1 Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS Status Report Local Programs Division December 1, 2015 Contact Information Kathleen Davis, Local Programs Director, (360) 705-7871

Transcript of 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department...

Page 1: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

1

Washington State Department of Transportation PEDESTRIAN and BICYCLE &

SAFE ROUTES TO SCHOOL GRANT PROGRAMS

Status Report

Local Programs Division

December 1, 2015

Contact Information Kathleen Davis, Local Programs Director, (360) 705-7871

Page 2: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

2

Washington State Department of Transportation (WSDOT) Local Programs PEDESTRIAN and BICYCLE &

SAFE ROUTES TO SCHOOL GRANT PROGRAMS

Status Report to the Washington State Legislature Introduction The Washington State Department of Transportation is pleased to present this status report for the Pedestrian and Bicycle and Safe Routes to School programs. These programs provide funding for facilities that improve pedestrian and bicycle safety and mobility. They help to further several of WSDOT’s strategic goals, through deliberate investments that advance modal integration and enhance community engagement through stakeholder collaboration. These programs provide funding to cities, counties, tribal nations, state agencies, and other public agencies to support pedestrian and bicycle projects within their respective communities. Pedestrian and Bicycle Program – Status and Past Performance The purpose of the Pedestrian and Bicycle Program is to improve the transportation system to enhance safety and mobility for people who chose to walk and bike. Since the program was created in 2005, (ESSB 6091), almost $55 million has been made available to 65 agencies for 132 projects across the state. That includes $10 million in state funds awarded to 29 projects for the 2015-2017 biennium. Eighty four percent of projects awarded in the first four cycles have been completed. To date, 76 projects have been completed and 2 were cancelled.

The table below includes a list of Pedestrian and Bicycle Program projects that are completed, underway and/or approved for funding. It does not include closed projects reported in previous reports. For more detailed information about these and other state and federal transportation projects administered by WSDOT Local Programs visit the WSDOT Local Programs Project Status Dashboard. If you would like more information about the program or to view previous reports go to the Pedestrian and Bicycle Program Funding website. The next call for projects is being planned for early 2016.

0

5

10

15

20

25

30

05-07 07-09 09-11 11-13 13-15

WSDOT Pedestrian and Bicycle Program Project Status 2005 to 2015

Completed Underway Cancelled

Page 3: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

3

TABLE 1 Pedestrian and Bicycle Program Status 2009 to 2015

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Anacortes 40 Commercial Avenue Planning and Underway

$75,000 Underway Design only project for pedestrian and bicycle improvements.

2015 Auburn 47

22nd Street NE and I street NE Intersection Improvements

$200,000 Approved

Design only project for pedestrian and bicycle intersection improvements.

2011 Auburn 31

Auburn Way South (SR 164) Pedestrian Improvements

$740,830 Underway

The project includes pedestrian lighting, relocating utility poles, landscaped median, mid-block crossing with flashing beacons, countdown pedestrian signal heads, pedestrian safety education campaign, and targeted enforcement.

2013 Bainbridge Island 23

Olympic Drive Non-Motorized Improvements

$764,200 Underway

The project completes a missing link between the ferry terminal and the city center through curb, gutter, sidewalks, ADA improvements, and bicycle facility improvements that may include bike lanes or shared lane markings.

2015 Bellevue 48 140th Avenue NE Pedestrian Crossings

$354,445 Underway

Project includes pedestrian activated crosswalk beacons, curb ramps, median refuge island improvements, street lights and street-landscaping.

2013 Bremerton 26

Washington Avenue/11th Street Sidewalk Connector

$1,700,000 Underway

The project installs curb, gutter, sidewalks, pedestrian scale lighting, street trees, and bike lanes between downtown, housing and the recently completed Manette Bridge.

2015 Clark Co 49 Highway 99 Pedestrian/Bicycle Improvements

$725,000 Approved

Project includes sidewalk, curb ramps, planter strip, mid-block pedestrian crossing with refuge island, accessible pedestrian signal (APS) upgrades, widened bicycle lanes, and a bicycle repair station.

2013 Ellensburg 13 5th Ave Sidewalk $92,000 Completed

The project installs curb, gutter, sidewalk, and ADA improvements connecting downtown, the University, and a regional park.

2015 Ellensburg 13 Ellensburg Bike Boulevard $120,000 Approved

Project includes signs, bicycle lanes, vehicle diverters and median refuge islands.

Page 4: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

4

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2011 Everett 38 North Everett Pedestrian and Bicycle Safety

$410,000 Underway

The project includes curb ramps, radar speed feedback signs, bicycle detection, pedestrian accessible signals, sidewalk, educational materials, safety patrols and speed enforcement.

2011 Everett 21

Evergreen Way (SR99) Airport Rd to 112th Street Pedestrian Safety

$390,000 Underway

The project includes sidewalk reconstruction, curb ramps, speed feedback signs, bicycle detection, accessible pedestrian signals, brochures, events, additional police patrols and speed enforcement.

2013 Everett 38

Everett Downtown Streetscape Improvements - Phase II

$554,520 Approved

The project constructs curb, gutter, wide sidewalk, ADA improvements, curb extensions, street trees, pedestrian scale lighting, and bike lanes in a downtown.

2015 Everett 38 W Marine View Dr. and Alverson Blvd Pedestrian Safety

$400,200 Approved

Project includes pedestrian activated crosswalk beacons, median refuge island, sidewalk, traffic calming channelization, signs and curb ramps.

