2010/10/06 Areva EPR DC - DRAFT Response to U.S. EPR ... · 6 From: BRYAN Martin (EXT) Sent:...
Transcript of 2010/10/06 Areva EPR DC - DRAFT Response to U.S. EPR ... · 6 From: BRYAN Martin (EXT) Sent:...
1
ArevaEPRDCPEm Resource
From: BRYAN Martin (EXTERNAL AREVA) [[email protected]]Sent: Wednesday, October 06, 2010 10:54 AMTo: Tesfaye, GetachewCc: DELANO Karen (AREVA); ROMINE Judy (AREVA); BENNETT Kathy (AREVA); LENTZ Tony
(EXTERNAL AREVA); HALLINGER Pat (EXTERNAL AREVA); WILLIFORD Dennis (AREVA); RYAN Tom (AREVA)
Subject: DRAFT Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Attachments: RAI 386 Supplement 6 Response US EPR DC - DRAFT.pdf
Getachew, Attached is a draft response for questions: 14.02-151 14.02-152 14.02-156 14.02-158 14.02-159 14.03.08-2 Please let me know if the staff has questions or if these can be sent as final. Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
From: BRYAN Martin (External RS/NB) Sent: Wednesday, September 22, 2010 12:31 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); LENTZ Tony (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Supplement 5
Getachew, AREVA NP Inc. provided a schedule for technically correct and complete responses to the 24 questions in RAI No. 386 on June 3, 2010. Supplement 1, Supplement 2, Supplement 3, and Supplement 4 responses to RAI No. 386 were sent on July 15, 2010, August 12, 2010, August 26, 2010, and September 9, 2010, respectively, to provide a revised schedule. To provide additional time to interact with the NRC, a revised schedule is provided in this e-mail for the response to the questions. The schedule for technically correct and complete responses to the questions has been revised and is provided below:
2
Question # Response Date RAI 386 — 14.02-149 October 28, 2010 RAI 386 — 14.02-150 October 28, 2010 RAI 386 — 14.02-151 October 28, 2010 RAI 386 — 14.02-152 October 28, 2010 RAI 386 — 14.02-153 October 28, 2010 RAI 386 — 14.02-154 October 28, 2010 RAI 386 — 14.02-155 October 28, 2010 RAI 386 — 14.02-156 October 28, 2010 RAI 386 — 14.02-157 October 28, 2010 RAI 386 — 14.02-158 October 28, 2010 RAI 386 — 14.02-159 October 28, 2010 RAI 386 — 14.02-160 October 28, 2010 RAI 386 — 14.03.02-44 October 28, 2010 RAI 386 — 14.03.02-45 October 28, 2010 RAI 386 — 14.03.02-46 October 28, 2010 RAI 386 — 14.03.02-47 October 28, 2010 RAI 386 — 14.03.02-48 October 28, 2010 RAI 386 — 14.03.02-49 October 28, 2010 RAI 386 — 14.03.02-50 October 28, 2010 RAI 386 — 14.03.02-51 October 28, 2010 RAI 386 — 14.03.03-37 October 28, 2010 RAI 386 — 14.03.03-46 October 28, 2010 RAI 386 — 14.03.08-2 October 28, 2010 RAI 386 — 14.03.08-3 October 28, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
From: BRYAN Martin (External RS/NB) Sent: Thursday, September 09, 2010 2:30 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); LENTZ Tony (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Supplement 4
Getachew, AREVA NP Inc. provided a schedule for technically correct and complete responses to the 24 questions in RAI No. 386 on June 3, 2010. AREVA NP Inc. provided technically correct and complete draft responses to 11 of the 24 questions in “RAI 386 Supplement 1 Response – DRAFT.pdf” on July 8, 2010. A revised schedule was provided in Supplement 1 on July 15, 2010, in Supplement 2 on August 12, 2010, and in Supplement 3 on August 26, 2010. To allow time for interaction between AREVA and the NRC staff, a revised schedule for submittal of final responses is provided in this e-mail.
3
The schedule for technically correct and complete responses to the questions has been revised and is provided below: Question # Response Date RAI 386 — 14.02-149 October 28, 2010 RAI 386 — 14.02-150 October 28, 2010 RAI 386 — 14.02-151 October 14, 2010 RAI 386 — 14.02-152 October 14, 2010 RAI 386 — 14.02-153 October 28, 2010 RAI 386 — 14.02-154 October 28, 2010 RAI 386 — 14.02-155 October 28, 2010 RAI 386 — 14.02-156 October 14, 2010 RAI 386 — 14.02-157 October 28, 2010 RAI 386 — 14.02-158 October 14, 2010 RAI 386 — 14.02-159 October 14, 2010 RAI 386 — 14.02-160 October 28, 2010 RAI 386 — 14.03.02-44 September 23, 2010 RAI 386 — 14.03.02-45 September 23, 2010 RAI 386 — 14.03.02-46 October 28, 2010 RAI 386 — 14.03.02-47 October 28, 2010 RAI 386 — 14.03.02-48 October 28, 2010 RAI 386 — 14.03.02-49 September 23, 2010 RAI 386 — 14.03.02-50 September 23, 2010 RAI 386 — 14.03.02-51 September 23, 2010 RAI 386 — 14.03.03-37 September 23, 2010 RAI 386 — 14.03.03-46 October 28, 2010 RAI 386 — 14.03.08-2 September 23, 2010 RAI 386 — 14.03.08-3 September 23, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
From: BRYAN Martin (External RS/NB) Sent: Thursday, August 26, 2010 8:27 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); LENTZ Tony (External RS/NB) Subject: Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Supplement 3
Getachew, AREVA NP Inc. provided a schedule for technically correct and complete responses to the 24 questions in RAI No. 386 on June 3, 2010.
4
AREVA NP Inc. provided technically correct and complete draft responses to 11 of the 24 questions in “RAI 386 Supplement 1 Response – DRAFT.pdf” on July 8, 2010. A revised schedule was provided in Supplement 1 on July 15, 2010 and in Supplement 2 on August 12, 2010. To allow time for interaction between AREVA and the NRC staff, a revised schedule for submittal of final responses is provided in this e-mail. The schedule for technically correct and complete responses has been revised and is provided below: Question # Response Date RAI 386 — 14.02-149 September 9, 2010 RAI 386 — 14.02-150 September 9, 2010 RAI 386 — 14.02-151 October 14, 2010 RAI 386 — 14.02-152 October 14, 2010 RAI 386 — 14.02-153 September 9, 2010 RAI 386 — 14.02-154 September 9, 2010 RAI 386 — 14.02-155 September 9, 2010 RAI 386 — 14.02-156 October 14, 2010 RAI 386 — 14.02-157 September 9, 2010 RAI 386 — 14.02-158 October 14, 2010 RAI 386 — 14.02-159 October 14, 2010 RAI 386 — 14.02-160 September 9, 2010 RAI 386 — 14.03.02-44 September 23, 2010 RAI 386 — 14.03.02-45 September 23, 2010 RAI 386 — 14.03.02-46 September 9, 2010 RAI 386 — 14.03.02-47 September 9, 2010 RAI 386 — 14.03.02-48 September 9, 2010 RAI 386 — 14.03.02-49 September 23, 2010 RAI 386 — 14.03.02-50 September 23, 2010 RAI 386 — 14.03.02-51 September 23, 2010 RAI 386 — 14.03.03-37 September 23, 2010 RAI 386 — 14.03.03-46 September 9, 2010 RAI 386 — 14.03.08-2 September 23, 2010 RAI 386 — 14.03.08-3 September 23, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
From: BRYAN Martin (EXT) Sent: Thursday, August 12, 2010 6:02 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen (RS/NB); ROMINE Judy (RS/NB); BENNETT Kathy (RS/NB); LENTZ Tony F (EXT) Subject: Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Supplement 2
5
Getachew, AREVA NP Inc. provided a schedule for technically correct and complete responses to the 24 questions in RAI No. 386 on June 3, 2010. A revised schedule was provided in Supplement 1 on July 15, 2010. AREVA NP Inc. provided technically correct and complete DRAFT responses to 7 of the 24 questions in “RAI 386 Supplement 1 Response – DRAFT.pdf” on July 8, 2010. To allow time for interaction between AREVA and the NRC staff, a revised schedule for submittal of final responses for these 7 questions is provided in this e-mail.
