179120236 NEBB Smoke Control Systems

84
Smoke Control Systems Introduction and Commissioning NEBB 2010 Semi-Annual Recertification Presented By: Matt Donahue, P.E. January 20, 2009

Transcript of 179120236 NEBB Smoke Control Systems

Page 1: 179120236 NEBB Smoke Control Systems

Smoke Control Systems

Introduction and Commissioning

NEBB 2010 Semi-Annual Recertification

Presented By: Matt Donahue, P.E.

January 20, 2009

Page 2: 179120236 NEBB Smoke Control Systems

Agenda

• Codes related to Smoke Control and

Design Guides

• System Concepts

• Smoke Control System Information –

Using Documents

• Commissioning

Page 3: 179120236 NEBB Smoke Control Systems

Requirements and Standards

• International Building Code, Section 909

– Formerly 1994 & 1997 UBC Section 905

– California Building Code

• NFPA 92A - Standard for Smoke Control Systems Using Barriers and Pressure Differences

• NFPA 92B - Standard for Smoke Management in Malls, Atria, and Large Areas

Page 4: 179120236 NEBB Smoke Control Systems

Design References

• Design of Smoke Management Systems

–Klote & Milke

• ICC Guide to Smoke Control

–Evans & Klote

• NFPA 92A & 92B

• National Resource Council of Canada

Page 5: 179120236 NEBB Smoke Control Systems

Types of Systems Required

• The IBC requires systems to be

installed or provided for certain special

uses or occupancy types.

• IBC refers designer to Section 909.

• There are no specific types of systems

required by Code.

• Type is based on a Rational Analysis.

Page 6: 179120236 NEBB Smoke Control Systems

International Building Code

• Smoke Control Required For:

–Atrium (Section 404.4)

–Enclosed Malls when Atrium qualifications

are met (Section 402.9)

–Some Underground Buildings (Section

405.5)

–Smokeproof Enclosure design options

(Sections 1019.1.8 and 909.20)

–Stages, in lieu of roof vents (Section

410.3.7.2)

Page 7: 179120236 NEBB Smoke Control Systems

Other Requirements

• May be required by local (or state)

ordinances for all high-rise buildings -

carry-over from previous codes.

• Timed egress studies.

• Smoke protected seating allowances.

• Alternate Materials and Method

Requests.

Page 8: 179120236 NEBB Smoke Control Systems

Smoke Control System

Concepts Introduction • It is important to recognize that these systems are not

intended for: – Preservation of contents.

– Timely restoration of operations.

– Assistance in fire operations/overhaul.

• They are intended to: – Manage where smoke goes and where smoke does not go.

– Maintain a tenable environment by limiting the spread of smoke to areas outside the zone of origin (IBC 909.1). They do not always maintain a tenable environment in the smoke control zone of fire origin.

Page 9: 179120236 NEBB Smoke Control Systems

Smoke Control System

Concepts

• ―Passive‖ vs. ―Active‖ Smoke Control

• Smoke Barriers, Zone Boundaries and

Opening Protection

• Stairwell Pressurization – ―Smokeproof‖

Enclosures‖

• Types of Mechanical Smoke Control

Systems

Page 10: 179120236 NEBB Smoke Control Systems

Passive vs. Active Control

• ―Passive‖ uses building construction to

limit the spread of smoke in a structure.

• ―Active‖ uses mechanical equipment to

control the spread of smoke in a

structure. Defined as mechanical

systems by Code and include

pressurization method, airflow method

and exhaust method.

Page 11: 179120236 NEBB Smoke Control Systems

Passive Smoke Control

• Previously known as ―compartmentation‖.

• When active is not feasible (small rooms, no make-up air, unoccupied areas)

• Depends upon location within zone.

• May be separate zone or part of the same zone (sub-zone).

• If entirely bounded within a zone, no pressure difference can be obtained between the active and passive zone.

Page 12: 179120236 NEBB Smoke Control Systems

Smoke Barriers • Used to separate smoke zones: 1-hour

rated wall construction, outside wall to outside wall.