2015

Fall City Metropolitan Parks District

5 West Side Trail $180,000 Approved

Design only project for pedestrian and bicycle improvements.

2013 Fife 25

Pacific Highway E (SR 99) Pedestrian and Bicycle Safety Improvements

$1,660,800 Approved

The project constructs curb, gutter, sidewalk, ADA improvements, landscape buffer, and bike lane in a commercial and residential area along a state highway.

2015 Island Co 10

Clinton Non-Motorized Improvements: Community Engagement

$120,000 Underway

Design only (90%) project for pedestrian and bicycle improvements.

2015 Issaquah 5

Upgrade Bicycle/Pedestrian Railroad crossing at Front St/Dogwood St

$403,200 Approved

Project includes rail crossing improvements.

2015 Jamestown S'Klallam 24

Hwy 101 Olympic Discovery Trail-Diamond Point Road West Shared Path Safety Project

$290,100 Approved

Project includes a shared-use path.

2009 Jefferson Co. 24 Rick Tollefson Trail

(Chimacum Valley) $441,514 Underway

Project includes a shared use path, two bridges, and a safety education program.

Page 5: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

5

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 Jefferson Co. 24 Quilcene Complete

Streets Project $884,165 Underway

The project constructs curb, gutter, sidewalk, ADA improvements, marked crosswalks, pedestrian scale lighting, bike lanes along a downtown main street highway.

2015 Kennewick 8

Columbia Park East –Bike/ Pedestrian Enhancements

$320,000 Approved

Project includes pavement markings, pathway lights and bike racks.

2011 Kent 5 Kent Kangley Pedestrian Safety $416,200 Underway

The project includes two pedestrian crossings, pedestrian refuge islands, flashing beacons, crosswalks, curb ramps, accessible signals, countdown pedestrian signals, pedestrian safety campaign and materials, and pedestrian enforcement patrols.

2013 King Co. 43

King County Bike Share Program Launch University District (Target Area B)

$750,000 Underway

The project installs bike share stations in the University District, a mixed use area.

2015 Kirkland 1,45 Juanita Drive Quick Wins $62,605 Underway

Project includes pedestrian walkways, widened sidewalk, buffered bicycle lanes, bike box, pedestrian activated crosswalk beacons, shared-use path, signs and street lights.

2015 Kirkland 45,48

Lakefront Pedestrian and Bicycle Improvements

$10,600 Underway

Project includes curb ramps, street lights, pedestrian activated crosswalk beacons, bike lanes, bike boxes, bicycle lane colored pavement markings, signs, channelization and a buffered bike lane.

2011 Lacey 22 College Street Corridor - Phase 1 $1,750,000 Underway

The project includes a roundabout, sidewalks, curb ramps, pedestrian lighting, landscaping, education program expansion, enforcement, pace car campaign.

2009 Leavenworth 12 Chumstick Multi-Use Trail $200,000 Underway

Project includes a shared use trail, landscaping, retaining walls, sidewalk, ADA curb ramps, striping, signs, crosswalk markings, speed feedback signs, and flashing beacons.

2015 Leavenworth 12 LINK Crossing $281,000 Approved

Project includes pedestrian activated crosswalk beacons, curb ramps, median refuge island, crosswalk markings and street lights.

Page 6: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

6

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Leavenworth 12 Gustav's Crosswalk $222,500 Approved Project includes crosswalk markings, signs and pedestrian activated crosswalk beacons.

2011 Longview 19 15th Avenue at Douglas and Hemlock

$200,000 Completed

The project includes curb extensions, curb ramps, countdown pedestrian signal heads with audible warnings, educational materials, and enhanced enforcement.

2015 Longview 19 Mark Morris Traffic Signal $294,000 Approved Project includes a traffic signal and

intersection upgrades.

2015 Lummi Nation 42

Kwina Drive Sidewalk-South Side

$276,521 Approved Project includes a side path, street lights, swale and signs.

2015 Lummi Nation 42 Lummi Shore Drive

Sidewalk $615,000 Approved Project includes a shared-use path, street lights, landscaping, swale and signs.

2015 Lummi Nation 42 Gooseberry Point

Pedestrian Project $894,219 Approved

The project includes pedestrian walkways, pedestrian activated crosswalk beacons, retaining wall and landscaping.

2015 Marysville 38

Grove Street Pedestrian and Bicycle Improvements

$276,500 Underway

Project includes curb, gutter, sidewalk, curb extensions, bicycle lanes, and rail crossing improvements.

2013 Newport 7

SR 2: 4th Street to 7th Street Non-Motorized Transportation Improvements

$646,200 Completed

The project constructs curb, gutter, sidewalk, ADA improvements, marked crosswalks at intersections, pedestrian scale lighting, and bike lanes connecting housing, schools and downtown along a state highway.

2013 Omak 7

Main Street/SR 215 & SR 155 Complete Street Project

$340,425 Underway

The project installs curb extensions at three intersections, pedestrian scale lighting, bike racks, and fill in gaps in curb, gutter, and sidewalk along a main street highway.

2015 Port Angeles 24

Waterfront and Olympic Discovery Trail: Valley Creek – 10th & Milwaukee

$200,000 Approved

Design only project for pedestrian and bicycle improvements.

2013 Redmond 48 Redmond Central Connector Phase 2 $500,000 Underway

The project constructs a shared-use path, ADA improvements, and way finding signs connecting downtown, housing, employment and a university.