The schedule for technically correct and complete responses to the questions has been revised and is provided below: Question # Response Date RAI 386 — 14.02-149 September 9, 2010 RAI 386 — 14.02-150 September 9, 2010 RAI 386 — 14.02-151 August 26, 2010 RAI 386 — 14.02-152 August 26, 2010 RAI 386 — 14.02-153 September 9, 2010 RAI 386 — 14.02-154 September 9, 2010 RAI 386 — 14.02-155 September 9, 2010 RAI 386 — 14.02-156 August 26, 2010 RAI 386 — 14.02-157 September 9, 2010 RAI 386 — 14.02-158 August 26, 2010 RAI 386 — 14.02-159 August 26, 2010 RAI 386 — 14.02-160 September 9, 2010 RAI 386 — 14.03.02-44 August 26, 2010 RAI 386 — 14.03.02-45 August 26, 2010 RAI 386 — 14.03.02-46 August 26, 2010 RAI 386 — 14.03.02-47 August 26, 2010 RAI 386 — 14.03.02-48 August 26, 2010 RAI 386 — 14.03.02-49 August 26, 2010 RAI 386 — 14.03.02-50 August 26, 2010 RAI 386 — 14.03.02-51 August 26, 2010 RAI 386 — 14.03.03-37 August 26, 2010 RAI 386 — 14.03.03-46 August 26, 2010 RAI 386 — 14.03.08-2 August 26, 2010 RAI 386 — 14.03.08-3 August 26, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
6
From: BRYAN Martin (EXT) Sent: Thursday, July 15, 2010 1:03 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen V (AREVA NP INC); ROMINE Judy (AREVA NP INC); BENNETT Kathy A (OFR) (AREVA NP INC); LENTZ Tony F (EXT) Subject: Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Supplement 1
Getachew, AREVA NP Inc. provided a schedule for technically correct and complete responses to the 24 questions in RAI No. 386 on June 3, 2010. AREVA NP Inc. provided technically correct and complete DRAFT responses to 7 of the 24 questions in RAI No. 386 on July 8, 2010. To allow additional time for interaction between AREVA and the NRC staff, a revised schedule for submittal of final responses for these 7 questions is provided in this e-mail (386-14.02-149, 150, 153, 154, 155, 157 and 160). The schedule for technically correct and complete responses to the questions has been revised and is provided below: Question # Response Date RAI 386 — 14.02-149 August 12, 2010 RAI 386 — 14.02-150 August 12, 2010 RAI 386 — 14.02-151 August 26, 2010 RAI 386 — 14.02-152 August 26, 2010 RAI 386 — 14.02-153 August 12, 2010 RAI 386 — 14.02-154 August 12, 2010 RAI 386 — 14.02-155 August 12, 2010 RAI 386 — 14.02-156 August 26, 2010 RAI 386 — 14.02-157 August 12, 2010 RAI 386 — 14.02-158 August 26, 2010 RAI 386 — 14.02-159 August 26, 2010 RAI 386 — 14.02-160 August 12, 2010 RAI 386 — 14.03.02-44 August 26, 2010 RAI 386 — 14.03.02-45 August 26, 2010 RAI 386 — 14.03.02-46 August 26, 2010 RAI 386 — 14.03.02-47 August 26, 2010 RAI 386 — 14.03.02-48 August 26, 2010 RAI 386 — 14.03.02-49 August 26, 2010 RAI 386 — 14.03.02-50 August 26, 2010 RAI 386 — 14.03.02-51 August 26, 2010 RAI 386 — 14.03.03-37 August 26, 2010 RAI 386 — 14.03.03-46 August 26, 2010 RAI 386 — 14.03.08-2 August 26, 2010 RAI 386 — 14.03.08-3 August 26, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager
7
AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
From: BRYAN Martin (EXT) Sent: Thursday, June 03, 2010 7:02 PM To: 'Tesfaye, Getachew' Cc: DELANO Karen V (AREVA NP INC); ROMINE Judy (AREVA NP INC); BENNETT Kathy A (OFR) (AREVA NP INC); LENTZ Tony F (EXT); RYAN Tom (AREVA NP INC) Subject: Response to U.S. EPR Design Certification Application RAI No. 386(4306,4418,4532,4349,2666,4512,4341), FSAR Ch. 14
Getachew, Attached please find AREVA NP Inc.’s response to the subject request for additional information (RAI). The attached file, “RAI 386 Response US EPR DC.pdf” provides a schedule since a technically correct and complete response to the 24 questions is not provided. The following table indicates the respective pages in the response document, “RAI 386 Response US EPR DC.pdf,” that contain AREVA NP’s response to the subject questions. Question # Start Page End Page RAI 386 — 14.02-149 2 2 RAI 386 — 14.02-150 3 3 RAI 386 — 14.02-151 4 4 RAI 386 — 14.02-152 5 5 RAI 386 — 14.02-153 6 6 RAI 386 — 14.02-154 7 7 RAI 386 — 14.02-155 8 8 RAI 386 — 14.02-156 9 9 RAI 386 — 14.02-157 10 10 RAI 386 — 14.02-158 11 11 RAI 386 — 14.02-159 12 12 RAI 386 — 14.02-160 13 13 RAI 386 — 14.03.02-44 14 15 RAI 386 — 14.03.02-45 16 16 RAI 386 — 14.03.02-46 17 17 RAI 386 — 14.03.02-47 18 18 RAI 386 — 14.03.02-48 19 19 RAI 386 — 14.03.02-49 20 20 RAI 386 — 14.03.02-50 21 21 RAI 386 — 14.03.02-51 22 22 RAI 386 — 14.03.03-37 23 23 RAI 386 — 14.03.03-46 24 24 RAI 386 — 14.03.08-2 25 26 RAI 386 — 14.03.08-3 27 27 A complete answer is not provided for the 24 questions. The schedule for a technically correct and complete response to these questions is provided below.
8
Question # Response Date RAI 386 — 14.02-149 July 15, 2010 RAI 386 — 14.02-150 July 15, 2010 RAI 386 — 14.02-151 August 26, 2010 RAI 386 — 14.02-152 August 26, 2010 RAI 386 — 14.02-153 July 15, 2010 RAI 386 — 14.02-154 July 15, 2010 RAI 386 — 14.02-155 July 15, 2010 RAI 386 — 14.02-156 August 26, 2010 RAI 386 — 14.02-157 July 15, 2010 RAI 386 — 14.02-158 August 26, 2010 RAI 386 — 14.02-159 August 26, 2010 RAI 386 — 14.02-160 July 15, 2010 RAI 386 — 14.03.02-44 August 26, 2010 RAI 386 — 14.03.02-45 August 26, 2010 RAI 386 — 14.03.02-46 August 26, 2010 RAI 386 — 14.03.02-47 August 26, 2010 RAI 386 — 14.03.02-48 August 26, 2010 RAI 386 — 14.03.02-49 August 26, 2010 RAI 386 — 14.03.02-50 August 26, 2010 RAI 386 — 14.03.02-51 August 26, 2010 RAI 386 — 14.03.03-37 August 26, 2010 RAI 386 — 14.03.03-46 August 26, 2010 RAI 386 — 14.03.08-2 August 26, 2010 RAI 386 — 14.03.08-3 August 26, 2010 Sincerely, Martin (Marty) C. Bryan U.S. EPR Design Certification Licensing Manager AREVA NP Inc. Tel: (434) 832-3016 702 561-3528 cell [email protected]
From: Tesfaye, Getachew [mailto:[email protected]] Sent: Tuesday, May 04, 2010 1:52 PM To: ZZ-DL-A-USEPR-DL Cc: Keim, Andrea; Rasmussen, Richard; Dehmel, Jean-Claude; Bernal, Sara; Roach, Edward; Jeng, David; Hawkins, Kimberly; Ng, Ching; Dixon-Herrity, Jennifer; Miernicki, Michael; Colaccino, Joseph; ArevaEPRDCPEm Resource Subject: U.S. EPR Design Certification Application RAI No. 386(4306,4418,4532,4349,2666,4512,4341), FSAR Ch. 14
Attached please find the subject requests for additional information (RAI). A draft of the RAI was provided to you on April 6, 2010, and discussed with your staff on May 4, 2010. Drat RAI Question 14.03.02-47 was modified as a result of that discussion. The schedule we have established for review of your application assumes technically correct and complete responses within 30 days of receipt of RAIs. For any RAIs that cannot be answered within 30 days, it is expected that a date for receipt of this information will be provided to
9
the staff within the 30 day period so that the staff can assess how this information will impact the published schedule.
