1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION...
Transcript of 1 Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION...
1
Turkish Power System Overview
27-28 March 2012
TURKISH ELECTRICITY TRANSMISSION CORPORATION
(TEIAS)
2
TURKISH POWER SYSTEM
- NUMBER OF SUBSTATIONS
- 400 kV 78
- 220 kV 2
- 154 kV 520
- 66 kV 14
TOTAL: 614 (103.100 MVA)
LENGTH OF TRANSMISSION LINES
- 400 kV 15830 km
- 154 kV 32513 km
- 220 kV 85 km
- 66 kV 508 km
- 154 kV and 400 kV cable length 220 km
- TOTAL 49.159 km
3
INSTALLED CAPACITY & PEAK LOAD
Installed Capacity : 53.235 MW
Renewable(hydro,wind,jeo.) : 36 %Thermal : 64%
Peak Load (2010) : 33.392 MW
Peak Load (2011 July) : 36.122 MW
THERMAL 34210; 64,3%
HYDRO17160; 32,3%
WIND1687; 3,2% OTHERS
115; 0,2%
INSTALLED CAPACITY (DECEMBER 2011)
THERMAL HYDRO
WIND OTHER RENEWABLES
4
GENERATION FOR 2011
Total : 229,3 TWh
Thermal : 73,7 %
Renewable : 26,3 %
5
CONSUMPTION
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
2011
Consumption(TWh) 114,0 118,5 128,3 126,9 132,6 141,2 150,0 160,8 174,6 190,0 198,1 194,1 210,4 228
İncrease (%) 8,1 3,9 8,3 -1,1 4,5 6,5 6,3 7,2 8,6 8,8 4,3 -2,0 8,4 9,0
6
PEAK LOAD AND ELECTRICITY CONSUMPTION 2001-2020
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
55000
60000
65000
70000
2001 2002 2003 2004 2005 2006 2007 2008 2009 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
MW
0
50000
100000
150000
200000
250000
300000
350000
400000
450000
GW
h
TÜKETİM (GWh) SENARYO 1 ENERJİ TALEBİ SENARYO 2 ENERJİ TALEBİ
PUANT YÜK (MW) SENARYO 1 PUANT TALEP SENARYO 2 PUANT TALEP
7
7
INTERCONNECTIONS (Existing Situation)
BULGARIA145 km 400kV
136 km 400kV
GREECE130 km 400kV
SYRIA124 km 400kV
IRAN 73 km 154kV100 km 400kV
NAHCİVAN87 km 154kV
GEORGIA28 km 220kV160km 400kV
ARMENIA80,7 km 154kV
400 kV Existing400 kV Underconstruction220 kV Existing154 kV Existing
IRAQ42 km 400kV
KKTC
400 MW
300 MW
15-8
0 M
W
40 MW40 MW
0 MW380MW
TÜRKİYE
0 MW
150 MW
8
8
PLAN FOR 2013
BULGARIA145 km 400kV
136 km 400kV
GREECE130 km 400kV
SYRIA124 km 400kV
IRAN 73 km 154kV100 km 400kV
NAHCEVAN87 km 154kV
GEORGIA28 km 220kV160km 400kV
ARMENIA80,7 km 154kV
IRAQ42 km 400kV
KKTC
1200 MW
1200MW
700 M
W
500 MW
TÜRKİYE
0 MW
350 MW
350
MW
If ENTSO-E connection will be approved
40 MW40 MW
400 kV Existing400 kV Underconstruction220 kV Existing154 kV Existing
9
9
PLAN FOR 2015
BULGARIA145 km 400kV
136 km 400kV
GREECE130 km 400kV
SYRIA124 km 400kV
IRAN 73 km 154kV100 km 400kV
NAHCEVAN87 km 154kV
GEORGIA28 km 220kV160km 400kV
ARMENIA80,7 km 154kV
400 kV Existing400 kV Under Construction220 kV Existing154 kV Existing
IRAQ42 km 400kV
KKTC
1200 MW
1200MW
700 M
W
600 MW
TÜRKİYE
Planning
phase
600 MW
350 M
W
40 MW
40 MW
If ENTSO-E connection will be approved
10
UCTE/ENTSO-E
• Trial Run period started with ENTSO-E on 18th of September 2010.
• The first phase system stability tests approved by
ENTSO-E Planary Group on 8th of February.
• Without any trade Import-Export tests for the second phase found successfull by ENTSO-E.