2015 Renton 37 Lake Washington Loop Trail $426,000 Approved

Design only project for pedestrian and bicycle improvements.

Page 7: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

7

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2011 Seattle 37 Rainier Beach Pedestrian Improvements

$275,000 Underway

The project includes re-channelization from 4-lanes to 3-lanes with bike lanes and parking, signal timing adjustments, education and enforcement campaign.

2011 Seattle 37 South Fisher Place at Rainier Ave S Sidewalk

$509,000 Underway

The project includes sidewalk, pedestrian lighting, landscaping, group walks, and targeted speed enforcement.

2011 Seattle 46 Aurora Ave N and N 95 St New Signal $585,000 Completed

The project includes a traffic signal, pedestrian countdown signals, curb ramps, marked crosswalks, public awareness campaign, and crosswalk enforcement.

2011 Seattle 1,2 2011 Pedestrian Safety Education Campaign

$260,000 Underway

The project is a pedestrian safety education campaign rolled out during the holiday season, multiple media outlets, and crosswalk compliance operations.

2011 Seattle 36,37 2011 Accessible Pedestrian Signals $246,000 Underway

The project includes accessible signals and curb ramps at 14 locations, education and enforcement campaign.

2013 Seattle 46 Delridge Multimodal Path $337,000 Underway

The project constructs a shared-use path and ADA improvements, relocates street lights, and installs a raised intersection crossing for trail users in a mixed-use area.

2013 Shoreline 32 Interurban Trail/Burke-Gilman Connectors

$540,000 Underway

The project completes a missing link between the ferry terminal and the city center through curb, gutter, sidewalks, ADA improvements, and bicycle facility improvements that may include bike lanes or shared lane markings.

2013 Snohomish 44 Second & Lincoln Traffic Signal $760,000 Completed

The project installs curb extensions, a shared-use path, traffic signal system, ADA improvements, pedestrian scale lighting, curb, gutter, sidewalk, and stamped concrete paving at a crossing between residential and downtown.

2015 Snohomish Co 10,39

Whitehorse Trail Pedestrian Trail Underpasses SR 530

$1,100,000 Approved

Project includes two pedestrian underpasses.

Page 8: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

8

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 Snoqualmie 5 Downtown Redevelopment Phase 2

$1,885,000 Underway

The project constructs curb, gutter, wide sidewalk, ADA improvements, pedestrian scale lighting, shared-use path, shared lane markings, signage, and bicycle parking connecting downtown, housing and existing connections.

2011 Spokane 3 Nevada St. Pedestrian/Bike Safety

$100,460 Completed

The project includes school zone flashers, sidewalk, signage, crosswalk relocation, safety education, health benefits outreach, and traffic enforcement.

2011 Spokane 3 North Division Pedestrian/Bike Safety

$214,035 Completed

The project includes sidewalk, crosswalks, pedestrian refuge islands, public service safety segments, health benefits outreach, informational handouts, and traffic enforcement.

2011 Spokane 3 Monroe St. Pedestrian/Bike Safety

$80,600 Completed

The project includes countdown pedestrian signals, public service safety segments, health benefits outreach, and traffic enforcement.

2011 Spokane 3 Browne St/Division Couplet Pedestrian/Bike

$410,000 Underway

This project includes curb extensions, pedestrian countdown signal heads, curb ramps, public service safety segments, health benefits outreach, and traffic enforcement.

2015 Spokane 3 North Monroe Street Road Diet $326,800 Approved

Project includes a reduction in the number of travel lanes, sidewalk widening, and curb extensions.

2015 Spokane 3 Sprague Avenue Pedestrian Safety $1,586,821 Approved

Project includes pedestrian refuge islands, and street lights.

2015 Tumwater 22 Capitol Boulevard at U St Pedestrian Improvement

$96,000 Approved

Project includes crosswalk markings, signs, median refuge island, curb ramps, pedestrian activated crosswalk beacons, and street lights.

2011 Vancouver 17

Mill Plain Blvd - Hybrid Pedestrian Beacons and Lead Pedestrian Intervals

$499,000 Completed

The project includes two flashing signal beacons, timing adjustments, pedestrian and bicycle safety classes, public outreach, and speed enforcement.

2015 Wenatchee 12 First Street Bikeway $25,000 Approved

Design only project for pedestrian and bicycle improvements.

2013 Wilkeson 31 Foothills Trail Extension $475,000 Approved

This project constructs curb, gutter, sidewalk, ADA improvements, bike lanes, shared-use path, refurbish a rail trestle for shared-use path, install pedestrian scale lighting, and marked crosswalks along a downtown main street highway.

Page 9: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

9

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 WSDOT (NWR) 23

SR 104/Edmonds - Mid Block Pedestrian Crossing

$465,000 Underway

The project installs a pedestrian hybrid beacon at a mid-block pedestrian crossing with median refuge, ADA improvements, crosswalk striping, raised pavement markers and signage in a mixed-use area.

2015 WSDOT-- SW 49

SR 14/Columbia House Blvd Westbound On Ramp-Bicycle/Pedestrian Signal

$22,000 Underway

Project includes pedestrian activated crosswalk beacons and narrows the travel lane.

2015

WSDOT/ Washington Bikes/ Cascade

N/A

Permanent Statewide Bike Counter Network Establishment

$302,698 Approved

Project includes permanent electronic bicycle counters across Washington state.

