1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION...

30
1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

Transcript of 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION...

Page 1: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

1

Turkish Power System Overview

27-28 March 2012

TURKISH ELECTRICITY TRANSMISSION CORPORATION

(TEIAS)

Page 2: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

2

TURKISH POWER SYSTEM

- NUMBER OF SUBSTATIONS

- 400 kV 78

- 220 kV 2

- 154 kV 520

- 66 kV 14

TOTAL: 614 (103.100 MVA)

LENGTH OF TRANSMISSION LINES

- 400 kV 15830 km

- 154 kV 32513 km

- 220 kV 85 km

- 66 kV 508 km

- 154 kV and 400 kV cable length 220 km

- TOTAL 49.159 km

Page 3: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

3

INSTALLED CAPACITY & PEAK LOAD

Installed Capacity : 53.235 MW

Renewable(hydro,wind,jeo.) : 36 %Thermal : 64%

Peak Load (2010) : 33.392 MW

Peak Load (2011 July) : 36.122 MW

THERMAL 34210; 64,3%

HYDRO17160; 32,3%

WIND1687; 3,2% OTHERS

115; 0,2%

INSTALLED CAPACITY (DECEMBER 2011)

THERMAL HYDRO

WIND OTHER RENEWABLES

Page 4: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

4

GENERATION FOR 2011

Total : 229,3 TWh

Thermal : 73,7 %

Renewable : 26,3 %

Page 5: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

5

CONSUMPTION

  1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

2011

Consumption(TWh) 114,0 118,5 128,3 126,9 132,6 141,2 150,0 160,8 174,6 190,0 198,1 194,1 210,4 228

İncrease (%) 8,1 3,9 8,3 -1,1 4,5 6,5 6,3 7,2 8,6 8,8 4,3 -2,0 8,4 9,0

Page 6: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

6

PEAK LOAD AND ELECTRICITY CONSUMPTION 2001-2020

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

55000

60000

65000

70000

2001 2002 2003 2004 2005 2006 2007 2008 2009 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

MW

0

50000

100000

150000

200000

250000

300000

350000

400000

450000

GW

h

TÜKETİM (GWh) SENARYO 1 ENERJİ TALEBİ SENARYO 2 ENERJİ TALEBİ

PUANT YÜK (MW) SENARYO 1 PUANT TALEP SENARYO 2 PUANT TALEP

Page 7: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

7

7

INTERCONNECTIONS (Existing Situation)

BULGARIA145 km 400kV

136 km 400kV

GREECE130 km 400kV

SYRIA124 km 400kV

IRAN 73 km 154kV100 km 400kV

NAHCİVAN87 km 154kV

GEORGIA28 km 220kV160km 400kV

ARMENIA80,7 km 154kV

400 kV Existing400 kV Underconstruction220 kV Existing154 kV Existing

IRAQ42 km 400kV

KKTC

400 MW

300 MW

15-8

0 M

W

40 MW40 MW

0 MW380MW

TÜRKİYE

0 MW

150 MW

Page 8: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

8

8

PLAN FOR 2013

BULGARIA145 km 400kV

136 km 400kV

GREECE130 km 400kV

SYRIA124 km 400kV

IRAN 73 km 154kV100 km 400kV

NAHCEVAN87 km 154kV

GEORGIA28 km 220kV160km 400kV

ARMENIA80,7 km 154kV

IRAQ42 km 400kV

KKTC

1200 MW

1200MW

700 M

W

500 MW

TÜRKİYE

0 MW

350 MW

350

MW

If ENTSO-E connection will be approved

40 MW40 MW

400 kV Existing400 kV Underconstruction220 kV Existing154 kV Existing

Page 9: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

9

9

PLAN FOR 2015

BULGARIA145 km 400kV

136 km 400kV

GREECE130 km 400kV

SYRIA124 km 400kV

IRAN 73 km 154kV100 km 400kV

NAHCEVAN87 km 154kV

GEORGIA28 km 220kV160km 400kV

ARMENIA80,7 km 154kV

400 kV Existing400 kV Under Construction220 kV Existing154 kV Existing

IRAQ42 km 400kV

KKTC

1200 MW

1200MW

700 M

W

600 MW

TÜRKİYE

Planning

phase

600 MW

350 M

W

40 MW

40 MW

If ENTSO-E connection will be approved

Page 10: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

10

UCTE/ENTSO-E

• Trial Run period started with ENTSO-E on 18th of September 2010.

• The first phase system stability tests approved by

ENTSO-E Planary Group on 8th of February.

• Without any trade Import-Export tests for the second phase found successfull by ENTSO-E.

