2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter...

18
Matthew Rylander Senior Project Engineer PV Distribution System Modeling Workshop May 6, 2014 Increasing Hosting Capacity with Advanced Inverter Functions

description

2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

Transcript of 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter...

Page 1: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

Matthew Rylander

Senior Project Engineer

PV Distribution System Modeling Workshop

May 6, 2014

Increasing Hosting Capacity with

Advanced Inverter Functions

Page 2: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

2 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Overview

Objective

• Demonstrate, via simulation, higher feeder PV hosting capacity via use of

advanced inverter functions

Outline

• Method for analysis

– Possible PV deployments

– Advanced inverter functions

– Feeder end-use load

– Feeder response metrics

• Analysis results

• Summary of findings

Page 3: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

3 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Method for Analysis

Step 1: Create thousands of possible PV deployments

– Utility-scale PV

– Customer-owned PV

Step 2: Run all PV deployments from zero to full output

while holding all controls fixed

– Observe feeder-wide impact

• Voltage Magnitude

• Voltage Deviation

– Repeat for different load conditions

Step 3: Repeat step 2 with advanced inverter functions

Page 4: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

4 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Step 1: PV Deployment

Baseline – No PV

20% Customers with PV

30% Customers with PV

50% Customers with PV

Beyond…

PV Systems

Process is

repeated

100’s of times

to capture

many

possible

scenarios

Page 5: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

5 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Step 2: PV Impact Analysis

• Voltage Magnitude

– Primary voltage nodes should be < 1.05 Vpu

– Secondary voltage nodes should be < 1.05 Vpu

• Voltage Deviation

– Primary voltage nodes should be < 0.03 Vpu

– Secondary voltage nodes should be < 0.05 Vpu

1.035

1.04

1.045

1.05

1.055

1.06

1.065

1.07

0 0.5 1 1.5 2

Max

imu

m F

ee

de

r V

olt

age

(Vp

u)

Total PV Penetraion of Deployment (MW)

Minimum Hosting Capacity

Maximum Hosting Capacity

A B C

Wo

rst-

Ca

se R

esu

lt fo

r E

ach

Un

iqu

e P

V D

ep

loym

ent

Increasing penetration (MW)

Threshold of violation

A – All penetrations in

this region are

acceptable, regardless

of location

B – Some penetrations

in this region are

acceptable, site specific

C – No penetrations in

this region are

acceptable, regardless

of location

Details on analysis method:

Stochastic Analysis to Determine

Feeder Hosting Capacity for

Distributed Solar PV. EPRI, Palo

Alto, CA: 2012. 1026640.

Ma

xim

um

Fe

ed

er

Vo

lta

ge

s (

pu)

Page 6: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

6 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Step 3: Impact of Advanced Inverters

PV at Unity Power Factor PV with Volt/var Control

2500 cases shown

Each point = highest primary voltage

ANSI voltage limit

ANSI voltage limit

Increasing penetration (kW)

Ma

xim

um

Fe

ed

er

Vo

lta

ge

(pu

)

Ma

xim

um

Fe

ed

er

Vo

lta

ge

s (

pu

)

Increasing penetration (kW)

No observable violations regardless of PV size/location

Possible violations based upon PV size/location

Observable violations occur regardless of size/location

Minimum Hosting Capacity Maximum Hosting Capacity Minimum Hosting Capacity Max Hosting Capacity

Page 7: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

7 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Advanced Inverter Functions

• Absorbing reactive power at constant power factor

– Unity power factor (Base case, control off)

– 98% power factor

– 95% power factor

• Inverter voltage determines reactive power output

Volt-Var 1 Volt-Var 2

Page 8: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

8 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Advanced Inverter Control, cont.

• Inverter voltage determines active power output

• Dynamic control of reactive power output based on voltage

deviation

Volt-Watt 1 Volt-Watt 2

0

100

0.9 0.95 1 1.05 1.1 1.15

Wat

ts G

en

era

ted

(%)

Local Voltage (pu)

0

100

0.9 0.95 1 1.05 1.1 1.15

Wat

ts G

en

era

ted

(%)

Local Voltage (pu)

-50

0

50

-0.2 -0.1 0 0.1 0.2

Re

acti

ve C

urr

ent

(%)

Local Voltage Change (pu)

Page 9: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

9 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Utility Feeder

Feeder

Characteristics Feeder

Voltage (kV) 12.47

Peak Load ~ 6 MW

Minimum Load 0.7

Existing PV (MW) 1.7

Substation LTC Yes

Feeder Regulators 3

Capacitors 2 – fixed

3 – voltage controlled

Total Circuit Miles 58

Feeder “Footprint” 35 mi2

Sub

Reg

Cap

Page 10: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

10 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Utility-Scale PV at Maximum Load