• Leakage area ratios

–walls 0.00100

–exits 0.00035

–other shafts 0.00150

– floors and roofs 0.00050

–openings determined by area

Page 13: 179120236 NEBB Smoke Control Systems

Opening Protection in Barriers

• Automatic closing (Self-closing OK in

many normally closed applications).

• Tight fitting smoke and draft control.

• 20-minute rating for doors.

• Gasketing - top, sides, and sill.

• Smoke/fire dampers at HVAC openings,

Class II minimum leakage rating, 250 oF

(121 oC) thermal release.

Page 14: 179120236 NEBB Smoke Control Systems

Opening Protection (cont.)

• Combination Fire/Smoke Dampers:

– When a fire damper is used within ductwork

on a smoke control system, the operating

temperature is required to be at least 50F

(10C) above the maximum smoke control

temperature or a maximum of 350F (177C).

– This is to ensure the damper will not close

prematurely when the system is operating in

the smoke control mode.

Page 15: 179120236 NEBB Smoke Control Systems

―Smokeproof‖ Enclosures

• Significant Changes to previous Code approaches used.

• Multiple Design Options Now Available:

–Natural ventilation alternative (909.20.3)

–Mechanical ventilation alternative (909.20.4)

–Stair pressurization alternative (909.20.5)

Page 16: 179120236 NEBB Smoke Control Systems

Natural Ventilation

• Open exterior balcony or vestibule with

opening 16 sq. ft. in area facing an open

area that is at least 20 ft. in width.

• Stair enclosure separated from building.

Page 17: 179120236 NEBB Smoke Control Systems

Mechanical Ventilation • Stair Shaft Pressurization –

+0.10‖w.c. (25 Pa) from stair to all

vestibules.

• Relief vent at top of stair shaft

adjusted to maintain +0.10‖ w.c.

pressure in stair shaft.

Page 18: 179120236 NEBB Smoke Control Systems

Mechanical Ventilation (cont.)

• Vestibule Ventilation – One air

change/minute supply with exhaust at

least 150% of supply.

– Engineered system sized to provide 90

air changes per hour serving up to three

vestibules simultaneously.

– Smoke trap in vestibule, ceiling at least

20‖ above door.

Page 19: 179120236 NEBB Smoke Control Systems

Mechanical Ventilation (cont.)

• Vestibule Ventilation (continued)

– Supply air within 6‖ of floor level.

– Exhaust air entirely within the smoke trap

and not more than 6‖ down from the top of

smoke trap.

– No dampers required in system, unless

engineered so.

Page 20: 179120236 NEBB Smoke Control Systems

Stair Pressurization

• Only in fully sprinklered buildings.

• Vestibules are not required.

• Stair Shaft Pressurization –

+0.15‖w.c. (37 Pa) minimum up to

+0.35‖w.c. (87 Pa) maximum to all

vestibules.

Page 21: 179120236 NEBB Smoke Control Systems

Stair Pressurization (cont.)

• Major Considerations:

– Beware of door opening force limitations!

– Consider maximum stack effect

pressures, temperature gradients.

– Tested with all doors closed.

– No relief vent required at top of shaft, but

may enhance system operation and

balance system operation.

– Difficult to achieve in tall buildings with a

single zone in stairway.

Page 22: 179120236 NEBB Smoke Control Systems

Ventilation Equipment

• Activated at each floor level at the entrance to the ―Smokeproof‖ Enclosure.

• Ventilation system to be separate from building systems

• Standby power required.

Items to Consider: Suggestions: 1) Stack effect 1) Pre-test before inspector arrives

2) Porosity of walls 2) Door sweeps may help

3) Door leakage 3) Multiple injection points ~7-9

4) Door opening forces floors max. for 1 injection point

5) Climate 4) Adjust fan capacities

5) Adjust barometric damper

Page 23: 179120236 NEBB Smoke Control Systems

Mechanical Smoke Control • Pressurization is default design method in

IBC.

• Exhaust can be used with the approval of

the AHJ.

• When is one is better than the other?

– Exiting considerations.

– Building configurations.

– Zone boundaries.

Page 24: 179120236 NEBB Smoke Control Systems

Mechanical Smoke Control • Typical Uses of Active Systems:

– Pressurization – enclosed spaces, office areas,

residential corridors, where no make-up air is

provided.