• The third phase (import-export with trade) related with the synchronous parallel operation of Turkey with European Power System started on 1th of June 2011 and it will be ended on September 2012.
• Trade will be limited with 400 MW from Bulgaria and Greece to Turkey; 300 MW from Turkey to Europe via these countries.
11
POWER PLANTS CONNECTION REQUESTS( December 2011)
MW
POWER PLANTS CONNECTION REQUESTS
HPP WPPTPP
TOTAL
NGCCP Other
CAPACITY APPROVED BY TEİAŞ 4.741 2.528 24.250 7.838 39.357
CAPACITY HAS BEEN LICENCED BY EMRA 10.114 5.066 5.765 2.715 23.660
CAPACITY HAS CONNECTION AGREEMENT BY TEİAŞ 6.473 3.464 5.715 6.391 28.267
TOTAL 21.328 11.058 35.730 16.944 85.060
The Turkey’s Parliament approved a new law 29 December 2010, on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of:
• 7.3 U.S. cents per kWh for wind energy and hydroelectric power, • 10.5 US cents for geothermal energy and • 13.3 US cents for energy from waste products and solar energy• These prices will cover energy firms that are established between May 13, 2005 and Dec.
31, 2015. • For energy purchases from companies founded later than Dec. 31, 2015, new prices defined
by the Cabinet will be implemented. The prices for the new companies will not exceed the current figures, the law said.
• In the event that operators use local equipment and technology in renewables energy facilities, an additional support of 0.4 cents to 2.4 $ per kw will be provided for a five year term to companies that started producing energy before the end of 2015.
• The surplus generation from the renewables will be bought by the distribution companies for ten years guarantee with the defined energy prices.
• The law limits the total production of licensed solar energy with 600 MW until the year of 31 December 2013 and authorizes the cabinet to determine the limits afterwards.
INCENTIVES FOR RENEWABLE POWER PLANTS
13
1 NOVEMBER 2007
78.000 MW TOTAL OVERLLAPPING APPLICATIONS
?
SINGULAR APPLICATIONSAND LICENCE – CONNECTION TO THE GRID3500MW CAPACITY ALLOCATED
-TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID?
-EVALUATING OVERLAPPING WPP’S APPLICATION?
WPP INTEGRATION PROCESS TO THE GRID
14
Wind Power Plants
15
WPP INTEGRATION PROCESS TO THE GRID
TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID?
16
WPP INTEGRATION PROCESS TO THE GRID
DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM
•Evaluation of the available wind power capacity can be connected to the system
•Power Flow studies
• Evaluation of wind variability on the effect of power flow and local grid
•Planning the investment of basin substation and transmission lines
17
APPLICATION 78.000 MW
APPLIED APPROACHES IN THE WORLD
-Integration to the 1/3 ratio to the demand of system minimum
-Integration to the 25% ratio to the demand of system maximum
2013 Estimated MinimumSystem Peak
2013 Estimated MaximumSystem Peak
18.703 MW 46.757
6.727 MW (1/3 of Peak ) 11.689 MW (25% of Peak)
-TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID?
WPP INTEGRATION PROCESS TO THE GRID
18
WPP INTEGRATION PROCESS TO THE GRID
DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM
NEGATIVE EFFECTS OF WIND POWER PLANTS ON GRID
- FAULT-RIDE TROUGH CAPABILITY OF WPP’S
-FLICKER (Turbulence/Output Power Source)
-VOLTAGE FLUCTUATION(Cause of Output Power fluctuation and insufficient of reactive power support)
-HARMONICS( Cause of Power Electronic Equipments)
Figure: Variable of wind generation
19
Wind Power Plants
0
20000
40000
60000
80000
100000
120000
MW
YEARS
INSTALLED CAPACITY AND PEAK LOAD OF TURKEY ACCORDING TO THE YEARS AND AVAILABLE RENEWABLE CAPACITY CAN BE CONNECTED TO THE SYSTEM
PEAK DEMAND
INSTALLED CAPACITY
CONNECTABLE RENEWABLE CAPACITY
20
• Process:
1. The available capacity of substations for connecting wind powerplants are published by TEİAS.
2. WPP applications are forwarded to TEIAS for studying connection opportunities.
3. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications.
4. If there are multiple applications in one substation, compitition process is done by TEIAS to determine the owner of the capacity.
5. After taking license the investor sign a connection agreement with TEIAS.
6. Project will be approved by MENR. After the realization of the project System Usage Agreement will be signed by TEIAS.