Thanks, Getachew Tesfaye Sr. Project Manager NRO/DNRL/NARP (301) 415-3361
Hearing Identifier: AREVA_EPR_DC_RAIs Email Number: 2096 Mail Envelope Properties (BC417D9255991046A37DD56CF597DB7107CE7286) Subject: DRAFT Response to U.S. EPR Design Certification Application RAI No. 386, FSAR Ch. 14, Sent Date: 10/6/2010 10:54:06 AM Received Date: 10/6/2010 10:54:31 AM From: BRYAN Martin (EXTERNAL AREVA) Created By: [email protected] Recipients: "DELANO Karen (AREVA)" <[email protected]> Tracking Status: None "ROMINE Judy (AREVA)" <[email protected]> Tracking Status: None "BENNETT Kathy (AREVA)" <[email protected]> Tracking Status: None "LENTZ Tony (EXTERNAL AREVA)" <[email protected]> Tracking Status: None "HALLINGER Pat (EXTERNAL AREVA)" <[email protected]> Tracking Status: None "WILLIFORD Dennis (AREVA)" <[email protected]> Tracking Status: None "RYAN Tom (AREVA)" <[email protected]> Tracking Status: None "Tesfaye, Getachew" <[email protected]> Tracking Status: None Post Office: AUSLYNCMX02.adom.ad.corp Files Size Date & Time MESSAGE 16509 10/6/2010 10:54:31 AM RAI 386 Supplement 6 Response US EPR DC - DRAFT.pdf 480451 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:
Response to
Request for Additional Information No. 386, Supplement 4 (4306, 4418, 4532, 4349, 2666, 4512, 4341), Revision 0, Supplement 6
5/4/2010
U. S. EPR Standard Design Certification AREVA NP Inc.
Docket No. 52-020 SRP Section: 14.02 - Initial Plant Test Program - Design Certification and New
License Applicants SRP Section: 14.03.02 - Structural and Systems Engineering - Inspections, Tests,
Analyses, and Acceptance Criteria SRP Section: 14.03.03 - Piping Systems and Components - Inspections, Tests,
Analyses, and Acceptance Criteria SRP Section: 14.03.08 - Radiation Protection Inspections, Tests, Analyses, and
Acceptance Criteria
Application Section: SRP 14.02 (NUREG 0800)
QUESTIONS for Quality and Vendor Branch 2 (ESBWR/ABWR) (CQVB) QUESTIONS for Health Physics Branch (CHPB)
QUESTIONS for Structural Engineering Branch 2 (ESBWR/ABWR Projects) (SEB2) QUESTIONS for Engineering Mechanics Branch 2 (ESBWR/ABWR Projects)
(EMB2)DRAFT
gineergine ing nce Criteria nce Criter
Components - InspComponents -ceptance Criteria ceptance Criteria
ection Inspectionstion Inspe , Tptance Criteria ptance Crite
ection: n: SRP 14.02 (NSRP 14.02 (N
lity and Vendor Brlity and Vendor B anTIONS for Health PhIONS for Health Ph
ctural Engineering Bctural Engineering Bor Engineering Mechor Engineering Me
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 2 of 9
Question 14.02-151:
Follow-up to RAI 313, Question 14.02-128
The response to RAI 14.02-128 refers to the criteria said to be contained in FSAR Section 9.3.2, Table 9.3.2-2 (Secondary Side). However, the current version of Table 9.3.2-2 does not provide this level of detail and the response does not commit to update Table 9.3.2-2 to ensure that the revised acceptance criteria are complemented with supporting FSAR data. The response should include a commitment to a parallel revision of Table 9.3.2-2 to ensure consistency.
Response to Question 14.02-151:
U.S. EPR FSAR Tier 2, Table 9.3.2-2—Secondary Side Sampling Points will be revised to include process instrument parameters.
Laboratory equipment used to measure grab samples is site-specific and is not specified in the U.S. EPR FSAR.
U.S. EPR FSAR Tier 2, Section 14.2.12.7.13, Subsection 5.1.4 and Section 14.2.12.18.5, Subsection 5.4 will be revised to reflect that laboratory equipment used to measure grab samples is site-specific and is not specified in the U.S. EPR FSAR.
FSAR Impact:
U.S. EPR FSAR Tier 2, Table 9.3.2-2 and Sections 14.2.12.7.13 and 14.2.12.18.5 will be revised as described in the response and indicated on the enclosed markup.
DRAFTite-specific and iite-specif
section 5.1.4 and Sectiosection 5.1.4 and Sectioratory equipment usedatory equipm
n the U.S. EPR FSAR. S. EPR
2-2 and Sections 14.2.12-2 and Sections 14.2.1onse and indicated on tonse and indicate
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 3 of 9
Question 14.02-152:
Follow-up to RAI 313, Question 14.02-129
The response to RAI 14.02-129 refers to the criteria said to be contained in FSAR Section 9.3.2, Table 9.3.2-2 (Secondary Side). However, the current version of Table 9.3.2-2 does not provide this level of detail and the response does not commit to update Table 9.3.2-2 to ensure that the revised acceptance criteria are complemented with supporting FSAR data. The response should commit to a parallel revision of Table 9.3.2-2 to ensure consistency.
Response to Question 14.02-152:
Refer to the Response to RAI 386, Question 14.02-151.
FSAR Impact:
The U.S. EPR FSAR will not be changed as a result of this question. this question. this question.
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 4 of 9
Question 14.02-156:
Follow-up to RAI 313, Question 14.02-137
The response to RAI 14.02-137 refers to the criteria said to be contained in FSAR Section 9.3.2, Table 9.3.2-2 (Secondary Side), but needs to include FSAR Table 9.3.2-1 (Primary Side). Also, the current versions of Tables 9.3.2-1 and 9.3.2-2 do not provide this level of detail and the response does not commit to update Tables 9.3.2-1 and 9.3.2-2 to ensure that the revised acceptance are complemented with supporting FSAR data. The response should commit to a revision of Tables 9.3.2-1 and 9.3.2-2 and include their citation in Test No. 155 to ensure consistency.
Response to Question 14.02-156:
U.S. EPR FSAR Tier 2, Table 9.3.2-1—Primary Side Sampling Points will be revised to include process instrument parameters.
Laboratory equipment used to measure grab samples is site-specific and is not specified in the U.S. EPR FSAR.
U.S. EPR FSAR Tier 2, Section 14.2.12.18.6, Subsections 2.3 and 5.4, and Section 14.2.12.12.9, Subsection 5.3 will be revised to include a citation to U.S. EPR FSAR Tier 2, Tables 9.3.2-1 and 9.3.2-2.
FSAR Impact:
U.S. EPR FSAR Tier 2, Table 9.3.2-1 and Sections 14.2.12.18.6 and 14.2.12.12.9 will be revised as described in the response and indicated on the enclosed markup. AF
Tng Points wng Po
s is site-specific and is s is site-specific and
, Subsections 2.3 and 5ections
RAFd to include a citation tod to include a cita
9.3.2-1 and Sections 19.3.2-1 and Sections
DRresponse and indicatedsponse and indicated
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 5 of 9
Question 14.02-158:
Follow-up to RAI 313, Question 14.02-139
The response to RAI 14.02-139 refers to the criteria said to be contained in FSAR Section 9.3.2, Table 9.3.2-2 (Secondary Side). The test needs to also cite FSAR Table 9.3.2-1 (Primary Side) since Test No. 204 is for sampling the primary and secondary systems. Omitting a citation of Table 9.3.2-1 results in the definition of an incomplete set of acceptance criteria. In addition, the current versions of Tables 9.3.2-1 and 9.3.2-2 do not provide this level of detail and the response does not commit to update Tables 9.3.2-1 and 9.3.2-2 to ensure that the revised acceptance are complemented with supporting FSAR data. The response should commit to a revision of Tables 9.3.2-1 and 9.3.2-2 and include their citation in Test No. 204 to ensure consistency.
Response to Question 14.02-158:
Refer to the Response to RAI 386, Question 14.02-151.
FSAR Impact:
The U.S. EPR FSAR will not be changed as a result of this question.
AFT. .
DRAF
a result of this questionof this
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 6 of 9
Question 14.02-159:
Follow-up to RAI 313, Question 14.02-140
The response to RAI 14.02-140 refers to the criteria said to be contained in FSAR Section 9.3.2, Table 9.3.2-2 (Secondary Side), but needs to include Table 9.3.2-1 for the primary side. The test is for failed fuel detection and the response should cite FSAR Table 9.3.2-1 (Primary Side) since Test No. 205 is for sampling the primary system. Omitting a citation of Table 9.3.2-1, results in the definition of an incomplete set of acceptance criteria. In addition, the current version of Table 9.3.2-1 does not provide this level of detail and the response does not commit to updating Table 9.3.2-1 to ensure that the revised acceptance are complemented with supporting FSAR data. Finally, the response refers to FSAR Section 11.5, Table 11.5-1 for supporting information. However, the current version of Table 11.5-1 does not provide this level of detail. The response should commit to a revision of Tables 9.3.2-1 and 11.5-1 and include their citation in Test No. 205 to ensure consistency.
Response to Question 14.02-159:
Refer to the response in RAI 386, Question 14.02-156 concerning the revision of U.S. EPR FSAR Tier 2, Table 9.3.2-1 and citation in U.S. EPR FSAR Tier 2, Section 14.2, Test No. 205.
Refer to the responses in RAI 273, Supplement 4, Questions 11.05-1 through 11.05-10 and RAI 290, Supplement 1 and 4, Question 11.05-15 concerning the revision of U.S. EPR FSAR Tier 2, Table 11.5-1.
FSAR Impact:
The U.S. EPR FSAR will not be changed as a result of this question.
