17th National Award for “Excellence in Energy Management...

66
17th National Award for “Excellence in Energy Management – 2017 Presented By : Mr. B Baral & Mr. Ravi Kumar

Transcript of 17th National Award for “Excellence in Energy Management...

17th National Award for “Excellence in Energy Management – 2017

Presented By : Mr. B Baral

&

Mr. Ravi Kumar

2

ACC Limited

Genesis of the plant....

1989 1995 1997 2005 2007 2007 2014

1923

1923 Plant Established

Total Capacity0.09 MTPA

Wet Process

1995: Inception of Dry process

(Kiln 1) – Total Capacity1.0 MTPA

1997: Inception of Dry process

(Kiln 2) – Total Capacity2.2 MTPA

2005 –Installation

of Over Land Conveyor(Length –

11.5 Kms)

2007 –

Installation

of New

25 MW CPP

2007 –Installation of

New Ball Mill –Total Grinding Capacity

– 2.5 MTPA (Old inefficient

ball millswere stopped)

2014 –

Successful

commissioning

of Geocycle

PCPF Project

Standing

with

pride in

2017

(after 94

years)

3

ACC Limited

Process Flow…

2 Raw Mills RM1 –333 TPH RM2 –337 TPH

2 Kilns -K-1 (ILC) –4820 TPD-K-2 (SLC) –4980 TPD

3 Cement mills (Ball Mill) with 1PG -2.35MTPA Capacity)

Packing House- 4 Packers with capacity of 180+180+150+240 TPH)

Quarry -- MHG Mines (2.9 MTPA) - BMG Mines (1.2 MTPA)- JamuwaniMines (0.2 MTPA)

Quarry Raw Mills Kilns Cement Mills Packing House

BDP figures are shown here.

4

ACC Limited

Encon Projects (Last 3 years summary)

UnitNo

Investment

Low

Investment

Medium

InvestmentTotal

No of project

implemented# 34 11 9 54

Electrical

Energy Saving

Million

kWh17.88 2.94 17.28 38.10

Thermal

Energy saving

Million

kcal 568.92 24084.84 28548.53 53202.29

5

ACC Limited

Last 3 years Thermal Encon Projects

Sr

No.

Project Description Thermal

Energy

(Mkcal)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

1 Full feed operation of PCPF Project for line-1 14867.12 253.0 620.00

2 Biomass feeding system for line-2 6446.16 9.01 40.00

3T A Duct partial replacement for improvement of

thermal energy consumption for line-245.94 0.06 0.00

4T.A Duct damper installation for improvement of

thermal energy consumption for line-1.372.94 0.52 5.70

5 Both kiln inlet Analyzer reliability improved. 149.99 0.21 0.00

6

ACC Limited

Last 3 years Thermal Encon Projects

Sr

No.

Project Description Thermal

Energy

(Mkcal)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

6Kiln feed SFM to coriolis feeding system

replacement Line-2738.7 8.07 4.5

7CFG to RFT conversion in Compartment

modification, fan replacement for Kiln-18362.6 8.1 1.6

8CFG to RFT conversion in Compartment

modification, fan replacement for Kiln-28362.6 8.1 4.0

9Coriolis system installation in Calciner firing for

coal fluctuation reduction Line-2.1456.5 1.4 11.0

10Kiln inlet ,Calciner outlet gas analyzer

installation.1456.5 1.4 1.2

7

ACC Limited

Last 3 years Thermal Encon Project...cont.

Sr

No.

Project Description Thermal

Energy

(Mkcal)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

11 Kiln-1 Pyrojet burner installation. 2913.0 2.8 14.8

12Kiln feed SFM to Coriolis feeding system

replacement Line-11456.5 1.4 4.5

13Use of thermo graphy for Preheater radiation

loss reduction728.2 0.7 Nil

14Applied of leakage arresting material loctite in

Preheater728.2 0.7 Nil

15Replacement of K2 Burner with high

momentum Burner2865.753 2.54 12.95

8

ACC Limited

Last 3 years Thermal Encon Projects..cont.