Page 10: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

10

Safe Routes to School Program – Status and Past Performance The purpose of the Safe Routes to School Program is to increase the number of children walking and biking to school safely. Since this program was created in 2005, (ESSB 6091) funding requests have consistently exceeded funding amounts provided. Only about 30% of the $242 million requested over the last 10 years has been awarded.

Between 2005 and 2013 approximately $71 million has been made available to 113 agencies for 182 projects across the state. That includes the $20 million in state and federal funds awarded to 44 projects this summer for the 2015-2017 biennium. Eighty six percent of projects awarded in the first four cycles have been completed. To date, 91 Safe Routes to School projects are complete and one was cancelled.

The table below includes a list of Safe Routes to School Program projects that are completed, underway and/or approved for funding. It does not include closed projects reported in previous reports. For more detailed information about these and other state and federal transportation projects administered by WSDOT Local Programs visit the WSDOT Local Programs Project Status Dashboard. If you would like more information about the program go to the WSDOT Safe Routes to School website. The next call for projects is being planned for early 2016.

05

101520253035404550

05-07 07-09 09-11 11-13 13-15 15-17

WSDOT Safe Routes to School Program Project Status 2005 to 2015

Completed Underway Cancelled

Page 11: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

11

TABLE 2 Safe Routes to School Program Status

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2011 Airway Heights 6

Sunset Elementary Safe Routes Grant 2010

$223,692 Underway

The project includes sidewalk, flashing beacons, fence, crosswalk markings, bicycle and pedestrian safety classes, materials and events, speed feedback signs, and additional enforcement.

2015 Algona 30 Milwaukee Avenue Sidewalks

$731,413 Approved The project includes sidewalk replacement.

2013 Anacortes 40

Anacortes Safe Routes to Schools - Covered Bike Parking and Mid-Block Crossing

$221,000 Underway

The project includes mid-block crossing, pavement markings, flashing beacons, curb extensions, curb ramps, covered bike parking, drainage, street lighting, educational materials and events, and emphasis patrols.

2011 Auburn 47

Lea Hill Safe Walking/Cycling Route Improvements

$398,500 Underway

The project includes sidewalk, bike lanes, bicycle racks, curb ramps, pedestrian countdown signal, crosswalk, public education materials, bicycle and pedestrian safety classes and events, crossing guards, increased traffic enforcement, photo speed enforcement, and speed feedback signs.

2013 Battle Ground 18

School Zone Safety Improvements, City Wide Battle Ground

$66,206 Completed

The project includes crosswalk pavement markings, rear flashing beacon strobe lights, flashing beacon, guided walk groups and crossing guards, student/parent education, and speed emphasis patrols.

2013 Bellevue 41

West Lake Sammamish Parkway Sidewalk Connection

$260,000 Underway

The project includes sidewalk, curb, gutter, planter strip, educational materials and events, walking school bus, and emphasis patrols.

2013 Bellingham 42 Carl Cozier Safe Routes to School Program

$237,300 Underway

The project includes sidewalk, curb, gutter, drainage, curb ramps, crosswalk markings and signage, curb extensions, flashing beacons, bicycle racks, educational materials and events, increased school zone crosswalk and speed emphasis patrols.

Page 12: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

12

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Bellingham 42 W. Maplewood Multimodal Improvements

$895,000 Approved

The project includes bicycle lanes, sidewalks, intersection bicycle markings, curb, gutter, curb ramps and street lights.

2015 Bellingham 42 Cordata Safe Routes to School Program

$778,127 Approved

The project includes bike lane, sidewalk, planter strip, curb, gutter, boardwalk stream crossing, street lights, education encouragement, walking school bus and enforcement.

2015 Bremerton 26 Crownhill Elementary Sidewalks

$545,000 Approved

The project includes sidewalk, curb, gutter, crosswalk markings, signs, and pedestrian activated crosswalk beacons.

2013 Brewster 12 Ferry Street Safety Improvements

$282,700 Underway

The project includes sidewalk, curb, gutter, curb ramps, street lights, drainage, flashing beacons, and emphasis patrols.

2015 Carnation 5 Spilman Avenue Walkway Project $290,000 Underway

The project includes sidewalk, drainage swale, crosswalk markings, signs, and pedestrian activated crosswalk beacons.

2011 Castle Rock 20

Castle Rock's Safe Routes to School Improvements

$322,000 Completed

The project includes sidewalk, path, crosswalk with signal, signage, shelter, pedestrian and bicycle safety classes, events and materials, crossing guards, photo speed enforcement, crosswalk enforcement and additional traffic enforcement.

2011 Chelan 12

Bradley Street - Morgen Owings Elementary to Gibson Ave

$423,413 Completed

The project includes shared use paths, on street parking, narrow/reduce travel lane width, planter strips, bike racks, crosswalks, curb extensions, flashing beacons, pedestrian and bicycle safety classes and materials, parent education, additional enforcement and crossing guards.

2015 Chelan County 12

South Wenatchee Pedestrian Safety Improvements, Phase II

$131,600 Underway

The project includes sidewalk, curb, gutter, crosswalk markings, signs, street lights, pedestrian activated crosswalk beacons, no parking zone, education, encouragement and use of a speed feedback signs.

Page 13: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

13

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 Clark County 49

Sacajawea Elementary Pedestrian Safety

$302,000 Completed

The project includes sidewalk, curb, gutter, crosswalk pavement markings, crossing guard safety equipment, walking school bus program, educational materials and events, speed feedback signs and emphasis patrols.

