H I S D Becoming #GreatAllOver
Agenda– Project Process– Implementation of Gate Reviews– Innotas– Q&A???
RIGOR & ACCOUNTABILI
TY
Project Process
A unified IT Governance, Application Lifecycle, Software Development, Service Management and Project framework for Team IT– Processes monitored by Gate Reviews (intersections) designed to ensure customer results and conformance
by establishing clear expectations of Team IT. Gate 5 focus on Value Recognition, Service Operations and ensuring Continuous Improvement is in progress
Digital TransformationConsistent Results for our Customers
Focus on the Right Changes Customer Approved Requirements Customer Validated and Tested
Engaged with our Customers
Phase 7 - Retire
• ARCHIVE & ELIMINATE
Phase 6 -
Operate
• SUSTAIN & GAIN VALUE
Phase 5 -Deploy
• IMPLEMENT
Phase 4b – Test
• VALIDATE & APPROVE
Phase 4a -
Construct
• BUILD
Phase 3 - Design
• DEFINE HOW BY REQUIREMENT
Phase 2 -Analyze
• DEVELOP REQUIREMENTS & GAIN CONSENSUS
Phase 1 - Initiate
• DEVELOP SCOPE
Gate 1
Gate 2
Gate 3
Gate 5
Gate 4
Project ProcessGate Approval Process
IT Governance – COBIT V4.1
SDLC PhasesPlan & Organize Acquire & Implement Deliver & Support Monitor & Evaluate
Service Management - ITIL V2 (V3 or V4 in the future)
Service Strategy
ServiceDesign
ServiceTransition
Service Operation
Continuous Service Improvement (CSI)
Project Process
Adherence to the requirements of every Phase Confirmation of acceptance at appropriate gates based on level of work
– Customer assessment / approval– PMO assessment / approval– IT Leadership assessment / approval
IT Accountability
H I S D Becoming #GreatAllOver
Enhancements to existing functions
Creation / Implementation of a new system or function
What is a Project?
What is not a Project? Break / Fix work – reported as
incidents in FootPrints with a close within x days requirement
H I S D Becoming #GreatAllOver
Minor Enhancement– Less than $50K (hours effort * $110
for all team labor) (Determined after initial business case developed)
Incremental Release less than 1 month Duration
Does not include Break / Fix or operational (sustain/maintain) activities
Project Criteria – Minor - No PMO PM Required
Phase 5 -Deploy
• IMPLEMENT
Phase 4b – Test
• VALIDATE & APPROVE
Phase 3 /4a-
Design & Construc
t
• DEFINE HOW BY REQUIREMENT
Phase 2 -Analyze
• DEVELOP REQUIREMENTS & GAIN CONSENSUS
Phase 1 - Initiate
• DEVELOP SCOPE
Minor Project - Key Deliverables by Phase (typically Non PMO PM Project )
Gate 1
Gate 2
Gate 4
Project ProcessGate Approval Process
IT Governance – COBIT V4.1
SDLC Phases
Plan & Organize Acquire & Implement Deliver & Support Monitor & Evaluate
Service Management - ITIL V2 (V3 or V4 in the future)
Service Strategy
ServiceDesign
ServiceTransition
Service Operation
Continuous Service Improvement (CSI)
Project Process
• Project Request In Footprints
• Project Charter• Gate 1 Review Package
• Minor Project Deliverable • WBS in Innotas• Resource Plan• Gate 2 Review Package
• Update Minor Project Deliverable
• Code• Update impacted
Operations Plan
• Previous Deliverable Updates
• Test Results• Change Controls• Deployment Schedule• Gate 4 Review Package
• Previous Deliverable Updates• Deployed Solution
NOTE if the Cost Estimate varies by more than 10% Standard Gate 2 meeting should be scheduled Gate 3
H I S D Becoming #GreatAllOver
Incremental Release more than 1 month Duration
Involves 2 or more IT Teams (more than an information request)
