1.0 EXECUTIVE SUMMARY TABLE: 1 LIST OF … · 2017-02-20 · Ion Exchange India Ltd. Plot No....
Transcript of 1.0 EXECUTIVE SUMMARY TABLE: 1 LIST OF … · 2017-02-20 · Ion Exchange India Ltd. Plot No....
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 1
1.0 EXECUTIVE SUMMARY
M/s. Heubach Colour Pvt Ltd (Unit I) is located at plot no 9002-9010, GIDC Estate
Ankleshwar. The unit is having valid CCA order no. AWH - 73997, valid till 18/08/2021,
for manufacturing of Organic Pigments, Inorganic Chemicals & Pigments preparation
from Gujarat Pollution Control Board.A detail of existing product is mentioned in below
Table No.1.
TABLE: 1
LIST OF EXISTING PRODUCT
Sr.
No.
Name of Product Total
Quantity in
MT/M
1. CPC Green 250
2. Beta Blue/ Crude Blue 320
3. Alpha Blue 100
4. Dispersion/ Flushes/ Pigments Preparations
(for paints, Inks, Plastics)
900
5. Aluminium Hydroxide/ Hydrotelsite/ Boehmite 400
6. Aluminium Solution 500
7. Electricity (MW) 6.72 MW
8. Pigment Blue- 60 (Crude/ Finished) 50
9. Pigment Violet- 23 10
10. Pigment Red-177 10
Total 2546.72
1. Ammonium Liquor (100 %) 325
2. Soda Ash (100 700
3. Steam (TPH) 5
4. Ammonium Carbonate (100%) 325
5. Sodium Hydrochloride/ Bromide (100%) 50
Total 1405
The unit has proposed expansion for manufacturing of existing products.. Proposed
production capacity is mentioned in Table No.2.
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 2
TABLE: 2
LIST OF PRODUCTS AS PER PROPOSED SCENARIO
COST OF PROJECT
The expansion will be carried out at existing plot in GIDC Estate, Ankleshwar Gujarat.
The expected cost of proposed expansion is Rs. 216 Crore.
FUEL CONSUMPTION
Existing Fuel Consumption
As per consent, unit is using 1400 SCM/Hr. of Natural Gas and 4.2/4.8 MT/Hr.
Coal/Biofuel.
After proposed expansion, unit will use 2100 SCM/Hr. Natural gas, 10.2/4.8 MT/Hr.
Coal/Biofuel & diesel 1500 Liter/Hr.
ELECTRICITY CONSUMPTION
The unit have electricity from Daxin Gujarat Vij Company Limited (DGVCL). The
existing electricity consumption is 5100 KVA and electricity consumption due to
proposed expansion will be 4900 KVA. Total electricity requirement after proposed
expansion will be 10000 KVA.
Sr.
No. Product Name
Capacity (MT/Month ) Total
Quantity
After
Expansion
(MT/Month)
Existing Proposed
1 Organic Pigments 740 368 1108
2 Inorganic Chemicals 900 -308 592
3 Pigment Preparation 900 0 900
4 Inorganic Stabilizer 0 100 100
Total 2540 160 2700
5 Electricity 6.72 MW 5.9 MW 12.62 MW
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 3
WATER CONSUMPTION
Existing Water Generation
The source of water is GIDC water supply system. As per consent, the unit is using
(125KLD Domestic + 3130 KLD Industrial + 100 KLD Gardening) 3355 KLD
freshwater for industrial and domestic purpose.
Total Proposed scenario after Expansion
The total water consumption after expansion, the unit will use total 5722 KLD. 200 KLD
will be used for domestic purpose & 5532 KLD will be used for industrial purpose.
A detail of water consumption & water balance diagram is attached as Annexure – 8.
WASTE WATER GENERATION, TREATMENT & DISPOSAL
Existing Waste Water Generation
The existing waste water generation from industrial activities is 2537 KLD. The sewage
generation is 125 KLD. Treated effluent is sent to FETP, Ankleshwar and the sewage of
50 KLD is sent in soak pit/septic tank.
Proposed Waste Water Generation
Due to proposed expansion, additional total industrial effluent generation will be 1615
KLD. Hence, after expansion total industrial effluent generation will be 4152 KLD (2537
KLD existing + 1615 KLD proposed).
Due to proposed expansion, additional sewage generation will be 0 KLD. Hence, after
expansion sewage generation will be 125 KLD. Sewage will be treated into STP and
treated effluent will be reused into cooling tower and gardening purpose.
Sewage treatment plant water will be reuse in gardening & cooling tower. Boiler &
cooling tower blow down will be send in RO plant. RO permeate will be reuse in cooling
tower. ETP treated water will be partially subjected to RO plant and RO permeate
(140KLD) will be reuse in process. Unit will be discharge 3000 KLD.
