2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

10
Failure Risk of Bar-Wrapped Pipe with Broken Bars and Corroded Cylinder Ali Alavinasab 1 , Muthu Chandrasekaran 2 , Edward Padewski III 3 1 Pure Technologies, 3322 State Route 22 West, Suite 902, Building 9, Branchburg, NJ 08876; PH (908) 526-6600; FAX (908) 526-9900; email: [email protected] 2 Pure Technologies, 8920 State Route 108, Suite D Columbia, MD 21045; PH (443) 766-7873; FAX (443) 766-7877; email: [email protected] 3 Pure Technologies, 3322 State Route 22 West, Suite 902, Building 9, Branchburg, NJ 08876; PH (908) 526-6600; FAX (908) 526-9900; email: [email protected] ABSTRACT Bar-wrapped pipe (“BWP”) commonly used in pressure pipelines due to its reliability, cost effectiveness and durability. Failure of BWP can occur as a result of long term leakage and subsequent corrosion or as a result of leakage and deterioration of the reinforcing bars over time. The failure can also be the direct result of a transient pressure or other sudden catastrophic events. The consequence of failure may result in a significant disruption of operation and service for a water utility without any warning. This is a concern because assessing the condition of a damaged BWP is very challenging. In this paper, a nonlinear finite element analysis was used to evaluate the performance of a damaged BWP. For the structural evaluation, stresses and strains developed in the damaged BWP were evaluated. Cracking and spalling of the mortar lining will eventually lead to the corrosion of the steel components. In an effort to account for the steel deterioration, the model was adjusted by reducing the thickness of the steel cylinder. This study investigates the behavior of a deteriorating BWP under various levels of distress and various internal pressures. The results based on a 24-inch pipe transmission main, are used to define criteria to evaluate the performance of a damaged BWP. Based upon the finite element results obtained in this study, suggestions for future work are presented and discussed. INTRODUCTION Since 1942, concrete cylinder pipe, commonly known as bar-wrapped pipe or pre- tensioned pipe, has been used in pipelines due to its reliability, cost effectiveness and durability. Typically, BWP is manufactured in standard diameters of 10 to 72 inches, with design pressures up to 400 psi and varying external earth loads. Although BWP resembles prestressed concrete cylinder pipe (“PCCP”), lined cylinder type, BWP and PCCP utilize different structural components to carry the loads. The steel cylinder in 457 Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance –—Doing More with Less © ASCE 2012

description

Barwrapped pipe failures

Transcript of 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

Page 1: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

Failure Risk of Bar-Wrapped Pipe with Broken Bars and Corroded Cylinder

Ali Alavinasab1, Muthu Chandrasekaran2, Edward Padewski III3

1 Pure Technologies, 3322 State Route 22 West, Suite 902, Building 9, Branchburg, NJ 08876; PH (908) 526-6600; FAX (908) 526-9900; email: [email protected] 2 Pure Technologies, 8920 State Route 108, Suite D Columbia, MD 21045; PH (443) 766-7873; FAX (443) 766-7877; email: [email protected] 3 Pure Technologies, 3322 State Route 22 West, Suite 902, Building 9, Branchburg, NJ 08876; PH (908) 526-6600; FAX (908) 526-9900; email: [email protected] ABSTRACT Bar-wrapped pipe (“BWP”) commonly used in pressure pipelines due to its reliability, cost effectiveness and durability. Failure of BWP can occur as a result of long term leakage and subsequent corrosion or as a result of leakage and deterioration of the reinforcing bars over time. The failure can also be the direct result of a transient pressure or other sudden catastrophic events. The consequence of failure may result in a significant disruption of operation and service for a water utility without any warning. This is a concern because assessing the condition of a damaged BWP is very challenging. In this paper, a nonlinear finite element analysis was used to evaluate the performance of a damaged BWP. For the structural evaluation, stresses and strains developed in the damaged BWP were evaluated. Cracking and spalling of the mortar lining will eventually lead to the corrosion of the steel components. In an effort to account for the steel deterioration, the model was adjusted by reducing the thickness of the steel cylinder. This study investigates the behavior of a deteriorating BWP under various levels of distress and various internal pressures. The results based on a 24-inch pipe transmission main, are used to define criteria to evaluate the performance of a damaged BWP. Based upon the finite element results obtained in this study, suggestions for future work are presented and discussed.

