13 Ncbc-2011-Validating Energy Sources-Von Bank

download 13 Ncbc-2011-Validating Energy Sources-Von Bank

of 46

Transcript of 13 Ncbc-2011-Validating Energy Sources-Von Bank

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    1/46

    Kenneth Von Bank, PE, CCPMechanical EngineerSustainable Engineering Group LLC

    Commissioning Geothermal Systems

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    2/46

    Learning Objectives

    1. Gain a better understanding of the challenges of geothermalsystem design, installation, and operation.

    2. Demonstrate the ability to incorporate the knowledge ofgeothermal systems into all phases of the commissioningprocess.

    AIA Quality Assurance

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    3/46

    Assumptions

    Geothermal system has been shown tobe the best fit for the project through aLife Cycle Cost Analysis or similar

    Geothermal feasibility study has beenperformed

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    4/46

    Energy From the Earth/Sun

    Earth = solar battery

    Absorbs nearly halfof the suns energy.

    The ground stays arelatively constanttemperature

    Warm heat source inwinter

    Cool heat sink in

    summer

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    5/46

    The earth is like a solar battery absorbing nearly half of the suns energy.

    The ground stays a relatively constant temperature through the seasons,

    providing a warm source in winter & a cool heat sink in summer.

    4% absorbedby clouds.

    17% reflected

    by clouds.

    6% reflected

    by surface.

    19% absorbed by

    water vapor, dust

    46% absorbed bythe ground

    Outer SpaceOuter SpaceOuter SpaceOuter Space

    AtmosphereAtmosphereAtmosphereAtmosphere

    EarthEarthEarthEarth

    100%100%100%100%

    Nearly of thesuns energy is

    absorbed by earth

    5

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    6/46

    Ground-Source Heat Pumps

    GSHP

    A term applied to a variety of system

    components that use the ground,groundwater, or surface water as a heatsource and sink.

    Also Known As: Ground-Coupled Heat Pumps (GCHP)

    Ground-Water Heat Pumps (GWHP)

    Surface Water Heat Pumps (SWHP)

    Direct Expansion (DX) GCHP

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    7/46

    Ground Coupled Heat Pumps (GCHP)

    Closed-loop ground-source

    heat pumps

    Reversible vaporcompression cycle

    Closed ground loop heatexchanger

    Water or Water/antifreezesolution

    Most common typeWater-to-air heat pump

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    8/46

    Focus on Geothermal Field:

    Once the system is buried, it should remain

    buried for 50+ years.

    Repairing geothermal systems is difficult and

    costly after the system has been backfilled.

    Proper design, installation, and Cx willminimize the chances that the buried systemwill need repairs.

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    9/46

    GCHP Further Subdivided

    Type of ground heat exchanger design

    Vertical vs. Horizontal

    Hybrid System

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    10/46

    Advantages of Vertical GCHP

    Requires relatively small plots

    Soil varies very little in temperature andthermal properties

    Requires smallest amount of pipe andpumping energy

    Can yield the most efficient GCHP

    system performance

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    11/46

    Disadvantages of Vertical GCHP

    Higher cost becauseof equipment needed

    to drill borehole

    Drill Rig

    Grout

    Grout Mixer

    Limited experienced

    contractors

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    12/46

    Horizontal GCHP

    Advantages

    Less Expensive than

    vertical GCHP Residential

    applications haveadequate ground area

    More trainedequipment operators

    Disadvantages

    Larger Ground area

    requirement Greater adverse

    variations inperformance

    Ground Temperatures

    Rainfall

    Burial Depth

    Higher Pumping-Energy Requirements

    Lower SystemEfficiencies

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    13/46

    Commissioning Phases

    Planning

    Design

    Construction

    Occupancy/Operations

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    14/46

    Commissioning Phases

    Part 1: Planning Phase

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    15/46

    Planning Phase

    Approval from DNR or other governing body

    or Authority Having Jurisdiction (AHJ)

    Formation & Thermal Conductivity (TC) Test to

    determine ground properties

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    16/46

    Field Tests

    Drill to desired depth

    Use same pipediameter and grout

    Wait 5 days

    Insulate entire device

    Minimum test length

    = 48 hours

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    17/46

    Thermal Conductivity Test

    Advantages

    Accurate borefield size Indicates level of effort

    required to insert loop

    Type of drilling

    Reduce Contractorsuncertainty

    May reduce bid price

    Can use test bore in design

    Disadvantage Initial cost

    Results can be inaccurate

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    18/46

    F&TC Test Report

    Copy of Drill Log

    Ground ThermalConductivity (Btu/hftF)

    Ground ThermalDiffusivity (ft2/day)

    Undisturbed GroundTemperature (F)

    Depth to Water Table

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    19/46

    Water Problems

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    20/46

    Commissioning Phases

    Part 2: Design Phase

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    21/46

    Design Review: What to Look For

    Qualifications: Geothermal contractor

    certified by IGSHPA As-built drawings of geo field required

    (including GPS coordinates)

    F&TC Test results Contractor to integrate test bore into the

    geothermal field

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    22/46

    Design Review: What to Look For

    Pipe and fittings shall be HDPE classified for

    geothermal installation (IGSHPA) 50 year warranty provided by pipe manufacturer

    Heat transfer fluid must be approved by DNR orState Regulatory Agency

    Locating Wire and Warning Tape

    Thermal Grout: TC of at least 1.0 Btu/hr-ft-F (obtainsamples for testing)

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    23/46

    Thermally Enhanced Grout

    80

    90

    100

    110

    120

    130

    Bores

    0.45 0.6 0.85 1 1.2

    Grout Conductivity (Btu/hftF)

    200-Ton, 300' deep Vertical System

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    24/46

    Design Review: What to Look For

    Header Pit Vault HDPE classified for geothermal installations

    Factory pressure tested no leaks at 1 psi air test for at least 30minutes

    Entry to vault minimum 28 diameter, neoprene gasket on lid,traffic rated frame and cover if located in traffic area.

