasted Standard 55 1 1
(0.95 < BF < 1.10) 61 61
INRB-70W-INDN H Induction Remote Ballasted Standard 70 1 1
(0.95 < BF < 1.10) 77 77
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 220 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
INRB-80W-INDN H Induction Remote Ballasted Standard 80 1 1
(0.95 < BF < 1.10) 86 86
INSB-15W Induction Self-Ballasted Standard 15 1 15 15
INSB-23W Induction Self-Ballasted Standard 23 1 23 23
INSB-40W Induction Self-Ballasted Standard 40 1 40 40
INSB-50W Induction Self-Ballasted Standard 50 1 50 50
LEDEPG-102W LED Exterior Parking Garage 102 1 105 105
LEDEPG-103W LED Exterior Parking Garage 103 1 92 92
LEDEPG-177W LED Exterior Parking Garage 177 1 177 177
LEDEPG-26W LED Exterior Parking Garage 26 1 26 26
LEDEPG-53W LED Exterior Parking Garage 53 1 53 53
LEDEPG-54W LED Exterior Parking Garage 54 1 55 55
LEDEPG-72W LED Exterior Parking Garage 72 1 59 59
LEDEPG-80W LED Exterior Parking Garage 80 1 75 75
LEDEPM-101W LED Exterior Pole Mount 101 1 101 101
LEDEPM-102W LED Exterior Pole Mount 102 1 102 102
LEDEPM-106W LED Exterior Pole Mount 106 1 112 112
LEDEPM-108W LED Exterior Pole Mount 108 1 108 108
LEDEPM-112W LED Exterior Pole Mount 112 1 112 112
LEDEPM-124W LED Exterior Pole Mount 124 1 120 120
LEDEPM-131W LED Exterior Pole Mount 131 1 119 119
LEDEPM-138W LED Exterior Pole Mount 138 1 138 138
LEDEPM-139W LED Exterior Pole Mount 139 1 139 139
LEDEPM-143W LED Exterior Pole Mount 143 1 201 201
LEDEPM-146W LED Exterior Pole Mount 146 1 146 146
LEDEPM-151W LED Exterior Pole Mount 151 1 108 108
LEDEPM-15W LED Exterior Pole Mount 15 1 15 15
LEDEPM-164W LED Exterior Pole Mount 164 1 164 164
LEDEPM-175W LED Exterior Pole Mount 175 1 201 201
LEDEPM-180W LED Exterior Pole Mount 180 1 180 180
LEDEPM-186W LED Exterior Pole Mount 186 1 186 186
LEDEPM-199W LED Exterior Pole Mount 199 1 199 199
LEDEPM-201W LED Exterior Pole Mount 201 1 201 201
LEDEPM-204W LED Exterior Pole Mount 204 1 205 205
LEDEPM-205W LED Exterior Pole Mount 205 1 205 205
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 221 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
LEDEPM-217W LED Exterior Pole Mount 217 1 210 210
LEDEPM-22W LED Exterior Pole Mount 22 1 22 22
LEDEPM-232W LED Exterior Pole Mount 232 1 235 235
LEDEPM-24W LED Exterior Pole Mount 24 1 24 24
LEDEPM-38W LED Exterior Pole Mount 38 1 39 39
LEDEPM-50W LED Exterior Pole Mount 50 1 50 50
LEDEPM-54W LED Exterior Pole Mount 54 1 56 56
LEDEPM-59W LED Exterior Pole Mount 59 1 60 60
LEDEPM-60W LED Exterior Pole Mount 60 1 63 63
LEDEPM-65W LED Exterior Pole Mount 65 1 66 66
LEDEPM-70W LED Exterior Pole Mount 70 1 70 70
LEDEPM-71W LED Exterior Pole Mount 71 1 71 71
LEDEPM-72W LED Exterior Pole Mount 72 1 72 72
LEDEPM-74W LED Exterior Pole Mount 74 1 75 75
LEDEPM-85W LED Exterior Pole Mount 85 1 85 85
LEDEPM-87W LED Exterior Pole Mount 87 1 93 93
LEDEPM-88W LED Exterior Pole Mount 88 1 85 85
LEDEPM-91W LED Exterior Pole Mount 91 1 91 91
LEDESMC-156W LED Exterior Canopy 156 1 157 157
LEDESMC-193W LED Exterior Canopy 193 1 193 193
LEDESMC-73W LED Exterior Canopy 73 1 73 73
LEDIDL-107W LED Interior Downlight 107 1 107 107