QUEUE MANAGEMENT OF WIND POWER PLANTS
21
Competitions
competition organisation
number of invited companies
number ofsubstations
number of winnercompanies
total connection capacity (MW)
1 27 12 16 626
2 11 5 6 281
3 26 8 8 500
4 31 3 8 395
5 30 8 9 520
6 38 8 16 289,4
7 46 6 15 427
8 54 6 12 607
9 41 3 4 74
10 37 5 9 217
11 175 16 31 1199
12 33 4 7 198
13 47 3 6 166
TOTAL 596 87 147 5500
Weighted average of the competition prices is 1,91 kurus/kwh
22
Winner prices and installed capacities
2215,7 MW%40
427 MW%8
605,5 MW%11
225,5 MW%4
816,6 MW%15
728 MW%13
481 MW%9 0 - 0,5
krş/kWh
0,5-1krş/kWh
1-2 krş/kWh
2-3 krş/kWh
3-4 krş/kWh
4-5 krş/kWh
5- krş/kWh
Winner prices according to installed capacity
23
Future Problems
• What will be the operation problems if ~11000 MW wind power plant will be in service ?
• Wind applications are concentrated in west side of Turkey. This will cause excessive voltage changes in the region
• Effective regional voltage control ;
• Effective secondary reserve control
• Effective ENTSO-E interconnection tie line control will be needed
• All these issues can be managed by an effective wind forecast and monitoring system
24
WPP INTEGRATION PROCESS TO THE GRID
U,
Lin
e V
olta
ge(p
.u)
Time, milisecond
0 150 700 1500 3000
1.0
0.9
0.7
0.45
2
1
Wind turbines do not trip above this line
FAULT RIDE THROUGH CAPABILITY of WPPS
Existed regulation Annex-18 New regulation for wind
25
WPP INTEGRATION PROCESS TO THE GRID
REACTIVE POWER CAPABILITY
Existed regulation Annex-18 New regulation for wind
-0.4 -0.3 -0.2 -0.1 0 0.1 0.2 0.3 0.40
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
Total Reactive Power (pu)
To
tal
Act
ive
Po
we
r (p
u)
PF 0.95 enductive
PF 0.95 capacitive
PF 0.835 capacitivePF 0.835 enductive
0.1 pu under output power (total active power) ,Reactive power capacity is not checked.
Over Excited RegionUnder Excited Region
26
According to the Transmission System Supply Reliability And Quality Regulation in the third section Generation Connection Principles - Design Principles of Generation Facility Switchyards defined that “Connection of generation facility based on wind energy is permitted for a capacity up to 5 % of the system short circuit power at the connection point ”
For example, A substation, minumum3 ϕ Short Circuit Power is Sk=3000 MVA Available wind power capacity for this busbar is3000x5/100 = 150 MW
- New regulation which will be published in the near future, IEC 61400 standarts are applied to determine available wind power capacity
AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE BUSBARS?
WPP INTEGRATION PROCESS TO THE GRID
27
Solar Energy in Turkey
28
Connection points for solar Power Plants
• The capacity of 600MW for Solar Power plants has been approved by TEIAS according to regions.
Number of substations
CAPACITY(MW)
546
4
26
6
22
326
11KAYSERİ
6
25
7MERSİN
735
8KAHRAMAN
MARAŞADIYAMAN
9
27
5ANTALYA
829
6KARAMAN
338
3VANAĞRI
577
4ANTALYA
629
468
2KONYA
1KONYA
10NİĞDE
NEVŞEHİRAKSARAY
9BURDUR
12MALATYA ADIYAMAN
Regions Number of substations
21MUŞ
19
23SİVAS
19
25ŞANLIURFADİYARBAKIR
17
TOTAL 121 600
Regions CAPACITY(MW)
32
35
221
18
9
5
24 ELAZIĞ
58
311
20ADANA
OSMANİYE4
9
2
18BİNGÖLTUNCELİ
411
16
718
16 DENİZLİ
3
14MUĞLA AYDIN
820
15 ISPARTA
AFYON
13HAKKARİ
19ŞIRNAK
22SİİRT
BATMANMARDİN
26 ERZURUM
17BİTLİS
27 ERZİNCAN
*Applications has to sellect the most nearest substation for system connection according to the regulations
29
Hydraulic Power Plants Capacities in North East Region (In Operation &Planned)
2500 MW
2500 MW
1500 MW
30
Thank you for your attention