    The purpose of this procedure is to define the

    engineering estimating works in relation to bid

    proposal development and preparation of ProjectBudget.

    This procedure covers the methods used by

    Engineering Department for estimating works and

    the interrelated sequence to achieve a competitive

    bid proposal and preparation of Project Budget

    Estimates.

    The scope covers Onshore and Offshore

    construction works.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    3/17

    BID APPROVAL SHEET (BAS)

    Form No. MKD-4-006 is a document prepared by MMG Marketing

    Department highlighting items of the bid, and including the customers

    name, scope of work, type of contract, bid due date, special

    information and executive management approval to proceed with the

    engineering estimate.

    ESTIMATING WORKSHEET

    Form No. END-4-009B , is the worksheet used by the Estimating

    Engineer for summarizing the data for total quantities, labor rates,man-hours, description of materials, unit cost of materials &

    consumables, Equipment line-up & rental costs, subcontract quotation

    costs and the grand total of the quantities and costs.

    COSTING SUMMARY SHEET

    Form NO. END-4-009D, is a summary of costs prepared by Engineeringupon completion of the bid estimate which covers costs for labor,

    material, equipment rental, mobilization & demobilization, catering &

    accommodation, subcontract work, contingency, projection and

    escalation, medical & dental, and other costs representing the total

    cost of the bid price.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    4/17

    (continuation)

    PROJECT BUDGET

    Form No. END-4-009E, is a budget prepared by the

    Engineering for the performance of a newly awarded

    project. This covers direct and indirect cost.

    DIRECT COST

    Is cost for direct materials, labor, subcontract works asdefined in the summarized breakdown of Form END-4-009E

    INDIRECT COST

    Is cost for the mobilization & demobilization, home office

    cost (i.e. requisitioning / procurement, task force, drafting,as-built, shop drawing. Etc..) construction of temporary

    facilities, plane fare, recruitment, iqama, freight and

    handling, field supervision , administration & support labor

    and lied expenses.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    5/17

    CHIEF ENGINEER

    Overall management of the Engineering Department.

    ESTIMATING MANAGER

    Manage the Engineering Department estimating works,

    prepare project budget.

    ESTIMATING SUPERVISING ENGINEERSupervises the respective discipline engineering estimate.

    ESTIMATING ENGINEER

    Performs the respective discipline engineering estimate

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    6/17

    BID ESTIMATING

    The Engineering Document Controller check all the bid documents from the

    Central Documentation Control Section and forward to the Chief Engineer for

    review. After his review, the bid documents are forwarded to the ProposalManager who makes a further review of the documents before distribution to

    the Discipline Estimating Engineers. A review Record Sheet (Form No. END-

    4-009F) will be signed by the Estimating Manager, Discipline Estimating

    Supervising Engineers and Discipline Estimating Engineers after completing

    their respective reviews.

    The Discipline Estimating Engineer will make himself familiar with the scopeof the bid, will scan for possible subcontract works and availability of

    material to be supplied by MMG.

    The Discipline Estimating Engineer will highlight all important items in the

    scope and check that no bid items have been overlooked. An Engineering

    Estimating Check list (Form END-4-009C0 which identifies relevant items is

    completed by checking the boxes for items considered to be part or not partof the bid scope. The Check List will be double check by the Discipline

    Estimating Supervising Engineer. A blank format, sheet 11 of 11 Form END-4-

    009C, will be completed up by the Discipline Estimating Engineer or by the

    Discipline Estimating Supervising Engineer indicating other relevant items

    for consideration.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    7/17

    (continuation)

    The Discipline Estimating Engineer shall produce a material quantity take-off

    for each specific scope covered in the Estimating Work Sheet (Form No,

    END-4-009B) The data on the Estimating Work Sheet are companyconfidential and is therefore not transferred to the customer provided

    Summary Sheet.

    Attendance to Job-Explanation Meeting and Site Visit will either be optional

    or mandatory. Where the Bid Instruction Specification requires participation

    to either or both, The Estimating Engineer will attend the Job-Explanation

    Meeting and participate in Site Visit, However, where site visit is necessary ,on optional case, due to lack to bid information's, the Discipline Estimating

    Engineer will conduct a site visit to get the true picture of the field situation.