LEDIDL-10W LED Interior Downlight 10 1 10 10
LEDIDL-11W LED Interior Downlight 11 1 11 11
LEDIDL-12W LED Interior Downlight 12 1 12 12
LEDIDL-13W LED Interior Downlight 13 1 13 13
LEDIDL-14W LED Interior Downlight 14 1 14 14
LEDIDL-15W LED Interior Downlight 15 1 15 15
LEDIDL-16W LED Interior Downlight 16 1 16 16
LEDIDL-17W LED Interior Downlight 17 1 17 17
LEDIDL-18W LED Interior Downlight 18 1 18 18
LEDIDL-19W LED Interior Downlight 19 1 19 19
LEDIDL-20W LED Interior Downlight 20 1 20 20
LEDIDL-21W LED Interior Downlight 21 1 21 21
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 222 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
LEDIDL-22W LED Interior Downlight 22 1 22 22
LEDIDL-23W LED Interior Downlight 23 1 23 23
LEDIDL-24W LED Interior Downlight 24 1 24 24
LEDIDL-25W LED Interior Downlight 25 1 25 25
LEDIDL-26W LED Interior Downlight 26 1 26 26
LEDIDL-28W LED Interior Downlight 28 1 28 28
LEDIDL-29W LED Interior Downlight 29 1 29 29
LEDIDL-30W LED Interior Downlight 30 1 30 30
LEDIDL-33W LED Interior Downlight 33 1 33 33
LEDIDL-35W LED Interior Downlight 35 1 35 35
LEDIDL-36W LED Interior Downlight 36 1 36 36
LEDIDL-40W LED Interior Downlight 40 1 40 40
LEDIDL-43W LED Interior Downlight 43 1 43 43
LEDIDL-53W LED Interior Downlight 53 1 53 53
LEDIDL-54W LED Interior Downlight 54 1 54 54
LEDIDL-6W LED Interior Downlight 6 1 6 6
LEDIDL-8W LED Interior Downlight 8 1 8 8
LEDIDL-9W LED Interior Downlight 9 1 9 9
LEDIE-2W LED Interior Exit 2 1 2 2
LEDIE-3W LED Interior Exit 3 1 3 3
LEDIHB-150W LED Interior High Bay 150 1 144 144
LEDIHB-160W LED Interior High Bay 160 1 160 160
LEDIRC-10W LED Interior
Refrigerated Cases 10 1 10 10
LEDIRC-15W LED Interior
Refrigerated Cases 15 1 15 15
LEDIRC-18W LED Interior
Refrigerated Cases 18 1 18 18
LEDIRC-20W LED Interior
Refrigerated Cases 20 1 20 20
LEDIRC-7W LED Interior
Refrigerated Cases 7 1 7 7
LEDIRC-8W LED Interior
Refrigerated Cases 8 1 7 7
LEDIRC-9W LED Interior
Refrigerated Cases 9 1 9 9
LEDISI-13W LED Interior Integral Screw-In 13 1 13 13
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 223 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
LEDISI-15W LED Interior Integral Screw-In 15 1 15 15
LEDISI-18W LED Interior Integral Screw-In 18 1 18 18
LEDISI-19W LED Interior Integral Screw-In 19 1 19 19
LEDISI-3W LED Interior Integral Screw-In 3 1 3 3
LEDISI-4W LED Interior Integral Screw-In 4 1 4 4
LEDISI-6W LED Interior Integral Screw-In 6 1 6 6
LEDISI-8W LED Interior Integral Screw-In 8 1 8 8
LEDITL-13W LED Interior Track Lighting 13 1 14 14
LEDITL-16W LED Interior Track Lighting 16 1 15 15
LEDITL-18W LED Interior Track Lighting 18 1 19 19
LEDITL-19W LED Interior Track Lighting 19 1 18 18
LEDITL-23W LED Interior Track Lighting 23 1 23 23
LEDITL-24W LED Interior Track Lighting 24 1 23 23
LEDITL-26W LED Interior Track Lighting 26 1 26 26
LEDITL-38W LED Interior Track Lighting 38 1 37 37
LEDITL-8W LED Interior Track Lighting 8 1 9 9
LEDIUC-10W LED Interior Under-Cabinet 10 1 10 10
LEDIUC-11W LED Interior Under-Cabinet 11 1 11 11
LEDIUC-12W LED Interior Under-Cabinet 12 1 12 12
LEDIUC-13W LED Interior Under-Cabinet 13 1 13 13
LEDIUC-22W LED Interior Under-Cabinet 22 1 22 22
