1(1) What is the composition of power sources for electric ...operating licenses (“IO Non-BBM”)....

47
Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士 が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図 したものではなく、また、2018 12 月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。 1 ©2019 Atsumi & Sakai/ Makarim & Taira S. アラブ首長国連邦UAEA Structure and Trends in the Electric Power Industry 1(1) What is the composition of power sources for electric power generation in your country at the present? By early 2018, Indonesia had roughly about 60.7 Gigawatt (“GW”) of installed power plant capacity, produced by PT Perusahaan Listrik Negara (Persero) (“PLN 1 ”) - Independent Power Producer (“IPP”) power plants, Private Power Utilities (“PPU”) and power plants operating under non-fossil fuel operating licenses (“IO Non-BBM”). These power plants generated 254.5 Terawatt hours (“TWh”) of electric power in 2017. The 60.7 GW total installed capacity is divided among: (1) 41.7 GW (69%) from PLN and its subsidiaries; (2) 14.2 GW (23%) from the IPPs; (3) 2.4 GW (4%) from the PPUs; and (4) the remaining 2.4 GW (4%) from IO Non-BBM holders. 2 Nation-wide, the power generation fuel mix in Indonesia is currently comprised of coal (57.22%), gas (24.82%), oil (5.81%) and renewables (12.15 %) as shown in the Table below. 3 Indonesia’s Electric Power Fuel Mix 2012 2013 2014 2015 2016 2017 Oil 14.97% 12.54% 11.81% 8.58% 6.96% 5.81% Gas 23.41% 23.56% 24.07% 24.89% 25.88% 24.82% Coal 50.27% 51.58% 52.87% 56.06% 54.70% 57.22% Hydro 6.39% 7.73% 6.70% 5.93% 7.88% 7.06% Geothermal & Other New and Renewable Energy sources (“NRE”) 4.96% 4.58% 4.55% 4.54% 4.58% 5.09% As can be seen above, thermal energy (ie from coal, gas, diesel etc.) remains the largest source of power in Indonesia. About 85% of electric power consumed in Indonesia is generated by thermal power plants, and 58% of the nation’s total generation comes from coal-fired power plants. Coal continues to be the 1 PLN is the state-owned electric power company. PLN holds the exclusive right to distribute all generated electric power to end-users (customer). 2 The Directorate General of Electric Power, Ministry of Energy and Mineral Resources, 2017 Electric Power Statistics, 31 st Edition, 2018 Financial Year, p. 1. 3 The Directorate General of Electric Power, Ministry of Energy and Mineral Resources, 2017 Performance Report (Laporan Kinerja Tahun 2017), p. 36. インドネシア共和国 / Indonesia

Transcript of 1(1) What is the composition of power sources for electric ...operating licenses (“IO Non-BBM”)....

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    1 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    アラブ首長国連邦(UAE)

    ◇A Structure and Trends in the Electric Power Industry

    1(1) What is the composition of power sources for electric power generation in your

    country at the present?

    By early 2018, Indonesia had roughly about 60.7 Gigawatt (“GW”) of installed power plant capacity,

    produced by PT Perusahaan Listrik Negara (Persero) (“PLN1”) - Independent Power Producer (“IPP”)

    power plants, Private Power Utilities (“PPU”) and power plants operating under non-fossil fuel

    operating licenses (“IO Non-BBM”). These power plants generated 254.5 Terawatt hours (“TWh”) of

    electric power in 2017.

    The 60.7 GW total installed capacity is divided among: (1) 41.7 GW (69%) from PLN and its

    subsidiaries; (2) 14.2 GW (23%) from the IPPs; (3) 2.4 GW (4%) from the PPUs; and (4) the remaining

    2.4 GW (4%) from IO Non-BBM holders.2

    Nation-wide, the power generation fuel mix in Indonesia is currently comprised of coal (57.22%), gas

    (24.82%), oil (5.81%) and renewables (12.15 %) as shown in the Table below.3

    Indonesia’s Electric Power Fuel Mix

    2012 2013 2014 2015 2016 2017

    Oil 14.97% 12.54% 11.81% 8.58% 6.96% 5.81%

    Gas 23.41% 23.56% 24.07% 24.89% 25.88% 24.82%

    Coal 50.27% 51.58% 52.87% 56.06% 54.70% 57.22%

    Hydro 6.39% 7.73% 6.70% 5.93% 7.88% 7.06% Geothermal & Other New and Renewable Energy sources (“NRE”)

    4.96% 4.58% 4.55% 4.54% 4.58% 5.09%

    As can be seen above, thermal energy (ie from coal, gas, diesel etc.) remains the largest source of power

    in Indonesia. About 85% of electric power consumed in Indonesia is generated by thermal power plants,

    and 58% of the nation’s total generation comes from coal-fired power plants. Coal continues to be the

    1 PLN is the state-owned electric power company. PLN holds the exclusive right to distribute all generated electric power

    to end-users (customer). 2 The Directorate General of Electric Power, Ministry of Energy and Mineral Resources, 2017 Electric Power Statistics,

    31st Edition, 2018 Financial Year, p. 1. 3 The Directorate General of Electric Power, Ministry of Energy and Mineral Resources, 2017 Performance Report

    (Laporan Kinerja Tahun 2017), p. 36.

    インドネシア共和国 / Indonesia

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    2 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    dominant fuel for electric power because of its low cost and availability. Coal mine-mouth power plants

    also remain integral to the Indonesian Government’s plans since Indonesia’s large low-rank coal

    deposits are often located in remote areas with minimal infrastructure, including hauling roads and

    jetties, making transportation of the coal uneconomical.

    The use of more eco-friendly (lower carbon) technology, such as supercritical and ultra-supercritical

    boilers is a key priority for PLN and the Government in the development of large-scale coal-fired power

    plants, particularly on the densely populated island of Java.

    Plans to diversify energy sources for electric power have been announced, but progress was slow. The

    use of other types of technology, such as integrated gasification combined cycles or carbon capture and

    storage, are not included in the 2018 Electric Power Supply Business Plan (Rencana Usaha Penyediaan

    Tenaga Listrik – “RUPTL”) as these are not commercially viable yet. The high investment cost and risk

    in developing renewable energy sources such as geothermal, wind, solar and other untapped potential

    energy sources are still the primary issues for the nation to face in making them commercially viable.

    However, the Indonesian Government actively supports the use of sustainable clean/green energy in its

    electric power development road map.

    While it seems that the Indonesian Government has yet taken the decision to use nuclear as one of its

    energy sources for electric power generation, however Indonesia is currently assessing for a potential

    first Nuclear Power Plant (“NPP”) development program through feasibility studies. The Indonesian

    Government is also considering an NPP project through an open bid mechanism, where presumably,

    the contract will use a turnkey approach and the nuclear fuel cycle will use an open cycle as an option.4

    1(2) At present, what is the composition of renewable energy source in your country?

    Also, please provide us with the government-established target numbers for

    renewable energy and composition of methods of electric power generation.