GASEOUS EMISSION
Flue gas emissions
As per CCA Amendment order no. AWH-73997, a common stack is attached to Boiler
(16 TPH, Bio fuel/ coal based) and Hot Oil Generator (TFH) (50 Lack K cal/hr, bio fuel/
coal based) or two stack of Boilers (10 TPH & 6 TPH, Natural gas based) and one stack
of Hot Oil Generator (TFH) (50 Lack K cal/hr, Natural gas based). A stack is attached to
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 4
Hot Oil Generator (Natural Gas Basis). Five stack is attached to Power Plant Engines
(Natural Gas based) & Waste Heat Recovery Boiler (WHRB) (Natural Gas based).
For proposed expansion, a stack will be attached to Boiler (40 TPH, coal based) and two
stack will be attached to D. G. Sets (4000 KVA & 1500 KVA).
Process Emission
As per CCA AWH- 81685, five stack are attached to spin flash dryer and three stack are
synthesis vessel in blue plant. Three stack are attached to spin flash dryer and two stack
are chlorination vessel in green plant. Two stack are attached to spin flash dryer and two
stack are purification vessel in Aluminum Hydroxide plant. To control the process
emission from stack, bag filters and scrubbers is attached to the stack as APCM.
For proposed expansion, five stack will be attached to spin flash dryer and two stack will
be synthesis vessel in blue plant. Two stack will be attached to spin flash dryer and three
stack will be chlorination vessel in green plant. Two stack will be attached to spin flash
dryer and a stack will be purification vessel in Aluminum Hydroxide plant. To control the
process emission from stack, bag filters and scrubbers is attached to the stack as APCM
HAZARDOUS WASTE MANAGEMENT
Existing Hazardous Waste
As per CCA order no. AWH-66579, the hazardous wastes generation i.e. ETP waste (30
MT/Year), Spent Oil (250 Lit/Year), discarded bags & drum (2 MT/Month & 75
nos./Month) and Copper salt (20 MT/M), Dust From Air Filteration System (2
MT/Month), Spent carbon Dust From ETP (2 MT/Month), Used Membrane (10
Kg/Year), Used Granular Activated Carbon (10 MT/Day), Gypsum (1500 MT/Month) &
Spent sulphuric Acid (30 KL/Day), Used Batteries (25 Nos./Year) & Used Insulation
Material (10 Mt/Year). Mode of disposal is given in table no. 13.
Proposed Hazardous Waste
After proposed expansion, details of total quantity of hazardous waste generation are
covered here. The unit has proposed ETP waste (70 MT/Year), Spent Oil (50 Lit/Year),
discarded bags, drum & liner (5 MT/Month & 150 nos./Month) and Copper salt
(0MT/M), Dust From Air Filteration System (2.5 MT/Month), Spent carbon Dust From
ETP (5 MT/Month), Used Membrane (12 Kg/Year), Used Batteries (30 Nos./Year), Used
Insulation Material (15 MT/Year) & Contaminated papers, plastics, cotton etc (60
MT/Month). Mode of disposal is given in table no. 13.
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 5
2. INTRODUCTION
2.1 THE PROJECT
M/s. Heubach Colour Pvt Ltd (Unit I) has obtained CCA order AWH-73997, issue on
dated 02/01/2016 for manufacturing of Organic Pigments & Preparation & inorganic
chemicals. The unit has proposed expansion for manufacturing of organic Pigments &
Pigments preparations, Inorganic chemicals and Inorganic stabilizers/fillers.
As per EIA notification 2006, the proposed expansion is falling under category 5(f).
Since the project will be established in industrial estate, it is classified as category “B”
project and will be evaluated by the State Level Expert Appraisal Committee (SEAC).
2.2 PROJECT PROPONENT
The Heubach Group is a leading manufacturer of organic, inorganic & anti-corrosive
pigments and preparations having a global presence with marketing and manufacturing
facilities in Asia, Europe & United States. Heubach Group is a world leading independent
and globally active pigment manufacturer. A more than 200-year history of pigment
expertise in pigment production combined with ongoing innovation has enabled
outstanding growth of Heubach group in last few decades.
More than 1000 employees worldwide and a wide reaching network of strategically
located offices across six continents ensure global customers short delivery times and
flexible service. Our extensive product portfolio and team of technical specialists allow
for ideal solutions in adhesives, paints, coatings, printing ink, textile colorants, latex,
paper, plasters, plastics and other building markets.
2.3 NATURE OF PROJECT
The proposed unit is for pigments & preparations, Inorganic Chemicals, Inorganic
stabilizers/fillers manufacturing unit. The project is covered under the category of 5(f) in
schedule of EIA Notification-2006. This project falls under category ‘B’.
2.4 MARKET FEASIBILITY
Proposed expansion shall bring in additional quantity for domestic/export market.