2015 Des Moines 33 Woodmont School Walkway Improvements

$431,000 Approved

The project includes sidewalk, curb, gutter, stop bar markings, drainage and utility improvements curb ramps, street lights and speed feedback signs.

2013 Edmonds 32

15th St. SW from Edmonds Way (SR-104) to 8th Ave. S

$374,000 Underway

The project includes sidewalk, curb, gutter, drainage, curb ramps, sharrow markings, flashing beacon, bicycle rack, educational materials and events, and emphasis patrols.

2013 Edmonds 32

238th St. SW from 100th Ave. W to 104th Ave. W

$591,000 Underway

The project includes sidewalk, curb, gutter, drainage, curb ramps, sharrow markings, flashing beacon, bicycle rack, educational materials and events, and emphasis patrols.

2013 Edmonds 21 Madrona Elementary Walkway Project

$494,000 Underway

The project includes sidewalk, curb, gutter, drainage, curb ramps, sharrow markings, flashing beacon, educational materials and events, and emphasis patrols.

2015 Ellensburg 13

Capitol Ave and Sampson St Pedestrian Improvements

$165,000 Approved

The project includes sidewalk, planter strip, curb, gutter, street lights, curb extensions and drainage improvements.

2009 Everett 38

Horizon Elementary School Walk Route Safety

$415,000 Underway

Project includes overhead school zone signs, speed feedback signs, pedestrian countdown signal heads, lighting, pedestrian and bicycle safety education, and increased enforcement.

2013 Everett 38 Hawthorne Elementary Safe Routes to School

$256,000 Underway

The project includes sidewalk, curb, gutter, crosswalk markings, curb ramps, flashing beacon, educational materials and events, and speed emphasis patrols.

2011 Federal Way 30

Lakota Middle School-Safe Routes to School Program

$1,039,080 Completed

The project includes a traffic signal, pedestrian countdown signals, pavement markings, curb ramps, sidewalk, planter strip, bike lanes, lighting, bicycle and pedestrian safety classes, events and materials, and crosswalk enforcement.

Page 14: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

14

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 Federal Way 30 Federal Way Pedestrian Connection

$775,000 Underway

The project includes sidewalk, curb, gutter, curb ramps, planter strips, sharrow markings, street lights, roundabout, and flashing beacons.

2013 Federal Way 30

Lakota Middle School - 13th Avenue SW Sidewalk Connection

$270,119 Completed

The project includes sidewalk, curb, gutter, curb ramps, school zone flashing beacons, website article, press release, assembly with in classroom follow up discussion, educational materials, pedestrian decoy operation, and school zone speed enforcement.

2015 Federal Way 30

Sacajawea Middle School Safe Routes to School

$1,200,000 Underway

The project includes sidewalk, curb, gutter, planter strip, bike lane, education, encouragement and enforcement.

2015 Ferndale 42

Washington Street Pedestrian and Bicycle Safety Improvements

$200,000 Approved

The project includes sidewalk, curb, gutter, planter strips, curb extensions, pedestrian activated crosswalk beacons, driveway narrowing, parking removal, street lights, and crosswalk markings.

2015 Grant County 13 Endeavor Middle School Sidewalk $135,200 Approved

The project includes pedestrian activated crosswalk beacon, crosswalk markings, and curb ramps.

2012 Jefferson County 24

SR 19 Pedestrian Crossing Improvement, Trail Connection, and Student Encouragement Project

$438,669 Completed

The project includes multi-use path, flashing beacons, signage, bike racks, parent and student pedestrian and bicycle safety classes, events and materials, and crosswalk enforcement.

2015 Kenmore 46

Kenmore NE 202nd Street Safe Routes to School

$814,056 Underway

The project includes sidewalk, curb, gutter, bike lane, and crosswalk markings

2009 Kirkland 48 Making the Connection $498,000 Underway

Project includes sidewalk, pedestrian safety education and events, radar speed feedback trailer and increased enforcement.

2011 Kirkland 48 Lakeview Elementary $348,000 Underway

The project includes sidewalk, crosswalk, flashing beacons, curb ramps, bicycle racks, bicycle and pedestrian safety classes, and additional enforcement.

2011 Kirkland 48 Peter Kirk Elementary $456,600 Underway

The project includes sidewalk, curb ramps, crosswalk, bike racks, maps, walk to school day events and materials, and increased enforcement.

Page 15: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

15

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 Lake Forest Park 32

NE 178th Street Sidewalk Improvements

$569,000 Underway

The project includes sidewalk, curb, gutter, curb ramps, removal of guardrail, curb extensions, crosswalk markings, flashing beacons, signage, bike lanes, bicycle racks, educational materials and events, and crossing guard equipment.

2015 Lake Stevens 44

91st Avenue SE Non-Motorized Facility Improvement Project

$483,200 Approved

The project includes sidewalk, curb, gutter, bike lanes, crosswalk markings, crosswalk flashing beacons, drainage improvements, signs, education, walking school bus and enforcement.

2011 Lakewood 29

Dower Elementary - Safe Routes to School Project

$257,000 Completed

The project includes sidewalk, curb ramps, flashing beacons, walk to school day events and materials, maps, and additional enforcement.