DRAFT
.5.59.3.2-19.3.2
-156 concerning the rev-156 concerning the revEPR FSAR Tier 2, SectPR FSAR Ti
ment 4, Questions 11.0ment 4, Question05-15 concerning the re15 concerning the
ot be changed as a resube changed as a resu
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 7 of 9
Question 14.03.08-2:
Follow-up to RAI 43, Question 14.03.08-1
In response to RAI 43, Question 14.3.8-1, Supplement 1, Revision 0, the applicant revised Tier 1 to include additional detail for the Radiation Monitoring System, specifically ITAAC for the safety-related radiation monitors and a sentence describing the non safety related monitors. This revision is satisfactory except for the following which is needed to demonstrate compliance with 10 CFR Part 52.47(b)(1).
As detailed in Staff RAI 292, Question 14.3.7-33, dated September 18, 2009, the staff evaluation of the applicant’s responses to prior RAIs (RAI No. 43, 105, and 116) indicates that the approach being used in addressing ITAAC is based on previous certified designs and that the EPR FSAR Tier 1 incorporates safety significant features credited to comply with the requirements of 10 CFR Parts 20, 50, 52, 73, or 100. However, 10 CFR Part 52.47(b)(1) states that a design certification application must contain the following:
“The proposed inspections, tests, and analyses, …that the licensee shall perform, and the acceptance criteria that are necessary and sufficient to provide reasonable assurance that, if the inspections, tests, and analyses are performed and the acceptance criteria met, a facility that incorporates the design certification has been constructed and will be operated in conformity with the combined license, the provisions of the Act, and the Commission’s rules and regulations.”
The staff concludes that Tier 1 safety significant radiation protection structures, systems and components (SSC), which the applicant has credited for complying with the requirements of 10 CFR Part 20, do not contain sufficient detail to provide reasonable assurance that the facility will be constructed and operated in accordance with the Commission’s rules and regulations, specifically 10 CFR Part 20, GDC 63 and GDC 64. For this reason, RG 1.206 Part C.II states that additional Tier 1 and ITAAC detail should be provided for those SSCs necessary to demonstrate compliance with 10 CFR Part 20, although they are not safety-related SSCs. As an example, the AP1000 certified design which the applicant referenced in its response to RAI 43, Question 14.3.8-1, has recognized this and, therefore, includes Tier 1 information and ITAAC for the non-safety related radiation monitoring system relevant to demonstrating the design’s compliance with 10 CFR Part 20, GDC 63, and GDC 64 in accordance with 10 CFR Part 52.47(b)(1). Similarly, the ESBWR Design Certification Document (Rev. 6) includes specific ITAACs for area and airborne radiation monitors. The staff maintains that these radiation monitors are equivalent in purpose and safety significance to corresponding monitors in the U.S. EPR design, for which FSAR Tier 1, Rev. 1 does not provide equivalent ITAACs. Therefore the EPR’s non-safety related radiation monitoring system should include additional Tier 1 information and ITAACs in order to demonstrate compliance with NRC regulations.
It is recognized that the level of Tier 1 and ITAAC details for these systems will be less than that required for safety related SSCs. However, without sufficient details the staff cannot complete its evaluation and conclude, with reasonable assurance, that if the tests and inspections were performed and acceptance criteria were met, that all design commitments will be fulfilled and that the plant will be built and operated in accordance with the design certification and comply with applicable NRC regulations. Accordingly, the applicant is requested to provide Tier 1 information and ITAACs for the U.S. EPR radiation monitoring system as described above.
DRAFT
reditedrediteever, 10 CFRever,
owing: owing:
es, …that the licensee ses, …that the licensand sufficient to provideand sufficient to provide
and analyses are perfond analysess the design certificationesign c
the combined license, tthe combined licenulationsions.””
ety significant radiation ety significant radiation pplicant has credited fopplicant has credit
sufficient detail to providsufficient detail to proved in accordance with thn accordance with th
DRt 20, GDC 63 and GDC 20, GDC 63 a
and ITAAC detail shouldand ITAAC detail sliance with 10 CFR Parliance with 10 CFR PaP1000 certified desigP1000 certified dD, has recognize, has recogniz
y related ray related rD0 CF0 CF
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 8 of 9
Response to Question 14.03.08-2:
AREVA NP based its development of U.S. EPR FSAR Tier 1 on Standard Review Plan (SRP) 14.3. SRP 14.3 states that not all information required for compliance with regulations and described in Tier 2 is required to be in Tier 1 and have ITAAC. SRP 14.3 describes a graded approach to selecting information from Tier 2 and including that information in Tier 1 with ITAAC. SRP 14.3 specifies specific non-safety-related criteria for inclusion in Tier 1 such as severe accident, anticipated transient without scram (ATWS), and fire protection.
U.S. EPR FSAR Tier 2 material is screened to determine if it is ”safety significant” as described in U.S. EPR FSAR Tier 2, Section 14.3. This screening process uses criteria developed from SRP 14.3, Appendixes A and C. The first process uses discipline checklists that include ITAAC criteria based on guidance in SRP, Section 14.3. For example, the discipline checklist for systems provides guidance to create ITAAC for the following features:
Major safety-related features.
Equipment that is seismic, EQ, or 1E.
Safety-related equipment.
Design features provided for severe accident mitigation, station blackout (SBO), and ATWS.
Significant system features identified in the applicable SRPs for the system.
Significant safety-related (and non-safety-related) functions derived from those listed in system design requirements documents.
The second process involves an expert review panel that selects safety-significant features based on assumptions and insights from key safety and integrated plant safety analyses in U.S. EPR FSAR Tier 2, where plant performance is dependent on contributions from multiple systems. This process is based on guidance in SRP 14.3, Page 14.3-21. Results of the expert review panel meetings are provided in U.S. EPR FSAR Tier 2, Tables 14.3-1 through 14.3-7.
Specifically:
SRP 14.3, Appendix A, Page 14.3-16 states:
“The applicant should put the top-level design features and performance characteristics that were the most significant to safety in the Tier 1 design descriptions. The level of detail in Tier 1 is governed by a graded approach to the SSCs of the design, based on the safety significance of the functions they perform.”
“For example, safety-related SSCs should be described in Tier 1 with a relatively greater amount of information. Other SSCs should also be included based on their importance to safety, such as containment isolation aspects of non-safety systems. Some non-safety aspects of SSCs need not be discussed in Tier 1. This graded approach recognizes that although many aspects of the design are important to safety, the level of design detail in Tier 1 and verification of the key design features and performance characteristics should be commensurate with the significance of the safety functions to be performed.”
RAFT
heheeatureseature
nt mitigation, station blamitigation,
the applicable SRPs fo the applicable S
safety-related) functionty-related) functioncuments.
n expert review panel n expert review pan
DRAthnsights from key safety sights from key safety
plant performance is deperformance is deis based on guidance iis based on gu
DRgs are provided in U.S. gs are provided in U.
Page 14.3Page 14.3
AREVA NP Inc.
Response to Request for Additional Information No. 386, Supplement 6 U.S. EPR Design Certification Application Page 9 of 9
SRP 14.3, Page 14.3-17 states:
“The level of detail specified in the ITAAC should be commensurate with the safety significance of the functions and bases for that SSC.”
SRP 14.3, Appendix A, Page 14.3-21 states:
“The staff is particularly interested in ensuring that the assumptions and insights from key safety and integrated plant safety analyses in Tier 2, where plant performance is dependent on contributions from multiple systems of the design, are adequately considered in Tier 1.Addressing these assumptions and insights in Tier 1 ensures that the integrity of the fundamental analyses for the design are preserved in an as-built facility referencing the certified design. These analyses include flooding analyses, over-pressure protection, containment analyses, core cooling analyses, fire protection, transient analyses, anticipated transient without scram analyses, steam generator tube rupture analyses (PWRs only), radiological analyses, USIs/GSIs and TMI items, or other key analyses as specified by the staff. Therefore, applicants should provide information, in tabular form, in Section 14.3 that cross references the important design information and parameters of these analyses to their treatment in Tier 1. The cross-references should be sufficiently detailed to allow a COL applicant or licensee to consider whether a proposed design change impacts the treatment of these parameters in Tier 1.”
SRP 14.3, Appendix A, Page 14.3-17 states:
“Also, the scope of the ITAAC is consistent with the SSCs that are in the design descriptions. In general, each system has one or more ITAAC that verify the information in the design descriptions. The system ITAAC should verify that the key design characteristics and performance requirements of the SSCs are verified. The level of detail specified in the ITAAC should be commensurate with the safety significance of the functions and bases for that SSC.”
SRP 14.3, Appendix C, Page 14.3-24 states:
“This section is not repeated here, but it provides a discussion of what should be included as a ‘key feature’, and therefore by exclusion what does not have to be addressed in Tier 1and hence ITAAC.”
As is stated in this question, these non-safety-related monitors are less ”safety significant” than the safety-related monitors.