    The site visit will help the Discipline Estimating Engineer in his evaluation to

    make realistic considerations and assumptions in his estimates that will

    have significant impact on the bid final costing.

    Where the attendance of the Discipline Estimating Engineer is not possible, theChief Engineer / Estimating Manager will appoint a deputy to attend the Job-Ex

    Meeting and Site Visit.

    For Bid projects located in Yanbu, Jeddah or elsewhere, where MMG has an

    existing project, the Chief Engineer / Estimating Manager may elect to dispatch

    the Discipline Estimating Engineer to the site or may request the Project Manager

    of that existing project to deputies a representative to attend the Job-Ex and

    participate the Site Visit.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    8/17

    (continuation)

    Grey areas in the work scope that required contract evaluation shall be

    referred to the Contract s Department for prior clarification with

    Customer.

    Materials to be supplied by MMG are identified, quantified and if there is

    no current cost (within 90 days) available for the material, Cost Request

    (END-4-007A) is prepared. This form is forwarded to the Central

    Purchasing Department (CPD) to obtain prices. CPD shall furnish

    Engineering with at least three (3) suppliers quotation to arrive atminimum cost for major MMG supplied plant permanent materials.

    Where there is no response to the Cost Request (END-4-007A) at the

    due date required from CPD. (reference Procedures No. END-3-007

    and CPD-3-006) the Discipline Estimating Supervising Engineer and /

    or the Discipline Estimating Engineer shall follow up the Cost

    Request with CPD, Likewise, CPD shall advise concerned DisciplineEstimating Engineer regarding the status of the Cost request or if

    the prices is not available from the vendor on time for inclusion in

    the bid proposal. For prices not available, the Estimating Manager

    will advise to use the previous canvass price.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    9/17

    (continuation)

    The Discipline estimating Supervising Engineer will determine items to

    be subcontracted, prepare a Request for Quotation, using Form No.

    END-4-007D and forward to Contracts Department. The request willinclude, the subcontract technical specifications, list of proposed

    subcontractors, and applicable drawings. Costs from quotations will be

    included in the final costing using the applicable Project Code of

    Accounts, PCD Procedure No. OCD-3-005. Contracts Department shall

    provide Engineering with the updated list of approved subcontractors.

    When all quantities have been establish, they are entered into thecomputer using Lotus/Excel Spreadsheet. Form No. END-4-009B. This

    gives the direct cost for consumables, equipment rental cost and other

    determined subcontract item costs.

    Once all data, such as direct man-hours, materials & consumables

    quantities and equipment line-up has been summarized, the estimate isanalyzed making use of the standard unit man-hours in the Estimating

    manual in Procedure END-3-011, by extracting the overall average

    productivity rate in various terms such as mhr/lm, mhr/ton, mhr/dia-inch,

    mhr/dia-m,. This data is then compared with previously awarded project

    estimates and adjusted as necessary.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    10/17

    (continuation)

    The Discipline estimating Supervising Engineer checks the progress

    of the estimate, correcting any discrepancies, and highlights any

    items which may have been overlooked.

    The Discipline Estimating Supervising Engineer shall review and

    check the status of the cost request, any queries on grey areas, or

    other items relevant to the bid estimate.

    Addenda to the bid, received from the Customer are brought to theattention of the Discipline Estimating Engineer for consideration.

    Once the estimate is completed, the Discipline Estimating

    Supervising Engineer review the final quantities, direct man-hours,

    material and equipment costs, including outside rentals.

    Corresponding adjustments to man-hours and cost are made after

    further analysis of other cost considerations and assumptions.

    The Estimating Manager conducts the final review of the estimate,

    checks the breakdowns and commercial conformity of the proposal.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    11/17

    (continuation)

    The Discipline Estimating Supervising Engineer supplies the

    Technical / Commercial / Documentation Proposal Manager the

    direct man-hour breakdowns per activity using Form No. END-4-

    009B, to provide a reference for extracting indirect man-hours,

    indirect equipment-hours, and the formulation of bid construction

    schedules by the Proposal Engineer assigned from bid Planning and

    Scheduling programs. Indirect man-hours and equipment-hours are

    then forwarded to the Bid Development Proposal Manager forcosting.