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 6
3. PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
The proposed expansion project is for manufacturing of Organic Pigments &
preparations, Inorganic chemicals, Inorganic stabilizers/fillers.
3.2 PROJECT LOCATION
The proposed project site is located at plot no. 9002-9010, GIDC Estate, Ankleshwar 393
002, Gujarat. The approximate geographical positioning of the project site is at Latitude:
21°37'45.89"N, Longitude: 73° 2'50.65"E. The location of the project site can be
identified from the location map shown in Figure no.1, 2 & 3.
The salient features of the project site are presented in below table no.3.
TABLE: 4
SALIENT FEATURES OF THE PROJECT SITE
Sr.
No.
Particulars Details Distance
w.r.t site
K.M.
Direction
w.r.t site
1. Latitude 21°37'45.89"N -- --
2. Longitude 73° 2'50.65"E -- --
3. Climatic
Conditions
Maxi. Temperature: 45°C
Mini. Temperature: 13°C
-- --
4. Present land use at
the location
Ankleshwar G.I.D.C Area -- --
5. Taluka Ankleshwar -- --
6. District Bharuch -- WSW
7. State Gujarat - --
8. Nearest Railway
Station
Ankleshwar Railway Station Approx.
3
SW
9. Nearest Highway National Highway No. 8 4 KM ---
10. Nearest Airport Vadodara Airport Approx. 94
Km
---
12. Ecologically
sensitive zones
within 10-km
distance
Not present within 10 km
radius
-- --
13. Historical/
Archaeological
places
Not present within 10 km -- --
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 7
Sr.
No.
Particulars Details Distance
w.r.t site
K.M.
Direction
w.r.t site
14. National
Parks/Wild Life
Sanctuary
Not present within 10 Km -- --
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 7
FIGURE: 1
LOCATION OF THE PROJECT SITE
Ankleshwar Industrial area
Panoli Industrial area
Jhagadia industrial area
Priaman CETP
Canal
Piraman to Katiyajal Effluent Pipe
Jhagadia to Piraman CETP
Panoli toPiraman CETP
Diffuser Point
PROJECT SITE
M/s. Heubach Colour Pvt Ltd (Unit I), Ankleshwar
M/s. Jyoti Om Chemical Research Centre Pvt. Ltd. 8
FIGURE: 2
AERIAL VIEW OF THE 5 KM RADIAL PERIPHERY FROM THE PROJECT
SITE
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
3.3 SITE SELECTION
The project proponent did not consider any other alternative site for proposed expansion.
3.4 NEIGHBOURING INDUSTRIES
TABLE: 4
DETAILS OF NEIGHBOURING INDUSTRIES
Sr.
No.
Name of Industry Address Directions Distance
(meter)
1. Sajjan India Ltd. Plot No. 6102-3, GIDC Estate,
Ankleshwar, Gujarat 393002
West 50
2. Ion Exchange India
Ltd.
Plot No. 811-12-13, , GIDC
Estate, Ankleshwar, Gujarat
393002
North East 200
3. Ratnamani
Biochem &
Pharmaceutical
Pvt. Ltd.
Plot No. 6112, GIDC,
Ankleshwar
South
west
100
4. BASF India Ltd. Plot No. 8001, GIDC,
Ankleshwar
South 100
3.5 SIZE OF PROJECT
The unit has proposed expansion of manufacturing of synthetic organic pigments.
Environment protection and safety systems have also been considered in planning the
cost projection. The unit has proposed to set up effluent treatment plant which will be
maintained as per requirements. The break-up of the proposed project cost is given in
below Table No. 5.
TABLE: 5
CAPITAL COST PROJECTION
Sr.
No.
Purpose Proposed
(Rs. In Lacs)
1. Land -
2. Building 4100
3. Plant and Machinery 16389
4. Q.A. Lab Set Up 100
5.
Environment Protection & Safety -
a) Effluent treatment Plant 700
b) Safety Equipment (PPE, fire
extinguishers, Ventilation, etc.)
100
c) Green belt development 11
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
d) Fire 200
Total 21600
3.6 PROCESS TECHNOLOGY
Process details like process description for each grade of products are covered separately
in Annexure-6.
3.7 RAW-MATERIALS
The expansion products are organic & inorganic pigment and the required raw materials
will be purchased from the local/ Indian/ Global market. Details of raw-material
consumption are covered in Annexure-5.
3.8 RESOURCE OPTIMIZATION/RECYCLING AND REUSE
Unit will be recovered 96 % Solvent. Sewage treatment plant water will be reuse in
gardening & cooling tower. Boiler & cooling tower blow down will be send in RO plant.
RO permeate will be reuse in cooling tower. ETP treated water will be partially subjected
to RO plant and RO permeate will be reuse in process.