INTRODUCTION Since 1942, concrete cylinder pipe, commonly known as bar-wrapped pipe or pre-tensioned pipe, has been used in pipelines due to its reliability, cost effectiveness and durability. Typically, BWP is manufactured in standard diameters of 10 to 72 inches, with design pressures up to 400 psi and varying external earth loads. Although BWP resembles prestressed concrete cylinder pipe (“PCCP”), lined cylinder type, BWP and PCCP utilize different structural components to carry the loads. The steel cylinder in

457Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 2: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

PCCP acts primarily as a water barrier, not a structural member. This is not the case with BWP where the steel cylinder is one of the key structural components. BWP is essentially a steel pipe that is stiffened with steel reinforcing bars; therefore, the failure mechanism of BWP tends to be the same as that of a steel pipe. Unlike PCCP, where failure typically involves a bursting of the pipe due to broken wire wraps, the failure of BWP usually involves leaking due to a hole in the cylinder. This may be a flowing leak or a weeping leak, depending on the condition of the concrete lining. An electromagnetic (“EM”) inspection can be a successful means of performing a condition assessment of a pipeline composed of BWP with the understanding that the EM inspection will only provide data about the current condition of the pipeline. To evaluate the design and the risk of failure associated with specific pipe sections, a structural evaluation, based on a finite element analysis, can provide insight into the future serviceability of a pipeline following an EM inspection. Increasing levels of distress can be evaluated to determine the reliability of the pipeline as the condition deteriorates. This type of investigation was used to inform the City of Calgary Water Department whether or not the pipes were adequately designed and to provide data and performance curves to assist the city in making management decisions for the 24-inch Rundle Feedermain BWP. A structural evaluation was performed to determine if any pipe sections were approaching one of the failure limit states, which can help prevent ruptures similar to the one that occurred on July 14, 2011. The performance of BWP is directly related to the condition of the rebars and the steel cylinder in the pipes. A Finite Element Analysis (FEA) was performed to predict the failure of PCCP due to an increasing number of broken wire wraps [1-8]. Based on the limited amount of literature available, the effects of broken rebars and corrosion in the steel cylinder have not been thoroughly investigated for BWP as compared to that of PCCP. The objective of this study is to investigate the effect that broken rebar and corrosion in the steel cylinder has on the structural integrity of a distressed BWP using three-dimensional (“3D”) FEA. A 24-inch (0.61 m) BWP was considered with two (2), five (5), ten (10), fifteen (15) and 25 broken rebars for this investigation. Based on the FEA results, a risk analysis was performed for the 24-inch Rundle Feedermain BWP located in Calgary. MODEL FORMULATION BWP is comprised of a welded steel cylinder that creates a watertight membrane and helically wrapped, pre-tensioned, steel reinforcing bars wrapped around the cylinder to provide additional strength. An internal concrete lining and external mortar coating provide corrosion protection to the steel components. Properties of the 24-inch BWP were obtained during site visits. Figure 1 shows the typical cross section of a BWP.

458Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 3: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

Figure 1. Cross section of a typical AWWA C303 Bar-Wrapped Pipe

Table 1 represents the field measurements of the inner and outer mortar of the Calgary 24-inch BWP.

Table 1 – Field measurement of mortar coating, Calgary 24 inch BWP Section Sample 1 Sample 2 Sample 3 Sample 4

Inner mortar (inch) 0.863 0.523 0.606 0.507 Outer mortar (inch) 0.872 0.854 0.800 0.802

Based on the data shown in Table 1, the average thickness of the inner and outer mortar used for the structural evaluation was 0.65 inches and 0.85 inches, respectively. FINITE ELEMENT ANALYSIS The finite element method (“FEM”) is a general method of structural analysis in which the solution of a problem in continuum mechanics is approximated by analyzing an assemblage of finite elements which are interconnected at a finite number of nodal points across the solution domain of the problem.