Sr

No.

Project Description Thermal

Energy

(Mkcal)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

16

Optimization of the DDF firing blower By

reducing the coal conveying air from 4300m3/hr

to 3900 M3/hr) in Kiln-13335 3.168 1.0

17Cooler horse shoe modification in Kiln-1 &

Kiln-2 as per Lafargeholcim norm1450 1.525

Nil

18 Both Cooler operation in auto mode 737.7 0.80 Nil

19 Kiln inlet trough modification in K-1 142.4 1.34 Nil

9

ACC Limited

Last 3 years Electrical Encon Projects

Sl no. Project Description

Elect. Energy

(Million

kWh)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

1Replacement of Low efficiency Pre heater fan by

new fan and GRR by MVVVF for kiln-11.12 5.62 10.00

2De-Coal Crusher Modification by replacing

hammer0.20 0.99 0.00

3Energy saving by optimization of Energy in CA unit

in CPP0.06 0.32 0.00

4Installation of VFD for Kiln-1 Main Drive Cooling

Blower Motor.0.02 0.12 0.00

6VRM table liner replacement & Replacement of

VRM Bucket elevator chain by New chain1.19 5.94 4.00

7Grinding media regrading for CM-1 second

chamber 0.48 2.38 2.00

8High torque motor in CM-1&CM-9 has been

installed for clinker Rotary Feeder0.59 2.97 0.00

10

ACC Limited

Last 3 years Electrical Encon Projects

Sl

no.Project Description

Elect. Energy

(Million

kWh)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

9 Restrict the grinding frequency from OPC & PPC. 0.48 2.38 0.00

10

Interconnecting of Bag Filter Suction pipe for Both

the Fly ash silo top Bag filetr & stoppage of Bag

filter fan for Old Fly ash Silo

0.24 1.19 0.00

11Clinker Quality analysis and action at raw mix /Coal

for reduction of hardgrove clinker grindability1.19 5.94 0.00

12 Dewatering Pump operation Optimisation done 0.36 1.80 0.00

13Synchronization of both the mining opertions

improve to more TPH of OLC0.51 2.57 0.00

14Improvement in LS size by maintaining the mines LS

input size , moisture to TC crusher,1.03 5.15 0.00

15False air points was arrested in Both the Preheater

Circuit0.79 3.96 0.00

11

ACC Limited

Last 3 years Electrical Encon Projects...cont.

Sl

no.Project Description

Elect. Energy

(Million

kWh)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

16 MV VVFD repair/ replacement for Bag house fan line-2 2.51 13.61 0.00

17Reduction in Bag house-1 Fan Power by GRR operation

inplace of damper control0.58 2.66 0.00

18Reduction in Clinkering Compressor Power by Leakage

arresting0.08 0.36 0.00

19Reduction in Specific Electrical energy by increasing in

Atox Mill Production 1.19 6.69 0.00

20Reduction in power Consumption of Flash Dryer Fan

RM-1 1.17 6.58 0.00

21Installation of new screen for tertiry crusher feeding

sysytem /Improvement in TC Screen availability 1.16 6.52 39.50

22

Regreding of grinding media , Grinding Pattern

optimization in all the cement mills & other

improvement (Sapex fan Replacement of CM-9, CM-8

Main motor replcaement)

1.92 10.41 0.00

12

ACC Limited

Last 3 years Electrical Encon Projects...cont.

Sl

no.Project Description

Elect.

