134-18 Woodville Tompkins HS Additions ADDENDA # 1 00 9113 - 1 DOCUMENT 00 9113 ADDENDUM No. 1 1.1 PROJECT INFORMATION A. Project Name: Woodville Tompkins HS Additions ESPLOST Bid C20-10 Savannah, Georgia B. Owner: Savannah Chatham County Public School System 208 Bull Street Savannah GA 31401 C. Architect: James W. Buckley & Associates, Inc. 7 East Congress Street Savannah, Georgia 31401 1.2 Date of Addendum: October 25, 2019 1.3 NOTICE TO BIDDERS A. This Addendum is issued to all registered plan holders pursuant to the Instructions to Bidders and Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement. B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid Form. 1.4 REVISIONS TO PROJECT MANUAL A. 01 1000 SUMMARY 1. 1.5 WORK UNDER SEPARATE CONTRACTS a. Delete Paragraph C in its entirety. B. 02 0600 GEOTECHNICAL DATA 1. GEOTECHNICAL ENGINEERING REPORT a. Delete the Geotechnical Engineer Report in its entirety. b. Add “Geotechnical Engineering Report – Proposed Gymnasium and Auditorium Addition Structure, Woodville Tompkins High School” copy enclosed this addendum.

Transcript of 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1...

Page 1: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,

134-18 Woodville Tompkins HS Additions

ADDENDA # 1 00 9113 - 1

DOCUMENT 00 9113

ADDENDUM No. 1

1.1 PROJECT INFORMATION

A. Project Name:

Woodville Tompkins HS Additions ESPLOST Bid C20-10

Savannah, Georgia

B. Owner:

Savannah Chatham County Public School System

208 Bull Street

Savannah GA 31401

C. Architect:

James W. Buckley & Associates, Inc.

7 East Congress Street

Savannah, Georgia 31401

1.2 Date of Addendum: October 25, 2019

1.3 NOTICE TO BIDDERS

A. This Addendum is issued to all registered plan holders pursuant to the Instructions to Bidders

and Conditions of the Contract. This Addendum serves to clarify, revise, and supersede

information in the Project Manual, Drawings, and previously issued Addenda. Portions of the

Addendum affecting the Contract Documents will be incorporated into the Contract by

enumeration of the Addendum in the Owner/Contractor Agreement.

B. The Bidder shall acknowledge receipt of this Addendum in the appropriate space on the Bid

Form.

1.4 REVISIONS TO PROJECT MANUAL

A. 01 1000 SUMMARY

1. 1.5 WORK UNDER SEPARATE CONTRACTS

a. Delete Paragraph C in its entirety.

B. 02 0600 GEOTECHNICAL DATA

1. GEOTECHNICAL ENGINEERING REPORT

a. Delete the Geotechnical Engineer Report in its entirety.

b. Add “Geotechnical Engineering Report – Proposed Gymnasium and Auditorium

Addition Structure, Woodville Tompkins High School” copy enclosed this

addendum.

Page 2: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,

134-18 Woodville Tompkins HS Additions

ADDENDA # 1 00 9113 - 2

C. 07 1500 VAPOR BARRIERS

1. 2.01 FLOOR SLAB MEMBRANE

a. Add Tex-trude as an acceptable manufacturer. Product subject to compliance with

specifications.

D. 09 6420 ATHLETIC WOOD FLOORING

1. 2.01 WOOD STRIP FLOORING SYSTEMS, B. Manufacturer

a. Add Horner Sports Flooring as an acceptable manufacturer. Product subject to

compliance with specifications.

E. 12 6100 FIXED AUDIENCE SEATING

1. 2.3 FIXED AUDIENCE SEATING, 1. Manufacturers

a. Add Davis Furniture Co., Melrose, WI, as an acceptable manufacturer. Product

subject to compliance with specifications.

b. Add Inorca as an acceptable manufacturer. Product subject to compliance with

specifications.

c. Add KI as an acceptable manufacturer. Product subject to compliance with

specifications.

F. 12 6600 TELESCOPING STANDS

1. 2.2 TELESCOPING STANDS, B, 1. Manufacturers

a. Add Sheridan Seating as an acceptable manufacturer. Product subject to

compliance with specifications.

2. 2.3 COMPONENTS SEATING, D, 2

a. Deck finish to be manufacturers standard high-density polyethylene laminated

panel.