    Currently, hydropower and geothermal energy are leading the renewable source energy generation in

    Indonesia – with hydroelectric power representing 9% of the 2017 total energy mix, and geothermal and

    other alternative energy representing 5% of the 2017 total energy mix.5 Other sources of renewable

    energy in Indonesia are including solar power, wind power and bioenergy. Further, the Indonesian

    Government is also projecting tidal power opportunities.6

    4 The International Atomic Energy Agency, “Country Nuclear Power Profiles 2018 Edition – Indonesia,” (updated 2018),

    https://www-pub.iaea.org/MTCD/Publications/PDF/cnpp2018/countryprofiles/Indonesia/Indonesia.htm, accessed 6 December 2018.

    5 Climate Bonds Initiative, Green Infrastructure Investment Opportunities – Indonesia, (May 2018), p. 17. 6 Price Waterhouse Coopers (“PwC”), Power in Indonesia 2018 – Investment and Taxation Guide, 6th Edition

    (November 2018), p. 108.

    https://www-pub.iaea.org/MTCD/Publications/PDF/cnpp2018/countryprofiles/Indonesia/Indonesia.htm

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    3 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    Renewable Energy Resources in Indonesia7

    Source Potential Power Generation

    Hydropower 75 GW

    Geothermal 29 GW

    Biomass 33 GW

    Solar Photovoltaic (PV) 208 GWp (4.80 kWh/m2/day)

    Wind Power 61 (3 – 6 m/s)

    Ocean 18 GW

    In 2014, Joko Widodo (Indonesia’s incumbent President) launched an aggressive program to build

    power plants to generate 35 GW during his five-year term that will end in October 2019. From PLN’s

    presentation, by May 2018, the 35 GW power development program implementation progress was the

    following:8

    By 2019, the actions in implementing the 35 GW program has been relatively slow. Even so, it is

    announced that the Indonesian Government has postponed the completion target for the 35 GW

    program to 2024 – 2025, also further reducing the new capacity target to be built for only 20 GW at the

    end of 2019.

    7 Directorate General of New and Renewable Energy and Energy Conservation, MEMR, 2016 EBTKE Statistics (Buku

    Statistik EBTKE 2016). 8 PLN presentation in the IPP Summit 17 – 18 July 2018.

    [VALUE] (1,007 MW) [VALUE] (2,130

    MW)

    [VALUE] (16,687 MW)

    [VALUE] (16,687 MW)

    6% (2,114 MW)

    Progress in the 35 GW program as at May 2018

    Planning Procurement

    Contracted (PPA) not yet under construction Contracted (PPA) under construction

    Reached Commercial Operation Date

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    4 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    Additionally, it is essential for all the investors in Indonesia’s electric power sector to understand that

    the electric power planning in Indonesia is primarily based on a RUPTL. RUPTL is a document which

    projects the 10 (ten) years electric power generation plan for each of the PLN’s operating areas (or

    Wilayah Usaha). RUPTL document will be reviewed annually. RUPTL is sourced from the General

    Electric Power Plan (Rencana Umum Ketenagalistrikan), comprising the National Electric General

    Power Plan (Rencana Umum Ketenagalistrikan Nasional – “RUKN”) as well as the Regional General

    Electric Power Plan (Rencana Umum Ketenagalistrikan Daerah – “RUKD”). The content of RUPTL

    includes, but not limited to, the predictions of electric power demands, future expansions, electric

    power production, and fuel mix. More importantly, RUPTL maps out the strategic infrastructure

    projects to be built by both PLN and IPP investors, and the procurement method for the IPPs. Therefore,

    RUPTL should be carefully considered when investing in the sector.9

    Published in early 2018, the 2018 – 2027 RUPTL sets a target for Indonesia to achieve a full percentage

    (100%) of electrification ratio by 2024. Unfortunately, once again, the target of 78 GW new power

    generation capacity by 2026 has been reduced to 56 GW by 2027. Therefore, PLN and IPP investors at

    this time are only expected to construct 56 GW of generating capacity by 2027, a significant reduction

    compared to the proposed 78 GW in the 2017 RUPTL.

    A decrease in the anticipated national average energy demand growth rate constitutes as one of the

    backgrounds for PLN to reduce those numbers set for the capacity generation. The average energy

    demand growth rate drops from 8.3% in the 2017 RUPTL to 6.9% in the 2018 RUPTL, causing a

    decrease in the estimated total demand for electric power in 2026 from 483 TWh to 407 TWh,

    accounting for a 15.7% decrease. The 21.9 GW reduction in plant capacity gas-fired power plants

    (including gas machine and combined-cycle power plants) saw the largest cut of 10.1 GW from 21.9 GW.

    This also represents a decrease in predicted gas consumption for the power sector from over 3,300

    billion British thermal units per day (“BBTUD”) in 2026 to around 2,000 BBTUD in 2027.10

    As projected in the Table below, the 2018 RUPTL also aims for the 23% energy mix from renewables

    power generation in 2025 as targeted by the 35 GW program. However, knowing that the power

    generation from renewables has been particularly low, achieving the 23% target by 2025 should means

    that the renewable power generation in 2018 RUPTL must be at least amounted to 25% of the fuel mix

    by 2025.

    Further, since the draft 2015 – 2034 RUKN sets a fuel mix of roughly 50% from coal, 24% from gas,

    25% from renewables and 1% from diesel fuel, this fact indicates a shift of focus back to coal powered

    generation.

    9 PwC, Alternating Currents: Indonesian Power Industry Survey 2018, 2nd Edition, (July 2018), p. 12. 10 PwC, Power in Indonesia 2018, p. 75.

  • Notice: “This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice.” 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    5 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    Electric Power fuel sharing targets in the 2018 – 2027 RUPTL (in GWh and percentage)11

    Fuel Type 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

    Hydropower 18,944

    (6.92%)

    17,594

    (5.98%)

    18,051

    (5.70%)

    19,784

    (5.82%)

    20,028

    (5.54%)

    23,749

    (6.17%)

    27,967

    (6.82%)

    43,135

    (9.91%)

    44,385

    (9.54%)

    46,700

    (9.30%)

    Geothermal 14,700

    (5.37%)

    16,532

    (5.62%)

    17,741

    (5.52%)

    19,299

    (5.67%)

    22,382

    (6.19%)

    23,666

    (6.15%)

    26,179

    (6.39%)

    50,782

    (11.66%)

    50,006

    (10.74%)

    49,201

    (9.80%)

    Other Renewables 419

    (0.15%)

    2,494

    (0.85%)

    2,906

    (0.91%)

    3,180

    (0.94%)

    3,204

    (0.89%)

    3,260

    (0.85%)

    3,545

    (0.86%)

    6,319

    (1.45%)

    6,591

    (1.42%)

    6,631

    (1.32%)

    Gas 57,049

    (20.84%)

    68,137

    (23.15%)

    76,069

    (24.02%)

    73,548

    (21.62%)

    80,047

    (22.12%)

    83,660

    (21.75%)

    85,745

    (20.92%)

    96,548

    (22.17%)

    98,120

    (21.08%)

    103,476

    (20.62%)

    Fossil Fuels 11,634

    (4.25%)

    11,429

    (3.88%)

    7,053

    (2.23%)

    3,639

    (1.07%)

    1,679

    (0.46%)

    1,713

    (0.45%)

    1,834

    (0.45%)

    1,826

    (0.42%)

    1,893

    (0.41%)

    2,007

    (0.40%)

    Coal 169,632

    (61.95%)

    176,517

    (59.99%)

    194,250

    (61.33%)

    220,081

    (64.70%)

    234,455

    (64.80%)

    248,560

    (64.63%)

    264,618

    (64.56%)

    236,841

    (54.39%)

    264,429

    (56.81%)

    293,902

    (58.56%)

    Import 1,433

    (0.52%)

    1,550

    (0.53%)

    907

    (0.29%)

    612

    (0.18%)

    -

    (0.00%)

    -

    (0.00%)

    -

    (0.00%)

    -

    (0.00%)

    -

    (0.00%)

    -

    (0.00%)

    Total 273,811

    (100%)

    294,253

    (100%)

    316,707

    (100%)

    340,142

    (100%)

    361,796

    (100%)

    384,609

    (100%)

    409,887

    (100%)

    435,452

    (100%)

    465,423

    (100%)

    501,918

    (100%)

    11 2018 – 2027 PLN’s Electric Power Supply Business Plan (Rencana Usaha Penyediaan Tenaga Listrik PLN Tahun 2018 – 2027) (“2018 RUPTL”), attached to MEMR

    Decree Number 1567/K/21/MEM/2018, p. V-63.