Energy

(Million

kWh)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

23

Fan efficiency improvement by installation of

new fan with suitable capacity (Kiln-1 Preheater

Fan)

1.40 7.13 10.00

24Reduction in E Mill-1 Fan Power by reducing

GRR steps inplace of Damper control0.16 0.79 0.00

25 Installation of VVFD for Bag Filter Fan 0.11 0.57 0.90

26 Auto Control Common Header pressure of BFPs 0.16 0.80 0.00

27 Installation of VVFD for BFPs 6 Nos. 1.60 8.14 20.00

28 Optimisation of Centralised AC System 0.03 0.13 0.00

29 Packer-3 Belt modification for energy saving 0.02 0.12 0.00

30Reduction of Electrical Energy Consumption

during Shutdown0.63 3.19 0.00

13

ACC Limited

Last 3 years Electrical Encon Projects...cont.

Sl

no.Project Description

Elect. Energy

(Million kWh)

Saving

(Million

Rs.)

Invest.

(Million

Rs.)

31 Voltage Optimization for Transformer 0.95 4.83 0.00

33

Electrical Energy saving due to E Mill and Atox

Mill Production increase after installation of coal

Mil inertization project

13.37 0.00 170.00

34Reduction in Bag house-1 Fan Power by GRR

operation inplace of damper control0.58 2.94 0.00

35Reduction in Clinkering Compressor Power by

Leakage arresting0.08 0.39 0.00

36Reduction in Specific Electrical energy by

increasing in Atox Mill Production 1.19 6.04 0.00

37Reduction in power Consumption of Flash Dryer

Fan RM-1 1.17 5.94 0.00

38

Installation of new screen for tertiry crusher

feeding sysytem /Improvement in TC Screen

availability

1.16 5.88 25.00

14

ACC Limited

Reduction in Specific Energy Consumption

76.4175.29

*79.74

77.04

72.00

74.00

76.00

78.00

80.00

82.00

2014 2015 2016 2017 YTD JUN

Year wise kWh/t of ClinkerHigher SEEC due to

Low Production

80.9979.31

*85.20

82.61

70.0072.0074.0076.0078.0080.0082.0084.0086.00

2014 2015 2016 2017 YTD

JUN

Year wise kWh/t Cement Higher SEEC due to Low Production

33.08

31.47

*34.3 34.3

30.00

32.00

34.00

36.00

2014 2015 2016 2017 YTD JUN

Year Wise kWh/t of Cement Grinding

Higher SEEC due to Low Production

729.10 730.57734.58 735.14

700.00

710.00

720.00

730.00

740.00

750.00

760.00

2014 2015 2016 2017 YTD

JUNE

KJ/ Kg of Clinker Increase due to higher TSR%

15

ACC Limited

Energy Benchmarking

79.31

65.0457.04

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

Best Achive Figure National Best International Best

SEEC (kWh/t Cement)

22% Gap

724

678

651

600

620

640

660

680

700

720

740

Best Achive Figure National Best International Best

STEC (Kcal/kg of Clinker)

Higher Electrical Energy due to

❖ Ball Mills in place of VRM

❖ Old & Scattered Colony

❖ Higher SEEC in PH fans due

to higher Pressure drop

across preheater

❖ 11 KM Long Belt Conveyor

for LS Conveying from Mines

Higher Thermal Energy due to

❖ Lower recuperation

efficiency of old design cooler

(Grate Cooler) as compared

to Latest cross bar cooler .

❖ Higher TSR %

6.4% Gap

Note: National Benchmark Source : Energy Benchmarking for Cement Industry - May 2015, Version-2 by CII and NCCBM Awards 2015

International Benchmark Source : N. A. Madlool et al./ Renewable and sustainable Energy reviews 15 (2011) 2042 -2060

16

ACC Limited

Sr

No.Description

Investment

Rs Lacs

Saving in

Kcal/kg

Clinker

1New high efficiency cooler is required with loading <45

TPD/m2.2000 10

2 Installation of tube dust conveyor for line-2 cooler. 70 1.5

3 TA diameter need to enlarge for Whole 66 m length for K-2 150 2.5

4Modification of existing hood with sufficient

volume to enable to obtain hot air velocity will be < 5m/s.200 2

5K-1 Preheater top Cyclone modification to get high

efficiency (efficiency > 96%)150 2

6

To reduce the thermal energy consumption by replacing

Single flap damper with double flap damper in lower most

cyclone in both Kilns

10 0.4

7 Alumina painting in Pre-heater Cyclone

25.80 Cr.18.4

kcal/kg cli.