3.9 RESOURCE REQUIREMENTS
3.9.1 LAND
The plot has been purchased by Heubach Colour Pvt Ltd. The total plot area is 110385.40
Sq.meter.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
3.9.2 ELECTRICITY AND FUEL
TABLE: 6
ELECTRICITY AND FUEL REQUIREMENT
3.9.3 WATER
The category wise bifurcation of the water requirement is given in below Table No.7. The
source of water will be from GIDC water supply scheme.
TABLE: 7
DETAILS OF WATER CONSUPTION
Sr.
No.
Particulars Present
requirement
Proposed
requirement
Total
requirement
Remark
1 Electricity 5100 KVA 4900 KVA 10000 KVA Will be met
through
Electricity
company
2. Coal/Biofuel 4.2/4.8
MT/Hr
6/0 MT/Hr 10.2/4.8
MT/Hr
Local
suppliers
2 Natural gas 1400 scm/Hr 700 scm/Hr 2100
scm/Hr
Will be
supplied by
Gujarat Gas
company
Ltd.
3 Diesel (4000 &
1500 KVA in
case of power
failure, DG set
will be operated)
0 Lit/hour 1500 Lit/hour 1500
Lit/hour
Local
suppliers
Sr.
No.
Particular Water Consumption in KL/Day
Existing Proposed After Expansion
1. Domestic 125 75 200
2. Industrial
a) Process 2730 1032 3762
b) Washing
c) Boiler 200 900 1100
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
3.9.4 MANPOWER
The manpower required for the project as well as during the construction/ commissioning
activities will be employed from the local area. The preference will be given to local
people.
TABLE: 8
MAN POWER REQUIREMENT
3.10 MITIGATION MEASURES & EMP
Based on overall manufacturing & operation activities, the mitigation measures have
been proposed by the company for the control of the anticipated pollution load.
3.10.1 WASTEWATER MANAGEMENT
WASTEWATER GENERATION
Details of Effluent Treatment Plant and Flow Diagram are attached as Annexure-7.
The category-wise bifurcation of the anticipated wastewater generation details is given in
below Table No.9.
d) Cooling 200 450 650
e) Gardening 100 -80 20
Total
(Domestic + Industries) 3355 2377
5732
Phase of project Type of Labour No. of workers
(Proposed Scenario)
During construction Contractual Workers 100
During operations
Technical Management Level 43
Administration Manager Level 46
Technical skilled staff 390
Un-skilled staff 343
Others-security, gardeners, etc 33
Total during operation phase 855
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
TABLE: 9
DETAILS OF WASTE WATER GENRATION
*Unit will install STP and treated water will be used for gardening & cooling tower
purpose.
** Cooling tower blow down and boiler blow down will be subjected to RO & 25 KL
reject will be discharged through ETP.
WASTEWATER CHARACTERISTICS
Industrial wastewater will be generated from process, washing, cooling tower blow down
and boiler blow down. The expected characteristics of industrial wastewater are provided
in below Table No.10.
TABLE: 10
CHARACTERISTICS OF WASTEWATER
Sr.
No. Parameters Units
Standards
prescribed
Before
Treatment After Treatment
1 pH -- 6.5 to 8.5 6 to 9 6.5 – 8.0
2
Total
Dissolved
Solids
mg/l - 5000-10000 5000 – 10000
3 Ammonical
nitrogen mg/l 50 10 -15 < 50
4 B.O.D.5
days at 20°C mg/l 30 400 – 500 < 200
5 C.O.D. mg/l 100 1500-3000 <500
Sr.
No.
Particular Wastewater generation in KL/Day
Existing Proposed After Expansion
1. Domestic 125 -125 0
2. Industrial
a) Process 2337 1615 3952
b) Washing
c) Boiler 100 0 100
d) Cooling 100 0 100
e) Gardening 0 0 0
f) Other
Total
(Domestic + Industries) 2663 1590 4152
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
3.10.2 GASEOUS EMISSIONS & CONTROL
3.10.2.1 FLUE GAS EMISSION
Details of flue gas emission, stacks height are covered in following Table no. 11.
TABLE: 11
EXISTING FLUE GAS EMISSIONS
SR.
NO
SOURCE
OF
EMISSION
STACK
HEIGHT
(METER)
FUEL
NAME
AND Qty.
