Chapter 2 – Software Processes 1Chapter 2 Software Processes.
2 1 Processes & Technologies
-
Upload
gazal-reyaz -
Category
Documents
-
view
216 -
download
0
description
Transcript of 2 1 Processes & Technologies
Module-2: Process Selection & Supply Chain Design
Mod: 2-2Processes & Technologies
Learning Outcomes
After going through this topic, you should be able to:
• Explain how manufacturing processes run
• Suggest appropriate technologies for different stages of
manufacturing process
• Identify and classify the wastes of a production uni
• Represent processes in a digital manufacturing environment
(PLM focus)
3
Operations strategy: Improve Speed to Market
Simultaneous (Concurrent) Engineering
Economic and TechnicalFeasibility Studies
Product/Service Ideas
Production Process DesignProduct/Service Design
Production and MarketingNew Product/Service
ContinuousInteraction
4
ProcessPlanning and Design
5
Process Planning and Design System
Inputs:• Product/Service Information
• Production System Information
• Operations Strategy
Process Planning & Design:• Process-Type Selection
• Vertical Integration Studies• Process/Product Studies
• Equipment Studies• Production Procedures Studies
• Facilities Studies
Outputs:• Process Technology • Facilities• Personnel
Estimates
6
Some Production ProcessesMetal-working Processes
Assembly Casting & Molding Cutting Forming Finishing
Brazing
Cementing
Fastening
Press-fitting
Shrink-fitting
Soldering
Welding
Die casting
Sand casting
Investment casting
Injection molding
Powder-metal molding
Permanent molding
Broaching
Drilling
Grinding
Honing
Milling
Shaping
Turning
Drawing
Extrusion
Punching
Rolling
Trimming
Swaging
Spinning
Blasting
Buffing
Cleaning
Deburring
Heat treatment
Painting
Polishing
7
Some Production ProcessesNon-metal-working Processes
Chemical Food Processing Mining Textiles Lumber
Cracking
Cooking
Curing
Distillation
Evaporation
Grinding
Screening
Canning
Cooking
Crushing
Freezing
Pasteurization
Press
Sterilization
Drying
Crushing
Excavation
Extraction
Loading
Screening
Smelting
Braid
Knit
Polish
Shrink
Spin
Wash
Weave
Debark
Cure
Join
Kiln
Plane
Saw
Turn
Process Flow Design
• A process flow design can be defined as a mapping of the specific processes that raw materials, parts, and sub-assemblies follow as they move through a plant
• The most common tools to conduct a process flow design include assembly drawings, assembly charts, and operation and route sheets
Material Received from
Supplier
Inspect Material for
DefectsDefects found?
Return to Supplier for
Credit
Yes
No, Continue…
Example: Process Flow Chart
Example: Assembly Chart (Gozinto)
A-2SA-2
4
5
6
7
Lock ring
Spacer, detent spring
Rivets (2)
Spring-detent
I-5
Component/Assy Operation
Inspection
OPERATIONS & ROUTE SHEET Material specifications ------------Purchased stock size -----------Pieces per purchase -----------Weight -----------
Part name -----Usage -----Assy. No. -----Sub Assy. No. ---
Part No. -------Date issued --------Date supplied ------Issued by --------
Opr No.
Operation Description Dept Machine Setup Hr.
Rate Pc. Hr.
Tools
20 Drill hole .32+.015
-.005Drill M/c. 513
Drill1.5 254 Drill fixture L-76
Jig # 10393
30 Deburr .312+.015 dia. hole
-.005
Drill M/c. 510Drill
.1 424 Multi-tooth burring tool
40 Chamfer .009/875. bore.878/.875 dia.
(2 passes. bore. 7600/7625 (1 pass)Lathe M/c. D109
Lathe1.0 44 Ramet-1, TPG 221, Chamfer
tool
50 Tap hole as designed ¼ min. full thread Tap M/c. 517Drill tap
2.0 180 Fixture # CR/353 tap. 4 flute sp.
