25 25 1 25 25 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ...
1[1]
-
Upload
alexminaya -
Category
Documents
-
view
34 -
download
1
Transcript of 1[1]
SMED
Quick Changeover
Set-up and Changeover Reductions for Equipment, Tooling and Machines
Jack E. Abbruzzese P.Eng. ([email protected])
Process Engineer, DJ Galvanizing Corporation.
Windsor-Essex Chapter PEO Lean Concepts Subcommittee
The goal is to reduce and/or eliminate downtime
due to setups and changeovers
Machine
Running
Machine
RunningMachine Stopped
Internal setup External setupExternal setup
Total Set up
What is SMED? Driven by the need to change over a process to produce
a product in the most efficient manner. Reducing Setup (or Change Over) is the technique allowing the mixing of production/products without slowing output or creating higher costs associated with non-value adding activity (NVAA). Changeovers add no value and therefore should be minimized.
Quick Changeover, also known as SMED (Single-Minute Exchange of Die) is a proven technique originally developed and refined over a period of 19 years of applications at Toyota by Mr. Shigeo Shingo. Systematic use of this technique has enabled that company to achieve a phenomenal reduction in all product changeovers on their production lines. Currently 85% of all of their changeovers are <100 seconds (OTED or One-Touch Exchange of Die), another 14% are <10 minutes (SMED), and only 1% take 10 minutes or longer!
Single Minutes Exchange of Dies
History
Valuable References Related to
SMED System: Ohno, Taiichi (1988), The Toyota Production System:
Beyond Large-Scale Production, Productivity Press, Portland, Oregon.
Shingo, Shigeo (1985), A Revolution in Manufacturing: The SMED System, Productivity Press, Inc., Portland, Oregon.
Shingo, Shigeo (1989), A Study of the Toyota Production System from an Industrial Engineering Viewpoint, Productivity Press, Portland, Oregon.
Shingo, Shigeo (1996), Quick Changeover for Operators: The SMED System, Productivity Press, Inc., Portland, Oregon.
SMED and EOQ Single Minute Exchange of Dies
More precisely, single digit minute exchange of dies –changing dies in under 10 minutes.
Tied to Economic Order Quantity or LOT SIZE. Balance of inventory costs versus downtime for
changeover.
Economic Order Quantity is the lot size where:
Cost associated with
inventory
(interest, storage
costs)
Cost associated with
Changing over
(downtime, retooling
costs)
Development Optimization of Lot Size.
High lot size reduces overhead costs due to changeover but…
Increases inventory, interest and storage costs.
Automotive industry sought to optimize the lot size by looking at changeover times. Toyota had an additional motivator.
Toyota optimization Space limitations and high added cost to inventory for leasing
storage drove Toyota engineers to look at changeover in earnest to greatly reduce inventory costs.
By greatly improving changeover, lot sizes dropped dramatically, almost making EOQ irrelevant.
Also, reduced finished goods lot size meant stock levels of material goods also dropped, further reducing costs.
TPS Development Over several years, Toyota reworked factory fixtures and
vehicle components to make common parts, minimize assembly, standardize the steps, all contributing to reduced changeover. Where tooling could not be made common, changeover was minimized.
The stamping dies presented the biggest challenges due to the sheer size of equipment.
By analyzing the then current practices, Toyota systematically and scientifically reduced changeover from days and hours down to hours and ultimately minutes. The EOQ was reduced to LESS THAN 1 vehicle!
Lean Manufacturing Model
Goal of Lean
CONTINUOUS IMPROVEMENT
Guiding principles to continually make
improvement in Quality, pace, and cost.
Better, Faster, Cheaper.
This reduces time between customer order
and shipment of finished product by
eliminating waste in all areas. Customer
Order
Shipment of
Finished ProductContinuous
Improvement
How Quick Changeover Fits in
Reduce non-productive change-over time.
Every minute stopped counts as waste.
Coordinates with implementation of cellular
manufacturing and progress to continuous
modelling.
Once operations formed into cells, transitions and
changeovers must be reduced and personnel trained
in the optimal changeover practices.
What is Quick Changeover? SMED – Single Minute Exchange of Dies
Stop Machine and Empty the Dirt! (ABB example for general product transition improvement).
RETAD – Rapid Exchange of Tools and Dies
OTED – One Touch Exchange of Dies (< 100 seconds).
