Update from ERCOT Retail Market Services to RMS October 16, 2003

40
1 Update from ERCOT Retail Market Services to RMS October 16, 2003

description

Update from ERCOT Retail Market Services to RMS October 16, 2003. Retail Market Update. Topics Data Variance / Data Archive Workshop Update FasTrak D2D / DEV Update Pre-TX SET 1.5 Clean up Progress Report Ongoing Data Clean Up Update Inadvertent Gain Task Force Update - PowerPoint PPT Presentation

Transcript of Update from ERCOT Retail Market Services to RMS October 16, 2003

Page 1: Update from ERCOT  Retail Market Services to RMS October 16, 2003

1

Update from ERCOT Retail Market Services to RMS

October 16, 2003

Page 2: Update from ERCOT  Retail Market Services to RMS October 16, 2003

2

Retail Market Update

Topics• Data Variance / Data Archive Workshop Update

• FasTrak D2D / DEV Update

• Pre-TX SET 1.5 Clean up Progress Report

• Ongoing Data Clean Up Update

• Inadvertent Gain Task Force Update

• Texas Market Link (Phase 1) Update

• Texas Market Link (Phase 2) Update

• Move-In /Move-Out Market Solution to Stacking (V2.0)

• Flight 1003 Update

Page 3: Update from ERCOT  Retail Market Services to RMS October 16, 2003

3

SCR 727 ExtractWorking Group Meeting

Page 4: Update from ERCOT  Retail Market Services to RMS October 16, 2003

4

RMS Decision from 9/26/03

Convene a Working Group to:

1. Work out details of the resolution process

2. Determine prioritization of issues to be worked

3. Identify any appropriate threshold for usage variance

4. Determine how to track Market Participant completion of data variance processing responsibility

Page 5: Update from ERCOT  Retail Market Services to RMS October 16, 2003

5

Actions from 9/30/03 SCR 727 Training Meeting

• Send out questionnaire on variance process and timelines• Responses due to ERCOT by COB Monday 10/6• Responses received from 3 TDSPs and 3 CRs• ERCOT to compile responses• At 10/8 meeting, Task Force to define timelines based on

responses• ERCOT to redline DEV manual to reflect prioritization

issue with Trade Month.

Page 6: Update from ERCOT  Retail Market Services to RMS October 16, 2003

6

Working Group Consensus

• Target 75 calendar days for complete resolution• Prioritization

– Keep prioritization as is currently outlined in DEV manual

– ERCOT to change internal validations to allow trade months that fall within any minimum start time and maximum stop time provided in the spreadsheets.

Page 7: Update from ERCOT  Retail Market Services to RMS October 16, 2003

7

Consensus on Target Timeline LSE Variances

Submit Variance at least 75 days prior to scheduled resettlement

ERCOT initial validation and analysis completed

ERCOT & CR:• Takes corrective action and/or• Performs Turnaround with MPs • Responds to submitter

LSE Variances

TDSP/CR Initial Response

14 Days

75 Calendar Days

21 Days

Issues to Consider:

• It is possible that the initial response from the TDSP/CR requires a turnaround to the initiator of the issue.

Settlement takes place

40 Days

Page 8: Update from ERCOT  Retail Market Services to RMS October 16, 2003

8

Consensus on Target Timeline NIDR Usage Variances

Submit Variance at least 75 days prior to scheduled resettlement

TDSP validation and analysis completed; Response provided to submitting party

NIDR Usage Variances

TDSP to send transactions if necessary or CR manually update system if needed

45 Calendar Days

75 Calendar Days

30 Calendar DaysSettlement takes place

Issues to Consider:

• Depending on the resolution of the variance, the TDSP may have to submit transactions.• ERCOT will work with TDSP to resolve any transaction issues to fix variances

Page 9: Update from ERCOT  Retail Market Services to RMS October 16, 2003

9

Consensus on Target Timeline IDR Usage Variances

Submit Variance at least 75 days prior to scheduled resettlement

TDSP validation and analysis completed; Response provided to submitting party

IDR Usage Variances

TDSP to send transactions if necessary or CR manually update system if needed

45 Calendar Days

75 Calendar Days

30 Calendar DaysSettlement takes place

Issues to Consider:

• Depending on the resolution of the variance, the TDSP may have to submit transactions.• ERCOT will work with TDSP to resolve any transaction issues to fix variances

Page 10: Update from ERCOT  Retail Market Services to RMS October 16, 2003

10

Consensus on Target Timeline Service History ESI ID Characteristics Variances

Submit Variance at least 75 days prior to scheduled resettlement

TDSP validation and analysis completed; Response provided to submitting party

ESI ID Characteristics

TDSP to send transactions if necessary or CR update system manually if needed

45 Calendar Days

75 Calendar Days

30 Calendar DaysSettlement takes place

Issues to Consider:

• Depending on the resolution of the variance, the TDSP may have to submit transactions.• ERCOT will work with TDSP to resolve any transaction issues to fix variances

Submit Variance at least 75 days prior to scheduled resettlement

ERCOT validation and analysis completed

TDSP to send transactions if necessary

10 Calendar Days 65 Calendar DaysSettlement takes place

ESI ID Existence

Page 11: Update from ERCOT  Retail Market Services to RMS October 16, 2003

11

10-16-03 RMS Vote

• Establish a 75 calendar day deadline for completion of each issue and each MP (including ERCOT) will complete the DEV process in accordance with the timelines and other requirements of the DEV manual.

Page 12: Update from ERCOT  Retail Market Services to RMS October 16, 2003

12

RMS Discussion on Reporting

• At ESI ID level for each point-to-point variance type, report:– % worked within 75 days

• % that result in change of data

• % worked that do not result in a change.

– % worked outside 75 days

• % that result in change of data

• % worked that do not result in a change.

• Data presented by REPs broken down by TDSP service territory

Page 13: Update from ERCOT  Retail Market Services to RMS October 16, 2003

13

RMS Decision from 9/26/03

Convene a Working Group to:

1. Work out details of the resolution process – RMS Vote

2. Determine prioritization of issues to be worked – WG Consensus

3. Identify any appropriate threshold for usage variance – WG Consensus

4. Determine how to track Market Participant completion of data variance processing responsibility – RMS Discussion

Page 14: Update from ERCOT  Retail Market Services to RMS October 16, 2003

14

Target Timeline for Extract, Variances, True-Ups

Extracts

10/1/03Clear all “old” extracts from Portal

9/26/03Post last “old” daily extract

10/6/03“New” extracts available

10/22/03“New” daily extracts

10/1/03Stop “old” variance process

2/22/04Begin True-Up runs for 2003

10/10/03Complete existing variances w/ answers; Close remaining 2002 variances

Deadline 75 days prior to 2/9/04 to file variances for 1/1/03 True-Up

Variances

Settlements

10/1/03Resettlement of 2003 dates beginning with selected June dates

10/13/03 Begin filing new variances;

Page 15: Update from ERCOT  Retail Market Services to RMS October 16, 2003

15

FasTrak Issue Status• Day-to-Day• Data Extract Variances (DEV)

Page 16: Update from ERCOT  Retail Market Services to RMS October 16, 2003

16

FasTrak 2003 “Day to Day”Issue Stats (as of 10-16-03)

• Of the 340 In Progress with ERCOT, 208 are resolved and awaiting other party resolution check off

• Total ESI IDs worked to date since January 1, 2003 = 242,111

STATUSIssueCount

Issues as a% of Total

New 52 0.48%

In Progress (ERCOT) 340 3.13%

In Progress (w/TDSP) 138 1.27%

In Progress (w/CR) 58 0.53%

Resolved 9,597 88.31%

Rejected 682 6.28%

Total 10,867

IssueCount

Issues as a% of Total

New 1,087 29.19%

In Progress 1,152 30.93%

Resolved 1,423 38.21%

Rejected 62 1.66%

Total 3,724

Non-ERCOT

ERCOT

• Of the 2,239 New and In Progress with Non- ERCOT, 18 are for the year 2002

• Number of ESI IDs not tracked

Page 17: Update from ERCOT  Retail Market Services to RMS October 16, 2003

17

FasTrak Data Extract VarianceIssue Stats (as of 10-16-03)

• Of the 171 In Progress with ERCOT, 16 are resolved and awaiting other party resolution check off