Figure 2. Geometry of BWP.

20 feet

24 inch

459Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 4: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

As shinner A comIt wafour-nthe pdegre3:

Breakwhenores, and wloweris the The correthe Fthe sdeterthe stforendama

hown in Figur diameter of

mmercial finas assumed tnode quadraipe. This tyees of freedo

kage in the n a significan

placing it iwill tend to r energy state controlling

FEA was psponding lo

FEA for the nsteel cylindeiorating expteel cylinder

nsic evaluatioage can be m

ure 2, the BWf 24 inches (0

nite element hat the inter

atic shell elemype of elemenom. The FE

Figur

rebar is oftent amount ofin a high-enreact with i

te (Fe2O3). Tfactor in a c

performed fss of thicknenumber of cer. The vaposing not or as well. Don of damag

modified to b

WP used in t0.61 m).

software (“Arface betweement (S4R)nt is charact

EM model of

e 3. 3-D fin

en due to sigf energy is p

nergy state. its environmThe environmcorrosion rea

for a differeess in the ste

continuous balues are baonly the reinDepending oged pipes in etter represe

the analysis h

ABAQUS”)en the rebarwas used forterized by thf the pipe wi

ite element m

gnificant corplaced into th

Therefore, ment (e.g., oment surrouaction.

ent number eel cylinder.

bar breaks anased on thenforcement bon the envira particular

ent the actua

has a length

) was used foand the morr modeling t

hree displaceith shell elem

model of BW

rrosion overhe steel durinsteel is ther

oxygen or wunding the re

of broken . Table 2 prnd the percee assumptiobars to a coronment andsystem, the

al conditions

h of 20 feet (6

or the numerrtar coating the undamagement and thments is sho

WP

r time. Corrng its extracrmodynamic

water) in ordebar and the

reinforcemresents the vntage of thicn the morta

orrosive envid, if possiblee amount of .

6.1 m) and a

rical analysiis perfect. A

ged portion ohree rotationaown in Figur

rosion beginction from thcally unstablder to reach steel cylinde

ment bars anvalues used ickness lost iar coating ironment, bue, external osteel cylinde

an

s. A of al re

ns he le a

er

nd in in is ut or er

460Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 5: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

Table 2 – FEA Damage Propagation in the Calgary 24 inch BWP No. of Continuous

Bar Breaks Percentage of steel cylinder

thickness lost in damaged zone 0 0 % 5 10 % 11 20 % 15 40 % 20 60 % 25 80 %

Material properties for the BWP were obtained using American Water Works Association (“AWWA”) C304 Standard [13]. The Young’s modulus, density and Poisson’s ratio used in the model are presented in Table 3.

Table 3: Material properties of PCCP based on AWWA C304 Standard

Young’s modulus (GPa) / (psi)

Density ( 3mkg ) / (lb/ft3) Poisson’s ratio

Mortar Coating 25.1 / 3.64E6 2242.58 / 140 0.2 Steel Cylinder 206.84 / 3E7 7832.8 / 489 0.3

RESULTS AND DISCUSSION The nonlinear response of a BWP to internal pressure and external loading is obtained using a FEA. Cracks occur at the mortar coating where the concrete tensile load exceeds the concrete tensile strength. Since cracking is considered a stage of deterioration which causes corrosion in the steel cylinder, realistic cracking models need to be developed in order to accurately predict the load-deformation behavior. Figure 4 demonstrates the stresses in the rebars, the steel cylinder, and the inner and outer mortar coatings with five broken rebars and a 10% steel cylinder loss in the damaged zone. In these figures, the color gradients indicate the calculated stress for each element in the FEA model.

a) Stress in the rebar

Damaged Area (Broken Rebar/Corroded Cylinder)

Undamaged Area (No Broken Rebar)

461Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 6: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

b) Stress in the coating

c) Stress in the inner liner

Figure 4. Stresses in the 24 inch BWP with five (5) broken rebars and a 10% loss of steel Figure 5 represents the damage in the mortar coating, caused by excessive tension, for the Calgary 24 inch BWP.