1.5 REVISIONS TO DRAWINGS (notes are general descriptions only)

A. Sheet D2.0 - Added demo notes, increased slab demo region

1. Replace sheet D2.0 in its entirety, copy enclosed this addendum.

B. Sheet A1.4 - Revisions to RAC on roof plan

1. Replace sheet A1.4 in its entirety, copy enclosed this addendum.

C. Sheet A2.0 - Revisions to coach’s toilet 326 and adjacent fountains, also affects A2.4 and A8.1

1. Replace sheet A2.0 in its entirety, copy enclosed this addendum.

2. Replace sheet A2.4, copy enclosed this addendum.

3. Replace sheet A8.1 in its entirely, copy enclosed this addendum.

D. Sheet A2.2 - Revisions to covered walk, added detail

1. Replace sheet A2.2 in its entirety, copy enclosed this addendum.

E. Sheet A2.3 – Added wood wainscoting, changes affect several detail sheets.

1. Replace sheet A2.3 in its entirety, copy enclosed this addendum.

2. Replace sheet A3.2, copy enclosed this addendum.

3. Replace sheet A6.9, copy enclosed this addendum.

4. Replace sheet A6.11, copy enclosed this addendum.

5. Replace sheet A8.3, copy enclosed this addendum.

6. Add sheet A9.0C, copy enclosed this addendum.

Page 3: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,

134-18 Woodville Tompkins HS Additions

ADDENDA # 1 00 9113 - 3

7. Replace sheet A10.2, copy enclosed this addendum.

8. Replace sheet A11.1, copy enclosed this addendum.

F. Sheet A3.0 – Revised/added door details, changes to schedules

1. Replace sheet A3.0 in its entirety, copy enclosed this addendum.

G. Sheet A6.3 – Clouded Revisions

1. Replace sheet A6.3 in its entirety, copy enclosed this addendum.

H. Sheet A6.4 – Clouded Revisions

1. Replace sheet A6.4 in its entirety, copy enclosed this addendum.

I. Sheet A14.0 – Clouded Revisions

1. Replace sheet A14.0 in its entirety, copy enclosed this addendum.

J. Sheet A14.1 – Clouded Revisions

1. Replace sheet A14.1 in its entirety, copy enclosed this addendum.

K. Sheet A14.2 – Clouded Revisions

1. Replace sheet A14.2 in its entirety, copy enclosed this addendum.

L. Sheet A17.1 – Omit detail 5 and move to sheet A14.2

M. Sheet S0.1

1. In structural notes, roof decks, roof deck type “RD1”, change metal deck to 1 2" x 22

gauge galvanized (G90) steel deck, minimum 3 spans. Add note “Refer to specification

035216 for additional information.”

N. Sheet S1.1

1. Add “Crossing Cover Foundation Plan” per Attachment SK-3, copy enclosed this

addendum.

O. Sheet S02.1

1. Revise top of steel and section cut designations on “Gymnasium front canopy roof

framing plan” in accordance with attachment SK-1, copy enclosed this addendum.

2. Revise roof framing over stage in accordance with attachment SK-2, copy enclosed this

addendum.

P. Sheet P0.1 – Replace existing fountains, rerouted gas piping, waste pipe phasing

1. Replace sheet P0.1 in its entirety, copy enclosed this addendum.

Q. Sheet P1.0 – Waste pipe revision, shift floor drains at showers.

1. Replace sheet P1.0 in its entirety, copy enclosed this addendum.

R. Sheet P1.1 – Add floor drains, connect new fountains.

1. Replace sheet P1.1 in its entirety, copy enclosed this addendum.

S. Sheet P2.0 – Water service relocation, add hose bib, move WH

1. Replace sheet P2.0 in its entirety, copy enclosed this addendum.

Page 4: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,

134-18 Woodville Tompkins HS Additions

ADDENDA # 1 00 9113 - 4

T. Sheet P3.0 – Relocated RAC’s

1. Replace sheet P3.0 in its entirety, copy enclosed this addendum.

U. Sheet P2.1 – connect new fountains

1. Replace sheet P2.1 in its entirety, copy enclosed this addendum.

V. Sheet M0.0 – Delete type “M” grille from Air Distribution Schedule

1. Replace sheet M0.0 in its entirety, copy enclosed this addendum.

W. Sheet M1.0 – Adjusted several RAC locations, Add notes 4-7, delete “G” grilles

1. Replace sheet M1.0 in its entirety, copy enclosed this addendum.

X. Sheet M1.1 – Replace type “M” grille, revised RAC-8 duct

1. Replace sheet M1.1 in its entirety, copy enclosed this addendum.

Y. Sheet M2.0 – Adjusted several RAC locations

1. Replace sheet M2.0 in its entirety, copy enclosed this addendum.

Z. Sheet E0.2 – Note for trash compactor relocation

1. Replace sheet E0.2 in its entirety, copy enclosed this addendum.

AA. Sheet E0.4 – Compactor circuit add

1. Replace sheet E0.4 in its entirety, copy enclosed this addendum.

BB. Sheet E1.0 – Relocate fixtures, add exterior fixtures

1. Replace sheet E1.0 in its entirety, copy enclosed this addendum.

CC. Sheet E3.0 – Adjust electrical connections for several RAC’s

1. Replace sheet E3.0 in its entirety, copy enclosed this addendum.

DD. Sheet E4.0 – Move duct smoke detector

1. Replace sheet E4.0 in its entirety, copy enclosed this addendum.

1.6 ATTACHMENTS

A. This Addendum includes the following attached Documents and Specification Sections:

1. PROJECT MANUAL

a. SECTION 02 0600 - Geotechnical Report

2. DRAWINGS

a. Sketches: SK-1, SK-2, SK-3

b. Sheets: D2.0, A1.4, A2.0, A2.2, A2.3, A2.4, A3.0, A3.2, A6.9, A6.11, A8.1, A8.3,

A9.0C, A10.2, A11.1, A14.0, A14.1, A14.2, P0.1, P1.0, P1.1, P2.0, P2.1, M0.0,

M1.0, M1.1, M2.0, E0.2, E0.4, E1.0, E3.0, E4.0

END OF DOCUMENT 00 9113

Page 5: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 6: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 7: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 8: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 9: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 10: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 11: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 12: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 13: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 14: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 15: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 16: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 17: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 18: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 19: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 20: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 21: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 22: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 23: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 24: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 25: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 26: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 27: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 28: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 29: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 30: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 31: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 32: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 33: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 34: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 35: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 36: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 37: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 38: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 39: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 40: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 41: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 42: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 43: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 44: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,
Page 45: 1.1 PROJECT INFORMATIONinternet.savannah.chatham.k12.ga.us › district › finance...R. Sheet P1.1 – Add floor drains, connect new fountains. 1. Replace sheet P1.1 in its entirety,