    Ladder Conform to current OSHA guidelines Anti-buoyancy calculations amount of concrete needed to

    anchor vault

    Valves: Isolation valve on supply line of each circuit. Balancing

    valve on return line of each circuit. P/T port on each supply and return main and all circuit pipes

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    25/46

    Vault Installation

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    26/46

    Header Pit Vault

    Circuits routed tounderground vault

    o Typically 3 Dia Circuits

    o Balancing Valves

    Only two pipes go backto building

    Concrete vs HDPE

    o

    Concrete cheapero HDPE water tight

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    27/46

    Design Review: What to Look For

    Pressure Testing

    Flushing and PurgingGrouting

    Backfilling

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    28/46

    Design Review: What to Look For

    Borefield Design

    Minimum bore spacing Bore depth

    Reverse Return piping configuration

    Minimum burial depth of lateral pipes (based on frost layer

    depth)

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    29/46

    Frost Layer

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    30/46

    Example: 100 Bore System

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    31/46

    Circuit

    Below Grade in Sand Bedding

    Reverse Return Balanced Flow

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    32/46

    Commissioning Phases

    Part 3: Construction Phase

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    33/46

    Construction Verification

    Before Excavation Begins

    Contractor Qualifications

    Shop drawings must be approved prior to ordering materials orstarting work

    Site Erosion Control Plan in place

    DNR and/or State Regulatory Agency approval

    Timing is critical

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    34/46

    Construction Verification

    During Excavation / Drilling / Pipe Installation Bore spacing / depth

    Materials on site: pipes, grout, backfill materials, vault, etc.

    Lateral pipe (trench) depth below frost line

    Grouting Procedure

    Must grout within 24 hours of drilling. No more than four un-grouted

    boreholes at any one time. Test grout mixture samples early.

    Seal open ends of pipes to prevent entry of contaminants

    Timing of verification is critical

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    35/46

    Open Pipe Ends

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    36/46

    Construction Verification

    Prior to Backfilling Pressure Testing successful and witnessed

    Test with water, NOT air

    Flushing and Purging successful and witnessed

    At least 2 ft/sec to remove air and debris

    Bedding material (sand) is free of rocks, clay, and sharp objects

    Locating wire installed on pipes Location of bores and pipes have been surveyed as-built

    drawings are accurate

    Did I mention that timing of verification is critical?

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    37/46

    Unapproved Pipe Bedding

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    38/46

    Construction Verification

    During Backfilling

    No backfilling in freezing weather or with frozen materials

    Warning tape installed approximately 36 above pipes

    C

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    39/46

    Commissioning Phases

    Part 4: Occupancy/Operations Phase

    S M i

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    40/46

    System Maintenance

    Borefield is essentially maintenance-free

    Verify glycol concentrationVerify system pressure

    Check fluid temperatures range of 30F to 100F isnormal

    Annual check of vault interior (if applicable)

    C li & H ti EWT Effi i

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    41/46

    Cooling & Heating EWT - Efficiency

    0

    1

    2

    3

    4

    5

    6

    20 30 40 50 60 70 80 90 100

    Entering Water Temp (F)

    COP_

    0

    5

    10

    15

    20

    25

    EER_

    EER & COP

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    42/46

    EER & COP

    EER = Energy Efficiency Ratio

    Cooling Mode Typical Range 18-27 EER

    COP = Coefficient of Performance

    Heating Mode

    Typical range 2.8-4.0 COP

    )(

    )/(

    WInputElectrical

    hrBtuOutputCoolingEER =

    )/(

    )/(

    hrBtuInputElectrical

    hrBtuOutputHeatingCOP =

    R

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    43/46

    Resources

    1. Kavanaugh, S.P., K. Rafferty. 1997. Ground-Source Heat Pumps:Design of Geothermal Systems for Commercial and InstitutionalBuildings, ASHRAE.

    2. 2007 ASHRAE Handbook-HVAC Applications, Chap. 32.

    3. 2008 ASHRAE Handbook-HVAC System & Equipment, Chap. 48.

    4. 1988. Closed-Loop Ground-Source Heat Pump Systems:Installation Guide, Oklahoma State University & International

    Ground Source Heat Pump Association.

    5. Wisconsin Department of Natural Resources. http://dnr.wi.gov

    6. U.S. Department of Energy, EERE Program.http://www.eere.energy.gov

    Q estions?

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    44/46

    Questions?

    AIA Quality Assurance

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    45/46

    AIA Quality Assurance

    Portland Energy Conservation, Inc is a registered provider with TheAmerican Institute of Architects Continuing Education Systems. Creditearned on completion of this program will be reported to CES Records

    for AIA members. Certificates of Completion for non-AIA members areavailable on request.

    This program is registered with the AIA/CES for continuingprofessional education. As such, it does not include content that maybe deemed or construed to be an approval or endorsement by the AIAof any material of construction or any method or manner of handling,using, distributing, or dealing in any material or product. Questions

    related to specific materials, methods, and services will be addressedat the conclusion of this presentation.

  • 7/23/2019 13 Ncbc-2011-Validating Energy Sources-Von Bank

    46/46

    THANK YOU

    Kenneth Von Bank, PE, CCP