2015 Lakewood 29 Steilacoom Blvd. SW: Weller to Phillips

$450,000 Approved

The project includes sidewalk, curb, gutter, bike lane, street lights, and drainage improvements, traffic signal improvements, and school zone photo enforcement.

2015 Lakewood 29 Phillips Road Sidewalk Improvements

$500,000 Approved

The project includes sidewalk, curb, gutter, bike lanes, street lights and pedestrian activated crosswalk beacons.

2015 Lakewood 29 John Dower Sidewalk Improvements

$550,000 Approved

The project includes sidewalk, curb, gutter, street lights, shared use travel lane, drainage improvements and pedestrian activated crosswalk beacons.

2011 Leavenworth 12 Cascade School District Safe Routes Program

$338,000 Underway

The project includes sidewalk, curb ramps, signage, pavement markings, intersection re-alignment, no parking zones, school zone flashing beacons, pedestrian and bicycle safety seminars, crossing guard training, flagger safety classes, bicycle safety education, walking school bus, radar speed feedback signs and additional enforcement.

2015 Longview 20

Longview School Zone Review Recommendations

$90,000 Approved

The project includes school speed zones signs with flashing beacons and pedestrian activated crosswalk beacons.

2013 Lynden 42 Jim Kaemingk Senior Trail Extension

$273,000 Underway

The project includes shared use path, sidewalk, curb, gutter, planter strip, speed feedback signs with flashing beacons, and educational materials and events.

Page 16: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

16

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2011 Lynnwood 32

Creating Walking and Cycling Paths in Lynnwood

$250,000 Completed

The project includes sidewalk, curb ramps, bike lanes, crossing flags, lighting, flashing beacons, pedestrian and bicycle safety classes and events, extra traffic enforcement and crosswalk enforcement, and speed feedback signs.

2015 Mabton 15 Mabton Safe Routes to School $560,000 Approved

The project includes sidewalk, curb, gutter, curb extensions, curb ramps, crosswalk markings, speed feedback signs, education, encouragement, walking school bus and enforcement.

2015 Marysville 38

Sunnyside Elementary Safe Routes to School Project

$205,000 Approved

The project includes sidewalk, planter strip, curb, gutter, curb ramps, and school zone beacons with speed feedback signs.

2015 Marysville 38

Marshall Elementary Safe Routes to School Project

$315,000 Underway

The project includes sidewalk, planter strip, bicycle lane, curb, gutter, curb ramps, pedestrian activated flashing beacon, school zone beacons with vehicle speed feedback signs, and street lights.

2015 Mattawa 13 William Avenue Sidewalk Improvements

$265,000 Approved

The project includes sidewalk, curb, gutter, planter strip/swale, crosswalk markings, signs, and street lights.

2013 Mount Vernon 10,40

Bike Walk Mount Vernon 2013 $389,500 Underway

The project includes bike lanes, a bike signal, a trail crossing improvement, a roundabout, and enforcement.

2015 Ocean Shores 24

Ocean Shores Safe Routes to School Point Brown South

$770,200 Approved

The project includes shared-use path, crosswalk markings, signs, street lights, pedestrian activated crosswalk beacons, education, encouragement and enforcement.

2013 Olympia 22 22nd Avenue Sidewalk Project $1,076,000 Underway

The project includes sidewalk, planter strip, education materials and events, walking school bus.

2015 Olympia 22 Quince Street Sidewalk $203,200 Underway

The project includes sidewalk, curb, gutter, school zone flashing beacons, education and encouragement.

2013 Port Townsend 24

Sheridan Street Sidewalk and Crossing Improvements

$497,913 Underway

The project includes sidewalk, curb, gutter, curb extensions, planter strips, crosswalk markings, signage, educational materials and events, and emphasis patrols.

Page 17: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

17

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2011 Poulsbo 23

North Kitsap Schools Poulsbo Campus Complex Safe Routes Program

$298,000 Underway

The project includes sidewalk, curb ramps, bicycle lane, narrow/reduce travel lane width, flashing beacons, pedestrian railing, pavement markings, walk and bike to school day events and materials, maps, speed feedback signs, and additional enforcement.

2013 Puyallup 25

Meeker Elementary, Aylen Junior High and Stewart Elementary School Crosswalk Improvements

$210,000 Underway

The project includes flashing beacons, street lights, curb ramps, educational materials and events, and speed emphasis patrols.

2013 Quincy 13 Quincy Valley K-7 Pathway $292,000 Underway

The project includes shared use path, bollards, enclose irrigation ditch, fencing, landscaping, bicycle racks, educational materials and events, walking school bus, adult crossing guard equipment, and emphasis patrols.

2015 Reardan 13 Ball-fields Safe Walkway Project, Phase 1

$302,027 Approved

The project includes a pedestrian walkway, crosswalk markings, signs, and pedestrian activated flashing beacon.

2015 Redmond 48

Redmond-Woodinville Road Safe Route Project

$550,000 Approved

The project includes sidewalk, bike lane, separation wall, education and enforcement.

2015 Redmond 48 134th Avenue Safe Route Project

$400,000 Approved The project includes sidewalk, curb and gutter.

2015 Renton 37 116th Ave SE $111,000 Approved The project includes sidewalk and planter strip.

2015 Rosalia 9

Josephine Avenue Sidewalk, Rosalia, WA

$243,559 Approved

The project includes sidewalk replacement, retaining wall, curb ramps, crosswalk markings and signs.