  • Notice: “This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice.” 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    6 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    Within the next 2 (two) years, according to the 2018 RUPTL, around 1,300 Megawatts (“MW”) of

    renewable power projects are presumed to be in progress12. Therefore, investment opportunities in

    Indonesia in renewable energy power generation facilities for 2018 – 2020 are considerable.

    2 Please explain the structure of the market for electricity in your country.

    The common structure of the current Indonesian electric power supply industry is shown below.13

    Under Law Number 30 of 2009 on Electric Power (“Electric Power Law”), PLN, a state-owned

    enterprise, is the only authority in the country having the priority to provide electric power across the

    area in the Republic of Indonesia – factually as the sole owner of transmission and distributions

    facilities/assets in the country. In carrying out its duty to fulfil the national demand for electric power,

    PLN usually produces electric power from its own power plants, including from its subsidiaries. PLN

    also serves as the single off taker, purchasing electric power from IPPs. Besides PLN and IPPs, other

    power producers are relatively captive power sources, including industries that produce power for their

    own uses, industrial estate companies, and some smaller companies, including cooperatives which

    directly sell their electric power to the consumers.

    For the most part, PLN builds and owns electric power infrastructure in the country where almost all

    types of power plants are owned by PLN, eg coal-fired and oil-fired steam power plants, gas turbines

    and geothermal, hydroelectric, as well as diesel power plants. PLN’s subsidiaries (ie PT Indonesia Power

    and PT Pembangkitan Jawa Bali), manage most of those generation facilities.14

    However, in recent years, about half of the new capacity came from the private sector or IPPs under

    particular PPAs, which have increased in number since the 35 GW program was introduced. The

    12 PwC, Alternating Currents: Indonesian Power, p. 11. 13 International Atomic Energy Agency, “Country Nuclear Power Profiles 2018: Current electric power market,” (Fig.3). 14 The International Atomic Energy Agency, “Country Nuclear Power Profiles 2018.”

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    7 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    presence of IPPs as investors is essential to achieve the national energy target since it is almost

    impossible for PLN to take on all the tasks alone. Therefore, it is necessary to create a proper investment

    climate to increase the development of NRE in Indonesia.

    In contrast, the Renewable Energy Country Attractiveness Index (RECAI) report from EY in 2017

    reveals that Indonesia ranked 38th in the top 40 most attractive countries in 2015 and 2016 and even no

    longer categorized in the top 40 by 2017. Furthermore, although PLN signed 70 contracts with IPPs in

    2017, barely 17 projects started the construction phase in 2018, while approximately 46 projects are now

    considered failed and should be re-evaluated, or even halted by the government.

    The failure of the projects was presumably due to financial issues, for example, non-approval loan and

    the unattractive Internal Rate of Return (IRR). Many also convinced that the proposed Feed-in Tariff by

    the government was much lower than the Local Average Generation Cost (Biaya Penyediaan Pokok –

    “BPP”), resulting some projects in economically difficult positions, and also affected the

    implementation for the Build, Own, Operate, Transfer (“BOOT”) scheme in most NRE sectors, except

    for the waste-to-energy sector. Given this, it is reasonable for the government to prioritize affordability

    over high cost green energy.15

    In spite of the above, according to the information currently available in the market, the government is

    currently planning to amend the Negative List of Investment (Presidential Regulation (“PR”) Number

    44 of 2016 on the List of Business Fields which are Closed to Investment and Business Fields which are

    Conditionally Open to Investment – “Negative List of Investment”), and there has been some

    suggestion that power generation above 10 MW will no longer be subject to foreign shareholding

    restrictions (currently it is limited to 95%, except for PPP which is 100% but only during the term of the

    concession). This can be seen as an important step by the government in reforming the electric power

    market and making it even more ‘investor-friendly’, placing emphasis on the partial liberalization of the

    energy market, decentralized energy planning and increasing transparency.

    Furthermore, we understand that in recent practice in dealing with PLN, PLN will require that it

    becomes the majority share ownership and is involved in the management of the project company. This

    scheme is usually implemented by PLN through its subsidiaries PT Indonesia Power, PT Pembangkitan

    Jawa-Bali and PT Pembangkitan Jawa-Bali Investasi, in which PLN will directly assign its subsidiary

    through a letter of assignment. Recent development in the expansion of coal-fired, renewables and mine

    mouth power plants show that PLN and its subsidiaries will require the “piggyback” or “numpang

    gendong” scheme (the term is informally used by PLN). Under this scheme, PLN through its

    15 The Purnomo Yusgiantoro Center, “Brief Notes for Indonesia’s Feed-in Tariff (FIT) Implementation,” (27 September 2018), http://www.purnomoyusgiantorocenter.org/2018/09/27/brief-notes-for-indonesias-feed-in-tariff-fit-implementation/, accessed 6 December 2018.

    http://www.purnomoyusgiantorocenter.org/2018/09/27/brief-notes-for-indonesias-feed-in-tariff-fit-implementation/

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    8 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    subsidiaries will require at least 51% of the shares in the project company with the actual capital

    investment of only 10% of the shares. The remaining capital must be borne by the other private

    sponsors. It is not entirely clear on how this mechanism will work and at the moment, we understand

    most of the investors are still on the ‘wait and see’ situation for more certainty in the investment climate

    especially in the power sectors. From our experience, the new green fields IPP projects are slowing

    down since the implementation of this mechanism plus the recent news and information indicating that

    there has been an overcapacity of electric power in Java Island. Nevertheless, the demands from the

    investors in the electric power sectors are still very high and the trends in the Indonesian electric power

    sectors now are that the investors are looking for the acquisition of the existing power plants rather than

    commencing a new green fields IPP with PLN.

    3 When an independent power producer (IPP) sells electricity, do they conclude a

    power purchase agreement (PPA)? Who are the typical purchasers? Is it possible

    to negotiate the terms of the PPA?

