Formula Memorization Trick CV = EV - AC SV = EV - PV CPI = EV / AC SPI = EV / PV EAC = BAC / CPI ETC = EAC - AC VAC = BAC - EAC When memorizing the formulas I have found it best to look for patterns. When I see the correct pattern I know the formula is correct. AC = ACWP PV = BCWS EV = BCWP

description

PMP

Transcript of 134970542-Basic-PMP-Formulas.pdf

Page 1: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

When memorizing the

formulas I have found

it best to look for

patterns. When I see

the correct pattern I

know the formula is

correct.

AC = ACWP

PV = BCWS

EV = BCWP

Page 2: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

Ok lets build this.

First is to see the

pattern of 2

subtractions, 3

divides, 2

subtractions

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 3: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

Next see the pattern

of Variance and

Index.

Cost, Schedule and

Cost, Schedule.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 4: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

Next see the pattern

of Earned Value (EV).

This used to be

BCWP.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 5: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

Next see the pattern

of Actual Cost (AC)

and Planned Value

(PV) and how they

alternate. Skip a line

and its AC again.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 6: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

Next see the pattern

of Estimated at

Completion (EAC).

As well as Budget at

Completion (BAC)

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 7: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

Not much left. Notice

that CPI is divisor of

EAC so find CPI skip

a line and place it at

the end of EAC

formula.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

ETC and VAC don’t

really match to

anything, you just

have to know where

they go.

Page 8: 134970542-Basic-PMP-Formulas.pdf

Formula Memorization Trick

This may look

confusing but it

worked great

for me and I

have had

others tell me it

worked for

them as well.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 9: 134970542-Basic-PMP-Formulas.pdf

Other Formulas to Know

• Communication Channels: N(N-1)/2

• Pert Mean: (Pessimistic + 4*Most Likely +

Optimistic) / 6

• Standard Deviation: (Pessimistic – Optimistic) / 6

• Variance: ((Pessimistic – Optimistic) / 6) squared

• Present Value or PV: Future Value / (1+ rate of

return) to the power of n. Where n = periods of

time.