– Exhaust – large open spaces (atrium, mall,

etc.) where make up is available or the zone is

not completely bounded by walls.

– Air Flow – protection of openings that do not

have physical protection.

– Modified type systems.

Page 25: 179120236 NEBB Smoke Control Systems

Design Options

• IBC 909.6 ―Pressurization Method‖ and NFPA 92A - Enclosed spaces, pressure differential developed for containment.

Page 26: 179120236 NEBB Smoke Control Systems

Pressurization Method

• Pressure difference across barrier at least 0.05-inch water column (12 Pa) for sprinkler protected buildings.

• Twice the maximum calculated pressure differential produced by the design fire in sprinkler protected buildings.

• Maximum pressure dependent on door opening forces.

Page 27: 179120236 NEBB Smoke Control Systems

Pressurization Method (cont.) • Add up leakage area from construction,

openings, including doors, to determine flow rate to achieve pressure differential.

– Q = 2610 A (ΔP)½

– where Q = Leakage Rate (cfm)

– A = Area of Openings (sq. ft.)

– ΔP = Pressure Difference (inch w.c.)

• Problems – Building may be tighter than calculated

– Oversizing fans means additional pressure

– Balancing with stairs

– Door opening forces

Page 28: 179120236 NEBB Smoke Control Systems

Door Force Calculations

• The opening force for doors at smoke zone boundaries is limited to no more than 30 lbs. (Some jurisdictions limit the opening force to no more than 15 lbs.).

• The opening force is determined by the force to overcome the closing device and the pressure against the door.

• The larger the door or the greater the pressure difference, the more the opening force will be.

Page 29: 179120236 NEBB Smoke Control Systems

• IBC 909.8 ―Exhaust Method‖ and NFPA 92B -

Open spaces, smoke exhaust to maintain smoke

layer above people on highest occupied level.

Page 30: 179120236 NEBB Smoke Control Systems

Exhaust Method

• Useful for large enclosed volumes.

• Maintain smoke 6 ft. above highest walking surface in the zone (previously 10 ft.)

• Natural or mechanical supply equal to or slightly less than exhaust (85% is general rule of thumb).

Page 31: 179120236 NEBB Smoke Control Systems

Exhaust Method (cont.) • Maximum velocity of air supply

toward the fire is limited to 200 fpm. – May affect plume geometry and

increase air inducted into the plume.

• Plume types - must consider the type:

– Axisymmetric

– Balcony spill

– Window

Page 32: 179120236 NEBB Smoke Control Systems

Make Up Air

• The IBC requires make up air to be provided

for exhaust method systems.

• Required to be introduced at a rate slightly

less than the exhaust rate and cannot exceed

200 feet per minute towards the fire.

• As indicated before, the typical rule of thumb

is to provide at least 85 percent of this make

up air either by mechanical or natural means.

The other 15 percent can be obtained

through infiltration (building leakage).

Page 33: 179120236 NEBB Smoke Control Systems

Make Up Air (cont.)

• Make up air for high volume rate systems

can be difficult to provide given building

geometry and configurations.

• An exhaust rate of 200,000 cfm requires up

to 850 square feet of free openings to meet

the 85 percent rule. That equates to 85

linear feet of 10 foot high openings!

Page 34: 179120236 NEBB Smoke Control Systems

Make Up Air (cont.) • Make up air needs to be introduced below the

smoke layer. If an exhaust system is being provided for a multi-level space (such as an atrium) the make up air can be introduced at multiple levels, thereby decreasing the impact of the make up air requirements for any one level.

• The free area of a vent, grille, louver or door opening needs to be included in the make up air flow rate. Most grilles and louvers do not provide 100 percent free openings. Even ―bird screens‖ can limit the free opening by as much as 10 to 15 percent.

Page 35: 179120236 NEBB Smoke Control Systems

Airflow Method (cont.) • Airflow cannot exceed 200 fpm.

• Problems:

– Must assume temperature of smoke.

– Not useful for large openings.

– Not useful for horizontal openings.

– 200 fpm velocity often exceeded.