    The Discipline Estimating Supervising Engineer forward all direct

    cost breakdown to the Bid Development Proposal Manager, The Bid

    Development Proposal Manager carry out the indirect costing an

    prepare the comprehensive Commercial Proposal. A costing

    Summary Sheet (Form No. END-4-009D) is used for summarizing thecosting breakdown.

    The completed Commercial Proposal is forwarded by the Bid

    Development Proposal Manager to the Estimating Manager for

    review.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    12/17

    (continuation)

    Reviewed Commercial Proposal is forwarded to the Technical

    / Commercial / Documentation Proposal Manager for finalcompilation in the bid form, and finally forwarded to the Chief

    Engineer for approval.

    Upon approval of the Chief Engineer, the Commercial

    Proposal is then presented by the Bid Development Proposal

    Manager to the Management for review and any directionadjustment to the final bid selling price, if no adjustment is

    directed, the Management makes the final approval.

    Any directed adjustments are made by the Bid Development

    Proposal Manager, and the adjusted commercial proposal is

    returned to the Management for approval or with theabsence of an Executive Officer, a designated authorized by

    the Management.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    13/17

    (continuation)

    PROJECT BUDGET

    Upon award of a project, the Estimating Manager prepares a

    Project Budget. The Estimating Manager prepares the

    project budget using Form No. END-4-009E.

    The Project Budget estimate covers all direct and indirect

    cost, for the complete performance of the project. Thecompleted Project Budget is forwarded by the Estimating

    Manager to the Chief Engineers approval.

    The Project Budget is then discussed by the Chief Engineer

    with the assigned Project Manager. Any adjustment is made

    before the budget is approved by the Project Manager andfinally forwarded for final approval of Management.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    14/17

    (continuation)

    HANDOVER TO PROJECT TEAM

    Upon approval of the Project Budget by the Management, the Chief Engineer willinstruct the Bid Development Proposal Manager to call a Project Briefing /

    Handover Meeting, attended by the following department:

    1. Executive Management

    2. Engineering

    3. Marketing

    4. Projects

    5. Projects Control6. Central Purchasing

    7. Contracts

    8. Quality Assurance / Quality Control

    9. Loss Prevention

    10. Finance & Accounting

    11. Equipment Supply Division

    12. Central Warehouse13. Human Resources

    (Personnel & General Services)

    Attendance is required by each participant in the Meeting Attendance register,

    Form No. QAD-4-213 used by the chairing personnel. Subject and agenda of the

    Project Handover Meeting is summarized using Form No. END-4-009G.

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    15/17

    (continuation)

    Engineering will provide the Project Overview for the Project

    Management Team and other parties involved.The Engineering Department will organize the Project Task Force,

    whose function is define in Procedure END-3-003, headed by the

    Project Task Force Supervising Engineer, to provide assistance to

    the assigned Project Manager prior to mobilization to the project

    site.

    The necessity for an organized Project Task Force is dependent and

    flexible to the size of the project, and upon recommendation by the

    Project Manager for its formation.

    The Engineering Department will then turnover the supervision of

    the Engineering Project task Force to the assigned Project Manager

    together with all project contracts and Engineering Documents.

