1 Dow Freeport PMDI MRU Optimization John Litzinger Sr. Improvement Specialist May 20, 2010.
-
date post
21-Dec-2015 -
Category
Documents
-
view
214 -
download
0
Transcript of 1 Dow Freeport PMDI MRU Optimization John Litzinger Sr. Improvement Specialist May 20, 2010.
1
Dow Freeport PMDIMRU Optimization
John LitzingerSr. Improvement Specialist
May 20, 2010
2
• Largest diversified chemical company
• Founded in Midland, Michigan in 1897
• Supplies more than 5,000 products to customers in 160 countries
• Annual sales of $45 billion
• 52,000 employees worldwide
• One of the world’s largest industrial energy consumers
• Committed to Sustainability
About Dow
3
Oil & Gas = Energy & Feedstock
Oil & GasOil & Gas
FeedstockEthane, Propane Butane, Naphtha
FeedstockEthane, Propane Butane, Naphtha
EnergySteam, HeatPower, Water
EnergySteam, HeatPower, Water
850,000 Barrels/day
4
The Dow Public ReportThe Dow Public Report
Corporate Commitment to Energy Reduction
www.dowpublicreport.com
Public Commitment:
• In 1995 Dow Committed:
• To Reduce Energy Intensity
• By 20% by the year 2005
• From Base Year 1994
5
We will further reduce our global energy intensity by 25% from 2005- 2015 We will reduce our GHG emissions intensity by 2.5 % per year thru 2015 By 2025, we aspire to reduce absolute emissions within the company
“No one in the world is more intenselyaware of the need, ultimately, to reinventour dependency on oil and natural gasthan we are… We will lead the way on energy transformation because we have to. And we have taken important steps already.”
-- Andrew Liveris Chairman, CEO & President The Dow Chemical Company
Corporate Commitment to 2015 Goals
Liveris Launches 2015 Sustainability Goals
Corporate Commitment & Acountability
6
Dow Polyurethane PMDI• PMDI (Polymeric Methylene Di-Phenyl
Di-Isocyanate) is a raw material in Polyurethane Formulations.– Typical end uses include insulation in
Appliances and Construction industries.– Dow directly markets Great StuffTM
insulation foam.
• Product end use is directly related to energy efficiency improvements in everyday life.
• Dow Operates 3 PMDI sites within integrated sites – Freeport, TX; Stade, Germany; Estarreja, Portugal
TM – Trademark of the Dow Chemical Company
7
PMDI Energy Efficiency Program
In 2007, the business started an energy efficiency improvement plan with the following results:– High Pressure Steam Optimization / Trap
Reliability– Thermal Oxidizer Fuel Gas Optimization– Internal Reflux and Reboiler Optimization for
several distillation columns– Furnace Optimization including majority use
of Hydrogen when available– Mechanical Refrigeration Unit (MRU)
Compressor Optimization
In 2005, Dow started up a new PMDI facility in Freeport, TX, with 500 MM lb/year capacity
8
MRU Optimization Summary
• Project Overview
• Approach
• Team Resources
• Phase 1 Implementation and Results
• Phase 2 Implementation and Results
• Final Summary
• Q&A
9
Project Overview
• Desired outcome was to reduce electricity usage while maintaining required process cooling.– The MRU Compressor is a 15,000 HP system with 3
stages and 8 impellers.– Due to plant optimization, the requirements for
cooling are 30% less than design.
• The project was implemented in 2 phases– Maximize improvements with no hardware changes– Maximize improvements with minimized capital
spending, and maximize Net Present Value (NPV)
10
Approach• First Pass - Used compressor curves to
determine if unit could be turned down as is • Worked with compressor manufacturer to
confirm using its internal modeling system• Dow Process Engineering confirmed modeling
results using AspenTM simulation programs.• Tested in field, confirming surge first, then full
implementation of Phase 1• Once confirmed, moved to Phase 2 –
Hardware changes
11
Team Resources• Improvement Engineer • Process Engineer • Mechanical Design Lead • Technology Consultant• Rotating Equipment Specialist• Refrigeration Consultant• Mechanical Engineer• Reliability Engineer• Plant Operations Staff• Vendor Input
12
Phase 1 – No Investment (August 2009)• Team reduced Compressor HP by 16%• Overall approach was to create a higher DP, with
lower flow on Stages 2 and 3 (left on the curve).• On Stage 1, volume flow was increased (moving
right on the curve)– Maintain proper cooling conditions
– Minimize false loading throughout the system
• Surge testing was attempted, but never confirmed since plant was operational
13
Phase 2 – Minor Capital (February 2010)• Team reduced Compressor HP by additional 17%
– Met goal of 30% energy reduction corresponding to refrigeration load• Evaluated different hardware options –
– Replace shaft and impeller wheels– Trim existing impeller wheels– Resize Gearbox Reducer
• Implemented “Resized Gearbox Reducer”– Decreased Compressor Shaft speed by 5%
• Replaced during one-week outage in February– Started compressor when plant was still down to test surge– Surge confirmed on Stage 3, and tested minimum flows on Stage 1 and 2.– Placed “anti-surge” set points at 10% above “tested” on Stage 1 and 2.– Placed “anti-surge” set point at 20% above for Stage 3.
• Current Operations– Zero false load on Stage 3– Minimum false load on Stage 2– Low false load on Stage 1– Proper pressure and exchanger level set points to maintain refrigeration
14
Final Summary
• Project Value– $2,500,000 savings– 17,330 tons CO2 reduced– Invested hardware cost approximately $250,000 in
Phase 2
• Project approach can be adopted throughout Dow, and may already be implemented throughout industry.– De-rates are especially important when electricity is
perceived as fixed cost, and energy requirements are lower downstream.
15
Thank YouThank You
Q&AQ&A