Page 36: 179120236 NEBB Smoke Control Systems

―6 Air Change‖ Design

• In ―purging‖ systems (which are not smoke-control systems) with 6 air changes per hour, air is not completely replaced in 10 minutes.

– HVAC systems promote mixing of air.

– 37% of original air (smoke) remains due to dilution and stirring.

• Detailed discussion in NFPA 92A, Section A.5.3.3.6

Page 37: 179120236 NEBB Smoke Control Systems

Modified Systems

• Sometimes the building configuration

presents restrictions to meeting the

specific design criteria for any one of

the four prescribed methods. In these

situations, a ―modified‖ approach may

be necessary.

Page 38: 179120236 NEBB Smoke Control Systems

Modified Airflow

• Below grade parking garages often do not have sufficient height to allow the exhaust method to work and the drive aisles are open to the exterior to prevent practical use of the pressurization method.

• The Modified Airflow approach has been used under these conditions, which is essentially a purge method approach that limits the make up air to no more than 200 feet per minute at the openings to the exterior or drive aisles.

• Not very scientific but has been used in many jurisdictions.

Page 39: 179120236 NEBB Smoke Control Systems

Design Considerations:

• Each of the four prescribed methods of

smoke control have certain limitations.

Often these come to light during

commissioning of the systems.

• The following are some of the lessons

learned during these times.

Page 40: 179120236 NEBB Smoke Control Systems

Design Considerations: • It is impossible to get a pressure difference from one

space to another if there is no make up air in the adjacent space.

• Not all small rooms will have smoke tight construction, even if confirmed during the design.

• Leakage rates given for construction walls, whether leaky or tight will always differ in the field from calculations.

• Horizontal sliding doors that have no bottom tracks do not work well at a pressurization zone boundary.

• Many building materials thought to be air-tight will leak if not painted or sealed.

• Air flow measurements at openings can often provide interesting results.

Page 41: 179120236 NEBB Smoke Control Systems

Rational Analysis

• There is no set document that is to be used for

the Rational Analysis. Each jurisdiction may

require or allow something different.

• The IBC requires the Rational Analysis to include

at a minimum:

– An explanation of the types of systems to be used.

– The methods of operation.

– The systems supporting them.

– The methods of construction to be used.

Page 42: 179120236 NEBB Smoke Control Systems

Rational Analysis

• The Rational Analysis should include

– A description of each zone, including the zone

designation.

– The type or method of smoke control.

– The method to activate the system.

– A description of how the system will configure.

– A description of whether the system will be

dedicated or non-dedicated.

– The pass/fail criteria for each system.

– What devices and equipment will be monitored

and in what position.

Page 43: 179120236 NEBB Smoke Control Systems

Rational Analysis

• Small-scale drawings should be

provided that show the zone boundaries

and the zone designation.

• Pressurized exit enclosures, passive

zones or sub-zones should also be

shown on these drawings.

Page 44: 179120236 NEBB Smoke Control Systems

Rational Analysis • The Rational Analysis should also include

information on how and what equipment will be monitored.

• Dampers to be monitored and which positions are monitored.

• Door monitoring, if required.

• How fans will be separated between uses.

• The design criteria for time to display the various status indications.

Page 45: 179120236 NEBB Smoke Control Systems

Rational Analysis

• The Rational Analysis can be part of an

overall document, such as a Fire

Protection Report or it can be a

separate Smoke Control Report,

depending upon the requirements of the

local jurisdiction.

Page 46: 179120236 NEBB Smoke Control Systems

Rational Analysis

• An example of a combined analysis may

look like this:

Page 47: 179120236 NEBB Smoke Control Systems

Rational Analysis

• And the Small-Scale Drawings like this:

Page 48: 179120236 NEBB Smoke Control Systems

Smoke Control Equipment • Fans (909.10.1)

• Ducts (909.10.2)

• Dampers (716.3 and 716.5.5)

• Power Systems (909.11)

• Detection & Control Systems

(909.12)

• Firefighters’ Control Panel (909.16)

Page 49: 179120236 NEBB Smoke Control Systems

Firefighters’ Control Panel

• Multiple Zone Example, shows status

and control on a zonal basis only.

