Pipeline Approvals in the Mackenzie Valley
Jann AtkinsonEnvironmental Specialist
Applications Unit, National Energy Board
16 October 2001
Calgary
National EnergyBoard
Office nationalde l’énergie
National EnergyBoard
Office nationalde l’énergie
Canada
Introduction The purpose of this presentation is to
provide an overview of the National Energy Board pipeline approvals process in the Mackenzie Valley
National EnergyBoard
Office nationalde l’énergie
Canada
Who are We? Independent regulatory tribunal - formed
40 years ago under NEB Act to regulate: construction and operation of inter-provincial and
international oil and natural gas pipelines (e.g., Alliance, Foothills pre-build, Norman Wells, TransCanada)
development of oil and gas resources in non-accord frontier areas (Mackenzie Delta, Fort Liard)
some international power lines the import and export of energy commodities
National EnergyBoard
Office nationalde l’énergie
Canada
Who are we really? 8 permanent board members, appointed by
Cabinet for 7-year terms Chair - Ken Vollman;
Vice Chair - Judith Snider 275 staff, one office
35 economists and financial experts 30 environmental specialists 30 engineers regulatory officers, project managers, library etc.
National EnergyBoard
Office nationalde l’énergie
Canada
National Energy Board Act The NEB regulates the construction and
operation of the oil and gas facilities
National EnergyBoard
Office nationalde l’énergie
Canada
Role in the North Three aspects to NEB’s job in the North
1) Canada Oil and Gas Operations Act (COGOA) regulation of upstream oil and gas activity in the NWT
2) regulation under the National Energy Board Act (NEB Act) of inter-provincial and international pipelines
3) provision of technical and advisory services upon request in the Yukon
National EnergyBoard
Office nationalde l’énergie
Canada
COGOA vs. NEB Act
Alberta or British Columbia
}NEB Act
NWT
COGOA
National EnergyBoard
Office nationalde l’énergie
Canada
COGOA authorizations Geological/Geophysical Operations
Authorizations Authority to Drill a Well Significant Discovery Declaration Commercial Discovery Declaration Development Plan Construction Authorizations Production Operations Authorization
National EnergyBoard
Office nationalde l’énergie
Canada
Help! Regulatory Roadmaps Project - regulatory
approvals processes for oil and gas exploration and production - CAPP
Southern Mackenzie Valley (October 2000) Inuvialuit Settlement Region (June 2001) others are in preparation: Gwich’in, Sahtu
National EnergyBoard
Office nationalde l’énergie
Canada
NEB Act
Order (pipelines < 40 km in length)
Certificate of Public Convenience and Necessity (pipelines 40 + km in length)
National EnergyBoard
Office nationalde l’énergie
Canada
National EnergyBoard
Office nationalde l’énergie
Canada
Certificate
General Phases: Application Environmental Assessment Process Public Hearing Process Environmental Assessment Decision Regulatory Decision and Recommendation Governor-in-Council Certificate of Public Convenience and Necessity Detailed Route Hearings Condition Compliance (pre-construction) Leave to Open
National EnergyBoard
Office nationalde l’énergie
Canada
Regulatory ProcessRegulatory Process EA ProcessEA Process
National EnergyBoard
Office nationalde l’énergie
Canada
Panel Assigned• 3 Board Members
Guidelinesfor
filingRequirements
Application is Filed
Project Working Group• environment• socio-economic• engineering• financial, etc
Is application Complete?No Yes
National EnergyBoard
Office nationalde l’énergie
Canada
Public Hearings
all proposed pipelines > 40 km in length are subject to a public hearing process
Flexible process
National EnergyBoard
Office nationalde l’énergie
Canada
Public Hearing
Consider a wide range of issues design and operation safety environmental and socio-economic issues supply, markets, economic feasibility pipeline tolls and tariffs effectiveness of public consultation landowner matters
NEB Act aspects involve consideration of anything in the ‘public interest’ - allows the NEB to focus on issues of key local importance
National EnergyBoard
Office nationalde l’énergie
Canada
Panel Assigned
Public HearingProcess
NEB Act
Regulatory Decision &Recommendation
GIC
Certificate Issuedby NEB
EAProcess
National EnergyBoard
Office nationalde l’énergie
Canada
Public Hearing
Hearing Process is Initiated
Notice is Published in the Newspapers, Press Release, Internet Directions on Procedure -what, when, how to participate etc. timelines established to identify participants evidentiary record is ‘built’
- information is filed
- information requests and responses
National EnergyBoard
Office nationalde l’énergie
Canada
Public Hearing
Oral Hearings
additional information questioning final argument ----------------------------------------- Held in centres directly affected by a project at times
convenient for the public Flexibility
National EnergyBoard
Office nationalde l’énergie
Canada
Oral Hearing Concludesand is Adjourned
Reasons for Decision
Recommendation to GIC
Approval Not to approve
Certificate
Accept Reject
National EnergyBoard
Office nationalde l’énergie
Canada
Construction? Now that you have the certificate, can you construct?
Not quite yet………….
Detailed Route Hearings Condition Compliance
National EnergyBoard
Office nationalde l’énergie
Canada
Detailed Route HearingsOpportunity for landowners or other affected parties to
comment on: the detailed route of the pipeline
and/or the method and timing of construction held in the vicinity of the subject lands similar hearing procedures apply different panel of Board Members
National EnergyBoard
Office nationalde l’énergie
Canada
Condition ComplianceConditions on the Certificate
environmental manuals (e.g. Environmental Protection Plan, Safety Manual) detailed mitigation and follow-up plans design supply sunset clause some must be met prior to construction, others prior to operation
etc.
National EnergyBoard
Office nationalde l’énergie
Canada
Construction
Construction Inspection
Environment Safety Engineering Canada Labour Code
National EnergyBoard
Office nationalde l’énergie
Canada
Leave to Open
Prior to placing the pipeline in service
design safety (including pressure testing) conditions complied with environmental commitments
National EnergyBoard
Office nationalde l’énergie
Canada
Environmental Assessment
NEB has EA responsibilities under MVRMA, CEAA and NEB Act MVRMA - Designated Regulatory Agency - MOU
signed with MVEIRB in Dec 2000 to cooperate on EAs - Cameron Hills
CEAA - Responsible Authority - projects south of 60 and in the ISR
NEB Act - matters in the public interest
National EnergyBoard
Office nationalde l’énergie
Canada
Status - Northern Coordination Preparations
participant in discussions on regulatory and EA coordination in the NWT and Yukon purpose of coordination is to minimize duplication
while respecting land claims legislation, institutions created therein, need for northern participation, and industry’s need for certainty and clarity of process
National EnergyBoard
Office nationalde l’énergie
Canada
Key Messages - Review Process
NEB is only one of many key organizations with authority to examine impacts and influence conditions around energy development proposals in the North
Coordination with and contributions from Northern agencies will be essential in producing the best decisions
the agencies with a role in energy development in the North will work in partnership to ensure that the process meets local needs and encourages local participation
these agencies will be prepared to deal with the application in a fair and impartial manner in the public interest
National EnergyBoard
Office nationalde l’énergie
Canada