1st Project TutorialIrriExpress

Page 2: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

Table of Contents

1. Import Map and Elevations

2. Place Pivot

3. Place Block

4. Fill Block

5. Create Valve to Block

6. Create Manifold for Block

7. Create Mainline

8. Run Hydraulics on Block

9. Run Hydraulics on Mainline

10. Run Analysis on Pivot

11. Labels and Appearance

12. Additional Help

Page 3: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Navigate to the maps tab2. Type in address, hit Go3. Move map to location by clicking and dragging map4. Switch to Satellite mode5. Import to Workspace6. Auto Model to have IrriExpress create triangles, pull in DTM points and draw contours

1

2

3

45

6

Import Map and Elevations

Page 4: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Decide spacing of DTM points

1

Import Map and Elevations

Page 5: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Turn off DTM by unchecking the box2. Navigate to the Irrigation menu3. Select Pivot > Center Point and click on map where you want to place a pivot4. Drag pivot to desired length and select number of spans5. Click Ok

1

2

3

4

5

Place Pivot

Page 6: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select Block from Irrigation Menu2. Click on Rectangle3. Select point on map and draw block, click on map again to complete block4. Click ESC when complete

1

3

4

2

Click ESC

Place Block

Page 7: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select Block (it will be highlighted)2. Select Solid Set3. Select Model for emitters in block, hit OK

1

2

3

Fill Block

Page 8: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select Pipes for block, hit Ok

1

Fill Block

Page 9: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select the Row Spacing and Emitter Spacing, click Ok

1

Fill Block

Page 10: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Move layout to desired location and click to place down emittersTo rotate emitters, use the Page Up and Page Down keys to before clicking and placing down emitters

Fill Block

Page 11: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Navigate to the Irrigation menu2. Click on Node3. Select a Valve, click Ok

1

2

3

Create Valve to Block

Page 12: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select point on map and click to place down valve2. Click ESC when done3. Click Cancel on the node menu that comes up

1

Create Valve to Block

Page 13: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select the Block, it will be highlighted2. Click on ‘Place Right’ on the manifold menu3. Select the manifold type, click Ok

1

2

3

Create Manifold for Block

Page 14: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. See the manifold placed from the previous steps2. Select the Mainline from the top right menu3. Navigate to the Irrigation menu4. Select Node5. Select Pump, choose your type of pump, and click Ok

1

2

3

5

4

Create Mainline

Page 15: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Click on map to place down pump2. Click ESC when done3. Click cancel on the node menu that comes up again

1

Create Mainline

Page 16: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Navigate to the Irrigation menu2. Click on Pipe3. Select the pipe class and type for your mainline4. Click Ok

1

2

3

4

Create Mainline

Page 17: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Snap to the Pump. It should be highlighted with a red box.2. Once you are snapped to the pump, click on New Node on the menu to the left3. Select the fitting image

12

3

Create Mainline

Page 18: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Place down a line of fittings towards your pivot2. On the left menu, change the mode to Snapping 3. Snap to the pivot node. It will be highlighted with a red box.4. After snapping to the pivot node, click ESC

1

2

3

Create Mainline

Page 19: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. You are still in the Snapping mode2. Snap to either a point on the mainline or directly to the valve of the block

1

2

Create Mainline

Page 20: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Switch to New Node on the left menu2. Select the fitting image3. Place down a line of fittings towards your block valve

1

2 3

Create Mainline

Page 21: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Using the left menu, switch back to Snapping mode2. Click and snap to the block’s valve3. Click ESC twice and click cancel when the node menu comes up again

1 2

Create Mainline

Page 22: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select the block, it will be highlighted2. Click on the Run button on the top menu3. If you can not see the Vale Pressure input box, check the Reduced Size at the bottom4. Input a desired Valve Pressure, click enter5. Navigate to the Sizing tab6. Click Update Pipe Sizes7. View results

1

2

3

4

5

6

Run Hydraulics on Block

Page 23: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Navigate between the tabs (Nodes, Pipes, Reports, Sizing, Shifts) to view the details of the block2. Click on the Refresh button if the Nodes or Pipes details are not shown3. Close when completed

1

3

Run Hydraulics on Block

Page 24: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select the Mainline on the right hand menu

1

Run Hydraulics on Mainline

Page 25: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Navigate to the Irrigation menu2. Click the Run button3. Navigate to the Sizing tab and click Update Pipe Sizes4. View results5. When complete, click Close

1 2

3

4

5

Run Hydraulics on Mainline

Page 26: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select the Pivot, it will be highlighted2. Click on the Section Analysis button

1

2

Run Analysis on Pivot

Page 27: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Select the limits to view on the pivot2. Change the limit values in the input boxes3. Click the Travel button and view the pivot move in the bottom graph

1 2

3

Run Analysis on Pivot

Page 28: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Navigate between the top tabs to view more about the pivot2. Below the Pivot Details are shown3. Click on the Section Report to have IrriExpress automatically create a pivot report

1

2

3

Run Analysis on Pivot

Page 29: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. View the pivot report

Run Analysis on Pivot

Page 30: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

1. Turn on or off different labels by using the General menu2. Adjust the labels’ size using the sliding bars3. Adjust the image’s transparency using the Object Inspector

1 2

3

Labels and Appearance

Page 31: 1st Project Tutorial - Irrimaker1st Project Tutorial IrriExpress Table of Contents 1. Import Map and Elevations 2. Place Pivot 3. Place Block 4. Fill Block 5. Create Valve to Block

For Additional Help

Please go to www.irriexpress.com