10 nomor ekotek
Click here to load reader
-
Upload
nurman-wibisana -
Category
Documents
-
view
205 -
download
1
Transcript of 10 nomor ekotek
Economy EngineeringTEKNIK INDUSTRI
Nama Anggota Kelompok :
Anggina Vanessa ( 1106013624 )
Deo Gratias ( 1106069430 )
Hasna Afifah ( 1106069595 )
Nurman Wibisana ( 1106069563 )
Richard Sihombing ( 1106054473 )
Yonathan Elia Munthe ( 1106054372 )
8.18. A chemical company is considering two processes for isolating DNA
material .The incremental cash flow between the two alternatives, J and S, is
estimated. The company uses a marr of 50 % per year. The rate of return on the
incremental cash flow below is less than 50%, but the company CEO prefers the
more expensive process. The CEO believes she can negotiate the initial cost of
the more expensive process downward. By how much would she have to reduce
the first cost of S, the higher cost alternatives, for it to have an incremental rate
of return of exactly 50 %?
Year Incremental cash flow
0 $-900,000
1 400,000
2 700,000
3 950,000
Answer
1. Calculated incremental cash flowpada in year 0 when NPV=0 with i*=50%
0 = X + $400,000 ( P/F, 50%, 1) + $700,000 ( P/F, 50%, 2) + $950,000 ( P/F, 50%,3 )
0 = X + $400,000 ( P/F, 50%, 1) + $700,000 ( P/F, 50%, 2) + $950,000 ( P/F, 50%,3 )
0 = X + $859,245
X = $-859,245
Reduce the initial cost = -$900,000-(-$859,245)
= -$40,755
8.23.Two roadway designs are under consideration for access to a permanent
suspension bridge. Design 1A will cost $3 million to build and $100,000 per year
to maintain. Design 1B will cost $3.5 million to build and $80,000 per year to
maintain. Use an AW-based rate of return equation to determine which design is
preferred. The marr is 10% per year.
Answer :
1A 1B Incremental
Initial -$ 3 million -$ 3.5 million -$0,5 million
Maintenance /
Year
-$ 100.000 -$ 80.000 $ 20.000
MARR / year 10%
Total -$4.000.000 -$4.300.000 -$300.000
PW A = -$3 million - $100.000 / 10% = -$4.000.000
PW B = -$3.5 million - $80.000 / 10% = -$4.300.000
PW Incremental = -$0.5 million + $20.000 / 10% = -$300.000
The incremental cash flow of the larger investment don’t justify ( -300.000 ) so the cheaper one is Design A
8.28 A metal plating company is considering four different methods for recovering
by product heavy metals from a manufacturing site’s liquid waste. The
investment costs and incomes associated with each method have been
estimated. All methods have a 10 year-life. The marr is 12% per year.(a) if the
methods are independent, because they can be implemented at different plants,
which ones are acceptable? (b)if the methods are mutually exclusive, determine
which one method should be selected, using a ROR evaluation.
Methode First cost,$ Salvage Value Annual Income
A -15,000 +1,000 +4,000
B -18,000 +2,000 +5,000
C -25,000 -500 +6,000
D -35,000 -700 +8,000
Answer :
A) using PW method
Method A B C D0 -15000 -18000 -25000 -350001 4000 5000 6000 80002 4000 5000 6000 80003 4000 5000 6000 80004 4000 5000 6000 80005 4000 5000 6000 80006 4000 5000 6000 80007 4000 5000 6000 80008 4000 5000 6000 80009 4000 5000 6000 8000
10 1000 2000 -500 -700IRR ( i* ) 23% 24% 19% 17%
Method A:
0 = -15000 + 4000(P/A,i*,10) + 1000(p/f, i*,10)
Subtituting MARR (=12%) for i*, the RHS is positive (=7922.8),
i*=23%>MARR therefore select A
Method B :
0 = -18000 + 5000 (P/A, i*,10) + 2000(p/f,i*,10)
Subtituting MARR (=12%) for i*, the RHS is positive (=10895),
i*=24%>MARR therefore select B
Method C :
0 = -25000 + 6000(P/A,I*,10) – 500(P/F,i*,10)
Subtituting MARR(=12%) for i*, the RHS is positive (=8740.2),
i*=19%>MARR therefore select C
Method D :
0 = -35000 + 8000(P/A,i*,10) – 700(P/F,i*,10)
Subtituting MARR(=12%) for i*, the RHS is positive (=9976.2),
i*=17%>MARR therefore select D
Project A, B, C, D selected because their i*>MARR
B)