LEDIUC-4W LED Interior Under-Cabinet 4 1 4 4
LEDIUC-5W LED Interior Under-Cabinet 5 1 5 5
LEDIUC-6W LED Interior Under-Cabinet 6 1 6 6
LEDIUC-7W LED Interior Under-Cabinet 7 1 7 7
LEDIUC-8W LED Interior Under-Cabinet 8 1 8 8
LEDIUC-9W LED Interior Under-Cabinet 9 1 9 9
LEDIWP-15W LED Interior Wall Pack 15 1 15 15
LEDIWP-20W LED Interior Wall Pack 20 1 22 22
LEDIWP-22W LED Interior Wall Pack 22 1 22 22
LEDIWP-53W LED Interior Wall Pack 53 1 53 53
LEDIWP-71W LED Interior Wall Pack 71 1 69 69
LEDIWP-88W LED Interior Wall Pack 88 1 85 85
MH-1000W-CWA HID Metal Halide Standard 1000 1 1 1080 1080
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 224 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
MH-100W-CWA HID Metal Halide Standard 100 1 1 128 128
MH-100W-HIDLF HID Metal Halide Standard 100 1 1 112 112
MH-1500W-CWA HID Metal Halide Standard 1500 1 1 1610 1610
MH-150W-CWA HID Metal Halide Standard 150 1 1 190 190
MH-150W-HIDLF HID Metal Halide Standard 150 1 1 168 168
MH-1650W-CWA HID Metal Halide Standard 1650 1 1 1770 1770
MH-175W-CWA HID Metal Halide Standard 175 1 1 215 215
MH-2000W-CWA HID Metal Halide Standard 2000 1 1 2140 2140
MH-250W-CWA HID Metal Halide Standard 250 1 1 295 295
MH-32W-CWA HID Metal Halide Standard 32 1 1 43 43
MH-360W-CWA HID Metal Halide Standard 360 1 1 418 418
MH-400W x 2L-CWA HID Metal Halide Standard 400 2 1 916 916
MH-400W-CWA HID Metal Halide Standard 400 1 1 458 458
MH-50W-CWA HID Metal Halide Standard 50 1 1 72 72
MH-50W-HIDLF HID Metal Halide Standard 50 1 1 55 55
MH-70W-CWA HID Metal Halide Standard 70 1 1 95 95
MH-70W-HIDLF HID Metal Halide Standard 70 1 1 80 80
MH-750W-CWA HID Metal Halide Standard 750 1 1 850 850
MHPS-1000W-SCWA HID Metal Halide Pulse-Start 1000 1 1 1080 1080
MHPS-100W-HIDLF HID Metal Halide Pulse-Start 100 1 1 110 110
MHPS-100W-SCWA HID Metal Halide Pulse-Start 100 1 1 125 125
MHPS-150W-HIDLF H HID Metal Halide Pulse-Start 150 1 1
(0.95 < BF < 1.10) 167 167
MHPS-150W-LR HID Metal Halide Pulse-Start 150 1 1 173 173
MHPS-150W-SCWA HID Metal Halide Pulse-Start 150 1 1 189 189
MHPS-175W-HIDLF HID Metal Halide Pulse-Start 175 1 1 191 191
MHPS-175W-LR HID Metal Halide Pulse-Start 175 1 1 194 194
MHPS-175W-SCWA HID Metal Halide Pulse-Start 175 1 1 208 208
MHPS-200W-HIDLF HID Metal Halide Pulse-Start 200 1 1 219 219
MHPS-200W-LR HID Metal Halide Pulse-Start 200 1 1 218 218
MHPS-200W-RL HID Metal Halide Pulse-Start 200 1 1 244 244
MHPS-200W-SCWA HID Metal Halide Pulse-Start 200 1 1 232 232
MHPS-20W-HIDLF HID Metal Halide Pulse-Start 20 1 1 26 26
MHPS-20W-HIDLF H HID Metal Halide Pulse-Start 20 1 1
(0.95 < BF < 1.10) 23 23
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 225 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
MHPS-250W-LR HID Metal Halide Pulse-Start 250 1 1 272 272
MHPS-250W-RL HID Metal Halide Pulse-Start 250 1 1 298 298
MHPS-250W-SCWA HID Metal Halide Pulse-Start 250 1 1 288 288
MHPS-300W-LR HID Metal Halide Pulse-Start 300 1 1 324 324
MHPS-300W-SCWA HID Metal Halide Pulse-Start 300 1 1 342 342
MHPS-320W-HIDLF HID Metal Halide Pulse-Start 320 1 1 345 345
MHPS-320W-HIDLF H HID Metal Halide Pulse-Start 320 1 1