2013 Seattle 46 Beach Square Safe Routes to School

$248,000 Underway

The project includes school speed zone signage, flashing beacons, crosswalk markings and stop bar, pedestrian refuge island, curb extensions, street lighting, pedestrian countdown signals, educational materials and events, and speed control campaign.

2013 Seattle 46

Beacon Hill Neighborhood Greenways Go to School

$597,000 Underway

The project includes a shared use path, educational materials and events, and a speed control campaign.

Page 18: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

18

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2013 Seattle 36,46

Greenwood Neighborhood Greenways Go to School

$153,000 Underway

The project includes curb extensions, rectangular rapid flashing beacons, educational materials and events, speed enforcement, speed feedback signs, and a speed control campaign.

2013 Seattle 46

Wedgwood Elementary Children and Neighbors

$439,000 Underway

The project includes sidewalk, curb, gutter, planter strip, drainage, educational materials and events, speed feedback signs, and emphasis patrols.

2015 Seattle 37

Rainier View Elementary School Safety Project

$420,000 Approved

The project includes sidewalk, planter strip, curb extensions, intersection re-alignment, education, encouragement, walking school bus and enforcement.

2013 Sedro Woolley 39

SR9 Pedestrian/Bicycle Safety Improvements

$300,000 Completed

The project includes sidewalk, curb, gutter, bike lane, storm-water improvements, educational materials and events, emphasis patrols.

2012 Sedro-Woolley 39

SR9 Pedestrian/Bicycle Safety Improvements Project

$400,000 Completed

The project includes sidewalk, bike lanes pedestrian safety education for children in grades 1-4 and additional enforcement.

2013 Shelton 35

Evergreen Elementary Safe Routes to School Program

$497,700 Approved

The project includes sidewalk, curb, gutter, curb ramps, curb extensions, signage, educational materials and events, walking school bus, speed feedback signs, crossing guard equipment and emphasis patrols.

2013 Shoreline 32 Einstein Safe Routes $435,000 Underway

The project includes sidewalks, curb, gutter, curb ramps, educational materials and events, and emphasis patrols.

2015 Shoreline 32 Echo Lake Elementary Safe Routes to School

$520,000 Approved The project includes sidewalk, planter strip, curb, gutter, education and enforcement.

2013 Spokane 6 Hamblen Elementary School

$592,232 Completed

The project includes sidewalk, curb, gutter, planter strips, curb ramps, educational materials and events, and emphasis patrols.

2013 Spokane 6 Westview Elementary School

$555,935 Completed

The project includes, curb, gutter, planter strip, curb ramps, educational materials and events, and increased traffic patrols

Page 19: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

19

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Spokane 3 Regal – Bemiss – Shaw Pedestrian Safety

$559,513 Approved

The project includes sidewalk, curb extensions, curb ramps, narrow/reduce travel lanes, crosswalk markings, signs, enforcement, education, and encouragement.

2015 Spokane 3

Ridgeview Elementary Pedestrian Safety

$803,207 Approved

The project includes sidewalks, curb extensions, crosswalk markings, signs, education, encouragement and enforcement.

2013 Stanwood 38 Cedarhome Elementary Safe Routes to School

$171,750 Underway

The project includes sidewalk, curb, gutter, planter strip, parking lane, educational materials and events, speed feedback signs, and emphasis patrols.

2013 Swinomish Indian Tribal Community

10 Swinomish to La Conner Safe Routes Project

$744,610 Underway

The project includes sidewalk, curb, gutter, bicycle lanes, signage, sharrow markings, crosswalk markings including stop bars, flashing beacons, bicycle and pedestrian safety education training, crossing guard training, speed feedback signs and emphasis patrols.

2011 Tacoma 27

Sheridan Elementary - Safe Routes to School Project

$379,960 Underway

The project includes sidewalk, curb extensions, curb ramps, bike racks, educational materials, maps, walk and bike to school day events and materials, additional enforcement, speed feedback sign, and neighborhood speed watch.

2015 Thurston County 2

Thurston County Safe Routes To School Program

$725,000 Underway

The project includes sidewalk, curb, gutter, traffic circles, street lights, drainage improvements, school zone flashing beacons, crosswalk markings, signs, speed humps, speed table, education, encouragement, walking school bus and enforcement.

2012 Tukwila 11

Cascade View Elementary Safe Routes Demonstration Program

$427,588 Underway

The project includes multi-use path, assembly, walk to school event and walking school buses.

2013 Tukwila 11

Thorndyke Elementary Safe Routes to School Application

$457,000 Underway

The project includes sidewalk, curb, gutter, drainage, widen road to 10 ft., walking school bus, educational materials, maps and events.

2015 Tukwila 11

Cascade View Elementary Safe Routes to School- Phase II

$838,950 Underway

The project includes sidewalk, curb, gutter, traffic circle, curb extensions, and curb ramps.

Page 20: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

20

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Tumwater 22 Peter G Schmidt Sidewalk Construction

$332,128 Approved The project includes sidewalk, curb, gutter and curb extensions.

2011 University Place 28

27th Street Safe Routes to Schools Project

$910,000 Underway

The project includes sidewalk, pedestrian lighting, planter strip, curb ramps, signal, pavement markings, signage, maps, pedestrian and bicycle safety education events and materials, additional enforcement and speed feedback signs.

2011 University Place 28

Beckonridge Drive Safe Routes to School Project

$830,000 Underway

The project includes sidewalk, lighting, planter strip, curb ramps, flashing beacon, pavement markings, signage, maps, pedestrian and bicycle safety materials and events, increased enforcement and speed feedback signs.