Road Map to Achieve Benchmark/Global Best

17

ACC Limited

Sr

No.Description

Investment

Rs Lacs

Saving in

kWh/ T of

Cement

1 Replacement of GRR by MV VVFD for Bag house fan of K-1 100 0.43

2 Replacement of Pre heater fan GRR by MVVVF for kiln-2 120 0.17

3Replacement of GRR by MV VVF Drives for both E Mill-1& E

Mill-2 Fan100 0.18

4 Elimination of Booster fan by rerouting the duct K-2 320 0.27

5

Reduction of Bag House DP by addition of two nos. of extra module

in both Bag House or additional bag filter capacity 1.6 Lacs m3/hr

along with existing Bag house

400 0.43

6Replacement of low efficient Cooler ESP Fan Kiln-1 by energy

efficient fan rotor 50 0.11

7Revamp of EMS Systems with Upgraded Server, with connectivity to

mines, colony, OLC 50 0.10

8Replacement of two nos. Compressors(capacity 1200cfm,2kg/cm2)

for Fly ash unloading by Energy efficient compressors50 0.23

Road Map to Achieve Benchmark/Global Best

18

ACC Limited

Sr

No.Description

Investment

Rs Lacs

Saving in kWh/

T of Cement

9 Replacement of GRR by MVVFD for Raw Mill-2 Sapex Fan 100 0.16

10 Replacement of GRR by MVVFD for Atox Mill Fan 60 0.10

11

Replacement of old reciprocating compressor used for coal

conveying from mill o/l to fine coal bin by turbo blower in E

Mills by turbo blower

40 0.08

12 Reduce pressure drop in preheater down comer duct – Kiln 1 Nil 0.08

13Reduce pressure drop in Line 2 Kiln – 3rd stage cyclone in Kiln

stringNil 0.04

14Reduce pressure drop across the duct from bag house outlet to

fan inlet –Kiln 2Nil 0.09

15 Reduce pressure drop across the circuit in Raw mills Nil 0.07

16Reduce pressure drop in down comer duct of Kiln Line 2 , Kiln

stringNil 0.05

17 Installation of RAL in feeding system of both the Raw Mills 20 0.21

13.05 Cr.2.38 kWh/t

Cement

Road Map to Achieve Benchmark/Global Best

19

ACC Limited

Innovative Project-1

Observation:

It has been observed that the Cooler ESP fan line-1 ID fan Drawing more

power…. Compare to cooler ESP fan line-2. ESP Dust spillage from various

point for ESP inlet Cone observe. During shut down we have found that

there is erosion in casing & missing Guide vanes . As a result extra air

ingress in ESP & disturbing gas distribution and damaging colleting

electrodes etc.

Reduction of Specific Electrical Energy Consumption by

Modification of Guide Vanes & Damage casing in Cooler

ESP line -1 inlet Cone.

In

no

vate

to

Excel

20

ACC Limited

Problem & Root Cause Analysis In

no

vate

to

Excel

Problem Defination

▪Cooler ESP ID draw more power.

▪ Dust spillage from ESP inlet Cone.

▪ Increase stack emission.

▪ Collecting Electrode bend and displacement in 1st Field in particular portion.

Root Cause Analysis : Observation During Kiln Shut down

▪Missing & Wear out existing Guide vanes.

▪Wear out ESP inlet cone casing as flue gas directly hit the casing due to missing of

Guide Vane.

▪ In absence of guide vane Gas Distribution has been disturbed, hence it damage

collecting electrodes in a particular part and reducing ESP efficiency. Increasing

Dust emission.

21

ACC Limited

Problem and Root cause analysisIn

no

vate

to

Excel

Guide

vane

position

Casing

Hole

Dust spillage from ESP

Casing

22

ACC Limited

What we have doneIn

no

vate

to

Excel

•Modification of Guide vanes in position based on CFD

analysis.