Enterprise Deployment $50K or more costs Implements an external vendor product on
more than 5 laptops Does not include Break / Fix or operational
(sustain/maintain) activities
Project Type Criteria – Major - PMO PM Required
Phase 7 - Retire
• ARCHIVE & ELIMINATE
Phase 6 -
Operate
• SUSTAIN & GAIN VALUE
Phase 5 -Deploy
• IMPLEMENT
Phase 4b – Test
• VALIDATE & APPROVE
Phase 4a -
Construct
• BUILD
Phase 3 - Design
• DEFINE HOW BY REQUIREMENT
Phase 2 -Analyze
• DEVELOP REQUIREMENTS & GAIN CONSENSUS
Phase 1 - Initiate
• DEVELOP SCOPE
PMO PM Led Project - Key Deliverables by Phase
Gate 1
Gate 2
Gate 3
Gate 5
Gate 4
Project ProcessGate Approval Process
IT Governance – COBIT V4.1
SDLC Phases
Plan & Organize Acquire & Implement Deliver & Support Monitor & Evaluate
Service Management - ITIL V2 (V3 or V4 in the future)
Service Strategy
ServiceDesign
ServiceTransition
Service Operation
Continuous Service Improvement (CSI)
Project Process
• Project Charter• Project
Request• Initial
Business Case
• Business Requirements
• Communication Plan
• Project Plan• Resource Plan• Cost Plan• Risk Plan• Weekly Status
Report• Resource
Timesheets• Gate 2 Review
Package
• Previous Deliverable Updates
• Technical / Functional Specifications
• Test Plans• Test Scenarios• Disaster Recovery
Plan• Gate 3 Review
Package
• Previous Deliverable Updates
• Code• Test Cases• Operations Plan• Deployment Plan• Post Production
Monitoring Plan• Retirement Plan
• Previous Deliverable Updates
• Test Results• Test Summary
Report• Change Controls• Deployment
Schedule• Gate 4 Review
Package
• Previous Deliverable Updates
• Deployed Solution• Post Production
Monitoring • After a predefined
value time -Value Review Components
• Gate 5 Review Package
ENGAGED STAKEHOLD
ERS
Project Requests– Entry into FootPrints– Assigned PMO Representative mines
FootPrints– Assigned PMO Representative works with
Customer to define Charter– Assigned PMO Representative enters
Request into Innotas – Submits– Request flows into Gate Process
• Initial Review by PMO• Review / Approval by IT Leadership
– Assignment to PM– Pending PM Assignment– Assignment to Portfolio– Rejected– Placed into Queue for Next Fiscal Year
RIGOR & ACCOUNTABILI
TY
Gate Reviews
RIGOR & ACCOUNTABILI
TY
Gate Reviews– Every Monday 9-10am
• PMs• Leadership team acting as Gatekeepers
– Goal – Customer Service through the Delivery of the Right / Quality Solutions to our Customers• Ensure the projects approved for work are the
right projects• Ensure the projects are achieving all goals
appropriately– Process– Involvement of the Right Areas– Customer Interactions / Communications are
appropriate– Quality – the project is ready from a completeness
perspective to move forward
Phase 7 - Retire
• ARCHIVE & ELIMINATE
Phase 6 -
Operate
• SUSTAIN & GAIN VALUE
Phase 5 -Deploy
• IMPLEMENT
Phase 4b – Test
• VALIDATE & APPROVE
Phase 4a -
Construct
• BUILD
Phase 3 - Design
• DEFINE HOW BY REQUIREMENT
Phase 2 -Analyze
• DEVELOP REQUIREMENTS & GAIN CONSENSUS
Phase 1 - Initiate
• DEVELOP SCOPE
Gate Review - Focus
Gate 1
Gate 2
Gate 3
Gate 5
Gate 4
Project ProcessGate Approval ProcessProject Process
• Meets minimum requirements to be accepted for definition of Requirements efforts within IT
• Acceptable Charter1. Scope Outlined2. Defined
Stakeholders and Engagement within IT
• + - 50% Cost Estimate
• Requirements appropriately approved
• Risks identified with clear mitigation steps
• Measureable benefits with appropriate metrics?