(0.95 < BF < 1.10) 343 343
MHPS-320W-LR HID Metal Halide Pulse-Start 320 1 1 342 342
MHPS-320W-SCWA HID Metal Halide Pulse-Start 320 1 1 370 370
MHPS-350W-HIDLF HID Metal Halide Pulse-Start 350 1 1 375 375
MHPS-350W-LR HID Metal Halide Pulse-Start 350 1 1 375 375
MHPS-350W-SCWA HID Metal Halide Pulse-Start 350 1 1 400 400
MHPS-39W-HIDLF H HID Metal Halide Pulse-Start 39 1 1
(0.95 < BF < 1.10) 43 43
MHPS-400W-HIDLF HID Metal Halide Pulse-Start 400 1 1 425 425
MHPS-400W-HIDLF H HID Metal Halide Pulse-Start 400 1 1
(0.95 < BF < 1.10) 428 428
MHPS-400W-LR HID Metal Halide Pulse-Start 400 1 1 425 425
MHPS-400W-RL HID Metal Halide Pulse-Start 400 1 1 467 467
MHPS-400W-SCWA HID Metal Halide Pulse-Start 400 1 1 455 455
MHPS-450W-LR HID Metal Halide Pulse-Start 450 1 1 485 485
MHPS-450W-RL HID Metal Halide Pulse-Start 450 1 1 530 530
MHPS-450W-SCWA HID Metal Halide Pulse-Start 450 1 1 514 514
MHPS-50W-SCWA HID Metal Halide Pulse-Start 50 1 1 68 68
MHPS-70W-HIDLF H HID Metal Halide Pulse-Start 70 1 1
(0.95 < BF < 1.10) 77 77
MHPS-70W-SCWA HID Metal Halide Pulse-Start 70 1 1 90 90
MHPS-750W-SCWA HID Metal Halide Pulse-Start 750 1 1 818 818
MHPS-875W-SCWA HID Metal Halide Pulse-Start 875 1 1 940 940
MV-1000W-CWA HID Mercury Vapor Standard 1000 1 1 1100 1100
MV-100W-CWA HID Mercury Vapor Standard 100 1 1 125 125
MV-160W-CWA HID Mercury Vapor Standard 160 1 1 160 160
MV-175W-CWA HID Mercury Vapor Standard 175 1 1 205 205
MV-250W-CWA HID Mercury Vapor Standard 250 1 1 290 290
MV-400W x 2L-CWA HID Mercury Vapor Standard 400 2 1 910 910
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 226 -
Fixture Code Light
Category Fixture Type FixtureType2
Lamp Watt
Lamps QTY
Lamp Length
FT
Ballast QTY
Ballast Factor
Regulation Wattage
Actual Wattage
MV-400W-CWA HID Mercury Vapor Standard 400 1 1 455 455
MV-40W-CWA HID Mercury Vapor Standard 40 1 1 50 50
MV-50W-CWA HID Mercury Vapor Standard 50 1 1 74 74
MV-700W-CWA HID Mercury Vapor Standard 700 1 1 780 780
MV-75W-CWA HID Mercury Vapor Standard 75 1 1 93 93
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 227 -
E. EM&V Sampling Guideline
E.1 Overview
This appendix provides guidelines for defining a sample of equipment for measurement and verification
purposes. In sampling, a large number of similar pieces of equipment affected by the same energy-
efficiency measure can be grouped into usage groups from which samples are selected. These sampling
guidelines are designed to provide assistance in determining the number of sample points that should be
monitored in order to meet the program precision requirements and provide a reliable estimate of
parameters such as annual energy savings or hours of operation. If alternative approaches are proposed,
they must be approved by CenterPoint Energy and based on sound statistical principles.
E.2 Steps in Calculating Sample Size
The number of pieces of equipment requiring monitoring can be calculated according to the following
steps:
E.2.1 Compile measure information
Compile the following information for the equipment affected by the measures. This step is normally
undertaken during the preparation of the Project Application.