• Patch work done in ESP Casing

ESP INLET CONE LAYOUT WITH modified GUIDE VANES

Fixing of Guide Vanes

23

ACC Limited

Identification of High velocity Zone Through CFDIn

no

vate

to

Excel

Before After

24

ACC Limited

Cooler ESP Fan Energy Conservation ProfileIn

no

vate

to

Excel

After Before

25

ACC Limited

SEEC performance trendIn

no

vate

to

Excel

0.00

0.50

1.00

1.50

2.00

2.50

SEEC Cooler ESP Fan K1 MTD

Before Project Implementation

NOV-2016

0.00

0.10

0.20

0.30

0.40

0.50

0.60

SEEC Cooler ESP Fan K1 MTDFEB-2017

After Project Implementation

26

ACC Limited

Backup calculation of Savings / Improvement In

no

vate

to

Excel Before Project implementation

Average TPD KW SEEC

4534.75 230 1.22

After Project implementation

Average TPD KW SEEC

4721.15 156 0.40

Annual Savings

Electrical Energy Savings in KW 74

Annul Savings in SEEC 0.4

Annual Energy Savings in KWH 5,83,462.18

Annual Monetary Savings INR @ Rs 5.0/unit 29,17,310.88

Annual Electrical energy Saving in KWH : 5.83L Unit.

Annual Monetary Savings INR @ Rs 5.0/unit : Rs. 29.17 Lacs

27

ACC Limited

Environment Improvement by installation of Guide Vanes to

prevent frequent failure of Filter Bag causes High Emission

Innovative Project-2In

no

vate

to

Excel

• kiln-2 Bag house commissioned in the year 2012.

• Bag house was designed with an inlet operating condition of 850,000 m3/hr at 150 °C and -50 mm WG for a dust load of 60

g/m3 at inlet and 30 mg/Nm3 at outlet.

• Bag types used are woven fibre glass with PTFE lamination.

• Initially the Bag house operation was good after one year wear problems in the bag filters started.

• In practice, gas flow is uneven in inlet, resulting in high gas velocity in some modules. This may lead to wear in bags and thus overall higher dust emissions than expected.

•Damages have been observed in all the modules with major impact in module Nos. 4A, 5A, 4B, 6B and 6A particularly.

Problems definition :

28

ACC Limited

Problem Definition & Root Cause Analysis

In

no

vate

to

Excel

• The CFD team analyzed the process data and

equipment dimensions, created a 3D geometry of the

Bag house, its inlet & outlet duct to prepare computer

model of flow distribution inside Bag house.

• Several modifications are tried and the most

optimum modification has been inferred.

• Modifications include the insertion of new guide

vanes in the inlet duct, inlet plenum and common

inlet duct.

CFD study Out Come :

29

ACC Limited

Problem Definition & Root Cause Analysis

In

no

vate

to

Excel

30

ACC Limited

Problem Definition & Root Cause Analysis

In

no

vate

to

Excel

31

ACC Limited

Site Implementation: Fixing of Guide Vanes

In

no

vate

to

Excel

Site Implementation based on CFD study :

32

ACC Limited

Impacts & BenefitsIn

no

vate

to

Excel

• Homogenized flow distribution inside the Bag

house inlet duct, which will lead to better gas

distribution to various bag modules.

• Reduction of velocity inside initial modules, lead

to reduction in damage of bags.

• Reduction in dust emissions.

The stack Emission come down to the level of 50 – 70

mg/Nm3, before shut down it was around250-

300 mg/Nm3 at normal operating condition for Bag

house stack.