    In brief, an IPP company (holding a specific license to provide electric power for public use (ie Izin

    Usaha Penyediaan Tenaga Listrik - “IUPTL”)) must sign a PPA with PLN to kickstart the project and it

    is the cornerstone operational agreement for an IPP. Commonly, the purchaser is PLN, as the sole

    off-taker of the electric power generated by the IPP company. However, the IPP company can also sell

    the electric power it generates to another integrated IUPTL (IUPTL terintegrasi) holder, eg an IPP

    company in industrial estate. The Electric Power Law and Government Regulation (“GR”) Number 14 of

    2012 on The Electric Power Supply Business as amended by GR Number 23 of 2014 open up private

    participation such as through IPPs in the supply of power for public use and for transmission and

    distribution. However, this is yet limited to the power generation business field. For distribution, PLN

    still retains the 'first priority' to supply electric power for public use.

    In practice, PLN provides a template PPA which ‘evolves’ from project to project. PLN ‘updates’ its PPA

    template based on past projects with the terms and conditions that PLN has agreed to. Therefore, an

    old-day PPA is very different from a recent PPA, while recent PPAs may be slightly different from each

    other, as PLN either includes provisions which benefit PLN and remove provisions which do not. The

    PLN procurement team provides the initial draft PPA in the Request For Proposals (RFP). However, the

    template is not a standard non-negotiable document. On the contrary, although it is common in the

    RFP that PLN only allows minor deviation to the PPA template, the parties need to negotiate the draft

    PPA. Without a doubt, PPA is the cornerstone and long-term agreement (the maximum term is 30

    years) between the IPP company and PLN and therefore, ideally, every aspect of it must be negotiated

    with PLN in all aspects, ie all technical, financial, commercial and legal clauses. Some of PLN’s new

    provisions for PPAs are the Project Cost Account (or Project Development Cost Account – a specific

    account in which the IPP must show PLN that it has sufficient financial resources to be able to develop

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    9 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    the project) and an increase in the value of Bank Guarantees from previous PPAs. This may be PLN’s

    way of mitigating the risk of development failure due to an IPP’s lack of financial resources from the

    beginning.

    Furthermore, in 2017, the Indonesian Government issued Minister of Energy and Mineral Resources

    (“MEMR”) Regulation Number 10 of 2017 on the Principles of Power Purchase Agreements, as

    amended first by MEMR Regulation Number 49 of 2017 and lastly by MEMR Regulation Number 10 of

    2018 (“MEMR Reg PPA”) establishing the legal minimum standard provisions of the PPA. MEMR Reg

    PPA sets out the principles of PPAs between PLN as the purchaser and IPPs as the sellers in the electric

    power system. The regulation aims to provide legal certainty in the power supply business by revising

    provisions of PPAs on risk allocation and force majeure. IPPs and PLN must both cover certain risks.

    However, MEMR Reg PPA has now removed government force majeure from the types of risk that both

    IPPs and PLN must cover. In practice, the allocation of the risk of government force majeure may

    significantly affect the bankability of IPP projects. Under previous PPAs, government force majeure was

    one of the types of risk PLN bore. It will be interesting to see how this provision is implemented under

    the new model PPAs, ie whether PLN will accept the risk of government force majeure or not. If not,

    certain assurances will have to be created to comfort the providers of loans to project companies.

    In addition, government force majeure events and force majeure due to changes to the laws no longer

    relieve either PLN or IPPs from their obligations under their PPAs, as both are removed from the

    MEMR Reg PPA. Despite this, the PPA is still negotiable, as the MEMR Reg PPA expressly states that

    any provisions which are not covered by the MEMR Reg PPA will be determined through

    business-to-business negotiations between PLN and the IPP company.

    The MEMR Reg PPA covers all types of power plant, including coal-fired, gas-fired, oil-fired,

    geothermal, hydro, and biomass power plants. While, PPAs with intermittently new and renewable

    energy power plants, mini-hydro power plants (below 10MW), biogas power plants, and municipal

    waste-to-energy power plants will be covered by specific MEMR Regulations – which are yet to be

    issued.

    Below is a summary of some provisions that a PPA must include according to MEMR Reg PPA. These

    are the minimum requirements and do not eliminate the transactional nature of a PPA:

    No. Provision Detailed Explanation

    1. The term of the PPA The term of a PPA may be up to 30 (thirty) years as of the

    Commercial Operation Date (“COD”), depending on the type of

    power plant. The form of business cooperation is typically

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    10 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    No. Provision Detailed Explanation

    Build-Own-Operate-Transfer (BOOT).

    2. IPP company’s rights

    and obligations (as the

    seller)

    1. The IPP’s rights are:

    • to receive payment for sales of electric power;

    • to obtain incentives for any acceleration of the COD, if

    requested by PLN; and

    • to receive the deemed dispatch, if PLN’s network is

    disrupted for reasons other than force majeure.

    2. The IPP’s obligations are:

    • to design, finance, build, own, operate and transfer the

    ownership of the power plant;

    • to provide security under a performance bond (jaminan

    pelaksanaan) and a performance guarantee (jaminan

    kinerja);

    • to pay a fine for any failure to achieve the guaranteed

    performance (jaminan kinerja) as well as a fine for a delay

    in the COD;

    • to submit a monthly power supply plan;

    • to supply electric power to PLN according to the electric

    power supply plan and maintain the supply during the

    term of the PPA;

    • to obtain all the required licenses and approvals including

    with regard to the local content requirements;

    • to pay fines in accordance with the applicable provisions of

    the PPA.

    3. PLN’s rights and

    obligations (as the

    purchaser)

    1. PLN’s rights are:

    • to receive a reliable and sustainable supply of electric

    power from the power plant; and

    • to obtain all approvals required for the PPA.

    2. PLN’s obligations are:

    • to provide IPPs incentives to accelerate the COD, if

    requested by PLN;

    • to purchase the electric power supplied by the IPPs in

    accordance with the PPAs which have been entered into for

    a certain term;

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    11 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    No. Provision Detailed Explanation

    • to pay for deemed dispatches, if the PLN network is

    disrupted for reasons other than force majeure; and

    • to maintain and preserve the reliability of the grid

    receiving the electric power.

    4. Risk Allocation

    PLN will bear the following risks:

    • the required power/load;

    • limited transmission capacity; and

    • force majeure.

    The IPP will bear the following risks:

    • land acquisition related matters;

    • licenses, including the environmental license;

    • fuel supplies;

    • construction schedule accuracy;

    • power plant performance; and

    • force majeure.

    5. Project Implementation

    Guarantee

    The IPP must provide performance security for completing the

    following stages and activities:

    Stage 1: reaching the financing date;

    Stage 2: reaching the commissioning date; and

    Stage 3: reaching the COD.

    6. Fuel Supply

    Fuel for electric power plants can be supplied by either the IPP or

    by PLN. If the fuel is supplied by PLN, the following conditions

    apply:

    1. the IPP must guarantee that the specific fuel consumption

    (SFC) or specific heat rate (SHR) will be in accordance with

    the PPA;

    2. the IPP must always monitor the relevant coal procurement

    costs under a contract aimed at achieving effective and

    efficient procurement costs; and

    3. gas suppliers must ensure the continuity of their gas supplies,

    otherwise they will be fined under the deliver-or-pay

    arrangement.

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    12 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    No. Provision Detailed Explanation

    7. Transaction

    All payments in power purchase transactions must be in

    Indonesian Rupiah, unless a Bank Indonesia exemption is

    obtained.

    - If the seller fails to deliver power to PLN, the seller must pay

    a fine to PLN for a certain period.

    - If PLN fails to take the power, PLN must pay a fine to the

    seller for a certain period.

    - The fine is determined according to the investment

    component.