Lack of inclusion in U.S. EPR FSAR Tier 1 does not mean the COL applicant does not have to address the items described in U.S. EPR FSAR Tier 2. The COL applicant must comply with U.S. EPR FSAR Tier 2 or take exception to it. Further evidence of this is provided in the inspection manual chapters have separate chapters on ITAAC (IMC 2503) inspections and non-ITAAC (2504) inspections.
FSAR Impact:
The U.S. EPR FSAR will not be changed as a result of this question.
DRAFT
n, transn, trarupture anaruptu
her key analysesher key antion, in tabular form, intion, in tabular f
n and parameters of then and parameters of uld be sufficiently detailuld be sufficiently detail
proposed design changoposed des
tates: s:
s consistent with the SSs consistent with the SSch system has one or mch system has one
The system ITAAC shouThe system ITAAC shrements of the SSCs arments of the SSCs ar
mmensurate with the sammensurate w
x C, Page 14.3-24 stx C, Page 14.3-2Depeated heepeated hereforerefore
U.S. EPR Final Safety Analysis Report Markups
DRAFT
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 9.3-20
NOTE:
1. Specific properties of liquid and gaseous grab samples to be measured are identified in plant procedures.
Table 9.3.2-1—Primary Side Sampling Points
Process or EquipmentNumber of
Sample PointsType of Sample Process Measurement
LHSI / RHR 4 Grab See Note
CVCS 2 Process Boron, hydrogen, oxygen, conductivity and activity beta.
RCS 2 Process Boron, hydrogen, oxygen, conductivity and activity beta.
Pressurizer 1 Process Boron, hydrogen, oxygen, conductivity and activity beta.
CPS 6 Grab See Note
SIS accumulators 4 Grab See Note
RBWMS (boric acid pump) 2 Grab See Note
FPCS 2 Grab See Note
FPPS 2 Grab See Note
CDS 2 Grab See Note
CTS 2 Grab See Note
GWPS 4 Grab See Note
CSSS 1 Grab See Note
NIDVS (primary effluents) 3 Grab See Note
NSS (back feed tank) 1 Grab See Note
14.02-156
TTTTbb TFTGrabGrab
FTFTFTGrabG FTFTAFTGrabGrab
AFT
AFT
AFGrabGrab
AFAFRAF4 AGrabGrabAFRARA
1
RAGrabGrabARARA
33
RAG
RRADRA11RADRRA
DRSpecific properties of liqSpecific properties of liqDplant procedures.plant procedureDD
TTFTFTAFAFRARARADRD
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
1
Tab
le9.
3.2-
1—Pr
imar
y Si
de S
ampl
ing
Poin
ts S
heet
1 o
f 3
Proc
ess
orEq
uipm
ent
Num
ber
of S
ampl
ePo
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
tR
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
antic
ipat
eddr
ift b
etw
een
calib
ratio
ns4
LHSI
/RH
R4
Gra
bSe
e N
otes
1,2
CVCS
2Co
ntin
uous
Boro
n0.
015-
20 p
pb6
min
utes
± 3%
or 0
.005
pp
b,
whi
chev
er is
gr
eate
r
<1%
of r
eadi
ng
(per
yea
r)
Hyd
roge
n0-
10 p
pm20
seco
nds
± 3%
or ±
60
ppb,
whi
chev
er
is gr
eate
r
<1%
of r
eadi
ng
(per
yea
r)
Oxy
gen
0-20
,000
ppb
30 se
cond
s±
2 pp
b<1
% o
f rea
ding
(p
er y
ear)
Cond
uctiv
ity0.
02-2
,000
�S/
cm20
seco
nds
± 0.
1 °F
of
tem
pera
ture
<1%
of r
eadi
ng
(per
yea
r)
Act
ivity
(Bet
a)Se
e Ta
ble
11.5
-1
RCS
2Co
ntin
uous
Boro
n0.
015-
20 p
pb6
min
utes
± 3%
or 0
.005
pp
b, w
hich
ever
is
grea
ter
<1%
of r
eadi
ng
(per
yea
r)
Hyd
roge
n0-
10 p
pm20
seco
nds
± 3%
or ±
60
ppb,
whi
chev
er
is gr
eate
r
<1%
of r
eadi
ng
(per
yea
r)
Oxy
gen
0-20
,000
ppb
30 se
cond
s±
2 pp
b<1
% o
f rea
ding
(p
er y
ear)
Cond
uctiv
ity0.
02-2
,000
�S/
cm20
seco
nds
± 0.
1 °F
of
tem
pera
ture
± 0.
1 °F
of
tem
pera
ture
Act
ivity
(Bet
a)Se
e Ta
ble
11.5
-1
14.0
2-15
6
DRAFT
DSee
NSe
e N
DousousD
Boro
Bor
DHyd
roge
nH
ydro
genRyg
enenRA0-
20,0
00 p
p0-
20,0
0
RA0.
02-2
,000
�S/
cm02
-2,0
00 �
S/cm
AF5-2
0 pp
bFT6
min
ut6
min
utFT
DRAFFT
DDDRRAAFAFFTT20
secTTT
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
2
Pres
suri
zer
1Co
ntin
uous
Boro
n0.
015-
20 p
pb6
min
utes
± 3%
or 0
.005
pp
b, w
hich
ever
is
grea
ter
<1%
of r
eadi
ng
(per
yea
r)
Hyd
roge
n0-
10 p
pm20
seco
nds
± 3%
or ±
60
ppb,
whi
chev
er
is gr
eate
r
<1%
of r
eadi
ng
(per
yea
r)
Oxy
gen
0-20
,000
ppb
30 se
cond
s±
2 pp
b<1
% o
f rea
ding
(p
er y
ear)
Cond
uctiv
ity0.
02-2
,000
�S/
cm20
seco
nds
± 0.
1 °F
of
tem
pera
ture
<1%
of r
eadi
ng
(per
yea
r)
Act
ivity
(Bet
a)Se
e Ta
ble
11.5
-1
CPS
6G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
SIS
Acc
umul
ator
s4
Gra
bSe
e N
otes
1,2
,3N
/AN
/AN
/AN
/A
RBW
MS
(bor
ic
acid
pum
p)2
Gra
bSe
e N
otes
1,2
,3N
/AN
/AN
/AN
/A
FPCS
2G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
FPPS
2G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
CDS
2G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
CTS
2G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
GW
PS4
Gra
bSe
e N
otes
1,2
,3N
/AN
/AN
/AN
/A
CSSS
1G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Tab
le9.
3.2-
1—Pr
imar
y Si
de S
ampl
ing
Poin
ts S
heet
2 o
f 3
Proc
ess
orEq
uipm
ent
Num
ber
of S
ampl
ePo
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
tR
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
antic
ipat
eddr
ift b
etw
een
calib
ratio
ns4
14.0
2-15
6DRAFT
Hyd
roge
nyd
roge
n
DR
Oxy
gen
Oxy
genRA
0-
RAductivityivitRA0.
02-2
,000
.0
2-2,
000
RAeta)eta)AN
/AA
AFN/A
N/AF
NN TN
/AFN
/AN
/ATN/A
T
DRAFT
DDRRARAAFAFFTTTTT
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
3
Not
es:
1.Sp
ecifi
c pr
oper
ties o
f liq
uid
and
gase
ous g
rab
sam
ples
to b
e m
easu
red
are
iden
tifie
d in
pla
nt p
roce
dure
s.
2.La
bora
tory
inst
rum
ents
use
d to
mea
sure
gra
b sa
mpl
es a
re id
entif
ied
in p
lant
pro
cedu
res.
Man
ufac
ture
r’s o
pera
ting
man
ual s
hall
be c
onsu
lted
for c
alib
ratio
n, m
easu
ring
, mai
nten
ance
, and
cle
anin
g an
d st
orag
e re
quir
emen
ts.
3.Ca
libra
ting
gase
s and
solu
tion
for i
nstr
umen
tatio
n ar
e pe
r the
man
ufac
ture
r’s o
pera
ting
man
ual.
4.V
alue
s are
typi
cal;
the
actu
al v
alue
s will
mee
t or e
xcee
d th
e lis
ted
para
met
ers.
5.Co
ntin
uous
on-
line
mon
itori
ng sy
stem
s will
be
in a
ccor
danc
e w
ith A
STM
D 3
864.
6.Co
ntai
ns c
onta
inm
ent a
tmos
pher
e an
d IR
WST
.
NID
VS (
prim
ary
efflu
ents
)3
Gra
bSe
e N
otes
1,2
,3N
/AN
/AN
/AN
/A
NSS
(bac
kfee
d ta
nk)
1G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Seve
re A
ccid
ent
Sam
plin
g Sy
stem
(SA
SS)
2G
rab
See
Not
e 6
N/A
N/A
N/A
N/A
Tab
le9.