TYPE OF
EMISSION
PERMISSI
BLE
LIMIT
APCM
Existing
1
Boiler
(16TPH)
(Bio
Fuel/Coal
based)
52
Biofuel/Co
al: 2.8/3.2
TPH
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
ESP +
Water
Scrubber
2
Hot Oil
Generator (50
Lack k cal
TFH) (Bio
Fuel/Coal
based)
Biofuel/Co
al: 1.4/1.6
TPH
OR
3
Boiler
(10TPH &
6TPH)
(2 Nos. Stack)
(Natural Gas
Base) 30
1200 M3/hr
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
-----
4
Hot Oil
Generator (50
Lack k cal
TFH)
(Natural Gas
Base)
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
5
Hot Oil
Generator
(Natural Gas
Basis)
30
200 M3/hr
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
---
6
Power Plant
Engines
(5Nos. of
stack)
(Natural Gas
Base)
16
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
WHRB (5
Nos. of Stack) 16
PM
150
mg/Nm3 ---
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
TABLE: 12
PROPOSED FLUE GAS EMISSIONS
(Natural Gas
Base)
SO2
NOx
100 ppm
50 ppm
SR.
NO
SOURCE OF
EMISSION
STACK
HEIGHT
(METER)
FUEL
NAME
AND Qty.
TYPE OF
EMISSION
PERMI
SSIBLE
LIMIT
APCM
After Expansion
1
Boiler (16TPH)
(Bio Fuel/Coal
based)
52
Biofuel/C
oal:
2.8/3.2
TPH
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
ESP +
Water
Scrubber
2
Hot Oil
Generator (50
Lack k cal
TFH) (Bio
Fuel/Coal
based)
Biofuel/C
oal:
1.4/1.6
TPH
OR
3
Boiler
(10TPH &
6TPH)
(2 Nos. Stack)
(Natural Gas
Base) 30
1200
M3/hr
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
-----
4
Hot Oil
Generator (50
Lack k cal
TFH) (Natural
Gas Base)
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
5
Hot Oil
Generator
(Natural Gas
Basis)
30
200 M3/hr
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
---
6
Power Plant
Engines (5Nos.
of stack)
(Natural Gas
Base)
16
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
WHRB (5 Nos.
of Stack)
(Natural Gas
Base)
16
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
---
7 Boiler (40 TPH)
(coal Based) 60
Coal: 6
TPH
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
ESP +
Water
Scrubber
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
3.10.2.2 PROCESS GAS EMISSIONS
The process emissions from the manufacturing activities are given in following Table.
The details of air pollution control system are also mentioned in Table no.13.
TABLE: 13
EXISTING & PROPOSED PROCESS GAS EMISSIONS AND CONTROL
MEASURES
Details of Process Stack as per CCA: AWH 73997
Sr.
No
APCM attached to Stack
Height
Air Pollution
Control Measure
Parameter Permissible
Limit
1 Blue Plant
Spin Flash Dryer (5
Nos. of Stack)
12 Bag Filter PM 150 mg/NM3
Synthesis Vessel (3
Nos. of Stack)
12 Scrubber Ammonia 175 mg/NM3
2 Green Plant
Spin Flash Dryer (3
Nos. of Stack)
18 Bag Filter PM 150 mg/NM3
Chlorination Vessel
(2 Nos. of Stack)
18 Water & Alkali
Scrubber
HCL
CL2
20 mg/NM3
09 mg/NM3
3 Aluminum
Hydroxide
Spin Flash Dryer (2
Nos. of Stack)
20 Bag Filter PM 150 mg/NM3
Purification Vessel
(1 Nos. of stack)
27 Alkali Scrubber H2S 45 mg/NM3
8. DG SET (4000
KVA) 12
1100
ltr/Hr
PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
---
9. DG SET (1500
KVA) 9
400 ltr/Hr PM
SO2
NOx
150
mg/Nm3
100 ppm
50 ppm
---
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
Details of Process Stack after Expansion
Sr.
No
APCM attached to Stack
Height
Air Pollution
Control Measure
Parameter Permissible
Limit
1 Blue Plant
Spin Flash Dryer
(10 Nos. of Stack)
12 Bag Filter PM 150 mg/NM3
Synthesis Vessel
(5 Nos. of Stack)
12 Scrubber Ammonia 175 mg/NM3
2 Green Plant
Spin Flash Dryer
(5 Nos. of Stack)
18 Bag Filter PM 150 mg/NM3
Synthesis Vessel
(5 Nos. of Stack)
18 Water & Alkali
Scrubber
HCL
CL2
20 mg/NM3
09 mg/NM3
3 Inorganic (Al
Hydroxide)
Spin Flash Dryer
(4 Nos. of Stack)
20 Bag Filter PM 150 mg/NM3
Purification Vessel
(3 Nos. of stack)
27 Alkali Scrubber H2S 45 mg/NM3
3.10.2.3 FUGITIVE EMISSIONS
Following steps will be taken to control fugitive emissions:
• All reactions will be taken in closed loop reactor system.
• The fugitive emissions in terms of handling losses will be reduced by proper
storage and handling. Raw-material feeding will be carried out by pumps. There
will be no manual handling.
• Regular monitoring will be done of piping and fittings for checking of any
leakages.
• Good housekeeping will be maintained in the plant.