• Issues submitted between 10-1-03 and 10-13-03 will be rejected (DEV Black-out Period)

• On 10-11-03, 1,452 existing issues for 2002 Trade Months were rejected with comment of “RMS directed close out of 2002 variances filed under the original extract process”

• A few 2002 remain open due to current work in progress

STATUSService History Usage

TotalIssues

Issues% of Total

New 0 0 0 0.00%

In Progress (ERCOT) 171 0 171 14.73%

In Progress (w/TDSP) 48 0 48 4.13%

In Progress (w/CR) 35 0 35 3.01%

Resolved 239 2 241 20.76%

Rejected 638 28 666 57.36%

Rejected (Old Extract) 440 0 440 37.90%

Total 1,131 30 1,161

Service History Usage

TotalIssues

Issues% of Total

New 6 3 9 0.63%

In Progress 176 118 294 20.69%

Resolved 315 479 794 55.88%

Rejected 106 218 324 22.80%

Rejected (Old Extract) 386 626 1,012 71.22%

Total 603 818 1,421

Non-ERCOT (CR to TDSP)

ERCOT

Page 18: Update from ERCOT  Retail Market Services to RMS October 16, 2003

18

Pre TX Set 1.5 Data Clean Up

• Directive from RMS 07-17-03 Meeting• Pre TX SET 1.5 Status Report• Ongoing Transaction Clean-up Process

Page 19: Update from ERCOT  Retail Market Services to RMS October 16, 2003

19

Pre-TX Set 1.5 Data Cleanup

Background:ERCOT identified “In Review”, “Scheduled” and “Canceled with Exception with Meter Reads” that were not completed from early 2002 to April 11, 2003.

RMS Vote, July 17th, 2003:Recommend RMS direct ERCOT to completely clean-up by August 13th, 2003 the Pre-Tx Set 1.5 In Review, Scheduled and Cancel With Exception that have been identified and sent to the market participants which should include cancels with CR approvals. ERCOT will provide at August RMS full statistics involving market participants broken down per issue type. ERCOT is directed that if the TDSP provides file names, ERCOT will locate and re-process if it is a valid transaction. RMS directs the TDSPs and CRs to provide transactions or information necessary to achieve the completion of the data clean-up.

Page 20: Update from ERCOT  Retail Market Services to RMS October 16, 2003

20

Pre-TX Set 1.5 Data Cleanup

Mar-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03In Review AEP - - 0 0 0 0

CNP - - 0 0 0 0

Oncor - - 6 0 0 0

TNMP - - 6 0 0 0

Total 16,188 207 12 0 0 0

Scheduled AEP - - 2,953 1,883 57 25

no completing CNP - - 1,215 530 93 10

meter read Oncor - - 991 2,039 1,413 765

TNMP - - 994 2,186 418 127

Shrylnd - - - 8 - 0

Total 23,030 11,038 6,153 6,638 1,981 927

CWE AEP - - 31 31 0 0

w/ Meter Data CNP - - 694 697 620 251

Oncor - - 624 624 4,365 72

Identified as TNMP - - NR NR 260 2"Need to Complete" Total Na 1,618 1,349 1,352 5,245 325

Page 21: Update from ERCOT  Retail Market Services to RMS October 16, 2003

21

Ongoing Transaction Data Clean-up

Clean-up Process Steps:

1. ERCOT runs the query and defines the Action Items needed a) In-Review with Meter Read: Notify TDSP and request 814_04/25

then transaction will complete. (Date Range equals or greater than 07/01/01.)

b) Scheduled No Meter Read: Notify TDSP and request 867 completing transaction. (Date Range equals or greater then 07/01/01.)

c) Cancel With Exception (CWE) with Meter Read: Notify CR and TDSP and find out if they thought the transaction had completed. If so – take corrective action. (Date Range is 04/12/03 to 08/31/03.)

d) Cancelled Permit Not Received with Meter Read: Notify CR and TDSP and find out if they thought the transaction had completed. If so – take corrective action. (Date Range is 04/12/03 to 08/31/03.)