    8. Commissioning and

    COD

    • The commissioning provisions refer to the regulation on the

    procedures for the accreditation and certification of electric

    power related matters (MEMR Regulation Number 38 of

    2018).

    • Power plant operations must be undertaken according to the

    relevant grid codes for the local system, or, in the absence of

    these codes, with any grid code determined by the Director

    General of Electric Power or other existing grid codes.

    • IPPs are entitled to incentives related to PLN requests to

    accelerate the COD.

    • IPPs are subject to liquidated-damages in an amount equal to

    the electric power generating cost incurred by PLN as a result

    of any delay in reaching the COD.

    9. Operating System

    (Dispatch) Control

    To maintain the reliability of the power system so it is according

    to the grid code, a dispatcher must plan and implement an

    operating system (dispatch), taking into account its cost and

    conformity to the PPA. Monthly dispatch reports must be

    delivered to the Director General recording among other things,

    any breach of the grid code by PLN or by the IPP.

    10. Fines for a Power

    Plant’s lack of

    Performance

    The actual power-plant performance value is measured taking

    into account any Availability Factor (“AF”) or Capacity Factor

    (“CF”), as well as the relevant heat rate and/or other technical

    provisions of the PPA. If this value does not meet the target

    agreed to under the PPA, the IPP may have to pay a certain type of

    fine, such as a liquidated-damages fine, an AF or CF fine, an

    outage-factor fine, a heat-rate fine etc.

    11. PPA Termination A PPA can be terminated for the following reasons:

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    13 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    No. Provision Detailed Explanation

    1. the term of the PPA has expired;

    2. unilateral termination before the term of the PPA expires (eg

    due to a license not being issued, no funding being available,

    major unexpected cost overruns, etc.);

    3. insufficient funding;

    4. bankruptcy; or

    5. force majeure.

    12. Transfer of Rights

    Ownership of an IPP may not be transferred to any other party

    before entering the COD stage, unless the transfer is to an

    affiliate, 90% of the shares of which are owned by the party

    intending to transfer its shares.

    A transfer of ownership upon reaching COD requires written

    approval from the purchaser. The transfer must be reported to the

    MEMR through the Director General.

    13. Price Adjustment

    The price for the electric power sold may only be adjusted if the

    following are adjusted:

    1. the regulations on the sale price of electric power;

    2. the tax regulations;

    3. the environmental protection regulations; and/or

    4. the regulations on the cost of energy.

    14. Dispute Settlement

    Any dispute which arises between PLN and an IPP must be settled

    according to the following procedure:

    1. amicable settlement; failing which,

    2. settlement by appointed experts; and finally,

    3. arbitration through the Indonesian National Board of

    Arbitration (BANI), The United Nations Commission on

    International Trade Law (UNCITRAL) or through another

    arbitration institution.

    15. Force Majeure

    PLN and the IPP are released from their respective obligations if a

    Natural Force Majeure event:

    • causes a COD delay: a time extension for as long as the

    natural disaster continues (including time for necessary

    repairs to the project); or

    • causes an inability to distribute electric power: a time

    extension for as long as the natural disaster continues

    (including time for necessary repairs to the project).

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    14 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    4 Does your country have a Feed in Tariff system? How are tariffs determined? Is a

    bidding system used?

    The rates of the Indonesian Feed-in Tariffs were set using PLN’s electric power basic cost (ie BPP), or in

    other words, the marginal production cost that PLN would incur to produce electric power in the region

    of the renewable energy project.16 This tariff sets from BPP does not include the transmission cost,

    which is determined based on business-to-business negotiations between PLN and the relevant

    developer.17

    In 2017, MEMR applied the latest Feed-in Tariff for all new renewable energy for electric power

    generation under MEMR Regulation Number 50 of 2017 on the Use of Renewable Energy Supplying

    Electric Power as amended by MEMR Regulation Number 53 of 2018 (“MEMR Reg. 50/2017”),

    which include solar PV, wind, hydro, biomass, biogas, waste-to-energy, geothermal18, ocean energy and,

    recently, biofuel.19 This regulation attempted to address the cost to PLN by capping renewable power

    purchase prices at 85% of the BPP. The BPP does not differentiate between areas in a region where

    there is a main grid despite some areas in that region not being connected. The main grid rate in this

    case is the one applied.20

    For waste-to-energy projects, if the regional BPP of a pertinent local grid is higher than the national

    BPP, the tariff will be capped at 100% of the regional BPP. In particular, for projects in Sumatra, Java,

    Bali and other locations in which the local BPP is equivalent to or lower than the national BPP, the tariff

    will be determined based on negotiations between the developer and PLN. Regardless of this, in practice,

    PLN remains capping the tariff in locations where its regional BPP is already lower than or equivalent to

    the national BPP. This move is taken to avoid the BPP to rise in the next year.

    In general, there are 3 (three) types of procurement procedure of electric power which PLN follows, ie:

    (i) open tender; (ii) direct appointment; and (iii) direct selection. 16 Climate & Development Knowledge Network, “Policy Brief – Indonesian Feed-in Tariffs: challenges & options,”

    https://cdkn.org/wp-content/uploads/2015/04/ECN-Policy-Brief-Indonesian-Feed-in-tariff-140304.pdf, accessed 6 December 2018.

    17 Global Business Guide – Indonesia, “Legal Updates: Expanded Coverage and New Feed-in Tariff for Indonesia’s Waste

    to Energy Projects,” (7 May 2018), http://www.gbgindonesia.com/en/main/legal_updates/expanded_coverage_and_new_feed_in_tariff_for_indonesia_s_waste_to_energy_projects.php, accessed on 6 December 2018.

    18 Specifically, the Feed-in Tariff for geothermal energy also remains subject to MEMR Regulation Number 17 of 2014 on

    the Purchase of Electric Power from Geothermal Power Plant and Geothermal Steam for Geothermal Power Plant by PLN.

    19 The Purnomo Yusgiantoro Center, “Brief Notes for Indonesia’s Feed-in Tariff (FIT) Implementation.” 20 The International Institute for Sustainable Development, Missing the 23 Per Cent Target: Roadblocks to the

    development of renewable energy in Indonesia – GSI Report, (February 2018), p. 7.

    https://cdkn.org/wp-content/uploads/2015/04/ECN-Policy-Brief-Indonesian-Feed-in-tariff-140304.pdfhttp://www.gbgindonesia.com/en/main/legal_updates/expanded_coverage_and_new_feed_in_tariff_for_indonesia_s_waste_to_energy_projects.phphttp://www.gbgindonesia.com/en/main/legal_updates/expanded_coverage_and_new_feed_in_tariff_for_indonesia_s_waste_to_energy_projects.php

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    15 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    For an open tender, the procedure follows provisions under MEMR Regulation No. 001 of 2006 on the

    Procedure for Selling Electric Power and/or Leasing of Networks for Electric Power Supply Business

    Activities for the Public Interest, as amended by MEMR Regulation No. 004 of 2007. PLN must publish

    an announcement of a public tender for the purchase of electric power by PLN. Afterwards, PLN must

    establish a tender committee to handle the pre-qualification and bidding process. The period for

    finalizing an open tender is approximately 316 days.