• Resource commitment from all required
• Assess current budget against HISD capability to fund reality
• Confirm scope is clearly documented
• Design appropriately approved
• Technically acceptable solution
• Support resource requirements identified and approved
• Risks identified with clear mitigation steps
• Resource commitment and in place from all required
• Assess remaining spend plan + - 10% against HISD capability to fund
• Confirm scope is adhered to or changes approved prior to work
• Initial transition plan created
• Occurs at predefined value review checkpoint
• Confirm anticipated value is received
• Lessons Learned captured
• Support levels are as expected or documented in lessons learned
• All stakeholders approve closure
• Testing complete and accepted
• User approved deployment plan
• Transition plan actively being worked
• Support resource requirements in place
• CAB approved• Risks identified
with clear mitigation steps
• Resource commitment from all required
• Assess remaining spend against actual; within + - 10%
• Confirm scope was adhered to or changes approved prior to work
• Value review checkpoint defined, Gate 5 scheduled
RIGOR & ACCOUNTABILI
TY
Innotas - Portfolio/Program/Project Management SaAS
H I S D Becoming #GreatAllOver
Innotas– PPM Software as a Service Product– Application Portfolio– Request Management– Project Components &
Management– Timesheets for Project Activity• Capture of sustain / maintain will be
manager decision
– Dashboards & Reporting
H I S D Becoming #GreatAllOver
Supporting Information
H I S D Becoming #GreatAllOver
What business problem and/or result is desired?
Confirm Initial Support for Scoping
Document Scope supporting desired business result
Gain the appropriate approvals & prioritize start
Gate 1 Review
Phase 1 - Initiating WorkKey Activities
H I S D Becoming #GreatAllOver
Form the team Develop the Project Plan and Schedule Develop the full Business Case including expected
value comparison data Develop the formal Business Requirements Document existing system impacts Document the Communication Plan Develop Project Assumptions & Constraints Develop the Risk Plan Document and Manage Issues Report Status Gain the appropriate approvals & adjust prioritization if
appropriate Gate 2 Review Meeting
Phase 2 – AnalyzeKey Activities
H I S D Becoming #GreatAllOver
Develop the technical design Formalize Use Cases Document Controls Determine the solution Determine / Perform RFP Develop the Functional Requirements Document the architecture Design integrations with existing systems Develop Test Scenarios and Cases (Unit, UAT, Integration, System and
Performance) Communicate Manage the Risk Plan Manage the Issues Manage Scope through Scope Change Requests (return to Gate 2 if +
or – 10% cost or schedule variation for 1 or all change requests) Report Status Gain the appropriate approvals & adjust prioritization if appropriate Gate 3 Review Meeting
Phase 3 – DesignKey Activities
H I S D Becoming #GreatAllOver
Construct / Code the desired products Finalize Test Scenarios and Cases (Unit, UAT, Integration, System,
Performance, Security and Controls) Perform Unit Testing Communicate Develop Operations Plan Develop Deployment Plan Develop Post Production Monitoring Plan Develop Retirement Plan Manage the Risk Plan Manage the Issues Manage Scope through Scope Change Requests (return to Gate 2
if + or – 10% cost or schedule variation for 1 or all change requests)
Report Status Gain the appropriate approvals & adjust prioritization if
appropriate
Phase 4a – ConstructKey Activities
H I S D Becoming #GreatAllOver
Construct / Code the desired products Perform Testing
– Unit– UAT– Integration– System– Security– Performance
Perform Project Quality Review / Assurance Review Test & Confirm Process & System Communicate Develop Operations Plan Develop Deployment Plan Develop Post Production Monitoring Plan Develop Retirement Plan Manage the Risk Plan Manage the Issues Manage Scope through Scope Change Requests (return to Gate 2 if + or – 10% cost or