Number of Fixtures/Equipment. Identify and document the fixtures/equipment that is affected by
the installation of measures in a survey that includes nameplate data, quantity of equipment, and
location information.
Projected Hours of Operation. Project the average hours of operation of the equipment. It should be
based on the experience of the building operator, on the operation of the affected equipment or even
some preliminary monitoring.
E.2.2 Designate usage group
Next, provide a brief description of the functional use of the space being audited. Functional uses
typically encountered in lighting for commercial and industrial facilities are provided in Section III,
Chapter 2, and Table 2.3 of this manual. Usage groups for non-lighting measures are dependent on type of
application. Sources of information on operating characteristics, other than monitoring, used in defining
usage groups include: (a) operating schedules that provide information on energy consumption or hours of
operation; and (b) type of application or location that provides information on how and when equipment
(e.g., fixtures or motors) are operated. In some instances, area type alone may be insufficient to designate
usage groups. Usage groups may need to be further subdivided if an area type is inherently variable in
nature due to different characteristics of their occupants. For example, some laboratories may have longer
operating hours than others and should be divided into different usage groups (e.g., computer laboratory
lighting operates for 8 hours per day while agriculture laboratories operate 4 hours per day).
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 228 -
E.2.3 Calculate sample sizes
Once the equipment has been divided into usage groups, the total sample size needed for these groupings
can be calculated. This approach produces a sample (with a coefficient of variation of 0.5) expected to
estimate the average hours of operation with sufficient accuracy. The following table shows the number
of samples required in a usage group.
Table D.1: Sample Size based on Usage Group Sampling
Usage
Group
Population
Sample
Size 80/20
Sample Size
80/20, plus
10%
4 3 4
5 4 5
12 6 7
16 7 8
20 7 8
25 8 9
30 8 9
35 8 9
40 9 10
45 9 10
60 9 10
65 9 10
70 9 10
80 10 11
90 10 11
100 10 11
125 10 11
150 10 11
175 10 11
200 10 11
300 10 11
400 11 13
500 11 13
E.3 Over-sampling
The initial sample size should be increased to compensate for potential reductions in the final usable
sample due to equipment failure or loss. Suggested guidelines are that the sample size be increased by 10
percent.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 229 -
F. Program and M&V Definitions
The following are definitions to commonly used terms in the CenterPoint Energy C&I Standard Offer
Program:
Affiliate — (A) a person who directly or indirectly owns or holds at least 5.0% of the voting securities of
an energy efficiency service provider; (B) a person in a chain of successive ownership of at least 5.0% of
the voting securities of an energy efficiency service provider; (C) a corporation that has at least 5.0% of
its voting securities owned or controlled, directly or indirectly, by an energy efficiency service provider;
(D) a corporation that has at least 5.0% of its voting securities owned or controlled, directly or indirectly,
by: (i) a person who directly or indirectly owns or controls at least 5.0% of the voting securities of an
energy efficiency service provider; or (ii) a person in a chain of successive ownership of at least 5.0% of
the voting securities of an energy efficiency service provider; or (E) a person who is an officer or director
of an energy efficiency service provider or of a corporation in a chain of successive ownership of at least
5.0% of the voting securities of an energy efficiency service provider; (F) a person who actually exercises
substantial influence or control over the policies and actions of an energy efficiency service provider; (G)
a person over which the energy efficiency service provider exercises the control described in
subparagraph (F) of this paragraph; (H) a person who exercises common control over an energy
efficiency service provider, where "exercising common control over an energy efficiency service
provider" means having the power, either directly or indirectly, to direct or cause the direction of the
management or policies of an energy efficiency service provider, without regard to whether that power is
established through ownership or voting of securities or any other direct or indirect means; or (I) a person
who, together with one or more persons with whom the person is related by ownership, marriage or blood
relationship, or by action in concert, actually exercises substantial influence over the policies and actions
of an energy efficiency service provider even though neither person may qualify as an affiliate
individually.
Baseline Energy Use: The calculated or measured energy use by a piece of equipment or a site prior to
the implementation of the project measures. Baseline physical conditions, such as equipment counts,
nameplate data, and control strategies, will typically be determined through surveys, inspections, and/or
metering at the site.
Commission: The Public Utility Commission of Texas (PUCT).