60 Bore hole 1.33 to 1.138 dia. Lathe H & HE 107
3.0 158 L44 turret fixture Hartford
Superspacer, pl. # 45 holder # L46
FDTW-100, insert#21Chk.fixture
70 Deburr .005 to .010 both sides,
hand to hard stop Lathe E 162
Lathe.3 175 Collect CR # 179 1327 RPM
80 Broach keyway to remove thread burrs Drill M/c. 507Drill
.4 91 B87 fixture, L59 broach tap. .875120 G-H6
90 Hone thread I.D. .822/.828 Grind Grinder 1.5 120
95 Hone .7600/.7625 Grind Grinder 1.5 120
Basic work flow structures
If the flow is of low volume, go for manual process; and for high volume, go for automation.
The basic flow structures are:
1.Project layout (Fixed position layout, by virtue of its bulk or weight)
Example - Dam, Road, House, Film-location, Ship-building, Aircraft mfg.
2.Workcenter (where similar equipments are grouped for one kind of work)
groups of machines/equipments in a Job-shop/Functional/ Process/Group/ Batch
Layout; discrete product moves from one to another workcenter.
Example - Photocopy of a single student’s term paper; Bread-making.
3.Manufacturing cell (dedicated to products with similar processing needs).
A specific set of processes run in a cellular layout.
Example - Different units of a publication house.
Basic work flow structures Contd.
4. Assembly Line (a fixed line or sequence of progressive operations) discrete parts are made by moving from workstation to workstation in a line/ product layout. Example - Automobile manufacturing
5. Continuous process (like assembly line, but continuous and integrated operations) with limited/no predetermined stops.Example - Manufacturing of petroleum, steel, aluminum etc.
Product-Process
Matrix
Product-Process Matrix
14
Operation strategy dictates the type of processes to be selected – the equipment, building, layout, technology, people, skill etc.
Major Factors Affecting Process Designs
Nature of product/service demand Scope for Expansion and Consolidation
Degree of vertical integration (of process) Make or Buy
Production flexibility Volume and Variety
Degree of automation Product/Service quality
15
Types of Process Designs
Product-Focused Production Line or Assembly Line Job Shop or Intermittent Production As per the operations sequence to produce a product or
provide a service Discrete Units or Continuous Process
Process-Focused Organizing Processes by similarities or groups Products/Services (jobs) progress from department to
department as required
16
Purchased
Components,Subassemblies
Product-Focused
2
31
4
7
6
5Components Subassembly
Assemblies
Product/Material Flow
Production OperationAsse
mblies
Raw Material Components
Components
Subassembly
Raw Material
Finished Goods
17
Process-Focused
Job B
Custom Woodworking Shop
Cutting Assembly Sanding FinishingPlanning
Drilling
Shaping
Turning
15 7
3
2
1 6
36
4
2Job A
4 5
Product/Material Flow
Production Operation
18
Process Reengineering
Drastically changing the process from the existing state
Truly reengineered processes are more efficient
19
Deciding a Process from Alternatives
Batch Size and Product/Service Variety
Capital Requirements
Economic Analysis
Cost Functions of Alternative Processes
Break-Even Analysis
Financial Analysis
20
Process Design Depends on Product Diversity and Batch Size
Smal
l
Bat
ch S
ize
Lar
ge
Few Number of Product Designs Many
ProductFocused,DedicatedSystems
ProductFocused,
BatchSystem
Process-Focused, Job Shop
CellularManufacturing
21
Economic Analysis
Cost Functions of Processing Alternatives Fixed Costs
Annual cost when production volume is zero Initial cost of buildings, equipment, and other
fixed assets Variable Costs
Costs that vary with production volumes Labor, material, and variable overhead
Break-Even Analysis (to select a process/equipment based on cost-trade-offs)
• A standard approach to choose a process or equipment
• A model determines the break-even-point (BEP) of units produced (and sold) where onwards the process or equipment goes in profit
• The total revenue and total cost are equal at BEP.
Fixed cost
Loss
Variable cost
Sales R
even
ue
Profit
Margin of Safety
BEP
Rs.
Nos.
BEC
BEQ
Break-Even Analysis (Continued)
* This formula can be used to find any of its components algebraically if the other known parameters
Break-even Demand =
Purchase cost of process or equipment Price per unit - Cost per unit
Break-Even Analysis (Continued)
Example:
Suppose you want to purchase a new computer that will cost $5,000.