Inner Coating

Outer Coating

462Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 7: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

Figure 5. Tension damage in 24 inch BWP with five (5) broken rebars and a 10% loss of

steel in the damaged zone.

A risk analysis evaluates the impact of a growing number of broken rebars, and the subsequent corrosion of the steel cylinder, on the performance of the pipe and determines the corresponding risk of failure resulting from this damage. Failure risk is expressed in terms of limit states that relate to serviceability (micro cracking and visible cracking), damage, and ultimate deflection of the pipe. The micro cracking limit state is based on the onset of cracking in the inner or outer mortar coating. It is further defined as a 1/16-inch crack at 12 inches in length. The visible cracking limit state is defined as a crack greater than 0.086 inches wide and 12 inches in length. The damaged limit state is based on structural cracking of the coating, which exposes the cylinder to corrosion, and an increase in deflection of the pipe based on Spangler’s equation. The ultimate deflection limit state is based on a critical deflection of the pipe which represents severe damage and changes in the geometry of the pipe section. Based on this analysis, performance curves were generated which denote the aformentioned limit states in terms of the number of contiguous broken rebars and a corroded steel cylinder versus the maximum deflection for different internal pressures and a given external load.

463Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 8: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

EXPECTED DETERIORATION OF BWP When steel reinforcing bars break or the steel cylinder corrodes, a pipe's strength is significantly reduced at the area of damage. The ends of the reinforcing bars retract, and then react to the constrictive forces of friction being applied by the mortar coating. These friction forces enable the reinforcing bars to redevelop their tension over a relatively short distance from the point of breakage. The length of the rebar that needs to be firmly encased in the mortar in order to redevelop the tensile strength can vary up to several feet depending on the size of the reinforcing bar and the level of corrosion, as well as the condition and quality of the mortar coating. The redevelopment of the tensile strength is referred to as bond. When the coating becomes soft, cracks, or is delaminated from the steel cylinder, the rebar’s bond to the mortar is reduced and the redevelopment length is increased significantly. Since it is not practical to understand the individual rebar’s bond for each pipe section, a conservative assumption must be made for modeling purposes. The most conservative assumption is to remove the broken rebars and reduce the thickness of the steel cylinder in the damaged zone. This is overly conservative and unrealistic. In this scenario, according to the structural model, the pipe would fail at the ultimate deflection limit. When actual information of the localized damage is incorporated, the performance risk curves predict that the ultimate strength of the pipe would occur at the ultimate deflection curve. It is important to understand that if conditions exist in a pipe section that lead to a thinner steel cylinder in the damaged zone than what was used for the analysis, the models indicate that the pipe section would fail prior to reaching the curve.

If the mortar coating becomes delaminated, the rebars may not be bonded for the entire damaged area. Also, if the mortar is under attack by aggressive soil and groundwater conditions surrounding the pipeline, the bond will be reduced. Based on this analysis, performance risk curves were generated which show the limit states in terms of the number of contiguous broken rebars, the loss of the thickness of steel cylinder steel cylinder and the different internal pressures for a given external load. The performance risk curve for the Calgary 24-inch BWP is shown below in Figure 6.

464Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 9: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

Figure 6. Expected deflection for BWP at various levels of deterioration

The maximum number of broken rebars and the corrosion of the steel cylinder required to reach the limit states under operational and surge conditions for each pipe was calculated using the FEA performance risk curves. Table 4 summarizes the FEA condition rating based on the quantity of wire breaks.