3.10.3 HAZARDOUS/ NON-HAZARDOUS WASTE MANAGEMENT
The following type of hazardous waste will be generated from the operational activities.
All the waste will be stored separately in a designated storage area.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
TABLE: 14
DETAILS OF HAZARDOUS WASTE
Sr.
No. Type of Waste
Qty. Total
quantity
after
expansion
Disposal method Existing Proposed
1 ETP Sludge 30 MT/Day 40 MT/Day 70 MT/Day
Collection,
storage,
Transportation &
Disposal by send
to TSDF-
BEIL/SEEPL
Kutch/sell
Authorized to
Cement
Industries.
2 Discarded
Bags/Drums/Liner
2 MT/M or
75 Nos./M
3 MT/M or
75 Nos./M
5 MT/M or
150 Nos./M
Collection,
Storage, Reuse &
Decontamination,
Disposal to
TSDF, or send to
GPCB authorized
Re-processor.
3 Spent Oil 250 Lit/M 50 Lit/M 300 Lit/M
Collection,
storage,
Transportation &
Disposal by sell
CPCB authorized
Re-Processors
4 Copper Salt 20 MT/M -20 Mt/M 0 Mt/M
Collection,
storage,
Transportation &
Disposal by sold
to authorize
industrial users.
5 Dust From Air
Filteration System 2 MT/M 0.5 MT/M 2.5 MT/M
Collection,
storage,
Transportation
Recovered &
Reprocessed.
6 Spent carbon Dust
From ETP 2 MT/M 3 Mt/M 5 Mt/M
Collection,
storage,
Transportation &
Disposal at
TSDF-
BEIL/SEPPL
Kutch for land
Fill.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
Sr.
No. Type of Waste
Qty. Total
quantity
after
expansion
Disposal method Existing Proposed
7 Used Membrane 10 kg/Year 2 kg/Year 12 kg/Year
Collection,
storage,
Transportation &
Disposal at
TSDF-BEIL for
land Fill.
8 Used Granular
Activated Carbon 10 MT/Day 0 10 MT/Day
Collection,
storage,
Transportation &
Disposal by send
to GPCB
approved industry
for regeneration /
reactivation.
9 Gypsum 1500 MT/M 0 1500 MT/M
Collection,
storage,
Transportation &
Disposal at
TSDF-
BEIL/SEPPL,
Kutch/sell to
authorized
Cement
Manufacturers.
10 Spent sulphuric
Acid 30 KL/Day 0 30 KL/Day
Collection,
storage,
Transportation &
Disposal By Sell
to Authorized
industrial
Reusers.
11 Used Batteries 25
Nos./Year 5 Nos./Year 30 Nos./Year
Collection,
storage,
Transportation &
Disposal by return
back to supplier.
12 Used Insulation
Material 10 Mt/Year 5 Mt/Year 15 Mt/Year
Collection,
storage,
Transportation &
Disposal by
Return back to
Supplier.
13 Contaminated
papers, plastics,
cotton etc
0 60 MT/Year 60 MT/Year Collection,
storage, and
transportation &
final disposal by
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
Sr.
No. Type of Waste
Qty. Total
quantity
after
expansion
Disposal method Existing Proposed
incineration at
BEIL
In addition to the provision of above, the unit will ensure proper management for
hazardous waste as below:
Transportation of hazardous waste to the TSDF Site will be governed as per the
guidelines and accompanied with Form-13. Annual returns of the disposal of wastes in
Form-4 will be uploaded online and submitted regularly to the local office of the GPCB.
3.10.4 NOISE CONTROL & ODOUR
The major noise generating installation will be the D.G. Set. However, DG Set will be
provided with Canopy for control of Noise pollution. Ear plugs will also be provided to
the operating personnel in boiler room.
The following steps will be taken for odour control.
• Raw-material feeding will be carried out by pumps.
• All reactions will be taken in closed reactor loop system.
• Roof top ventilation will be provided in the entire plant area.
• Regular monitoring will be done of piping and fittings for checking of any
leakages.
3.10.5 STORAGE, HANDLING AND TRANSPORT OF HAZARDOUS
CHEMICALS
The storage and mode of transport of chemicals will be done as per detailed MSDS and
Chemical hazards guide (NIOSH) for the hazardous chemicals.
Few chemical to be used in the proposed activities are listed as ‘Hazardous Chemicals’ as
per the Schedule-1 of the MSIHC Rules, as amended in 2000.
3.10.6 HEALTH AND SAFETY MEASURES
Few chemical to be used in the proposed activities are listed as ‘Hazardous Chemicals’ as
per the Schedule-1 of the MSIHC Rules, as amended in 2000.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
Physical hazards may manifest as fires, explosions, excessive temperatures, or the release
of large volumes of gas or toxic or flammable gases or vapors. According to Schedule 2
& 3 of MSIHC Rules.