    Distribution controlled copy of the approved Project Budget (Form

    No. END-4-009E) is issued by the Engineering Chief Engineer to the

    assigned Project Manager only, using the Transmittal Form No. QAD

    4-202

  • 7/28/2019 139405799 END 3 009 Engineering Estimating

    16/17

    START

    EXECUTIVEMANAGEMENT

    FINAL APPROVAL

    ESTIMATING MANAGER

    PREPARE PROJECTBUDGET

    END-4-009E

    AWARDEDPROJECTS

    BID

    ESTIMATING

    ESTIMATING MANAGER

    FORWARD PROJECTBUDGET TO CHIEF

    ENGINEER

    END-4-009E

    CHIEF ENGINEER

    DISSCUSS THE BUDGETWITH THE ASSIGNEDPROJECT MANAGER

    END-4-009E

    CHIEF ENGINEER /PROPOSAL MANAGER

    CALL PROJECT BRIEFINGHANDOVER MEETING /

    PROVIDE PROJECTOVERVIEW TO PROJECT

    MANAGEMENT TEAM

    CHIEF ENGINEER

    FORWARD PROJECTBUDGET FOR APPROVAL

    BY MANAGEMENT

    END-4-009E

    CHIEF ENGINEER/PROJECT MANAGER

    ORGANIZE PROJECT TASKFORCE, TURNOVER

    SUPERVISION AND PROJECTDOC. TO PROJECT MANAGER,PROJECT DOCUMENTATION &

    BID DRAWINGS

    ENGINEERING DOCUMENTCONTROLLER

    FORWARD ALL BIDDOCUMENTS FROM CENTRALDOCUMENTATION SECTION

    TO THE ESTIMATINGMANAGER

    BID DOCUMENT

    ESTIMATING ENGINEER

    ENTER ESTABLISHIEDQUANTITIES INTO COMPUTERPROGRAM FOR DIRECT MAN-

    HOURS AND COST

    END-4-009B / END-4-009B1

    ESTIMATINGSUPERVISING ENGINEER

    REVIEW FINALQUANTITIES DIRECT

    MAN-HOURS,MATERIALS AND

    EQUIPMENT COST

    PROPOSAL MANANGER

    PRESENT TO THE EXECUTIVEMANAGEMENT FOR REVIEWAND DIRECTION OF ANY

    ADJUSTMENT TO FINAL BID

    BID COMMERCIAL PROPOSAL

    ESTIMATING MANAGER

    REVIEW AND FORWARD TOESTIMATING SUPERVISING

    ENGINEER

    END-4-009F

    ESTIMATING ENGINEER

    IDENTIFY MATERIALSSUPPLIED BY MMG &PREPARE COST REQUEST FORMATERIAL & SUBCONTRACT

    ITEMS

    END-4-007A / END-4-007D

    ESTIMATING MANAGER

    CONDUCT FINAL REVIEWOF ESTIMATE CHECKBREAKDOIWN AND

    PROPOSAL COMMERCIALCONFORMITY

    TECHNICAL / COMMERCIAL /DOC PROPOSAL MANAGER

    FORWARD COMMERCIALBID PROPOSAL TO THECHIEF ENGINEER FOR

    APPROVAL

    ESTIMATINGSUPERVISING ENGINEER

    FURTHER REVIEW ANDDISTRIBUTE TO ESTIMATING

    ENGINEER

    END-4-009F

    ESTIMATING MANAGER

    ATTEND JOBEXPLANATION MEETINGAND PARTICIPATE IN

    SITE VISIT

    ESTIMATINGSUPERVISING ENGINEER

    SUPPLY THE TECHNICALCOMMERCIAL/DOC PROPOSALMANAGER THE DIRECT MAN-

    HOURS BREAKDOWN PERACTIVITY

    END-4-009B

    ESTIMATING MANAGER & TECH/ COMM / DOCUMENTATION

    PROPOSAL MANAGER

    REVIEW COMPLETEDCOMMERCIAL PROPOSAL /

    COMPILATION TO BID FORMAND FORWARD TO CHIEFENGINEER FOR APPROVAL

    END-4-009F

    ESTIMATING ENGINEER

    HIGHLIGHTS / CHECK BIDITMES ACCOMPLISH THEESTIMATING CHECKLIST

    END-4-009F/END-4-009C

    ESTIMATING ENGINEER

    PRODUCE MATERIALQUANTITY TAKE-OFF FOREACH SPECIFIC SCOPE

    END-4-009B1

    PROPOSAL ENGINEER(Planning & Scheduling)

    EXTRACT INDIRECT MHRS &EQPT HOURS ANDFORMULATED BID

    SCHEDULES,FORWARDINDIRECT HOURS TO BIDDEVELOPMENT MANAGER

    BID DEVELOPMENTPROPOSAL MANAGER

    CARRY OUT INDIRECTCOSTING & PREPARE

    COMPREHENSIVECOMMERCIAL PROPOSAL

    END-4-009D

    END