Customer: Any individual CenterPoint Energy distribution customer (connected to the CenterPoint
Energy distribution system) distinguished by a unique address or CenterPoint Energy account number
(ESI ID). For purposes of the C&I Standard Offer Program, “site” is synonymous with “customer,” and is
also distinguished by a unique address or CenterPoint Energy account number (ESI ID).
Deemed Savings Estimates: A pre-determined, validated estimate of energy and peak demand savings
attributable to an energy efficiency measure in a particular type of application that a utility may use
instead of energy and peak demand savings determined through measurement and verification activities.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 230 -
Demand Savings: The maximum one-hour average demand reduction (in kW) that occurs when the
system undergoing retrofit is operating at peak conditions during the summer or winter period. The
summer period is defined as weekdays, between the hours of 1 PM and 7 PM from June 1 until
September 30, excluding holidays. The winter peak period is defined as weekdays, from 6 AM to 10 AM
and 6 PM to 10PM, from December 1 through February 28, excluding holidays.
Energy Efficiency Measure (EEM): A system, piece of equipment, or materials that result in either
reduced electric energy consumption, or reduced peak demand, or both.
Energy Efficiency Project: An energy efficiency measure or combination of measures installed under a
Standard Agreement that results in both a reduction in customers’ electric energy consumption and peak
demand, as well as a reduction in energy costs.
Energy Savings Estimates: Energy savings (in kWh) over 12 months derived from metering and/or
calculations in accordance with the provisions of the approved measurement and verification plans, and
documented in the Savings Report.
Project Application (PA): With the PA, CenterPoint Energy will collect a non-refundable deposit equal
to 5% of the incentive funding requested. Approval by CenterPoint Energy of the PA signifies that
funding has been reserved for the project. Project Sponsors must have detailed the expected demand and
energy savings and incentive payments for each project, to be included in the Project Authorization,
which is attached to the signed Standard Offer Program Contract between CenterPoint Energy and the
Project Sponsor.
Full Measurement and Verification: A detailed estimate of savings using a higher level of rigor than in
the deemed savings or simple M&B approaches through the application of metering, billing analysis, or
computer simulation.
Installation Payment: The first of two incentive payments made to a Project Sponsor. The installation
payment is 40% of the total estimated incentive amount.
Installation Report (IR): After approval of the PA and issuance of a Project Authorization, a Project
Sponsor may proceed to install the energy efficiency measures included in an application. After
installation is complete, the Project Sponsor will submit an Installation Report giving details about the
equipment actually installed at each customer site. Once CenterPoint Energy receives the IR, CenterPoint
Energy or its M&V contractor will inspect the customer sites to ensure installation and operation of the
equipment.
Measurement & Verification (M&V): A term referring to all necessary equipment surveys, metering
and monitoring, statistical estimation and analysis, and reporting used to quantify the Energy and Demand
savings resulting from the installation of EEMs. Any M&V approach will need to result in savings
estimates that meet certain accuracy requirements.
Performance Payment: The second of two incentive payments that may be up to 60% of the total
estimated incentive payment.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 231 -
Post-Installation (or Post-Retrofit) Energy Use: The calculated energy usage (or demand) by a piece of
equipment or a site after implementation of the project. Post-installation energy use is verified by the
Sponsor and CenterPoint Energy. They also verify that the reported equipment components or systems
were installed, are operating, and have the potential to generate the predicted savings.
Power Adjustment Factor: A stipulated value used to estimate the reduction in operating hours
associated with a lighting controls measure.
Pre-Installation (or Pre-Retrofit) Energy Use: The calculated energy usage (or demand) by a piece of
equipment or a site before implementation of the project. Pre-installation energy use is verified by the
Sponsor and CenterPoint Energy. They also verify that the existing equipment components or systems
were properly documented and can be retrofitted to generate savings.
Project: The term "project" refers to a single application's set of proposed energy efficiency measures or
other improvements that are necessary to produce energy savings under the program. To be eligible, a
project must be expected to save at least 50 kW of peak demand and must be developed at a CenterPoint
Energy commercial distribution customer's site.
Project Authorization: A document containing project savings and incentive estimates as stated in the
approved PA. The CenterPoint Energy Program Manager and the Project Sponsor will sign the Project
Authorization and attach it to the Standard Offer Contract. The Project Authorization is a signal to the
Project Sponsor to begin the installation of EEMs.
Project-Specific M&V Plan: Plan providing details on how a specific project’s savings will be verified
based on the general M&V approaches contained in this document and the contract between CenterPoint
Energy and Sponsor.