schedule variation for 1 or all change requests) Create Change Orders Report Status Gain the appropriate approvals & adjust prioritization if appropriate Gate 4 Meeting
Phase 4b – TestKey Activities
H I S D Becoming #GreatAllOver
CAB Approval Deploy Service (solution or product) Operate Service (solution or product) Monitor Service Operations; produce Early Operations Monitoring Reports
weekly Manage the Risk Plan Manage the Issues Define items for next Phase; initiate request if required Publish final Operations Monitoring at agreed time Document Lessons Learned Request Project Survey Response Move project to Implemented status
After pre-defined Value Period– Develop value gained materials– Develop Final Gate Review Materials– Confirm Project Deliverables are in place– Formally Close Project– Gate 5 Meeting
Phase 5 – DeployKey Activities
H I S D Becoming #GreatAllOver
Phase 7 - Retire
• ARCHIVE & ELIMINATE
Phase 6 -
Operate
• SUSTAIN & GAIN VALUE
Phase 5 -Deploy
• IMPLEMENT
Phase 4b – Test
• VALIDATE & APPROVE
Phase 4a -
Construct
• BUILD
Phase 3 - Design
• DEFINE HOW BY REQUIREMENT
Phase 2 -Analyze
• DEVELOP REQUIREMENTS & GAIN CONSENSUS
Phase 1 - Initiate
• DEVELOP SCOPE & 1 Page Project Charter
Lifecycle Roles
Gate 1 Gate
2Gate 3
Gate 5
Gate 4
Project ProcessGate Approval Process
IT Governance – COBIT V4.1
SDLC Phases
Service Management - ITIL V2 (V3 or V4 in the future)Project Process
IT Business Analyst
IT Project Manager
IT Project Manager
IT Project Manager
IT Project Manager
IT Project Manager
Systems Analyst
IT Team that Owns the Service
PMO IT Business Analyst or Systems Business Analyst (OR PM PERFORMS BA Role)
IT Business Analyst (clarification of requirements) (OR PM PERFORMS BA Role)
IT Business Analyst (clarification of requirements or test scenarios) (OR PM PERFORMS BA Role)
IT Business Analyst (customer liaison / testing) (OR PM PERFORMS BA Role), QA
IT Business Analyst (customer facing) (OR PM PERFORMS BA Role)
Developer
IT Leadership IT Leadership Systems Analyst
Systems Analyst, QA
Systems Analyst (technical testing)
Systems Analyst (technical)
IT Team that Owns the Service
IT Leadership Developer, Technical Support
Developer, Technical Support
IT Leadership
UI Designer (if applicable)
IT Leadership IT LeadershipSupporting Resource Type for Phase
Key Resource Type for Phase
ENGAGED STAKEHOLD
ERS
Product Owner Submits Project Requests into
Footprints as appropriate Customer Liaison
– Roadmap Development & Updates– Schedules Steering Committee Meetings– Steering Committee Communicator– Communicates Issues to Area Director,
PMO and mid level Customers (Directors communicate to CITO & BRM(s), BRM(s) communicates to Chief(s) prior to steering committee meetings)
– Manages Change Order Approvals & all related customer communications
Engages Portfolio Resources Manages Portfolio Resources if
applicable Reviews project costs
– Validates project estimates for completeness
– Understand and approve cost assumptions
– Discuss with PM to mitigate budget risks – Requests additional funding as required
(gains approval for Change Order) Manages project related contracts that
charge to portfolio budget strings Ensures Production Transition occurs as
expected works with PM to revise plan and actions as required
Production Support Owner Defines Release Schedules Submits Project Requests for Releases
Portfolio Manager Project Manager Project Owner Manages project activities to deliver
Product Prepares & distributes Status Reports
(weekly and for Steering Committee use by Portfolio Manager)
Communicates Issues & Risks to Portfolio Manager & PMO Director
Requests signoff on project deliverables except Change Orders
Manages Team Resources from the perspective of the project
Coordinates with Resource Owners to schedule and ensure Resource Engagement occurs as expected
Prepares project costs, assumptions & backup
Reviews project costs with Portfolio Manager to mitigate budget risks.
