1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.
-
Upload
godfrey-caldwell -
Category
Documents
-
view
212 -
download
0
Transcript of 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.
![Page 1: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/1.jpg)
1
DOING A PARTICIPATORY PER
THE VIETNAM EXPERIENCE
David Shand
PEAM Seminar
24 May, 2001
![Page 2: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/2.jpg)
2
Why a Participatory PER?
1996 PER of good technical quality, not used by GOV - various reasons including inter-ministry rivalries
Vietnam a CDF pilot country
Idea of a participatory PER seemed logical - and strongly endorsed by World Bank Hanoi
But perceived as the first step in a lengthy process - build ownership and capacity to do their own PERs in future
Impact through dialogue, not just a report
![Page 3: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/3.jpg)
3
Obtaining Ownership by Government
Agreement on scope and timing on PER
Set out a continuous consultation process
Everything to be translated into Vietnamese
And stress the advantages to GOV
And little to fear - “no surprises”
“Flexible”, non-preaching approach by WB
High standing of WB with GOV
But WB and GOV “agree to disagree if necessary”
![Page 4: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/4.jpg)
4
Some Other Issues GOV will not be pushed around
Apparently good results from public expenditures - “if it ain’t broke don’t fix it”
Government itself doesn’t know what is going on - and therefore isn’t in full control
Shining light into dark corners - but focus on a few key issues - sowing some ideas
Comparisons with other countries in the region interest GOV
Other topics can be covered in later PER
![Page 5: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/5.jpg)
5
Involvement of Donor Community
Key stakeholders in the PER - PER was A C-G requirement
Key donors involved, UK, Netherlands, Denmark
Provision of funding ($242k of total PER spending of $522K)
Interest in particular issues (Netherlands gender, UK programmatic lending)
![Page 6: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/6.jpg)
6
Involvement of Donor Community
Regular consultation with key donors (but some difficulty - one donor felt it was not consulted closely enough)
General briefing meetings of all donors and NGOs at the end of each mission
UNDP funding of capacity building
Cooperation with IMF - Fiscal sustainability and transparency chapter
![Page 7: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/7.jpg)
7
The Mechanisms and Theory of Consultation
GOV a “full partner” to sign a joint report with WB/International donor community
GOV counterpart committee of officials (MOF, MPI and sectoral ministries) to work with PER team
Agreement on TOR and timing and provision of information
WB consultants work with local consultants - to improve quality and increase local capacity
Critical role of WB Hanoi Office in maintaining the liaison
![Page 8: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/8.jpg)
8
The Mechanisms and Theory of Consultation
GOV comment on draft chapters as they emerge
WB held the pen
Key role of WB Hanoi Office in maintaining the liaison
But in reality there were some problems Some local counterparts not appropriate - only
from accounting/finance branch of the ministries In some areas local consultants did not add value
or were not used - GOV decision Initially some lack of cooperation by other
ministries - PER perceived as only a MOF exercise
![Page 9: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/9.jpg)
9
Chronology of the Participatory Approach
October/November 1999: Preliminary mission
Meeting with Vice-Minister of Finance
Meetings with MOF, MPI and Sectoral Ministries
Workshop on PER for senior officials
Discussion of draft concept paper with GOV
agreement on scope
timetable and meeting information requirements - consultants to provide these in advance to GOV
![Page 10: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/10.jpg)
10
Chronology of the Participatory Approach
January: Main mission (two weeks)
team of 12
some work with local consultants
visits to Quang Binh province
workshop in HCMC
End February/early March
draft chapters provided to GOV
![Page 11: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/11.jpg)
11
Chronology of the Participatory Approach
March 24 - April 4: Follow-up mission
discussions with MOF, MPI and sectoral ministries on draft chapters
sectoral workshops (some involving Vice Ministers) and plenary workshops
first draft of report provided to GOV
![Page 12: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/12.jpg)
12
Chronology of the Participatory Approach
Late April
final draft report provided to GOV
Mid May
formal comments from MOF
WB Hanoi line by line discussion with MOF
![Page 13: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/13.jpg)
13
Chronology of the Participatory Approach
June: Final mission to discuss PER report
Agreement with MOF and submission to leadership
June 23-23: C-G meeting in Vietnam
GOV presents PER report to C-G
September: discussions on PER implementation and follow-up
![Page 14: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/14.jpg)
14
Impact of a Participatory Approach
On issues to be covered
Agreement on: Cross-cutting issues
fiscal sustainability and transparency public expenditure management and public investment
processes fiscal decentralization gender (Netherlands interest,
fees and contributions) Sectoral issues: agriculture, education, health, transport,
social safety nets (added later) Issues not to be covered: Civil Service Reform,
Corruption, Defense expenditure
![Page 15: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/15.jpg)
15
Impact of a Participatory Approach
On timing and costs Lengthy consultations with GOV and number of missions As much emphasis on dialogue as on report writing
Value added by GOV?Detailed study of all draft material, correction of errors and
elaboration of information, mainly by MOFMPI provided draft chapter on PIP Improved consistency and overall qualityBut not major changes or disagreements
On tone of recommendations - not preaching “An agenda of reform options”, “GOV should consider”, were we “tough” enough?
![Page 16: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/16.jpg)
16
Follow-up
Recommendations which are well specified
Areas needing further work or study
Areas not yet covered
Consideration of T.A. needs
Action Plan to guide follow up/implementation
![Page 17: 1 DOING A PARTICIPATORY PER THE VIETNAM EXPERIENCE David Shand PEAM Seminar 24 May, 2001.](https://reader035.fdocuments.in/reader035/viewer/2022081908/56649e255503460f94b14b9b/html5/thumbnails/17.jpg)
17
Follow-up
MAIN MESSAGES IN THE REPORT
Fiscal sustainability problems
Overall reasonably good expenditure management
but improvements needed in expenditure prioritization capital/recurrent imbalance, improve pro-poorness
and need to improve information flows, both external and internal