3.2-
1—Pr
imar
y Si
de S
ampl
ing
Poin
ts S
heet
3 o
f 3
Proc
ess
orEq
uipm
ent
Num
ber
of S
ampl
ePo
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
tR
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
antic
ipat
eddr
ift b
etw
een
calib
ratio
ns4
14.0
2-15
6
RAFT
grab
sam
ples
to b
e m
easu
grab
sam
ples
to b
e m
easu
Aampl
es a
re id
entif
ied
in p
ples
are
iden
tifie
d in
p
AFing, mainte
nanc
e, a
nd c
leg,
mai
nten
ance
, and
cl
AFper th
e m
anuf
actu
rer’s
op
per t
he m
anuf
actu
rer’s
op
FTlisted para
met
ers.
met
erTh A
STM
D 3
h A
STT
DRA
See
Not
e 6
See
Not
e 6
DRDRA
DRSee
Not
es
Not
DDDDDSee
See DDDDDRRA
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 9.3-24
Table 9.3.2-2—Secondary Side Sampling Points
Process or Equipment
Number of Sample Points Type of Sample
Process Measurement of Continuous Samples
SG blowdown 15 Continuous/grab Activity gamma, cation conductivity, specific
conductivity, sodium, and pH
Feedwater (upstream valve chamber)
1 Continuous/grab Specific conductivity, cation conductivity, pH and oxygen
Feedwater pumps discharge (combined with start-up
feedwater pump)
1 per pump (5 total)
Continuous/grab Hydrazine, specific conductivity, cation
conductivity, pH, O2 and Na
Main steam (upstream HP turbine)
4 Continuous/grab Cation conductivity, degassed cation conductivity and sodium
Main steam (downstream reheater)
2 Continuous/grab Cation conductivity, degassed cation conductivity and sodium
Reheater drains 4 Continuous/grab Cation conductivity, degassed cation conductivity and Na
Auxiliary steam system 1 Grab
Auxiliary steam condensate 1 Grab
Condensate pump discharge 1 Continuous/grab Specific conductivity, cation conductivity, O2 and Na
Condensate polisher discharge Site specific Continuous/grab Cation conductivity, O2 and Na
Condenser hotwells 6 Continuous Cation conductivity, O2 and Na
Moisture separator drains 2 Grab
HP heater drains 2 Grab
LP heater drains 2 Grab
Clean drains 1 Grab
Demineralized water storage tank
1 Grab
Closed cooling water system 1 Grab
Circulating water cooling water basin makeup
1 Continuous pH/ORP and specific conductivity
14.02-151
AFT
grabgrab
TCatio
Tcation cocaTnuous/grabnuou
FTCation conCatio
FTcation cotion c
FTContinuous/grabContinuous/grFTCatioFTGrabrabAFAFTTTFTAFRAF1 AGrabGrabARARA
11
RAContinuoCo
RARRADRArge RSite specificSite specificRACoCoRADRRA
DRlss
D6RDRDRor drainsor dra D22RDRDainsains D2DDDDDAFRARADRDRDDD
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
5
Tab
le9.
3.2-
2—Se
cond
ary
Side
Sam
plin
g Po
ints
She
et 1
of 5
Proc
ess
or
Equi
pmen
t
Num
ber
of S
ampl
e Po
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
t of
Con
tinuo
us
Sam
ples
R
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
ant
icip
ated
dr
ift b
etw
een
calib
ratio
ns4
SG b
low
dow
n15
Cont
inuo
us/g
rab
Act
ivity
(g
amm
a)Se
e Ta
ble
11.5
-1
Catio
n Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
Spec
ific
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
pH1-
11 p
H30
seco
nds
±0.0
2 pH
<1%
of r
eadi
ng (p
er st
anda
rd
solu
tion
volu
me)
Feed
wat
er
(ups
trea
m
valv
e ch
ambe
r)
1Co
ntin
uous
/gra
bSp
ecifi
c Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
Catio
n Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
pH1-
11 p
H30
seco
nds
±0.0
2 pH
<1%
of r
eadi
ng (p
er st
anda
rd
solu
tion
volu
me)
Oxy
gen
0-20
,000
pp
b30
seco
nds
± 2
ppb
<1%
of r
eadi
ng (p
er y
ear)
14.0
2-15
1
FT30 seconds
FT±0
.02
.02
TFTFT0.
001
0.00
1
T(dep
ends
(dep
ends
FTAFT
30 se
cond
sse
conFTAF1000 1000 FAFFTFT
(d(d
FAFT
30 se
cond
s0
seco
nds
AFAF.06
to 1
000
to 1
00AF�S/cmcmAAFFT
AF30
se
ARAF
1-11
pH
1-11
pH
RARARAAF
RA0.1
– 10
00
0.1
–
RApp
b
RARAodiu
mod
iuRRAARA0.06
0.
06
R
�S/c
m�S
/
RDRA
Spec
ific
Spec
ific
DRConduct
ivity
uctiv
ity
DRDRCatio
n on
DConduct
ivity
duct
ivity
DRDAct
ivA
ctiv D(gamm
a)(g
amm
a
DDRDRA
DDDRRARAAFAFTTnd
snd
sTTFTT
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
6
Feed
wat
er
pum
ps
disc
harg
e (c
ombi
ned
with
star
t-up
fe
edw
ater
pu
mp)
1 pe
r pum
p (4
tota
l)Co
ntin
uous
/gra
bH
ydra
zine
0-
200
ppb
4 m
inut
es±2
ppb
<1%
of r
eadi
ng (p
er y
ear)
Spec
ific
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Catio
n Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
pH1-
11 p
H30
seco
nds
±0.0
2 pH
<1%
of r
eadi
ng (p
er st
anda
rd
solu
tion
volu
me)
Oxy
gen
0-20
,000
pp
b30
seco
nds
± 2
ppb
<1%
of r
eadi
ng (p
er y
ear)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Mai
n St
eam
(u
pstr
eam
HP
turb
ine)
4Co
ntin
uous
/gra
bCa
tion
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Deg
asse
d Ca
tion
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Mai
n St
eam
(d
owns
trea
m
rehe
ater
)
2Co
ntin
uous
/gra
bCa
tion
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Deg
asse
d Ca
tion
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Tab
le9.
3.2-
2—Se
cond
ary
Side
Sam
plin
g Po
ints
She
et 2
of 5
Proc
ess
or
Equi
pmen
t
Num
ber
of S
ampl
e Po
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
t of
Con
tinuo
us
Sam
ples
R
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
ant
icip
ated
dr
ift b
etw
een
calib
ratio
ns4
14.0
2-15
1
FT0.
001
t.0
01 t
T(depend
s ode
pend
s oFTFT30
seco
nds
conFTF00 00FFFTFT
±0.1
TFTminutessTFTFT
(dep
(dep
FTAFT
30 se
cond
s30
seco
nds
AFAF6 to 1000 100AF/cmcmAAFFTTds
0.TAF
2 m
in
AFRAF
0.1
– 10
00
0.1
– 10
00 AFpp
bpbARARAAF
RA0-
20,0
00
0
RApp
bpp
b
RARAygenRRAARA
1-11
1-
11
RDRA
pHHDRRARR
��
DRCatio
n io
n
DRCond
uctiv
ityCo
nduc
tivity
DRDSpecifi
cSp
ecifi
c
DConduct
ivity
Cond
uctiv
DDHyd
rH
ydr DDDRDDDRRARAAFFTFTT
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
7
Reh
eate
r D
rain
4Co
ntin
uous
/gra
bCa
tion
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Deg
asse
d Ca
tion
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Aux
iliar
y St
eam
Sys
tem
1G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Aux
iliar
y St
eam
Co
nden
sate
1G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Cond
ensa
te
Pum
p D
ischa
rge
1Co
ntin
uous
/gra
bSp
ecifi
c Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
Catio
n Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
Oxy
gen
0-20
,000
pp
b30
seco
nds
± 2
ppb
<1%
of r
eadi
ng (p
er y
ear)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Tab
le9.
3.2-
2—Se
cond
ary
Side
Sam
plin
g Po
ints
She
et 3
of 5
Proc
ess
or
Equi
pmen
t
Num
ber
of S
ampl
e Po
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
t of
Con
tinuo
us
Sam
ples
R
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
ant
icip
ated
dr
ift b
etw
een
calib
ratio
ns4
14.0
2-15
1
FT0 secondsT
± 2
pp2
pp
TFTFT000
000 F30 secon
ds0
seco
nFT0.
