Primary Activities in Progress
1. Monitor/Support Implementation of SCR745
2. Review ERCOT Certificate Policies and Certification Practice Statement
3. Addressing ERCOT System Outages and system failures
4. Monitor/Support Implementation of SCR748
5. Goal/Accomplishment 2007
6. Review Testing Connectivity Scripts
7. Run through of new Outage Notification
3
#1
1. TDTWG continues working with ERCOT to support implementation of SCR745 including the new architecture design
Update provided on technical solution. Currently in test. Planned implementation to production on 12-8. This will complete ERCOT initiatives for SCR 745.
4
#2
2. Review ERCOT Certificate Policies and Certification Practice Statement
Christian Brennan updated TDTWG with information related to Digital Certificate Management strategy
5
3. Continue working with the ERCOT Manager of Operations to address each system incident.
ERCOT Operations Manager reviewed November’s incident report.
#3
6
#4
4. TDTWG continues working with ERCOT to support implementation of SCR748
Kevin Tanner presented early preview of the working ERCOT website for Outage Notifications.
7
#5
5. Goal/Accomplishment 2007
TDTWG put together list of this years accomplishments
8
#6
6. Review Testing Connectivity Scripts
TDTWG reviewed testing connectivity scripts and made recommendations to discuss details with ERCOT test group and take recommendations to TTPT.
9
#7
7. Run through of new Outage Notification
Jack Adams will give you a quick run through of the new Outage Notifications Calendar from SCR748.