Year A B C DInitial Cost -15.000 -18.000 -25.000 -35.000salvage Value 1.000 2000 -500 -700Annual Income 4.000 5000 6000 8.000Incremental Comparison A to DN B to A C to B D to B
0 -15.000 -3.000 -7000 -170001 4.000 1000 1000 30002 4.000 1000 1000 30003 4.000 1000 1000 30004 4.000 1000 1000 30005 4.000 1000 1000 30006 4.000 1000 1000 30007 4.000 1000 1000 30008 4.000 1000 1000 30009 4.000 1000 1000 3000
10 1.000 1000 -2500 -2700incremental i* ( ∆i* ) 23% 31% -2% 9%incremental justified ? yes yes no noalternative selected A B B B
A-DN : It is already shown in Athat i* for method A >MARR. Therefore, A is
selected over DN. Alternatively, we can write (using PW method) :
0 = -15000 + 4000(P/A,i*,10) + 1000 (P/F,i*,10)
I*>MARR select A
B-A :
0 = -3000 + 1000(P/A,Di*,10) + 1000(P/F,Di*,10)
It can be shown Di* > 12% RHS is positive therefore select B
C-B :
0 = -7000 + 1000(P/A,Di*,10) -2500(P/F,Di*,10)
With Di* = 12% RHS is negative; Hence Di* < MARR(=12%) therefore select
B again
D-B :
0 = -17000 + 3000(P/A,Di*,10) – 2700(P/F,Di*,10)
Here,again Di* < MARR therefore B is still the selection. Select B
8.30 An independent dirt contractor is trying to determine which size dump truck to
buy. The contractor knows that as the bed size increases, the net income
increases, but he is uncertain whwther the oincremental expenditure required for
the larger trucks is justifie. The cash flow associated with each size truck are
estimated below. The contractor’s MARR is 18% per year, and all trucks are
expected to have a useful life of 8 years. (a) determine which size truck should
be purchased. (b) if two trucks are to be purchased, what should be the size of
the second truck?
Truck Bed Size, Cubic Meters Initial Investment, $
Annual Operating Cost, $
Slavage Value, $
Annual Income, $
8 -10.000 -4.000 2000 6.50010 -14.000 -5.500 2.500 10.00015 -18.000 -7.000 3.000 14.00020 -24.000 -11.000 3.500 20.50025 -33.000 -16.000 6.000 26.500
Answer :
Year 8 10 15 20 25Initial Cost -10.000 -14.000 -18.000 -24.000 -33.000Annual Operating Cost -4.000 -5.500 -7.000 -11.000 -16.000salvage Value 2.000 2.500 3.000 3.500 6.000Annual Income 6.500 10.000 14.000 20.500 26.500Annual Profit 2.500 4.500 7.000 9.500 10.500Incremental Comparison 8 to DN 10 to DN 15 to 10 20 to 15 25 to 20 0 -10.000 -14.000 -4.000 -6.000 -9.000
1 1.500 4.500 3.500 2.500 1.000 2 1.500 4.500 3.500 2.500 1.000
3 1.500 4.500 3.500 2.500 1.000 4 1.500 4.500 3.500 2.500 1.000
5 1.500 4.500 3.500 2.500 1.000 6 1.500 4.500 3.500 2.500 1.000
7 1.500 4.500 3.500 2.500 1.000 8 2.000 2500 500 500 2.500incremental i* ( ∆i* ) 5% 27% 86% 37% 1%incremental justified ? no yes yes yes noalternative selected 10 15 20 20
A ) DN vs 8:0 = -10000(A/P,i,5) + (6500-4000) + 2000(A/F,i,5)
Solve for i by trial and error or excel
I= 5% < MARR
Eliminate 8
DN vs 10:0 = -14000(A/P,i,5) + (10000-5500) + 2500(A/F,i,5)
Solve for i by trial and error or excel
i = 27% > MARR
Eliminate DN
10 vs 15:0 = -4000(A/P,i,5) + (7000 – 4500) + 500(A/F,i,5)
Solve for i by trial and error or excel
I = 86%
Eliminate 10
15 vs 20:0 = -6000(A/P,i,5) + (9500-7000) + 500(A/F,i,5)
Solve for i by trial and error or excel
I = 37% > MARR
Eliminate 15
20 vs 25:0 = -9000(A/P,i,5) + (10.500-9500) + 2500(A/F,i,5)
Solve for i by trial and error or excel
I = 1% < MARR
Eliminate 25
Purchase 20 m3 truck
B) for second truck, purchase truck that was eliminated next to 15 m3
8.31 An engineer at anode metal is considering the projects below, all of which can
be considered to last indefinitely.if the company’s MARR is 13 % per year,
determine which should be selected (a) if they are independent and (b) if they
are mutually exclusive (c)assume the projects are mutually exclusive and that
the incorrect decision rule to select the one project that invests the most
money and has a ROR that exceeds the MARR has been applied. What
project was selected ? why is this an incorrect choice?