Project Sponsor: Any organization, group, or individual contracting with CenterPoint Energy to provide
energy savings at customer sites under the program(s).
Sampling Plan: A description of the methods for choosing a representative number of pieces of
equipment for monitoring. Often used with lighting retrofits, sample sizes should be generated based on
an 80% confidence interval, precision of 20%, and a coefficient of variation (cv) of 0.5 for the population
indicated.
Savings Report (SR): Pre-specified documentation provided by the Sponsor to document energy savings
achieved for 12 months after project installation. This documentation verifies continued operation of the
installed equipment components or systems and the associated energy savings and provides M&V results.
The energy savings documented in the SR serves as the basis for the Sponsor’s invoice once the report
has been reviewed and approved by CenterPoint Energy.
Simplified M&V: Savings values are based on engineering calculations using typical equipment
characteristics and operating schedules developed for particular applications, with some short-term testing
of simple, long-term metering.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 232 -
Standard Agreement: All Project Sponsors participating in any of the Standard Offer Programs will be
required to sign a Standard Agreement with CenterPoint Energy. The terms of the contract are standard
for all participants, and will include a maximum payment value, a scope of work, a nondisclosure form,
and an installation deadline.
Usage Group: A collection of equipment (e.g., motors or rooms with light fixtures) with similar
operating schedules and functional uses.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 233 -
G. M&V Example
G.1 Project Summary
An owner of a 250,000 square foot office complex is participating in CenterPoint Energy’s C&I Standard
Offer Program. A central chilled water plant cools the facility with a 15-year-old 700-ton centrifugal
chiller. The owner of the building is planning to replace the older chiller with a new, high efficiency unit.
The new unit under consideration is rated with an ARI nominal COP of 6.4 (0.55 kW/Ton). The baseline
and minimum efficiency standards for water-cooled electric chillers are taken from Appendix A, Table 7
of the Standard Cooling Equipment Tables. For a 700-ton water-cooled chiller, the baseline efficiency is
4.7 COP, which is equivalent to 0.748 kW/ton. Likewise, for a 700-ton water-cooled chiller, the minimum
efficiency is 6.1 COP, which is equivalent to 0.577 kW/ton (and the unit qualifies for the program by
having a higher efficiency than the required minimum).
G.2 Assumptions
This M&V plan is written with the following assumptions:
1. The office building is not planning any major projects that would significantly alter the chiller load or
schedule, such as building additions, significant changes in building occupancy, or significant
changes in building schedule.
2. The chiller operating schedule will not change because of this project.
Based on the assumptions and the fact that the new chiller is similar to the existing one (similar size,
water-cooled, no VFD, etc.), the only characteristic needed to estimate the demand and energy savings is
the full load efficiency of each chiller.
G.3 Project Activities
The proposed method for conducting the M&V is from Section III, Chapter 3: Guidelines for
Replacement of Cooling Equipment. Since the simplified guidelines are being used, pre-installation
monitoring is not required. The project does require pre-installation and post-installation inspections,
post-installation monitoring of chiller demand (kW for at least one hour at peak operating conditions),
post-installation monitoring of chiller consumption (kWh for the entire year), an Installation Report, and a
Savings Report. The Project Sponsor shall be responsible for all M&V activities and production of
reports.
G.3.1 Inspections
CenterPoint Energy shall perform a pre-installation inspection to validate assumptions used in the savings
calculations, and verify the existing chiller efficiency. The best source of information for the existing
efficiency is the ARI certification, which accompanies the existing chiller. A post-installation inspection
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 234 -
will be performed to verify that the chiller was installed and is operating as proposed in the approved
Project Application.
G.3.2 Post-Installation Monitoring
Post-installation monitoring of chiller electrical consumption shall be conducted for the entire M&V
period. This monitoring will be accomplished using an ACME Inc., self-contained, three-phase, true RMS
kW logger. The logger collects time stamped data at 15-minute intervals. The logger will be downloaded
monthly and the data validated and stored. In the event that there is a significant gap in the data due to a
logger failure, the process to replace the missing data with interpolated or averaged data will be clearly
documented. The 15-minute time stamped data will be used to satisfy all post-installation monitoring
requirements.