    Further, PLN may purchase electric power through a direct appointment under the prevailing laws and

    regulations, depending on which type of power plant is being procured, ie GR Number 7 of 2017 on the

    Indirect Utilization of Geothermal (Energy) for Geothermal Power Plant (“GR 7/2017”), and MEMR

    Regulation Number 44 of 2015 on The Purchase of Electric Power by PLN from Municipal

    Waste-to-Energy Power Plant (“MEMR Reg. 44/2015”) for Municipal Waste-to-Energy Power Plant.

    The mandate given by the MEMR under the relevant regulations to PLN to purchase electric power

    from the relevant power plant is deemed as the MEMR's approval for PLN to make a direct appointment

    and to agree on the electric power purchase price. The period for finalizing a direct appointment is

    approximately 100 days.

    The direct selection procedure is provided under MEMR Reg. 50/2017. In this type of procurement,

    PLN must conduct a due diligence study on the technical and financial capacity of the IPP candidates

    that will operate the power plant and sell electric power to PLN. The due diligence study can also be

    conducted by a procurement agent appointed by PLN. In this case, MEMR approval is required for the

    electric power purchase price. For a direct selection, the pre-qualification procedure until a contract is

    agreed on may take up to 150 days.

    In connection with the above, please see below the procurement procedure and Feed-in-Tariff for each

    type of NRE power plant:

    No. NRE Power

    Plant Type

    Relevant

    Regulation

    Procurement

    Procedure

    Feed-In Tariff

    Regional BPP >

    national average

    BPP

    Regional BPP ≤

    national average

    BPP

    1. Solar Power

    Plant

    (“PLTS”)

    MEMR Reg.

    50/2017

    Direct selection

    based on Capacity

    Quota21

    85% of the regional

    BPP

    Business-to-Busines

    s negotiations

    2. Wind Power

    21 Under MEMR Reg 50/2017, the capacity quota is the power plant’s maximum capacity offered to a business entity for a

    certain term at a determined electric power price.

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    16 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    No. NRE Power

    Plant Type

    Relevant

    Regulation

    Procurement

    Procedure

    Feed-In Tariff

    Regional BPP >

    national average

    BPP

    Regional BPP ≤

    national average

    BPP

    Plant

    (“PLTB”)

    3. Biomass

    Power Plant

    (“PLTBm”)

    Direct selection

    4. Biogas Power

    Plant

    (“PLTBg”)

    5. Ocean

    Energy

    Power Plant

    (“PLTA

    Laut”)

    6. Hydro-Electr

    ic Power

    Plant

    (“PLTA”)

    The regional BPP

    In Sumatra, Java

    and Bali, or in other

    systems where the

    regional BPP ≤ the

    national average

    BPP, the tariff will

    be based on B2B

    negotiations. In

    other regions, the

    tariff will be the

    regional BPP.

    7. Geothermal

    Power Plant

    (“PLTP”)

    GR 7/2017 Open tender or

    Direct

    appointment

    8. Municipal

    Waste-to-En

    ergy Power

    Plant

    (“PLTSa”)

    MEMR Reg.

    50/2017 and

    MEMR Reg.

    44/2015

    Direct

    appointment22

    9. Biofuel

    Power Plant

    (“PLTBBN”)

    MEMR Reg.

    50/2017

    Direct selection Mutual agreement of the parties.

    22 However, under PR Number 35/2018, specific to waste-to-energy, the local government can assign developers from

    among region-owned-enterprises (Badan Usaha Milik Daerah - “BUMD”) or hold an open tender for the private sector. If the private sector is not interested and the BUMD is considered not capable, the MEMR can assign the waste-to-energy power plant to a state-owned enterprise based on a recommendation from the local government.

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    17 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    5 Will an IPP take the quantity risk (i.e. the risk that the generating facility may not

    be dispatched by the offtaker (in case of PPA) or due to low demand or competition

    in the market (in case of sale into market))?

    According to the market precedent, PLN will continue paying for the generated electric power as

    ‘deemed dispatch’ if the PLN network is disrupted whether due to force majeure or not.

    In a recent PPA, this payment was to be made during the take or pay period (i) if one or more events or

    circumstances affecting PLN's grid system (other than due to an Event of Force Majeure) affect the IPP

    company’s ability to provide net dependable capacity or net electrical output for a certain period of

    time; or (ii) if a force majeure event affects PLN’s Grid System or other PLN owned facilities

    necessitating repairs, the power plant will be ‘deemed dispatched’ to the extent that the IPP company

    would have been able to deliver and/or PLN would have been able to accept net electrical output in

    accordance with the terms and conditions of the PPA and PLN will continue obliged to pay for net

    dependable capacity as per the PPA until the facilities are repaired.

    This payment is limited to a certain period under the PPA, eg up to a maximum of 14 days in aggregate

    in any contract year and 120 days in the aggregate during the term of the PPA. If a Force Majeure event

    caused a long-term interruption (eg 6 months), PLN also had to pay for termination payments to the

    IPP.

    The MEMR Reg PPA has considerably changed this condition. As now if a Natural Force Majeure event

    (the only force majeure event covered by the MEMR Reg PPA) prevents PLN from taking power, the

    PPA may instead be extended by the length of time the Natural Force Majeure event and subsequent

    repairs have taken. The power plant is not ‘deemed dispatched’ and PLN is no longer required to make

    the deemed dispatch payments. No doubt, this will become major concern and issue for sponsors and

    also lenders who require regular scheduled loan repayments from the project’s cash flow. So far, no

    precedent has been set yet for how this provision should be implemented in practice. For future projects,

    PLN will likely insist on the inclusion of this provision in the PPA to conform to the MEMR Reg PPA.

    6 Please explain risk allocation and remedies upon occurrence of force majeure in

    connection with electric power generation projects. Are there any differences

    between the risk allocation and remedies (i) upon occurrence of Political Force

    Majeure and (ii) upon occurrence of General Force Majeure?

    General

    The market practice for force majeure in electric power projects applies the same fairness principle.

    Either party will be excused from complying with its obligations and will not be deemed in default of

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    18 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    any obligation under the PPA for as long as its failure to comply with the obligation is due to force

    majeure.

    Events of force majeure include, but are not limited to:

    a) acts of war or the public enemy whether war is declared or not;

    b) public disorders, insurrection, rebellion, sabotage, riots or violent demonstrations;

    c) explosions, fires, earthquakes, floods, or other natural calamities and acts of God, or the

    discovery of hazardous materials or historical artefacts on the Site;

    d) strikes or other industrial action by workers or employees of either party and/or its contractors

    or subcontractors or any other parties engaged or appointed by either party;

    e) with respect to the IPP company only:

    • the occurrence of an event of force majeure as specified in paragraphs (a) to (d) above

    affecting the coal supplier – as the coal supply will be the IPP company’s responsibility; and

    • any Change in Circumstance, ie government/political force majeure, change of law.

    Effects of Force Majeure

    In practice, if the force majeure event occurs before the COD and causes a delay in the project’s

    milestone schedule, the milestone schedule will be equitably adjusted to avoid or minimize overall

    delays resulting from the force majeure event. However, if it results in a ‘material delay’ in the

    completion of the project or causes material damage to the Plant, and there is no insurance for force

    majeure (as it is not normally required to be insured for according to Good Utility Practice), or it could

    not be insured against before it occurred, the parties will negotiate in good faith a satisfactory solution

    to allow the construction or the operation of the power plant to continue, and any extension of the take

    or pay period (if reasonably necessary). If they fail to find a solution satisfactory to both parties, PLN

    and the IPP company may jointly terminate the PPA.