First Cost ($) Annual Income ($) Alternative rate of
return (%)
A -$20,000 $4,000 20%
B -$10,000 $2,000 20%
C -$15,000 $2,000 19,3%
D -$70,000 $10,000 14,3%
E -$50,000 $6,000 12%
Answer :
(a) If they are independent we must selected the choice who has ROR >
MARR alternative A, B, C, and D are selected
(b) (b) If they’re mutually exclusive
A B C D E
First Cost ($) -$20,000 -$10,000 -$15,000 -$70,000 -$50,000
Annual Income ($) $4,000 $2,000 $2,000 $10,000 $6,000
Alternative rate of return (%) 20% 20% 19,3% 14,3% 12%
Project E is eliminated due to its ROR which is less than MARR
Now compare B and C, C will the new challenge and B the defender.
∆ i¿fromC to B comparison is determined from
0=−15000− (−10000 )+ 2900∆ i¿
+ 2000∆ i¿
∆ i¿=18%
Since ∆ i¿>MARR so C will be the new defender.
Compare A to C is determined from
0=−20000− (−15000 )+ 4000∆ i¿
−2900∆ i¿
∆ i¿=12%
The ∆ i¿is less than MARR so D eliminated and A remains. So, A is selected.
c) The incorrect decision rule to select the one project that invest the most money and has a ROR that exceeds the MARR has been applied.
A B C D E
First Cost ($) -$20,000
-$10,000
-$15,000
-$70,000
-$50,000
Annual Income ($) $4,000 $2,000 $2,000 $10,000 $6,000
Alternative rate of return (%)
20% 20% 19,3% 14,3% 12%
Find the NPV
Project B
NPV=−10000+ 20000,13
NPV=5384,6
Project C
NPV=−15000+ 29000,13
NPV=7307,69
Project A
NPV=−20000+ 40000,13
NPV=−10769,2
Project D
NPV=−70000+ 100000,13
NPV=−6923,07
9.15 A state highway department is considering the conscruction of a new
highway through a scenic rural area.The road is expected to cost $6million, with
annual upkeep estimated at $20,000 per year. The improved accessibility is
expected to result in additional income from tourists of $350,000 per year. If the
road is expected to have a useful life of 25 years, use the (a) B-C method and
(b)B/C method at an interest rate of 6% per year to determine if the highway
should be constructed .(c) what is the modified B/C value?
Answer :
(a) B-C analysis
AW = C = 469,380 + 20,000 = $ 489,380
Annual benefits = B = $350,000
B-C = 350,000 – 489,380 = - $ 139,380
Since B-C <0, the highway shouldn’t be build.
(b) B/C analysis
AW = C = 469,380 + 20,000 = $ 489,380
Annual benefits = B = $350,000
B/C = 350,000/489,380 = 0.715
Since B/C < 1.0, the highway shouldn’t be build.
(c)For modified B/C ratio,
C = 6,000,000 (0.07823) = $ 469,380
B = 350,000 – 20,000 = $ 330,000
Modified B/C = 330,000/469,380
= 0.703
Since modified B/C < 1.0, the highway shouldn’t be build
9.18 Two routes are under consideration for a new interstate highway segment. The
long route would be 25 kilometers and would have an initial cost of $21 million.
