Transcript of 1 The Future Air-Land Interface: A Shared Responsibility Gp Capt Andrew Joint Air Land Organisation.
1
The Future Air-Land Interface: A Shared Responsibility
Gp Capt AndrewJoint Air Land Organisation
2
1914-1918 1942 – North Africa 1944-45
The Cold War Op GRANBY KOSOVO
ALI – Historical Context
Op TELIC Op HERRICK
3
ALI Over-TimeA
LI C
apab
ility
Time
?
?
WW1WW1
BEFBEF
WW2 -WW2 -N AfricaN Africa
Cold WarCold War
KosovoKosovo
Op GRANBYOp GRANBY
Op TELIC/ Op TELIC/ HERRICKHERRICK1944-451944-45
4
Project Coningham Keyes Milestones
• Op Granby/Ex SAIF SAREEA 2/Op TELIC Air-Land interoperability was not good
• Mid 02 – 1Gp supported BATUS• Jul 03 – First PC-K Policy Group Meeting• 02/3 DOC Offensive Air Audit. Confirmed
shortcomings in Air’s ability to support Land/Maritime component.
• 2007 – PC-K concludes, CK2 Starts• Mar 10 – CK2 Concludes, Institutionalising
ALI commences
5
ALI Contribution to Joint Action
Fires Influence
Manoeuvre
Battlespace Management
Capability Understanding Will
CK 2 Focus
6
Collective Training• MST Jt Fires package
• Campaign FORM
UK FAC Requirement• Op capability doubled
• Future capability identified
Education• Joint Training Objectives
Air ISR• Video Downlink
Danger Close• GMLRS PROCEDURES
ALI Capability at BG Level• 1 TACP per BG
• 1 FAC per Coy
Close Combat Attack• Rotary Wing CAS and CCA
Inter-Service Liaison Elements• ASOC resourced
• DAIT/GLO/ASO
Individual FAC Training• Completely revised
• New 8-week FAC cse
Equipment• FIRESTORM
• VCDS Ops Package
Coningham-Keyes 2
7
ARMOUR
ENG SPT
8
Op Blenheim LessonsOp Blenheim Lessons
• 100% coverage by Tornado GR4 for 45 hours.
• Air Fuel Tanker availability:– Bespoke 216 Sqn Tristar extra fuel.– GR4 refuelling at Basra.
– SH sorties fully integrated into plan • Presence and speed of Air = flexibility.• No UK Casualties!• Enabled by forward leaning individuals from
Land and Air Components & a JOINT PLAN
9
Op OQAB TSUKA – Turbine Move
• Shaping Operations– ISR– Tac AT
• Decisive Operations– STRIKE – CAS– Avn – Electronic Attack– ARTY
• Sustaining Operations– Battlespace Management (BM)– Strike Support to framework operations
10
SECTOR 1 - RBG(S)
(NOWHERE TOC)
SECTOR 3 -13 CSLR
(WIDOW 49)
SECTOR 2 - TF 71(JAG)
HIDACZ STIRLINGSFC-17K AMSL – BGs
17K- 22K AMSL –WWTOCRADIUS 10NM
Check-in WWTOC PM37
1
3
2
CAS HOLD GOOJERAT
CAS HOLD MERVILLE
Battlespace Management
TF RV Pt
TRP
ROZ’s removed for clarity
11
Op OQAB TSUKA – Lessons
• Early Joint/Combined Planning– Ensures air capabilities are exploited
• Air for flank protection:– DETER– INFORM
• Flexibility of Air Platforms• Avn for intimate support:
– Convoy– SH resupply
• ISTAR 24 hour coverage
12
Final Thought
• We can consider ALI to be institutionalised when we no longer refer to an interface, rather to seamless output that marbles capability across all environmental domains, from the lowest tactical to the highest strategic levels and into a single symbiotic effect.
Or when it just happens
13
Institutionalising ALI
Fires Influence
Manoeuvre
Battlespace Management
Capability Understanding Will
CK I-ALI Focus
14
Enduring Principles Survive
• Robust integrated Joint C2 from Tactical through to Theatre level.
• Greater focus on non-Kinetic Approach.• Increased exploitation of the DIGITAL arena.• Common Joint Education and Training.• Increase role and utility of ISTAR in
UNDERSTANDING
15