Moreover transport activity will be through drums, so there will be manual loading and
unloading and no unloading through pipe at the site. Hence, the risk of static charge
generation during transfer of such chemicals is not significant.
4. SITE ANALYSIS
4.1 CONNECTIVITY
The site is located at Plot No.9002-9010, GIDC Estate, Ankleshwar, Gujarat. The land
and Infrastructure is already available and the raw materials are easily available through
the easy transport via road connectivity.
Ankleshwar Industrial Estate was set up by Gujarat Industrial Development Corporation
in early 70s. This industrial estate is spread over an area of 1600 hectares in close
proximity to National Highway No.8 and Delhi-Mumbai Railway Line. Being an ideal
location for industrialization, as on date, more than 1500 industries, consisting of
chemicals, pesticides, pharmaceuticals, bulk drugs, petroleum products, engineering,
textiles, plastics, rubber and packaging etc. are located in this industrial estate.
The town is known for its industrial township called GIDC (Gujarat Industrial
Development Corporation). Ankleshwar has an office of the ONGC (Oil and Natural Gas
Corporation Limited). GIDC is organizing Trade fare and Industrial expo occasionally to
attract large number of industries all over from India. It also helps to get customer on
large basis.
4.2 LAND USE AND LAND OWNERSHIP
The project site is located at Plot No 9002-9010, GIDC Estate, Ankleshwar Gujarat. The
plot had been purchased by M/s. Heubach Colour Pvt Ltd (Unit 1) from GIDC. The total
plot area of the unit is 110385.40 Sq.meter.
4.3 LAND USE
The proposed project site is located at Plot No 9002-9010, GIDC Estate, Ankleshwar,
Gujarat. The plot is notified by GIDC for industrial purpose.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
4.4 EXISTING INFRASTRUCTURE
The plant is located in a well-developed industrial zone, which will have all essential
facilities such as internal roads, arrangement for supply of water and power to industries,
effluent disposal facilities etc.
4.5 CLIMATE DATA
Based on the meteorological data, wind rose have been prepared for the summer season
period between the October 2016 to November 2016. The wind rose diagram prepared
from same data is shown at Figure 6.
TABLE: 15
METEOROLOGICAL DATA
Month -- Temp. (°C) Relative
Humidity (%)
Wind Speed
km/hr
October-16 Min. 23 28 0
Max. 35 94 13
Average 29 61 6.5
November-16 Min. 20 24 0
Max. 34 51 10
Average 27 37.5 5
December-16 Min. 17 23 0
Max. 32 52 11
Average 24.5 37.5 5.5
FIGURE: 3
WIND ROSE DIAGRAM FOR PERIOD OF OCTOBER-2016 TO DECEMBER -
2016
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
Observation: It was observed that wind is blowing mainly towards the SW direction
from NE. average wind speed was 2.38 m/s with calm winds recorded to be 10.6%.
4.6 SOCIAL INFRASTRUCTURE
Population density and sex ratio of Bharuch District was reported 238 persons/sq.km. and
920 females per 1000 males respectively in 2011 census report. Total literacy of Bharuch
District was found 81.51 %.The basic amenities like primary and secondary education
schools, community health workers, primary health sub centre, private practitioners,
primary health centre, maternity and child welfare, dispensaries, T.B clinic, family
welfare centre, hospital, drinking water, transportation facilities, electricity , telephone
etc. are available.
5.0 PLANNING BRIEF
5.1 PLANNING CONCEPT
Ankleshwar is largely an industrial area dominated by large scale industries, especially
chemical plants& Pharmaceutical plants. Now the unit has proposed for expansion
Ankleshwar in Gujarat has an industrial area with common effluent treatment plant,
common incinerator and land fill site. Govt. agencies provide many basic facilities like
uninterrupted water supply, power and road network.
5.2 POPULATION PROJECTION
As per provisional reports of Census India, Population of Bharuch District in 2011 is
1,551,019. Population of male and female are 805,707 and 713,676 respectively. The sex
ratio of Bharuch city is 920 females per 1000 males.
In education section, total literates in Vadodara District are 2,893,080 of which 1,614,087
are males while 1,278,993 are females. Average literacy rate of Vadodara district is
78.92%.
5.3 LAND USE PLANNING
Details will be covered in EIA report.
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND
The M/s. Heubach Colour Pvt Ltd (Unit I) shall get water from GIDC water supply
scheme. So there will be no additional stress on ground water resources and there will be
no adverse effect on the ground water resources available in the nearby area.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
The unit has total proposed 10000KVA connected load from GEB. The transportation
facilities will also expect to improve due to increase in the movement of workers and raw
material and finished products.
5.5 AMENITIES
The available basic amenities are as under:
(A) Education Facilities:
All the villages have a minimum of one primary school.
