2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

download 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

of 7

Transcript of 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    1/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    1. Field Layout

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    2/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    2. Sequence of TL-DD Project

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    3/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    3. Schedule of Review (1/2)

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    4/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    3. Schedule of Review (2/2)

    Description

    Add . Weather Standby

    HD-2500 Sch.

    Star t Finish Dur .

    Original

    HD-2500 Sch.

    Start Finish Dur.

    MILESTONE

    Start

    HD-2500

    Finish Dur.

    DSV Sch.

    Star t Finish Dur

    Catch-up Plan

    2013-08-12 2013-09-19 39.0

    19 TL PLEM Installation

    20 Flooding/Cleaning/Gauging from DD WHP(6/8/10")

    21 Spool Install at DD PLEM~P/L from DD WHP(3 points)

    22 Weather Standby 2013-08-12 2013-08-13 2.0

    2013-08-02 2013-08-05 4.0

    2013-08-06 2013-08-11 6.0

    2013-07-30 2013-08-01 3.0

    6.0

    3.0

    2013-08-05 4.0

    2013-08-09 2013-08-10 2.0

    2013-08-06 2013-08-08 3.0

    2013-07-30 2013-08-01 3.02013-07-15

    2013-07-20

    2013-07-13

    2013-07-25

    2013-07-16 2013-07-19 4.0 2013-08-02

    2013-08-16 2013-08-18 3.0

    2013-08-19 2013-08-20 2.0

    poo nsta at ~ rom po nts

    24 Flooding/Cleaning/Gauging from TL PLEM(6")

    25 Weather Standby

    26 Spool Installation at TL PLEM(6")

    27 Spool Installation at TL PLEM(12")

    2013-08-22 2013-08-23 2.0

    2013-08-24 2013-08-25 2.0

    2013-08-18 2013-08-19 2.0

    2013-08-20 2013-08-21 2.0

    1 - -1 1 - -1 .

    2.0

    .

    2013-08-15 2013-08-16

    2.0

    2.0 2013-08-17 2013-08-17 1.0

    2013-08-18

    2.0

    1 - -11 1 - -1 .

    2013-08-13 2013-08-14 2.02013-07-31

    2013-08-022013-08-01

    1 - - 1 - -

    2013-08-04

    2013-07-30

    2013-08-03 2013-08-18 1.0

    1 - - 1 1 - -

    2013-08-23 2013-08-24

    2013-08-25 2013-08-25

    .

    2.0

    1.0

    2013-08-26 2013-08-26 1.0

    28 Weather Standby

    29 DD WHP Topside Installation

    30 Spool Installation at DD WHP(6"/8"/10")

    31 Weather Standby

    2013-09-01 2013-09-05 5.0

    2013-09-06 2013-09-06 1.0

    2013-08-26 2013-08-27 2.0

    2013-08-28 2013-08-31 4.04.0

    5.0 2013-08-25 2013-08-27 3.0

    2013-08-24 4.02013-08-05

    2013-08-28 2013-08-28 1.0

    2013-08-212013-08-08

    2013-08-09 2013-08-13

    1.0

    2013-08-27 2013-08-28 2.02013-08-19 2013-08-20 2.0

    2013-08-29 2013-08-30

    2013-08-31 2013-08-31

    2.0

    32 PLET Installation33 Spool Installation at PLET(6")

    34 H/Test for 6" P/L from TL PLEM to PLET

    35 H/Test for 6"/8"/10" P/L DD WHP~DD PLEM~TL WHP

    36 H/Test from TL WHP to TL PLEM 2013-09-22 2013-09-24 3.0

    2013-09-11 2013-09-12 2.0

    2013-09-13 2013-09-21 9.0

    2013-09-07 2013-09-08 2.02013-09-09 2013-09-10 2.0

    2013-08-29 2013-08-302.02.0 2013-08-31 2013-08-31 1.0

    2013-08-19

    2013-08-20 2013-08-28

    2013-08-16

    2013-08-29

    2013-08-172.02013-08-14 2013-08-15

    2013-08-18 2.0

    9.0

    3.02013-08-31

    1.0

    2.0

    9.0

    2013-09-01

    2013-09-13 2013-09-15

    2013-09-01

    2013-09-02 2013-09-03

    2013-09-04 2013-09-12

    3.0

    Demo Customs Clearance 2013-09-25 2013-09-25 1.0 2013-09-01 2013-09-01 1.02013-09-01 2013-09-01 1.0 2013-09-19 4.02013-09-16

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    5/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    4. Schedule (Catch-up Plan)

    Note : In case of weather standby 14 days from 21st of June.

    1 5 10 15 20 25 30 1 5 10 15 20 25 30 1 5 10 15 20 25 30 1 5 10 15 20 25 30

    5 31

    J une J uly Aug SepCase SpreadNo.

    5 24

    Original1

    2

    HD-2500

    Add.

    WeatherHD-2500

    1 Weather impact is 8 days so far

    Catch-up3-

    +DSV

    1. Weather impact is 8 days so far2. Assume 14 days as further weather impact, completion date is 24-Sep3. Reduce 10 days when DSV is mobilized4. Diving team of DSV will be bolting after HD-2500 put seabed with spool assembly5. Additional catch-up will be tried by HD-2500 operating simultaneously (spool measuring andl bl ) t l i t ll ti itipool assembly) at spool installation position

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    6/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    5. Progress & Delay Status

    5 10 15 20 25 30 5 10

    Plan 5-J un 7-J un

    Actual 5-J un 9-J un

    Plan 8-J un 10-J unTL~DD PLEM (8" x 14.3 x 3.1 km)

    TL~DD PLEM (6" x 12.7 x 3.05 km)

    Description Start FinishJune July

    - -

    Plan 11-J un 14-J un

    Actual 21-Jun 24-Jun

    Plan 15-J un 17-J un

    Actual 27-Jun 29-JunPipelaying DD~DD PLEM (8" x 14.3 x 2.88 km)

    DD~DD PLEM (6" x 12.7 x 2.68 km)

    - -

    Actual 30-J ul 2-J ul

    Plan 21-J un 23-J un

    Actual 4-J ul 6-J ul

    Plan 24-J un 25-J un8-Jul

    - -TL PLEM~PLET(6" x 12.7 x 0.8 km)

    TL~TL PLEM(12" x 19.1 x 2.77 km)

    DD~DD PLEM(10" x 12.7 x 2.53 km)

    15

    Delayed

    5

    10

    Delayed

    0

    Delayed

    Period

    Weather

    Standby

    Welding

    Repair

    Others

  • 7/30/2019 2013-06-26HHI, TLDD TI Catch-Up Plan Presentation

    7/7

    Petroleum Vietnam Gas CorporationPTSC Mechanical & Construction

    6. Spool Lowering