The short transmountain route would span 10 kilometers and would have an
initial cost of $45 million. Maintenance costs are estimated at $40,000 per year
for the long route and $15,000 per year for the short route. Additionally, a major
overhaul and resurfacing will be required every 10 years at a cost of 10% of the
first cost of each route. Regardless of which route is se- lected, the volume of
traffic is expected to be 400,000 vehicles per year. If the vehicle operating
expense is assumed to be $0.35 per kilometer and the value of reduced travel
time for the short route is estimated at $900,000 per year, determjne which route
should be selected, using a conven- tionalBIC analysis. Assume an infirute life
for each road, an interest rate of 6% per year, and that one of the roads wiII be
built.
Answer :
Alternative Comparison
A B
Distance 25 km 10 km
Initial Cost $21 million $45 million
Maintenance
Cost/year
$40.000 $15.000
Overhaul Cost/10
year
10% Initial Cost 10% Initial Cost
Vehicle 400.000 unit 400.000 unit
Operating Vehicle/km $0.35 $0.35
Reduced Travel Time 0 $900.000
Cost
A. FW10 = 21
million
(F/P,6%,10) + 40.000 (F/A,6%,10) + 2.100.000
= 21 million (1.7908) + 40.000 (13.1808) + 2.100.000
= 37.606.800 + 527.232 + 2.100.000
= $40.234.032
B. FW10 = 45 million (F/P,6%,10) + 15.000 (F/A,6%,10) + 4.500.000
= 45 million (1.7908) + 15.000 (13.1808) + 4.500.000
= 80.586.000 + 197.712 + 4.500.000
= $85.283.712
∆C = FWb – FWa
= $85.283.712 - $40.234.032
= $45.049.680
Benefit
A. 0 + 400.000 (0.35)(25) = $3.500.000
B. $900.000 + 400.000 (0.35)(10) = $2.300.000
∆B = A-B = $3.500.000 - $2.300.000 = $1.200.000
B/C = $1.200.000/$45.049.680
= $0.02
Because B/C less than 1, so we choose option A (long road)
A BDistance 25 km 10 kmInitial Cost $21 million $45 millionMaintenance Cost/year $40.000 $15.000Overhaul Cost/10 year 10% Initial Cost 10% Initial CostVehicle 400.000 unit 400.000 unitOperating Vehicle/km $0.35 $0.35Reduced Travel Time 0 $900.000Total Benefit ( B ) 3.500.000 2.300.000Total Cost ( C ) 40.234.032 85.283.712Overall B/C 0,086991033 0,026968807Incremental B ( ∆B ) 1.200.000Incremental cost ( ∆C ) 45.049.680∆B/C 0.02
9.20 A privately owned utility is considering two cash rebate programs to achieve
water conservation. Program 1, which is ex- pected to cost an average of $60 per
household, would involve a rebate of 75 % of the purchase and installation costs
of an ultralow-ftush toilet. This program is pro- jected to achieve a 5% reduction
in overall household water use over a 5-year evalua- tion period. This will benefit
the citizenry to the extent of $1 .25 per household per month. Program 2 would
involve grass re- placement with desert landscaping. This is expected to cost
$500 per household, but it will result in reduced water cost at an estimated $8 per
household per month (on average). At a discount rate of 0.5% per month , which
program , if either, should the utility undertake? Use the B/C method.
Answer :
First compare program 1 to do-nothing (DN).
Cost/household/mo = $60(A/P,0.5%,60)
= 60(0.01933)
= $1.16
B/C1 = 1.25/1.16
= 1.08, Eliminate DN
Compare program 2 to program 1.
Δcost = 500(A/P,0.5%,60) – 60(A/P,0.5%,60)
= (500 – 60)(0.01933)
= $8.51
Δbenefits = 8 – 1.25
= $6.75
Incr B/C2 = 6.75/8.51
= 0.79 Eliminate program 2
The utility should undertake program 1.