    If a force majeure event occurs:

    (i) during the take or pay period: the take or pay period will be extended and proportionately

    adjusted for a period of time equal to the period during which the IPP company is affected; or

    (ii) during the take and pay period: the PPA will be extended and proportionately adjusted for a

    period of time equal to the period during which the IPP company is affected,

    provided however, in each case, that the term of the PPA will not exceed 30 years commencing from the

    COD.

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    19 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    Deemed To be Commissioned and Deemed Dispatch

    If an event of force majeure (other than a Change in Circumstances) affects PLN’s grid system or other

    PLN owned facilities necessitating repairs, and the repairs are not completed within a certain period,

    the affected unit or power plant (with an agreed to MW capacity) will be ‘deemed to be commissioned’

    and ‘deemed to be providing’ net dependable capacity for the power plant with the actual AF deemed to

    be 80%.

    Subsequently, PLN will compensate the IPP company for the net dependable capacity for the unit or

    power plant due to the delayed the net dependable capacity test. If the unit or power plant is then tested

    and fails the net dependable capacity test, the deemed commissioned status will cease, and PLN will not

    be obliged to make any further payment. If it passes the test and an excess in payment is caused by the

    difference between the test results and the agreed MW capacity in the PPA, the payment will be credited

    against future payments from PLN to the IPP company.

    In addition, during the take or pay period, if an event of force majeure (other than a Change in

    Circumstances) affects PLN’s grid system or other PLN owned facilities necessitating repairs, and the

    repairs are not completed within a certain period, the power plant will be ‘deemed dispatched’ to the

    extent that the IPP company would have been able to deliver and/or PLN would have been able to

    accept the net electrical output and PLN will be obliged to pay for net dependable capacity in

    accordance with the PPA.

    However, the MEMR Reg PPA has considerably changed the above as PLN and the IPP company are

    now released from their respective obligations if the Natural Force Majeure event:

    • causes a COD delay: a time extension for as long as the natural disaster continues (including time

    for necessary repairs to the project); or

    • causes an inability to distribute electric power: a time extension for as long as the natural disaster

    continues (including time for necessary repairs to the project).

    Matters Not Exempted

    An event of force majeure will not excuse the IPP company from the following:

    a) any late payment;

    b) any late delivery of equipment or materials caused by negligence or any omission by the IPP

    company or its contractors;

    c) any late performance by the IPP company or its contractors due to a failure to engage qualified

    subcontractors or to hire an adequate number of personnel or workers;

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    20 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    d) submitting documents and/or drawings for approval by PLN without allowing sufficient time

    for their review prior to purchase or manufacture; or

    e) responsibility for delays resulting from reasonably foreseeable unfavorable weather or

    unsuitable ground or sea conditions or other similar reasonably foreseeable adverse conditions.

    Termination due to Force Majeure

    Under a recent PPA, an event of force majeure can lead to the termination of the PPA if:

    a) (i) it prevents or will prevent the construction of the project or operation of the power plant for a

    continuous period of more than 24 months, and the event of force majeure fundamentally

    frustrates the economic basis of the transaction under the PPA, or (ii) it is a Change in

    Circumstances event of force majeure and the parties fail to find solution satisfactory to them

    both, the parties may jointly terminate the PPA.

    b) it affects PLN’s grid system or other PLN owned facilities necessitating repairs following a

    continuous period of 180 days; in which case, the parties will discuss good faith an alternative

    acceptable solution. If within 90 days no solution is reached, either party may terminate the

    PPA, and PLN will have the option to purchase the project or all of the shares in the IPP

    company, including the company’s title and interest in the project and rights and obligations at

    the purchase price determined in the PPA.

    Costs and Savings

    A change of law is included as a ‘Triggering Event’ under the PPA provided that it will cause any (a)

    increase in Costs (the cost of producing electric power including any capital, financing, operation and

    maintenance costs, and tax, duty or levy costs imposed on or payable by the IPP company) or result in

    Savings (a reduction in costs or expenses related to the project that have been realized by the IPP

    company and directly affect the cost of producing electric power).

    Note that ‘taxes, duties or levies’ are not considered “Savings” under the PPA. Such savings or

    reductions in costs or expenses relating to the project must have already been realized by the IPP

    company. For example, the approval of a corporate income tax holiday obtained by an IPP may arguably

    not trigger any “Savings” yet as the corporate income tax holiday is currently not yet in effect and will

    only apply after the IPP company has generated a profit and no further losses could be set off under the

    applicable income tax laws and regulations.

    Discussions of the price adjustment resulting from any savings or reduction of cost must commence

    within 7 days of the notice for the triggering event. If the content of the notice (including the claim for

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    21 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    Costs or Savings attributable to the Triggering Event) is not disputed by the Parties, the appropriate

    components of the price will be adjusted:

    • as of the project COD, to reflect all undisputed claims submitted from the date of the agreement

    until the project COD; and

    • as of the first day of each contract year commencing with the first day of contract year 2, to reflect

    all undisputed claims in the preceding contract year.

    7 Please explain the components of termination payments for PPA (typically,

    intended for project finance).

    The components of a PPA termination payment are provided in the Appendix to the PPA and depend on

    the cause of the PPA’s termination as follows:

    a. Termination by PLN due to an event of default by the IPP company.

    PLN will purchase all of the company's rights, title and interests in the project for a price equal

    to:

    • the total amount outstanding and payable by the company as the outstanding senior debt

    and interest due and payable on the calculation date; minus

    • the greater of (i) the sponsors’ equity commitment plus the sponsors’ contingent equity

    commitment, minus the sponsors’ actual equity contributions, and, (ii) zero.

    b. Before the project’s COD, (i) termination by the IPP company due to event of default by PLN; or

    (ii) termination by the IPP company or PLN due to a certain construction period force majeure

    (political force majeure or other force majeure affecting PLN or PLN’s grid system).

    PLN will purchase all of the company’s rights, title and interests in the project for a price equal

    to:

    • the total amount outstanding and payable by the company as the senior debt and interest

    due and payable on the calculation date; plus

    • the sum of:

    (A) the lesser of (x) the sponsors’ actual equity contribution and (y) the sum of the

    sponsors’ equity commitment plus the sponsors’ contingent equity commitment; and

    (B) an amount equal to a rate of 15% per annum calculated of the sum of the sponsors

    actual equity contributions compounded annually from the date of each sponsor’s

    actual equity contribution to the calculation date; less

    • the sum of:

    (A) the debt service reserve amounts; and

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    22 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    (B) payments made by PLN during any deemed period that have not been used to repay

    the senior debt or to meet fixed operating and maintenance expenditures (including

    c. After the project COD, (i) termination by the IPP company due to an event of default by PLN; or

    (ii) termination by PLN due to political force majeure or other force majeure.

    PLN will purchase all of the company’s rights, title and interests in the project for a price equal to the

    sum of a calculation using certain formula provided in the PPA considering the net dependable capacity,

    contract capacity and the senior debt component.

    ◇B Investment in the Electric Power Generation Industry

    1 Are there any regulations on foreign companies to invest in electric power

    generation projects in your country? If yes, what sort of regulations?