001
0.00
1
T(depend
s ep
ends
FTFFTFT
(de
(de
FTAFT
30 se
cond
s30
seco
nds
AFAF06 to 1000 100AFS/cmcmAAFFT
RAF
N/A
N/A
RARA1,2,3,3RARAAF
RA
N/A
N/
RADRA
e N
otes
1,2
,3N
otes
1,2
,3RARAAR0.0. R
pppp
RDRSodi
umSo
dium
DRDRDeg
asse
d Ca
tioD
egas
sed
Ca
DConduct
ivity
ctiv
DRDCaCa DCond
ucti
Cond
ucti
DDDRDDRDRRAAFAFTFTTte
stTTT
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
8
Cond
ensa
te
Polis
her
Disc
harg
e
Site
Spe
cific
Cont
inuo
us/g
rab
Catio
n Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
Oxy
gen
0-20
,000
pp
b30
seco
nds
± 2
ppb
<1%
of r
eadi
ng (p
er y
ear)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Cond
ense
r H
otw
ell
6Co
ntin
uous
Catio
n Co
nduc
tivity
0.06
to 1
000
�S/c
m30
seco
nds
0.00
1 to
1 �
S/cm
(d
epen
ds o
n ra
nge)
± 1%
of m
easu
red
valu
e or
±
digi
t (w
hich
ever
is g
reat
er)
Oxy
gen
0-20
,000
pp
b30
seco
nds
± 2
ppb
<1%
of r
eadi
ng (p
er y
ear)
Sodi
um0.
1 –
1000
pp
b2
min
utes
±0.1
ppb
<1%
of r
eadi
ng (p
er y
ear)
Moi
stur
e Se
para
tor
Dra
ins
2G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
HP
Hea
ter
Dra
in2
Gra
bSe
e N
otes
1,2
,3N
/AN
/AN
/AN
/A
LP H
eate
r D
rain
2G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Clea
n D
rain
s1
Gra
bSe
e N
otes
1,2
,3N
/AN
/AN
/AN
/A
Dem
iner
aliz
ed
wat
er st
orag
e ta
nk
1G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Tab
le9.
3.2-
2—Se
cond
ary
Side
Sam
plin
g Po
ints
She
et 4
of 5
Proc
ess
or
Equi
pmen
t
Num
ber
of S
ampl
e Po
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
t of
Con
tinuo
us
Sam
ples
R
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
ant
icip
ated
dr
ift b
etw
een
calib
ratio
ns4
14.0
2-15
1
FTN/ATN
/AN
/A
TFTAFT
/A/AAN
/AN
/A
AFT
AFFT
AF2
min
ute
min
ute
AFAF0.1
– 10
00
1000
AFppbbAAAAFFAF303
ARAF
0-20
,000
20
,000
RApp
bpp
b
RARAenRAAF
RA0.06
to 1
006
to
RA�S
/cm
�S
RADRA
Catio
n Ca
tionRductivityductivityRRAAR0.0. R
pppp
RDRSodi
umSo
dium
DRDROxy
gen
gen
DDCaCa DCond
ucti
Cond
ucti
DDDRDDRDRRAAFAFFTTTT
U.S
. EPR
FIN
AL
SAFE
TY A
NA
LYSI
S R
EPO
RT
Tier
2 R
evis
ion
3—
Inte
rim
Pag
e 9
.3-2
9
Not
es:
1.Sp
ecifi
c pr
oper
ties o
f liq
uid
and
gase
ous g
rab
sam
ples
to b
e m
easu
red
are
iden
tifie
d in
pla
nt p
roce
dure
s.
2.La
bora
tory
inst
rum
ents
use
d to
mea
sure
gra
b sa
mpl
es a
re id
entif
ied
in p
lant
pro
cedu
res.
Man
ufac
ture
r’s o
pera
ting
man
ual s
hall
be c
onsu
lted
for c
alib
ratio
n, m
easu
ring
, mai
nten
ance
, and
cle
anin
g an
d st
orag
e re
quir
emen
ts.
3.Ca
libra
ting
gase
s and
solu
tion
for i
nstr
umen
tatio
n ar
e pe
r the
man
ufac
ture
r’s o
pera
ting
man
ual.
4.V
alue
s are
typi
cal;
the
actu
al v
alue
s will
mee
t or e
xcee
d th
e lis
ted
para
met
ers.
5.Co
ntin
uous
on-
line
mon
itori
ng sy
stem
s will
be
in a
ccor
danc
e w
ith A
STM
D 3
864.
Clos
ed
Cool
ing W
ater
Sy
stem
1G
rab
See
Not
es 1
,2,3
N/A
N/A
N/A
N/A
Circ
ulat
ing
Wat
er C
oolin
g W
ater
Bas
in
Mak
eup
1Co
ntin
uous
pH1-
11 p
H±0
.02
pH<1
% o
f rea
ding
(per
stan
dard
so
lutio
n vo
lum
e)
Spec
ific
Cond
uctiv
ity0.
06 to
100
0 �S
/cm
30 se
cond
s0.
001
to 1
�S/
cm
(dep
ends
on
rang
e)±
1% o
f mea
sure
d va
lue
or ±
di
git (
whi
chev
er is
gre
ater
)
Tab
le9.
3.2-
2—Se
cond
ary
Side
Sam
plin
g Po
ints
She
et 5
of 5
Proc
ess
or
Equi
pmen
t
Num
ber
of S
ampl
e Po
ints
Type
of
Sam
ple5
Proc
ess
Mea
sure
men
t of
Con
tinuo
us
Sam
ples
R
ange
4R
espo
nse
Tim
e4Se
nsiti
vity
4
Max
imum
ant
icip
ated
dr
ift b
etw
een
calib
ratio
ns4 N
ext F
ile
14.0
2-15
1
RAFT
grab
sam
ples
to b
e m
easu
grab
sam
ples
to b
e
Aampl
es a
re id
entif
ied
in p
ples
are
iden
tifie
d in
p
AFing, mainte
nanc
e, a
nd c
leg,
mai
nten
ance
, and
cl
AFper th
e m
anuf
actu
rer’s
op
per t
he m
anuf
actu
rer’s
op
FTlisted para
met
ers.
met
erTh ASTM D 3h ASTTRA0.
06 t
.06
t
R
�S/c
m�S
/
RDRA
Spec
ific
Spec
ific
DRConduct
ivity
duct
ivityRDRpHHDRDususDDDe
No
e N
o DDDRA
DDRRA
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 14.2-126
��� Verify power-operated valves fail upon loss of motive power as designed (refer to Section 9.3.2).
��� Verify that continuous monitors and sample flow rate meets design requirements.
��� Check electrical independence and redundancy of power supplies for safety-related functions by selectively removing power and determining loss of function.
4.0 DATA REQUIRED
��� Setpoints at which alarms and interlocks occur.
�� Sampling flow rate from each sample point.
��� Analytical instrument data.
��� Valve performance data, where required.
�� Valve position indication.
��� Position response of valves to loss of motive power.
5.0 ACCEPTANCE CRITERIA
�� The SECSS meets design requirements (refer to Section 9.3.2):
���� SECSS alarms, interlocks, and controls (manual and automatic) function as designed.
��� SECSS valves perform as designed (i.e., opening times, closing times, and pressure/temperature controls).
���� SECSS meet design requirements for representative samples.���� Continuous and chemistry lab instrumentation used to analyze
SECSS parameters described in Table 9.3.2-2 will meet the design requirements for the measurements. This includes, but is not limited to, the following (that could adversely impact the ability to accurately measure the parameters described in Table 9.3.2-2):� Range.� Response time.� Sensitivity.� Maximum anticipated drift between calibrations.
� Verify that safety-related components meet electrical independence and redundancy requirements.
14.02-151 DRAFT
required.requir
ves to loss of motive powves to loss of motive p
eets design requirementseets design require
ECSS alarms, interlocks, aalarms, interlocks, afunction as designed.function as designed.
SECSS valves perforSECSS valvestimes, and pressumes, and pres
�������� SECSS meet dSECSS meet d��������
SECSSSECSdesiesiDRContinuoCSECSSSE
iDRDRDRDD
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 14.2-247
� Plant systems required to support testing are functional to the extent necessary to perform the testing or suitable simulation of this system is used.
�� Verify preoperational Test #143 has been satisfactorily completed for radiation monitoring instrumentation.
3.0 TEST METHOD
��� Verify power sources to post accident related equipment.
�� Validate that external inputs are received and processed correctly by the appropriate system devices.
��� Verify that alarms and indication displays respond correctly to actual or simulated inputs.
��� Verify the functionality of required software application programs.
�� Verify the correct operation of data output devices and displays at applicable work stations and terminals.
4.0 DATA REQUIRED
��� Computer generated summaries of external input data, data processing, analysis functions, displayed information, and permanent data records.
5.0 ACCEPTANCE CRITERIA
�� The instruments that are designated as the post-accident monitoring instruments have been verified to include all of the instruments listed in the emergency operating procedures (Abnormal Operating Procedures, Emergency Operating Procedures, Severe Accident Mitigation Guidelines, etc.)
� The PAM functions as described in Section 7.5.
�� RadiationContinuous monitoring instrumentation used to perform post-accident monitoring that is described in Section 9.3.2Tables 9.3.2-1 and 9.3.2-2 will meet the design requirements for the radiation monitor. This includes, but is not limited to, the following (that could adversely impact the ability to measure the parameters described in Section 9.3.2Tables 9.3.2-1 and 9.3.2-2):
���� Range.��� Response time.���� Sensitivity.���� Maximum anticipated drift between calibrations.