2013 University Place 28

44th Street Safe Routes to Schools Project

$820,000 Underway

The project includes sidewalk, curb, gutter, bike lane, street lights, curb ramps, signage, educational materials and events, speed feedback signs and emphasis patrols.

2013 University Place 28

56th Street Safe Routes to Schools Project

$464,000 Underway

The project includes sidewalk, curb, gutter, street lights, curb ramps, crosswalk markings, signage, pedestrian refuge island, educational materials and events, speed feedback signs, and emphasis patrols.

2013 University Place 28

Cirque Drive Safe Routes to Schools Project

$1,040,000 Underway

The project includes sidewalk, curb, gutter, bike lane, planter strip, street lights, crosswalk markings, signalized crosswalks, curb ramps, educational materials and events, speed feedback signs and emphasis patrols.

2013 University Place 28

Elwood Drive/44th Street SRTS

$811,131 Underway

The project includes sidewalk, pedestrian lighting, planter strip, curb ramps, pavement markings, signage, maps, pedestrian and bicycle safety events and materials, additional enforcement, and speed feedback signs.

2013 Vancouver 17

Endeavour Elementary Pathway and Safety Improvement Program

$209,654 Underway

The project includes a shared use path, educational materials and events, speed feedback sign, and emphasis patrols.

Page 21: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

21

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Wapato 15 9th Street Sidewalk Improvements

$402,850 Approved

The project includes sidewalk, curb, gutter, curb extensions, curb ramps, crosswalk markings, and speed feedback signs.

2015

Washington State Department of Health

N/A State Student Travel Survey $299,501 Underway

The project includes implementation of the Washington State Student Travel Survey.

2013

Washington State Department of Health

22 State Student Travel Survey $173,052 Completed

Project conducts a statewide student travel survey to support state, regional and local project development and performance measurement.

2015

Washington State Office Superintendent of Public Instruction

N/A Bike and Pedestrian Safety Education

$837,000 Underway

The project includes expansion of and support for the bicycle and pedestrian safety education project (curriculum, education materials, encouragement and walking school buses).

2013

Washington State Office Superintendent of Public Instruction (OSPI)

22

Safe Routes to School Bicycle & Pedestrian Safety Education Program

$500,000 Completed

The project conducts Bicycle and Pedestrian Safety Training for students across the state (to be conducted at schools determined by OSPI to have need).

2013 Washougal 18 Jemtegaard Trail Improvements $599,305 Underway

The project includes multi-use path, pedestrian bridge, sidewalk, curb, gutter, walking and biking mobility and safety trainings, staff and volunteer training, active transportation mentor/role model project, bicycle and pedestrian education materials, encouragement activity, incentives, bicycle parking, increased traffic patrols, and pedestrian decoy crosswalk operations.

2015 Washougal 18 34th Street Improvements $470,078 Approved

The project includes sidewalk, a pedestrian path, curb, gutter, planter strip, crosswalk markings, signs, street lights and enforcement.

2013 Wenatchee 12

Okanogan and Red Apple Road Sidewalk and Pedestrian Enhancements

$354,420 Underway

The project includes sidewalk, curb, gutter, crosswalk signs, pavement markings, curb ramps, flashing beacons, speed feedback signs, walking school bus, crossing guard equipment, educational materials and events, and emphasis patrols.

Page 22: 2015 Pedestrian and Bicycle & Safe Routes to School · PDF file1 . Washington State Department of Transportation PEDESTRIAN and BICYCLE & SAFE ROUTES TO SCHOOL GRANT PROGRAMS . Status

22

Award Year Location Leg

Dis. Project Title Award Amount Status Project Description

2015 Wenatchee 12 Lewis and Clark Sidewalk Improvements

$372,794 Approved

The project includes sidewalk, curb, gutter, on the east side, and replace speed feedback signs. Adds mid-block crosswalk with pedestrian activated crosswalk beacons.

2015 White Salmon 14

White Salmon Safe Route to School Sidewalk Improvement Project

$330,242 Underway

The project includes sidewalk, curb, gutter, planter strips, crosswalk markings with flashing beacons, signs, crosswalk flags, speed feedback sign, education and walking school bus.

2015 Wilson Creek 13 Navar Street Sidewalk $186,035 Approved

The project includes sidewalk, curb ramps, drainage improvements and retaining walls.

2013 Woodland 20 South Woodland Safe Walking Route

$306,473 Underway

The project includes sidewalk, curb, gutter, crossing improvements, crossing guards, and walking school bus program.

2013 Yakima 14

West Valley Middle School Vicinity Improvements

$544,000 Underway

The project includes sidewalk, curb, gutter, drainage, traffic signal, pedestrian safety and crosswalk public service announcements, television, radio and print media efforts, and pedestrian crosswalk decoy operation.

2015 Yakima 14

Garfield Elementary Safety Improvements

$180,000 Approved

The project includes sidewalk, curb, gutter, school speed zone signs, curb ramps, crosswalk markings, no parking signs, education, walking school bus, encouragement and enforcement.

2015 Yakima 14

Adams/ Washington Vicinity Sidewalk Improvements

$357,000 Approved

The project includes sidewalk, curb, gutter, planter strip, curb extension, street lights, crosswalk markings, crosswalk signs, stop signs, no parking signs, education, encouragement and enforcement.