Page 50: 179120236 NEBB Smoke Control Systems

Firefighters’ Control Panel

• Single Zone Example, shows status and

control for each piece of equipment.

Page 51: 179120236 NEBB Smoke Control Systems

Firefighters’ Control Panel • System Status Indication:

– Pilot-lamp-type indicators required in

909.16.1 (LED’s more commonly used—

more reliable, much longer life).

– Indication by each piece of equipment

(fans, dampers).

– Alternately for complex systems,

indication by single smoke zone of all

zone associated equipment.

Page 52: 179120236 NEBB Smoke Control Systems

Firefighters’ Control Panel

• System Control (Override) Capability:

– Manual switches by each equipment or by

whole zone.

– Don’t blow-up the duct!

Stay aware of what you are doing if you

throw any switch, anywhere, any time.

Page 53: 179120236 NEBB Smoke Control Systems

Commissioning

Page 54: 179120236 NEBB Smoke Control Systems

Special Inspection • Section 909.18.8 requires all smoke control

systems to be tested by a Special Inspector. – The Special Inspector shall have expertise in fire

protection engineering, mechanical engineering and/or certification as air balancers.

• Special Inspection is to occur: – During erection of ductwork and prior to

concealment for the purposes of leakage testing and recording of device location.

– Prior to occupancy and after sufficient completion for the purposes of pressure-difference testing, flow measurements, and detection and control verification.

Page 55: 179120236 NEBB Smoke Control Systems

Be Calm in the Chaos

Page 56: 179120236 NEBB Smoke Control Systems

Special Inspection • Team approach utilizing combination

of:

– Fire Protection/Mechanical Engineers.

– Air Balance Personnel.

– Fire Alarm/Controls Companies.

• More common during annual retesting.

Page 57: 179120236 NEBB Smoke Control Systems

Special Inspection

• Expertise in multiple fields required.

• Team approach often used.

• Lead Agency with subcontractors,

subconsultants to fill out areas of

expertise.

– Observation of Builder’s Subcontractors.

Page 58: 179120236 NEBB Smoke Control Systems

Special Inspectors • Responsible to certify that the system has been

installed in accordance with the approved design

documents, which are assumed to comply with the

Code.

• The Special Inspector is not the Designer. Do not

redesign the system. Where questions arise in the

design, they must be referred to the Designer.

• Don’t try to break the system, test to the designer’s

sequence of operation. Does the system work as

designed?

Page 59: 179120236 NEBB Smoke Control Systems

Plan for Testing • Agree on performance goals.

– Contained in approved Rational Analysis.

– If not, develop a test plan before testing

begins.

• Confirm agreement with:

– Design Engineer/Architect

– Building and Fire Inspection Authorities

– General Contractor

– All Subcontractors

Page 60: 179120236 NEBB Smoke Control Systems

Plan for Testing

• Schedule test time, including time of

day, days of the week.

• Keep the AHJ informed.

• Keep the Client informed.

• Keep the Contractor informed.

Page 61: 179120236 NEBB Smoke Control Systems

Inspection Sequence • Detailed device inspections.

• Subsystem operation tests.

• Full system functional tests.

• Air flow/pressure differential verification.

Page 62: 179120236 NEBB Smoke Control Systems

Early Stage Inspection Item

• Duct leakage:

– Allowed 5% of fan capacity at 150% static.

– Test duct work in segments if too large or

concealment is imminent.

• Usually done by the Air Balance firm.

Page 63: 179120236 NEBB Smoke Control Systems

Check Devices (Elements)

• Fans – tag number, capacity, power,

speed, rotation, service rating, VFD

settings, HOA bypass.

Page 64: 179120236 NEBB Smoke Control Systems

Check Devices (Elements) • Fire & smoke dampers - operation,

speed, installation, type, location,

power.

• Doors - label, operation, location.

• Smoke barriers - leakage, integrity.

Page 65: 179120236 NEBB Smoke Control Systems

Check Full System Operation

• Sequence of events.

• Control Priorities—Automatic and

Manual Overrides.

• Operability of other system

components in alarm conditions.

• Emergency power.

Page 66: 179120236 NEBB Smoke Control Systems

Functional Testing

• Pressure differential/exhaust air flow

measurements - includes fan data.