9.23 The California Forest Service is consider- ing two locations for a new state park.
Lo- cation E would require an investment of $3 million and $50,000 per year in
mainte- nance. Location W would cost $7 million to construct, but the Forest
Service would receive an additional $25,000 per year in park use fees. The
operating cost of loca- tion W will be $65,000 per year. The rev- enue to park
concessionaires will be $500,000 per year at location E and $700,000 per year at
location W. The disbenefits associated with each location are $30,000 per year
for location E and $40,000 per year for location W. Use (a) the B/C method and
(b) the modified B/C method to determine which location , if either, should be
selected, using an in- terest rate of 12% per year. Assume that the park will be
maintained indefinitely.
Answer :
E WFirst Cost $ 3.000.000 $7.000.000Annual / Year $ 50,000 $ 65,000Revenue / Year $ 500,000 $ 700,000Disbenefit $ 30.000 $ 40,000
(a) Location E
AW = C = 3,000,000(0.12) + 50,000
= $410,000
Revenue = B = $500,000 per year
Disbenefits = D = $30,000 per year
Location W
AW = C = 7,000,000 (0.12) + 65,000 - 25,000
= $880,000
Revenue = B = $700,000 per year
Disbenefits = D = $40,000 per year
B/C ratio for location E:
(B – D)/C = (500,000 – 30,000)/410,000
= 1.15
Location E is economically justified. Location W is now incrementally compared
to E.
Δcost of W = 880,000 – 410,000
= $470,000
Δbenefits of W = 700,000 – 500,000
= $200,000
Incr disbenefits of W = 40,000 – 30,000
= $10,000
Incr B/C = (B – D)/C = (200,000 – 10,000)/470,000
= 0.40
Since incr(B – D)/C < 1, W is not justified. Select location E.
(b) Location E
B = 500,000 – 30,000 – 50,000 = $420,000
C = 3,000,000 (0.12) = $360,000
Modified B/C = 420,000/360,000 = 1.17
Location E is justified.
Location W
ΔB = $200,000
ΔD = $10,000
ΔC = (7 million – 3 million)(0.12)
= $480,000
ΔM&O = (65,000 – 25,000) – 50,000
= $-10,000
Note that M&O is now an incremental cost advantage for W.
Modified ΔB/C = 200,000 – 10,000 + 10,000 = 0.42
480,000
W is not justified; select location E.
9.26 Public service company of Texas is considering four size of pipe for a new
pipeline. The costs per kilometer (km) for each size are given in the table.
Assuming that all pipes will last 15 years and the company’s MARR is 8% per
year, which size pipe should be purchased based on a B/C analysis? Installation
cost is considered a part opf the initial cost.
140 160 200 240
Initial
investment,$/km
9,180 10,510 13,180 15,850
Installation cost,
$/km
600 800 800 1,500
Annual cost,
$/km
6,000 5,800 5,200 4,900
Answer :
Size 140 160 200 240
Total first cost 9,180+600 =
9,780
10,510+800 =
11,310
13,180+800 =
14,580
15,850+1,500
= 17,350
140 160 200 240Initial investment,$/km 9,18 10,51 13,18 15,85Installation cost,$/km 600 800 800 1,5Annual cost, $/km 6.000 5.800 5.800 4.900Annual Total Cost ( C ) 1142,6 1321,347 1703,381 2027,001Benefit ( B ) 6.000 5.800 5.200 4.900Overall B/C 5,25119 4,389459 3,052751 2,417365Alternative Compared 160-140 200-160 240-200Incremental Benefits ( ∆B ) 200 600 300Incremental Cost ( ∆C ) 178,7499 382,0341 323,6191∆B/C 1,118882 1,57054 0,927016Incremental Justified yes yes no
Pipeline Selected 160 200 200
160 - 140 mm
DC = (11,310 – 9,780)(A/P,8%,15)
= 1,530(0.11683)
= $178.75
DB = 6,000 – 5,800
= $200
DB/C = 200/178.75
= 1.12 > 1.0 Eliminate 140 mm size.
200 - 160 mm
DC = (14,580 – 11,310)(A/P,8%,15)
= 3270(0.11683)
= $382.03
DB = 5800 – 5200
= $600
DB/C = 600/382.03
= 1.57 > 1.0 Eliminate 160 mm size.
240 - 200 mm
DC = (17,350 – 14,580)(A/P,8%,15)
= 2770(0.11683)
= $323.62
DB = 5200 – 4900
= $300
DB/C = 0.93 < 1.0 Eliminate 240 mm size.
So Select 200mm