    Certain conditions and limits apply to foreign investment in certain sectors, including infrastructure

    involving joint cooperation or joint operation schemes for electric power generation projects. These are

    imposed under the Negative List of Investment. We understand from the news that the government of

    Indonesia is preparing an updated and more relaxed negative list with foreign investment restrictions in

    certain sectors which include foreign shareholdings in power plants with a capacity of above 10 MW.

    However, as of January 2019, we understand that the draft on updated negative list is still being

    discussed and has not yet to come into effect. Therefore, for the purpose of this publication, we refer to

    the currently prevailing Negative List of Investment.

    Under the Negative List of Investment which restricts investment in certain business fields, foreign

    shareholdings in power plants are generally limited to the following:

    Capacity Conditions

    < 1 MW 100% domestic shareholders

    1 – 10 MW maximum 49% foreign shareholding is permitted

    > 10 MW

    maximum 95% foreign shareholding is permitted (or

    maximum 100% if it is a Public Private Partnership, during

    the term of the concession)

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    23 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    2 What is the most common form of company (such as LLC) as a project company for

    an electric power generation project, and its characteristics? In addition, please

    let us know if there is any important restriction on the shareholders agreement

    from the legal or other perspective.

    The form of project company for an electric power generation project is a limited liability company

    (perseroan terbatas) established under Law Number 40 of 2007 on Limited Liability Companies

    (“Company Law”). Investors (foreign or domestic) must also observe other Indonesian laws and

    regulations issued by the relevant government authorities which impose terms and conditions on the

    business activities under their supervision. Any Indonesian company in which foreign investors own

    shares is considered a foreign investment company ("PMA Company").

    A PMA company must have a purpose and objectives and its business activities may not violate the

    prevailing laws or regulations, public order, and/or morality. The purpose and objectives of a PMA

    company are those listed in its business license and must be specified in detail in its Articles of

    Association. As explained above, the business activities of a PMA Company are subject to certain

    conditions, limitations and exceptions under the Negative List of Investment.

    A PMA Company must have at least 2 (two) shareholders. For its management, a PMA Company has 3

    (three) organs: the General Meeting of Shareholders (“GMS”), the Board of Directors (“BOD”) and the

    Board of Commissioners (“BOC”), each of which serves different functions. The GMS is the company

    organ with the authorities which are not assigned to the BOD or the BOC, subject to the limitations

    imposed under the Company Law and/or the Articles of Association of the company. The BOD has the

    authority and is responsible for the management of the company for its best interest, according to its

    purpose and objectives, as well as to represent the company in and out of the courts in accordance with

    its Articles of Association. The BOC is responsible for the general and/or specific supervision of the

    company, in accordance with its Articles of Association, and provides advice to the BOD.

    In general, except for the restriction for the transfer of the ownership of an electric power generation

    project company (IPP) to any other party before the COD (as will be elaborated below), no specific

    provisions or requirements apply to shareholders agreements for electric power generation projects,

    other than those under the Company Law which apply generally whatever the business sector.

    3 Where a domestic or foreign company intends to sell its equities in an electric

    power generation project in whole or in part, does any regulation apply?

    Under the MEMR Reg PPA and MEMR Regulation Number 48 of 2017 on Business Supervision In The

    Energy And Mineral Resources Sector, the ownership of an electric power generation project company

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    24 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    (IPP) may not be transferred to any other party before the COD, unless the transfer is to its affiliated

    subsidiary, 90% of the shares of which are owned by the party intending to transfer its shares. Such a

    transfer requires prior written approval from the purchaser (eg PLN) and must be reported to the

    MEMR through the Director General of Electric Power. The regulation is silent on transfers of shares

    after the project reaches its COD. However, the Sponsors’ Agreement (the generic form is attached as a

    schedule to the PPA) will further regulate such transfer of shares from the sponsors after the project

    reached COD. Nevertheless, this is a contractual arrangement between the sponsors and PLN.

    4 In your country, what is the common method for a sponsor to invest in or provide

    funds to a project company other than by way of acquisition of shares (or equity) of

    a project company?

    Foreign investment in Indonesia, including for electric power generation projects, is commonly made by

    (i) acquiring shares in an existing Indonesian company; or (ii) establishing a new Indonesian company

    (the company in each of (i) and (ii): the “Project Company”). Meanwhile, the most common method

    for sponsors to provide funds to a Project Company as project finance is a common loan arrangement

    provided by banks. However, in some cases, the funds are not provided by banks but are institutional

    funds provided through the issuance of bonds by the Project Company to sponsors. Although this

    scheme is not as common as an acquisition of shares in an existing company or the establishment of a

    new company, the issuance of project bonds has been an alternative source of capital for project finance

    in Indonesia, with the financing of PT Paiton Energy’s coal fired power plants in Probolinggo, East Java,

    being a landmark for this scheme.

    ◇C Project Finance

    1 Please list commonly used project finance schemes used for electric power

    generation projects in your country.

    Electric power generation projects are mostly financed through some or all of the following finance

    schemes and sources of funds:

    a. Equity

    Equity can usually be provided through (i) shareholders’ participation; (ii) project sponsors

    (subordinated debt); and (iii) shareholders loans (subordinated debt). Either the sponsor alone

    or a consortium of investors can provide the funding.

  • Notice: This article is prepared and contributed by the authors shown in this article and therefore Atsumi & Sakai is not responsible for this article in any respect. The information contained in this article is as of the end of 2018 and has not been updated since then and provided as a general guidance information only. This article should not be relied upon as constituting legal advice. 各国の記事は当該記事末尾記載の現地法律事務所弁護士が作成したものであり、渥美坂井法律事務所・外国法共同事業はその内容につき責任を負っておりません。これらの記事は、一般的な説明であり、具体的な案件への適用を意図したものではなく、また、2018年 12月末日時点の情報を元に作成されたものであり、以降の更新は行っておりません。

    25 ©2019 Atsumi & Sakai/ Makarim & Taira S.

    b. Debt/Loans

    In Indonesia, generally, debt is obtained through (i) bank loans; (ii) bonds (capital market); and

    (iii) multilateral agencies.

    1. Bank loans

    Bank loans are structured based on the expected project cash flow, with a moratorium or

    grace period, and an interest payment and principal repayment schedule. Bank loans are

    usually fully secured and have recourse to project assets in the event of default. Since

    electric power generation projects are capital intensive, they are often funded by a high

    proportion of debt (to reduce overall funding costs). To reduce individual exposure, banks

    often prefer to be part of a consortium or ‘syndicate’ of banks in which one bank often acts

    as the ‘lead bank’.

    2. Bonds (Capital Market)

    Bonds represent the debt funding obtained for a project from the capital markets. The

    benefits of bonds are:

    (1) they can be cheaper and quicker than bank loans;

    (2) they are less restrictive than bank loans, except regarding disclosure;

    (3) the proceeds are disbursed in a single lump sum; and

    (4) the investors are disparate (not a club of banks), many of which only hold a small

    part of the project loan.

    3. Multilateral Agencies

    Multilateral agencies usually follow the same debt structure as purely private investors.

    For example, multilateral agencies typically lend for long-term projects, are focused on

    projects with an economic development impact, and provide technical guidance

    throughout the project lifecycle.

    c. Other Support

    In specific cases, especia