Page 22: Update from ERCOT  Retail Market Services to RMS October 16, 2003

22

Ongoing Transaction Data Clean-up

Clean-up Process Steps Continued:

2. ERCOT distributes the lists to MP who owe the follow-up action.

3. MP Responds and ERCOT coordinates the clean-up activities.

4. ERCOT to report Monthly to RMS.

Next Steps – Proposed Clean-up Process Timeline:

October 20, 2003: ERCOT sends out new lists to CRs and TDSPs

October 29, 2003: TDSPs send analysis to CR

November 4, 2003: CRs respond to TDSPs and coordinate final response to ERCOT

November 7, 2003: ERCOT receives responses from TDSP

November 11, 2003 ERCOT prepares RMS report and sends out

November 13, 2003: ERCOT reports at RMS

Page 23: Update from ERCOT  Retail Market Services to RMS October 16, 2003

23

Customer Protection and 814_08 Issue

• Background and Completed Items• Matrix and Progress Report• Other Status Items and Next Steps

Page 24: Update from ERCOT  Retail Market Services to RMS October 16, 2003

24

BackgroundERCOT has determined that there was an issue with the 814_08 manual-processing tool related to the “cancel by customer objection” process. While ERCOT systems were updated appropriately, 972 ESI IDs (spanning the August 2002 through July 2003 time frame) were identified where ERCOT has been unable to confirm that the TDSP was sent the 814_08 cancel.

Completed Items• ERCOT compiled lists and forward them to the TDSPs on 8/6/03 and

CRs on 9/16/03• Most responses to original request received by 9/19/03 (Still missing

A.C.N. Response)• Scenarios resulting from original response included matrix• ONCOR and AEP TDSPs responded on Scenario 1 records by

10/3/03. (TNMP received 10/13/03 and CNP received 10/14/03)• ERCOT sent out all modified inadvertent FasTrak issues on 93 issues

identified in Scenarios 2 through 7

Customer Protection Period and 814.08

Page 25: Update from ERCOT  Retail Market Services to RMS October 16, 2003

25

Customer Protection Period and 814.08

TDSP Losing

CR Gaining

CR Total

Instances

CR Claiming

ESI ID Suggested Action

Status

1 Completed Completed Completed 425 Gaining

CR ERCOT manually correct

rep of record history In Progress

2 Completed Canceled Completed 16 Both CRs

ERCOT create modified inadvertent issue

1 completed 15 in progress

3 Completed Completed Canceled 13 No CR ERCOT create modified

inadvertent issue 13 in progress

4 Completed Canceled Canceled 8 Losing

CR ERCOT create modified

inadvertent issue 8 in progress

5 Canceled Completed Completed 6 Gaining

CR ERCOT create modified

inadvertent issue 1 completed 5 in progress

6 Canceled Canceled Completed 33 Both CRs

ERCOT create modified inadvertent issue 33 in progress

7 Canceled Completed Canceled 17 No CR ERCOT create modified

inadvertent issue 3 completed

14 in progress

8 Canceled Canceled Canceled 387 Losing

CR No action necessary NA

Unable to categorize response 8

Total Responses 905

Total Sent to Market 972

Page 26: Update from ERCOT  Retail Market Services to RMS October 16, 2003

26

Other Status Items• Of 34 FasTrak issues created (some contain multiple ESI IDs) –

“dialog” has occurred on 18 (as of 10/13/03). • 4 of the 34 FasTrak issues are considered “resolved” (updated

accordingly)─ Note: Concern ERCOT not informed of “resolution” in some cases?

Next Steps• ERCOT to continue to escalate missing responses• ERCOT to complete manual corrections to un-cancel and complete the

transactions per Scenario 1• CRs and TDSPs make decisions on outstanding FasTrak issues and

provide response to ERCOT • ERCOT to provide status report to RMS Chair/Vice Chair by Nov 3rd

Customer Protection Period and 814.08

Page 27: Update from ERCOT  Retail Market Services to RMS October 16, 2003

27

Texas Market Link(Phase 1) Update

Page 28: Update from ERCOT  Retail Market Services to RMS October 16, 2003

28

Texas Market Link (TML) Status

• TML migration activities began Friday, 10/3 and completed Sunday evening 10/5; Retail components down during migration.