Table 4 - FEA Condition Rating based on the Design Working Pressures

Pressure (psi) Limit State Broken Rebars / % of cylinder thickness lost When Microcracking Occurs When Damage Occurs

40 0/0% 22/70% 60 0/0% 17/50% 80 0/0% 10/20% 100 0/0% 0/0%

CONCLUSIONS In this study, the numerical FEM was used to determine the performance of BWP at various levels of deterioration. The effects of broken rebars and corrosion in steel cylinder of a 24-in BWP (61 cm) were investigated under combined internal pressures and external earth loads. The results were shown for the pipe with (i) 2 broken rebars and 5% corrosion in steel cylinder, (ii) 5 broken rebars and 10% corrosion in steel cylinder, (iii) 10 broken rebars and 20% corrosion in steel cylinder, (iv) 15 broken rebars and 40% corrosion in steel cylinder, (v) 20 broken rebars and 60% corrosion in steel cylinder and (vi) 25 broken rebars and 80% corrosion in steel cylinder. The results indicates the

465Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012

Page 10: 2012 Failure Risk of Bar Wrapped Pipe With Broken Bars and Corroded Cylinder (1)

deflection based performance of the pipe change significantly when the level of damage increases. Utility owners can use the proposed method to assess risk of failure of BWP based on condition data. Broken rebars and corrosion in steel cylinder can be obtained by physical testing, electromagnetic inspections or other testing. Based on the collected data and the proposed performance curve, an estimation of remaining useful life in a BWP main can be obtained. REFERENCES [1] Zarghamee, M. S., Eggers, D. W., Ojdrovic, R. P., and Rose, B., (2003). “Risk analysis of Prestressed concrete cylinder pipe with broken wires.” Int. Conf. on Pipeline Eng. and Construction, ASCE, Baltimore, MD, 599-609. [2] Zarghamee, M. S., Eggers, D., and Ojdrovic, R. P., (2002). “Finite element modeling of failure of PCCP with broken wires subjected to combined loads.” Beneath Our Feet: Challengers and Solutions (CD-ROM), ASCE Press, Reston, VA. [3] Erbay, O. O., Zarghamee, M. S., and Ojdrovic, R. P., (2007). “Failure risk analysis of lined cylinder pipes with broken wires and corroded cylinder.” Int. Conf. on Pipeline Eng. and Construction, ASCE, Boston, MA, 1-10. [4] Xionga, H., Li, P., and Lia, Q., (2010) “FE model for simulating wire-wrapping during prestressing of an embedded prestressed concrete cylinder pipe.” Simul. Model. Prac. Theo. 18(5), 624-636. [5] Lewis, R. A., Wheatley, M., (2003). “Prestressed Concrete Cylinder Pipeline Evaluation, A Toolbox Approach.” Int. Conf. on Pipeline Eng. and Construction, ASCE, Baltimore, MD, 276-285. [6] Alavinasab,A., Padewski E., Holley, M., Jha R., Ahmadi, G., (2010). “Damage Identification Based on Vibration Response of Prestressed Concrete Pipes.” ASCE Pipelines Conf.: Climbing New Peaks to Infrastructure Reliability —Renew, Rehab, and Reinvest, Keystone, CO, 909-919. [7]Alavinasab, A., Padewski, E., Holley, M., Jha, R., Ahmadi, G., “Crack Propagation in Prestressed Concrete Noncylinder Pipe using Finite Element Method,” ASCE Pipelines Conf.: A Sound Conduit for Sharing Solutions, Seattle, WA, 420-426. [8]Alavinasab, A., Jha, R., Ahmadi, G., “Damage Identification based on Modal Analysis of Prestressed Concrete Pipes,” ASCE Pipelines Conf.: A Sound Conduit for Sharing Solutions, Seattle, WA, 12-23. [9] American Water Works Association (2007), “AWWA C304 Standard for Design of Prestressed Concrete Cylinder Pipe.” Denver, CO. [10] American Water Works Association (2009), “AWWA C303 Standard for Design of Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type.” Denver, CO.

466Pipelines 2012: Innovations in Design, Construction, Operations, and Maintenance–—Doing More with Less © ASCE 2012