It will be used to process written orders from customers who will pay
$25 each for the service. The cost of labor, electricity and the form
used to place the order is $5 per customer. How many customers will
we need to serve to permit the total revenue to break-even with our
costs?
Answer: Break-even Demand:= Total fixed costs of process or equip.
Unit price to customer – Variable costs
= 5,000/(25-5)
= 250 customers
25
Example: Economic Analysis at Valley Hospital
Valley Hospital is planning to install a new linen retrieval system. Two alternatives being considered are: a continuous vacuum (CV) system and a batch robotic/chute (BR/C) system. The following estimates were prepared:
CV BR/C Annual Fixed Costs ($000) $2,690 $975 Average Variable Cost per Ton $1,660 $2,590
At a forecast annual operating level of 2,000 tons of linen, which alternative should be chosen based only on total annual cost?
26
Solution:
TCCV = 2,690,000 + 1,660(2,000) = $6,010,000 TCBR/C = 975,000 + 2,590(2,000) = $6,155,000
The continuous vacuum (CV) alternative has a lower total annual cost.The annual volume of linen has to increase or decrease to what level in order for the BR/C alternative to be favored?
TCCV = TCBR/C
2,690,000 + 1,660(Q) = 975,000 + 2,590(Q) 830Q = 1,715,000 Q = 1,844.1 tons
Annual volume must decrease to 1,844 tons or less.
27
Economic Analysis
Break-Even Analysis Widely used to analyze and compare decision
alternatives Can be displayed either algebraically or graphically
Disadvantages: Cannot incorporate uncertainty Costs assumed over entire range of values Does not take into account time value of money
28
Break-Even Analysis
Example Break-Even Points of Processes A, B, and C, assuming a $6.95 selling price per unit
Q = FC / (p-v)
A: Q = 120,000 / (6.95 - 3.00) = 30,380 unitsB: Q = 90,000 / (6.95 - 4.00) = 30,509 unitsC: Q = 80,000 / (6.95 - 4.50) = 32,654 units
Process A has the lowest break-even point.
29
Economic Analysis
Financial Analysis Huge investment is done in production processes and
these assets are expected to last a long time Therefore, time value of money is important
Payback period Net present value Internal rate of return Profitability index
30
Deciding Among Processing Alternatives
Assembly Charts (Gozinto Charts) Macro-view of how materials are united Starting point to understand factory layout needs,
equipment needs, training needs
Process Charts Details of how to build product at each process Includes materials needed, types of processes
product flows through, time it takes to process product through each step of flow
31
Wrap-Up: World Class Practice
Fast new product introduction Design products for ease of production Refine forecasting Focus on core competencies ... less vertical
integration Lean production Flexible automation Job shops move toward cellular manufacturing Manage information flow ..... automate and simplify!
Question Bowl
What is the break-even in demand for a new process that costs $25,000 to install, will generate a service product that customers are willing to pay $500 per unit for, and whose labor and material costs for each unit is $100?
a. 400 units
b. 250 units
c. 100 units
d. 62.5 units
e. None of the above
Answer: d. 62.5 units i.e. 25,000/(500-100) = 62.5
Question Bowl
Which of the following is an example of a Continuous Flow type of process flow structure?
a. Fast foodb. Grocery c. Hospitalsd. Chemical companye. None of the above
Answer: d. Chemical company (in Process Industry)
So we need to study:• Hardware Systems• Software Systems• Evaluating a Robot Investment• Computer Integrated Manufacturing• Benefits & Risks
PROCESS TECHNOLOGIESRecent growth in productivity comes from the
application of Operations technology.
In manufacturing it comes from Soft (information) Technologies and Hard (machine) Technologies.