33

ACC Limited

Impacts & BenefitsIn

no

vate

to

Excel

Investment : INR 10 Lacs

Savings in Filter Bags : INR 55 Lacs

Materials Consumed

Year Wise materials consumtion details Year wise cost incurred in INR Lacs

2014 2015 2016

2017 ( actual 200 nos. till July & estimated 550 nos. for remaining period)

2014 2015 20162017 ( Actul till Jul-17 & estimated till Dec-17)

Saving w.r.t 2016 on A/C of Bag

Cages0 0 1460 0 0 0 69.27 0

54.95

Filter Bags

3550 945 2120 750 126.27 32.94 76.39 21.44

Total 3550 945 3580 750 126.27 32.94 145.66 21.44

34

ACC Limited

In

no

vate

to

Excel

Innovative Project-3

The objective of the project is to Lead Reduction by making a shorter distance Haul Road at Block I,

Connecting Block III to Block I

ACTIONS TAKEN

1. Backfilling is planned in worked out pit of Block I for Hauling Limestone to BMG Crusher

2. Design of optimized Layout of new haul road.

3. Comparison of Results between them.

RESULTS

1. Average lead reduction to be achieved 0.7 kms

2. Safe running hours of Dumpers

3. Reduction in Diesel consumption Rs 0.88Lak

Total saving 19.5 Lakhs / Year

35

ACC Limited

In

no

vate

to

Excel

Innovative Project-4

Changing the mindset

of people from

comfort to highly

stretched zone

Discussion / Brain Storming with Unionrepresentatives, HEOs, Maintenance,Crusher & support staff.

1 Shift - Maintenance (HEMM & Crushers)2 Shift - Operations

Mining Operations optimized to work in 2 shifts instead of 3 shifts in both the Mines

1

2

• United acceptance of challenge• Counseling operators and mechanicsand giving confidence.• Cascading targets• We Can & We Will

• Safety: Elimination of Night operationsof machines• To iterate plan & establish sequence ofworkings so as to get ample time forboth Operation & Maintenance.•Reduction in Idle Hours duringoperation• Hot seat changeover of operations•Good coordination in production andmines site in-charge with singleobjective• Improved Morale of workmen

Improved Quality of Life

3

Improved Working conditionReduction in overall Mining Cost by 3.80 Rs/T

(excluding royalty)

36

ACC Limited

Environmental Projects conti....

Sr

No.Name of the Environment Project

Year of

ImplementationCorrective & preventive actions

1Installation of Roof Top Solar system at

Admin Building and SMTI.

2016 Installed 2 nos. 10 kVA Roof Top

Solar system

2

Online continuous emission monitoring at CM-

1, CM-8, VRM, Coal Mill kiln -1 & 2, Cooler

ESP kiln -1 & 2

2016-2017 Installed CEMS in 8 nos. Stacks at

plant

3

Reduction of energy consumption in Pre-

heater fan line-1 by installing MVVF Drive by

replacing GRR

2016 Purchasing & erection of 1 no.

MVVF Drive with control panel & 1

lot control and power cable.

4

To improve the mine discharge water qualities

by construction of check dams.

2015 To construct 03 Nos. of check dams

in the mine discharge water drain in

Kalehra Village.

5

To improve aesthetic beauty and rehabilitation

of land by plantation and fencing to cover the

plantation.

2015 To plant sapling in the back filled

area and around the mines boundary.

6 Reduction of oil leakage and soil pollution by

replacing old Transformer (huge oil leakage)

with new 2MVA 6.6/440V transformer.

2015 Purchasing & installation of new

2MVA 6.6kV/440V

37

ACC Limited

Environmental Projects

Sr No. Name of the Environment ProjectYear of

Implementationcorrective & preventive actions

7Online continuous emission monitoring at

CM-9

2015 Installed CEMS in CM-9

8Online continuous emission monitoring at

Boiler-1 , Boiler-2 & Boiler-3 in CPP

2015Installed CEMS in Boiler-1 , Boiler-2 &

Boiler-3

9

To reduce thermal losses through

plenum chamber of Boiler No.1,2,&3

2015 Arresting of heat losses through plenum

air box by application of insulating

material in Boiler No. 1,2&3

10To reduce noise and dust emission while

drilling

2014 To deploy new drilling machine ROC L6

to increase efficiency and reduce dust

emission and noise levels at BMG

11To control resource (fuel) depletion by

introducing efficient hauling equipment

2014 To control resource (fuel) depletion by

introducing efficient hauling equipment at

MHG

12

Reduction of energy consumption in

Plant area to replace 70W MH light

fitting by 48W LED light.