Primary Voltage Magnitude

• Dyn-Var and Volt-Watt 2 controls help is minimal

• Volt-Watt 1, Volt-Var 1, and 95% pf controls help limit

voltage magnitude

Line indicates

average impact

from all PV

deployments

1.02

1.04

1.06

1.08

1.1

1.12

1.14

1.16

1.18

1.2

1.22

0 2000 4000 6000 8000 10000

Max

imu

m F

ee

de

r V

olt

age

(pu

)

Total PV (kW)

Page 11: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

11 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Utility-Scale PV at Maximum Load

Primary Voltage Deviation

• Dyn-Var and Volt-Watt 2 controls help in minimal

• Volt-Watt 1, Volt-Var 1, and 95% pf controls help limit

voltage deviation

Page 12: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

12 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Utility-Scale PV at Maximum Load

Feeder Head Demand

• Volt-Watt controls limits PV active power output

• All other controls only impact the reactive power demand

– Bulk power system to provide or local resources

– 95% pf and Volt-Var 1 require the most reactive power

-6000

-4000

-2000

0

2000

4000

6000

8000

0 2000 4000 6000 8000 10000

Feed

er

Po

we

r (k

W)

Total PV (kW)

Control Off 98% pfVolt-Var 1 Volt-Var 295% pf Volt-Watt 1Dyn-Var Volt-Watt 2

-500

0

500

1000

1500

2000

2500

3000

3500

4000

0 2000 4000 6000 8000 10000

Feed

er

Po

we

r (k

var)

Total PV (kW)

Control Off 98% pf

Volt-Var 1 Volt-Var 2

95% pf Volt-Watt 1

Dyn-Var Volt-Watt 2

Page 13: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

13 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Utility-Scale PV

Advanced Inverter Summary

0 2000 4000 6000 8000 10000

Control Off

Volt-Var 1

Volt-Var 2

98% pf

95% pf

Volt-Watt 1

Volt-Watt 2

Dyn-Var

Feeder Hosting Capacity (kW)

Co

ntr

ol

No observable violations regardless of PV size/location

Possible violations based upon PV size/location

Observable violations occur regardless of size/location

Page 14: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

14 © 2014 Electric Power Research Institute, Inc. All rights reserved.

0 1000 2000 3000 4000 5000

Control Off

Volt-Var 1

Volt-Var 2

98% pf

95% pf

Volt-Watt 1

Volt-Watt 2

Dyn-Var

Feeder Hosting Capacity (kW)

Co

ntr

ol

Customer-Owned PV

Advanced Inverter Summary

No observable violations regardless of PV size/location

Possible violations based upon PV size/location

Observable violations occur regardless of size/location

Page 15: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

15 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Potential Adverse Impacts Due to Increased

Var Flow

PV @ Unity

Power Factor

PV @ 0.98

Power Factor

PV @ 0.95

Power Factor

Hosting Capacity Based on

Feeder Overvoltage (kW)

Hosting Capacity Based on

LTC/Line Regulator

Operations (kW)

Increased

hosting capacity Decreased

hosting capacity

0 2000 4000 6000 8000 10000

P3

0 2000 4000 6000 8000 10000

P3

0 2000 4000 6000 8000 10000

P3

0 2000 4000 6000 8000 10000

P3

0 2000 4000 6000 8000 10000

P3

0 2000 4000 6000 8000 10000

P3

No observable violations regardless of PV size/location

Possible violations based upon PV size/location

Observable violations occur regardless of size/location

Page 16: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

16 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Inverter Settings are Critical

% A

vaila

ble

Var

s

% voltage

100%

0.95

1.05

-100%

1.0V

% A

vaila

ble

Var

s

% voltage

100%

0.99

1.01

-100%

1.0

Volt-var A

1

1.01

1.02

1.03

1.04

1.05

0 60 120 180 240 300 360 420 480 540

PV

Te

rmin

al V

olt

age

(p

u)

Time (seconds)

1

1.01

1.02

1.03

1.04

1.05

0 60 120 180 240 300 360 420 480 540

PV

Te

rmin

al V

olt

age

(p

u)

Time (seconds)

Unity Power Factor

Volt-var A

Volt-var B

1

1.01

1.02

1.03

1.04

1.05

0 60 120 180 240 300 360 420 480 540

PV

Te

rmin

al V

olt

age

(p

u)

Time (seconds)

If wrong setpoints are used, adverse

impacts can occur

0

0.5

1

PV

Act

ive

P

ow

er

Volt-var B

Page 17: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

17 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Summary

• Feeder hosting capacity can increase with advanced

inverter functions

– Volt-Var and off-nominal power factor provides the

greatest benefit

• Volt-Var and power factor control requires reactive power

resources

– Requiring significant reactive power can have adverse

impact

• Inverter settings must be chosen carefully

Page 18: 2014 PV Distribution System Modeling Workshop: Increasing Hosting Capacity with Advanced Inverter Functions: Matt Rylander, EPRI

18 © 2014 Electric Power Research Institute, Inc. All rights reserved.

Together…Shaping the Future of Electricity