• Performance issues surfaced on morning of 10/6; related to Operating System corruption on web servers.

• TML backed out and pre-migration portal restored by 10/7.

• IT team is evaluating flaw in migration process and identifying corrective steps for re-launch.

Page 29: Update from ERCOT  Retail Market Services to RMS October 16, 2003

29

ERCOT Portal Replacement Phase 2 Project

Update to RMSPresented by Dave Odle

Page 30: Update from ERCOT  Retail Market Services to RMS October 16, 2003

30

Portal Phase 2 Update

Phase 2 is on schedule with requirements and initial design

COMPLETED ITEMS:

• Requirements Gathering

• Market priority session – 10/2/03

• Requirements documentation

• Documentation distributed to MPs

Page 31: Update from ERCOT  Retail Market Services to RMS October 16, 2003

31

Portal Phase 2 Update

Next Steps:

• Build internal Project Plan – 10/25

• Requirements Transition to I.T. – 11/1

• Begin Initial Design – 11/1

Page 32: Update from ERCOT  Retail Market Services to RMS October 16, 2003

32

Move-In/Move-Out Market Solution to Stacking (Texas Set V.2.0)

Update to RMSPresented by Glen Wingerd

Page 33: Update from ERCOT  Retail Market Services to RMS October 16, 2003

33

• Continuing efforts for Project Success.– Continued improvements in communication

• FAQ E-mail address for questions [email protected]

• Educational Seminars at MP shops

• Posted additional development documentation

– Working design/functional issues as they are discovered

• Most have been identified and resolved

– Working on defining recommendations to TTPT for testing

V2.0 Coordination Team Accomplishments/Goals

Page 34: Update from ERCOT  Retail Market Services to RMS October 16, 2003

34

Project Overview

Summary of Changes:Manage customer expectations by accepting and processing all valid requests.

Imp

act

Lev

el

Efficiency

Communication

Competition

Business Problem• Existing NFI logic forces an unreasonable amount

of dependency on labor intensive workarounds.• Execution of workarounds are causing

synchronization issues between market participants.

• Lack of synchronization leads to improper billing and mismanagement of customer expectations

Solution• All valid transactions will be accepted and

processed based on a set of market rules.• Drop notifications will be sent at a point in time

where the proper recipient can be positively identified.

• Rule based cancellations are sent on a pre-determined timeline with enough time for the recipient to react.

Page 35: Update from ERCOT  Retail Market Services to RMS October 16, 2003

35

Solution to Stacking

Production Implementation Timeline

1/12004

Oct. RMS

Production Implementation

Date:8/1/2004

7/72003

MIMO Task Force delivery of

PRR to PRS

7/312003

Texas SET Version 2.0

Final Baseline

10/12003

Market Coordination team

review of Production Processing Schedules

8/312003

TDSPs and ERCOT

Production Processing

Schedules due

11/142003

38 weeks

Details on ERCOT

exception processing

due

Draft Implementation

schedule and plan due

5/32004

7/232004

5/172004

10 weeks

Market Test

Testing checkpoints at

weeks 5 & 8

Final Implementation

schedule and plan due

Page 36: Update from ERCOT  Retail Market Services to RMS October 16, 2003

36

• Details on ERCOT Exception Processing Due 11/14/03

• Develop Flight Test Plan– Procedural Requirements – TTPT

– Conceptual Requirements – Market Coordination Team

– Functional Requirements – TTPT Script Sub-Team

– Monitoring Requirements – Stacking Testing Advisory Team

• Develop Production Implementation Plan

Next Steps

Page 37: Update from ERCOT  Retail Market Services to RMS October 16, 2003

37

Thank-you

Page 38: Update from ERCOT  Retail Market Services to RMS October 16, 2003

38

Flight 1003 Status Report

Page 39: Update from ERCOT  Retail Market Services to RMS October 16, 2003

39

Flight 1003 Status Report

Flight stats:

• There are 16162 transactions/steps

• There are 302 trading partnerships

Progress:

• Connectivity – complete

• Frame 1 – started Monday

• A total of 3 frames for testing

• Flight scheduled to conclude – 12/05/03

Page 40: Update from ERCOT  Retail Market Services to RMS October 16, 2003

40

Questions ?