2015 Purchasing & Installation of 200 nos.

LED light in 2nd phase

38

ACC Limited

Environmental Projects linking with Carbon

Emission Reduction

1199 1211

1045

800 800 800

0

200

400

600

800

1000

1200

1400

Actual 2015 Actual 2016 2017 YTD Target 2017 Target 2018 Target 2019

Net CO2 emissions(kg CO2/t cement)

39

ACC Limited

Environmental Projects linking with Carbon

Emission Reduction

62.7 63.5 63.962.8

76.475.3

79.7

76.8

33.131.5

34.3 34.5

81.079.3

85.282.7

3047.6

3054.0

3072.0

3074.3

3030.0

3040.0

3050.0

3060.0

3070.0

3080.0

3090.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

2014 2015 2016 2017 (TILL MAY)

Clinker Factor Production %

Electrical Energy

Consumption in Clinkering

Kwh/t Clk

Electrical Energy

Consumption in Grinding

Kwh/t CemGrd

Electrical Energy

Consumption Cement Kwh/t

Cem

Specific Thermal Energy

Consumption MJ/T Clinker

40

ACC Limited

Environmental Projects linking with Carbon

Emission Reduction

81.879.8 78.9

87.0

9.1 8.9 9.1 9.1

3268.0

3288.0

3300.7 3300.0

3200.0

3220.0

3240.0

3260.0

3280.0

3300.0

3320.0

3340.0

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

2014 2015 2016 2017 (TILL MAY)

PLF %

Aux.

Consumption

%

Heat Rate

kCal/kWh

41

ACC Limited

Environmental Projects with carbon Emission Reduction

11.5 Km long

overland Belt

Conveyor was

installed in 2007 to

eliminate the

vehicle movement

& carbon emission.

Massive plantation

in & around plant &

mining area to

reduce the CO2

42

ACC Limited

Involvement of Employees, Team Work in Encon

0102030405060

3121

4551

28

1421 18

39

MS

SFA

Total SGAs

Total Nos. of Person Involved

MS-132

SFA-135

Total Nos. of project implemented-267

43

ACC Limited

Brainstorming session: Energy Reduction

44

ACC Limited

Awareness Campaign: Energy Dream Run-’17

45

ACC Limited

GreenCo Site Assessment & Training

46

ACC Limited

ISO 50001-11: 2nd Surveillance Audit

47

ACC Limited

Energy Monitoring System

48

ACC Limited

Daily Reporting Section Wise Format

49

ACC Limited

Daily Reporting Equipment Wise Format

50

ACC Limited

ISO 50001-2011 & CII GreenCo Gold

51

ACC Limited

Renewal Energy

0

1

2

3

4

5

6

7

2013-14 2014-15 2015-16 2016-17 2017-18

4.7

6.0 6.0

6.5

7.0

0.80 1.00 1.001.25

1.50

Renewal Energy

Target Non-solar %Target Solar%

52

ACC Limited

% Investment for Energy Conservation Projects

The Financial Resource Allocation for energy conservation projects is conducted on monthly basis, where a committee of DGM Capex and Director Plant in the chair, review the activities carried out in the month, gives directions to the Energy Conservation cell for focused attention. Certain identified schemes where sizeable investment is required, the same are discussed at length and accordingly Director Plant sanctions the funds. Wherever the Financial commitments are substantial, the same are referred to Corporate Office for necessary sanctions under Capital Schemes

The total financial allocation for Energy efficiency projects is around 26.40% of our total fund allocation.