NOTED – NO Touch Exchange of Dies
Elimination of transition waste.
Changeover
can involve
fouling.
STOP
ResumeClean -
changeover
Why Quick Changeover
Promotion of One Piece Flow
Reduction of WIP levels
Reduction of downtime
Reduction of Inventory
Increase flexibility
Simplify the process – make more repeatable
Benefits
Reduced tangible and intangible costs related with setup time, inventory, space, materials, and customer delivery. Reduced defect rates by promoting quality from the first piece.
Adjustments for setup reduced.
Reduced inventory costs – smaller batches, lot sizes. JIT and stockless production possible through quick changeover.
Goods not lost due to deterioration.
Improved on-time delivery. Meet customer demands.
Increased production flexibility. Shorten time to customer, increase production. Simplified housekeeping.
Simpler system, better safety.
And MORE…
Quick Changeover Improvement
Technique - Process Establish the current changeover time.
Identify each task to accomplish changeover
Identify tasks that can be ELIMINATED
Determine EXTERNAL AND INTERNAL TASKS
ELIMINATE all unnecessary tasks
EXTERNALIZE all tasks identified as External This means these tasks are DONE while machine is running or in service.
STREAMLINE all internal tasks. This means optimization of the select tasks that MUST be done when the
machine is stopped.
ESTABLISH New Changeover Time.
It doesn’t end here… REPEAT the process on other applications.
Return to this application and optimize again.
See it, solve it, do it, done!
What’s next?
Lather, Rinse, Repeat.
Quick Changeover Improvement Technique
– External and Internal tasks EXTERNALIZE all tasks identified as External
This means these tasks are DONE while machine is running or in service.
Make sure you are not WAITING for these tasks to complete while machine is stopped!
Examples, Securing a crane for lifts, forklift availability, clearing floor-space, spare die at machine ready for insertion.
STREAMLINE all internal tasks. This means optimization of the select tasks that MUST be done when the
machine is stopped.
Some tasks or events CANNOT happen with the machine running. Examine each one for opportunity for improvement to shorten the down-time to a minimum.
MachineRunning
MachineRunning
Machine Stopped
Internal setup External setupExternal setup
Total Set up
Quick Changeover Improvement
Technique - Specifics Form Cells – Cellular manufacturing.
Combine dies.
Rotate dies.
Redesign dies for rapid changes, various techniques.
Gage blocking and precision gaging for dies, ensure setup repeatable.
Sequence the change to utilize associated equipment efficiently (cranes etc)
Convert to continuous process model Welders, rollers, conveyors, logical stitching of components so pieces
flow through from one operation to another.
Shuttle and rail exchange systems
Automatic scheduling and preset control
Application
Racing Teams – 10 second pit stop!
Stamping dies – classic example.
Deposition systems, rapid clean and
changeover to various deposit media.
Rolling, forming, cutting equipment.
Examples – Racing Team
NEWS HEADLINE:Think NASCAR pit crew members aren't athletes? Think again. "It's a far cry from how it was on pit road just 15 years ago," says Ray Evernham.
Quick Changeover Enablers:
Single lug wheels.
Precision fuel additions.
Sequenced tire changes.
Defined roles.
And now….
Athletic PIT CREW!
Examples – Shuttle coater - DJG
Coater
Shuttle provision for
online offline
movement and
coater A, coater B
(future) placement
Examples – Trimmers, Slitters
Tooling – close to
equipment!
Trimmer, Slitter
exchange rail and
transfer car.
Taylor Steel, tri-axle
quick change slitter
(left).
DJG trimmer, slitter
exchange rail and
transfer car. (right)
Examples – Temper Mill (SPM)
Steel sheet runs through
line continuously. Rail
and cart system facilitate
QUICK CHANGE of work
rolls with minimal product
loss (<200m steel).
Examples – CGL Oiler
Oiler replaced with latest technology, Dec 2009 improved control – Saves MONEY!
Purge (oil changeover) time reduced from 60 s to 30 s. New system purges faster and with less cross-contamination, improving defects and reducing rework!
Examples – CGL Furnace
Anneal code models and setpoint control via weld point tracking allow for transitions of furnace temperature as the product is running, maintaining quality and eliminating changeover times! Scheduling
Anneal code smoothing
Speed control
Furnace controls