G.3.3 Reports
After the chiller is installed and commissioned, an Installation Report will be produced documenting that
the equipment specified in the PA was installed and is functioning as expected. A Savings Report,
following the guidelines and forms provided in the procedures manual, will be generated and submitted
upon completion of the data collection activities. Savings estimates will be provided in spreadsheet form,
following the template provided in Table 2, below. In addition to the reports, all monitoring data will be
submitted in electronic format for review by CenterPoint Energy.
G.4 Metering Plan
The electrical demand of the proposed (new) chiller will be monitored to support the required M&V
activities. This three-phase load will be monitored using an ACME true RMS kW meter. Current
Transducers will be placed on Breakers 1, 3 and 5 of switch-gear SG-1. These breakers are the A, B, and
C phases of the 460 volt service that supplies the chiller. No other devices draw power from these
breakers.
The ACME meter will record electrical consumption at 15 Minute intervals for the duration of the
monitoring period. This logger is capable of storing 41 days of 15-minute data using a fifteen minute
interval. Data will be downloaded and stored on the first working day of each month to ensure that the
logger does not run out of memory.
G.5 Accuracy Requirements
The ACME logger will be calibrated at the time of installation and then checked for calibration every 6
months. This will be accomplished using a Powersite true RMS meter calibrated at the factory to 2
percent of reading.
G.6 Data Gathering and Quality Control
The data will be collected using quality control procedures for checking reasonableness. Any and all
missing intervals will be replaced either by interpolation or use of average values. CenterPoint Energy
will be notified of any data substitution because of missing data, and the method employed to substitute
the data.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 235 -
G.7 Calculations and Adjustments
The calculations described below will be performed for the Savings Report. The nominal efficiencies of
the chillers are provided again in Table G.1 below.
Table G.1: Proposed and Baseline Chiller Statistics
Chiller Efficiency (COP) Full-Load
kW
Baseline 4.7 524
Proposed 6.4 385
Using the post-installation data described above and the information in Table F.1, the savings will be
calculated using Equations below.
1
COP Baseline
chillernew of COP[kWh] Metering onInstallati Post [kWh] Sav ingsEnergy
1
COP Baseline
chillernew of COP[kW] Measured Demand Max [kW] Sav ings Demand
The ratio of new to existing chiller is computed as 6.4 divided by 4.7 to yield 1.36. Table G.2 below
provides a template to illustrate how monthly savings calculations will be estimated when actual M&V
data are available.
2016 Commercial Standard Offer Program
CenterPoint Energy Appendix - 236 -
Table G.2: Template for Computing Savings
Time of Day
Measured kW
for peak day in
June
(hourly average)
Peak
savings
(kW)
Average
demand profile
in June (kW)
Days of
Operation
for
June
Energy
Consumptio
n (kWh)
Energy
Savings for
June (kWh)
0:00 127.0 45.7 82.6 23 1899 684
1:00 142.4 51.3 92.6 23 2129 767
2:00 134.8 48.5 87.6 23 2016 725
3:00 127.0 45.7 82.6 23 1899 684
4:00 134.8 48.5 87.6 23 2016 725
5:00 127.0 45.7 95.3 23 2191 789
6:00 142.4 51.3 106.8 23 2456 884
7:00 173.2 62.4 129.9 23 2988 1076
8:00 269.6 97.1 202.2 23 4651 1674
9:00 288.8 104 216.6 23 4982 1793
10:00 319.6 115.1 271.7 23 6248 2250
11:00 346.6 124.8 294.6 23 6776 2439
12:00 354.2 127.5 301.1 23 6925 2493
13:00 358.0 128.9 304.3 23 6999 2520
14:00 362.0 130.3 271.5 23 6245 2248
15:00 365.8 131.7 274.4 23 6310 2272
16:00 365.8 131.7 274.4 23 6310 2272
17:00 346.6 124.8 260.0 23 5979 2153
18:00 327.2 117.8 245.4 23 5644 2032
19:00 308.0 110.9 200.2 23 4605 1658
20:00 192.6 69.3 125.2 23 2879 1037
21:00 127.0 45.7 82.6 23 1899 684
22:00 142.4 51.3 92.6 23 2129 767
23:00 115.6 41.6 75.1 23 1728 622
Total
Savings:
131.7 35,248
The illustrative load data represents chiller consumption in the month of June. Energy savings (kWh) will
be estimated in each month by multiplying the average hourly kWh with the number of days in the month.
The energy savings for each month will then be aggregated into an annual savings estimate. The peak data
shall be used to estimate the peak demand savings (kW).