Page 67: 179120236 NEBB Smoke Control Systems

Functional Testing

Page 68: 179120236 NEBB Smoke Control Systems

Pressure Tests

• Pressure gauges:

–Lack the accuracy required to measure

system performance.

• Inclined manometer:

–Specified in IBC, not very accurate.

Page 69: 179120236 NEBB Smoke Control Systems

Pressure Tests

• Transducers:

–Equipment is calibrated to a known source.

–Commonly used by air balance personnel.

Page 70: 179120236 NEBB Smoke Control Systems

Door Opening Forces • Verify door opening forces on all

or representative sample of doors at zone boundaries, including stair doors, to confirm opening force does not exceed the allowed door opening force. Will likely require adjustments to closers in some cases.

• Test apparatus can be easily obtained but can also be easily lost, so buy many.

Page 71: 179120236 NEBB Smoke Control Systems

Flow Rate Measurement

• Flow hood.

• Velocity – traverse, pitot tube.

Page 72: 179120236 NEBB Smoke Control Systems

Passive Barrier Testing • Listed blower door

assemblies.

– Pressurize room and compare

actual leakage to calculated

allowable leakage rate at the

observed pressure.

• Configure HVAC to pressurize

space.

– Engineer may provide table of

allowable leakage rates at

varying pressure differentials.

Page 73: 179120236 NEBB Smoke Control Systems

Passive Barrier Testing • In general, if the room is ready

to test it should pass and that most rooms have actual leakage less than allowable by up to 50 percent.

• When testing representative sample of rooms, choose rooms for both sides of building.

• Equipment is usually calibrated with reference charts to be tested at 0.05-inch water column.

• When room is too large, multiple fans or door blowers can be used.

Page 74: 179120236 NEBB Smoke Control Systems

Test Methods - Reflect Design

• Systems are designed to manage where smoke goes.

• Systems are not designed to provide tenable conditions in the area of fire origin.

• Smoke tests, if used, should demonstrate air flow direction of the system considering the buoyant nature of smoke.

Page 75: 179120236 NEBB Smoke Control Systems

Other Test Methods

• Chemical smoke, tracer gas and real

fire tests.

– Limited value in evaluating certain system

performance.

– Validity as methods of testing a smoke-

control system is questionable.

– Detailed discussion in NFPA 92A, Section

A.5.3.3.6 and NFPA 92B, Section 5.3.6.2.

• Some jurisdictions will still require it.

Page 76: 179120236 NEBB Smoke Control Systems

Chemical Smoke Products

Page 77: 179120236 NEBB Smoke Control Systems

―Cold‖ Smoke Test

Page 78: 179120236 NEBB Smoke Control Systems

Documentation

• Complete test records are essential.

• Provide a copy of all test documentation

to the Special Inspector:

– Copy of deficiency lists provided to

General Contractor

– Copy of interim and final air balance

reports.

– Complete fan start-up information.

Page 79: 179120236 NEBB Smoke Control Systems

Documentation – Daily Report

The daily report

provides specific

information on the

areas and system

components tested,

whether there were

any deficiencies

noted and resolved

or left outstanding.

Page 80: 179120236 NEBB Smoke Control Systems

Documentation – NCR

The Non-

Conformance Report

identifies outstanding

issues or deficiencies

noted during the

course of testing and

also provides a

means to officially

notify the Contractor.

Deficiencies should

be specifically

identified.

Page 81: 179120236 NEBB Smoke Control Systems

Documentation - Fans

Page 82: 179120236 NEBB Smoke Control Systems

Documentation – Passive Barriers

Page 83: 179120236 NEBB Smoke Control Systems

Additional Inspection

Guidance • National Environmental Balancing Bureau

(NEBB).

• Associated Air Balance Council (AABC).

• American Society of Heating, Refrigerating

and Air Conditioning Engineers (ASHRAE).

• Society of Fire Protection Engineers (SFPE)

• Sheet Metal and Air Conditioning Contractors

National Association (SMACNA).

Page 84: 179120236 NEBB Smoke Control Systems

Thank You For Your Time!

Questions?

rjainc.com (925) 938-3550