• The third phase (import-export with trade) related with the synchronous parallel operation of Turkey with European Power System started on 1th of June 2011 and it will be ended on September 2012.

• Trade will be limited with 400 MW from Bulgaria and Greece to Turkey; 300 MW from Turkey to Europe via these countries.

Page 11: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

11

POWER PLANTS CONNECTION REQUESTS( December 2011)

MW

POWER PLANTS CONNECTION REQUESTS

HPP WPPTPP

TOTAL

NGCCP Other

CAPACITY APPROVED BY TEİAŞ 4.741 2.528 24.250 7.838 39.357

CAPACITY HAS BEEN LICENCED BY EMRA 10.114 5.066 5.765 2.715 23.660

CAPACITY HAS CONNECTION AGREEMENT BY TEİAŞ 6.473 3.464 5.715 6.391 28.267

TOTAL 21.328 11.058 35.730 16.944 85.060

Page 12: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

The Turkey’s Parliament approved a new law 29 December 2010, on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of:

• 7.3 U.S. cents per kWh for wind energy and hydroelectric power, • 10.5 US cents for geothermal energy and • 13.3 US cents for energy from waste products and solar energy• These prices will cover energy firms that are established between May 13, 2005 and Dec.

31, 2015. • For energy purchases from companies founded later than Dec. 31, 2015, new prices defined

by the Cabinet will be implemented. The prices for the new companies will not exceed the current figures, the law said.

• In the event that operators use local equipment and technology in renewables energy facilities, an additional support of 0.4 cents to 2.4 $ per kw will be provided for a five year term to companies that started producing energy before the end of 2015.

• The surplus generation from the renewables will be bought by the distribution companies for ten years guarantee with the defined energy prices.

• The law limits the total production of licensed solar energy with 600 MW until the year of 31 December 2013 and authorizes the cabinet to determine the limits afterwards.

INCENTIVES FOR RENEWABLE POWER PLANTS

Page 13: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

13

1 NOVEMBER 2007

78.000 MW TOTAL OVERLLAPPING APPLICATIONS

?

SINGULAR APPLICATIONSAND LICENCE – CONNECTION TO THE GRID3500MW CAPACITY ALLOCATED

-TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID?

-EVALUATING OVERLAPPING WPP’S APPLICATION?

WPP INTEGRATION PROCESS TO THE GRID

Page 14: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

14

Wind Power Plants

Page 15: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

15

WPP INTEGRATION PROCESS TO THE GRID

TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID?

Page 16: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

16

WPP INTEGRATION PROCESS TO THE GRID

DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM

•Evaluation of the available wind power capacity can be connected to the system

•Power Flow studies

• Evaluation of wind variability on the effect of power flow and local grid

•Planning the investment of basin substation and transmission lines

Page 17: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

17

APPLICATION 78.000 MW

APPLIED APPROACHES IN THE WORLD

-Integration to the 1/3 ratio to the demand of system minimum

-Integration to the 25% ratio to the demand of system maximum

2013 Estimated MinimumSystem Peak

2013 Estimated MaximumSystem Peak

18.703 MW 46.757

6.727 MW (1/3 of Peak ) 11.689 MW (25% of Peak)

-TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID?

WPP INTEGRATION PROCESS TO THE GRID

Page 18: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

18

WPP INTEGRATION PROCESS TO THE GRID

DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM

NEGATIVE EFFECTS OF WIND POWER PLANTS ON GRID

- FAULT-RIDE TROUGH CAPABILITY OF WPP’S

-FLICKER (Turbulence/Output Power Source)

-VOLTAGE FLUCTUATION(Cause of Output Power fluctuation and insufficient of reactive power support)

-HARMONICS( Cause of Power Electronic Equipments)

Figure: Variable of wind generation

Page 19: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

19

Wind Power Plants

0

20000

40000

60000

80000

100000

120000

MW

YEARS

INSTALLED CAPACITY AND PEAK LOAD OF TURKEY ACCORDING TO THE YEARS AND AVAILABLE RENEWABLE CAPACITY CAN BE CONNECTED TO THE SYSTEM

PEAK DEMAND

INSTALLED CAPACITY

CONNECTABLE RENEWABLE CAPACITY

Page 20: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

20

• Process:

1. The available capacity of substations for connecting wind powerplants are published by TEİAS.

2. WPP applications are forwarded to TEIAS for studying connection opportunities.

3. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications.

4. If there are multiple applications in one substation, compitition process is done by TEIAS to determine the owner of the capacity.

5. After taking license the investor sign a connection agreement with TEIAS.

6. Project will be approved by MENR. After the realization of the project System Usage Agreement will be signed by TEIAS.