Hardware Systems
• Numerically controlled (NC) machines– Have Adaptive controls to receive/read instructions and
translate them into machine operations• CNC – computer numerically controlled• DNC – direct numerically controlled (several machines
controlled by a single computer)
• Industrial robots– Human-like machines performing production tasks, controlled
by a microcomputer, have grippers (vacuum, magnetized, adhesive), Equipped with an end effectors to pick, grip, hold) sensors (tactile, proximity, vision/optical); can operate in environments hostile to humans (heat, noise, dust, darkness, skin irritants, …)
– Perform precisely and repeatedly without fatigue– Weld, assemble, paint, inspect, transport, …..– Automated Inspection, Quality control, Material handling
• Automated material handling (AMH) systems– Computerized conveyors, AS/RS (load/pick/place), AGVS
• FMS – Manufacturing Cells, Robots, Machining Centers, ……...
36
Flexible Manufacturing System (FMS)
Machine 1
Tools X
X
Machine 2
Tools X
X
Machine 3
Tools X
XComputer
Worker
X
X
X
X
X
X
X
UnloadLoad
PalletTransferSystem
Parts
Pallet withworkpieceattached
Workpiecein queue
37
Group Technology/Cellular Manufacturing
Group Technology Each part produced receives a multi-digit code that
describes the physical characteristics of the part. Parts with similar characteristics are grouped into
part families Parts in a part family are typically made on the
same machines with similar tooling
38
Group Technology/Cellular Manufacturing
Cellular Manufacturing Some part families (those requiring significant
batch sizes) can be assigned to manufacturing cells.
The organization of the shop floor into cells is referred to as cellular manufacturing.
Flow of parts within cells tend to be more like product-focused systems
39
Group Technology/Cellular Manufacturing
Advantages (relative to a job shop) Process changeovers simplified Variability of tasks reduced (less training needed) More direct routes through the system Quality control is improved Production planning and control simpler Automation simpler
40
Group Technology/Cellular Manufacturing
Disadvantages Duplication of equipment Under-utilization of facilities Processing of items that do not fit into a family
may be inefficient
41
Group Technology/Cellular Manufacturing
Candidates for GT/CM are job shops having: A degree of parts standardization Moderate batch sizes
Software Systems
• Automated manufacturing planning and control systems (MP & CS)
• Enterprise Resource Planning (ERP)• Computer-aided-design (CAD)• Computer-aided engineering (CAE)• Computer-aided process planning (CAPP)• Computer-integrated manufacturing (CIM)
ProcessControls
MRP II
ASRS
CAD/CAM
AutomatedAssembly GT
Systems
Evaluating a Robot Investment
Where
P = Payback period in years
I = Total capital investment required in robot and accessories
L = Annual labor costs replaced by the robot (wage and
benefit costs per worker times the number of shifts per day)
E = Annual maintenance cost for the robot
Z = Annual depreciation
q = Fractional speedup (or slowdown) factor (in decimals).
Example: If robot produces 150 % of what the normal worker is
capable of doing, the fractional speedup factor is 1.5.
Z)q(LE-LP
IThe payback formula for an investment in robots is:
Example: Evaluating a Robot Investment
Suppose a company wants to buy a robot. The bank wants to know what the payback period is before they will lend them the $120,000 the robot will cost. You have determined that the robot will replace one worker per shift, for a one shift operation. The annual savings per worker is $35,000. The annual maintenance cost for the robot is estimated at $5,000, with an annual depreciation of $12,000. The estimated productivity of the robot over the typical worker is 110%. What is the payback period of this robot?
P = I = 120,000 = 1.47years L–E+q(L + Z) 35,000–5,000+1.1(35,000+12,000)
Computer Integrated Manufacturing (CIM)
• Product and process design– CAD and CAM
• Planning and control– CAPP and MP&CS
• The manufacturing process
Cost Reduction Benefits from Adopting New Technologies
• Labor costs• Material costs• Inventory costs• Transportation or distribution costs• Quality costs• Other costs
Other Benefits….
• Increased product variety
• Improved product features and quality
• Shorter cycle times
Risks
• Technological risks
• Organizational risks
• Environmental risks
• Market risks
References :
1. Operations & Supply Management; Chase, Shankar, Jacobs
and Aquilano; 12th Ed.; TMH Publication.
2. Operations Management; Gaither, N. and Frazier, G.;
Cengage Learning, 9th Edition.
End of Chapter