Develops Change Order to request additional funding / scope changes
Develops or ensure CAB documentation is created / submitted
Ensures Project Transition activities are identified and occur
Monitors product for some period post deployment
Portfolio Manager / Project ManagerHigh Level Roles
RIGOR & ACCOUNTABILI
TY
What skills should PMs/BAs and BSAs have? What vs how.– Business Analysis– Business Process Modeling– Effect Communications– Some Project Management– Problem Solving Tools
• Root Cause Analysis• Pereto
– Effective Facilitation– Organizational Change Management– ITIL
• Service Design• Service Strategy• Service Transition• Service Operations• Continual Service Improvement
RIGOR & ACCOUNTABILI
TY
IT Business Analyst (BA) Role (Performed by PM in many cases)– Interfaces with the Customer to develop charter document,
business case, business requirements and test cases. Facilitates detailed requirements definition meetings and sessions.
– Knowledgeable or becomes knowledgeable and able to assist with business domain issues. Becomes the voice of the customer strategy, problems and goals to IT in relation to projects.
– Key Skills• Customer Service• Listening• Business Analysis, Business requirements definition and begins the
Requirements Traceability Matrix• Facilitator • Process Mapping (As Is / To Be)• Develops Test Plan and Scenarios• Documents initial User Interface• Participates and works with the customer to ensure User Acceptance
Testing occurs and that results are recorded• Integrates with Business Systems Analyst / Systems Analyst so that
the BSA / SA can ensure testing results are incorporated into the technical specifications and code by the technical resources
RIGOR & ACCOUNTABILI
TY
Business Systems Analyst (BSA) Role– Translates business requirements into detailed
functional, technical requirements and test cases
– Key Skills• Technical Knowledge• Translation of business need to technical• Develops Test Cases and works with QA resources
where available• Performs Unit Testing• Analyzes and manages work related Small Projects /
enhancements• Analyzes production issues, part of the level 3
support team• Approves technical solution • Integrates with BA during User Acceptance Testing to
ensure testing results are incorporated into the technical specifications and code by the technical resources
H I S D Becoming #GreatAllOver
SDLC Phase
–Deliverables
•Project Activities–Gate Approval
Methodology Hierarchy
H I S D Becoming #GreatAllOver
September 13• Minimal
standardization & commonly adhered to project processes
• No Enterprise Project Management tool to enable enterprise visibility
• Non Standardized Work Intake
• Key projects at risk
• Key roles need staffed
• Implement standardized Project Status Template for enterprise projects
November 2013• Standardized
Work Intake within IT
• Socialized & gained acceptance of Standardized Project Process• Minor
Projects• Major
Projects• Recommended
search be taken for aSaAS Project Management Information System (PMIS)
December 13• Selected Innotas SaAs
PMIS solution• Completed Gate
Design• Standardized Work
January 14• First Gate Review• Design Innotas
Implementation & Metadata
• Ongoing development of PMO Vision
February 14• All Enterprise Projects
conducting Gate Reviews
• Projects began to be created in Innotas
• At Risk Project Reviews implemented
• CTO Project Reviews implemented
• IT Leadership introduced to project process, Innotas and gate process.
IT PMO 6 Month Maturity
04/08/2023
March 14• Project WBSs
entered into Innotas
• Gate meetings processed through Innotas
• Refined Steering Committee Meeting Attendees
• Improved Project Deliverable options
• Implemented standard project WBS in Innotas
• Implemented standard project deliverables
Focused on building the foundation for standardization, visibility and CUSTOMER SERVICE through projects