Energy Savings projects (in Lacs) 6,948.20

SUB TOTAL (in Lacs) 26323.20

26.40%

CAPITAL SCHEMES_May_2014 (1).xlsx

53

ACC Limited

Utilization of waste

for replacing the conventional energy

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

200000

2013 2014 2015 2016 2017 till

Jun

85221

60289

101633

143142

195563

4.03% 2.85%

4.75%

6.69%

9.14%

M kcal from AFRTSR %

54

ACC Limited

List of Industrial Waste Co-Processed by ACC

✓ HUL Waste

✓ Plastic Waste

✓ Spent Carbon

✓ ETP Sludge & ETP

Bio Sludge

✓ Paint Sludge

✓ Nivea Waste

✓ CIL Waste

✓ Acid Tar Sludge

✓ Mattel Toys

✓ Plant & Colony

Waste

✓ Laminated Waste

✓ SRF Waste

✓ Trade Rejects

✓ Scrap Tyres

✓ Chemical Sludge

✓ Phosphate Sludge

✓ Footwear Scrap

✓ Green Mash with

Resin

✓ Godrej Waste

✓ ITC Waste

✓ SEP Sludge

✓ N Butanol Salt

✓ Spent Wash

✓ Liquid wastes

Trade rejects

Process waste

F

M

C

G

ETP Sludge, WTP Sludge, Spent Carbon

Food

Pro

ducts

Auto

mobile

Chem

i

cal

Narmada Chematur Petrochemicals

55

ACC Limited

GreenCo Best Practices in Waste Management- 2016

56

ACC Limited

Best Practices – 1: Implemented in Green Supply Chain DIESEL CONS,. LOCO 2015

D/CON. Loco 1 Loco 2 Loco 3 Loco 4

JAN 0 3254 3764 6208

Feb 0 2540 2870 5397

Mar 0 3702 3214 7706

Apr 0 3597 3103 7603

May 0 3713 2494 6813

Jun 0 4583 4382 8272

Jul 0 3500 3920 7998

Aug 320 5480 3100 6000

Sep 0 3200 3250 2750

Oct 0 3150 3832 3850

Nov 0 3341 3790 1720

Dec 0 3729 3402 3700

TOTAL 320 43789 41121 68017

DIESEL CONS,. LOCO 2016

D/CON. Loco 1 Loco 2 Loco 3 Loco 4

JAN 0 3350 2131 6346

Feb 0 2363 2650 4367

Mar 0 3434 4548 4350

Apr 0 2970 2512 4060

May 0 3280 3650 6100

Jun 0 5250 4000 6650

Jul 0 4270 3750 7050

Aug 0 3750 2850 6300

Sep 0 3600 2800 4650

Oct 0 3590 2000 5100

Nov 0 4050 2200 5550

Dec 0 3150 1450 5550

TOTAL 0 43057 34541 66073

Total Diesel Consumption in

2015 is 153247 LitreTotal Diesel Consumption in

2016 is 143671 Litre

1.Decrease in ideal time of loco(Earlier loco was kept on running due to starting issue, the problem

was solved by replacing the old ignition system with new and advanced circuit)

Reason for Diesel Saving

Total Diesel Saving 9576 Litre and

Cost benefit is 612864 INR

57

ACC Limited

Best Practices–2: Implemented in Green Supply Chain

58

ACC Limited

Best Practices–3: Implemented in Green Supply Chain

59

ACC Limited

Best Practices–4: Implemented in Green Supply Chain

60

ACC Limited

Kymore Mining Lease is Awarded as 5 star Mines by Ministry of Mines

61

ACC Limited

CII National Award for Energy Efficiency 2016

62

ACC Limited

Earth Care Award for Reduction of Green House Gases

Emission (Large Enterprises Category) - 2014

63

ACC Limited

CII 14th National Award for Energy Efficiency-2013

64

ACC Limited

CII 14th Environmental Best Practices Awards 2013

65

ACC Limited

National Awards : At a Glance

66

ACC Limited