14.02-156 DRAFT
ed softwared sof
of data output of data outp devind terminals.nd terminals.
ated summaries of externmmarietions, displayed informatiions, displayed inf
CRITERIARIA
e instruments that are dee instruments thatnstruments have been vnstruments have been
in the emergency opein the emergency opeProcedures, Emergocedures, EmergMitigation GuidMitigation
� The PAM fuhe PAM fu
���� RadiatiodiatDpost-post-SeSeDD
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 14.2-303
4.0 DATA REQUIRED
��� Reactor power level.
�� Temperature data in designated locations (i.e., general area and adjacent to major heat loads).
��� Equipment operating data.
5.0 ACCEPTANCE CRITERIA
�� Temperature conditions are maintained within the operable limits in areas as designed (refer to Section 9.4).
14.2.12.18.5 Sampling Primary and Secondary Systems (Test #204)
1.0 OBJECTIVE
��� To collect chemistry samples of the RCS and secondary at various power levels to record the following:
����� Boron concentration and boron-10 isotopic abundance.���� Concentration of non-radioactive elements and soluble
particulates.����� Measured pH of the fluids.����� Radio isotopic concentration data of the radioactive elements
(e.g., cesium, iodine, iron, cobalt). �� To demonstrate performance of permanent plant sampling and analysis
procedures, while confirming that primary and secondary chemistry requirements are being met.
��� To verify that the primary and secondary systems are operating within design limits. This procedure shall be performed at the following plateau:
����� 25 percent reactor power in accordance with RG 1.68.���� 50 percent reactor power in accordance with RG 1.68.����� 75 percent reactor power in accordance with RG 1.68.����� �98 percent reactor power in accordance with RG 1.68.
2.0 PREREQUISITES
�� The reactor is stable at the desired power level.
� Required sampling systems are functional and analysis instrumentation are calibrated using calibration gases and solutions as referenced in the radioactive and non-radioactive analyses of Table 9.3.2-2Tables 9.3.2-1 and 9.3.2-2.14.02-151
of the RCS and secof the RCS following:follo
tration and boron-10 isottration and boron-10 isotion of non-radioactive en of non-rad
ates.asured pH of the fluids.ured pH of the fluids
Radio isotopic concentratsotopic concentrat(e.g., cesium, iodine, ir(e.g., cesium, iodine, ir
o demonstrate performano demonstrate perforprocedures, while confiprocedures, while confrequirements are beiequirements are bei
������ To verify that thTo verify thdesign limits. design limitsplateau:teau
��������
������
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 14.2-304
3.0 TEST METHOD
��� Samples shall be collected from the RCS and secondary system at various power levels and analyzed in the laboratory using applicable sampling and analysis procedures.
�� Collect samples at various process radiation monitors, perform analysis in the laboratory, and compare the samples with the process radiation monitor output.
��� Verify that primary and secondary sample results meet design limits.
4.0 DATA REQUIRED
��� Reactor power.
�� RCS and secondary temperature.
��� Boron concentration and boron-10 isotopic abundance.
��� Core average burnup.
�� Isotopic activities.
5.0 ACCEPTANCE CRITERIA
�� Measured activity levels are within their limits.
� Laboratory analyses and process radiation monitors agree with the within measurement uncertainties as designed (refer to Section 9.3.2), or investigation of the discrepancies has been initiated.
�� Samples of RCS and secondary fluids can be obtained from design locations as designed (refer to Sections 9.3.2 and 11.5).
�� Continuous and chemistry lab instrumentation used to analyze primary and secondary sampling parameters described in Table 9.3.2-1 and Table 9.3.2-2 will meet the design requirements for the measurements. This includes, but is not limited to, the following (that could adversely impact the ability to measure the parameters described in Table 9.3.2-1 and Table 9.3.2-2):
���� Range.��� Response time.���� Sensitivity.���� Maximum anticipated drift between calibrations.
� Radiation monitoring instrumentation used to perform radiation monitoring that is described in Table 11.5-1 will meet the design requirements for the radiation monitor. This includes, but is not limited to, the following (that could adversely impact the ability to measure the parameters described in Table 11.5-1):
��� Range.�� Response time.
14.02-151 DRAFTn-10 isotopic abn-10 iso
A
tivity levels are within thivity levels are with
ory analyses and process rlyses and process rn measurement uncertainn measurement uncertain
investigation of the discrinvestigation of th
Samples of RCS and secSamples of RCS and selocations as designedocations as designed
����
DRContinuous Continuou and Rprimary and srimary andand dDDTableTameasureeasucouldcouldininDRDD51
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 14.2-305
��� Sensitivity.��� Maximum anticipated drift between calibrations.
14.2.12.18.6 Failed Fuel Detection (Test #205)
1.0 OBJECTIVE
��� To collect chemistry samples of the RCS and secondary at the specified power level to record the following:
����� Boron concentration and boron-10 isotopic abundance.���� Concentration of non-radioactive elements and soluble
particulates.����� Measured pH of the fluids.����� Radioisotopic concentration data of the radioactive elements
(e.g., cesium, iodine, strontium, barium, cerium, and noble gases).
�� To demonstrate performance of permanent plant sampling and analysis procedures. There is typically some RCS activity from tramp, fuel dust that is on the outer surface of the cladding.
��� To perform a cross-check of the failed fuel monitor instrumentation.
��� This test shall be performed at the following power plateaus:
����� 25 percent reactor power.���� �98 percent reactor power.
2.0 PREREQUISITES
�� The reactor is stable at the desired power level.
� Required sampling systems are functional.
�� Calibrating gases and solutions are available for radioactive and non-radioactive analyses referenced in Table 9.3.2-2Tables 9.3.2-1 and 9.3.2-2.
3.0 TEST METHOD
��� Samples shall be collected from the RCS and secondary system at various power levels and analyzed in the laboratory using applicable sampling and analysis procedures.
�� Collect samples at various process radiation monitors, perform analysis in the laboratory, and compare the samples with the process radiation monitor output.
4.0 DATA REQUIRED
��� Reactor power.
�� RCS and secondary temperature.
14.02-156 DRAFT
on data oon datrontium, bariumrontium
ance of permanent plant sance of permanent pltypically some RCS activitypically some RCS activ
r surface of the cladding.urface of the
ross-check of the failed fross-check of th
hall be performed at the fbe performed at the
25 percent reactor pow25 percent reactor pow �98 percent reactor�98 percent r
REQUISITESQUISITES
���� The reactor is staThe reacto
� Required samequired sam
���� Calibratiibrradioaradioa9.39.3DD
U.S. EPR FINAL SAFETY ANALYSIS REPORT
Tier 2 Revision 3—Interim Page 14.2-306
��� Boron concentration and boron-10 isotopic abundance.
��� Core average burnup.
�� Isotopic activities.
5.0 ACCEPTANCE CRITERIA
�� Measured activity levels are within their limits.
� Laboratory analyses and process radiation monitors agree with the within measurement uncertainties as designed (refer to Section 9.3.2 or investigation of the discrepancies has been initiated.
�� Samples of RCS and secondary fluids can be obtained from design locations as designed (refer to Sections 9.3.2 and 11.5).
�� Chemistry labContinuous instrumentation used to analyze primary sampling parameters described in Table 9.3.2-2Tables 9.3.2-1 and 9.3.2-2 will meet the design requirements for the measurements. This includes, but is not limited to, the following (that could adversely impact the ability to measure the parameters described in Table 9.3.2-2Tables 9.3.2-1 and 9.3.2-2):
���� Range.��� Response time.���� Sensitivity.���� Maximum anticipated drift between calibrations.
� Radiation monitoring instrumentation used to perform primary system monitoring that is described in Table 11.5-1 will meet the design requirements for the radiation monitor. This includes, but is not limited to, the following (that could adversely impact the ability to measure the parameters described in Table 11.5-1):
��� Range.�� Response time.��� Sensitivity.��� Maximum anticipated drift between calibrations.
14.2.12.18.7 Self Powered Neutron Detector Calibration (Test #206)
1.0 OBJECTIVE
��� To perform a test on the Aeroball Measurement System (AMS) to verify the adequacy of time dependent decay constant functions of the vanadium steel flux measurement balls.
�� To perform a full core flux map using the following:
���� Moveable incore system - AMS.��� Fixed incore system - Self powered neutron detectors (SPND).
14.02-156
DRAFT
ntationntatinn Table 9.3.2Tab
Tequirements for thequiremento, the following (that to, the followin
asure the parameters desasure the parameters d.3.2-1 and 9.3.2-2.3.2-1 and 9.3FT):onse time.nse tim
ensitivity.vityMaximum anticipated Maximum anticipated
adiation monitoring instradiation monitoringmonitoring that is descrmonitoring that is descrequirements for the requirements for the limited to, the folllimited tomeasure the pameasure the
����� Ran���
����
FT