(B) Medical Facilities:
All the surrounding villages have medical facilities.
(C) Drinking water Facilities & Power Supply:
All the villages have potable water supply and in 100% area the drinking water is
supplied through taps, wells and tube wells. All the villages have power supply facilities
in the study region.
(D) Post, Telegraph & Telephone facilities
The information collected clearly indicates that the infrastructural facilities are provided
by respective government agencies for the development of this area. For communication
purpose, post office and phones are available in most of the villages.
(E) Transport Facilities:
Bus services are available in all the villages of the study region within 5 km area and are
the most preferable mode of transport in the region. Auto-rickshaw is also used as
transport facility. Villages are connected with paved roads. All the surrounding area is
covered with 108 emergency facilities.
6.0 PROPOSED INFRASTRUCTURE
6.1 PROCESSING AREA
The process area will cover plant area, raw material storage area, Hazardous waste
storage area, ETP, utilities etc. The process area covered by the unit at ground level will
be 49078 sq. m.
6.2 NON PROCESSING AREA
The non process area will green belt, office and security cabin etc. The non process area
covered by unit at ground level will be around 61307.4 sq. m.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
6.3 GREEN BELT
The unit having existing green belt area 19555 sq.m within premises & 4078 outside.
6.4 SOCIAL INFRASTRUCTURE
The availability of basic amenities is covered as under:
Training & Education: All the employees will be trained and educated periodically
about the hazardous nature of chemicals used in the process. Also, training for fire
fighting, work permits system, first aid, safe handling of hazardous chemicals and
integrating safety, in all activities.
Medical facility: Pre-employment medical checkup at the time of employment. In order
to safe guard the health of the employees, all the employees undergo periodic health
checkup.
Drinking water: There will be provision of Aqua Guard/R.O. at different places to
provide purified water for drinking purpose.
Transportation: The unit will provide basic transportation facility for workers.
Telegraph & Post: There will be provision of telephone, fax & internet facility.
Power supply: At present, the unit has 5100 KVA connected load. Additional 4900
KVA connected load for proposed expansion. The unit will use total 10000 KVA
electricity connected load from GEB.
6.5 DRINKING WATER MANAGEMENT
The source of water is already availability from existing water works of GIDC and the
same is adequate and satisfactory. The unit has proposed additional 75 KL/Day water for
domestic purpose.
6.6 SEWERAGE SYSTEM
Sewage water will be sent to Sewage treatment plant.
6.7 INDUSTRIAL WASTE MANAGEMENT
The hazardous waste like Chemical Sludge from Waste Water Treatment, Discarded
Containers/barrels/Liners used for HW/Chemicals, and Used/Spent Oil will be generated
from proposed project activity. The hazardous waste management and disposal is shown
in Table No.13.
6.8 SOLID WASTE MANAGEMENT
The record of nonhazardous solid waste like paper waste, wooden waste, etc. will be
mentioned.
M/S. HEUBACH COLOUR PVT. LTD.(UNIT III), ANKLESHWAR
M/s. Jyoti Om Chemical Research Centre Pvt Ltd
6.9 POWER REQUIREMENT & SUPPLY
At present, the unit has 5100 KVA connected load. Additional 4900 KVA connected load
for proposed expansion. The unit will use total 10000 KVA electricity connected load
from GEB. Unit will install captive power plant and partially power from captive power
plant will be utilized in Heubach Colours Pvt. Ltd. (Unit 1) and Heubach Colours Pvt.
Ltd. (Unit 3).
7.0 REHABILITATION AND RESETTLEMENT(R &R) PLAN
The proposed project is located in GIDC Industrial Estate Ankleshwar, Gujarat. There
will be no any human settlement affected by proposed project. So, there is no requirement
of any R & R Plan.
8. PROJECT SCHEDULE & COST ESTIMATES
8.1 PROJECT IMPLEMENTATION SCHEDULE
TABLE: 16
PROJECT IMPLEMENTATION SCHEDULE
Project implementation schedule after getting NOC from GPCB
Sr.
No.
Activity Required Period
1. Procurement of machinery Immediately after getting NOC
2. Erection & installation of
machinery
18 month after getting NOC
3. Trial of machinery &
equipments
Immediately after completion of activity
no.2
4. Commercial activity 1 months after completion of activity no.3
8.2 ESTIMATED PROJECT COST
Project cost for proposed expansion will be 216 Crore. Details for estimated project cost
are covered in Table no 5.
9. ANALYSIS OF PROPOSAL
All the manpower is utilized from local region around Ankleshwar. Company shall also
try to provide indirect employment opportunities by availing local contract services
during transportation during operational phase.
The company intends to donate 5 % of the capital cost to agencies like NGOs or social
welfare societies for projects carried out in nearby village for their welfare and
upliftment.