Presentation to Technical Services
• Step 1 - Walk-through of new premises• Step 2 – This presentation will focus on
next steps to relocate staff and departmental operations from 2nd floor to the 1st floor
• Timing of next steps is not final• Uncertainty centers on time required to
correct deficiencies – we’ve allowed 2 weeks in our plans for this, may be less!
2
Presentation to Technical Services
• Recognize that timing of the move is important to staff – vacations, etc.
• Some staff may be sensitive on how their workstations should be relocated. Please feel free to discuss with me confidentially!
3
Overview of Move
• York Grounds moves boxes containing personal possessions, Kardex, supply cabinets, book trucks, filing cabinets, and lunchroom furniture
• Personal possessions will be secured• LCS will move most computers & equipment to
room 530 (Stage 1) & then to 1st floor (Stage 2)• Outside mover dismantle & reassemble cubicles • York Telecom does network/phone connections • Outside vendor to move compact shelving• Facilities assist packing compact shelve material
4
Objective of Move
• Each staff member should receive their existing chair, computer, and cabinets.
• However, as the configuration of cubicles is changing in the new premises, you may not end up with the same cubicle components.
• Move is carried out in a systematic, orderly manner
• Operations are disrupted as little as possible
5
Move for Office Holders
• Office holders will move into new premises first, as their new offices will be ready to be occupied prior to cubicles.
• Once everything is packed and labeled, all goods moved directly to new offices.
• LCS and York Telecom will disconnect and reconnect computers and phones, which should not be packed!
6
Request Staff Assistance on Move
• Empty cubicles, pack, label boxes
• Leave drawers, cabinets unlocked
• Tape keys inside drawers
• Label chairs and computers
• Empty shelves and load material onto book trucks
7
Request Staff Assistance on Move
• Unload, box, & label filing cabinet material
• Call forward all work phones (excluding office phones) to ext. 88854. York Telecom will disconnect office phones from columns.
8
Move for Staff
• Once staff pack & label their possessions, materials, furniture & equipment, LCS moves computers to Room 530, which will be a temporary staging area during move.
• Movers to disassemble cubicles in Room 208 and reassemble cubicles on 1st floor
• York Grounds move possessions, Kardex, materials, furniture, cabinets, book trucks, lunch room & scanning room equipment
9
Move for Staff
• Once cubicles are reassembled, LCS will relocate computers to 1st floor.
• York Telecom reconnects phones/network
• Unpacking process begins
10
What Happens During the Move
• For some staff, the time between the completion of packing and moving into new premises may be 7- 8 days.
• During the move some staff will continue working on their regular duties. Dept heads may assign people a variety of regular and/or temporary duties such as shelf reading or data clean up .
11
Initial Planning Steps May 27- June 1
• JHSC and DOHS review
• Contractor deficiency review
• Staff walk through new premises
• Presentation to Tech Services
• Arrange Custodial Services
• Office wall installation complete
12
Changes in Activity during Move
• Serials mail held in storage in room 007 until Kardex operational
• Book deliveries held in storage in room 007 until move complete
• Mail delivery to Technical Services special handled until move complete
13
Compact Shelving
• Compact shelving moved after all staff relocated
• Facilities will help Tech Services pack/ unpack material on compact shelving under the direction of Linda Smith
• Compact shelving dismantled and reassembled by contractor in room 106
14
Washrooms
• Located in corridor leading to emergency exits
• Not included in renovations; no funding
• Will post “staff only” signs on doors
• Will work to maintain cleanliness
• new campus policy to remove paper towel dispensers starting; reduce waste; powered hand dryers in place
15
Next Steps• Aim is to provide staff with one week’s
notice on move date
• More frequent communications required going forward. Will use blog updates, handouts, departmental meetings, etc.
• Staff issued security cards before move
• Would appreciate your help on any departmental issues not covered.
• Address any concerns to your dept head.