QUEUE MANAGEMENT OF WIND POWER PLANTS

Page 21: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

21

Competitions

competition organisation

number of invited companies

number ofsubstations

number of winnercompanies

total connection capacity (MW)

1 27 12 16 626

2 11 5 6 281

3 26 8 8 500

4 31 3 8 395

5 30 8 9 520

6 38 8 16 289,4

7 46 6 15 427

8 54 6 12 607

9 41 3 4 74

10 37 5 9 217

11 175 16 31 1199

12 33 4 7  198

13 47 3  6 166

TOTAL 596 87 147 5500

Weighted average of the competition prices is 1,91 kurus/kwh

Page 22: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

22

Winner prices and installed capacities

2215,7 MW%40

427 MW%8

605,5 MW%11

225,5 MW%4

816,6 MW%15

728 MW%13

481 MW%9 0 - 0,5

krş/kWh

0,5-1krş/kWh

1-2 krş/kWh

2-3 krş/kWh

3-4 krş/kWh

4-5 krş/kWh

5- krş/kWh

Winner prices according to installed capacity

Page 23: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

23

Future Problems

• What will be the operation problems if ~11000 MW wind power plant will be in service ?

• Wind applications are concentrated in west side of Turkey. This will cause excessive voltage changes in the region

• Effective regional voltage control ;

• Effective secondary reserve control

• Effective ENTSO-E interconnection tie line control will be needed

• All these issues can be managed by an effective wind forecast and monitoring system

Page 24: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

24

WPP INTEGRATION PROCESS TO THE GRID

U,

Lin

e V

olta

ge(p

.u)

Time, milisecond

0 150 700 1500 3000

1.0

0.9

0.7

0.45

2

1

Wind turbines do not trip above this line

FAULT RIDE THROUGH CAPABILITY of WPPS

Existed regulation Annex-18 New regulation for wind

Page 25: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

25

WPP INTEGRATION PROCESS TO THE GRID

REACTIVE POWER CAPABILITY

Existed regulation Annex-18 New regulation for wind

-0.4 -0.3 -0.2 -0.1 0 0.1 0.2 0.3 0.40

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

Total Reactive Power (pu)

To

tal

Act

ive

Po

we

r (p

u)

PF 0.95 enductive

PF 0.95 capacitive

PF 0.835 capacitivePF 0.835 enductive

0.1 pu under output power (total active power) ,Reactive power capacity is not checked.

Over Excited RegionUnder Excited Region

Page 26: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

26

According to the Transmission System Supply Reliability And Quality Regulation in the third section Generation Connection Principles - Design Principles of Generation Facility Switchyards defined that “Connection of generation facility based on wind energy is permitted for a capacity up to 5 % of the system short circuit power at the connection point ”

For example, A substation, minumum3 ϕ Short Circuit Power is Sk=3000 MVA Available wind power capacity for this busbar is3000x5/100 = 150 MW

- New regulation which will be published in the near future, IEC 61400 standarts are applied to determine available wind power capacity

AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE BUSBARS?

WPP INTEGRATION PROCESS TO THE GRID

Page 27: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

27

Solar Energy in Turkey

Page 28: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

28

Connection points for solar Power Plants

• The capacity of 600MW for Solar Power plants has been approved by TEIAS according to regions.

Number of substations

CAPACITY(MW)

546

4

26

6

22

326

11KAYSERİ

6

25

7MERSİN

735

8KAHRAMAN

MARAŞADIYAMAN

9

27

5ANTALYA

829

6KARAMAN

338

3VANAĞRI

577

4ANTALYA

629

468

2KONYA

1KONYA

10NİĞDE

NEVŞEHİRAKSARAY

9BURDUR

12MALATYA ADIYAMAN

Regions Number of substations

21MUŞ

19

23SİVAS

19

25ŞANLIURFADİYARBAKIR

17

TOTAL 121 600

Regions CAPACITY(MW)

32

35

221

18

9

5

24 ELAZIĞ

58

311

20ADANA

OSMANİYE4

9

2

18BİNGÖLTUNCELİ

411

16

718

16 DENİZLİ

3

14MUĞLA AYDIN

820

15 ISPARTA

AFYON

13HAKKARİ

19ŞIRNAK

22SİİRT

BATMANMARDİN

26 ERZURUM

17BİTLİS

27 ERZİNCAN

*Applications has to sellect the most nearest substation for system connection according to the regulations

Page 29: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

29

Hydraulic Power Plants Capacities in North East Region (In Operation &Planned)

2500 MW

2500 MW

1500 MW

Page 30: 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

30

Thank you for your attention